Installation method for special-shaped air corridor between high-rise buildings
By building a cantilevered operating platform and a lifting device, and assembling and lifting the "Z"-shaped special-shaped connecting beam structure on the ground, the problems of high construction difficulty and long construction period in traditional construction methods were solved, and efficient and safe special-shaped aerial corridor installation was achieved.
Patent Information
- Application Number
- CN202411010485.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-10-01
AI Technical Summary
The traditional construction method of high-altitude conjoined steel structures has the problems of large amount of work, difficulty in docking, difficulty in ensuring welding quality, low safety factor, and long construction period. It is especially suitable for the construction of special-shaped sky corridors.
A cantilevered operating platform is built between staggered buildings, pre-assembled steel structures and lifting devices are installed, the "Z" shaped special-shaped connecting beam main structure is assembled on the ground, and is raised to a predetermined height through the lifting device. Set up the fixed connection of the supplementary rod, and finally unload the lifting device.
It greatly reduces the amount of high-altitude work, improves construction safety, simplifies construction difficulty, and shortens the construction period while ensuring quality.
Smart Images

Figure CN118728097A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of aerial corridor construction, and in particular to an installation method for a special-shaped aerial corridor between high-rise buildings. Background Art
[0002] With the development of social economy, high-rise and super-high-rise building connected structures are a new type of structural form developed in the past decade. On the one hand, the connection between different buildings can be convenient; on the other hand, the structure has a unique appearance, which can bring a strong visual effect and make the building more distinctive. For the construction technology of high-altitude connected steel structures, there are methods of setting up high-altitude operating platforms or assembling high-altitude parts. The high-altitude connected steel structure is installed between two buildings by building high-altitude operating platforms or by bulk assembly in the air. There is also a special-shaped aerial corridor for connecting multiple buildings. Its structure is special-shaped, heavy, and has a large span. The traditional method of high-altitude operating platforms or high-altitude parts assembly has the disadvantages of large engineering volume, difficulty in aerial docking, difficulty in ensuring welding quality, low safety factor, and long construction period. Therefore, a new installation method of special-shaped aerial corridors is urgently needed to achieve the effect of reducing construction difficulty and shortening construction period. Summary of the invention
[0003] The invention discloses a method for installing a special-shaped sky corridor between high-rise buildings, so as to solve the problem of how to provide a new method for installing a special-shaped sky corridor in the above-mentioned background technology, so as to achieve the effect of reducing the construction difficulty and shortening the construction period.
[0004] In order to solve the above technical problems, the following technical solutions are proposed:
[0005] A method for installing a special-shaped sky corridor between high-rise buildings, which is used to set up a "Z"-shaped special-shaped sky corridor between a first building, a second building, a third building and a fourth building that are staggered, comprising the following steps:
[0006] S1. Build a cantilevered operating platform:
[0007] S2. Install the pre-assembled steel structure and lifting device on the top of the first building, the second building, the third building and the fourth building through the cantilevered operating platform;
[0008] S3, ground assembly of the main structure of "Z"-shaped special-shaped connecting beams;
[0009] S4, using the lifting devices on the first building, the second building, the third building and the fourth building as hanging points, determining the positions of the connecting parts according to the orthographic projection positions of the hanging points on the main structure of the "Z"-shaped special-shaped coupling beam, and connecting the steel strands of the lifting devices to the corresponding connecting parts;
[0010] S5. Lift the main structure of the "Z"-shaped special-shaped coupling beam to a predetermined height through the lifting devices on the first building, the second building, the third building and the fourth building;
[0011] S6. A supplementary rod is arranged between the main structure of the "Z"-shaped special-shaped connecting beam and the pre-installed steel structure, so that the main structure of the "Z"-shaped special-shaped connecting beam is fixedly connected to the pre-installed steel structure of the first building, the second building, the third building and the fourth building;
[0012] S7, unloading, dismantling the lifting devices on the first building body, the second building body, the third building body and the fourth building body.
[0013] Preferably, before step S3, the method further includes:
[0014] S3', the installation positions of the "Z"-shaped special-shaped connecting beam main structure on the first building, the second building, the third building and the fourth building are provided with an assembly area for assembling the "Z"-shaped special-shaped connecting beam main structure at the orthographic projection of the ground, and a flat tire frame for receiving the "Z"-shaped special-shaped connecting beam main structure is provided in the assembly area.
[0015] Preferably, after the main structure of the "Z"-shaped special-shaped connecting beam is lifted to a predetermined height, posture detection is performed on each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam, posture detection data of each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam is obtained, and the lifting device is controlled to adjust each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam according to the posture detection data.
[0016] Preferably, sensors are provided at each lower hanging point on the main structure of the "Z"-shaped special-shaped connecting beam, and posture detection data of each lower hanging point on the main structure of the "Z"-shaped special-shaped connecting beam is acquired in real time by the sensors.
[0017] As a preference, a model of the main structure of the "Z"-shaped special-shaped connecting beam is established, and the control point coordinates of each node of the main structure of the "Z"-shaped special-shaped connecting beam are extracted according to the model; control points corresponding to the control point coordinates are marked in the assembly area, and a flat tire frame is erected at the control points.
