Elevator power failure cabinet test system and test method
Through the use of the elevator power outage cabinet test system, all-in-one equipment and tooling equipment are used to conduct independent and batch testing of elevator power outage cabinets, which solves the problems of difficult testing and inability to conduct batch testing in the existing technology, and improves the testing efficiency and accuracy. , reducing costs.
Patent Information
- Application Number
- CN202410768402.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2024-10-01
AI Technical Summary
The existing testing methods for elevator power outage cabinets have problems such as difficulty in positioning, complex operations, difficulty in maintenance, and inability to perform batch testing, resulting in increased labor costs and expenses.
Provide an elevator power outage cabinet testing system, including all-in-one equipment and tooling equipment. Through components such as tooling control boards, input switches, load switches, and load resistors, independent testing and batch testing of elevator power outage cabinets are realized to determine whether they exist. Fault.
It improves the efficiency and accuracy of elevator power outage cabinet testing, simplifies the testing process, and reduces labor costs and expenses.
Smart Images

Figure CN118731534A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of elevator testing, and in particular to an elevator power failure cabinet testing system and a testing method. Background Art
[0002] The elevator power outage cabinet is a device that provides emergency power supply output and rescue when the mains power is abnormal, and is an important component of the elevator safety system. The elevator power outage cabinet needs to be strictly and comprehensively tested during the production process to ensure its quality and reliability. In the related technology, the test plan for the elevator power outage cabinet is mainly to test the entire elevator system after the entire elevator system is assembled. Although this test method is direct and effective, when a fault occurs, it is difficult to locate the problem caused by the elevator power outage cabinet during the elevator whole machine test. At the same time, for the after-sales maintenance of the elevator power outage cabinet in the later stage, this method has problems such as difficult operation, complex structure, and difficult maintenance. In addition, it is impossible to test the elevator power outage cabinet in batches, which seriously increases labor costs and expenses. Summary of the invention
[0003] The purpose of the present invention is to solve one of the technical problems existing in the prior art to at least a certain extent.
[0004] To this end, the object of the present invention is to provide an efficient elevator power outage cabinet testing system and testing method.
[0005] In order to achieve the above technical objectives, the technical solutions adopted by the embodiments of the present invention include:
[0006] On the one hand, an embodiment of the present invention provides an elevator power outage cabinet test system, including: an all-in-one device and a tooling device; the all-in-one device is used to be connected to the elevator power outage cabinet under test through the tooling device; the tooling device includes a tooling control board, an input switch and an output module; the tooling control board is used to be connected to the mains input end of the elevator power outage cabinet through the input switch, and the all-in-one device is used to control the mains input of the elevator power outage cabinet through the tooling control board; the output module includes a load switch and a load resistor, the tooling control board is used to be connected to the output end of the elevator power outage cabinet through the load switch, and the tooling control board is also used to be connected to the output end of the elevator power outage cabinet through the load resistor, and the all-in-one device controls the state of the load switch through the tooling control board to perform full load output, no-load output or half-load output test on the elevator power outage cabinet; the all-in-one device is also used to test the elevator power outage cabinet according to the output signal of the elevator power outage cabinet to determine whether the elevator power outage cabinet has a fault. The embodiment of the present application tests the output of the elevator power outage cabinet through an all-in-one device and tooling equipment to determine whether the elevator power outage cabinet has a fault. The embodiment of the present application can independently test the elevator power outage cabinet, has a simple structure, can realize batch testing, and is conducive to improving the efficiency and accuracy of the elevator power outage cabinet test.
[0007] In addition, the elevator power failure cabinet test system according to the above embodiment of the present invention may also have the following additional technical features:
[0008] Furthermore, in the elevator power outage cabinet testing system of an embodiment of the present invention, the output module also includes a short-circuit switch, one end of the short-circuit switch is connected to the load switch, and the other end of the short-circuit switch is connected to the load resistor; the tooling control board is used to perform an emergency output short-circuit test on the elevator power outage cabinet through the short-circuit switch.
[0009] Furthermore, in one embodiment of the present invention, the tooling control board is used to connect to the elevator power outage cabinet through a first communication line, and the tooling control board is also used to receive a first signal issued by the elevator power outage cabinet through the first communication line; the tooling control board is connected to the all-in-one device through a second communication line, and the all-in-one device receives the first signal through the second communication line, and determines whether the elevator power outage cabinet has a fault based on the first signal.
[0010] Furthermore, in one embodiment of the present invention, the output module includes a first module and a second module, the first module is used to receive the AC power output of the elevator power outage cabinet or receive the first emergency output of the elevator power outage cabinet, and the second module is used to receive the second emergency output of the elevator power outage cabinet; the first emergency output is AC power, and the second emergency output is DC power.
[0011] Furthermore, in one embodiment of the present invention, the tooling control board collects the output signal of the elevator power outage cabinet through a differential amplifier; the tooling control board is also used to determine the effective value of the output signal through the root mean square method if the output signal is an AC component; or, if the output signal is a DC component, determine the effective value of the output signal through an operational amplifier multiple.
[0012] On the other hand, an embodiment of the present invention provides an elevator power outage cabinet test method, which is applied to the above-mentioned elevator power outage cabinet test system, and the method includes:
[0013] receiving a first instruction sent by the all-in-one device;
[0014] According to the first instruction, determine the status of the input switch and the load switch, and receive the output signal of the elevator power failure cabinet;
[0015] The elevator power outage cabinet is tested according to the output signal to determine whether the elevator power outage cabinet has a fault.
[0016] Furthermore, the elevator power outage cabinet testing method of the embodiment of the present invention further includes:
[0017] If the first instruction is an emergency output test, disconnect the input switch;
[0018] If the first request signal sent by the elevator power outage cabinet is not received through the first communication line, it is determined that the elevator power outage cabinet has a fault;
[0019] Alternatively, if the emergency output exceeds a first preset emergency voltage range, it is determined that the elevator power outage cabinet has a fault; the first preset emergency voltage range is related to the rated output voltage of the emergency output.
