Method and device for determining reasonable number of gas injection wells of underground gas storage

By generating a gas storage numerical model and gas injection simulation, the reasonable number of gas injection wells in the underground gas storage is calculated, which solves the problem of inaccurate prediction of the number of gas injection wells in the existing technology and improves the gas injection efficiency and effective gas volume.

CN118734728APending Publication Date: 2024-10-01CHINA PETROLEUM & CHEMICAL CORP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310327078.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

Existing technology cannot accurately predict the reasonable number of gas injection wells in underground gas storage, resulting in the actual effective working gas volume being lower than expected.

Method used

By generating a gas storage numerical model based on gas reservoir-related data, we perform gas injection simulation, calculate the effective working gas volume of the gas well, and determine the reasonable gas injection capacity under different reservoir pressures, combined with the pipe string erosion flow rate of the gas well and the maximum compressor Gas injection pressure, calculate the reasonable number of gas injection wells.

Benefits of technology

It achieves high-precision calculation of the number of gas injection wells, ensuring the effective working gas volume and gas injection capacity of the underground gas storage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118734728A_ABST
    Figure CN118734728A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of underground gas storage gas injection wells, and provides a method and device for determining the reasonable number of gas injection wells of an underground gas storage. The method comprises the steps of generating a gas storage numerical model of a gas well based on obtained gas reservoir related data of a target area and the gas reservoir related data; performing gas injection simulation according to the gas storage numerical model, and calculating the effective working gas quantity of the gas well; determining a gas injection capacity intersection point of the gas well according to a gas flow inflow curve and a gas flow outflow curve of the gas well in the related data of the gas reservoir, and determining reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection point, the tubular column erosion flow of the gas well and the maximum gas injection pressure of a compressor; and calculating the single well control area of the gas well according to the effective working gas amount, and calculating the reasonable gas injection well number in combination with the effective working gas amount, the reasonable gas injection capacity and the block area of the target area. According to the embodiment of the invention, the high-precision gas injection well number can be obtained through calculation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present disclosure relates to the technical field of gas injection wells for underground gas storages, and in particular to a method and device for determining a reasonable number of gas injection wells for underground gas storages. Background Art

[0002] Gas injection in gas storage is different from gas field development. The injection time is shorter, generally from March to October. Gas storage injects a large amount of natural gas in a short period of time. On the one hand, it requires a high gas injection capacity of a single well, and on the other hand, it is necessary to ensure a sufficient number of gas injection wells and injection pressure. Especially during gas reservoir development, the drop in formation pressure may cause pore deformation and crack closure, resulting in the reservoir's suction capacity being far lower than its exhaust capacity. In addition, the gas reservoir development time is much longer than the gas injection time of the gas storage. Only relying on the gas production capacity data in the gas reservoir development stage to evaluate the injection capacity of the gas storage wells and determine the number of gas storage wells may result in the actual effective working gas volume of the gas storage being far lower than the working gas volume determined by the pressure drop method. There is no good method in the prior art to determine the reasonable number of gas injection wells for underground gas storage, and it is impossible to accurately predict the reasonable number of gas injection wells for underground gas storage. Summary of the invention

[0003] In view of this, the embodiments of the present disclosure provide a method and device for determining a reasonable number of gas injection wells for an underground gas storage reservoir, so as to solve the problem in the prior art that the reasonable number of gas injection wells for an underground gas storage reservoir cannot be accurately predicted.

[0004] A first aspect of an embodiment of the present disclosure provides a method for determining a reasonable number of gas injection wells in an underground gas storage reservoir, comprising:

[0005] Based on the acquired gas reservoir related data of the target area, a gas storage reservoir numerical model of the gas well is generated based on the gas reservoir related data;

[0006] Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well;

[0007] Determine the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor;

[0008] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0009] In some embodiments, generating a gas storage numerical model based on the gas reservoir related data includes:

[0010] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0011] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0012] In some embodiments, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0013]

[0014] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0015] In some embodiments, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0016]

[0017]

[0018] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0019] In some embodiments, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0020]

[0021] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0022] In some embodiments, the gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including:

[0023] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0024] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0025] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0026] In some embodiments, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0027] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0028] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0029] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0030] In some embodiments, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0031] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0032] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0033]

[0034]

[0035] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0036] The single well control area is calculated according to the single well control radius.

