Assessment method, device and equipment of power distribution system planning scheme and storage medium

Through the state enumeration method and associated fault scenario processing of the impact incremental method, the evaluation efficiency of the distribution system planning scheme is improved, the problem of low evaluation efficiency under the traditional method is solved, and the efficient evaluation of multiple distribution system planning schemes is achieved. Evaluate.

CN118747609APending Publication Date: 2024-10-08GUANGDONG POWER GRID CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410919318.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-10
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

In the process of power distribution system improvement, the traditional state enumeration method leads to inefficiency in the evaluation of multiple distribution system planning solutions, especially when the distribution system has many nodes and the grid structure is complex.

Method used

The state enumeration method based on the impact increment method is used to enumerate the fault state set of the power distribution system, calculate the first reliability index, and generate the associated fault state set through associated fault scenarios, and perform quantitative processing to obtain the reliability increment, and then A second reliability index is calculated to determine the optimal distribution system planning solution.

Benefits of technology

It improves the evaluation efficiency of multiple distribution system planning schemes, reduces repeated calculations, reduces the number of fault states for detailed calculation, and significantly improves the evaluation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118747609A_ABST
    Figure CN118747609A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution system planning scheme evaluation method and device, equipment and a storage medium, and the method comprises the steps: employing a state enumeration method which influences an incremental method, and calculating a first reliability index of a power distribution system based on an enumerated fault state set of the power distribution system, the number of elements, and element information corresponding to each element; newly-added elements corresponding to multiple power distribution system planning schemes of the power distribution system are obtained, and associated fault scenes corresponding to the newly-added elements are enumerated to generate an associated fault state set; performing quantification processing on the associated fault state set to obtain reliability increments corresponding to the plurality of power distribution system planning schemes, and calculating second reliability indexes corresponding to the plurality of power distribution system planning schemes based on the reliability increments and the first reliability indexes; the power distribution system planning module is used for determining an optimal power distribution system planning scheme and improving a power distribution system to obtain an improved power distribution system; compared with the prior art, the method can improve the evaluation efficiency of a plurality of power distribution system planning schemes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of power distribution system planning, and in particular to an evaluation method, device, equipment and storage medium for a power distribution system planning scheme. Background Art

[0002] At present, in the process of distribution system improvement, it is necessary to formulate and evaluate the reliability of multiple distribution system planning schemes; the traditional reliability evaluation method usually adopts the state enumeration method to evaluate, which requires analyzing the performance of each distribution system planning scheme under various possible fault conditions.

[0003] However, due to the large number of distribution system nodes and the complex grid structure, this state enumeration method may lead to a large number of fault states in the enumeration process. If the state enumeration method is used to evaluate each distribution system planning scheme, in the scenario of multiple distribution system planning schemes, the evaluation efficiency of the scheme will be reduced. Summary of the invention

[0004] The technical problem to be solved by the present application is to provide a method, device, equipment and storage medium for evaluating a power distribution system planning scheme, so as to improve the evaluation efficiency of multiple power distribution system planning schemes.

[0005] In order to solve the above technical problems, the present application provides an evaluation method for a power distribution system planning scheme, including:

[0006] Based on the number of components corresponding to the power distribution system and the component information corresponding to each component, a state enumeration method of an influence increment method is adopted to enumerate a set of fault states corresponding to the power distribution system, and based on the set of fault states, the number of components, and the component information corresponding to each component, a first reliability index of the power distribution system is calculated;

[0007] Acquire multiple power distribution system planning schemes corresponding to the power distribution system, determine newly added components corresponding to each of the multiple power distribution system planning schemes, enumerate associated fault scenarios corresponding to the newly added components, and generate associated fault state sets corresponding to each of the multiple power distribution system planning schemes based on the associated fault scenarios;

[0008] Quantifying the associated fault state set to obtain reliability increments corresponding to each of the plurality of power distribution system planning schemes, and calculating second reliability indicators corresponding to each of the plurality of power distribution system planning schemes based on the reliability increments and the first reliability indicator;

[0009] Based on the second reliability index, an optimal power distribution system planning scheme among the multiple power distribution system planning schemes is determined, and the power distribution system is improved based on the optimal power distribution system planning scheme to obtain an improved power distribution system.

[0010] In a possible implementation, calculating a first reliability index of a power distribution system based on the set of fault states, the number of components, and component information corresponding to each component specifically includes:

[0011] Based on the fault state set, the number of components, and component information corresponding to each component, wherein the component information includes component unavailability rate and fault state impact amount;

[0012] The fault state set, the number of components, the component unavailability rate and the fault state impact amount are input into a preset first reliability index calculation formula to obtain a first reliability index of the power distribution system; wherein the preset first reliability index calculation formula is as follows:

[0013]

[0014] In the formula, R ex is the first reliability index, N is the number of components in the power distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the power distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, is the k-order subset of fault state s, w is the system fault state element in the k-order subset of system fault state s, I w is the fault state impact quantity corresponding to the system fault state element w.

