Construction data visualization method, device and equipment of cast-in-place pile and medium

Through the connection of optical fiber sensors and electronic equipment, the graphical display of cast-in-place pile construction data is realized, which solves the problem of visual processing of cast-in-place pile construction data and improves the progress and quality control of engineering projects.

CN118734388APending Publication Date: 2024-10-01SHENZHEN GONGKAN GEOTECHN GRP +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410724688.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-05
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Visual processing of cast-in-place pile construction data is difficult to achieve, affecting project progress and quality control.

Method used

Through the connection of optical fiber sensors and electronic equipment, the construction data of cast-in-place piles are obtained, and the current and target pouring heights, hole depths, conduit burial depths and concrete pouring times are graphically displayed on the visualization page, and early warning values ​​and reminder messages are generated to improve Data visualization efficiency and intuitiveness.

Benefits of technology

It realizes efficient visual processing of cast-in-place pile construction data, improves the intuitiveness and visualization efficiency of construction data, and ensures project quality and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734388A_ABST
    Figure CN118734388A_ABST
Patent Text Reader

Abstract

The invention discloses a construction data visualization method, device and equipment of a cast-in-place pile and a medium, and the method comprises the steps that if the current time is the construction time, an indication signal is sent to an optical fiber sensor through an optical fiber; receiving construction data sent by the optical fiber sensor according to the indication signal; in the construction data, the current hole depth of the cast-in-place pile, the current depth of a guide pipe embedded in concrete and the current pouring height are obtained; a preset target pouring height is obtained, the height difference between the current pouring height and the target pouring height is obtained, the concrete pouring time of each time of the cast-in-place pile is obtained, the concrete pouring time of each time is added, and the current concrete pouring time of the cast-in-place pile is obtained; and a visual page of the cast-in-place pile is obtained, and the height difference, the current cast-in-place height, the target cast-in-place height, the current hole depth, the current depth of the guide pipe embedded in the concrete and the current concrete cast-in-place time are displayed on the visual page in a graphical mode. The pouring process of the cast-in-place pile can be visually displayed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of Internet technology, and in particular to a method, device, equipment and medium for visualizing construction data of cast-in-place piles. Background Art

[0002] Cast-in-place piles are usually poured with the conduit method. The basic principle is that under the action of height difference pressure, the concrete falls into the poured concrete through the sealed conduit, and the concrete and mud in the jacking hole gradually rise until the concrete is poured to the predetermined height. The construction data of cast-in-place piles plays an important role in engineering projects. The construction data is not only a measure of project progress, but also a key factor in ensuring the quality and safety of the project. Therefore, how to visualize the construction data of cast-in-place piles is an urgent problem to be solved. Summary of the invention

[0003] The embodiments of the present application provide a method, device, equipment and medium for visualizing the construction data of bored piles to solve the above-mentioned technical problem of how to visualize the construction data of bored piles.

[0004] In a first aspect, an embodiment of the present application provides a method for visualizing construction data of a cast-in-place pile, which is applied to an electronic device, wherein the electronic device is connected to an optical fiber sensor fixed on a steel cage of the cast-in-place pile via an optical fiber, and the method for visualizing construction data comprises:

[0005] Obtain the current time and the construction time of the cast-in-place pile;

[0006] Determine whether the current time is the construction time;

[0007] If the current time is the construction time, an indication signal is sent to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0008] receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0009] In the construction data, the current hole depth of the bored pile, the current depth of the conduit buried in the concrete, and the current pouring height are obtained;

[0010] Obtaining a preset target pouring height, obtaining a height difference between the current pouring height and the target pouring height, obtaining each concrete pouring time of the bored pile, and adding each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0011] A visualization page of the bored pile is obtained, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0012] Exemplarily, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method includes:

[0013] When the height difference is less than a preset difference, a preset reminder message is displayed on the visualization page.

[0014] Exemplarily, the cast-in-place pile early warning value generation model is a generation model of the cast-in-place pile early warning value, and the cast-in-place pile early warning value is a value for early warning of the cast-in-place pile;

[0015] Exemplarily, the cast-in-place pile warning value generation model is:

[0016] E=M*MAX(E1, E2, E3, E4);

[0017] Among them, E is the current bored pile warning value, E1 is the ratio of the current hole depth to the target hole depth, E2 is the ratio of the current pouring height to the target pouring height, E3 is the ratio of the current conduit buried depth in concrete to the target conduit buried depth in concrete, E4 is the ratio of the current concrete pouring time to the target concrete pouring time, and M is a preset amplification factor.