[0037] In some embodiments, the calculating of the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0038] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0039]

[0040] Among them, the Nwell represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0041] A second aspect of the embodiment of the present disclosure provides a device for determining a reasonable number of gas injection wells in an underground gas storage, comprising:

[0042] A generation module, for generating a gas storage reservoir numerical model of a gas well based on the acquired gas reservoir related data of the target area and based on the gas reservoir related data;

[0043] A first calculation module is used to perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well;

[0044] A determination module, for determining the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor;

[0045] The second calculation module is used to calculate the single well control area of ​​the gas well according to the effective working gas volume, and calculate the reasonable number of gas injection wells in combination with the effective working gas volume, reasonable gas injection capacity and the block area of ​​the target area.

[0046] In some embodiments, generating a gas storage numerical model based on the gas reservoir related data includes:

[0047] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0048] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0049] In some embodiments, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0050]

[0051] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0052] In some embodiments, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0053]

[0054]

[0055] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0056] In some embodiments, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0057]

[0058] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0059] In some embodiments, the first computing module is further configured to:

[0060] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0061] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0062] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0063] In some embodiments, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0064] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0065] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0066] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0067] In some embodiments, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0068] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0069] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0070]

[0071]

[0072] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0073] The single well control area is calculated according to the single well control radius.

[0074] In some embodiments, the calculating of the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0075] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0076]

[0077] Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0078] According to a third aspect of the embodiments of the present disclosure, an electronic device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the steps implemented when the processor executes the computer program include:

[0079] Based on the acquired gas reservoir related data of the target area, a gas storage reservoir numerical model of the gas well is generated based on the gas reservoir related data;

[0080] Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well;

[0081] Determine the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor;

[0082] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0083] In some embodiments, generating a gas storage numerical model based on the gas reservoir related data includes:

[0084] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0085] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0086] In some embodiments, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0087]

[0088] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0089] In some embodiments, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0090]

[0091]

[0092] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0093] In some embodiments, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0094]

[0095] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0096] In some embodiments, the gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including:

[0097] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0098] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0099] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0100] In some embodiments, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0101] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0102] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0103] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0104] In some embodiments, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0105] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0106] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0107]

[0108]

[0109] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0110] The single well control area is calculated according to the single well control radius.

[0111] In some embodiments, the calculating of the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0112] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0113]

[0114] Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0115] In a fourth aspect of the embodiments of the present disclosure, a computer-readable storage medium is provided, wherein the computer-readable storage medium stores a computer program, and the steps implemented when the computer program is executed by a processor include:

[0116] Based on the acquired gas reservoir related data of the target area, a gas storage reservoir numerical model of the gas well is generated based on the gas reservoir related data;

[0117] Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well;

[0118] Determine the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor;

[0119] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0120] In some embodiments, generating a gas storage numerical model based on the gas reservoir related data includes:

[0121] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0122] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0123] In some embodiments, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0124]

[0125] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0126] In some embodiments, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0127]

[0128]

[0129] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0130] In some embodiments, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0131]

[0132] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0133] In some embodiments, the gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including:

[0134] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0135] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0136] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0137] In some embodiments, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0138] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0139] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0140] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0141] In some embodiments, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0142] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0143] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0144]

[0145]

[0146] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0147] The single well control area is calculated according to the single well control radius.

[0148] In some embodiments, the calculating of the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0149] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0150]

[0151] Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0152] In a fifth aspect of the embodiments of the present disclosure, a computer program product is provided. The computer program product includes a computer program or an instruction. When the computer program or the instruction is executed by a processor, the steps implemented include:

[0153] Based on the acquired gas reservoir related data of the target area, a gas storage reservoir numerical model of the gas well is generated based on the gas reservoir related data;

[0154] Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well;

[0155] Determine the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor;

[0156] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0157] In some embodiments, generating a gas storage numerical model based on the gas reservoir related data includes:

[0158] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0159] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0160] In some embodiments, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0161]

[0162] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0163] In some embodiments, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0164]

[0165]

[0166] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0167] In some embodiments, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0168]

[0169] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0170] In some embodiments, the gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including:

[0171] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0172] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0173] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0174] In some embodiments, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0175] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0176] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0177] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0178] In some embodiments, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0179] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0180] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0181]

[0182]

[0183] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0184] The single well control area is calculated according to the single well control radius.