[0018] Preferably, the Z-shaped special-shaped coupling beam main structure includes a main truss composed of a main truss lower chord, a main truss lower chord connecting beam, a main truss web, a main truss upper chord, and a main truss upper chord connecting beam, and a secondary truss composed of a secondary truss lower chord, a secondary truss lower chord connecting beam, a secondary truss web, a secondary truss upper chord, and a secondary truss upper chord connecting beam, and in step S3,
[0019] A1. Plan the splicing positions of the lower chord of the main truss and the lower chord of the secondary truss in the assembly area according to the coordinates of the control points of each node of the main structure of the "Z"-shaped special-shaped coupling beam;
[0020] A2. Install the main truss lower chord at the corresponding splicing position of the main truss lower chord in the assembly area, and connect the main truss lower chord connecting rod between the main truss lower chords to form a stable main truss lower chord plane structure;
[0021] A3. Install the main truss web members from both ends of the lower chord plane structure of the main truss toward the middle;
[0022] A4. Install the main truss upper chord on the main truss web, and connect the main truss upper chord connecting beam between the main truss upper chords to form the main truss;
[0023] A5. According to steps A2, A3 and A4, assemble the secondary trusses at both ends of the main truss.
[0024] Preferably, the pre-installed steel structure at the roof of the first building, the second building, the third building and the fourth building is installed on the roof of the first building, the second building, the third building and the fourth building by high-altitude loose parts hoisting and installation, wherein the various components of the pre-installed steel structure of the first building, the third building and the fourth building are fixed to the first building, the third building and the fourth building by welding, and the various components of the pre-installed steel structure of the second building are movably arranged on the second building by bolts.
[0025] Preferably, in step S6, the patch rod is fixedly connected to the main structure of the "Z"-shaped special-shaped coupling beam and the pre-assembled section steel structure by welding; and after the patch rod welding operation is completed, the weld is subjected to a nondestructive testing inspection.
[0026] Preferably, a lower winding deformation threshold is set to detect the lower winding deformation of each end of the "Z"-shaped special-shaped connecting beam main structure. When the lower winding deformation is less than the lower winding deformation threshold, the "Z"-shaped special-shaped connecting beam main structure and the pre-assembled section steel structure are connected by means of weld transition. When the lower winding deformation is greater than the lower winding deformation threshold, the end of the "Z"-shaped special-shaped connecting beam main structure is adjusted by a jack.
[0027] Beneficial effect: The present invention discloses a method for installing a special-shaped sky corridor between high-rise buildings, which is used for setting up a "Z"-shaped special-shaped sky corridor between a first building, a second building, a third building and a fourth building that are staggered. The method comprises the following steps: building a cantilevered operating platform: installing a pre-assembled steel structure and a lifting device on the top of the first building, the second building, the third building and the fourth building; assembling a "Z"-shaped special-shaped connecting beam main structure on the ground; connecting the "Z"-shaped special-shaped connecting beam main structure to the lifting device; lifting the "Z"-shaped special-shaped connecting beam main structure to a predetermined height through the lifting device; and A supplementary rod is arranged between the pre-installed section steel body structure, so that the "Z"-shaped special-shaped connecting beam main structure is fixedly connected to the pre-installed section steel body structure; finally, the "Z"-shaped special-shaped connecting beam main structure lifting device is unloaded, and a "Z"-shaped special-shaped aerial corridor is erected between the staggered first building body, the second building body, the third building body and the fourth building body through the "ground assembly and overall lifting" method in the present invention, which not only greatly reduces the high-altitude work workload of the staff, thereby greatly increasing the safety of the staff, but also greatly simplifies the construction difficulty of the "Z"-shaped special-shaped aerial corridor, and greatly shortens the construction period while ensuring the construction quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 This is a schematic diagram of the distribution of the "Z"-shaped special-shaped sky corridor of the present invention;
[0029] Figure 2 This is a schematic diagram of the structure of the "Z"-shaped special-shaped aerial corridor of the present invention;
[0030] Figure 3 It is a schematic diagram of the position of the connection part between the lifting device of the present invention and the main body of the "Z"-shaped special-shaped connecting beam;
[0031] Figure 4 It is a structural schematic diagram of the main body of the "Z"-shaped special-shaped coupling beam of the present invention when it is assembled on the ground;
[0032] Figure 5 This is a schematic diagram of the state when the main body of the "Z"-shaped special-shaped coupling beam of the present invention begins to be lifted;
[0033] Figure 6 It is a schematic diagram of the state when the main body of the "Z"-shaped special-shaped coupling beam of the present invention is lifted to the vicinity of a predetermined position;
[0034] Figure 7 It is a schematic diagram of the state when the main body of the "Z"-shaped special-shaped coupling beam of the present invention is connected with the pre-assembled section;
[0035] Figure 8 It is a structural schematic diagram of the pre-installed section of the present invention;
[0036] Fig. 9It is a schematic structural diagram of a pre-installed section in another embodiment of the present invention.
[0037] The main component symbols are described as follows:
[0038] A, the first building; B, the second building; C, the third building; D, the fourth building;
[0039] 1. "Z"-shaped special-shaped connecting beam main structure; 11. Main truss; 12. Secondary truss;
[0040] 2. Pre-assembled section; 21. Support frame; 22. Truss lower chord; 23. Truss straight web;
[0041] 24. Truss upper chord; 25. Truss diagonal web member; 3. Supplementary rod;
[0042] 4. The connection between the lifting device and the main body of the "Z"-shaped special-shaped connecting beam; 5. The flat tire frame;
[0043] 6. Lifting device. DETAILED DESCRIPTION
[0044] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0045] The following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] The present invention discloses a method for installing a special-shaped sky corridor between high-rise buildings. Figure 1-9 , which is used to build a "Z"-shaped special-shaped aerial corridor between the staggered first building, the second building, the third building and the fourth building. In this embodiment, taking a hospital aerial corridor hydraulic lifting project as an example, the hospital is divided into east and west districts, and each district is built with two inpatient buildings (that is, the west district consists of the first building and the third building, and the east district has the second building and the fourth building). In this project, it is necessary to build a "Z"-shaped special-shaped aerial corridor between the first building, the second building, the third building and the fourth building, so that the first building, the second building, the third building and the fourth building are interconnected through the "Z"-shaped special-shaped aerial corridor, forming a large-span oblique asymmetric complex connected structure.
