Cultivated land quality investigation monitoring method and system

By constructing and dividing monitoring points on the cultivated land area plan, and combining the sensitive label matching model with organic matter content and sunshine duration data, the problem of inconsistent monitoring point settings is solved and the accuracy and efficiency of cultivated land quality evaluation are improved.

CN118735334APending Publication Date: 2024-10-01SICHUAN ZHONGTU TESTING & INSPECTION CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410784896.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-18
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the existing cultivated land quality monitoring, there is a lack of unified standards for the setting of monitoring points, which leads to inconsistent quality evaluation of different cultivated land area plans, affecting accuracy.

Method used

By obtaining the regional plan of the target farmland, construct a square primary selection frame and divide it into sub-selection frames, set the diagonal intersection points of the sub-selection frames as monitoring points, obtain data on organic matter content and sunshine duration, establish a sensitive label matching model, and conduct quality control Evaluate.

Benefits of technology

The automatic setting of target cultivated land monitoring points is realized, which improves the accuracy and efficiency of cultivated land quality evaluation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735334A_ABST
    Figure CN118735334A_ABST
Patent Text Reader

Abstract

The invention provides a cultivated land quality investigation monitoring method and system. The method comprises the following steps: acquiring a region planar graph of a target cultivated land; a primary selection box is constructed on the area planar graph, and the primary selection box is square; according to a preset division rule, dividing the primary selection box into a plurality of sub-selection boxes; setting the cross point of the opposite angles of each sub-selection box as a monitoring point; acquiring quality monitoring data of all monitoring points, wherein the quality monitoring data comprises organic matter content and sunshine duration; setting a sensitive label about the organic matter content and a sensitive label about the sunshine duration; matching the sensitive label of the organic matter content and the sensitive label of the sunshine duration with the organic matter content and the sunshine duration, establishing a cultivated land quality evaluation model, and scoring the quality monitoring data of the target cultivated land to obtain a scoring result; the monitoring points of the target cultivated land can be automatically set, and the accuracy of quality evaluation of the target cultivated land is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cultivated land quality monitoring, and in particular to a cultivated land quality investigation and monitoring method and system. Background Art

[0002] In the existing arable land quality monitoring, the monitoring points are generally set according to the arable land area plan. The setting of monitoring points is usually arbitrarily set by humans, and there is no unified standard for selecting monitoring points, which will have a certain impact on the arable land quality evaluation of different arable land area plans. Summary of the invention

[0003] In response to the above-mentioned problems, this application proposes a method and system for investigating and monitoring the quality of cultivated land, which can realize the automatic setting of monitoring points of the target cultivated land and improve the accuracy of the quality evaluation of the target cultivated land.

[0004] The present application embodiment provides a monitoring method,

[0005] This application provides a method for investigating and monitoring cultivated land quality, including:

[0006] Obtain a regional plan of the target cultivated land;

[0007] Constructing a preliminary selection box on the regional plan, wherein the preliminary selection box is a square;

[0008] Divide the primary selection box into multiple sub-selection boxes according to a preset division rule;

[0009] Set the intersection of the diagonal corners of each sub-selection box as the monitoring point;

[0010] Obtain the quality monitoring data of all monitoring points, including the organic matter content E 测 and sunshine duration T 测 ;

[0011] Set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels;

[0012] The organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.

[0013] In some embodiments, the constructing of a preliminary selection box on the regional plan, wherein the preliminary selection box is a square, includes:

[0014] constructing a foundation frame on the regional plan;

[0015] Adjust the angle of the basic frame so that the length direction and width direction of the basic frame are consistent with the length direction and width direction of the regional plan;

[0016] The length and width of the basic frame are adjusted until the area of ​​the basic frame reaches the maximum area, and the basic frame with the maximum area is used as the primary selection frame.

[0017] In some embodiments, dividing the primary selection box into a plurality of sub-selection boxes according to a preset division rule includes:

[0018] Divide the primary selection box into multiple sub-selection boxes along the length direction of the primary selection box, or

[0019] The primary selection box is divided into a plurality of sub-selection boxes along the width direction of the primary selection box.