[0020] Furthermore, in the elevator power failure cabinet testing method of the embodiment of the present invention, the load switch includes a full load switch and a half load switch; the method further includes:
[0021] If the first instruction is an emergency output load shedding test, the half-load switch is closed, and the emergency output is connected to the corresponding half-load ripple resistor;
[0022] If the current emergency output meets the third preset emergency voltage range, the half-load switch is disconnected, the full-load switch is closed, and the emergency output is connected to the corresponding full-load ripple resistor; the third preset emergency voltage range is related to the rated output voltage of the emergency output under half-load conditions;
[0023] If the current emergency output meets the fourth preset emergency voltage range, it is determined that the elevator power outage cabinet passes the emergency output load shedding test; the fourth preset emergency voltage range is related to the rated output voltage of the emergency output under full load.
[0024] Furthermore, the elevator power outage cabinet testing method of the embodiment of the present invention further includes:
[0025] If the first instruction is a no-response test of the elevator master control, disconnect the input switch;
[0026] If the emergency output within the first preset time period meets the first preset emergency voltage range, the emergency output signal of the elevator power outage cabinet is not responded to, and a response timeout signal sent by the elevator power outage cabinet is received through the first communication line, the first voltage of the current emergency output is obtained;
[0027] If the first voltage is zero, it is determined that the elevator power failure cabinet passes the elevator master control no response test.
[0028] Furthermore, the elevator power outage cabinet testing method of the embodiment of the present invention further includes:
[0029] If the first instruction is a timeout test, disconnect the input switch, respond to the emergency output signal of the elevator power failure cabinet, and close the load switch;
[0030] If the emergency output within the second preset time period meets the first preset emergency voltage range, no rescue completion instruction is issued, and an operation timeout signal issued by the elevator power failure cabinet is received through the first communication line, the second voltage of the current emergency output is obtained;
[0031] If the second voltage is zero, it is determined that the elevator power outage cabinet passes the operation timeout test.
[0032] On the other hand, an embodiment of the present invention provides an elevator power failure cabinet testing device, comprising:
[0033] at least one processor;
[0034] at least one memory for storing at least one program;
[0035] When the at least one program is executed by the at least one processor, the at least one processor implements the above-mentioned elevator power outage cabinet testing method.
[0036] On the other hand, an embodiment of the present invention provides a storage medium, in which a program executable by a processor is stored. When the program executable by the processor is executed by the processor, it is used to implement the above-mentioned elevator power outage cabinet testing method.
[0037] The test system provided by the embodiment of the present invention includes: an all-in-one device and a tooling device; the all-in-one device is used to connect to the elevator power-off cabinet under test through the tooling device; the tooling device includes a tooling control board, an input switch and an output module; the tooling control board is used to connect to the mains input end of the elevator power-off cabinet through the input switch, and the all-in-one device is used to control the mains input of the elevator power-off cabinet through the tooling control board; the output module includes a load switch and a load resistor, the tooling control board is used to connect to the output end of the elevator power-off cabinet through the load switch, and the tooling control board is also used to connect to the output end of the elevator power-off cabinet through the load resistor, and the all-in-one device controls the state of the load switch through the tooling control board to perform full-load output, no-load output or half-load output test on the elevator power-off cabinet; the all-in-one device is also used to test the elevator power-off cabinet according to the output signal of the elevator power-off cabinet to determine whether the elevator power-off cabinet has a fault. The embodiment of the present application tests the output of the elevator power-off cabinet through the all-in-one device and the tooling device to determine whether the elevator power-off cabinet has a fault. The embodiment of the present application can independently test the elevator power outage cabinet, has a simple structure, and can implement batch testing, which is beneficial to improving the efficiency and accuracy of the elevator power outage cabinet test. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the embodiments of the present invention or the drawings of related technical solutions in the prior art are introduced below. It should be understood that the drawings introduced below are only for the convenience of clearly describing some embodiments of the technical solutions of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.
[0039] Figure 1 A structural schematic diagram of an embodiment of an elevator power outage cabinet test system provided by the present invention;
[0040] Figure 2 A circuit schematic diagram of an embodiment of output voltage measurement provided by the present invention;
[0041] Figure 3 A circuit diagram of an embodiment of the switch control provided by the present invention;
[0042] Figure 4 A schematic diagram of a flow chart of an embodiment of a method for testing an elevator power outage cabinet provided by the present invention;
[0043] Figure 5 A schematic flow chart of another embodiment of the elevator power outage cabinet testing method provided by the present invention;
[0044] Figure 6A structural schematic diagram of an embodiment of an elevator power outage cabinet testing device provided by the present invention. DETAILED DESCRIPTION
[0045] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and are not to be construed as limitations of the present invention. For the step numbers in the following embodiments, they are only provided for the convenience of explanation, and the order between the steps is not limited in any way, and the execution order of each step in the embodiment can be adaptively adjusted according to the understanding of those skilled in the art.
[0046] The elevator power outage cabinet is a device for emergency power supply output and rescue of elevators when the mains power is abnormal. It is an important component of the elevator safety system. The elevator power outage cabinet needs to be strictly and comprehensively tested during the production process to ensure its quality and reliability. At present, the mainstream testing method for elevator power outage cabinets is mainly to test the entire elevator system after the entire elevator system is assembled. Although this testing method is direct and effective, when the elevator power outage cabinet fails, it is difficult to locate the problem caused by the elevator power outage cabinet failure in the elevator whole machine test. Secondly, for the after-sales maintenance of the elevator power outage cabinet in the later stage, this method has problems such as difficult operation, complex structure, and difficult maintenance. In addition, it is impossible to test the elevator power outage cabinet in batches, which seriously increases labor costs and expenses.
[0047] The elevator power outage cabinet test system and implementation method proposed in the embodiments of the present invention are described in detail below with reference to the accompanying drawings. First, an elevator power outage cabinet test system proposed in the embodiments of the present invention is described with reference to the accompanying drawings.