[0047] The project object is a "Z"-shaped special-shaped sky corridor, and the structural form is a large-span oblique asymmetric complex joint structure. The plane of the aerial joint corridor is Z-shaped, and it adopts a cross-layer steel truss structure. The main span of the corridor is 79m, the width is about 8m, and the structural height is 10m; the spans of the secondary bridges of the corridor are 37m and 42m, respectively, the width is about 7m, and the structural height is 5m. The span-to-height ratios are 7.4 and 8.4 respectively. The corridor floor adopts a steel truss floor deck. The steel truss corridor has a seismic resistance level of three. The maximum lifting height of the joint is about 51m, and the lifting weight is about 850 tons.
[0048] The "Z"-shaped special-shaped aerial corridor includes a main corridor with one span and two secondary corridors connected to it. According to the characteristics of the building structure, the "Z"-shaped special-shaped aerial corridor is divided into three parts: the pre-installed section, the main structure of the "Z"-shaped special-shaped connecting beam, and the supplementary rod. The pre-installed section is affected by the building structure. In order to avoid the part that cannot be directly lifted by the structure, a 200-ton crawler crane is required to be used to directly assemble and install the steel structure at high altitude; the main structure of the "Z"-shaped special-shaped connecting beam refers to the part of the corridor that can be directly projected to the ground without being affected by the structure. A tire frame is set on the surface. After being assembled into a whole by a car crane, the part of the steel structure is planned to be lifted as a whole at one time. There are 4 docking positions and 8 docking points between the 3 sections of the corridor and the 4 main buildings, and a group of hoists are set for each; the supplementary rod refers to the steel structure rod that connects the pre-installed section and the main structure of the "Z"-shaped special-shaped connecting beam after the pre-installed section is installed and the main structure of the "Z"-shaped special-shaped connecting beam is lifted to the specified elevation.
[0049] In this embodiment, the overall installation idea of the "Z"-shaped special-shaped aerial corridor is: construction preparation work → measurement of defense line → erection of cantilever operation platform → installation of pre-installed steel structure → installation of lifting bracket → installation of roof lifting equipment → installation of ground frame → overall assembly of the main structure of the ground "Z"-shaped special-shaped connecting beam → installation of floor decking → commissioning of lifting equipment → preparation work before lifting → overall lifting of steel corridor → addition of poles → unloading.
[0050] The specific steps are as follows:
[0051] 1. Construction preparation, measuring defense lines and building cantilevered operating platforms
[0052] (1) Before construction, construction layout shall be carried out, and the column base position, elevation, and site entrance and exit positions shall be checked to ensure that they are correct before use;
[0053] (2) Confirm the lifting plan, including the overall plan, assembly sequence, material stacking, equipment entry and exit routes, etc.;
[0054] (3) The road surface and foundation of the equipment access route and support position should be leveled and compacted;
[0055] (4) Effective protective measures must be taken for high-altitude operations;
[0056] (5) Pay attention to local weather conditions, take wind and flood prevention measures, and do a good job of site leveling;
[0057] (6) Effective protection measures should be taken for wires, cables and pipe trenches within the construction site;
[0058] (7) Ensure security and isolation of the construction site;
[0059] (8) Build cantilevered operating platforms on the first building, the second building, the third building, and the fourth building.
[0060] 2. Install the pre-assembled steel structure
[0061] The pre-installed section is affected by the building structure. In order to avoid the parts that cannot be directly lifted, a 200-ton crawler crane is needed to directly install some steel structures at high altitude. The installation method uses high-altitude loose parts lifting and installation.
[0062] The pre-installed section is mainly composed of embedded parts, embedded part connectors, a truss lower chord, a truss straight web, a truss diagonal web and a truss upper chord. Among them, the embedded parts need to be pre-embedded in the main bodies of the first building, the second building, the third building and the fourth building according to the design drawings during the construction of the main bodies of the first building, the second building, the third building and the fourth building. The truss lower chord and the truss upper chord are connected by truss straight webs to form a semi-enclosed pre-installed section frame structure. At the same time, the truss diagonal webs are obliquely arranged on both sides of the opening of the pre-installed section frame structure to increase the stability between the truss lower chord and the truss upper chord. One side of the opening of the frame structure of the preinstalled section is used to connect the main structure of the "Z"-shaped special-shaped connecting beam, and an embedded part connector is set on the side of the preinstalled section opposite to the opening, and the preinstalled section is connected to the main body of the first building, the second building, the third building and the fourth building through the embedded part connector. Secondly, a support frame is also provided at the bottom end of the preinstalled section, one end of the support frame is set at a position close to the opening at the bottom end of the preinstalled end, and the other end of the support frame is connected to the main body of the first building, the second building, the third building and the fourth building through the embedded parts on the main body of the first building, the second building, the third building or the fourth building.