[0020] In some embodiments, the area of ​​each of the sub-selection boxes is the same.

[0021] In some embodiments, the quality monitoring data of all monitoring points are obtained, and the quality monitoring data includes organic matter content E 测 and sunshine duration T 测 ,include:

[0022] Obtain the time series organic matter content data set (E 1 ,E 2 ...E n );

[0023] According to the matrix content data group (E 1 ,E 2 ...E n ), calculate the average organic matter content E n is the matrix content of the nth monitoring point, is the average organic matter content of the mth monitoring point;

[0024] Repeat the above steps to calculate the average organic matter content of all monitoring points and obtain the corresponding data set

[0025] According to the data group Calculate the organic matter content of quality monitoring data

[0026]

[0027] Get the data set of sunshine duration at the monitoring point (T 1 ,T 2 ...T n ), Tn is the nth sunshine duration at the monitoring point;

[0028] According to the data set of sunshine duration (T 1 ,T 2 ...T n ), calculate the average sunshine duration is the average sunshine duration of the mth monitoring point;

[0029] Repeat the above steps to calculate the average sunshine duration of all monitoring points and obtain the corresponding data set

[0030] According to the data group Calculate the sunshine duration for quality monitoring data

[0031] In some embodiments, the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is performed, a farmland quality assessment model is established, and the quality monitoring data of the target farmland is scored to obtain the scoring results, including:

[0032] Utilize organic matter content E 测 The sensitive label matches the organic matter content E of the target cultivated land. 测 , and the organic matter content E of the target cultivated land 测 To give a score;

[0033] Organic matter content E 测 The sensitive label is the range of organic matter content: [0, 0.6%], (0.6%, 1%], (1%, 2%], (2%, 3%], (3%, 4%], (4%, +∞);

[0034] The scoring standards for different ranges of organic matter content are: [0, 0.6%] = n, (0.6%, 1%] = N + 1, (1%, 2%] = N + 2, (2%, 3%] = N + 3, (3%, 4%] = N + 4, (4%, + ∞) = N + 5;

[0035] The organic matter content E of the target cultivated land 测 Compared with the range of each organic matter content, according to the organic matter content E 测 The range of organic matter content falls into, and the corresponding score a is output;

[0036] Use sunshine duration T 测 The sensitive label matches the sunshine duration T of the target farmland. 测, and the sunshine duration T of the target cultivated land 测 To give a score;

[0037] Sunshine duration T 测 The sensitive label is the range of sunshine duration: [0,3.8]h, (3.8,6]h, (6,8.2]h, (8.2,8.5]h, (8.5,+∞]h;

[0038] The scoring criteria for different sunshine duration ranges are: [0,3.8]h=N, (3.8,6]h=N+1, (6,8.2]h=N+2, (8.2,8.5]h=N+3, (8.5,+∞]h=N+4;

[0039] The sunshine duration T of the target cultivated land 测 Compared with the range of each sunshine duration, according to the sunshine duration T 测 The range of sunshine duration falls into, and the corresponding score b is output;

[0040] Construct a farmland quality assessment model, score the soil environment data of the target farmland, and obtain the scoring results;

[0041] The arable land quality assessment model is:

[0042]

[0043] In the formula, α 1 , α 2 The organic matter content E 测 and sunshine duration T 测 The weight coefficient of M is the scoring result of the target cultivated land.

[0044] The present application provides a farmland quality survey and monitoring system, comprising:

[0045] The first acquisition module is used to acquire a regional plan of the target cultivated land;

[0046] A construction module, used to construct a preliminary selection box on the regional plan, wherein the preliminary selection box is a square;

[0047] A division module, used to divide the primary selection box into multiple sub-selection boxes according to a preset division rule;

[0048] A setting module, used for setting the intersection of the diagonal corners of each sub-selection box as a monitoring point;

[0049] The second acquisition module is used to obtain the quality monitoring data of all monitoring points, and the quality monitoring data includes the organic matter content E 测 and sunshine duration T 测 ;

[0050] Setting module, used to set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels;

[0051] Evaluation module for the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.