[0185] In some embodiments, the calculating of the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0186] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0187]

[0188] Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0189] Beneficial Effects

[0190] Compared with the prior art, the beneficial effects of the disclosed embodiments include at least: generating a gas storage reservoir numerical model of the gas well based on the acquired gas reservoir-related data of the target area and based on the gas reservoir-related data; performing gas injection simulation according to the gas storage reservoir numerical model to calculate the effective working gas volume of the gas well; determining the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir-related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor; calculating the single well control area of ​​the gas well according to the effective working gas volume, and calculating the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area, so as to calculate the number of gas injection wells with high precision. BRIEF DESCRIPTION OF THE DRAWINGS

[0191] In order to more clearly illustrate the technical solutions in the embodiments of the present disclosure, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only the embodiments, and for ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0192] Figure 1 It is a schematic diagram of an application scenario of a method for determining a reasonable number of gas injection wells in an underground gas storage provided by an embodiment of the present disclosure;

[0193] Figure 2 It is a flowchart of some embodiments of a method for determining a reasonable number of gas injection wells in an underground gas storage provided according to an embodiment of the present disclosure;

[0194] Figure 3 It is a flowchart of some other embodiments of another method for determining the reasonable number of gas injection wells of an underground gas storage provided by an embodiment of the present disclosure;

[0195] Figure 4 It is a simplified structural schematic diagram of a device for determining the reasonable number of gas injection wells in an underground gas storage provided according to an embodiment of the present disclosure;

[0196] Figure 5 is a schematic diagram of an electronic device provided according to an embodiment of the present disclosure. DETAILED DESCRIPTION

[0197] Embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although certain embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be construed as being limited to the embodiments set forth herein. On the contrary, these embodiments are provided to provide a more thorough and complete understanding of the present disclosure. It should be understood that the drawings and embodiments of the present disclosure are only for exemplary purposes and are not intended to limit the scope of protection of the present disclosure.

[0198] It should also be noted that, for ease of description, only the parts related to the present disclosure are shown in the drawings. In the absence of conflict, the embodiments and features in the embodiments of the present disclosure can be combined with each other.

[0199] It should be noted that the concepts such as "first" and "second" mentioned in the present disclosure are only used to distinguish different systems, devices, modules or units, and are not used to limit the order or interdependence of the functions performed by these systems, devices, modules or units.

[0200] It should be noted that the modifications of "one" and "plurality" mentioned in the present disclosure are illustrative rather than restrictive, and those skilled in the art should understand that unless otherwise clearly indicated in the context, it should be understood as "one or more".

[0201] The names of the messages or information exchanged between multiple devices in the embodiments of the present disclosure are only used for illustrative purposes and are not used to limit the scope of these messages or information.

[0202] The present disclosure will be described in detail below with reference to the accompanying drawings and in conjunction with embodiments.

[0203] Embodiment 1:

[0204] Figure 1 It is a schematic diagram of an application scenario of the method for determining the reasonable number of gas injection wells of an underground gas storage according to the first embodiment of the present disclosure.

[0205] exist Figure 1 In the application scenario, first, the computing device 101 can generate a gas storage reservoir numerical model 103 of the gas well based on the acquired gas reservoir related data 102 of the target area and based on the gas reservoir related data 102.

[0206] Secondly, the computing device 101 can perform gas injection simulation according to the gas storage numerical model 103 to calculate the effective working gas volume 104 of the gas well.

[0207] Again, the computing device 101 can determine the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir-related data, and determine the reasonable gas injection capacity 105 corresponding to different reservoir pressures based on the intersection of the gas injection capacity, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor.

[0208] Finally, the computing device 101 can calculate the single well control area 106 of the gas well according to the effective working gas volume 104, and calculate the reasonable number of gas injection wells 108 in combination with the effective working gas volume 104, the reasonable gas injection capacity 105 and the block area 107 of the target area.

[0209] It should be noted that the computing device 101 can be hardware or software. When the computing device is hardware, it can be implemented as a distributed cluster consisting of multiple servers or terminal devices, or as a single server or a single terminal device. When the computing device is embodied as software, it can be installed in the hardware devices listed above. It can be implemented as multiple software or software modules for providing distributed services, or as a single software or software module. No specific limitation is made here.