[0018] In a possible implementation of the first aspect, obtaining, in the construction data, a current hole depth of the bored pile, a current depth of the conduit buried in concrete, and a current pouring height includes:

[0019] Preprocessing the construction data, wherein the preprocessing includes processing of error values, missing values, duplicate values ​​and abnormal values;

[0020] The current hole depth of the bored pile, the depth of the front guide pipe buried in concrete, and the current pouring height are obtained from the preprocessed construction data.

[0021] In a possible implementation of the first aspect, the obtaining of a visualization page of the bored pile, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed, includes:

[0022] The height difference, the current perfusion height, and the target perfusion height are set as a first set of data, and a preset chart component is controlled to draw a bar chart based on the first set of data;

[0023] The current hole depth, the current depth of the conduit buried in the concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data;

[0024] Setting the current concrete pouring time as a third set of data, and controlling the chart component to draw a bar chart based on the third set of data;

[0025] The visualization page of the cast-in-place pile is obtained, and the column chart, the line chart and the bar chart are displayed on the visualization page.

[0026] In a possible implementation manner of the first aspect, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data, including:

[0027] Using the time of recording the current hole depth as the abscissa of the first line graph, using the current hole depth as the ordinate of the first line graph, and plotting the current hole depth on the first line graph;

[0028] The time of recording the current depth of the conduit buried in the concrete is used as the horizontal coordinate of the second line graph, and the current depth of the conduit buried in the concrete is used as the vertical coordinate of the second line graph, and the current depth of the conduit buried in the concrete is plotted on the second line graph.

[0029] In a possible implementation of the first aspect, in acquiring the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method includes:

[0030] Obtaining preset target hole depth, target conduit buried depth in concrete, and target concrete pouring time;

[0031] Generate a cast-in-place pile warning value according to the ratio of the current hole depth to the target hole depth, the ratio of the current pouring height to the target pouring height, the ratio of the current conduit buried in concrete depth to the target conduit buried in concrete depth, the ratio of the current concrete pouring time to the target concrete pouring time, and a preset cast-in-place pile warning value generation model;

[0032] Determine whether the cast-in-place pile warning value is greater than the target value;

[0033] If the cast-in-place pile warning value is greater than the target value, a warning message of the cast-in-place pile is displayed on the visualization page.

[0034] Exemplarily, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method includes:

[0035] When the height difference is less than a preset difference, a preset reminder message is displayed on the visualization page.

[0036] Exemplarily, the cast-in-place pile early warning value generation model is a generation model of the cast-in-place pile early warning value, and the cast-in-place pile early warning value is a value for early warning of the cast-in-place pile;

[0037] Exemplarily, the cast-in-place pile warning value generation model is:

[0038] E=M*MAX(E1, E2, E3, E4);

[0039] Among them, E is the current bored pile warning value, E1 is the ratio of the current hole depth to the target hole depth, E2 is the ratio of the current pouring height to the target pouring height, E3 is the ratio of the current conduit buried depth in concrete to the target conduit buried depth in concrete, E4 is the ratio of the current concrete pouring time to the target concrete pouring time, and M is a preset amplification factor.

[0040] In a possible implementation of the first aspect, in acquiring the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method includes:

[0041] Obtain the operation log, and display the operation button corresponding to the operation log on the visualization page.

[0042] In a possible implementation manner of the first aspect,

[0043] In the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method comprises:

[0044] The height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time are pushed to a preset user device through the preset network, and the preset network includes one of the 3G network, 4G network, 5G network, WIFI network or a combination thereof.

[0045] In a second aspect, an embodiment of the present application provides a construction data visualization device for a bored pile, which is applied to an electronic device, wherein the electronic device is connected to an optical fiber sensor fixed on a steel cage of the bored pile via an optical fiber, and comprises:

[0046] A first acquisition module is used to acquire the current time and the construction time of the cast-in-place pile;

[0047] A judgment module, used to judge whether the current time is the construction time;

[0048] A sending module, used for sending an indication signal to the optical fiber sensor through the optical fiber if the current time is the construction time, wherein the indication signal is used for instructing the optical fiber sensor to send the construction data of the cast-in-place pile;

[0049] A receiving module, used for receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0050] A second acquisition module is used to acquire the current hole depth of the cast-in-place pile, the current depth of the conduit buried in the concrete, and the current pouring height from the construction data;

[0051] A third acquisition module is used to acquire a preset target pouring height, acquire a height difference between the current pouring height and the target pouring height, acquire each concrete pouring time of the bored pile, and add up each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0052] A visualization module is used to obtain a visualization page of the bored pile, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0053] In a third aspect, an embodiment of the present application provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, the construction data visualization method of any one of the above-mentioned first aspects is implemented.