[0052] The present application provides a method and system for investigating and monitoring the quality of cultivated land, which obtains a regional plan of the target cultivated land; constructs a preliminary selection frame on the regional plan, wherein the preliminary selection frame is a square; divides the preliminary selection frame into a plurality of sub-selection frames according to a preset division rule; sets the intersection of the diagonal corners of each sub-selection frame as a monitoring point; obtains the quality monitoring data of all monitoring points, wherein the quality monitoring data includes the organic matter content E 测 and sunshine duration T 测 ; Set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label of organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained; the automatic setting of the monitoring points of the target farmland can be realized, and the accuracy of the quality assessment of the target farmland can be improved. BRIEF DESCRIPTION OF THE DRAWINGS

[0053] Hereinafter, the present application will be described in more detail based on embodiments and with reference to the accompanying drawings.

[0054] Figure 1 A schematic diagram of the implementation flow of the cultivated land quality survey and monitoring method provided in the embodiment of the present application;

[0055] Figure 2 A schematic diagram of the structure of the farmland quality survey and monitoring system provided in the embodiment of the present application;

[0056] Figure 3 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application.

[0057] In the drawings, the same reference numerals are used for the same components, and the drawings are not drawn to scale. DETAILED DESCRIPTION

[0058] In order to make the purpose, technical solutions and advantages of the present application clearer, the present application will be further described in detail below in conjunction with the accompanying drawings. The described embodiments should not be regarded as limiting the present application. All other embodiments obtained by ordinary technicians in the field without making creative work are within the scope of protection of this application.

[0059] In the following description, reference is made to “some embodiments”, which describe a subset of all possible embodiments, but it will be understood that “some embodiments” may be the same subset or different subsets of all possible embodiments and may be combined with each other without conflict.

[0060] If similar descriptions of "first\second\third" appear in the application documents, the following instructions will be added. In the following description, the terms "first\second\third" involved are merely used to distinguish similar objects and do not represent a specific ordering of the objects. It can be understood that "first\second\third" can be interchanged in a specific order or sequence where permitted, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.

[0061] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein are only for the purpose of describing the embodiments of this application and are not intended to limit this application.

[0062] Based on the problems existing in the related art, the embodiment of the present application provides a method for investigating and monitoring the quality of cultivated land, and the execution subject of the monitoring method can be an electronic device. The electronic device can be various types of terminals such as a laptop computer, a tablet computer, a desktop computer, a set-top box, a mobile device (for example, a mobile phone, a portable music player, a personal digital assistant, a dedicated messaging device, a portable gaming device), and can also be implemented as a server. The server can be an independent physical server, or a server cluster or a distributed system composed of multiple physical servers, or a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, content delivery networks (Content Delivery Network, CDN), and big data and artificial intelligence platforms.

[0063] In some embodiments, the functions implemented by the monitoring method provided in the embodiments of the present application can be implemented by calling program codes by a processor of an electronic device, wherein the program codes can be stored in a computer storage medium.

[0064] The present application embodiment provides a method for investigating and monitoring the quality of cultivated land. Figure 1A schematic diagram of the implementation flow of the cultivated land quality survey and monitoring method provided in the embodiment of the present application is shown in FIG. Figure 1 As shown, including:

[0065] Step S1: Obtain a regional plan of the target cultivated land;

[0066] In an embodiment of the present application, the regional plan map of the target cultivated land can be obtained by remote sensing technology to obtain high-precision image data of the target cultivated land. The remote sensing technology can use satellite images or images taken by drones and use the image data as the regional plan map.

[0067] Step S2: constructing a preliminary selection box on the regional plan, wherein the preliminary selection box is a square;

[0068] In some embodiments, the step S2 comprises:

[0069] Step S21: constructing a basic frame on the regional plan;

[0070] Step S22: adjusting the angle of the basic frame so that the length direction and the width direction of the basic frame are consistent with the length direction and the width direction of the regional plan view;

[0071] Step S23: adjusting the length and width of the basic frame until the area of ​​the basic frame reaches the maximum area, and taking the basic frame with the maximum area as the primary selection frame.

