Water distribution wall prefabrication construction method
The water distribution wall construction method of segmented prefabrication and hoisting installation solves the problems of difficulty in vibrating and concrete defects in the existing technology, and achieves efficient connection strength and construction safety.
Patent Information
- Application Number
- CN202410829350.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-25
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-06-25
AI Technical Summary
During the construction process of the existing water distribution wall, due to the staggered arrangement of water distribution holes, it is difficult to vibrate, and defects such as concrete honeycombs and pitted surfaces are prone to occur. In addition, it is difficult to tie steel bars, there is a risk of working at high altitude, and a large amount of formwork and support frames are used. .
Using the segmented construction method, the water distribution wall is divided into two parts: the upper part with holes and the lower solid part. The upper perforated water distribution wall is prefabricated, hoisted and installed, and connected through post-casting tape and threaded sleeves, and the post-casting tape is sealed with formwork. Pour in micro-expansion grouting material to ensure connection strength.
It effectively avoids concrete defects, reduces the difficulty of tying steel bars, avoids the risks of high-altitude operations, reduces the use of formwork and support frames, and improves connection strength and construction efficiency.
Smart Images

Figure CN118728078A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a prefabricated construction method of a water distribution wall. Background Art
[0002] The secondary sedimentation tank is an important process unit in the sewage treatment process. Through the principle of gravity sedimentation, the sewage is allowed to settle in a static state, forming two layers of sludge at the bottom and clear water at the top. It is usually located after the biochemical tank and is used to remove undegraded organic matter and suspended solids in the biochemical tank to make the sewage meet the discharge standards.
[0003] In order to distribute water evenly and avoid the impact of inflow flow affecting sedimentation, the water distribution wall of the secondary sedimentation tank of the sewage treatment plant is generally designed with three layers of water distribution holes (the water distribution holes are located on the upper part of the water distribution wall). The water distribution holes in each layer are arranged in a staggered manner. Generally, cast-in-place concrete is used to form the water distribution wall in one step. However, in actual projects, due to the staggered arrangement of the holes in the water distribution wall, a square wooden box customized with a template is used at the reserved holes. The vibrating rod cannot be inserted into the concrete for vibration during the pouring and vibration process of the cast-in-place concrete, which is very likely to cause concrete defects such as honeycombs and rough surfaces in the wall. In order to improve the construction quality of the water distribution wall concrete, a prefabricated construction method for the water distribution wall is developed to ensure quality and improve work efficiency. Summary of the invention
[0004] The main purpose of the present invention is to propose a prefabricated construction method for a water distribution wall, which can effectively solve the problems in the background technology.
[0005] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0006] A water distribution wall prefabrication construction method comprises the following steps:
[0007] S1: Segment the water distribution wall into an upper perforated water distribution wall and a lower solid water distribution wall;
[0008] S2: Cast the main structure of the pool and the lower solid water distribution wall. The lower solid water distribution wall is cast in situ with the main structure of the pool. When casting the main structure of the pool, a post-cast strip is reserved at the connection between it and the upper perforated water distribution wall. When casting the lower solid water distribution wall, a full-length secondary grouting groove is reserved on its top surface;
[0009] S3: prefabricated upper perforated water distribution wall, with threaded sleeves embedded on both sides of the upper perforated water distribution wall connected to the main structure of the pool body;
[0010] S4: hoist the upper perforated water distribution wall and install it on the upper part of the lower solid water distribution wall;
[0011] S5: Weld the steel plate on the main reinforcement of the post-casting belt, and the bolts pass through the steel plate and are connected and fastened with the embedded threaded sleeve on the side of the upper perforated water distribution wall;
[0012] S6: sealing of post-casting strip formwork;
[0013] S7: pouring concrete in the post-cast zone;
[0014] S8: Pour the micro-expansion grouting material into the secondary grouting groove on the top surface of the lower solid water distribution wall, and the lower solid water distribution wall and the upper perforated water distribution wall are connected as a whole.
[0015] Preferably, in step S2, the post-casting zone is separated by a dense mesh steel wire mesh.
[0016] Preferably, in step S3, the upper perforated water distribution wall is prefabricated directly at the bottom of the pool body.