[0210] It should be understood that Figure 1 The number of computing devices in the embodiment is only illustrative. Any number of computing devices may be provided according to implementation requirements.

[0211] Embodiment 2:

[0212] Continue to refer Figure 2 , shows the process 200 of the second embodiment of the method for determining the reasonable number of gas injection wells of the underground gas storage according to the present disclosure. The method can be Figure 1 The method for determining the reasonable number of gas injection wells in the underground gas storage comprises the following steps:

[0213] Step 201: Generate a gas storage numerical model of a gas well based on the acquired gas reservoir related data of the target area and based on the gas reservoir related data.

[0214] In some optional implementations, the execution subject of the method for determining the reasonable number of gas injection wells in the underground gas storage reservoir (such as Figure 1 The computing device 101 shown can be connected to the target device via a wired connection or a wireless connection, and then, based on the acquired gas reservoir-related data of the target area, a gas reservoir numerical model of the gas well is generated based on the gas reservoir-related data. Gas reservoir-related data may refer to production-related data collected during gas reservoir exploitation and subsequent processes. The gas reservoir numerical model may refer to a model set for predicting the gas injection volume of the gas reservoir. The numerical simulation model may refer to a model generated based on numerical simulation technology. The model is often referred to as a gas production prediction process. Numerical simulation is any existing or future discovered numerical simulation method for gas reservoir prediction in the prior art, and all belong to the protection scope of the present disclosure.

[0215] In some optional implementations, a gas storage numerical model is generated based on the gas reservoir related data, including: determining a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data; optimizing the gas reservoir numerical simulation model to obtain a gas storage numerical model based on production data of the target area between the gas reservoir development stage and before the reservoir is built, as well as deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir. The gas reservoir numerical simulation model may refer to a numerical simulation model determined based on production data of the gas reservoir development stage. Deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure are common technical terms in this field and will not be elaborated on here.

[0216] In some optional implementations, the gas storage reservoir numerical model can be expressed as:

[0217]

[0218] Where p represents the reservoir pressure, k represents the effective permeability, represents the deformation porosity, C f It indicates the fracture conductivity.

[0219] In some optional implementations, the deformation porosity is determined based on a preset first calculation formula, wherein the first calculation formula includes:

[0220]

[0221] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0222] In some optional implementations, the fracture conductivity is determined based on a preset second calculation formula, where the second calculation formula includes:

[0223]

[0224]

[0225] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0226] In some optional implementations, the effective permeability of the substrate is determined based on a preset third calculation formula, and the third calculation formula includes:

[0227]

[0228] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0229] It should be noted that the above-mentioned wireless connection methods may include but are not limited to 3G / 4G / 5G connection, WiFi connection, Bluetooth connection, WiMAX connection, Zigbee connection, UWB (ultra wideband) connection, and other wireless connection methods currently known or to be developed in the future.

[0230] Step 202: Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well.

[0231] In some embodiments, the above-mentioned execution subject can perform gas injection simulation according to the gas storage reservoir numerical model to calculate the effective working gas volume of the gas well. Gas injection simulation can refer to importing different data parameters into the gas storage reservoir numerical model to perform gas injection simulation test, thereby predicting gas production and further calculating the effective working gas volume of the gas well. The effective working gas volume of the gas well is a common term in this field and will not be described in detail here.

[0232] In some optional implementations, a gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including: obtaining the design upper limit pressure and the design lower limit pressure of the gas well; respectively importing the design upper limit pressure and the design lower limit pressure into the gas storage numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory; and calculating the effective working gas volume of the gas well according to the upper limit pressure inventory and the lower limit pressure inventory. The design upper limit pressure and the design lower limit pressure may refer to the preset maximum pressure that the gas storage can bear, and the minimum design pressure, respectively. Obviously, the greater the pressure, the greater the gas storage volume. The effective working gas volume can be obtained by subtracting the lower limit pressure inventory from the upper limit pressure inventory.

[0233] Step 203, determining the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor.

[0234] In some embodiments, the above-mentioned execution entity can determine the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir-related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor.