[0072] In the embodiment of the present application, the basic frame with the largest area is used as the primary selection frame to disperse various monitoring points.

[0073] Step S3: dividing the primary selection box into multiple sub-selection boxes according to a preset division rule;

[0074] In some embodiments, step S3 includes:

[0075] Step S31: Divide the primary selection box into multiple sub-selection boxes along the length direction of the primary selection box, or

[0076] The primary selection box is divided into a plurality of sub-selection boxes along the width direction of the primary selection box.

[0077] In some embodiments, the area of ​​each of the sub-selection boxes is the same.

[0078] Step S4: setting the intersection of the diagonal corners of each sub-selection box as a monitoring point;

[0079] In the embodiment of the present application, the intersection of the diagonals of each sub-selection box is set as a monitoring point, which can ensure that there is a sufficient distance between each monitoring point.

[0080] Step S5: Obtain quality monitoring data of all monitoring points, the quality monitoring data including organic matter content E 测 and sunshine duration T 测 ;

[0081] In some embodiments, step S5 includes:

[0082] Step S51: Obtaining a time series data set of organic matter content (E 1 ,E 2 ...E n );

[0083] Step S52: According to the matrix content data group (E 1 ,E 2 ...E n ), calculate the average organic matter content E n is the matrix content of the nth monitoring point, is the average organic matter content of the mth monitoring point;

[0084] Repeat steps S51-S52 to calculate the average organic matter content of all monitoring points and obtain the corresponding data set

[0085] Step S53: According to the data group Calculate the organic matter content of quality monitoring data

[0086]

[0087] Step S54: Obtain the data set of sunshine duration at the monitoring point (T 1 ,T 2 ...T n ), T n is the nth sunshine duration at the monitoring point;

[0088] Step S55: Based on the data set of sunshine duration (T 1 ,T 2 ...T n ), calculate the average sunshine duration is the average sunshine duration of the mth monitoring point;

[0089] Repeat steps S54-S55 to calculate the average sunshine duration of all monitoring points and obtain the corresponding data set

[0090] Step S56: According to the data group Calculate the sunshine duration for quality monitoring data

[0091]

[0092] Step S6: Setting the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels;

[0093] Step S7: The organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.

[0094] In some embodiments, the step S7 includes:

[0095] Step S71: Using the organic matter content E 测 The sensitive label matches the organic matter content E of the target cultivated land. 测 , and the organic matter content E of the target cultivated land 测 To give a score;

[0096] Organic matter content E 测 The sensitive label is the range of organic matter content: [0, 0.6%], (0.6%, 1%], (1%, 2%], (2%, 3%], (3%, 4%], (4%, +∞);

[0097] The scoring standards for different ranges of organic matter content are: [0, 0.6%] = n, (0.6%, 1%] = N + 1, (1%, 2%] = N + 2, (2%, 3%] = N + 3, (3%, 4%] = N + 4, (4%, + ∞) = N + 5;

[0098] Step S72: The organic matter content E of the target cultivated land 测 Compared with the range of each organic matter content, according to the organic matter content E 测 The range of organic matter content falls into, and the corresponding score a is output;

[0099] Step S73: Using the sunshine duration T 测 The sensitive label matches the sunshine duration T of the target farmland. 测 , and the sunshine duration T of the target cultivated land 测 To give a score;

[0100] Sunshine duration T 测 The sensitive label is the range of sunshine duration: [0,3.8]h, (3.8,6]h, (6,8.2]h, (8.2,8.5]h, (8.5,+∞]h;

[0101] The scoring criteria for different sunshine duration ranges are: [0,3.8]h=N, (3.8,6]h=N+1, (6,8.2]h=N+2, (8.2,8.5]h=N+3, (8.5,+∞]h=N+4;

[0102] Step S74: The sunshine duration T of the target cultivated land is 测 Compared with the range of each sunshine duration, according to the sunshine duration T 测 The range of sunshine duration falls into, and the corresponding score b is output;

[0103] Step S75: constructing a farmland quality assessment model, scoring the soil environment data of the target farmland, and obtaining a scoring result;

[0104] The arable land quality assessment model is:

[0105]

[0106] In the formula, α 1 , α 2 The organic matter content E 测 and sunshine duration T 测 The weight coefficient of M is the scoring result of the target cultivated land.