[0048] Figure 1 This is a structural diagram of an elevator power outage cabinet test system according to an embodiment of the present invention. The system specifically includes:
[0049] All-in-one equipment and tooling equipment;
[0050] The all-in-one device is used to connect to the power-off cabinet of the elevator under test through the tooling equipment;
[0051] The tooling equipment includes a tooling control board, an input switch and an output module; the tooling control board is used to connect to the AC input terminal of the elevator power outage cabinet through the input switch, and the all-in-one device is used to control the AC input of the elevator power outage cabinet through the tooling control board; the output module includes a load switch and a load resistor, the tooling control board is used to connect to the output terminal of the elevator power outage cabinet through the load switch, and the tooling control board is also used to connect to the output terminal of the elevator power outage cabinet through the load resistor, and the all-in-one device controls the state of the load switch through the tooling control board to perform full load output, no-load output or half-load output tests on the elevator power outage cabinet; the all-in-one device is also used to test the elevator power outage cabinet according to the output signal of the elevator power outage cabinet to determine whether there is a fault in the elevator power outage cabinet.
[0052] Reference Figure 1 In one embodiment shown, the test system consists of three parts: the tested elevator power outage cabinet product, tooling equipment, and an all-in-one device. The all-in-one device consists of a scanner, a USB to RS485 converter, and an all-in-one device. The scanner is connected to the USB port of the all-in-one device. During the test, the scanner scans the unique identification code on the elevator power outage cabinet and uploads the identification code information to the all-in-one device for tracking and recording the test status of the elevator power outage cabinet.
[0053] The tooling equipment in the embodiment of the present application is the execution unit in the entire functional test system, executing the commands issued by the integrated machine to perform the test process. The input switch in the embodiment of the present application is used to connect or close the mains input of the elevator power outage cabinet. For example, the input switch can be a contactor, a relay, or other devices with switching functions. This application does not make specific restrictions. The tooling equipment in the embodiment of the present application is mainly composed of a tooling control board (i.e. Figure 1 The tooling board in the embodiment shown), input contactor, load contactor, short-circuit contactor, and load resistor are composed, wherein the input contactor controls the mains input of the elevator power outage cabinet; the load contactor controls the output of the elevator power outage cabinet under no-load, half-load, and full-load conditions, and can simulate the power supply of the elevator power outage cabinet when the traction machine, brake and other high-power components are in action during the operation of the elevator; the short-circuit contactor can control the emergency output short circuit of the elevator power outage cabinet to simulate the short-circuit fault of the elevator power outage cabinet; the load resistor is composed of a corrugated resistor, and the corrugated resistor corresponding to the half-load and full-load working conditions is configured according to the specifications of the elevator power outage cabinet for the elevator to stop Electric cabinet load test; the tooling board is the core component of the tooling equipment. It integrates a main RS485 circuit inside to connect with the all-in-one machine, which is used to receive commands issued by the all-in-one machine and upload test data in real time; in order to adapt to different elevator power outage cabinet models, the tooling board also integrates a variety of RS485 / CAN / IO circuits and elevator power outage cabinet communications to obtain the emergency output status of the elevator power outage cabinet and control the emergency output of the elevator power outage cabinet; there are multiple contactor control circuits inside the tooling board to control the closing and opening of the contactor; there are multiple ADC measurement circuits inside the tooling board, which can test the output voltage of the elevator power outage cabinet.
[0054] Reference Figure 1 In one embodiment shown, the mains input of the elevator power outage cabinet is connected to the input contactor of the tooling equipment, and the tooling equipment controls the input power supply of the elevator power outage cabinet; the emergency output interface of the elevator power outage cabinet is connected to the load contactor and load resistor of the tooling equipment, and the tooling equipment controls the load status of the elevator power outage cabinet; the communication protocol of the elevator power outage cabinet generally uses three methods: RS485 / CAN / IO, and the communication line of the elevator power outage cabinet can be connected to the interface corresponding to the tooling board of the tooling equipment.
[0055] It can be understood that the embodiments of the present application implement various tests of the elevator power outage cabinet through the tooling control board, input switch and output module, and the elevator power outage cabinet can be tested separately to improve the test accuracy.
[0056] Optionally, in the elevator power outage cabinet test system in the embodiment of the present invention, the output module also includes a short-circuit switch, one end of the short-circuit switch is connected to the load switch, and the other end of the short-circuit switch is connected to the load resistor; the tooling control board is used to perform an emergency output short-circuit test on the elevator power outage cabinet through the short-circuit switch.
[0057] In some possible implementations, such as Figure 1 The test system shown in the figure is composed of the mains input of the elevator power outage cabinet connected to the input contactor of the tooling equipment, the emergency output of the elevator power outage cabinet connected to the load contactor and the load resistor, one end of the short-circuit contactor is connected to the load resistor, and the other end is connected to the load contactor. One end of the USB to 485 converter is connected to the main RS485 interface on the tooling equipment tooling board, and the other end is connected to the USB port of the all-in-one machine. The scanner is also connected to the all-in-one machine through the USB port. The short-circuit switch in the embodiment of the present application can control the short circuit of the emergency output of the elevator power outage cabinet to simulate the short-circuit fault of the elevator power outage cabinet.
[0058] Optionally, in the elevator power outage cabinet test system in the embodiment of the present invention, the tooling control board is used to connect to the elevator power outage cabinet through a first communication line, and the tooling control board is used to receive a first signal issued by the elevator power outage cabinet through the first communication line; the tooling control board is connected to the all-in-one device through a second communication line, and the all-in-one device receives the first signal through the second communication line, and determines whether there is a fault in the elevator power outage cabinet based on the first signal.