[0235] In some optional implementations, the intersection of the gas injection capacity, as well as the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor, determine the reasonable gas injection capacity corresponding to different reservoir pressures, including: selecting the maximum value from the tubing erosion flow rate and the maximum gas injection pressure of the compressor; if the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity; otherwise, the gas volume corresponding to the intersection of the gas injection capacity is determined as the reasonable gas injection capacity. The maximum value may refer to the data with the largest number between the tubing erosion flow rate and the maximum gas injection pressure of the compressor. As an example, assuming that the tubing erosion flow rate is 90 and the maximum gas injection pressure of the compressor is 100, the maximum value is 100. If the gas volume corresponding to the intersection of the gas injection capacity is 80, since 80 is less than 100, the reasonable gas injection capacity is 80. If the gas volume corresponding to the intersection of the gas injection capacity is 130, since 130 is greater than 100, the reasonable gas injection capacity is 100.

[0236] Step 204, calculating the single well control area of ​​the gas well according to the effective working gas volume, and calculating the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0237] In some embodiments, the execution entity may calculate the single-well control area of ​​the gas well according to the effective working gas volume, and calculate the reasonable number of gas injection wells in combination with the effective working gas volume, reasonable gas injection capacity and the block area of ​​the target area.

[0238] The single well control area can refer to the effective area that a single gas well can control for gas injection / production. The block area can refer to the total area related to gas storage on the horizontal plane of the target area. The reasonable number of gas injection wells can refer to the reasonable number of gas injection wells that need to be set up in the target area.

[0239] In some optional implementations, calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0240] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0241] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0242]

[0243]

[0244] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0245] The single well control area is calculated according to the single well control radius.

[0246] In some optional implementations, the reasonable number of gas injection wells is calculated based on the effective working gas volume, the reasonable gas injection capacity, and the block area of ​​the target area, including:

[0247] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0248]

[0249] Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0250] The beneficial effects of one of the implementation methods in the above-mentioned embodiments of the present disclosure include at least: generating a gas storage reservoir numerical model of the gas well based on the acquired gas reservoir-related data of the target area and based on the gas reservoir-related data; performing gas injection simulation according to the gas storage reservoir numerical model to calculate the effective working gas volume of the gas well; determining the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir-related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor; calculating the single well control area of ​​the gas well according to the effective working gas volume, and calculating the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area, so as to calculate the number of gas injection wells with high precision.

[0251] Embodiment three:

[0252] Continue to refer Figure 3 , shows a process 300 of the third embodiment of the method for determining the reasonable number of gas injection wells in the underground gas storage according to the present disclosure, which can be Figure 1 The method for determining the reasonable number of gas injection wells in the underground gas storage includes:

[0253] Step 301, based on the acquired gas reservoir related data of the target area.

[0254] Step 302: Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data.

[0255] Step 303, based on the production data of the target area from the gas reservoir development stage to before the reservoir construction, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage reservoir numerical model.

[0256] Step 304: perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well.

[0257] Step 305, determining the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor.

[0258] Step 306, calculating the single well control area of ​​the gas well according to the effective working gas volume, and calculating the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0259] In some optional implementations, the specific implementation of steps 301-306 and the technical effects brought about can be referred to Figure 2 The corresponding steps in the second embodiment are not repeated here.

[0260] All the above optional technical solutions can be combined in any way to form optional implementation methods of the present application, and will not be described in detail here.

[0261] Embodiment 4:

[0262] The following are embodiments of the device disclosed herein, which can be used to execute the method embodiments disclosed herein. For details not disclosed in the device embodiments disclosed herein, please refer to the method embodiments disclosed herein.

[0263] Further references Figure 4 As an implementation of the above methods in the above figures, the present disclosure provides an embodiment of a device for determining the reasonable number of gas injection wells in an underground gas storage reservoir. Figure 2 The above-mentioned embodiment 2 corresponds.

[0264] like Figure 4 As shown, the device 400 for determining the reasonable number of gas injection wells in an underground gas storage in this embodiment includes:

[0265] The generation module 401 is used to generate a gas storage reservoir numerical model of a gas well based on the acquired gas reservoir related data of the target area and based on the gas reservoir related data.

[0266] The first calculation module 402 is used to perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well.

[0267] Determination module 403 is used to determine the intersection of the gas injection capacity of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the intersection of the gas injection capacity, the tubing erosion flow rate of the gas well and the maximum gas injection pressure of the compressor.