[0107] In summary, by obtaining a regional plan of the target cultivated land; constructing a preliminary selection frame on the regional plan, wherein the preliminary selection frame is a square; dividing the preliminary selection frame into a plurality of sub-selection frames according to a preset division rule; setting the intersection of the diagonal corners of each sub-selection frame as a monitoring point; obtaining the quality monitoring data of all monitoring points, wherein the quality monitoring data includes the organic matter content E 测 and sunshine duration T 测 ; Set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label of organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a arable land quality assessment model is established, the quality monitoring data of the target arable land is scored, and the scoring results are obtained; the automatic setting of monitoring points of the target arable land can be realized, and the accuracy of the quality evaluation of the target arable land can be improved; the quality monitoring data is scored through the arable land quality assessment model, which can efficiently and accurately evaluate the quality of the target arable land.

[0108] Based on the foregoing embodiments, the embodiments of the present application provide a farmland quality investigation and monitoring system, wherein the modules included in the system and the units included in each module can be implemented by a processor in a computer device; of course, they can also be implemented by a specific logic circuit; in the implementation process, the processor can be a central processing unit (CPU, Central Processing Unit), a microprocessor (MPU, Microprocessor Unit), a digital signal processor (DSP, Digital Signal Processing) or a field programmable gate array (FPGA, Field Programmable Gate Array), etc.

[0109] The present application embodiment provides a system for investigating and monitoring farmland quality. Figure 2 The structural diagram of the cultivated land quality investigation and monitoring system provided in the embodiment of the present application is as follows: Figure 2 As shown, including:

[0110] The first acquisition module is used to acquire a regional plan of the target cultivated land;

[0111] A construction module, used to construct a preliminary selection box on the regional plan, wherein the preliminary selection box is a square;

[0112] A division module, used to divide the primary selection box into multiple sub-selection boxes according to a preset division rule;

[0113] A setting module, used for setting the intersection of the diagonal corners of each sub-selection box as a monitoring point;

[0114] The second acquisition module is used to obtain the quality monitoring data of all monitoring points, and the quality monitoring data includes the organic matter content E 测 and sunshine duration T 测 ;

[0115] Setting module, used to set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels;

[0116] Evaluation module for the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.

[0117] In some embodiments, the building blocks include:

[0118] A first construction unit is used to construct a basic frame on the regional plan;

[0119] A first adjustment unit is used to adjust the angle of the basic frame so that the length direction and the width direction of the basic frame are consistent with the length direction and the width direction of the regional plan view;

[0120] The second adjustment unit is used to adjust the length and width of the basic frame until the area of ​​the basic frame reaches a maximum area, and use the basic frame with the maximum area as a primary selection frame.

[0121] In some embodiments, the partitioning module includes:

[0122] a dividing unit, configured to divide the primary selection box into a plurality of sub-selection boxes along the length direction of the primary selection box, or

[0123] The primary selection box is divided into a plurality of sub-selection boxes along the width direction of the primary selection box.

[0124] In some embodiments, the area of ​​each of the sub-selection boxes is the same.

[0125] In some embodiments, the second acquisition module includes:

[0126] The first acquisition unit is used to acquire the time series organic matter content data group (E 1 ,E 2 ...E n );

[0127] The first calculation unit is used to calculate the matrix content data set (E 1 ,E 2 ...E n ), calculate the average organic matter content E n is the matrix content of the nth monitoring point, is the average organic matter content of the mth monitoring point;

[0128] Repeat the above steps to calculate the average organic matter content of all monitoring points and obtain the corresponding data set

[0129] The second computing unit is used to calculate the Calculate the organic matter content of quality monitoring data

[0130] The second acquisition unit is used to acquire the data group (T 1 ,T 2 ...T n ), T n is the nth sunshine duration at the monitoring point;

