Power grid project contract performance management system and method

Through the design of the power grid project contract performance management system, the problem of inconvenient query of contract performance information in power grid operation management is solved, digital management of contract performance is realized, the analysis and processing capabilities of the dedicated performance team are improved, and the comprehensiveness and timeliness of the information are ensured. sex.

CN118735480AInactive Publication Date: 2024-10-01STATE GRID SHANGHAI MUNICIPAL ELECTRIC POWER CO +1
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202310342691.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-10-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

In power grid operation management, the query and statistics of information related to the entire chain of project materials rely on offline manual matching of different systems, resulting in inconvenient information query and incomplete data, making it difficult to achieve effective contract performance management.

Method used

Design a power grid project contract performance management system, including a supply chain performance management module, a project performance management module, an exception monitoring module, a contract performance time monitoring module, an early warning module and a suggestion module. By acquiring and monitoring supply chain and project data, early warnings can be set Rules and risk plans to achieve digital management of contract performance.

Benefits of technology

It has realized the monitoring and management of contract performance from different perspectives, improved the digital management capabilities of contract performance, ensured the comprehensiveness and timeliness of information, timely warning and triggering of risk plans, and improved the analysis and processing capabilities of dedicated contract performance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735480A_ABST
    Figure CN118735480A_ABST
Patent Text Reader

Abstract

The invention relates to a power grid project contract fulfillment management system and method, and the system comprises a supply chain fulfillment management module which obtains supply chain nodes related to contract fulfillment from supply chain data; the project fulfillment management module is used for acquiring project stages related to contract fulfillment in the full life cycle of the project; the first abnormity monitoring module is used for monitoring whether the supply chain node related to contract performance is abnormal or not; the second abnormity monitoring module is used for monitoring whether the execution progress of the project stage related to contract performance is abnormal or not; the contract fulfillment time monitoring module is used for combing time nodes in contract fulfillment and fulfillment content corresponding to each time node, and judging whether the fulfillment content is completed or not when the current time reaches the time node; and the early warning module is used for sending out corresponding early warning information after the early warning rule is triggered. Compared with the prior art, in combination with the supply chain node and the project stage, contract fulfillment is monitored and managed from different perspectives, and digital management of contract fulfillment is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid performance management, and in particular to a power grid project contract performance management system and method. Background Art

[0002] At present, a unified material management system has been established in the operation and management of power grids, including complete processes, systems and various operating instructions, which can realize the digitalization and intelligence of material management. However, the current query and statistics work of the planning and performance specialists on the relevant information of the entire chain of project materials is still at the stage of obtaining data from different systems and carrying out it through offline manual matching of multiple reports, which has problems such as inconvenient information query and incomplete data items.

[0003] In order to implement digital construction, give play to the radiation effect of smart supply chain system construction, promote the integration of material management and project contract performance business, and give full play to the role of the supply chain system in serving internal supply chain planning and performance specialists, it is necessary to digitize the project contract performance business. Summary of the invention

[0004] The purpose of the present invention is to provide a power grid project contract performance management system and method in order to overcome the defects of the above-mentioned prior art.

[0005] The purpose of the present invention can be achieved by the following technical solutions:

[0006] According to a first aspect of the present invention, a power grid project contract performance management system is provided, comprising:

[0007] The supply chain fulfillment management module obtains supply chain data and obtains supply chain nodes related to contract fulfillment from the supply chain data;

[0008] Project performance management module, which obtains the project stages related to contract performance throughout the project life cycle;

[0009] The first abnormality monitoring module monitors whether there are abnormalities in the supply chain nodes related to contract performance. If there are abnormalities, a supply chain node abnormality prompt is issued;

[0010] The second abnormality monitoring module monitors whether there are any abnormalities in the execution progress of the project phase related to the contract performance. If there are any abnormalities, a project phase abnormality prompt is issued;

[0011] The contract performance time monitoring module sorts out the time nodes in the contract performance and the performance content corresponding to each time node, and determines whether the performance content is completed when the current time reaches the time node. If not, a performance content expiration reminder is issued;

[0012] The early warning module is pre-set with multiple early warning rules, and sends out corresponding early warning information after the early warning rules are triggered.