[0268] The second calculation module 404 is used to calculate the single well control area of ​​the gas well according to the effective working gas volume, and calculate the reasonable number of gas injection wells in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

[0269] In some preferred implementations, generating a gas storage numerical model based on the gas reservoir related data includes:

[0270] Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data;

[0271] Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

[0272] In some preferred implementations, the deformation porosity is determined based on a preset first calculation formula, which includes:

[0273]

[0274] Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

[0275] In some preferred implementations, the fracture conductivity is determined based on a preset second calculation formula, and the second calculation formula includes:

[0276]

[0277]

[0278] Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

[0279] In some preferred implementations, the effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes:

[0280]

[0281] Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

[0282] In some preferred implementations, the first calculation module 402 is further configured to:

[0283] Obtaining a design upper limit pressure and a design lower limit pressure of the gas well;

[0284] The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory;

[0285] The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

[0286] In some preferred implementations, the gas injection capacity intersection point, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor are used to determine the reasonable gas injection capacity corresponding to different reservoir pressures, including:

[0287] Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor;

[0288] If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity;

[0289] Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

[0290] In some preferred implementations, the calculating the single well control area of ​​the gas well according to the effective working gas volume includes:

[0291] Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume;

[0292] The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes:

[0293]

[0294]

[0295] Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well;

[0296] The single well control area is calculated according to the single well control radius.

[0297] In some preferred implementations, the calculation of the reasonable number of gas injection wells based on the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area includes:

[0298] The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes:

[0299]

[0300] Among them, the Nwell represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

[0301] It is understandable that the modules described in the device 400 are similar to those described in the reference Figure 2 Therefore, the operations, features and beneficial effects described above for the method are also applicable to the device 400 and the modules contained therein, and will not be described in detail here.

[0302] Embodiment five:

[0303] like Figure 5 As shown, the electronic device 500 may include a processing device (e.g., a central processing unit, a graphics processing unit, etc.) 501, which can perform various appropriate actions and processes according to a program stored in a read-only memory (ROM) 502 or a program loaded from a storage device 508 into a random access memory (RAM) 503. In the RAM 503, various programs and data required for the operation of the electronic device 500 are also stored. The processing device 501, the ROM 502, and the RAM 503 are connected to each other via a bus 504. An input / output (I / O) interface 505 is also connected to the bus 504.

[0304] Typically, the following devices may be connected to the I / O interface 505: an input device 506 including, for example, a touch screen, a touch pad, a keyboard, a mouse, a camera, a microphone, an accelerometer, a gyroscope, etc.; an output device 507 including, for example, a liquid crystal display (LCD), a speaker, a vibrator, etc.; a storage device 508 including, for example, a magnetic tape, a hard disk, etc.; and a communication device 509. The communication device 509 may allow the electronic device 500 to communicate with other devices wirelessly or by wire to exchange data. Although Figure 5 The electronic device 500 is shown with various devices, but it should be understood that it is not required to implement or possess all the devices shown. More or fewer devices may be implemented or possessed instead. Figure 5 Each block shown in the figure may represent one device, or may represent multiple devices as required.

[0305] In particular, according to this embodiment, the process described above with reference to the flowchart can be implemented as a computer software program. For example, this embodiment includes a computer program product, which includes a computer program or instructions carried on a computer-readable medium, and the computer program or instructions contain program codes for executing the method shown in the flowchart. In this embodiment, the computer program can be downloaded and installed from the network through the communication device 509, or installed from the storage device 508, or installed from the ROM 502. When the computer program is executed by the processing device 501, it can be executed. Figure 2 The corresponding steps.

[0306] It should be noted that the computer-readable medium in the present embodiment may be a computer-readable signal medium or a computer-readable storage medium or any combination of the two. The computer-readable storage medium may be, for example, but not limited to, an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, device or device, or any combination of the above. More specific examples of computer-readable storage media may include, but are not limited to: an electrical connection with one or more wires, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the above. In the present embodiment, the computer-readable storage medium may be any tangible medium containing or storing a program that may be used by or in combination with an instruction execution system, device or device. In the present embodiment, the computer-readable signal medium may include a data signal propagated in a baseband or as part of a carrier wave, which carries a computer-readable program code. This propagated data signal may take a variety of forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination of the above. The computer readable signal medium may also be any computer readable medium other than a computer readable storage medium, which may send, propagate or transmit a program for use by or in conjunction with an instruction execution system, apparatus or device. The program code contained on the computer readable medium may be transmitted using any suitable medium, including but not limited to: wires, optical cables, RF (radio frequency), etc., or any suitable combination of the above.