[0131] The third calculation unit is used to calculate the sunshine duration data group (T 1 ,T 2 ...T n ), calculate the average sunshine duration is the average sunshine duration of the mth monitoring point;

[0132] Repeat the above steps to calculate the average sunshine duration of all monitoring points and obtain the corresponding data set

[0133] The fourth computing unit is used to calculate the Calculate the sunshine duration for quality monitoring data

[0134] In some embodiments, the evaluation module comprises:

[0135] The first scoring unit is used to use the organic matter content E 测 The sensitive label matches the organic matter content E of the target cultivated land. 测 , and the organic matter content E of the target cultivated land 测 To give a score;

[0136] Organic matter content E 测 The sensitive label is the range of organic matter content: [0, 0.6%], (0.6%, 1%], (1%, 2%], (2%, 3%], (3%, 4%], (4%, +∞);

[0137] The scoring standards for different ranges of organic matter content are: [0, 0.6%] = N, (0.6%, 1%] = N + 1, (1%, 2%] = N + 2, (2%, 3%] = N + 3, (3%, 4%] = N + 4, (4%, +∞) = N + 5;

[0138] The first comparison unit is used to compare the organic matter content E of the target cultivated land. 测 Compared with the range of each organic matter content, according to the organic matter content E 测 The range of organic matter content falls into, and the corresponding score a is output;

[0139] The second scoring unit is used to use the sunshine duration T 测 The sensitive label matches the sunshine duration T of the target farmland. 测 , and the sunshine duration T of the target cultivated land 测 To give a score;

[0140] Sunshine duration T 测The sensitive label is the range of sunshine duration: [0,3.8]h, (3.8,6]h, (6,8.2]h, (8.2,8.5]h, (8.5,+∞]h;

[0141] The scoring criteria for different sunshine duration ranges are: [0,3.8]h=N, (3.8,6]h=N+1, (6,8.2]h=N+2, (8.2,8.5]h=N+3, (8.5,+∞]h=N+4;

[0142] The second comparison unit is used to compare the sunshine duration T of the target cultivated land. 测 Compared with the range of each sunshine duration, according to the sunshine duration T 测 The range of sunshine duration falls into, and the corresponding score b is output;

[0143] The second construction unit is used to construct a farmland quality assessment model, score the soil environment data of the target farmland, and obtain a scoring result;

[0144] The arable land quality assessment model is:

[0145]

[0146] In the formula, α 1 , α 2 The organic matter content E 测 and sunshine duration T 测 The weight coefficient of M is the scoring result of the target cultivated land.

[0147] It should be noted that in the embodiment of the present application, if the above-mentioned monitoring method is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. Based on such an understanding, the technical solution of the embodiment of the present application is essentially or the part that contributes to the prior art can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including several instructions to enable a computer device (which can be a personal computer, a server, or a network device, etc.) to execute all or part of the methods described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as a U disk, a mobile hard disk, a read-only memory (ROM, Read Only Memory), a disk or an optical disk. In this way, the embodiment of the present application is not limited to any specific combination of hardware and software.

[0148] Accordingly, an embodiment of the present application provides a storage medium on which a computer program is stored, characterized in that when the computer program is executed by a processor, the steps in the monitoring method provided in the above embodiment are implemented.

[0149] An embodiment of the present application provides an electronic device; Figure 3 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application is shown in FIG. Figure 3 As shown, the electronic device 400 includes: a processor 401, at least one communication bus 402, a user interface 403, at least one external communication interface 404, and a memory 405. The communication bus 402 is configured to realize the connection and communication between these components. The user interface 403 may include a display screen, and the external communication interface 404 may include a standard wired interface and a wireless interface. The processor 401 is configured to execute the program of the monitoring method stored in the memory to implement the steps in the monitoring method provided in the above embodiment.

[0150] It should be noted here that the description of the above storage medium and electronic device embodiments is similar to the description of the above method embodiments, and has similar beneficial effects as the method embodiments. For technical details not disclosed in the storage medium and device embodiments of this application, please refer to the description of the method embodiments of this application for understanding.

