Underground roadway drainage method based on aquifer freezing
By using the aquifer freezing method in coal mining, the problem of difficulty in draining the roof aquifer when tunneling downhill in steep-angle tunnels has been solved, achieving complete drainage of the water body and ensuring the safety and efficiency of tunneling construction.
Patent Information
- Application Number
- CN202410886315.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-03
- Publication Date
- 2024-10-01
AI Technical Summary
In the process of coal mining, especially when tunneling with high angles downhill, the traditional gravity flow method is difficult to completely drain the roof aquifer, resulting in water-conducting cracks penetrating into the aquifer, causing water inrush on the working face, and the existing method has safety hazards and increases Project quantity issues.
The underground tunnel water drainage method based on aquifer freezing is adopted. By obtaining hydrogeological and mining technical parameters, the freezing range is determined, freezing holes are arranged in the tunnel, and freezing and thawing are carried out during the excavation process to ensure complete drainage of the water body and reduce Risk of water inrush.
It achieves the thorough drainage of aquifers that are difficult to drain with traditional methods, ensures safe mining at the working face, reduces the risk of water inrush, reduces the workload of equipment and workers, increases the excavation rate, and controls water pressure and outflow speed.
Smart Images

Figure CN118728477A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of drainage methods for tunneling, in particular to an underground tunnel drainage method based on freezing of aquifers. Background Art
[0002] Mine water hazards are one of the most common and serious problems that endanger the personal safety of miners and the safety of mine property in the process of coal mining. For coal mine water prevention and control, the "Coal Mine Safety Regulations" and the "Coal Mine Water Prevention and Control Regulations" both stipulate the basic principles of "prediction and forecast, exploration when in doubt, exploration before excavation, and treatment before mining". However, in the process of downhill excavation of some large-angle tunnels, due to the low water level and low water pressure of the aquifer on the roof of the tunnel ahead, the traditional gravity method of exploration and drainage cannot be released, or only a part of it can be released. Due to the low water content of the aquifer, the roof aquifer must be thin. If the tunnel continues to advance, the impact of mining can easily cause the water-conducting cracks in the roof to penetrate into the aquifer, causing water inrush at the working face. In addition, if the aquifer cannot be completely drained, it will bring huge challenges to the safe and efficient recovery of the later working face.
[0003] At present, the following methods and measures are mainly used for the above-mentioned complex and difficult-to-release water bodies: (1) Strengthen support and seal water-conducting fissures through grouting anchor cables, continue to excavate forward to the appropriate position and then conduct water exploration and release; (2) Change the layout of the tunnel orientation, inclination, etc. to conduct advanced water exploration and release; (3) Add auxiliary cutting grooves or tunnels to conduct advanced water exploration and release. Although these methods and measures have been effective in some mines, they may have certain safety hazards, or fail to completely drain the aquifer, or change the original tunnel design, increase the amount of excavation and support engineering, and limit the efficient mining of the mine. In addition, the above methods and measures are not universally applicable and cannot fundamentally solve the reasonable and effective drainage of complex and difficult-to-release water bodies. Therefore, for mines in water-rich mining areas, especially modern large-scale mines, how to scientifically drain aquifers under special conditions has become a key issue that needs to be solved urgently. Summary of the invention
[0004] In order to overcome the various shortcomings of the prior art, the present invention provides an underground tunnel water exploration and drainage method based on aquifer freezing, which can effectively freeze and consolidate the aquifer in close proximity to the roof of the steeply inclined tunnel, while ensuring safety, minimizing the impact of the roof aquifer on the normal excavation and construction of the tunnel, and at the same time achieving complete drainage of the water body.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is: A method for draining water from underground tunnels based on freezing of aquifers comprises the following steps: Step 1: Obtain the hydrogeological information of the target coal stratum and the technical parameters of the tunnel mining, where the hydrogeological information includes: the length of the aquifer along the tunnel direction;l ,thickness h , distribution range of aquifer, water volume and water pressure of aquifer p , aquifer recharge, runoff and discharge information; tunnel mining technical parameters include: tunnel design azimuth, inclination, tensile strength of roof aquifer σ b , Lane width L , height, tunnel support form and support technical parameters; Step 2: Determine the freezing range of the aquifer based on the hydrogeological information and tunnel mining technical parameters obtained in step 1; Step 3: Within the freezing range, a row of freezing holes is arranged at the same distance along the center line of the laneway, and then a number of freezing holes are arranged at the same distance on both sides with the row of freezing holes as the center, until the freezing range is filled with a number of freezing holes with the same spacing, thereby completing the freezing hole construction, and then carrying out the preparation work before freezing; Step 4: Excavate the tunnel. When the tunnel is excavated to the distance from the aquifer water body, When the freezing process starts, K is the safety factor; Step 5: Continue tunneling and support operations during the freezing process. When the tunnel is excavated to the lowest position of the aquifer, drill water holes in the top plate to the lowest end of the water body, install water pipes, and construct water storage tanks in the tunnel and install drainage facilities to prepare for water drainage. Step 6, draining water by thawing the aquifer; Step 7: After the water in the aquifer is drained, withdraw the water pipes and drainage pipes. After the withdrawal work is completed, continue to excavate the tunnel.