[0063] The specific steps of pre-installed steel structure are as follows:
[0064] (1) When constructing the main body of the first, second, third and fourth buildings, embed floor embedded parts in the first, second, third and fourth buildings in advance according to the design drawings;
[0065] (2) Plan the installation positions of the truss lower chord, truss straight web, truss upper chord, truss diagonal web and support frame according to the design drawings;
[0066] (3) Installing a support frame on the first building, the second building, the third building and the fourth building through a cantilevered operating platform to form a support platform for assembling the pre-assembled section, hoisting the lower chord of the truss to the installation position of the lower chord of the truss, and providing an embedded component connector at one end of the lower chord of the truss, connecting the lower chord of the truss to the embedded floor components embedded in the first building, the second building, the third building and the fourth building through the embedded component connector, and at the same time connecting the support frame to the bottom end of the lower chord of the truss, thereby supporting the lower chord of the truss through the support frame;
[0067] (4) hoisting the truss straight web member to the installation position of the truss straight web member through the cantilever operating platform, so that one end of the truss straight web member is fixedly arranged on the end of the truss lower chord portion connected to the embedded part, and an embedded part connector is arranged at the other end of the truss straight web member, and the truss straight web member is connected to the embedded part through the embedded part connector;
[0068] (5) hoisting the truss upper chord to the installation position of the truss upper chord through the cantilever operating platform, and connecting it with the truss straight web bar to form a semi-enclosed pre-assembled segment frame structure;
[0069] (6) The truss diagonal web members are obliquely arranged on both sides of the opening of the pre-installed section frame structure, thereby completing the installation of the pre-installed section steel structure.
[0070] In order to prevent the main structure of the "Z"-shaped special-shaped connecting beam from being unable to be connected with the preinstalled end due to construction errors, in the present embodiment, the preinstalled sections on the first building body, the third building body and the fourth building body are fixedly welded to the first building body, the second building body and the fourth building body, while the preinstalled section on the second building body is only temporarily fixed to the second building body. When the main structure of the "Z"-shaped special-shaped connecting beam is connected with the preinstalled end, the preinstalled section on the second building body is adjusted (that is, the components of the preinstalled section on the second building body are temporarily fixed by bolts. When the main structure of the "Z"-shaped special-shaped connecting beam is connected with the preinstalled end, the preinstalled section on the second building body can be adjusted by adjusting the position of the component or replacing the component), and then the deviation between the main structure of the "Z"-shaped special-shaped connecting beam and the preinstalled section is adjusted, so that the main structure of the "Z"-shaped special-shaped connecting beam can be connected with the preinstalled section smoothly.
[0071] In an optional embodiment, the "Z"-shaped special-shaped skywalk is a double-layer structure. Therefore, in order to meet the installation requirements of the "Z"-shaped special-shaped connecting beam main structure, the above steps (4) to (6) can be repeated on the basis of the above-mentioned pre-installed section steel structure, and an upper frame layer can be set on the top of the above-mentioned pre-installed section steel structure.
[0072] 3. Install lifting device
[0073] The lifting device mainly consists of four parts: lifting bracket, hydraulic lifter, hydraulic pump source system and synchronous control system, among which:
[0074] The lifting bracket is usually made of steel and is used to provide support for the hydraulic lifter and stabilize the heavy objects during the process of lifting the main structure of the "Z"-shaped special-shaped coupling beam.
[0075] The hydraulic lifter is a through-core structure, with flexible steel strands as lifting rigging. The hydraulic lifter uses a hydraulic system to drive the lifting action. It includes one or more hydraulic cylinders, which generate linear motion through liquid pressure to lift heavy objects. The steel strands are used as flexible load-bearing rigging, and high-strength, low-relaxation prestressed steel strands are used. The configuration principle of the steel strands is based on the actual load of a single steel strand not exceeding 50% of the theoretical breaking force.
[0076] The hydraulic pump source system provides hydraulic power for the hydraulic lifter and completes the corresponding actions under the control of various hydraulic valves. In different engineering uses, the requirements and models of lifters are different. In order to improve the versatility and reliability of hydraulic lifting equipment, the design of the pump source hydraulic system adopts a modular structure. The number of pump source systems is configured according to the number and model of lifters, and multiple modules can be combined. Each module is based on a pump source system. It can independently control a group of hydraulic lifters and can be expanded to multiple lifting points to meet the needs of actual lifting projects. In this embodiment, a hydraulic pump source system with a rated power of 60KW can be selected.
[0077] The hydraulic synchronous control system is mainly controlled by a computer control system. Through data feedback and control command transmission, it can automatically realize multiple functions such as synchronous action, load balancing, posture correction, stress control, operation locking, process display and fault alarm.