[0059] In some possible implementations, reference Figure 1 As shown, the second communication line in the embodiment of the present application can be an RS485 communication line, referring to Figure 1In the integrated device, the USB to RS485 converter is connected to the main RS485 bus of the tooling equipment and the USB of the integrated device at both ends. The USB to RS485 converter converts the RS485 protocol on the tooling equipment and the USB protocol between the integrated device. The integrated device is the central control unit of the entire functional test system, responsible for starting and stopping the test, recording the test data and results in real time, and uploading the test data to the cloud through the network to realize the processing and storage of the test data. The first communication line in the embodiment of the present application can be Figure 1 The RS485 / CAN / IO communication line in the embodiment shown realizes data transmission between the tooling equipment and the elevator power outage cabinet. The embodiment of the present application realizes data transmission through the first communication line and the second communication line, and the embodiment of the present application does not limit the specific types of the first communication line and the second communication line.
[0060] Optionally, in the elevator power outage cabinet test system in the embodiment of the present invention, the output module includes a first module and a second module, the first module is used to receive the AC power output of the elevator power outage cabinet or receive the first emergency output of the elevator power outage cabinet, and the second module is used to receive the second emergency output of the elevator power outage cabinet; the first emergency output is alternating current, and the second emergency output is direct current.
[0061] In some possible implementations, a group of output modules in the tooling equipment (exemplarily, it can be a load resistor, a load contactor, a short-circuit contactor) corresponds to an emergency output of an elevator power outage cabinet, and when the elevator power outage cabinet has multiple emergency outputs, it can be expanded according to actual conditions. The first module and the second module in the embodiment of the present application are illustrative examples and do not limit the number of output modules in the embodiment of the present application. A set of tooling equipment corresponds to a set of tested elevator power outage cabinets, and multiple sets of tooling equipment can be expanded according to actual conditions. Batch testing can be carried out uniformly between multiple sets of elevator power outage cabinets, or the elevator power outage cabinets to be tested can be freely configured. The tooling equipment sets the address code of the tooling equipment through the dial switch on the tooling board. The address codes between the tooling equipment are different. The all-in-one machine uses the address code to distinguish the information set by different tooling on the RS485 bus.
[0062] Figure 1The elevator power outage cabinet in the illustrated embodiment has two emergency output power supplies, of which the mains output and the emergency power supply output 1 (i.e., the first emergency output in the embodiment of the present application) are the same output. When the mains is normal, the elevator power outage cabinet outputs AC220V mains. When the mains is abnormal, the battery in the elevator power outage cabinet boosts and inverts the emergency power supply to output AC220V; the elevator power outage cabinet emergency output 2 (i.e., the second emergency output in the embodiment of the present application) has no output when the mains is normal, and when the mains is abnormal, the battery in the elevator power outage cabinet boosts and outputs DC330V; the rated power of emergency output 1 and emergency output 2 are both 500W. According to the rated power, the half-load and full-load load resistances of emergency output 1 are selected as 200Ω and 100Ω ripple resistors respectively; the half-load and full-load load resistances of emergency output 2 are selected as 430Ω and 220Ω ripple resistors respectively. The communication mode of the elevator power outage cabinet is RS485, and its communication line is connected to the corresponding RS485 interface of the tooling equipment tooling board. The rated voltage of the emergency output 1 of the elevator power failure cabinet is AC220V, and the rated voltage of the emergency output 2 is DC330V. Of course, those skilled in the art can set the specific voltage and corresponding resistance of the emergency output according to actual needs.
[0063] Optionally, in the elevator power outage cabinet test system in the embodiment of the present invention, the tooling control board collects the output signal of the elevator power outage cabinet through a differential amplifier; the tooling control board is also used to determine the effective value of the output signal by the root mean square method if the output signal is an AC component; or, if the output signal is a DC component, determine the effective value of the output signal by the operational amplifier multiple.
[0064] In some possible implementations, such as Figure 2 As shown in the voltage measurement circuit diagram provided by the embodiment of the present invention, the emergency output voltage of the elevator power outage cabinet is connected from the interface J1 to the differential amplifier composed of resistors R41, R42, R43, R44, R45, R46, and amplifier U7 to obtain the sampled voltage to the controller MCU for processing. This voltage measurement circuit supports AC and DC voltage input. When there is no voltage output, the sampled voltage is the differential amplifier bias voltage of 1.55V. When the DC voltage is input, the DC component of the superimposed bias voltage is obtained, and when the AC output is obtained, the sinusoidal AC component of the bias voltage is obtained at zero. The MCU on the tooling board determines whether it is a DC or AC voltage component based on the voltage waveform. The AC component uses the mean square root method to calculate the effective value of the AC voltage, and the DC component is directly calculated using the voltage divider and the op amp multiple.
[0065] In other embodiments, referring to Figure 3The control circuit of the switch shown in the figure, the contactor control circuit KM1 interface is connected to the positive and negative ends of the contactor power input, the tooling board MCU controls the high level output to the resistor R48, after the voltage is divided by the resistor R48 and the resistor R49, it reaches the transistor Q9 to reach the conduction voltage drop, and the transistor Q9 is turned on to supply power to both ends of the contactor; the MCU on the tooling board controls the low level output to the resistor R48, the transistor Q9 is lower than its conduction voltage drop, and the transistor Q9 is cut off to disconnect the power supply to both ends of the contactor.
[0066] The test system of the elevator power outage cabinet provided in the embodiment of the present application includes: an all-in-one device and a tooling device; the all-in-one device is used to connect to the elevator power outage cabinet under test through the tooling device; the tooling device includes a tooling control board, an input switch and an output module; the tooling control board is used to connect to the mains input end of the elevator power outage cabinet through the input switch, and the all-in-one device is used to control the mains input of the elevator power outage cabinet through the tooling control board; the output module includes a load switch and a load resistor, the tooling control board is used to connect to the output end of the elevator power outage cabinet through the load switch, and the tooling control board is also used to connect to the output end of the elevator power outage cabinet through the load resistor, and the all-in-one device controls the state of the load switch through the tooling control board to test the elevator power outage cabinet with full load output, no-load output or half-load output; the all-in-one device is also used to test the elevator power outage cabinet according to the output signal of the elevator power outage cabinet to determine whether the elevator power outage cabinet has a fault. The embodiment of the present application tests the output of the elevator power outage cabinet through the all-in-one device and the tooling equipment to determine whether the elevator power outage cabinet has a fault. The embodiment of the present application can independently test the elevator power outage cabinet, has a simple structure, and can implement batch testing, which is beneficial to improving the efficiency and accuracy of the elevator power outage cabinet test.
