Large-diameter vertical shaft one-time counter-drawing forming construction method

Through the one-time reverse pull forming construction method, using a crawler drill and a reaming head connected with high-strength bolts and pin keys, the problems of slow construction speed, low forming quality and high safety risks of traditional shafts were solved, and a 6m diameter was achieved. Efficient mechanized construction and safety improvement.

CN118745900APending Publication Date: 2024-10-08SINOHYDRO BUREAU 14 CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411013161.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-26
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

Traditional shaft construction has problems such as slow construction speed, low molding quality and high safety risks, and it cannot achieve one-time molding, resulting in low construction efficiency and economic losses.

Method used

A one-time back-drawing construction method for a granite 6m diameter shaft is adopted, which involves bedrock cleaning, pre-grouting, drilling rig foundation concrete pouring, foundation beam installation, drilling rig installation and debugging, pilot hole construction, hole-expanding back-drawing cutterhead installation and For steps such as reaming and reverse pulling construction, a crawler drilling rig and a reaming cutter head connected with high-strength bolts and pin keys are used to achieve mechanized continuous operations and avoid manual entry underground.

Benefits of technology

It improves construction efficiency, shortens the project cycle, ensures the quality of excavation molding, reduces safety risks, and achieves one-time molding of 6m diameter, which greatly improves construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118745900A_ABST
    Figure CN118745900A_ABST
Patent Text Reader

Abstract

The invention discloses a one-time counter-drawing forming construction method for a large-diameter vertical shaft, and belongs to the field of civil construction. The construction method comprises the steps of raise boring machine foundation bedrock cleaning and pre-grouting, raise boring machine foundation concrete pouring, raise boring machine foundation beam installation, raise boring machine installation and debugging, vertical shaft pilot hole construction, vertical shaft reaming cutter head installation, vertical shaft reaming counter-pulling construction, equipment dismantling, vertical shaft through measurement and the like. The construction method comprises the steps of raise boring machine foundation bedrock cleaning and pre-grouting, raise boring machine foundation concrete pouring, raise boring machine foundation beam installation, raise boring machine installation and debugging, vertical shaft pilot hole construction and vertical shaft reaming counter-pulling construction. The problems that the excavation construction progress of the vertical shaft with the diameter of 6 m is slow, the forming quality is poor, and potential safety hazards are many are effectively solved. On the basis of the construction progress, safety and practicability, the safety production problem in the process is reduced, the labor and material investment in the later period is reduced, the construction efficiency is greatly improved, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of underground engineering construction, and particularly relates to a one-time reverse-pulling forming construction method for a granite 6m large-diameter vertical shaft. Background Art

[0002] Traditional shaft construction has the disadvantages of slow construction speed, low quality of shaft forming, and high safety risks. During traditional shaft construction, workers need to enter the working face to perform drilling, charging, blasting and support operations. The workers are in areas with poor environmental and safety conditions, and are easily harmed by falling rocks, water, and harmful gases. Traditional shafts are constructed using the forward shaft method or reverse shaft method, which cannot be formed in one go, greatly reducing construction efficiency. At the same time, during expansion construction, there is a large over-excavation and under-excavation situation in the shaft section, causing economic losses to subsequent construction. Summary of the invention

[0003] The purpose of the present invention is to effectively solve the shortcomings of slow construction, low molding quality and great safety risks in shaft construction, and to provide a one-time reverse pulling molding construction method for a 6m diameter granite shaft, which effectively improves the construction efficiency, shortens the project period, ensures the excavation molding quality, and improves the safety of construction.