[0078] The specific installation steps of the lifting device are as follows:
[0079] 1. Install lifting brackets: According to the design drawings, install two sets of lifting brackets on the first building, the second building, the third building and the fourth building respectively by means of high-altitude scattered parts hoisting installation;
[0080] 2. Install the hydraulic lifter: According to the weight of the connected structure and the configuration of the hydraulic lifter, install a hydraulic lifter on each set of lifting brackets by hoisting;
[0081] 3. Install steel strand:
[0082] Use a grinding wheel cutter or gas cutting machine to cut the steel strand into the specified length, and use a grinder or gas cutting machine to repair the two ends of the steel strand to make it smooth and round without loose strands;
[0083] Install the drainage plate directly below the lifter, adjust the position of the drainage plate holes to align them with the anchor holes of the lifter (note the triangular structure), and temporarily fix them;
[0084] Use a catheter to check the sky anchor, upper anchor, middle partition, lower anchor, safety anchor and drainage plate holes of the riser from top to bottom to ensure that the corresponding holes are aligned;
[0085] The guide tube is passed through the sky anchor, upper anchor, middle partition, lower anchor, safety anchor and drainage plate from top to bottom, and the position is ensured to be correct; the steel strand is passed through the guide tube in turn through the sky anchor, upper anchor, middle partition, lower anchor, safety anchor and drainage plate, and the remaining part of the steel strand at the top of the hoist is locked on the sky anchor with a temporary anchor plate; each steel strand of the hoist must be inserted in a left-hand or right-hand rotation interval; and generally, a small part of the outer circle is inserted first, then the entire inner circle, and then the remaining outer circle is inserted (left-hand or right-hand rotation intervals);
[0086] After threading two steel strands, use a clamp to clamp the steel strands in pairs to prevent them from slipping out of the air;
[0087] After all the steel strands are threaded, use the upper and lower anchor cylinders to lock the steel strands, and tighten the anchor plate screws to lock the sky anchor;
[0088] 4. Install the hydraulic pump system: select the hydraulic pump system according to the number of hydraulic lifters and the reaction force value of each lifting point. In this embodiment, a hydraulic pump system is installed on the first building, the second building, the third building and the fourth building respectively. Each pump controls two hydraulic lifters. Secondly, the pump is arranged close to the lifter so that the hydraulic oil pipe between the lifter and the pump is as short as possible.
[0089] 5. Arrange the computer synchronous control system: install a pressure sensor in the oil cylinder of the hydraulic pump source system, and connect the computer synchronous control system with the pressure sensor and the proportional valve and solenoid valve of the hydraulic pump source system.
[0090] In this embodiment, the lifting device also includes a guide frame. During the lifting or lowering process of the hydraulic lifter, the top of the guide frame must be reserved for the excess steel strands. If too many steel strands are reserved, it will have a great impact on the operation of the steel strands during the lifting or lowering process and the locking and opening of the sky anchor and upper anchor of the hydraulic lifter. Therefore, each hydraulic lifter must be equipped with a guide frame in advance to facilitate the smooth export of the excess steel strands reserved at the top. The guide frame is a frame structure, which is arranged on the lifting bracket, and the upper end of the guide frame is a receiving portion for receiving the steel strands, thereby playing a guiding role.
[0091] In this embodiment, it should be noted that if the bottom end of the steel strands is uneven after being threaded, a horizontal line should be drawn on all the steel strands at the appropriate position, and the steel strands below the line should be cut off, and the ends of the steel strands should be repaired to be smooth;
[0092] 4. Ground-assembled "Z"-shaped special-shaped connecting beam main structure
[0093] (1) Setting up a flat tire stand
[0094] The installation positions of the Z-shaped special-shaped connecting beam main structure on the first building, the second building, the third building and the fourth building are provided with an assembly area for assembling the Z-shaped special-shaped connecting beam main structure at the orthographic projection of the ground, and a flat tire frame for receiving the Z-shaped special-shaped connecting beam main structure is provided in the assembly area. By supporting and fixing various parts of the Z-shaped special-shaped connecting beam main structure, the stability and safety of the steel frame during the assembly process are ensured.
[0095] Specific:
[0096] 1. First, draw the total length of the truss and the arch height at the midpoint in the drawing software, then loft the arch height of each node according to the length of each section of the truss to form a lofting diagram, and then make the truss processing drawing based on the lofting diagram.
[0097] 2. Establish the model of the main structure of the "Z"-shaped special-shaped coupling beam according to the truss processing drawing, and extract the control point coordinates of the node according to the model;
[0098] 3. Use the total station to mark the control points corresponding to the coordinates of the control points in the assembly area, and erect a flat tire frame based on the control points.
[0099] (2) Assembly of the main structure of the “Z” shaped special-shaped connecting beam
[0100] The main structure of the "Z"-shaped special-shaped coupling beam includes a main truss composed of a main truss lower chord, a main truss lower chord connecting beam, a main truss web, a main truss upper chord, and a main truss upper chord connecting beam, and a secondary truss composed of a secondary truss lower chord, a secondary truss lower chord connecting beam, a secondary truss web, a secondary truss upper chord, and a secondary truss upper chord connecting beam. The specific steps are as follows:
[0101] 1. Plan the splicing positions of the lower chord of the main truss and the lower chord of the secondary truss in the assembly area according to the coordinates of the control points;
[0102] 2. Install the main truss lower chord at the corresponding splicing position of the main truss lower chord in the assembly area, and connect the main truss lower chord connecting rod between the main truss lower chords to form a stable main truss lower chord plane structure;
[0103] 3. Start from both ends of the lower chord plane structure of the main truss and install the main truss web members in sequence towards the middle;
[0104] 4. Install the main truss upper chord on the main truss web, and connect the main truss upper chord connecting beam between the main truss upper chords to form the main truss;
[0105] 5. Follow steps 1-4 to assemble the secondary trusses at both ends of the main truss.
[0106] (3) Review of the assembly dimensions of the main structure of the “Z”-shaped special-shaped coupling beam
[0107] After the truss is assembled, it will be self-inspected before all-round welding. After passing the self-inspection, it will be handed over to a full-time quality inspector for inspection, and then handed over to the supervisor for acceptance. Only after passing the acceptance can welding be carried out.
[0108] The main contents of truss inspection and acceptance are the elevation of the truss assembly node position, the axis position and the spacing between the truss nodes, and the design arch size of the truss is also checked.
