Permanent and temporary combined plugging structure for horizontal preformed hole of anchor cable of flood discharge gate and construction method
By arranging a structure of steel pipe body and stiffening rib plate in the flood gate pier, the reserved holes of the flood gate are temporarily blocked, which solves the problem of blocking the reserved holes of the anchor cable under the tight construction period, and achieves the tightness and tightness of the permanent sealing. Safety, avoiding damage to the gate pier concrete.
Patent Information
- Application Number
- CN202410884655.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-03
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-03
AI Technical Summary
Under the tight construction schedule, early blocking of the horizontal reserved holes for the prestressed anchor cables of the floodgates will cause difficulty in removal and may damage the concrete of the gate piers.
A reserved hole for the anchor cable is set in the floodgate pier, and a steel pipe body is set in the reserved hole for the anchor cable. An anchor cable penetration hole is set on the steel pipe body, and end steel plates are provided at both ends. and longitudinal stiffening ribs. The end steel plates are used to temporarily retain water. The steel plates are removed under dry ground conditions, and construction is carried out inside the steel pipes and concrete is poured to form a permanent seal.
The temporary sealing of the reserved holes for the anchor cables is achieved to prevent water flow pollution and influence on the water flow pattern. The permanent sealing structure is dense and does not damage the concrete of the gate pier, making the construction safe and reliable.
Smart Images

Figure CN118727673A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of water conservancy and hydropower engineering, and in particular to a permanent and temporary blocking structure for horizontal reserved holes of anchor cables of a flood discharge gate and a construction method. Background Art
[0002] The flood gate is a commonly used water discharge structure in water conservancy and hydropower projects. The flood gate is generally equipped with an arc-shaped working gate. The gate is lowered to block water and the gate is raised to discharge water. Under the water-blocking condition, the flood gate bears the upstream water thrust, which acts on the reinforced concrete anchor block through the support hinge structure of the arc-shaped working gate. The anchor block is pre-tightened by setting a through-type prestressed anchor cable to stabilize the anchor block. The downstream end of the anchor cable is located on the surface of the anchor block, and the upstream end is located inside the gate pier. The upstream end has a lower elevation. The anchor cable can only be tensioned after the concrete of the gate pier has reached the age. Therefore, a horizontal reserved hole needs to be set at the upstream end of the anchor cable perpendicular to the water flow direction to the gate pier for subsequent tensioning of the anchor cable.
[0003] According to the normal construction schedule, in order to avoid construction interference, the prestressed anchor cable tensioning and the plugging of the horizontal reserved holes need to be completed before the flood gate flows. When the construction schedule is tight and the anchor cable tensioning cannot be completed before the flood gate flows, temporary plugging measures need to be taken for the reserved holes to prevent water from entering the reserved holes and polluting the holes and affecting the flow state of the flood gate. When dry land construction conditions are formed and the arc working gate is installed, the temporary plugging structure is removed to complete the anchor cable tensioning and plugging of the reserved holes.
[0004] However, the existing temporary blocking structure needs to be fixed in the concrete structure, and the removal work is cumbersome and will damage the gate pier concrete. Summary of the invention
[0005] The purpose of the present invention is to provide a permanent and temporary blocking structure for the horizontal reserved holes of the anchor cables of the flood discharge gate, so as to solve the problem of early blocking of the horizontal reserved holes of the prestressed anchor cables of the flood discharge gate when the construction period is tight. The contact part between the blocking structure and the gate pier does not need to be removed and will not damage the concrete of the gate pier.
[0006] Another object of the present invention is to provide a construction method for a permanent and temporary combined sealing structure of horizontal reserved holes for anchor cables of a flood discharge gate.
[0007] The technical solution adopted by the permanent and temporary sealing structure of the horizontal reserved holes for anchor cables of a flood discharge gate of the present invention is as follows: the reserved holes for anchor cables are arranged in the piers of the flood discharge gate, a steel pipe body is arranged in the reserved holes for anchor cables, an anchor cable threading hole is arranged on the steel pipe body, end steel plates are arranged at both ends of the steel pipe body, transverse stiffening ribs and longitudinal stiffening ribs are arranged on the inner and outer wall surfaces of the steel pipe body respectively, and the end steel plates are used to temporarily block water during the flow during the construction period; after dry land construction conditions are formed in the flow channel of the subsequent flood discharge gate, the end steel plates are cut off along the inner wall of the steel pipe body, and then the anchor cables are constructed in the steel pipe body, and a slurry inlet pipe and a slurry return pipe are arranged in the steel pipe body, and then concrete is poured in the steel pipe body to form a permanent concrete plugging.