[0067] Next, a method for testing an elevator power outage cabinet according to an embodiment of the present invention will be described with reference to the accompanying drawings.
[0068] Reference Figure 4 In an embodiment of the present invention, a method for testing an elevator power outage cabinet is provided. The method for testing an elevator power outage cabinet in the embodiment of the present invention can be applied to a terminal, a server, or software running in a terminal or a server. The terminal can be a tablet computer, a laptop computer, a desktop computer, etc., but is not limited thereto. The server can be an independent physical server, or a server cluster or distributed system composed of multiple physical servers, or a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, CDN, and big data and artificial intelligence platforms. The method for testing an elevator power outage cabinet in an embodiment of the present invention is applied to the above elevator power outage cabinet test system, and mainly includes the following steps:
[0069] S100: receiving a first instruction sent by the all-in-one device;
[0070] S200: According to the first instruction, determine the status of the input switch and the load switch, and receive the output signal of the elevator power failure cabinet;
[0071] S300: Test the elevator power outage cabinet according to the output signal to determine whether there is a fault in the elevator power outage cabinet.
[0072] In some possible implementations, the above steps S100-S300 are used for the tooling control board. In the embodiment of the present application, the tooling control board receives the first instruction issued by the all-in-one device, drives the input switch and the load switch to act according to the first instruction, adjusts the state of the switch, and determines the test result according to the output signal of the elevator power outage cabinet.
[0073] Optionally, the elevator power outage cabinet testing method in the embodiment of the present invention further includes:
[0074] If the first command is an emergency output test, disconnect the input switch;
[0075] If the first request signal sent by the elevator power outage cabinet is not received through the first communication line, it is determined that the elevator power outage cabinet has a fault;
[0076] Alternatively, if the emergency output exceeds a first preset emergency voltage range, it is determined that the elevator power outage cabinet has a fault; the first preset emergency voltage range is related to the rated output voltage of the emergency output.
[0077] In some possible implementations, the first preset emergency voltage range can be adjusted according to actual equipment or devices. When the input switch is disconnected, the elevator power failure cabinet should perform emergency output, and the output voltage should be within the preset range.
[0078] Optionally, in the elevator power outage cabinet testing method in the embodiment of the present invention, the load switch includes a full-load switch and a half-load switch; the method further includes:
[0079] If the first instruction is an emergency output load shedding test, the half-load switch is closed, and the emergency output is connected to the corresponding half-load ripple resistor;
[0080] If the current emergency output meets the third preset emergency voltage range, the half-load switch is disconnected, the full-load switch is closed, and the emergency output is connected to the corresponding full-load ripple resistor; the third preset emergency voltage range is related to the rated output voltage of the emergency output under half-load conditions;
[0081] If the current emergency output meets the fourth preset emergency voltage range, it is determined that the elevator power outage cabinet has passed the emergency output load shedding test; the fourth preset emergency voltage range is related to the rated output voltage of the emergency output under full load.
[0082] In some possible implementations, the embodiments of the present application adjust the load resistance of the emergency output through a load switch, and perform an emergency output load shedding test on the elevator power outage cabinet by driving and controlling the responsible switch.
[0083] Optionally, the elevator power outage cabinet testing method in the embodiment of the present invention further includes:
[0084] If the first instruction is a no-response test of the elevator master control, disconnect the input switch;
[0085] If the emergency output within the first preset time period meets the first preset emergency voltage range, the emergency output signal of the elevator power outage cabinet is not responded to, and the response timeout signal sent by the elevator power outage cabinet is received through the first communication line, the first voltage of the current emergency output is obtained;
[0086] If the first voltage is zero, it is determined that the elevator power outage cabinet has passed the elevator master control no response test.
[0087] In some possible implementations, when the elevator power outage cabinet enters the emergency output state, an emergency output signal is sent to the tooling control board. If the tooling control board cannot respond to the emergency output signal in time, the elevator power outage cabinet output voltage is zero and the elevator rescue process fails.
[0088] Optionally, the elevator power outage cabinet testing method in the embodiment of the present invention further includes:
[0089] If the first instruction is to run the timeout test, disconnect the input switch, respond to the emergency output signal of the elevator power failure cabinet, and close the load switch;
[0090] If the emergency output within the second preset time period meets the first preset emergency voltage range, no rescue completion command is issued, and an operation timeout signal from the elevator power failure cabinet is received through the first communication line, the second voltage of the current emergency output is obtained;
[0091] If the second voltage is zero, it is determined that the elevator power outage cabinet has passed the operation timeout test.
[0092] In some possible implementations, the second preset duration is the longest emergency power supply duration of the elevator power outage cabinet. When the elevator fails to complete the rescue within the longest emergency power supply time of the elevator power outage cabinet, the elevator power outage cabinet is required to upload an operation timeout fault and adjust the output voltage to zero.
[0093] Optionally, the elevator power outage cabinet testing method in the embodiment of the present invention further includes:
[0094] If the first instruction is a short-circuit test, the load switch is opened and the short-circuit switch is closed;
[0095] If an emergency output short-circuit signal is received from the elevator power outage cabinet through the first communication line, and the voltage of the emergency output is zero, it is determined that the elevator power outage cabinet has passed the short-circuit test.
[0096] In some possible implementations, when the emergency output is short-circuited, the elevator power outage cabinet is required to send an emergency output short-circuit signal and adjust the output voltage to zero.