[0151] It should be understood that "one embodiment" or "an embodiment" mentioned throughout the specification means that specific features, structures or characteristics related to the embodiment are included in at least one embodiment of the present application. Therefore, "in one embodiment" or "in an embodiment" appearing throughout the specification does not necessarily refer to the same embodiment. In addition, these specific features, structures or characteristics can be combined in one or more embodiments in any suitable manner. It should be understood that in various embodiments of the present application, the size of the sequence number of the above-mentioned processes does not mean the order of execution, and the execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application. The above-mentioned sequence numbers of the embodiments of the present application are only for description and do not represent the advantages and disadvantages of the embodiments.

[0152] It should be noted that, in this article, the terms "include", "comprises" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, object or device including a series of elements includes not only those elements, but also includes other elements not explicitly listed, or also includes elements inherent to such process, method, object or device. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the existence of other identical elements in the process, method, object or device including the element.

[0153] In the several embodiments provided in the present application, it should be understood that the disclosed devices and methods can be implemented in other ways. The device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as: multiple units or components can be combined, or can be integrated into another system, or some features can be ignored or not executed. In addition, the coupling, direct coupling, or communication connection between the components shown or discussed can be through some interfaces, and the indirect coupling or communication connection of the devices or units can be electrical, mechanical or other forms.

[0154] The units described above as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units; they may be located in one place or distributed on multiple network units; some or all of the units may be selected according to actual needs to achieve the purpose of the present embodiment.

[0155] In addition, all functional units in the embodiments of the present application may be integrated into one processing unit, or each unit may be a separate unit, or two or more units may be integrated into one unit; the above-mentioned integrated units may be implemented in the form of hardware or in the form of hardware plus software functional units.

[0156] A person of ordinary skill in the art can understand that: all or part of the steps of implementing the above-mentioned method embodiment can be completed by hardware related to program instructions, and the aforementioned program can be stored in a computer-readable storage medium. When the program is executed, it executes the steps of the above-mentioned method embodiment; and the aforementioned storage medium includes: mobile storage devices, read-only memories (ROM, Read Only Memory), disks or optical disks, etc. Various media that can store program codes.

[0157] Alternatively, if the above-mentioned integrated unit of the present application is implemented in the form of a software function module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the embodiment of the present application can essentially or in other words, the part that contributes to the prior art can be embodied in the form of a software product, which is stored in a storage medium and includes a number of instructions for a controller to execute all or part of the methods described in each embodiment of the present application. The aforementioned storage medium includes: various media that can store program codes, such as mobile storage devices, ROMs, magnetic disks, or optical disks.

[0158] The above is only an implementation method of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A method for investigating and monitoring cultivated land quality, characterized in that: include: Obtain a regional plan of the target cultivated land; Constructing a preliminary selection box on the regional plan, wherein the preliminary selection box is a square; Divide the primary selection box into multiple sub-selection boxes according to a preset division rule; Set the intersection of the diagonal corners of each sub-selection box as the monitoring point; Obtain the quality monitoring data of all monitoring points, including the organic matter content E 测 and sunshine duration T 测 ; Set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels; The organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.

2. The method for investigating and monitoring cultivated land quality according to claim 1, characterized in that: The preliminary selection box is constructed on the regional plan, wherein the preliminary selection box is a square and includes: constructing a foundation frame on the regional plan; Adjusting the angle of the basic frame so that the length direction and the width direction of the basic frame are consistent with the length direction and the width direction of the regional plan; The length and width of the basic frame are adjusted until the area of ​​the basic frame reaches the maximum area, and the basic frame with the maximum area is used as the primary selection frame.

3. The method for investigating and monitoring cultivated land quality according to claim 1, characterized in that: The primary selection box is divided into a plurality of sub-selection boxes according to a preset division rule, including: Divide the primary selection box into multiple sub-selection boxes along the length direction of the primary selection box, or The primary selection box is divided into a plurality of sub-selection boxes along the width direction of the primary selection box.