[0054] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the construction data visualization method of any one of the above-mentioned first aspects is implemented.

[0055] In a fifth aspect, an embodiment of the present application provides a computer program product. When the computer program product is run on an electronic device, the electronic device executes the construction data visualization method described in any one of the first aspects above.

[0056] The beneficial effects of the embodiments of the present application lie in two aspects. On the one hand, a visualization page of the bored pile is obtained, and on the visualization page, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner. Therefore, the electronic device visualizes the construction data of the bored pile, which is beneficial to improving the visualization efficiency of the construction data. On the other hand, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner, which is beneficial to intuitively displaying the pouring process of the bored pile. BRIEF DESCRIPTION OF THE DRAWINGS

[0057] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0058] Figure 1 An application scenario diagram of the construction data visualization method provided in an embodiment of the present application;

[0059] Figure 2 It is a flowchart of a construction data visualization method provided in an embodiment of the present application;

[0060] Figure 3 A sample diagram of a bar graph provided in an embodiment of the present application;

[0061] Figure 4 A schematic block diagram of a construction data visualization device provided in an embodiment of the present application;

[0062] Figure 5 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application. DETAILED DESCRIPTION

[0063] In order to make the purpose, technical solutions and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not intended to limit the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of the present application.

[0064] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0065] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.

[0066] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0067] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.

[0068] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0069] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0070] In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the fact that they can be implemented by ordinary technicians in this field. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by this application.

[0071] The flowcharts shown in the accompanying drawings are only examples and do not necessarily include all the contents and operations / steps, nor must they be executed in the order described. For example, some operations / steps may also be decomposed, combined or partially merged, so the actual execution order may change according to actual conditions.

[0072] The construction data visualization method provided in the embodiments of the present application can be applied to electronic devices such as mobile phones, tablet computers, wearable devices, vehicle-mounted devices, augmented reality (AR) / virtual reality (VR) devices, laptop computers, ultra-mobile personal computers (UMPC), netbooks, personal digital assistants (PDA), etc. The embodiments of the present application do not impose any restrictions on the specific types of electronic devices.

[0073] For example, the electronic device may be a station (STAION, ST) in a WLAN, a cellular phone, a cordless phone, a Session Initiation Protocol (SIP) phone, a Wireless Local Loop (WLL) station, a Personal Digital Assistant (PDA) device, a handheld device with wireless communication function, a computing device or other processing device connected to a wireless modem, a vehicle-mounted device, a vehicle networking terminal, a computer, a laptop computer, a handheld communication device, a handheld computing device, a satellite wireless device, a wireless modem card, a TV set top box (STB), customer premises equipment (CPE) and / or other devices for communicating on a wireless system and a next-generation communication system, such as a mobile terminal in a 5G network or a mobile terminal in a future evolved Public Land Mobile Network (PLMN) network, etc.

[0074] See also Figure 1 , Figure 1 The application scenario diagram of the construction data visualization method provided in the embodiment of the present application is described in detail as follows:

[0075] The electronic device is connected to the fiber optic sensor fixed on the steel cage of the cast-in-place pile through optical fiber.

[0076] The optical fiber sensor collects the construction data of the cast-in-place piles in real time.

[0077] The construction data may come from one optical fiber sensor on the steel cage or from multiple optical fiber sensors on the steel cage.

[0078] For ease of explanation, the construction data is taken from two optical fiber sensors as an example, as detailed below:

[0079] The two optical fiber sensors include an optical fiber sensor A and an optical fiber sensor B. The electronic device is connected to the optical fiber sensor A and the optical fiber sensor B respectively, and obtains the construction data of the cast-in-place pile from the optical fiber sensor A and the optical fiber sensor B.

[0080] In the embodiment of the present application, the electronic device can be connected to different optical fiber sensors at the same time to obtain the construction data of the cast-in-place piles from the different optical fiber sensors.

[0081] See also Figure 2 , Figure 2It is a flow chart of the construction data visualization method provided in an embodiment of the present application. The method can be applied to electronic equipment, and the electronic equipment is connected to a fiber optic sensor fixed on a steel cage of a cast-in-place pile via an optical fiber.

[0082] like Figure 2 As shown, the construction data visualization method provided in the embodiment of the present application includes the following steps, which are described in detail as follows:

[0083] S201, obtaining the current time and the construction time of the cast-in-place pile;

[0084] The construction time is set by the user or by system default and is not restricted here.

[0085] For the sake of illustration, an example is given below:

[0086] For example, the construction time is from 9 am to 6 pm.