[0097] The following is a detailed description of the test method of the elevator power outage cabinet proposed in this application with a specific embodiment:
[0098] like Figure 5 As shown in the test flow chart of the elevator power outage cabinet test system and method of the present invention, the elevator power outage cabinet function test system mainly consists of mains output test, RS485 test, emergency output test, emergency output load shedding test, emergency output 1 short circuit test, emergency output 2 short circuit test, elevator master control no response test, elevator rescue completion test, and operation timeout test. Specifically, each test process is as follows:
[0099] In the AC power output test, the tooling equipment and tooling board control the input contactor to close, and the AC220V AC power supplies the elevator power outage cabinet. At this time, the AC output interface of the elevator power outage cabinet outputs AC220V AC power. The tooling equipment and tooling board detects the AC output voltage. If the output voltage range is within AC220±10%, the test is considered to have passed and enter the next test item. Otherwise, an error is directly reported and the elevator power outage cabinet test is exited.
[0100] RS485 test, the tooling equipment tooling board sends a command from the RS485 bus to query the status of the elevator power outage cabinet. If the elevator power outage cabinet can respond correctly, the test passes and enters the next test item. Otherwise, it will directly report an error and exit the elevator power outage cabinet test.
[0101] In the emergency output test, the tooling equipment tooling board controls the input contactor to disconnect and stop supplying power to the elevator power outage cabinet. After the elevator power outage cabinet detects that the mains is disconnected, it will start the emergency power supply output. The tooling equipment tooling board detects whether the elevator power outage cabinet uploads a request signal on the RS485 bus and monitors the two emergency output voltages. If the request signal uploaded by the elevator power outage cabinet is received and the two emergency output voltages are within 3% of their rated output voltages, the test passes and enters the next test item. Otherwise, an error is directly reported and the elevator power outage cabinet test is exited.
[0102] Emergency output load shedding test, the tooling equipment tooling board controls the two emergency output half-load contactors to close, and the two emergency outputs are connected to the corresponding half-carrier ripple resistors. During this process, the two emergency output voltages are detected. If the two emergency output voltages are within 3% of their rated output voltages, the next test step will be entered, otherwise an error will be directly reported to exit the elevator power outage cabinet test. The tooling equipment tooling board controls the two emergency output half-load contactors to disconnect, and the two emergency output full-load contactors to close, and the two emergency outputs are connected to the corresponding full-carrier ripple resistors. During this process, the two emergency output voltages are detected. If the two emergency output voltages are within 3% of their rated output voltages, the test will pass and enter the next test item, otherwise an error will be directly reported to exit the elevator power outage cabinet test. This test simulates the power supply of the elevator power outage cabinet when the emergency output of the elevator power outage cabinet is powered on and the high-power components such as the traction machine and brake are in action during the operation of the elevator.
[0103] Emergency output 1 short circuit test, the tooling equipment tooling board controls the emergency output 1 short circuit contactor to close, and the two emergency output full load contactors are disconnected. At this time, the elevator power outage cabinet emergency output 1 has a short circuit fault. The tooling equipment tooling board detects the emergency output 1 short circuit fault uploaded by the elevator power outage cabinet from the RS485 bus, and the two emergency output voltages of the elevator power outage cabinet are 0, then the test passes and enters the next test item, otherwise it directly reports an error and exits the elevator power outage cabinet test.
[0104] Emergency output 2 short circuit test, the tooling equipment tooling board controls the emergency output 1 short circuit contactor to disconnect, the input contactor is closed to supply power to the elevator power outage cabinet, and then the tooling equipment tooling board controls the input contactor to disconnect, the elevator power outage cabinet starts the emergency power supply output, first detects the two emergency output voltages of the elevator power outage cabinet, if the two emergency output voltages are within 3% of their rated output voltages, enter the next test step, otherwise directly report an error and exit the elevator power outage cabinet test. The tooling equipment tooling board controls the emergency output 2 short circuit contactor to close, at this time the elevator power outage cabinet emergency output 2 has a short circuit fault. The tooling equipment tooling board detects the short circuit fault of the emergency output 2 uploaded by the elevator power outage cabinet from the RS485 bus, and the two emergency output voltages of the elevator power outage cabinet are 0, then the test passes and enters the next test item, otherwise it directly reports an error and exits the elevator power outage cabinet test.
[0105] Elevator master control no response test, the tooling equipment tooling board controls the emergency output 2 short-circuit contactor to disconnect, the input contactor is closed to supply power to the elevator power outage cabinet, and then the tooling equipment tooling board controls the input contactor to disconnect, the elevator power outage cabinet starts the emergency power supply output, and detects the two emergency output voltages of the elevator power outage cabinet within 15 seconds. If the two emergency output voltages are within 3% of their rated output voltage, enter the next test step, otherwise directly report an error and exit the elevator power outage cabinet test. After 15 seconds, because the elevator power outage cabinet did not receive the response command issued by the tooling equipment tooling board, the elevator power outage cabinet generates a master control response timeout fault. The tooling equipment tooling board detects the master control response timeout fault uploaded by the elevator power outage cabinet from the RS485 bus, and the two emergency output voltages of the elevator power outage cabinet are 0, then the test passes and enters the next test item, otherwise it directly reports an error and exits the elevator power outage cabinet test. This test simulates the process in which the elevator master control fails to respond to the elevator power outage cabinet emergency rescue request command in time and replies to the elevator power outage cabinet response command, resulting in the failure of the elevator rescue.
[0106] After the elevator rescue test is completed, the tooling equipment tooling board controls the input contactor to close and supply power to the elevator power outage cabinet, and then the tooling equipment tooling board controls the input contactor to disconnect, and the elevator power outage cabinet will start the emergency power supply output. The tooling equipment tooling board sends a response command through the RS485 bus. After receiving the response command, the elevator power outage cabinet will no longer detect the elevator master control no response fault. Detect the two emergency output voltages of the elevator power outage cabinet for 30 consecutive seconds. If the two emergency output voltages are within 3% of their rated output voltages, enter the next test step, otherwise directly report an error and exit the elevator power outage cabinet test. After 30 seconds, the tooling equipment tooling board sends a rescue completion command to the elevator power outage cabinet from the RS485 bus. The tooling equipment tooling board detects that the two emergency output voltages of the elevator power outage cabinet are 0 and judges that the elevator power outage cabinet emergency power supply output is stopped. If the test passes, enter the next test item, otherwise directly report an error and exit the elevator power outage cabinet test. This test simulates the complete rescue process in which the elevator starts the rescue operation after receiving the request signal uploaded by the elevator power outage cabinet, and sends the rescue completion command to the elevator power outage cabinet after completing the rescue operation, so that the emergency power supply output of the elevator power outage cabinet stops.