[0109] 5. The lifting device is connected to the main structure of the "Z"-shaped special-shaped connecting beam
[0110] The lifting devices on the first building, the second building, the third building and the fourth building are used as upper hanging points, and the positions of the lower hanging points are determined according to the orthographic projection positions of the upper hanging points on the main structure of the "Z"-shaped special-shaped coupling beam (that is, two sets of lower hanging points are respectively provided at the two ends of the main structure of the "Z"-shaped special-shaped coupling beam and the corners of the main structure of the "Z"-shaped special-shaped coupling beam);
[0111] After determining the position of the lower hanging point, use a soft rope to lower the drainage plate to the upper part of the lower hanging point, and adjust the orientation of the drainage plate; adjust the position of the anchor hole of the ground anchor to align it with the hole of the drainage plate, insert the steel strands into the ground anchor in sequence and align them, lock the steel strands, and finally install the ground anchor on the truss at the corresponding lower hanging point.
[0112] 6. "Z" shaped special-shaped connecting beam main structure improvement
[0113] The lifting process of the main structure of the "Z"-shaped special-shaped coupling beam can be divided into two main stages, namely the trial lifting stage and the formal lifting stage. In the trial lifting stage, through careful observation and monitoring of the steel structure, lifting facilities and lifting equipment system, it is verified whether these components meet the calculation predictions and design requirements under simulated working conditions. This preliminary lifting test is crucial to ensure the safety of the entire lifting operation.
[0114] The goal of the subsequent formal lifting phase is to accurately lift the main structure of the "Z"-shaped special-shaped coupling beam to the predetermined height position. This phase is carried out after completing the trial lifting phase and confirming that all systems are operating normally, and aims to achieve accurate transfer of the structure from the ground to the final position.
[0115] These two stages each have specific tasks and together ensure the safety, accuracy and success of the entire lifting operation.
[0116] (1) Trial promotion
[0117] 1. During the lifting process, the steel structure, lifting facilities and equipment systems are carefully observed and monitored to ensure that they meet the predetermined simulation conditions and design parameters to ensure the safety of the entire lifting process.
[0118] 2. Based on the theoretical load of the main structure, the lifting equipment is loaded at each lifting point in stages, reaching 20%, 40%, 60%, and 80% in sequence. After confirming that all parts have no abnormal response, it can continue to increase to 90%, then 100%, until the steel structure is completely off the ground.
[0119] 3. After each level of loading, the structural condition of the stress point must be checked. Use a total station to track and measure the height difference and deflection of the steel structure so that necessary adjustments can be made after the structure leaves the ground. At the same time, all monitoring data during the loading process should be recorded in detail.
[0120] 4. When the graded loading is nearly completed, that is, when the steel structure is about to be lifted from the assembly cradle (or directly from the ground), it is possible that each point will not leave the ground synchronously. At this time, it is necessary to reduce the lifting speed and carefully monitor the lifting situation of each point. If necessary, the lifting device can be used to make separate lifting adjustments for the lagging points to ensure that the structure is lifted off the ground smoothly and all points are synchronized.
[0121] 5. After completing the graded loading and lifting the structure to about 100mm above the assembly frame, pause and keep this state for 12 hours for a comprehensive inspection. During this period, organize relevant professionals to conduct detailed special inspections on the lifting bracket, steel structure, lifting device, connecting parts and all lifting related equipment.
[0122] 6. After the stay period, each professional team will summarize the inspection results and, after confirming that there are no potential risks or problems, officially issue an upgrade order to start the next stage of upgrade work.
[0123] (2) Formal promotion
[0124] During the formal lifting operation, the first task is to ensure that the main structure of the "Z"-shaped special-shaped coupling beam can be lifted smoothly along the set channel. This process is achieved through a computer synchronous control system, which coordinates the lifting devices on the first, second, third and fourth floors to ensure that they lift the main structure of the "Z"-shaped special-shaped coupling beam synchronously.
[0125] During the lifting process, every time the main structure is lifted by 5 meters, the engineering team will suspend the operation and use a total station or sensor to accurately measure the height of each connection point between the lifting device and the main structure of the "Z"-shaped special-shaped coupling beam. This is done to detect whether there is a height difference between the connection points, the so-called asynchronous height difference. If the height difference of any connection point is found to exceed the specified range, the engineering team will correct the height difference by adjusting the lifting device corresponding to the connection point to ensure that the height difference of all connection points does not exceed 25 mm.
[0126] In this project, the formal lifting is divided into two stages. The first stage is the normal lifting stage, during which the lifting device operates at the preset first lifting speed to stably lift the main structure of the "z"-shaped special-shaped coupling beam. When the main structure approaches the predetermined height and is only 1 meter away from the target, it enters the second stage, the slow lifting stage. In this stage, the lifting device will reduce the lifting speed and switch to the second lifting speed (which is lower than the first lifting speed) for operation. The purpose of this is to more finely control the lifting posture and accuracy of the main structure of the "z"-shaped special-shaped coupling beam, and ensure the stability and accuracy of the entire lifting process.
[0127] This strategy of controlling the lifting speed in stages, combined with precise monitoring and timely adjustments, can effectively ensure the stability and safety of the main structure of the "Z"-shaped special-shaped coupling beam during the entire lifting process, while meeting the requirements of precise installation.