[0087] For example, the construction time is from 8 am to 5 pm.

[0088] S202, determining whether the current time is the construction time;

[0089] S203, if the current time is the construction time, sending an indication signal to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0090] Exemplarily, the format of the construction data includes one of the CSV format and the JSON format or a combination thereof.

[0091] Among them, the CSV (Comma Separated Values) format is a plain text file format for storing tabular data.

[0092] Among them, JSON (JavaScript Object Notation) is a lightweight data exchange format.

[0093] S204, receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0094] Wherein, the construction data sent by the optical fiber sensor according to the indication signal is received through the optical fiber.

[0095] S205, obtaining the current hole depth of the bored pile, the current depth of the conduit buried in concrete, and the current pouring height from the construction data;

[0096] The current buried depth of the conduit in the concrete is the current depth of the conduit buried in the concrete, that is, the current value of the buried depth of the conduit.

[0097] Wherein, in the construction data, obtaining the current hole depth of the bored pile, the current depth of the conduit buried in concrete, and the current pouring height includes:

[0098] Preprocessing the construction data, wherein the preprocessing includes processing of error values, missing values, duplicate values ​​and abnormal values;

[0099] The current hole depth of the bored pile, the depth of the front guide pipe buried in concrete, and the current pouring height are obtained from the preprocessed construction data.

[0100] S206, obtaining a preset target pouring height, obtaining a height difference between the current pouring height and the target pouring height, obtaining each concrete pouring time of the bored pile, and adding each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0101] The concrete pouring time of each time of the bored pile is obtained, and the concrete pouring time of each time is added up to obtain the current concrete pouring time of the bored pile. For the convenience of explanation, an example is given below:

[0102] For example, the number of pouring times of the bored pile is 2, and the two concrete pouring times are 0.5 hours and 0.5 hours respectively. By adding the concrete pouring time of each time, the current concrete pouring time of the bored pile is 1 hour.

[0103] For example, the number of pouring times of the bored pile is 3, and the three concrete pouring times are 0.5 hour, 1 hour, and 1 hour respectively. By adding up the concrete pouring time of each time, the current concrete pouring time of the bored pile is 2.5 hours.

[0104] S207, obtaining a visualization page of the bored pile, and displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time in a graphical manner on the visualization page.

[0105] The step of obtaining a visualization page of the bored pile, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed, includes:

[0106] The height difference, the current perfusion height, and the target perfusion height are set as a first set of data, and a preset chart component is controlled to draw a bar chart based on the first set of data;

[0107] The current hole depth, the current depth of the conduit buried in the concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data;

[0108] Setting the current concrete pouring time as a third set of data, and controlling the chart component to draw a bar chart based on the third set of data;

[0109] The visualization page of the cast-in-place pile is obtained, and the column chart, the line chart and the bar chart are displayed on the visualization page.

[0110] The current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data, including:

[0111] Using the time of recording the current hole depth as the abscissa of the first line graph, using the current hole depth as the ordinate of the first line graph, and plotting the current hole depth on the first line graph;

[0112] The time of recording the current depth of the conduit buried in the concrete is used as the horizontal coordinate of the second line graph, and the current depth of the conduit buried in the concrete is used as the vertical coordinate of the second line graph, and the current depth of the conduit buried in the concrete is plotted on the second line graph.

[0113] Wherein, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time on the visualization page, the construction data visualization method comprises:

[0114] Step A, obtaining a preset target hole depth, a target catheter buried in concrete depth, and a target concrete pouring time;

[0115] The target buried depth of the conduit in the concrete is the target depth of the conduit buried in the concrete, that is, the target value of the buried depth of the conduit.

[0116] Generate a cast-in-place pile warning value according to the ratio of the current hole depth to the target hole depth, the ratio of the current pouring height to the target pouring height, the ratio of the current conduit buried in concrete depth to the target conduit buried in concrete depth, the ratio of the current concrete pouring time to the target concrete pouring time, and a preset cast-in-place pile warning value generation model;

[0117] Determine whether the cast-in-place pile warning value is greater than the target value;

[0118] If the cast-in-place pile warning value is greater than the target value, a warning message of the cast-in-place pile is displayed on the visualization page.

[0119] The target value is set by the user or by the system default and is not restricted here.

[0120] Exemplarily, the cast-in-place pile early warning value generation model is a generation model of the cast-in-place pile early warning value, and the cast-in-place pile early warning value is a value for early warning of the cast-in-place pile;

[0121] Exemplarily, the cast-in-place pile warning value generation model is:

[0122] E=M*MAX(E1, E2, E3, E4);

[0123] Among them, E is the current bored pile warning value, E1 is the ratio of the current hole depth to the target hole depth, E2 is the ratio of the current pouring height to the target pouring height, E3 is the ratio of the current conduit buried depth in concrete to the target conduit buried depth in concrete, E4 is the ratio of the current concrete pouring time to the target concrete pouring time, and M is a preset amplification factor.