[0013] Furthermore, the warning rules include:

[0014] If the supply chain node related to contract performance is on the pre-recorded list of risky supply chain nodes, a supply chain node risk warning will be issued.

[0015] Furthermore, the warning rules include:

[0016] If the types of materials involved in the supply chain nodes related to contract performance are on the pre-recorded list of risk materials, a supply chain node risk warning will be issued.

[0017] Furthermore, the warning rules include:

[0018] If the project stage related to contract performance is on the list of pre-recorded risk project stages, a project stage risk warning will be issued.

[0019] Furthermore, the warning rules include:

[0020] If the types of materials involved in the project stage related to contract performance are on the pre-recorded list of risk materials, a project stage risk warning will be issued.

[0021] Furthermore, it also includes a suggestion module, which is pre-set with multiple risk plans, each risk plan is associated with at least one warning rule, and after the warning rule is triggered, it is checked whether the triggered warning rule is associated with a risk plan. If so, the associated risk plan is issued.

[0022] Furthermore, the contract performance time monitoring module also includes: creating new performance content and setting the time node of the performance content.

[0023] Furthermore, in the contract performance time monitoring module, each performance content is also provided with a prior reminder node. When the current time reaches the prior reminder node, it is determined whether to start executing the performance content. If it has not started, a performance content expiration reminder is issued.

[0024] Furthermore, the performance content is set with a priority, and the performance content with different priorities corresponds to different performance content expiration reminders and performance content imminent expiration reminders.

[0025] According to a second aspect of the present invention, there is provided a method for managing contract performance of a power grid project, comprising:

[0026] Obtain supply chain data, and obtain supply chain nodes related to contract performance from the supply chain data; obtain project stages related to contract performance throughout the project life cycle;

[0027] Monitor whether there are any abnormalities in the supply chain nodes related to contract performance. If there are any abnormalities, issue a supply chain node abnormality prompt;

[0028] Monitor whether there are any abnormalities in the execution progress of the project phases related to contract performance. If there are any abnormalities, issue a project phase abnormality prompt;

[0029] Sorting out the time nodes in the performance of the contract and the performance contents corresponding to each time node, and determining whether the performance contents are completed when the current time reaches the time node;

[0030] A plurality of warning rules are preset, and corresponding warning information is issued after the warning rules are triggered.

[0031] Compared with the prior art, the present invention has the following beneficial effects:

[0032] The present invention combines supply chain nodes and project stages to monitor and manage contract performance from different perspectives, so as to grasp the contract performance status and realize digital management of contract performance. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a structural schematic diagram of the power grid project contract performance management system of the present invention. DETAILED DESCRIPTION

[0034] The present invention is described in detail below in conjunction with the accompanying drawings and specific embodiments. This embodiment is implemented on the premise of the technical solution of the present invention, and a detailed implementation method and a specific operation process are given. Obviously, the described embodiment is only an embodiment of a part of the present invention, not all embodiments, and the protection scope of the present invention is not limited to the following embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present invention.

[0035] "One embodiment" or "embodiment" referred to herein refers to a specific feature, structure or characteristic that may be included in at least one implementation of the present invention. In the description of the present invention, it should be understood that the terms "first", "second" and "third" in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but optionally includes steps or units that are not listed, or optionally includes other steps or units that are inherent to these processes, methods, products or devices.

[0036] This specification provides method operation steps such as embodiments or flowcharts, but more or fewer operation steps may be included based on conventional or non-creative labor. The order of steps listed in the embodiments is only one way of executing the order of many steps and does not represent the only execution order. When the actual system or server product is executed, it can be executed in sequence or in parallel (for example, in a parallel processor or multi-threaded processing environment) according to the method shown in the embodiments or the drawings, or the execution order of steps without timing restrictions can be adjusted.