[0107] During the timeout test, the tooling equipment tooling board controls the input contactor to close and supply power to the elevator power outage cabinet, and then the tooling equipment tooling board controls the input contactor to disconnect. The elevator power outage cabinet will start the emergency power supply output, and the tooling equipment tooling board sends a response command from the RS485 bus. After receiving the response command, the elevator power outage cabinet will no longer detect the elevator master control no response fault. The tooling equipment tooling board controls the two emergency output full-load contactors to close, and the two emergency outputs are connected to the corresponding full-load carrier ripple resistors. Detect the two emergency output voltages of the elevator power outage cabinet within 6 consecutive minutes. If the two emergency output voltages are within 3% of their rated output voltage, enter the next test step, otherwise directly report an error and exit the elevator power outage cabinet test. After 6 minutes, the elevator power outage cabinet has a running timeout fault because it did not receive the rescue completion command sent by the tooling equipment tooling board from the RS485 bus. The tooling equipment tooling board detects the running timeout fault uploaded by the elevator power outage cabinet from the RS485 bus, and the two emergency output voltages of the elevator power outage cabinet are 0. The elevator power outage cabinet passes the functional test, otherwise it will directly report an error and exit the elevator power outage cabinet test. This test simulates the failure of the elevator to complete the rescue operation within the longest emergency power supply time of the elevator power outage cabinet.
[0108] It can be seen that the contents of the above system embodiments are all applicable to the present method embodiments, the functions specifically implemented by the present method embodiments are the same as those of the above system embodiments, and the beneficial effects achieved are also the same as those achieved by the above system embodiments.
[0109] Reference Figure 6 The embodiment of the present invention provides an elevator power failure cabinet testing device, comprising:
[0110] at least one processor 610;
[0111] At least one memory 620, used to store at least one program;
[0112] When the at least one program is executed by the at least one processor 610, the at least one processor 610 implements the elevator power outage cabinet testing method.
[0113] Similarly, the contents of the above method embodiments are all applicable to the present device embodiments. The functions specifically implemented by the present device embodiments are the same as those of the above method embodiments, and the beneficial effects achieved are also the same as those achieved by the above method embodiments.
[0114] An embodiment of the present invention further provides a computer-readable storage medium, in which a program executable by a processor is stored. When the program executable by the processor is executed by the processor, it is used to execute the above-mentioned elevator power outage cabinet testing method.
[0115] Similarly, the contents of the above method embodiments are all applicable to the present storage medium embodiments. The functions specifically implemented by the present storage medium embodiments are the same as those of the above method embodiments, and the beneficial effects achieved are also the same as those achieved by the above method embodiments.
[0116] In some selectable embodiments, the function / operation mentioned in the block diagram may not occur in the order mentioned in the operation diagram. For example, depending on the function / operation involved, the two boxes shown in succession can actually be executed substantially simultaneously or the boxes can sometimes be executed in reverse order. In addition, the embodiment presented and described in the flow chart of the present invention is provided by way of example, for the purpose of providing a more comprehensive understanding of technology. The disclosed method is not limited to the operation and logic flow presented herein. Selectable embodiments are expected, wherein the order of various operations is changed and the sub-operation of a part for which is described as a larger operation is performed independently.
[0117] In addition, although the present invention is described in the context of functional modules, it should be understood that, unless otherwise specified, one or more of the functions and / or features can be integrated into a single physical device and / or software module, or one or more functions and / or features can be implemented in a separate physical device or software module. It is also understood that a detailed discussion of the actual implementation of each module is unnecessary for understanding the present invention. More specifically, in view of the properties, functions and internal relationships of the various functional modules in the device disclosed herein, the actual implementation of the module will be understood within the conventional skills of the engineer. Therefore, those skilled in the art can implement the present invention set forth in the claims without excessive experimentation using ordinary techniques. It is also understood that the specific concepts disclosed are merely illustrative and are not intended to limit the scope of the present invention, which is determined by the full scope of the appended claims and their equivalents.
[0118] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present invention, or the part that contributes to the prior art or the part of the technical solution, can be embodied in the form of a software product. The computer software product is stored in a storage medium, including several programs to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in each embodiment of the present invention. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk, etc., which can store program codes.
[0119] The logic and / or steps represented in the flowchart or otherwise described herein, for example, may be considered as an ordered list of executable programs for implementing the logical functions, and may be embodied in any computer-readable medium for use by a program execution system, device or apparatus (such as a computer-based system, a system including a processor, or other system that can fetch and execute a program from a program execution system, device or apparatus), or in conjunction with such program execution systems, devices or apparatuses. For purposes of this specification, a "computer-readable medium" may be any device that can contain, store, communicate, propagate or transmit a program for use by a program execution system, device or apparatus, or in conjunction with such program execution systems, devices or apparatuses.
[0120] More specific examples of computer-readable media (a non-exhaustive list) include the following: an electrical connection with one or more wires (electronic device), a portable computer disk case (magnetic device), a random access memory (RAM), a read-only memory (ROM), an erasable and programmable read-only memory (EPROM or flash memory), an optical fiber device, and a portable compact disk read-only memory (CDROM). In addition, the computer-readable medium may even be a paper or other suitable medium on which the program is printed, since the program may be obtained electronically, for example, by optically scanning the paper or other medium, followed by editing, deciphering or, if necessary, processing in another suitable manner, and then stored in a computer memory.