[0008] Furthermore, the strength and thickness of the steel pipe body material need to be determined in accordance with the relevant requirements of the template, and Q235 steel with a thickness of not less than 10mm should be used.
[0009] Furthermore, inner and outer side walls of the transverse stiffening ribs and longitudinal stiffening ribs are respectively provided with inner transverse connecting holes, outer transverse connecting holes and inner longitudinal connecting holes, outer longitudinal connecting holes, so as to facilitate the compaction of concrete.
[0010] Furthermore, the thickness of the transverse stiffening ribs should be verified for shear resistance according to the maximum dynamic water pressure that may be received under the single-sided water retaining condition; the longitudinal stiffening ribs are configured according to the structure. The thickness of the transverse stiffening ribs can be calculated using the following formula: Among them, h is the thickness of the transverse stiffening rib, k is the safety factor, f is the dynamic water pressure, A is the cross-sectional area of the anchor hole, n is the number of rows of transverse ribs, D is the outer diameter of the steel pipe body, and v is the shear strength of the transverse stiffening rib.
[0011] The present invention provides a construction method for a permanent and temporary combined plugging structure of a horizontal reserved hole for an anchor cable of a flood discharge gate, comprising the following steps: S1. Produce steel pipes for plugging reserved holes for anchor cables according to design requirements, including steel pipe bodies, end steel plates, transverse stiffening ribs and longitudinal stiffening ribs; S2. Fabricate and install steel bars according to design requirements, erect formwork, and pour pier concrete to the anchor cable reserved hole pouring bin, with the bin surface lower than the hole bottom height; S3, according to the design requirements, make and install the steel bars of the casting bin where the anchor cable pre-holes are located, install and fix the steel pipes processed in step S1, use the steel pipes as the supporting formwork at the anchor cable pre-holes, support the formworks of the remaining parts and pour concrete; S4. According to the design requirements, make and install steel bars, set up formwork and pour gate pier concrete to the gate top. The flood discharge gate can be opened only after the concrete reaches the age. During the construction period, the end steel plates at both ends of the steel pipe body are used to temporarily block water at the reserved holes of the anchor cables; S5. When the dry land construction conditions are formed to install the arc working gate, the end steel plate is cut off along the inner wall of the steel pipe body, and the construction personnel enter the anchor cable reserved hole to construct the anchor cable, and tie the surface steel bars at both ends of the steel pipe body. The surface steel bars are bent at the end and welded to the steel pipe body, and then concrete is poured to form a permanent concrete plug in the anchor cable reserved hole; S6. After the permanent concrete plugging in the anchor cable reserved hole is finally solidified, the permanent concrete plugging is grout-filled and compacted through the grouting pipe and the grouting return pipe.
[0012] The present invention has the following beneficial effects: (1) It can solve the need for temporary plugging of anchor cable reserved holes before the anchor cable is tensioned under tight construction schedule, preventing water from entering the reserved holes and polluting the holes and affecting the flow pattern of the flood discharge gate; (2) When implementing permanent sealing of concrete, only the end steel plate that is not in direct contact with the gate pier concrete needs to be cut off, which will not damage the gate pier concrete; (3) After cutting off the steel plate, anchor cables are directly installed on the inside of the steel pipe and first-grade concrete or self-compacting micro-expansive concrete is pumped and poured to form a permanent structure. The seal is dense and the shear resistance of the inner and outer stiffening ribs of the steel plate is utilized to ensure that the permanent sealing structure is safe and reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] Figure 1 is a schematic cross-sectional view of the plugging structure during the temporary plugging period of the present invention; Figure 2 is a schematic longitudinal section diagram of the plugging structure during the temporary plugging period of the present invention; Figure 3 is a schematic cross-sectional view of the plugging structure of the permanent plugging period of the present invention; Figure 4 It is a schematic transverse and longitudinal view of the plugging structure in the permanent plugging period of the present invention. DETAILED DESCRIPTION
[0014] In order to enable ordinary technicians in the field to more clearly understand the objectives, technical solutions and advantages of the present invention, the present invention is further described below in conjunction with the accompanying drawings and embodiments, but the present invention is not limited to the following embodiments.
[0015] In the description of the present invention, it should be noted that the directions or positional relationships indicated by the terms "upper", "lower", "inside", "outside", "left", "right", etc. are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the construction referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention.