[0017] Preferably, in step S4, after the upper perforated water distribution wall is installed, a temporary fixed support is used to fix it on its side.
[0018] The present invention provides a water distribution wall prefabrication construction method, which has the following beneficial effects:
[0019] 1. The present invention prefabricates the upper part of the water distribution wall where water distribution holes are required, that is, the upper water distribution wall with holes is prefabricated, and then it is assembled and installed. The upper water distribution wall with holes is prefabricated, and the concrete is easy to vibrate and the molding quality is high. It can effectively avoid the problem of concrete defects such as honeycomb and rough surface of the wall caused by the current one-time molding of the water distribution wall using cast-in-place concrete. At the same time, it also reduces the difficulty of steel bar binding, avoids the risk of high-altitude operations, and reduces the use of templates and support frames.
[0020] 2. The main structure of the pool body and the upper perforated water distribution wall are connected by post-cast strips, which can effectively ensure the connection strength between the main structure of the pool body and the upper perforated water distribution wall. The main steel bars of the post-cast strips are connected to the embedded threaded sleeves of the upper perforated water distribution wall through steel plates and bolts, further ensuring the connection strength.
[0021] 3. Pour micro-expansion grouting material into the secondary grouting groove on the top surface of the lower solid water distribution wall, and connect the lower solid water distribution wall and the upper perforated water distribution wall as a whole to ensure the connection strength between the lower solid water distribution wall and the upper perforated water distribution wall. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 is an elevation view of the pool body of the present invention;
[0023] Figure 2 is a cross-sectional view of a pool body of the present invention;
[0024] Figure 3 It is a partial plan view of the pool body of the present invention;
[0025] Figure 4 This is a schematic diagram of the structure of the upper perforated water distribution wall of the present invention;
[0026] Figure 5 It is a schematic structural diagram of the post-cast strip of the present invention.
[0027] In the figure: 1. Upper perforated water distribution wall; 2. Lower solid water distribution wall; 3. Main structure of the pool; 4. Post-casting strip; 5. Secondary grouting groove; 6. Threaded sleeve; 7. Water distribution hole; 8. Temporary fixed support; 9. Steel plate; 10. Bolts; 11. Dense mesh. DETAILED DESCRIPTION
[0028] In order to make the purpose, technical solutions and advantages of the present invention more clear, the technical solutions of the present invention will be clearly and completely described below in conjunction with the accompanying drawings of the present invention.
[0029] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are part of the embodiments of the present invention, rather than all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0031] In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, "multiple" means two or more, unless otherwise clearly and specifically defined. In addition, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal connection of two components. For those of ordinary skill in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0032] Example
[0033] Reference Figure 1-5 , a water distribution wall prefabrication construction method, comprising the following steps:
[0034] S1: Segment the water distribution wall into an upper perforated water distribution wall 1 and a lower solid water distribution wall 2;
[0035] S2: Cast the main structure 3 of the pool body and the lower solid water distribution wall 2. The lower solid water distribution wall 2 is cast in situ with the main structure 3 of the pool body. When casting the main structure 3 of the pool body, a post-cast strip 4 is reserved at the connection between the main structure 3 of the pool body and the upper perforated water distribution wall 1. When casting the lower solid water distribution wall 2, a full-length secondary grouting groove 5 is reserved on its top surface;
[0036] In this embodiment, the post-cast strip 4 is separated by a dense mesh steel wire mesh 11. The functions of the dense mesh steel wire mesh 11 are to prevent the concrete in the main structure 3 of the pool body from penetrating into the post-cast strip 4 and to improve the toughness and tensile strength of the concrete subsequently poured in the post-cast strip 4.
[0037] The cross section of the post-cast strip 4 is in the shape of a "I", a "earth" or a "cross", which is selected according to the wall structure of the main structure 3 of the pool body.
[0038] S3: prefabricate the upper perforated water distribution wall 1, and embed threaded sleeves 6 on both sides of the upper perforated water distribution wall 1 connected to the main structure 3 of the pool body;
[0039] In this embodiment, the upper perforated water distribution wall 1 is prefabricated directly at the bottom of the pool body, and the water distribution wall steel bars and water distribution holes 7 are arranged according to the design requirements. The upper perforated water distribution wall 1 is prefabricated on site, which can save transportation costs, facilitate hoisting and installation, and improve construction efficiency.