4. The method for investigating and monitoring cultivated land quality according to claim 3, characterized in that: The area of ​​each of the sub-selection boxes is the same.

5. The method for investigating and monitoring cultivated land quality according to claim 1, characterized in that: The quality monitoring data of all monitoring points are obtained, and the quality monitoring data includes organic matter content E 测 and sunshine duration T 测 ,include: Obtain the time series organic matter content data set (E1, E2...E n ); According to the matrix content data group (E1, E2...E n ), calculate the average organic matter content E n is the matrix content of the nth monitoring point, is the average organic matter content of the mth monitoring point; Repeat the above steps to calculate the average organic matter content of all monitoring points and obtain the corresponding data set According to the data group Calculate the organic matter content of quality monitoring data Get the data set of sunshine duration at the monitoring point (T1, T2...T n ), T n is the nth sunshine duration at the monitoring point; According to the data set of sunshine duration (T1, T2...T n ), calculate the average sunshine duration is the average sunshine duration of the mth monitoring point; Repeat the above steps to calculate the average sunshine duration of all monitoring points and obtain the corresponding data set According to the data group Calculate the sunshine duration for quality monitoring data 6. The method for investigating and monitoring cultivated land quality according to claim 5, characterized in that: The organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is performed, a farmland quality assessment model is established, and the quality monitoring data of the target farmland is scored to obtain the scoring results, including: Utilize organic matter content E 测 The sensitive label matches the organic matter content E of the target cultivated land. 测 , and the organic matter content E of the target cultivated land 测 To give a score; Organic matter content E 测 The sensitive label is the range of organic matter content: [0, 0.6%], (0.6%, 1%], (1%, 2%], (2%, 3%], (3%, 4%], (4%, +∞); The scoring standards for different ranges of organic matter content are: [0, 0.6%] = n, (0.6%, 1%] = N + 1, (1%, 2%] = N + 2, (2%, 3%] = N + 3, (3%, 4%] = N + 4, (4%, + ∞) = N + 5; The organic matter content E of the target cultivated land 测 Compared with the range of each organic matter content, according to the organic matter content E 测 The range of organic matter content falls into, and the corresponding score a is output; Use sunshine duration T 测 The sensitive label matches the sunshine duration T of the target farmland. 测 , and the sunshine duration T of the target cultivated land 测 To give a score; Sunshine duration T 测 The sensitive label is the range of sunshine duration: [0,3.8]h, (3.8,6]h, (6,8.2]h, (8.2,8.5]h, (8.5,+∞]h; The scoring criteria for different sunshine duration ranges are: [0,3.8]h=N, (3.8,6]h=N+1, (6,8.2]h=N+2, (8.2,8.5]h=N+3, (8.5,+∞]h=N+4; The sunshine duration T of the target cultivated land 测 Compared with the range of each sunshine duration, according to the sunshine duration T 测 The range of sunshine duration falls into, and the corresponding score b is output; Construct a farmland quality assessment model, score the soil environment data of the target farmland, and obtain the scoring results; The arable land quality assessment model is: In the formula, α1 and α2 are respectively the organic matter content E 测 and sunshine duration T 测 The weight coefficient of M is the scoring result of the target cultivated land.

7. A system for investigating and monitoring cultivated land quality, characterized in that: include: The first acquisition module is used to acquire a regional plan of the target cultivated land; A construction module, used to construct a preliminary selection box on the regional plan, wherein the preliminary selection box is a square; A division module, used to divide the primary selection box into multiple sub-selection boxes according to a preset division rule; A setting module, used for setting the intersection of the diagonal corners of each sub-selection box as a monitoring point; The second acquisition module is used to obtain the quality monitoring data of all monitoring points, and the quality monitoring data includes the organic matter content E 测 and sunshine duration T 测 ; Setting module, used to set the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive labels; Evaluation module for the organic matter content E 测 Sensitive labels and sunshine duration T 测 Sensitive label and organic matter content E 测 and sunshine duration T 测 Matching is carried out, a farmland quality assessment model is established, the quality monitoring data of the target farmland is scored, and the scoring results are obtained.