[0016] The present invention relates to a permanent and temporary combined sealing structure for horizontal reserved holes of anchor cables in a flood discharge gate, comprising an anchor cable reserved hole 02 arranged in a flood discharge gate pier 01, a steel pipe body 1 arranged in the anchor cable reserved hole 02, an anchor cable threading hole 2 arranged on the steel pipe body 1, end steel plates 9 arranged at both ends of the steel pipe body 1, transverse stiffening ribs 3 and longitudinal stiffening ribs 4 arranged on the inner and outer wall surfaces of the steel pipe body 1 respectively, and the end steel plates 2 are used to temporarily block water during the flow during the construction period; after dry land construction conditions are formed in the flow channel of the subsequent flood discharge gate, the end steel plates 3 are cut off along the inner wall of the steel pipe body 1, and then the anchor cables are constructed in the steel pipe body 1, and a slurry inlet pipe 10 and a slurry return pipe 11 are arranged in the steel pipe body 1, and then concrete is poured in the steel pipe body 1 to form a permanent concrete plugging 03.
[0017] like Figure 1 , Figure 2 As shown, it is a plugging structure for the temporary plugging period. The steel pipe body 1 is processed according to the shape of the anchor cable reserved hole 02. The two ends of the steel pipe body 1 are closed with end steel plates 9. Only the anchor cable threading hole 2 is provided at the anchor cable threading position. The inner and outer walls of the steel pipe body 1 are welded with transverse stiffening ribs 3 and longitudinal stiffening ribs 4 according to the design requirements. During the flow period during the construction period, the end steel plates 9 are used to temporarily block water.
[0018] Figure 3 , Figure 4 As shown, it is a plugging structure for the permanent plugging period. On the basis of the plugging structure for the temporary plugging period, after the dry land construction conditions are formed in the flood discharge gate flow channel, the end steel plate 9 is cut along the inner wall of the steel pipe body 1 to form a pipe mouth, and then the construction personnel enter the steel pipe body 1 from the pipe mouth to construct the anchor cable, and then pour concrete in the steel pipe body 1 to form a permanent concrete plug 03. In order to ensure the dense pouring, the concrete adopts a first-graded or self-compacting micro-expansive concrete, and the permanent concrete plugging can be grouted through the slurry inlet pipe 10 and the slurry return pipe 11, and the permanent concrete plugging is more dense.
[0019] The strength and thickness of the steel pipe body 1 material must be determined in accordance with the template requirements, and Q235 steel with a thickness of not less than 10 mm is preferably used.
[0020] The inner and outer side walls of the transverse stiffening ribs 3 and the longitudinal stiffening ribs 4 are respectively provided with inner transverse connecting holes 5, outer transverse connecting holes 6, inner longitudinal connecting holes 7, and outer longitudinal connecting holes 8 to facilitate the compaction of concrete.
[0021] The thickness of the transverse stiffening ribs 3 is checked for shear resistance according to the maximum dynamic water pressure under the single-sided water retaining condition; the longitudinal stiffening ribs 4 are configured according to the structure. The thickness of the transverse stiffening ribs 3 is calculated using the following formula: Among them, h is the thickness, k is the safety factor, f is the dynamic water pressure, A is the cross-sectional area of the anchor cable reserved hole 02, n is the number of rows of the transverse stiffening ribs 3, D is the outer diameter of the steel pipe body 1, and v is the shear strength of the transverse stiffening ribs 3.
[0022] A construction method of a permanent and temporary combined plugging structure for a flood discharge gate anchor cable horizontal reserved hole of the present invention comprises the following steps: S1. According to the design requirements, a steel pipe for plugging the reserved hole of the anchor cable is manufactured, including a steel pipe body 1, an end steel plate 9, a transverse stiffening rib plate 3 and a longitudinal stiffening rib plate 4; S2. According to the design requirements, make and install steel bars, set up formwork and pour the gate pier concrete to the anchor cable reserved hole pouring bin. The bin surface should be lower than the hole bottom by a proper height. S3, according to the design requirements, make and install the steel bars of the casting bin where the anchor cable pre-holes are located, install and fix the steel pipes processed in step S1, use the steel pipes as the supporting formwork at the anchor cable pre-holes, support the formworks of the remaining parts and pour concrete; S4, according to the design requirements to produce and install steel bars, support formwork and pour gate pier concrete to the gate top, after the concrete reaches the age, the flood discharge gate can be allowed to flow, during the construction period, the anchor cable reserved hole uses the end steel plates 9 at both ends of the steel pipe body 1 to temporarily block water; S5. When the dry land construction conditions are formed to install the arc working gate, the end steel plate is cut off along the inner wall of the steel pipe body, and the construction personnel enter the anchor cable reserved hole to construct the anchor cable, and tie the surface steel bars 12 at both ends of the steel pipe body. The surface steel bars 12 are bent at the end and welded to the steel pipe body 1, and then concrete is poured by pumping to form a permanent concrete plug in the anchor cable reserved hole; S6. After the permanent concrete plugging in the anchor cable reserved hole is finally solidified, the permanent concrete plugging is grout-filled and compacted through the grouting pipe and the grouting return pipe.