[0037] The present invention provides a power grid project contract performance management system, such as Figure 1 As shown, including:

[0038] (1) Supply chain fulfillment management module, which obtains supply chain data and obtains supply chain nodes related to contract fulfillment from the supply chain data;

[0039] Gather information on key supply chain nodes, and collect statistics on the business volume of the entire material chain, the duration between each business link, and other data. Based on the sorted and statistical data, analyze the statistical data of key supply chain links that the performance specialist is concerned about, that is, obtain the supply chain nodes related to contract performance from the supply chain data, and help the performance specialist to fully grasp the material information of key supply chain nodes by monitoring the supply chain nodes, and assist the performance specialist to improve the analytical ability of material supply guarantee.

[0040] (2) Project performance management module, which obtains the project stages related to contract performance throughout the project life cycle;

[0041] According to the project dimension, key information such as the stage of project materials from plan submission to contract performance and receipt (such as submitted, shipped, waiting to be received, etc.) is sorted out, and key business information of the entire process such as project pre-stage, project execution, planning, bidding and procurement, contract supply, warehousing and distribution, and waste disposal is gathered. The project stages related to contract performance in the entire life cycle of the project are monitored, and the performance status is determined by monitoring the progress information of project materials.

[0042] (3) A first abnormality monitoring module, which monitors whether there are abnormalities in the supply chain nodes related to contract performance, and if there are abnormalities, issues a supply chain node abnormality prompt;

[0043] Generally, the contract fulfillment process involves material preparation, delivery, receipt, and other supply chain-related information. Therefore, by monitoring the supply chain nodes, if the supply chain nodes are abnormal, it may affect the contract fulfillment. Therefore, a supply chain node abnormality prompt is issued to prompt management personnel to pay attention in time.

[0044] (4) A second abnormality monitoring module monitors whether there are any abnormalities in the execution progress of the project phase related to the contract performance, and if there are any abnormalities, issues a project phase abnormality prompt;

[0045] Similarly, a project may involve the performance of multiple contracts. Therefore, for each contract performance, the project stages related to the contract performance are monitored. If the project stage is delayed or materials are insufficient, it may affect the contract performance. Therefore, abnormal project stage prompts are issued to remind managers to pay attention in time.

[0046] (5) Contract performance time monitoring module, which sorts out the time nodes in the contract performance and the performance content corresponding to each time node, and determines whether the performance content has been completed when the current time reaches the time node. If not, a performance content expiration reminder is issued;

[0047] Considering that contract performance is not a simple start-end, and involves multiple time nodes in the middle, such as the application submission stage, quality inspection stage, replenishment stage, etc., therefore, according to the contract performance content, the contract performance is divided into multiple small phased performance contents, and corresponding time nodes are set. If the performance content is still not completed when the time node is reached, it means that the performance content has expired and has not been completed, and a performance content expiration reminder is given for the management personnel to handle it.

[0048] Of course, in order to apply the possible additional supplementary agreements, or the new performance content added by the management personnel as needed, the contract performance time monitoring module also includes: creating new performance content and setting the time node of the performance content. You can also add some to-do items as the performance content of the contract performance, such as entering the task name, process link, receiving time, initiator, department, business type, business completion status and other information. The to-do items include batch submission agency, drawing confirmation agency, overlong order processing, etc.

[0049] Considering that only expiration reminders of performance content can only take post-event measures, in the contract performance time monitoring module, each performance content is also set with a pre-reminder node. When the current time reaches the pre-reminder node, it is determined whether the performance content has started to be executed. If it has not started, a performance content expiration reminder is issued, so that the performance content can be prompted to start execution as soon as possible, which serves as a prior reminder. In the case of a large number of performance contents, managers may not have the energy to identify them one by one. Therefore, performance contents are given priorities. Performance contents of different priorities have different performance content expiration reminders and performance content expiration reminders, so as to quickly determine the performance content with the highest priority and avoid more losses caused by unfinished performance.