[0128] In this embodiment, one of the lower hanging points is set as the master command point, and the other lower hanging points are slave command points. The speed and position of the lifting device lifting the master command point are taken as standard values, and the position heights of the other slave command points are obtained. By calculating the height difference between the master command point and the other slave command points, the lifting speed of the slave command point is controlled, and the position height of the slave command point is kept consistent with that of the master command point. Specifically, by calculating the height difference between the master command point and the other slave command points (i.e., the height difference between the slave command point and the master command point = the position height of the slave command point - the position height of the master command point), when a certain slave command point is lifted, the height difference between the master command point and the other slave command points is calculated. When the height difference between a certain slave point and the master point is positive, it is judged that the position of the slave point is higher than the position of the master point. At this time, the computer synchronous control system controls the lifting device of the slave point to reduce the lifting speed of the slave point, so that the position of the slave point follows the master point consistently; and when the height difference between a certain slave point and the master point is negative, it is judged that the position of the slave point is lower than the position of the master point. At this time, the computer synchronous control system controls the lifting device of the slave point to increase the lifting speed of the slave point, so that the position of the slave point follows the master point consistently.
[0129] In this embodiment, the computer synchronous control system also integrates an alarm function for the safety of the system. When the height difference between any slave command point and the master command point exceeds the preset critical value, the control system will automatically determine the possible equipment failure and instruct all lifting devices to stop operating. This measure enables the staff to carry out necessary inspections and maintenance to ensure the safety and accuracy of the entire lifting process.
[0130] This control strategy effectively optimizes the synchronization and precision of the lifting process, while increasing the safety of the operation and ensuring the smooth lifting of the entire structure.
[0131] In this embodiment, after the main structure of the "Z"-shaped special-shaped connecting beam is lifted to a predetermined height, posture detection is performed on each lifting point when the main structure of the "Z"-shaped special-shaped connecting beam is lifted to a predetermined height, and the lifting device is controlled to adjust the main structure of the "Z"-shaped special-shaped connecting beam according to the posture detection data, so that each end of the main structure of the "Z"-shaped special-shaped connecting beam is lifted to a predetermined height and is aligned with the corresponding pre-installed section.
[0132] In this embodiment, a lower winding deformation threshold is set to detect the lower winding deformation of each end of the "Z"-shaped special-shaped connecting beam main structure. When the lower winding deformation is less than the lower winding deformation threshold, the "Z"-shaped special-shaped connecting beam main structure and the pre-assembled section steel structure are connected by a weld transition. When the lower winding deformation is greater than the lower winding deformation threshold, the end of the "Z"-shaped special-shaped connecting beam main structure is adjusted by a jack.
[0133] More preferably, in the present embodiment, before assembling the main structure of the "Z"-shaped special-shaped connecting beam on the ground, the downward deformation of each end of the main structure of the "Z"-shaped special-shaped connecting beam is calculated by computer simulation, and the downward deformation of each end of the main structure of the "Z"-shaped special-shaped connecting beam is compared with the downward deformation threshold. When the downward deformation of each end of the main structure of the "Z"-shaped special-shaped connecting beam is greater than the downward deformation threshold, the main structure of the "Z"-shaped special-shaped connecting beam is assembled on the ground, and the end of the main structure of the "Z"-shaped special-shaped connecting beam greater than the downward deformation threshold is pre-arched to overcome the downward deformation of the end of the main structure of the "Z"-shaped special-shaped connecting beam during the lifting process, thereby ensuring that the quality of the butt welding meets the requirements.
[0134] 7. "Z" shaped special-shaped connecting beam main structure connection
[0135] After the main structure of the "Z"-shaped special-shaped connecting beam is lifted to the specified elevation, a supplementary rod is set between the end of the main structure of the "Z"-shaped special-shaped connecting beam and the pre-installed section by means of supplementary rod welding, so that the main structure of the "Z"-shaped special-shaped connecting beam is fixedly connected to the pre-installed section steel structure of the first building, the second building, the third building and the fourth building. After the supplementary rod welding operation is completed, the weld is inspected by nondestructive testing.
[0136] 8. Uninstall by levels
[0137] After the welding seam of the patch rod has passed the flaw detection inspection, the lifting device is controlled to unload the main structure of the "Z"-shaped special-shaped coupling beam in stages, which are 20%, 40%, 60% and 80% respectively. The condition of each part is detected during the staged unloading process. When it is confirmed that there is no abnormality in each part, the next stage of unloading can be continued until it is unloaded to 100%, that is, the steel strand of the lifter is no longer stressed, the structural load is completely transferred to the pre-installed section, and the structural stress form is converted into the design working condition.
[0138] 9. Dismantle the lifting device
[0139] After the lifting device completely removes the load on the main structure of the "Z"-shaped special-shaped connecting beam, cut the connection between the steel strand and the main structure of the "Z"-shaped special-shaped connecting beam to separate the lifting device from the main structure of the "Z"-shaped special-shaped connecting beam, and finally remove the lifting devices on the first building, the second building, the third building and the fourth building.
[0140] In this embodiment, it also includes step 10, dismantling the support members. During step 2, installing the pre-installed section steel structure, it is necessary to first temporarily build support members on the first building, the second building, the third building and the fourth building through a cantilevered operating platform to provide a support platform for the assembly of the pre-installed sections. Therefore, after completing the connection between the main structure of the "Z"-shaped special-shaped connecting beam and the pre-installed section, the temporarily built support members need to be dismantled.
[0141] The above disclosures are only several specific embodiments of the present invention, but the present invention is not limited thereto, and any changes that can be conceived by those skilled in the art should fall within the protection scope of the present invention.