[0121] It should be understood that the various parts of the present invention can be implemented by hardware, software, firmware or a combination thereof. In the above-mentioned embodiments, a plurality of steps or methods can be implemented by software or firmware stored in a memory and executed by a suitable program execution system. For example, if implemented by hardware, as in another embodiment, it can be implemented by any one of the following technologies known in the art or their combination: a discrete logic circuit having a logic gate circuit for implementing a logic function for a data signal, a dedicated integrated circuit having a suitable combination of logic gate circuits, a programmable gate array (PGA), a field programmable gate array (FPGA), etc.
[0122] In the above description of this specification, the description with reference to the terms "one embodiment / example", "another embodiment / example" or "certain embodiments / examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner.
[0123] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the claims and their equivalents.
[0124] The above is a specific description of the preferred implementation of the present invention, but the present invention is not limited to the embodiments. Those skilled in the art may make various equivalent modifications or substitutions without violating the spirit of the present invention. These equivalent modifications or substitutions are all included in the scope defined by the claims of the present invention.
Claims
1. An elevator power outage cabinet test system, characterized in that: The test system includes: an all-in-one device and a tooling device; The integrated device is used to be connected to the elevator power outage cabinet under test through the tooling equipment; The tooling equipment includes a tooling control board, an input switch and an output module; the tooling control board is used to be connected to the AC input terminal of the elevator power outage cabinet through the input switch, and the all-in-one device is used to control the AC input of the elevator power outage cabinet through the tooling control board; the output module includes a load switch and a load resistor, the tooling control board is used to be connected to the output terminal of the elevator power outage cabinet through the load switch, and the tooling control board is also used to be connected to the output terminal of the elevator power outage cabinet through the load resistor, and the all-in-one device controls the state of the load switch through the tooling control board to perform full load output, no-load output or half-load output test on the elevator power outage cabinet; the all-in-one device is also used to test the elevator power outage cabinet according to the output signal of the elevator power outage cabinet to determine whether the elevator power outage cabinet has a fault.
2. The elevator power failure cabinet test system according to claim 1 is characterized in that: The output module also includes a short-circuit switch, one end of which is connected to the load switch, and the other end of which is connected to the load resistor; the tooling control board is used to perform an emergency output short-circuit test on the elevator power outage cabinet through the short-circuit switch.
3. The elevator power failure cabinet test system according to claim 1 is characterized in that: The tooling control board is used to connect to the elevator power outage cabinet through a first communication line, and the tooling control board is used to receive a first signal issued by the elevator power outage cabinet through the first communication line; the tooling control board is connected to the all-in-one device through a second communication line, and the all-in-one device receives the first signal through the second communication line, and determines whether the elevator power outage cabinet has a fault based on the first signal.
4. The elevator power failure cabinet test system according to claim 1, characterized in that: The output module includes a first module and a second module, the first module is used to receive the AC power output of the elevator power outage cabinet or the first emergency output of the elevator power outage cabinet, and the second module is used to receive the second emergency output of the elevator power outage cabinet; the first emergency output is alternating current, and the second emergency output is direct current.
5. The elevator power failure cabinet test system according to claim 1 is characterized in that: The tooling control board is used to collect the output signal of the elevator power outage cabinet through a differential amplifier; the tooling control board is also used to determine the effective value of the output signal through the root mean square method if the output signal is an AC component; or, if the output signal is a DC component, determine the effective value of the output signal through an operational amplifier multiple.
6. A method for testing an elevator power outage cabinet, characterized in that: Applied to the elevator power outage cabinet test system according to claim 1, the method comprises: receiving a first instruction sent by the all-in-one device; According to the first instruction, determine the status of the input switch and the load switch, and receive the output signal of the elevator power failure cabinet; The elevator power outage cabinet is tested according to the output signal to determine whether the elevator power outage cabinet has a fault.
7. The elevator power failure cabinet testing method according to claim 6, characterized in that: The method further comprises: If the first instruction is an emergency output test, disconnect the input switch; If the first request signal sent by the elevator power outage cabinet is not received through the first communication line, it is determined that the elevator power outage cabinet has a fault; Alternatively, if the emergency output exceeds a first preset emergency voltage range, it is determined that the elevator power outage cabinet has a fault; the first preset emergency voltage range is related to the rated output voltage of the emergency output.
8. The elevator power failure cabinet testing method according to claim 6, characterized in that: The load switch includes a full load switch and a half load switch; the method further includes: If the first instruction is an emergency output load shedding test, the half-load switch is closed, and the emergency output is connected to the corresponding half-load ripple resistor; If the current emergency output meets the third preset emergency voltage range, the half-load switch is disconnected, the full-load switch is closed, and the emergency output is connected to the corresponding full-load ripple resistor; the third preset emergency voltage range is related to the rated output voltage of the emergency output under half-load conditions; If the current emergency output meets the fourth preset emergency voltage range, it is determined that the elevator power outage cabinet passes the emergency output load shedding test; the fourth preset emergency voltage range is related to the rated output voltage of the emergency output under full load.
9. The elevator power failure cabinet testing method according to claim 6, characterized in that: The method further comprises: If the first instruction is a no-response test of the elevator master control, disconnect the input switch; If the emergency output within the first preset time period meets the first preset emergency voltage range, the emergency output signal of the elevator power outage cabinet is not responded to, and a response timeout signal sent by the elevator power outage cabinet is received through the first communication line, the first voltage of the current emergency output is obtained; If the first voltage is zero, it is determined that the elevator power failure cabinet passes the elevator master control no response test.
10. The elevator power failure cabinet testing method according to claim 6, characterized in that: The method further comprises: If the first instruction is a timeout test, disconnect the input switch, respond to the emergency output signal of the elevator power failure cabinet, and close the load switch; If the emergency output within the second preset time period meets the first preset emergency voltage range, no rescue completion instruction is issued, and an operation timeout signal issued by the elevator power failure cabinet is received through the first communication line, the second voltage of the current emergency output is obtained; If the second voltage is zero, it is determined that the elevator power outage cabinet passes the operation timeout test.
Citation Information
Cited By
Automatic testing method and device for integrated CAN door motor, medium and elevator door motor