[0006] Furthermore, the freezing range of the water layer in step 2 is: the freezing width is the lane width L+ 10. The freezing length is the length of the aquifer along the tunnel direction. l , the freezing height is the thickness of the aquifer along the tunnel direction h .
[0007] Furthermore, in step 4, the freezing work is performed in the order of high water level first, then low water level, and then the middle and then the two ends.
[0008] Furthermore, in step 4, the safety factor K= 4~10, safety factor K The specific value of is determined according to the water conductivity of the tunnel surrounding rock, the freezing rate of the aquifer and the tunnel excavation speed.
[0009] Furthermore, in step 5, the tunnel support type and support parameters of the frozen section are related to the surrounding rock type, the thickness of the roof aquiclude, the lithology and the freezing condition of the aquifer.
[0010] Furthermore, in step 6, the thawing sequence is carried out in the order of low water level first, then high water level, first the middle and then the two sides, and the thawing speed is adjusted at any time according to the water pressure displayed by the water pressure valve.
[0011] Compared with the prior art, the present invention has the following advantages: (1) The present invention uses a method of freezing and thawing the aquifer to effectively drain the aquifer on the roof of the downhill tunnel, which is difficult to drain or can only be partially drained by traditional water exploration and drainage methods, and can achieve complete drainage, ensuring safe recovery of the working face.
[0012] (2) In the present invention, when the tunnel is excavated to a certain distance from the aquifer, the aquifer is frozen to make the water lose its fluidity and permeability, thereby reducing the risk of water inrush and achieving the inherent safety of tunnel excavation construction in the water-rich roof.
[0013] (3) The present invention installs a water pipe at the bottom of the aquifer to conduct centralized and unified exploration and drainage, thereby reducing the amount of equipment used and the workload of workers, reducing the cost of exploration and drainage, and increasing the tunnel excavation rate.
[0014] (4) The present invention controls the water pressure and outflow rate by adjusting the thawing rate of the aquifer, thereby achieving uniform water outflow and safe and controllable water exploration and release process. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the arrangement of freezing holes for the aquifer in the tunnel roof of the present invention; Figure 2 It is a cross-sectional view of the arrangement of freezing holes for the water-bearing layer in the roof of the tunnel according to the present invention, taken along the AA direction; In the figure: 1-excavated tunnel, 2-tunnel to be excavated, 3-aquifer water body, 4-freezing hole, 5-water pipe. DETAILED DESCRIPTION
[0016] The present invention is further described below in conjunction with the accompanying drawings and embodiments.
[0017] like Figure 1 As shown, this embodiment discloses a method for draining water from underground tunnels based on freezing of aquifers, which is described by taking a certain western mine field as an example.