[0307] In some embodiments, the client and the server may communicate using any currently known or future developed network protocol such as HTTP (HyperText Transfer Protocol), and may be interconnected with any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include a local area network ("LAN"), a wide area network ("WAN"), an internet (e.g., the Internet), and a peer-to-peer network (e.g., an ad hoc peer-to-peer network), as well as any currently known or future developed network.

[0308] The computer-readable medium may be included in the device; or it may exist independently without being installed in the electronic device. The computer-readable medium carries one or more programs. When the one or more programs are executed by the electronic device, the electronic device executes Figure 2 The corresponding steps.

[0309] The computer program code for performing the operation of the present embodiment can be written in one or more programming languages ​​or a combination thereof, including object-oriented programming languages, such as Java, Smalltalk, C++, and conventional procedural programming languages, such as "C" language or similar programming languages. The program code can be executed entirely on the user's computer, partially on the user's computer, as an independent software package, partially on the user's computer and partially on a remote computer, or entirely on a remote computer or server. In the case of a remote computer, the remote computer can be connected to the user's computer through any type of network, including a local area network (LAN) or a wide area network (WAN), or can be connected to an external computer (e.g., using an Internet service provider to connect through the Internet).

[0310] The flow chart and block diagram in the accompanying drawings illustrate the possible architecture, function and operation of the system, method and computer program product according to various embodiments of the present disclosure. In this regard, each square box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and the module, the program segment or a part of the code contains one or more executable instructions for realizing the specified logical function. It should also be noted that in some implementations as replacements, the functions marked in the square box can also occur in a sequence different from that marked in the accompanying drawings. For example, two square boxes represented in succession can actually be executed substantially in parallel, and they can sometimes be executed in the opposite order, depending on the functions involved. It should also be noted that each square box in the block diagram and / or flow chart, and the combination of the square boxes in the block diagram and / or flow chart can be implemented with a dedicated hardware-based system that performs a specified function or operation, or can be implemented with a combination of dedicated hardware and computer instructions.

[0311] The modules described in this embodiment may be implemented by software or hardware. The modules described may also be set in a processor, for example, may be described as:

[0312] A generation module, a first calculation module, a determination module, and a second calculation module. For example, the generation module can also be described as "a module for generating a gas reservoir numerical model of a gas well based on the acquired gas reservoir-related data of the target area and based on the gas reservoir-related data".

[0313] The functions described above herein may be performed at least in part by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), and the like.

[0314] The above descriptions are only some preferred embodiments of the present disclosure and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the embodiments of the present disclosure is not limited to the technical solutions formed by a specific combination of the above-mentioned technical features, but should also cover other technical solutions formed by any combination of the above-mentioned technical features or their equivalent features without departing from the above-mentioned inventive concept. For example, the above-mentioned features are replaced with the technical features with similar functions disclosed in the embodiments of the present disclosure (but not limited to) and the technical solutions formed.

Claims

1. A method for determining the reasonable number of gas injection wells in an underground gas storage, characterized in that: include: Based on the acquired gas reservoir related data of the target area, a gas storage reservoir numerical model of the gas well is generated based on the gas reservoir related data; Perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well; Determine the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determine the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor; The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area.

2. The method according to claim 1, characterized in that The generating of the gas storage numerical model based on the gas reservoir related data comprises: Determine a gas reservoir numerical simulation model based on production data of the gas reservoir development stage in the gas reservoir related data; Based on the production data of the target area between the gas reservoir development stage and before the construction of the gas storage facility, as well as the deformation porosity, fracture conductivity, matrix effective permeability and reservoir pressure of the target area reservoir, the gas reservoir numerical simulation model is optimized to obtain a gas storage facility numerical model.

3. The method according to claim 2, characterized in that The deformation porosity is determined based on a preset first calculation formula, which includes: φ=0.9303φ0(1-1.4353T-0.3715φ0 1.9653T-0.1671 ) Among them, φ0 represents the original porosity, T represents the number of injection-production cycles, and φ represents the deformed porosity.