[0004] To achieve the above purpose, the technical solution adopted by the present invention is as follows: A one-time reverse pulling forming construction method for a large diameter vertical shaft is carried out according to the following steps: Step 1: Bedrock cleaning and pre-grouting: Use an excavator to clean the bottom slag within the construction range of the shaft until it reaches the bedrock surface. After the bedrock surface is cleaned, in order to reinforce the excavation foundation surface, a number of pre-grouting holes are arranged at two circular positions with a radius of 2m and 4m with the design center of the shaft mouth as the center of the circle, and pre-grouting reinforcement is performed; Step 2: Concrete pouring of drilling rig foundation: C35 concrete is used as the foundation of the patio drilling rig. The foundation concrete is poured in layers and stages, with each layer being 1m. The second-phase concrete is poured after the patio drilling rig foundation beam is installed. Inserted reinforcement is set in the second-phase concrete. Step 3: Installation of foundation beam: The wellhead platform uses two H-shaped weldments as the main beams of the foundation beam for the raise drilling rig construction. After the first layer of foundation concrete is poured, the position of the supporting I-beam is determined through precise lofting, and then the foundation beam is hung on the I-beam support, the foundation beam is fixed, and the foundation beam anchor bolts are connected with the inserted bars in the second phase concrete. After the foundation beam is installed, the second layer of foundation concrete and the second phase concrete are poured; Step (4): Drilling rig installation and commissioning: The riser drilling rig is a crawler type drilling rig. After the crawler tracks move to the shaft, they enter the laid track. The riser drilling rig is moved into position, the drill rod center is adjusted to face the shaft center, the verticality gauge is checked and calibrated, the track position is aligned, the drilling rig is leveled and reinforced. After the installation is completed, the various functions of the drilling rig are checked and commissioned; Step (5): Pilot hole construction: The vertical shaft uses a drill pipe to vertically drill the pilot hole from top to bottom. The drilling is carried out at low pressure, low speed and slow advance. After the pilot hole is penetrated, the pilot hole penetration measurement is carried out to determine the verticality deviation of the pilot hole; Step (6): Installation of the hole-reaming back-pull cutter disc: After the guide hole is through, replace the hole-reaming cutter head and perform the back-pull construction. The hole-reaming cutter head consists of five parts: a pull rod, a cutter disc, a blade, a cutter seat and a hob. The hob and the cutter seat are fixed with bevel-cut bolts, and other connections are made of high-strength bolts with pins and keys. After the cutter disc is installed and installed, a test run is performed, and then the back-pull construction is performed; Step (7): Hole expansion and reverse pulling construction: The hole expansion cutter head is composed of five units: a pull rod, a cutter disc, a blade, a cutter holder and a roller cutter. The roller cutter and the cutter holder are fixed with bevel groove bolts, and other connections are made with high-strength bolts, pins and keys. After the cutter disc is connected, the hole is expanded and the cutter disc is slowly lifted until the roller cutter begins to contact the rock. It is rotated at the lowest speed of 5-9 rpm and slowly fed to ensure that the drill bit roller cutter is not damaged by excessive impact. When the drill bit is evenly in contact with the rock, normal hole expansion and drilling are carried out. Step (8): Equipment dismantling: The dismantling of the skylight equipment mainly includes the skylight equipment mainframe, foundation beam and cutter head; Step (9): Through measurement: Use a total station to perform cross-sectional measurement on the rock surface of the shaft after the back-pulling is completed. Determine the deviation value and actual diameter of each section of the shaft based on the cross-sectional data, and finally determine the verticality deviation of the shaft.

[0005] Furthermore, a plurality of pre-grouting holes respectively arranged at two circular positions with a radius of 2m and 4m are spaced 2m apart.

[0006] Furthermore, the pre-grouting adopts a crawler-type down-the-hole drill to make holes with a hole diameter of Φ110mm, a row spacing of 2m*2m, a grouting pressure of 3MPa, and a slurry ratio of 1:1 pure cement slurry.

[0007] Furthermore, the foundation concrete is C35 concrete with a size of 11.5m*8.8m*2.0m; the embedded dowel bars are Φ25 steel bars with a length of 2.5m and a depth of 2.0m into the rock.

[0008] Furthermore, the foundation beams are two H-shaped steel structure weldments made of Q355B and M42 anchor bolts.

[0009] Furthermore, the shaft drilling rig is an AT-5000L (CY-R200V) type shaft drilling rig, with a main engine weight of 32t, a main engine size of 2250mm*2140mm*4380mm, a rotation speed of 0~28rpm, and an installed power of 400kW.

[0010] Furthermore, the drill rod is Φ327 mm, the drill rod length is 1.7 m, the thread length is 0.2 m, the effective length is 1.5 m, and the drill bit is Φ350 mm.

[0011] Furthermore, a φ327mm drill rod is used in the vertical shaft to drill a φ350mm pilot hole vertically from top to bottom. Stabilizer rods are set on the 1st, 3rd, 5th, 10th and 30th drill rods. Low pressure, low speed and slow advance are adopted for drilling. The average thrust pressure is 8.0-7.5Mpa, the average rotation speed is 16.7-16.3r / min, and the average rotation pressure is 6.4-5.8Mpa. After the pilot hole is penetrated, the pilot hole penetration measurement is carried out to determine the verticality deviation of the pilot hole.