[0018] A mine in the west of China with an area of 165km 2, with a strike length of 14.5km, a dip length of 11.7km, a mine geological reserve of 1929.13Mt, and recoverable reserves of 1035.72Mt. The main mining coal seam is generally monocline, without large faults and fold structures, with a coal seam dip angle of 5.5-37°, an average dip angle of 17.5°, a coal seam burial depth of 125-520m, a stable coal seam occurrence, and an average thickness of 3.0m. There are multi-layer porous and fissure aquifers such as the Grape Valley Formation and the Xishan Kiln Formation within the mining range of the mine. Among them, there is a water-rich strong-medium aquifer with a permeability coefficient of 0.196-0.853m / d and a unit water inflow q of 0.0597-0.8680L / s·m above the main mining coal seam. The existence of this aquifer has a serious impact on the tunnel excavation and working face recovery, and it must be effectively drained during the tunnel excavation process. However, according to the mining design and tunnel layout, due to the large inclination of the tunnel and the downhill excavation, the traditional water exploration and drainage method cannot completely drain the roof water. The process of freezing the roof aquifer of a western mine is as follows: Step 1: Obtain the hydrogeological information of the target coal stratum and the technical parameters of the tunnel mining, where the hydrogeological information includes: the length of the aquifer along the tunnel direction; l ,thickness h , distribution range of aquifer, water volume and water pressure of aquifer p , aquifer recharge, runoff and discharge information; tunnel mining technical parameters include: tunnel design azimuth, inclination, tensile strength of roof aquifer σ b , Lane width L , height, tunnel support form and support technical parameters.
[0019] For a certain western mine, the hydrogeological information obtained in this embodiment includes: the length of the aquifer along the tunnel direction l= 25m, thickness h= 7m, the impermeable layer is mudstone, and the water pressure of the aquifer is p= 1.3MPa, the aquifer recharge conditions are poor and there is very little recharge water source.
[0020] For a certain western mine, the tunnel mining technical parameters obtained in this embodiment include: tunnel azimuth 290°, average inclination 21°, downhill excavation, and tensile strength of the roof waterproof layer σ b= 0.85MPa, tunnel width L= 5.0m, height 3.0m, the tunnel adopts anchor net cable spraying support method; Step 2: According to the hydrogeological information and tunnel mining technical parameters in step 1, determine the freezing range of the aquifer: the freezing width is L+ 10. Freeze length l , Freeze Height h ; For a certain western mine, this embodiment determines the freezing range of the aquifer as follows: the freezing width is L+ 10=15m, the frozen length is l= 25m, freezing height h= 7m.
[0021] Step 3: Figure 1 , Figure 2 As shown, for a certain western mine, within the freezing range, a row of freezing holes 4 are arranged every 1.5m along the center line of the tunnel, and then a number of freezing holes are arranged every 1.5m on both sides with the row of freezing holes 4 as the center, until a number of freezing holes with a spacing of 1.5m are arranged within the freezing range. After the freezing holes are constructed, preparatory work before freezing is carried out; Step 4: Carry out tunnel excavation, such as Figure 1 , Figure 2 As shown in the figure, the tunnel 2 to be excavated continues along the excavated tunnel 1. When the tunnel is excavated to the distance 3 from the aquifer water body When the freezing process starts, K is the safety factor, K= 4~10, safety factor K The specific value of is determined according to the water conductivity of the tunnel surrounding rock, the freezing rate of the aquifer and the tunnel excavation speed.
[0022] For a certain western mine, this embodiment takes K= 10. It is calculated that when the tunnel is excavated to 54m from the aquifer, the freezing work begins. The freezing work is carried out in the order of high water level first, then low water level, and then the middle and then the two ends; Step 5: Continue tunneling and supporting operations during the freezing process. When the tunnel is excavated to the lowest position of the aquifer, drill water holes in the top plate to the lowest end of the water body, install water pipeline 5, and construct a water storage tank in the tunnel and install drainage facilities to prepare for water discharge.
[0023] The tunnel support type and support parameters of the frozen section are related to the surrounding rock type, the thickness of the roof aquifer, the rock properties and the freezing of the aquifer. In this embodiment, for a western mine, the tunnel support type is selected as anchor grid spraying, in which the anchor rod adopts BHRB-400 / 20×2400mm left-handed non-longitudinal rib threaded steel anchor rod, the spacing between rows is 800×800mm, a single row has 15 anchor rods, and the prestressing force is 70kN; the metal mesh is made of HPB300, 6.5mm steel bars, and the mesh size is 100×100mm; the frame shed adopts a three-section straight-leg 29U steel shed, with a spacing of 800mm and a mountain angle of 3°; the spraying thickness is 120mm, and the concrete strength grade is C25.