[0124] The amplification factor is set by the user or by system default and is not restricted here.

[0125] For the sake of illustration, an example is given below:

[0126] For example, if M is 100, the cast-in-place pile warning value generation model is:

[0127] E=100*MAX(E1, E2, E3, E4);

[0128] For example, if M is 1000, the cast-in-place pile warning value generation model is:

[0129] E=1000*MAX(E1, E2, E3, E4);

[0130] Among them, the maximum value among E1, E2, E3, and E4 can be amplified by the amplification factor, which is helpful to help the system monitor the maximum value among E1, E2, E3, and E4.

[0131] Wherein, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time on the visualization page, the construction data visualization method comprises:

[0132] Step B, obtaining the operation log, and displaying the operation button corresponding to the operation log on the visualization page.

[0133] Wherein, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time on the visualization page, the construction data visualization method comprises:

[0134] Step C, pushing the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time to a preset user device through the preset network, wherein the preset network includes one of a 3G network, a 4G network, a 5G network, and a WIFI network, or a combination thereof.

[0135] Exemplarily, in the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method includes:

[0136] Step D: When the height difference is less than a preset difference, a preset reminder message is displayed on the visualization page.

[0137] Among them, step A can be executed before or after step B, step C, and step D, step B can be executed before or after step A, step C, and step D, step C can be executed before or after step A, step B, and step D, step D can be executed before or after step A, step B, and step C, and steps A, step B, step C, and step D can also be executed simultaneously. The specific execution order is not limited here.

[0138] The beneficial effects of the embodiments of the present application lie in two aspects. On the one hand, a visualization page of the bored pile is obtained, and on the visualization page, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner. Therefore, the electronic device visualizes the construction data of the bored pile, which is beneficial to improving the visualization efficiency of the construction data. On the other hand, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner, which is beneficial to intuitively displaying the pouring process of the bored pile.

[0139] See also Figure 3 , Figure 3 The sample diagram of the bar graph provided in the embodiment of the present application is described in detail as follows:

[0140] The bar graph includes the current filling height and the target filling height.

[0141] Among them, the black filled part represents the poured concrete.

[0142] The difference between the current filling height and the target filling height is the height difference.

[0143] For the sake of illustration, an example is given below:

[0144] For example, the current filling height is 1 meter, the target filling height is 20 meters, and the height difference is 19 meters.

[0145] For example, the current filling height is 2 meters, the target filling height is 20 meters, and the height difference is 18 meters.

[0146] For example, the current filling height is 4 meters, the target filling height is 24 meters, and the height difference is 20 meters.

[0147] In the embodiment of the present application, the current perfusion height and the target perfusion height can be intuitively displayed based on a bar graph, which can meet the personalized needs of users, improve the user experience, and improve the efficiency of obtaining the current perfusion height and the target perfusion height.

[0148] Corresponding to the construction data visualization method described in the above embodiment, please refer to Figure 4 , Figure 4 A schematic block diagram of a construction data visualization device provided in an embodiment of the present application, Figure 4 The construction data visualization device 400 shown can be applied to Figure 1 The electronic device in the application scenario diagram shown below takes the electronic device as an example. Figure 4The construction data visualization device 400 shown is described in detail. The construction data visualization device 400 may include a first acquisition module 401, a judgment module 402, a sending module 403, a receiving module 404, a second acquisition module 405, a third acquisition module 406, and a visualization module 407.

[0149] The first acquisition module 401 is used to acquire the current time and the construction time of the cast-in-place pile;

[0150] A judgment module 402 is used to judge whether the current time is the construction time;

[0151] The sending module 403 is used for sending an indication signal to the optical fiber sensor through the optical fiber if the current time is the construction time, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0152] A receiving module 404, configured to receive the construction data sent by the optical fiber sensor according to the indication signal;

[0153] The second acquisition module 405 is used to acquire the current hole depth of the cast-in-place pile, the current depth of the conduit buried in the concrete, and the current pouring height from the construction data;

[0154] The third acquisition module 406 is used to acquire a preset target pouring height, acquire a height difference between the current pouring height and the target pouring height, acquire each concrete pouring time of the bored pile, and add up each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0155] The visualization module 407 is used to obtain a visualization page of the bored pile, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0156] It should be noted that the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0157] The beneficial effects of the embodiments of the present application lie in two aspects. On the one hand, a visualization page of the bored pile is obtained, and on the visualization page, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner. Therefore, the electronic device visualizes the construction data of the bored pile, which is beneficial to improving the visualization efficiency of the construction data. On the other hand, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are displayed in a graphical manner, which is beneficial to intuitively displaying the pouring process of the bored pile.