[0015] In a possible implementation, the associated fault scenarios corresponding to the newly added components are enumerated, and based on the associated fault scenarios, associated fault state sets corresponding to the multiple power distribution system planning schemes are generated, specifically including:

[0016] Obtaining grid topology diagrams corresponding to each of the plurality of power distribution system planning schemes, and enumerating all single-element associated fault scenarios and all double-element associated fault scenarios corresponding to the newly added components based on the grid topology diagrams;

[0017] Based on the all single-component fault scenarios and the all dual-component fault scenarios, associated fault state sets corresponding to the multiple power distribution system planning schemes are determined.

[0018] In a possible implementation, the associated fault state set is quantified to obtain reliability increments corresponding to a plurality of distribution system planning schemes, specifically including:

[0019] Obtain the parallel fault impact difference and the target fault state probability corresponding to each target fault state in the associated fault state set, substitute the parallel fault impact difference, the target fault state probability and the associated fault state set into a preset reliability increment calculation formula, and obtain the reliability increments corresponding to each of the multiple distribution system planning schemes, wherein the reliability increment calculation formula is as follows:

[0020]

[0021] Where ΔR is the reliability increment, Ω ex is the fault state set corresponding to the power distribution system, is the associated fault state set corresponding to the distribution system planning scheme, y is the target fault state in the associated fault state set, A fault condition in which a new component is included in the power distribution system planning scheme. The distribution system planning includes M-1 fault states of the newly added components, M is the fault state corresponding to k newly added components, and M=2 k , ΔI y is the parallel fault impact difference corresponding to the target fault state, P y is the target failure state probability.

[0022] In a possible implementation manner, determining the optimal power distribution system planning scheme among the multiple power distribution system planning schemes based on the second reliability indicator specifically includes:

[0023] Based on the second reliability index, calculate the reliability cost and commission measure cost corresponding to each of the plurality of distribution system planning schemes, and based on the reliability cost and commission measure cost, determine the reliability commission benefits corresponding to each of the plurality of distribution system planning schemes;

[0024] Based on the reliability commission benefit, determine the optimal distribution system planning scheme among the multiple distribution system planning schemes.

[0025] In a possible implementation manner, based on the second reliability index, calculating the reliability costs corresponding to each of the plurality of power distribution system planning schemes specifically includes:

[0026] The second reliability index is input into a preset power outage loss calculation formula to obtain a power outage loss value, and the power outage loss value is used as the reliability cost corresponding to each of the multiple distribution system planning schemes; wherein the preset power outage loss calculation formula is as follows:

[0027]

[0028] In the formula, Csave is the power outage loss, bus is the number of system nodes, state is the number of system fault states, BusPLC is the second reliability indicator of the node under a certain fault state, which refers to the load reduction probability of the load node, BusType is the node type, including commercial, industrial, and residential loads, f(BusPLC, BusType) is the power outage loss function under different load types and different power outage times, in yuan / kW, and BusLCsum is the expected power shortage of the load node.

[0029] In a possible implementation, based on the second reliability index, calculating the commission measure costs corresponding to each of the plurality of power distribution system planning schemes specifically includes:

[0030] Respectively obtaining corresponding operating cost related parameters from the plurality of power distribution system planning schemes, inputting the operating cost related parameters and the second reliability index into a preset operating cost calculation formula to obtain the operating cost;

[0031] Respectively obtaining corresponding investment cost related parameters from the plurality of power distribution system planning schemes, and inputting the investment cost related parameters into a preset investment cost calculation formula to obtain the investment cost;

[0032] Substituting the investment cost and the operating cost into a preset commission measure cost calculation formula to obtain the commission measure costs corresponding to each of the plurality of power distribution system planning schemes;

[0033] The preset commission measure cost calculation formula is as follows:

[0034] C add =C(I)+C(O);

[0035] The preset investment cost calculation formula is as follows:

[0036]

[0037] The preset operating cost calculation formula is as follows:

[0038]

[0039] In the formula, C add To improve the cost of measures, C(I) is the investment cost, C(O) is the operating cost, L is the line length, C line is the cost of the tie line, in yuan / km, C SOP is the investment cost of the intelligent soft switch, n is the number of intelligent soft switches, η is the line loss rate, r is the discount rate, T is the total service life, O L is the dispatching cost of the tie line, O SOPis the dispatching cost of the intelligent soft switch, μ is the second reliability index corresponding to the distribution system planning scheme, P is the transmission power between the tie line and the intelligent soft switch, S ele is the store price, S sop It is the dispatching unit price of intelligent soft switch.