[0012] Compared with the prior art, the patent of this invention has the following beneficial effects: 1. The construction method of the present invention can effectively improve construction efficiency and shorten the project period; the function of the drill bit to automatically adjust the direction and angle ensures the accuracy and quality of excavation, avoiding quality problems that may occur in manual construction; workers do not need to enter the underground operation, avoiding the safety risks brought by underground operations, and improving the safety of construction.

[0013] 2. High work efficiency: The vertical shaft construction adopts the positive guide hole and reverse pulling construction technology of the raise drilling rig, and uses the most advanced domestic CY-R200V raise drilling rig. It has mechanized continuous operation and high speed. The diameter of the well can reach 6 meters at one time, which greatly improves the construction efficiency of the raise drilling rig.

[0014] 3. Good forming quality: The shaft drilling rig adopts a roller cutter to break the rock, which causes little damage to the surrounding rock and makes the shaft wall smooth, thus ensuring the excavation forming quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the one-time reverse pulling construction of the vertical shaft of the present invention.

[0016] Figure 2 It is a schematic diagram of the plan layout of the drilling rig of the present invention.

[0017] Figure 3 It is a schematic diagram of the arrangement of the pre-grouting holes of the present invention.

[0018] In the figure, 1-drilling rig foundation beam, 2-anchor bolt M42, 3-water tank, 4-masonry drilling rig main unit, 5-drill rod, 6-mobile pump station, 7-6m diameter reverse puller disc, 8-foundation concrete, 9-pre-grouting hole. DETAILED DESCRIPTION

[0019] The present invention adopts AT-5000L (CY-R200V) type riser drilling machine and adopts the top expansion drilling method for construction. First, a guide hole with a diameter of 350mm penetrating the vertical shaft is drilled from top to bottom with a roller drill bit, and then the hole expansion cutter head is replaced to expand the diameter from bottom to top to 6m. The rock slag can fall by its own weight without repeated crushing, which not only improves the working conditions, but also facilitates the maintenance and repair of the equipment, and does not need to add additional devices for releasing the rock slag. It is easy to open the hole, convenient to remove the slag, easy to prevent deflection, and can ensure the drilling quality.