[0158] See also Figure 5 , Figure 5 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application.

[0159] like Figure 5 As shown, Figure 5 The electronic device 2 includes: at least one processor 20, a memory 21, and a computer program 22 stored in the memory 21 and executable on the at least one processor 20, and when the processor 20 executes the computer program 22, the steps in any of the above-mentioned method embodiments are implemented.

[0160] The electronic device 2 may include, but is not limited to, a processor 20 and a memory 21. Those skilled in the art will appreciate that Figure 5 It is only an example of the electronic device 2 and does not constitute a limitation on the electronic device 2. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components. For example, it may also include input and output devices, network access devices, etc.

[0161] The processor 20 is used to run the computer program 22 stored in the memory 21, and implement the following steps when executing the computer program 22:

[0162] Obtain the current time and the construction time of the cast-in-place pile;

[0163] Determine whether the current time is the construction time;

[0164] If the current time is the construction time, an indication signal is sent to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0165] receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0166] In the construction data, the current hole depth, current depth of the conduit buried in concrete, and current pouring height of the bored pile are obtained; the preset target pouring height is obtained, the height difference between the current pouring height and the target pouring height is obtained, each concrete pouring time of the bored pile is obtained, and each concrete pouring time is added to obtain the current concrete pouring time of the bored pile; a visualization page of the bored pile is obtained, and on the visualization page, the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0167] In some embodiments, the processor 20 is configured to implement:

[0168] Preprocessing the construction data, wherein the preprocessing includes processing of error values, missing values, duplicate values ​​and abnormal values;

[0169] The current hole depth of the bored pile, the depth of the front guide pipe buried in concrete, and the current pouring height are obtained from the preprocessed construction data.

[0170] In some embodiments, the processor 20 is configured to implement:

[0171] The height difference, the current perfusion height, and the target perfusion height are set as a first set of data, and a preset chart component is controlled to draw a bar chart based on the first set of data;

[0172] The current hole depth, the current depth of the conduit buried in the concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data;

[0173] Setting the current concrete pouring time as a third set of data, and controlling the chart component to draw a bar chart based on the third set of data;

[0174] The visualization page of the cast-in-place pile is obtained, and the column chart, the line chart and the bar chart are displayed on the visualization page.

[0175] In some embodiments, the processor 20 is configured to implement:

[0176] Using the time of recording the current hole depth as the abscissa of the first line graph, using the current hole depth as the ordinate of the first line graph, and plotting the current hole depth on the first line graph;

[0177] The time of recording the current depth of the conduit buried in the concrete is used as the horizontal coordinate of the second line graph, and the current depth of the conduit buried in the concrete is used as the vertical coordinate of the second line graph, and the current depth of the conduit buried in the concrete is plotted on the second line graph.

[0178] In some embodiments, the processor 20 is configured to implement:

[0179] Obtaining preset target hole depth, target conduit buried depth in concrete, and target concrete pouring time;

[0180] Generate a cast-in-place pile warning value according to the ratio of the current hole depth to the target hole depth, the ratio of the current pouring height to the target pouring height, the ratio of the current conduit buried in concrete depth to the target conduit buried in concrete depth, the ratio of the current concrete pouring time to the target concrete pouring time, and a preset cast-in-place pile warning value generation model;

[0181] Determine whether the cast-in-place pile warning value is greater than the target value;

[0182] If the cast-in-place pile warning value is greater than the target value, a warning message of the cast-in-place pile is displayed on the visualization page.

[0183] In some embodiments, the processor 20 is configured to implement:

[0184] Obtain the operation log, and display the operation button corresponding to the operation log on the visualization page.

[0185] In some embodiments, the processor 20 is configured to implement:

[0186] The height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time are pushed to a preset user device through the preset network, and the preset network includes one of the 3G network, 4G network, 5G network, WIFI network or a combination thereof.

[0187] The processor 20 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0188] In some embodiments, the memory 21 may be an internal storage unit of the electronic device 2, such as a hard disk or memory of the electronic device 2. In other embodiments, the memory 21 may also be an external storage device of the electronic device 2, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), etc. equipped on the electronic device 2. Further, the memory 21 may also include both an internal storage unit of the electronic device 2 and an external storage device. The memory 21 is used to store an operating system, an application program, a boot loader (Boot Loader), data, and other programs, such as the program code of the computer program, etc. The memory 21 may also be used to temporarily store data that has been output or is to be output.