[0023] Through the above steps, the problem of early sealing of the horizontal reserved holes of the prestressed anchor cables of the flood discharge gate when the construction period is tight is solved, and the contact part of the sealing structure with the gate pier does not need to be removed, and the gate pier concrete will not be damaged, which has a very beneficial positive effect.
[0024] The above is only a preferred embodiment of the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A permanent and temporary plugging structure for the horizontal reserved holes of flood discharge gate anchor cables, characterized in that The invention comprises providing an anchor cable pre-hole (02) in a flood discharge gate pier (01), providing a steel pipe body (1) in the anchor cable pre-hole (02), providing an anchor cable threading hole (2) on the steel pipe body (1), providing end steel plates (9) at both ends of the steel pipe body (1), and providing transverse stiffening ribs (3) and longitudinal stiffening ribs (4) on the inner and outer wall surfaces of the steel pipe body (1), respectively; during the construction period, the end steel plates (2) are used to temporarily block water; after dry land construction conditions are formed in the flow channel of the flood discharge gate, the end steel plates (3) are cut off along the inner wall of the steel pipe body (1), and then the anchor cables are constructed in the steel pipe body (1), and a slurry inlet pipe (10) and a slurry return pipe (11) are provided in the steel pipe body (1), and then concrete is poured in the steel pipe body (1) to form a permanent concrete plug (03).
2. A permanent and temporary plugging structure for horizontal reserved holes for anchor cables of flood discharge gates as claimed in claim 1, characterized in that The strength and thickness of the steel pipe body (1) are determined according to the requirements of the template, and Q235 steel with a thickness of not less than 10 mm is preferably selected.
3. A permanent and temporary plugging structure for horizontal reserved holes for anchor cables of flood discharge gates as claimed in claim 1, characterized in that The inner and outer side walls of the transverse stiffening ribs (3) and the longitudinal stiffening ribs (4) are respectively provided with inner transverse connecting holes (5), outer transverse connecting holes (6), inner longitudinal connecting holes (7), and outer longitudinal connecting holes (8) to facilitate compact concrete pouring.
4. A permanent and temporary plugging structure for horizontal reserved holes for anchor cables of flood discharge gates as claimed in claim 1, characterized in that The thickness of the transverse stiffening ribs (3) is checked for shear resistance according to the maximum dynamic water pressure under the single-sided water retaining condition; the longitudinal stiffening ribs (4) are configured according to the structure. The thickness of the transverse stiffening ribs (3) is calculated using the following formula: Wherein, h is the thickness, k is the safety factor, f is the dynamic water pressure, A is the cross-sectional area of the anchor cable reserved hole (02), n is the number of rows of the transverse stiffening ribs (3), D is the outer diameter of the steel pipe body (1), and v is the shear strength of the transverse stiffening ribs (3).
5. A construction method for a permanent and temporary plugging structure of a horizontal reserved hole for anchor cables of a flood discharge gate, characterized in that The following steps are involved: S1. Produce steel pipes for plugging reserved holes for anchor cables according to design requirements, including steel pipe bodies, end steel plates, transverse stiffening ribs and longitudinal stiffening ribs; S2. Fabricate and install steel bars according to design requirements, erect formwork, and pour pier concrete to the anchor cable reserved hole pouring bin, with the bin surface lower than the hole bottom height; S3, according to the design requirements, make and install the steel bars of the casting bin where the anchor cable pre-holes are located, install and fix the steel pipes processed in step S1, use the steel pipes as the supporting formwork at the anchor cable pre-holes, support the formworks of the remaining parts and pour concrete; S4. According to the design requirements, make and install steel bars, set up formwork and pour gate pier concrete to the gate top. The flood discharge gate can be opened only after the concrete reaches the age. During the construction period, the end steel plates at both ends of the steel pipe body are used to temporarily block water at the reserved holes of the anchor cables; S5. When the dry land construction conditions are formed to install the arc working gate, the end steel plate is cut off along the inner wall of the steel pipe body, and the construction personnel enter the anchor cable reserved hole to construct the anchor cable, and tie the surface steel bars at both ends of the steel pipe body. The surface steel bars are bent at the end and welded to the steel pipe body, and then concrete is poured to form a permanent concrete plug in the anchor cable reserved hole; S6. After the permanent concrete plugging in the anchor cable reserved hole is finally solidified, the permanent concrete plugging is grout-filled and compacted through the grouting pipe and the grouting return pipe.
Citation Information
Patent Citations
Quick plugging method for pre-stressed anchor cable preformed hole of gate pier
CN117926763A
Modular flood discharge water intaking structure
CN204589952U
Gate pier anchor draw hole unilateral thin layer block structure