[0020] A one-time reverse pulling forming construction method for a 6m diameter vertical shaft of granite is carried out in the following steps: Step (1): Bedrock cleaning and pre-grouting: Use an excavator to clean the bottom slag within the construction range of the shaft, clean it to the bedrock surface, and pile the cleaned slag on the other side for subsequent backfill construction. After the bedrock surface is cleaned, in order to reinforce the excavation foundation surface and provide a solid foundation for the shaft drilling rig, two rings of pre-grouting holes with a radius of 2m and 4m are arranged at the shaft mouth with the design center as the center of the circle, and the hole spacing is 2m, and pre-grouting reinforcement is carried out; Step (2): Concrete pouring for the drilling rig foundation: C35 concrete is used for the foundation concrete, with a pouring size of 11.5m long, 8.8m wide and 2.0m thick, as the foundation of the raise drilling rig. The foundation concrete is poured in layers (1m per layer) and phases (the second phase concrete is poured after the installation of the base beam of the raise drilling rig is completed); to ensure the stability of the drilling rig, the second phase concrete is equipped with dowels, with a length of 2.5m, 2.0m into the rock and 0.5m exposed; Step (3): Installation of foundation beam: The wellhead platform uses two H-shaped weldments as the main beams of the foundation beam for the shaft drilling rig construction. The material is Q355B and the foundation beam weighs 10 tons. After the first layer of foundation concrete is poured, the surveying personnel accurately lay out and determine the position of the supporting I-beam. Then, the foundation beam is placed on the I-beam support by a crane. The position of the foundation beam is reasonably adjusted and then the foundation beam is fixed. The foundation beam anchor bolts (M42) are connected to the dowel bars in the second phase concrete. The installation accuracy of the foundation beam is strictly controlled. After the foundation beam is centered and leveled, the anchor bolt nuts are tightened. After the foundation beam is installed and the centering and leveling are confirmed to be correct, the second layer of foundation concrete and the second phase concrete are poured. Step (4): Drilling rig installation and commissioning: The skylight drilling rig is a crawler-type drilling rig. After unloading the truck, the crawler tracks move. After walking to the shaft, enter the laid track. After the skylight drilling rig is moved to the designed position, adjust the center of the drill rod to face the center of the shaft. Use a vertical ruler to check the verticality of the support cylinder and calibrate the total station. Align the track position, level and reinforce the drilling rig. After the installation is completed, check and debug all functions of the drilling rig; Step (5): Pilot hole construction: The vertical shaft uses a φ327mm drill rod (drill rod length 1.7m, thread length 0.2m, effective length 1.5m) and a φ350mm drill bit to drill a φ350mm pilot hole vertically from top to bottom. Stabilizer rods are set at the 1st, 3rd, 5th, 10th, and 30th drill rods. Drilling is carried out at low pressure, low speed, and slow advance. The average thrust pressure is 8.0-7.5Mpa, the average rotation speed is 16.7-16.3r / min, and the average rotation pressure is 6.4-5.8Mpa. After drilling 10m, the drilling pressure and rotation speed are appropriately adjusted according to the surrounding rock structure, and the drill rod deviation is adjusted according to the hole mouth drill rod stabilizer. After the pilot hole is penetrated, the pilot hole penetration measurement is carried out to determine the verticality deviation (inclination) of the hole guide; Step (6): Installation of the hole-reaming back-pull cutterhead: After the pilot hole is through, the drill pipe is lowered to the bottom of the shaft and replaced with a 6.0 m hole-reaming cutterhead. The hole-reaming cutterhead consists of five modular units: a pull rod, a cutterhead, a blade, a cutter holder and a roller cutter. The roller cutter and the cutter holder are fixed with bevel groove bolts, and other connections are made with high-strength bolts, pins and keys. After the cutterhead is installed, a test run is carried out. After confirmation, the back-pull construction is carried out. Step (7): Hole expansion reverse pulling construction: After the hole expansion is completed, slowly lift the cutter disc until the roller cutter begins to contact the rock, then stop lifting, rotate at the lowest speed (5-9rpm), and slowly feed to ensure that the drill roller cutter is not damaged by excessive impact. When the hole expansion begins, someone is watching below and notifies the operator of the situation in a timely manner. Only when the drill bit is in full and uniform contact with the rock can the hole expansion and drilling proceed normally. During the hole expansion process, when the rock hardness is high, the drilling pressure can be appropriately increased, otherwise it can be reduced. When the hole expansion is being drilled, the rock chips broken by the hole expansion should be cleaned in time to prevent the lower opening from being blocked. The hole expansion cutter head is composed of five units: pull rod, cutter disc, blade, cutter holder and roller cutter. The roller cutter and the cutter holder are fixed with bevel groove bolts, and other connections are made of high-strength bolts with pins and keys.

[0021] Step (8): Equipment dismantling: The dismantling of the overhead equipment mainly includes the overhead equipment main unit (32t), foundation beam (10t) and cutter head (25t). A 100t truck crane and a 50t truck are used for lifting and transportation of the equipment dismantling.

[0022] Step (9): Through measurement: Use a total station to measure the cross-section of the shaft rock surface after the back-pulling is completed. Determine the deviation value and actual diameter of each section of the shaft based on the cross-section data, and finally determine the verticality deviation of the shaft to complete the one-time back-pulling forming construction of the 6m diameter granite shaft.