[0189] It should be noted that the information interaction, execution process, etc. between the above-mentioned devices / units are based on the same concept as the method embodiment of the present application. Their specific functions and technical effects can be found in the method embodiment part and will not be repeated here.

[0190] An embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps in the above-mentioned method embodiments can be implemented.

[0191] The computer-readable storage medium stores program codes, which can be called by a processor to execute the construction data visualization method described in the above method embodiment.

[0192] The computer-readable storage medium has a storage space for program codes.

[0193] The program code includes the code of any step in the construction data visualization method described in the above method embodiment.

[0194] For example, the program code is called by the processor and can execute the following steps:

[0195] Obtain the current time and the construction time of the cast-in-place pile;

[0196] Determine whether the current time is the construction time;

[0197] If the current time is the construction time, an indication signal is sent to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0198] receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0199] In the construction data, the current hole depth of the bored pile, the current depth of the conduit buried in the concrete, and the current pouring height are obtained;

[0200] Obtaining a preset target pouring height, obtaining a height difference between the current pouring height and the target pouring height, obtaining each concrete pouring time of the bored pile, and adding each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0201] A visualization page of the bored pile is obtained, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0202] The specific implementation of the above operations can be found in the previous embodiments, which will not be described in detail here.

[0203] The computer-readable storage medium may also be an external storage device of the construction data visualization device or electronic device, for example, a plug-in hard disk, a smart memory card (SmartMedia Card, SMC), a secure digital (Secure Digital, SD) card, a flash card (Flash Card), a non-transitory computer-readable storage medium (non-transitory computer-readable storage medium), etc., equipped on the construction data visualization device or electronic device.

[0204] Since the computer program stored in the computer-readable storage medium can execute any one of the methods for visualizing the construction data of cast-in-place piles provided in the embodiments of the present application, the computer-readable storage medium can achieve the beneficial effects that can be achieved by any one of the methods for visualizing the construction data of cast-in-place piles provided in the embodiments of the present application. Please see the previous embodiments for details and will not be repeated here.

[0205] An embodiment of the present application provides a computer program product. When the computer program product is run on an electronic device, the electronic device executes the above-mentioned construction data visualization method.

[0206] The computer program product is loaded into the electronic device and can execute the following steps:

[0207] Obtain the current time and the construction time of the cast-in-place pile;

[0208] Determine whether the current time is the construction time;

[0209] If the current time is the construction time, an indication signal is sent to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile;

[0210] receiving the construction data sent by the optical fiber sensor according to the indication signal;

[0211] In the construction data, the current hole depth of the bored pile, the current depth of the conduit buried in the concrete, and the current pouring height are obtained;

[0212] Obtaining a preset target pouring height, obtaining a height difference between the current pouring height and the target pouring height, obtaining each concrete pouring time of the bored pile, and adding each concrete pouring time to obtain the current concrete pouring time of the bored pile;

[0213] A visualization page of the bored pile is obtained, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

[0214] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium.

[0215] The technicians in the relevant field can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example for illustration. In practical applications, the above-mentioned function allocation can be completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above. The functional units and modules in the embodiment can be integrated in a processing unit, or each unit can exist physically separately, or two or more units can be integrated in one unit. The above-mentioned integrated unit can be implemented in the form of hardware or in the form of software functional units. In addition, the specific names of the functional units and modules are only for the convenience of distinguishing each other, and are not used to limit the scope of protection of this application. The specific working process of the units and modules in the above-mentioned system can refer to the corresponding process in the aforementioned method embodiment, which will not be repeated here.

[0216] Based on such understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device capable of carrying the computer program code to an electronic device, a recording medium, a computer memory, a read-only memory (ROM, Read-Only Memory), a random access memory (RAM, Random Access Memory), an electric carrier signal, a telecommunication signal, and a software distribution medium. For example, a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk. In some jurisdictions, according to legislation and patent practice, computer-readable media cannot be electric carrier signals and telecommunication signals.