[0050] (6) An early warning module is pre-set with multiple early warning rules, and sends out corresponding early warning information after the early warning rules are triggered.

[0051] In this application, the warning rules include:

[0052] If the supply chain node related to contract performance is on the pre-recorded list of risky supply chain nodes, a supply chain node risk warning will be issued.

[0053] If the types of materials involved in the supply chain nodes related to contract performance are on the pre-recorded list of risk materials, a supply chain node risk warning will be issued.

[0054] If the project stage related to contract performance is on the list of pre-recorded risk project stages, a project stage risk warning will be issued.

[0055] If the types of materials involved in the project stage related to contract performance are on the pre-recorded list of risk materials, a project stage risk warning will be issued.

[0056] In combination with the characteristics of platform operation, remind the planning and performance specialists to pay attention to abnormal pending and early warning business on a regular basis, and assist the planning and performance specialists to handle problems in a timely manner. According to the project material supply risk warning, dig out the key risk points that affect project delivery, extract the corresponding risk factors and related impact coefficients in each link of the project life cycle, design a monitoring and analysis model for key links of the supply chain from a project perspective, and improve the project risk management early warning mechanism based on the risk digital model, such as plan declaration, batch selection, etc., compilation and reporting warning, overlong order warning, inventory material collection warning, etc.

[0057] Of course, in other implementations, more warning rules may be designed as needed, which will not be described one by one here, and those skilled in the art will understand.

[0058] (7) Suggestion module: The suggestion module is pre-set with multiple risk plans, each risk plan is associated with at least one warning rule. After the warning rule is triggered, it is checked whether the triggered warning rule is associated with a risk plan. If so, the associated risk plan is issued.

[0059] The early warning module will issue timely warnings, prompt relevant personnel, and intervene in time when project engineering time nodes are delayed or material supply risks occur due to different types of reasons (such as: agreement interruption, warehouse interruption, insufficient supplier capacity, and quality problems of supplied materials), thereby improving the performance risk insight of the performance specialist for the failure to supply materials in a timely manner. For projects with delayed material supply and delivery risks, based on the lag time, lag reasons, etc., identify the paths that can be accelerated in subsequent project links, form strategic recommendations for project risk prevention, and generate suggestion modules, such as changing procurement methods, green channels, and recommending materials based on the remaining share of the agreement, material standardization, cost, timeliness, etc. when insufficient material supply or interruption occurs, and calculate the estimated arrival time and estimated time savings based on the new procurement and supply method.

[0060] The present invention combines supply chain nodes and project stages to monitor and manage contract performance from different perspectives in order to grasp the contract performance situation and realize digital management of contract performance. It uses the full-chain and full-volume data assets of the company's data center as the working basis, enables the improvement of monitoring and analysis capabilities of key links in planning and performance, and ensures that all planning and performance tasks are integrated into the modern supply chain operation system.

[0061] The present invention also provides a power grid project contract performance management method, comprising:

[0062] Obtain supply chain data, and obtain supply chain nodes related to contract performance from the supply chain data; obtain project stages related to contract performance throughout the project life cycle;

[0063] Monitor whether there are any abnormalities in the supply chain nodes related to contract performance. If there are any abnormalities, issue a supply chain node abnormality prompt;

[0064] Monitor whether there are any abnormalities in the execution progress of the project phases related to contract performance. If there are any abnormalities, issue a project phase abnormality prompt;

[0065] Sort out the time nodes in the contract performance and the performance contents corresponding to each time node, and determine whether the performance contents are completed when the current time reaches the time node;

[0066] There are multiple pre-set warning rules, and corresponding warning information is issued after the warning rules are triggered.

[0067] Technical personnel in the relevant field can clearly understand that for the convenience and brevity of description, the specific working process of the described power grid project contract performance management method can refer to the corresponding process in the aforementioned system embodiment, and will not be repeated here.