[0023] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A one-time reverse-pulling forming construction method for a large-diameter vertical shaft, characterized in that: Follow these steps: Step 1: Bedrock cleaning and pre-grouting: Use an excavator to clean the bottom slag within the construction range of the shaft until it reaches the bedrock surface. After the bedrock surface is cleaned, in order to reinforce the excavation foundation surface, a number of pre-grouting holes are arranged at two circular positions with a radius of 2m and 4m with the design center of the shaft mouth as the center of the circle, and pre-grouting reinforcement is performed; Step 2: Concrete pouring of drilling rig foundation: C35 concrete is used as the foundation of the patio drilling rig. The foundation concrete is poured in layers and stages, with each layer being 1m. The second-phase concrete is poured after the patio drilling rig foundation beam is installed. Inserted reinforcement is set in the second-phase concrete. Step 3: Installation of foundation beam: The wellhead platform uses two H-shaped weldments as the main beams of the foundation beam for the raise drilling rig construction. After the first layer of foundation concrete is poured, the position of the supporting I-beam is determined through precise lofting, and then the foundation beam is hung on the I-beam support, the foundation beam is fixed, and the foundation beam anchor bolts are connected with the inserted bars in the second phase concrete. After the foundation beam is installed, the second layer of foundation concrete and the second phase concrete are poured; Step (4): Drilling rig installation and commissioning: The riser drilling rig is a crawler type drilling rig. After the crawler tracks move to the shaft, they enter the laid track. The riser drilling rig is moved into position, the drill rod center is adjusted to face the shaft center, the verticality gauge is checked and calibrated, the track position is aligned, the drilling rig is leveled and reinforced. After the installation is completed, the various functions of the drilling rig are checked and commissioned; Step (5): Pilot hole construction: The vertical shaft uses a drill pipe to vertically drill the pilot hole from top to bottom. The drilling is carried out at low pressure, low speed and slow advance. After the pilot hole is penetrated, the pilot hole penetration measurement is carried out to determine the verticality deviation of the pilot hole; Step (6): Installation of the hole-reaming back-pull cutter disc: After the guide hole is through, replace the hole-reaming cutter head and perform the back-pull construction. The hole-reaming cutter head consists of five parts: a pull rod, a cutter disc, a blade, a cutter seat and a hob. The hob and the cutter seat are fixed with bevel-cut bolts, and other connections are made of high-strength bolts with pins and keys. After the cutter disc is installed and installed, a test run is performed, and then the back-pull construction is performed; Step (7): Hole expansion and reverse pulling construction: The hole expansion cutter head is composed of five units: a pull rod, a cutter disc, a blade, a cutter holder and a roller cutter. The roller cutter and the cutter holder are fixed with bevel groove bolts, and other connections are made with high-strength bolts, pins and keys. After the cutter disc is connected, the hole is expanded and the cutter disc is slowly lifted until the roller cutter begins to contact the rock. It is rotated at the minimum speed of 5-9 rpm and slowly fed until the drill bit is evenly in contact with the rock, and then the hole is expanded and drilled normally. Step (8): Equipment dismantling: The dismantling of the skylight equipment mainly includes the skylight equipment mainframe, foundation beam and cutter head; Step (9): Through measurement: Use a total station to perform cross-sectional measurement on the rock surface of the shaft after the back-pulling is completed. Determine the deviation value and actual diameter of each section of the shaft based on the cross-sectional data, and finally determine the verticality deviation of the shaft.

2. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The spacing between several pre-grouting holes arranged at two circular positions with radii of 2m and 4m is 2m.

3. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The pre-grouting is performed by using a crawler-type down-the-hole drill, the hole diameter is Φ110mm, the row spacing is 2m*2m, the grouting pressure is 3MPa, and the slurry ratio is 1:1 pure cement slurry.

4. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The foundation concrete is C35 concrete with dimensions of 11.5m*8.8m*2.0m; the embedded dowel bars are Φ25 steel bars with a length of 2.5m and a depth of 2.0m into the rock.

5. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The foundation beams are two H-shaped steel structure weldments made of Q355B and M42 anchor bolts.

6. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The skylight drilling rig is an AT-5000L (CY-R200V) skylight drilling rig, with a main engine weight of 32t, a main engine size of 2250mm*2140mm*4380mm, a rotation speed of 0~28rpm, and an installed power of 400kW.

7. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The drill rod is Φ327mm, the drill rod length is 1.7m, the thread length is 0.2m, the effective length is 1.5m, and the drill bit is Φ350mm.

8. The one-time reverse-pulling forming construction method for a large-diameter vertical shaft according to claim 1 is characterized in that: The vertical shaft uses φ327mm drill rods, and φ350mm pilot holes are drilled vertically from top to bottom. Stabilizer rods are set on the 1st, 3rd, 5th, 10th and 30th drill rods. Low pressure, low speed and slow advance are adopted for drilling. The average thrust pressure is 8.0-7.5Mpa, the average rotation speed is 16.7-16.3r / min, and the average rotation pressure is 6.4-5.8Mpa. After the pilot hole is penetrated, the pilot hole penetration measurement is carried out to determine the verticality deviation of the pilot hole.