[0217] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0218] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A method for visualizing construction data of a cast-in-place pile, characterized in that: Applied to electronic equipment, the electronic equipment is connected to an optical fiber sensor fixed on a steel cage of a cast-in-place pile through an optical fiber, and the construction data visualization method includes: Obtain the current time and the construction time of the cast-in-place pile; Determine whether the current time is the construction time; If the current time is the construction time, an indication signal is sent to the optical fiber sensor through the optical fiber, wherein the indication signal is used to instruct the optical fiber sensor to send the construction data of the cast-in-place pile; receiving the construction data sent by the optical fiber sensor according to the indication signal; In the construction data, the current hole depth of the bored pile, the current depth of the conduit buried in the concrete, and the current pouring height are obtained; Obtaining a preset target pouring height, obtaining a height difference between the current pouring height and the target pouring height, obtaining each concrete pouring time of the bored pile, and adding each concrete pouring time to obtain the current concrete pouring time of the bored pile; A visualization page of the bored pile is obtained, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

2. The construction data visualization method according to claim 1, characterized in that: The current hole depth of the bored pile, the current depth of the conduit buried in concrete, and the current pouring height are obtained from the construction data, including: Preprocessing the construction data, wherein the preprocessing includes processing of error values, missing values, duplicate values ​​and abnormal values; The current hole depth of the bored pile, the depth of the front guide pipe buried in concrete, and the current pouring height are obtained from the preprocessed construction data.

3. The construction data visualization method according to claim 1, characterized in that: The step of obtaining a visualization page of the bored pile, graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, includes: The height difference, the current perfusion height, and the target perfusion height are set as a first set of data, and a preset chart component is controlled to draw a bar chart based on the first set of data; The current hole depth, the current depth of the conduit buried in the concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data; Setting the current concrete pouring time as a third set of data, and controlling the chart component to draw a bar chart based on the third set of data; The visualization page of the cast-in-place pile is obtained, and the column chart, the line chart and the bar chart are displayed on the visualization page.

4. The construction data visualization method according to claim 3, characterized in that: The current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are set as a second set of data, and the chart component is controlled to draw a line chart based on the second set of data, including: Using the time of recording the current hole depth as the abscissa of the first line graph, using the current hole depth as the ordinate of the first line graph, and plotting the current hole depth on the first line graph; The time of recording the current depth of the conduit buried in the concrete is used as the horizontal coordinate of the second line graph, and the current depth of the conduit buried in the concrete is used as the vertical coordinate of the second line graph, and the current depth of the conduit buried in the concrete is plotted on the second line graph.

5. The construction data visualization method according to claim 1, characterized in that: In the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method comprises: Obtaining preset target hole depth, target conduit buried depth in concrete, and target concrete pouring time; Generate a cast-in-place pile warning value according to the ratio of the current hole depth to the target hole depth, the ratio of the current pouring height to the target pouring height, the ratio of the current conduit buried in concrete depth to the target conduit buried in concrete depth, the ratio of the current concrete pouring time to the target concrete pouring time, and a preset cast-in-place pile warning value generation model; Determining whether the cast-in-place pile warning value is greater than a target value; If the cast-in-place pile warning value is greater than the target value, a warning message of the cast-in-place pile is displayed on the visualization page.

6. The construction data visualization method according to claim 1, characterized in that: In the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method comprises: Obtain the operation log, and display the operation button corresponding to the operation log on the visualization page.

7. The construction data visualization method according to any one of claims 1 to 6, characterized in that: In the obtaining of the visualization page of the bored pile, after graphically displaying the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time on the visualization page, the construction data visualization method comprises: The height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete and the current concrete pouring time are pushed to a preset user device through the preset network, and the preset network includes one of the 3G network, 4G network, 5G network, WIFI network or a combination thereof.

8. A construction data visualization device for cast-in-place piles, characterized in that: Applied to electronic equipment, the electronic equipment is connected to an optical fiber sensor fixed on a steel cage of a cast-in-place pile through an optical fiber, comprising: A first acquisition module is used to acquire the current time and the construction time of the cast-in-place pile; A judgment module, used to judge whether the current time is the construction time; A sending module, used for sending an indication signal to the optical fiber sensor through the optical fiber if the current time is the construction time, wherein the indication signal is used for instructing the optical fiber sensor to send the construction data of the cast-in-place pile; A receiving module, used for receiving the construction data sent by the optical fiber sensor according to the indication signal; A second acquisition module is used to acquire the current hole depth of the cast-in-place pile, the current depth of the conduit buried in the concrete, and the current pouring height from the construction data; A third acquisition module is used to acquire a preset target pouring height, acquire a height difference between the current pouring height and the target pouring height, acquire each concrete pouring time of the bored pile, and add up each concrete pouring time to obtain the current concrete pouring time of the bored pile; A visualization module is used to obtain a visualization page of the bored pile, on which the height difference, the current pouring height, the target pouring height, the current hole depth, the current depth of the conduit buried in concrete, and the current concrete pouring time are graphically displayed.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the construction data visualization method according to any one of claims 1 to 7 is implemented.