4. The method according to claim 2, characterized in that: The fracture conductivity is determined based on a preset second calculation formula, wherein the second calculation formula includes: Among them, C f represents the fracture conductivity when the fracture is closed, C fi represents the fracture conductivity at the initial moment, γ represents the permeability correction coefficient, and p i represents the overlying formation pressure, and p represents the formation pressure.

5. The method according to claim 2, characterized in that: The effective permeability of the matrix is ​​determined based on a preset third calculation formula, and the third calculation formula includes: Where b is the permeability correction factor, k0 is the original permeability, and p i represents the overlying formation pressure, p represents the formation pressure, and k represents the effective permeability of the matrix considering stress sensitivity.

6. The method according to claim 2, characterized in that The gas injection simulation is performed according to the gas storage numerical model to calculate the effective working gas volume of the gas well, including: Obtaining a design upper limit pressure and a design lower limit pressure of the gas well; The design upper limit pressure and the design lower limit pressure are respectively introduced into the gas storage reservoir numerical model to obtain the upper limit pressure inventory and the lower limit pressure inventory; The effective working gas volume of the gas well is calculated according to the upper limit pressure inventory volume and the lower limit pressure inventory volume.

7. The method according to claim 1, characterized in that Based on the intersection of the gas injection capacity, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor, the reasonable gas injection capacity corresponding to different reservoir pressures is determined, including: Filter out the maximum value from the string erosion flow rate and the maximum gas injection pressure of the compressor; If the gas volume corresponding to the intersection of the gas injection capacity is greater than the maximum value, the maximum value is determined as the reasonable gas injection capacity; Otherwise, the gas volume corresponding to the intersection of the gas injection capacities is determined as the reasonable gas injection capacity.

8. The method according to claim 2, characterized in that: The calculating of the single well control area of ​​the gas well according to the effective working gas volume comprises: Obtaining the single-well controlled storage capacity of the gas well in the gas reservoir-related data, and calculating the effective gas volume ratio in combination with the effective working gas volume; The single well control radius of the gas well is calculated according to the effective gas volume ratio, the single well control storage capacity, the gas well gas production time, reserve abundance, gas well allocation production in the gas reservoir related data, and a preset fourth calculation formula, wherein the fourth calculation formula includes: Where T represents the gas extraction time, q sc represents the gas well production allocation, E g Indicates the effective gas volume ratio, N s represents the controlled storage capacity of a single well, R represents the reserve abundance, and r represents the controlled radius of a single well; The single well control area is calculated according to the single well control radius.

9. The method according to claim 2, characterized in that: The calculating of the reasonable number of gas injection wells by combining the effective working gas volume, the reasonable gas injection capacity and the block area of ​​the target area comprises: The single well control area of ​​the gas well is calculated according to the effective working gas volume, and the reasonable number of gas injection wells is calculated in combination with the effective working gas volume, the reasonable gas injection capacity, the block area of ​​the target area and the preset fifth calculation formula, wherein the fifth calculation formula includes: Among them, the N well represents the reasonable number of gas injection wells, and A represents the controlled area of ​​a single well.

10. A device for determining the reasonable number of gas injection wells in an underground gas storage, characterized in that: include: A generation module, for generating a gas storage reservoir numerical model of a gas well based on the acquired gas reservoir related data of the target area and based on the gas reservoir related data; A first calculation module is used to perform gas injection simulation according to the gas storage numerical model to calculate the effective working gas volume of the gas well; A determination module, for determining the gas injection capacity intersection of the gas well according to the gas flow inflow curve and the gas flow outflow curve of the gas well in the gas reservoir related data, and determining the reasonable gas injection capacity corresponding to different reservoir pressures based on the gas injection capacity intersection, the pipe erosion flow rate of the gas well and the maximum gas injection pressure of the compressor; The second calculation module is used to calculate the single well control area of ​​the gas well according to the effective working gas volume, and calculate the reasonable number of gas injection wells in combination with the effective working gas volume, reasonable gas injection capacity and the block area of ​​the target area.

11. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method according to any one of claims 1 to 9 are implemented.

12. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method according to any one of claims 1 to 9 are implemented.

13. A computer program product, comprising a computer program or instructions, characterized in that: When the computer program or instruction is executed by a processor, the steps of the method according to any one of claims 1 to 9 are implemented.