[0024] Step 6: Drain water by thawing the aquifer. The thawing sequence is low water level first, high water level second, middle first, then both sides. The thawing speed is adjusted at any time according to the water pressure displayed by the water pressure valve; Step 7: After the water in the aquifer is drained, withdraw the water pipe 5 and the drainage pipe. After the withdrawal work is completed, continue to excavate the tunnel.
[0025] The preferred embodiments of the present invention are described in detail above in conjunction with the accompanying drawings. The embodiments described in the present invention are merely descriptions of the preferred embodiments of the present invention, and do not limit the concept and scope of the present invention. The various specific technical features described in the above specific embodiments can be combined in any suitable manner without contradiction, and such combinations should also be regarded as the contents disclosed in the present disclosure as long as they do not violate the concept of the present invention. In order to avoid unnecessary repetition, the present invention will not further describe various possible combinations.
[0026] The present invention is not limited to the specific details of the above-mentioned embodiments. Within the technical concept of the present invention and without departing from the design concept of the present invention, various modifications and improvements made to the technical solution of the present invention by technical personnel in this field should fall within the protection scope of the present invention. The technical contents for which protection is sought in the present invention have been fully recorded in the claims.
Claims
1. A method for draining water from underground tunnels based on freezing of aquifers, characterized in that: The following steps are involved: Step 1: Obtain the hydrogeological information of the target coal stratum and the technical parameters of the tunnel mining, where the hydrogeological information includes: the length of the aquifer along the tunnel direction; l ,thickness h , distribution range of aquifer, water volume and water pressure of aquifer p , aquifer recharge, runoff and discharge information; tunnel mining technical parameters include: tunnel design azimuth, inclination, tensile strength of roof aquifer σ b , Lane width L , height, tunnel support form and support technical parameters; Step 2: Determine the freezing range of the aquifer based on the hydrogeological information and tunnel mining technical parameters obtained in step 1; Step 3: Within the freezing range, a row of freezing holes is arranged at the same distance along the center line of the laneway, and then a number of freezing holes are arranged at the same distance on both sides with the row of freezing holes as the center, until the freezing range is filled with a number of freezing holes with the same spacing, thereby completing the freezing hole construction, and then carrying out the preparation work before freezing; Step 4: Excavate the tunnel. When the tunnel is excavated to the distance from the aquifer water body, When the freezing process starts, K is the safety factor; Step 5: Continue tunneling and support operations during the freezing process. When the tunnel is excavated to the lowest position of the aquifer, drill water holes in the top plate to the lowest end of the water body, install water pipes, and construct water storage tanks in the tunnel and install drainage facilities to prepare for water drainage. Step 6, draining water by thawing the aquifer; Step 7: After the water in the aquifer is drained, withdraw the water pipes and drainage pipes. After the withdrawal work is completed, continue to excavate the tunnel.
2. The method for draining water from underground tunnels based on freezing of aquifers according to claim 1, characterized in that: The freezing range of the water layer in step 2 is: the freezing width is the width of the lane L+ 10. The freezing length is the length of the aquifer along the tunnel direction. l , the freezing height is the thickness of the aquifer along the tunnel direction h .
3. The method for draining water from underground tunnels based on freezing of aquifers according to claim 1, characterized in that: In step 4, the freezing work is performed in the order of high water level first, then low water level, and then the middle and then the two ends.
4. The method for draining water from underground tunnels based on freezing of aquifers according to claim 1, characterized in that: In step 4, the safety factor K= 4~10, safety factor K The specific value of is determined according to the water conductivity of the tunnel surrounding rock, the freezing rate of the aquifer and the tunnel excavation speed.
5. The method for draining water from underground tunnels based on freezing of aquifers according to claim 1, characterized in that: In step 5, the tunnel support type and support parameters of the frozen section are related to the surrounding rock type, the thickness of the roof aquifer, the lithology and the freezing condition of the aquifer.
6. The method for draining water from underground tunnels based on freezing of aquifers according to claim 1, characterized in that: In step 6, the thawing sequence is carried out in the order of low water level first, then high water level, first the middle and then the two sides, and the thawing speed is adjusted at any time according to the water pressure displayed by the water pressure valve.