[0040] S4: hoisting the upper perforated water distribution wall 1 and installing it on the upper part of the lower solid water distribution wall 2;
[0041] In this embodiment, after the upper perforated water distribution wall 1 is installed, a temporary fixing support 8 is used to fix it on its side.
[0042] S5: Weld the steel plate 9 on the main steel bars of the post-cast zone 4, and the bolts 10 pass through the steel plate 9 and are connected and fastened to the embedded threaded sleeve 6 on the side of the upper perforated water distribution wall 1;
[0043] S6: Seal the formwork of post-casting zone 4;
[0044] S7: pouring concrete in post-cast zone 4;
[0045] The main structure 3 of the pool body and the upper perforated water distribution wall 1 are connected by a post-cast strip 4, which can effectively ensure the connection strength between the main structure 3 of the pool body and the upper perforated water distribution wall 1, and the main steel bars of the post-cast strip 4 are connected to the embedded threaded sleeve 6 of the upper perforated water distribution wall 1 through a steel plate 9 and bolts 10, further ensuring the connection strength.
[0046] S8: Pour micro-expansion grouting material into the secondary grouting groove 5 on the top surface of the lower solid water distribution wall 2, and connect the lower solid water distribution wall 2 and the upper perforated water distribution wall 1 as a whole to ensure the connection strength between the lower solid water distribution wall 2 and the upper perforated water distribution wall 1.
[0047] The present invention prefabricates the upper part of the water distribution wall where the water distribution holes 7 need to be set, that is, the upper water distribution wall 1 with holes is prefabricated, and then it is assembled and installed. The upper water distribution wall 1 with holes is prefabricated, and the concrete is easy to vibrate and the molding quality is high. It can effectively avoid the problem of concrete defects such as honeycomb and rough surface of the wall caused by the current water distribution wall formed by cast-in-place concrete in one time. At the same time, it also reduces the difficulty of steel bar binding, avoids the risk of high-altitude operations, and reduces the use of templates and support frames.
[0048] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit the same. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A prefabricated construction method for a water distribution wall, characterized in that: The following steps are involved: S1: Segment the water distribution wall into an upper perforated water distribution wall and a lower solid water distribution wall; S2: Cast the main structure of the pool and the lower solid water distribution wall. The lower solid water distribution wall is cast in situ with the main structure of the pool. When casting the main structure of the pool, a post-cast strip is reserved at the connection between it and the upper perforated water distribution wall. When casting the lower solid water distribution wall, a full-length secondary grouting groove is reserved on its top surface; S3: prefabricated upper perforated water distribution wall, with threaded sleeves embedded on both sides of the upper perforated water distribution wall connected to the main structure of the pool body; S4: hoist the upper perforated water distribution wall and install it on the upper part of the lower solid water distribution wall; S5: Weld the steel plate on the main reinforcement of the post-casting belt, and the bolts pass through the steel plate and are connected and fastened with the embedded threaded sleeve on the side of the upper perforated water distribution wall; S6: sealing of post-casting strip formwork; S7: pouring concrete in the post-cast zone; S8: Pour the micro-expansion grouting material into the secondary grouting groove on the top surface of the lower solid water distribution wall, and the lower solid water distribution wall and the upper perforated water distribution wall are connected as a whole.
2. A water distribution wall prefabrication construction method according to claim 1, characterized in that: In step S2, the post-casting zone is separated by a dense mesh steel wire mesh.
3. A water distribution wall prefabrication construction method according to claim 1, characterized in that: In step S3, the upper perforated water distribution wall is prefabricated directly on the bottom of the pool body.
4. A water distribution wall prefabrication construction method according to claim 1, characterized in that: In step S4, after the upper perforated water distribution wall is installed, a temporary fixed support is used to fix it on its side.
Citation Information
Patent Citations
Device and method for improving denitrification effect of subsurface flow constructed wetland
CN106946353A
Prefabricated wall, prefabricated wall and cast-in-situ component horizontal connecting node and construction method
CN110424574A
Prefabricated perforated water distribution flower wall
CN213347892U
The pc wall for water-storage tank of assembly type and Method for constructing thereof
KR101327388B1