[0068] The preferred specific embodiments of the present invention are described in detail above. It should be understood that a person skilled in the art can make many modifications and changes based on the concept of the present invention without creative work. Therefore, any technical solution that can be obtained by a person skilled in the art through logical analysis, reasoning or limited experiments based on the concept of the present invention on the basis of the prior art should be within the scope of protection determined by the claims.

Claims

1. A power grid project contract performance management system, characterized in that: include: The supply chain fulfillment management module obtains supply chain data and obtains supply chain nodes related to contract fulfillment from the supply chain data; Project performance management module, which obtains the project stages related to contract performance throughout the project life cycle; The first abnormality monitoring module monitors whether there are abnormalities in the supply chain nodes related to contract performance. If there are abnormalities, a supply chain node abnormality prompt is issued; The second abnormality monitoring module monitors whether there are any abnormalities in the execution progress of the project phase related to the contract performance. If there are any abnormalities, a project phase abnormality prompt is issued; The contract performance time monitoring module sorts out the time nodes in the contract performance and the performance content corresponding to each time node, and determines whether the performance content is completed when the current time reaches the time node. If not, a performance content expiration reminder is issued; The early warning module is pre-set with multiple early warning rules, and sends out corresponding early warning information after the early warning rules are triggered.

2. A power grid project contract performance management system according to claim 1, characterized in that: The warning rules include: If the supply chain node related to contract performance is on the pre-recorded list of risky supply chain nodes, a supply chain node risk warning will be issued.

3. A power grid project contract performance management system according to claim 1, characterized in that: The warning rules include: If the types of materials involved in the supply chain nodes related to contract performance are on the pre-recorded list of risk materials, a supply chain node risk warning will be issued.

4. A power grid project contract performance management system according to claim 1, characterized in that: The warning rules include: If the project stage related to contract performance is on the list of pre-recorded risk project stages, a project stage risk warning will be issued.

5. A power grid project contract performance management system according to claim 1, characterized in that: The warning rules include: If the types of materials involved in the project stage related to contract performance are on the pre-recorded list of risk materials, a project stage risk warning will be issued.

6. A power grid project contract performance management system according to claim 1, characterized in that: It also includes a suggestion module, which is pre-set with multiple risk plans, each risk plan is associated with at least one warning rule, and after the warning rule is triggered, it is checked whether the triggered warning rule is associated with a risk plan, and if so, the associated risk plan is issued.

7. A power grid project contract performance management system according to claim 1, characterized in that: The contract performance time monitoring module also includes: creating new performance content and setting the time node of the performance content.

8. A power grid project contract performance management system according to claim 7, characterized in that: In the contract performance time monitoring module, each performance content is also provided with a prior reminder node. When the current time reaches the prior reminder node, it is determined whether the performance content has started to be executed. If it has not started, a performance content expiration reminder is issued.

9. A power grid project contract performance management system according to claim 8, characterized in that: The performance content is set with a priority, and the performance content with different priorities corresponds to different performance content expiration reminders and performance content imminent expiration reminders.

10. A power grid project contract performance management method, characterized in that: A power grid project contract performance management system based on any one of claims 1 to 9, comprising: Obtain supply chain data, and obtain supply chain nodes related to contract performance from the supply chain data; obtain project stages related to contract performance throughout the project life cycle; Monitor whether there are any abnormalities in the supply chain nodes related to contract performance. If there are any abnormalities, issue a supply chain node abnormality prompt; Monitor whether there are any abnormalities in the execution progress of the project phases related to contract performance. If there are any abnormalities, issue a project phase abnormality prompt; Sorting out the time nodes in the performance of the contract and the performance contents corresponding to each time node, and determining whether the performance contents are completed when the current time reaches the time node; A plurality of warning rules are preset, and corresponding warning information is issued after the warning rules are triggered.