Claims
1. A method for installing a special-shaped sky corridor between high-rise buildings, which is used to set up a "Z"-shaped special-shaped sky corridor between the first building, the second building, the third building and the fourth building which are staggered, characterized in that: The following steps are involved: S1. Build a cantilevered operating platform: S2. Install the pre-assembled steel structure and lifting device on the top of the first building, the second building, the third building and the fourth building through the cantilevered operating platform; S3, ground assembly of the main structure of "Z"-shaped special-shaped connecting beams; S4, using the lifting devices on the first building, the second building, the third building and the fourth building as the hanging points, determining the positions of the connecting parts according to the orthographic projection positions of the hanging points on the main structure of the "Z"-shaped special-shaped coupling beam, and connecting the steel strands of the lifting devices to the corresponding connecting parts; S5. Lift the main structure of the "Z"-shaped special-shaped coupling beam to a predetermined height through the lifting devices on the first building, the second building, the third building and the fourth building; S6. A supplementary rod is arranged between the main structure of the "Z"-shaped special-shaped connecting beam and the pre-installed steel structure, so that the main structure of the "Z"-shaped special-shaped connecting beam is fixedly connected to the pre-installed steel structure of the first building, the second building, the third building and the fourth building; S7, unloading, dismantling the lifting devices on the first building body, the second building body, the third building body and the fourth building body.
2. The installation method for special-shaped sky corridors between high-rise buildings according to claim 1 is characterized in that: Before step S3, the method further includes: S3', the installation positions of the "Z"-shaped special-shaped connecting beam main structure on the first building, the second building, the third building and the fourth building are provided with an assembly area for assembling the "Z"-shaped special-shaped connecting beam main structure at the orthographic projection of the ground, and a flat tire frame for receiving the "Z"-shaped special-shaped connecting beam main structure is provided in the assembly area.
3. The installation method for special-shaped sky corridors between high-rise buildings according to claim 1 is characterized in that: When the main structure of the "Z"-shaped special-shaped connecting beam is lifted to a predetermined height, posture detection is performed on each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam to obtain posture detection data of each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam, and the lifting device is controlled to adjust each lower hanging point of the main structure of the "Z"-shaped special-shaped connecting beam according to the posture detection data.
4. The installation method for special-shaped sky corridors between high-rise buildings according to claim 3 is characterized in that: Sensors are arranged at each hanging point on the main structure of the "Z"-shaped special-shaped coupling beam, and posture detection data of each hanging point on the main structure of the "Z"-shaped special-shaped coupling beam is obtained in real time through the sensors.
5. The installation method for special-shaped sky corridors between high-rise buildings according to claim 2 is characterized in that: A model of the main structure of the "Z"-shaped special-shaped coupling beam is established, and the control point coordinates of each node of the main structure of the "Z"-shaped special-shaped coupling beam are extracted according to the model; the control points corresponding to the control point coordinates are marked in the assembly area, and a flat tire frame is erected at the control points.
6. The installation method for special-shaped sky corridors between high-rise buildings according to claim 5 is characterized in that: The main structure of the "Z"-shaped special-shaped coupling beam includes a main truss composed of a main truss lower chord, a main truss lower chord connecting beam, a main truss web, a main truss upper chord, and a main truss upper chord connecting beam, and a secondary truss composed of a secondary truss lower chord, a secondary truss lower chord connecting beam, a secondary truss web, a secondary truss upper chord, and a secondary truss upper chord connecting beam. Step S3 includes: A1. Plan the splicing positions of the lower chord of the main truss and the lower chord of the secondary truss in the assembly area according to the coordinates of the control points of each node of the main structure of the "Z"-shaped special-shaped coupling beam; A2. Install the main truss lower chord at the corresponding splicing position of the main truss lower chord in the assembly area, and connect the main truss lower chord connecting rod between the main truss lower chords to form a stable main truss lower chord plane structure; A3. Install the main truss web members from both ends of the lower chord plane structure of the main truss toward the middle; A4. Install the main truss upper chord on the main truss web, and connect the main truss upper chord connecting beam between the main truss upper chords to form the main truss; A5. According to steps A2, A3 and A4, assemble the secondary trusses at both ends of the main truss.
7. The installation method for special-shaped sky corridors between high-rise buildings according to claim 1 is characterized in that: The pre-installed steel structure sections at the roofs of the first building, the second building, the third building and the fourth building are installed on the roofs of the first building, the second building, the third building and the fourth building by means of high-altitude loose-fitting hoisting installation. The components of the pre-installed steel structure sections at the roofs of the first building, the second building, the third building and the fourth building are fixedly arranged on the first building, the third building and the fourth building by welding, while the components of the pre-installed steel structure sections of the second building are movably arranged on the second building by means of bolts.
8. The installation method for special-shaped sky corridors between high-rise buildings according to claim 1 is characterized in that: In step S6, the patch rod is fixedly connected to the "Z"-shaped special-shaped coupling beam main structure and the pre-assembled section steel structure by welding; and after the patch rod welding operation is completed, the weld is inspected by flaw detection.
9. The installation method for special-shaped sky corridors between high-rise buildings according to claim 1, characterized in that: Set the lower winding deformation threshold, detect the lower winding deformation of each end of the "Z"-shaped special-shaped coupling beam main structure, when the lower winding deformation is less than the lower winding deformation threshold, connect the "Z"-shaped special-shaped coupling beam main structure and the pre-assembled section steel structure by means of weld transition, when the lower winding deformation is greater than the lower winding deformation threshold, adjust the end of the "Z"-shaped special-shaped coupling beam main structure by a jack.