[0040] The present application also provides an evaluation device for a power distribution system planning scheme, comprising: a first reliability index calculation module, an associated fault state set determination module, a second reliability index calculation module, and an optimal power distribution system planning scheme determination module;

[0041] The first reliability index calculation module is used to enumerate the set of fault states corresponding to the power distribution system based on the number of components corresponding to the power distribution system and the component information corresponding to each component, using the state enumeration method of the influence increment method, and calculate the first reliability index of the power distribution system based on the set of fault states, the number of components, and the component information corresponding to each component;

[0042] The associated fault state set determination module is used to obtain multiple power distribution system planning schemes corresponding to the power distribution system, determine the newly added components corresponding to each of the multiple power distribution system planning schemes, enumerate the associated fault scenarios corresponding to the newly added components, and generate the associated fault state sets corresponding to each of the multiple power distribution system planning schemes based on the associated fault scenarios;

[0043] The second reliability index calculation module is used to quantify the associated fault state set to obtain the reliability increments corresponding to each of the multiple power distribution system planning schemes, and calculate the second reliability index corresponding to each of the multiple power distribution system planning schemes based on the reliability increments and the first reliability index;

[0044] The optimal distribution system planning scheme determination module is used to determine the optimal distribution system planning scheme among the multiple distribution system planning schemes based on the second reliability index, and improve the distribution system based on the optimal distribution system planning scheme to obtain an improved distribution system.

[0045] In a possible implementation, the first reliability index calculation module is used to calculate the first reliability index of the power distribution system based on the fault state set, the number of components, and the component information corresponding to each component, specifically including:

[0046] Based on the fault state set, the number of components, and component information corresponding to each component, wherein the component information includes component unavailability rate and fault state impact amount;

[0047] The fault state set, the number of components, the component unavailability rate and the fault state impact amount are input into a preset first reliability index calculation formula to obtain a first reliability index of the power distribution system; wherein the preset first reliability index calculation formula is as follows:

[0048]

[0049] In the formula, R ex is the first reliability index, N is the number of components in the power distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the power distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, is the k-order subset of fault state s, w is the system fault state element in the k-order subset of system fault state s, I w is the fault state impact quantity corresponding to the system fault state element w.

[0050] In a possible implementation, the associated fault state set determination module is used to enumerate the associated fault scenarios corresponding to the newly added components, and generate the associated fault state sets corresponding to the multiple power distribution system planning schemes based on the associated fault scenarios, specifically including:

[0051] Obtaining grid topology diagrams corresponding to each of the plurality of power distribution system planning schemes, and enumerating all single-element associated fault scenarios and all double-element associated fault scenarios corresponding to the newly added components based on the grid topology diagrams;

[0052] Based on the all single-component fault scenarios and the all dual-component fault scenarios, associated fault state sets corresponding to the multiple power distribution system planning schemes are determined.

[0053] In a possible implementation, the second reliability index calculation module is used to quantify the associated fault state set to obtain the reliability increments corresponding to the plurality of distribution system planning schemes, specifically including:

[0054] Obtain the parallel fault impact difference and the target fault state probability corresponding to each target fault state in the associated fault state set, substitute the parallel fault impact difference, the target fault state probability and the associated fault state set into a preset reliability increment calculation formula, and obtain the reliability increments corresponding to each of the multiple distribution system planning schemes, wherein the reliability increment calculation formula is as follows:

[0055]

[0056] Where ΔR is the reliability increment, Ω ex is the fault state set corresponding to the power distribution system, is the associated fault state set corresponding to the distribution system planning scheme, y is the target fault state in the associated fault state set, A fault condition in which a new component is included in the power distribution system planning scheme. The distribution system planning includes M-1 fault states of the newly added components, M is the fault state corresponding to k newly added components, and M=2 k , ΔI y is the parallel fault impact difference corresponding to the target fault state, P y is the target failure state probability.

[0057] In a possible implementation, the optimal power distribution system planning scheme determining module is used to determine the optimal power distribution system planning scheme among the multiple power distribution system planning schemes based on the second reliability index, specifically including:

[0058] Based on the second reliability index, calculate the reliability cost and commission measure cost corresponding to each of the plurality of distribution system planning schemes, and based on the reliability cost and commission measure cost, determine the reliability commission benefits corresponding to each of the plurality of distribution system planning schemes;

[0059] Based on the reliability commission benefit, determine the optimal distribution system planning scheme among the multiple distribution system planning schemes.

[0060] In a possible implementation, the optimal power distribution system planning scheme determining module is used to calculate the reliability costs corresponding to each of the plurality of power distribution system planning schemes based on the second reliability index, specifically including:

[0061] The second reliability index is input into a preset power outage loss calculation formula to obtain a power outage loss value, and the power outage loss value is used as the reliability cost corresponding to each of the multiple distribution system planning schemes; wherein the preset power outage loss calculation formula is as follows:

[0062]

[0063] In the formula, C saveis the power outage loss, bus is the number of system nodes, state is the number of system fault states, BusPLC is the second reliability indicator of the node under a certain fault state, which refers to the load reduction probability of the load node, BusType is the node type, including commercial, industrial, and residential loads, f(BusPLC, BusType) is the power outage loss function under different load types and different power outage times, in yuan / kW, and BusLCsum is the expected power shortage of the load node.

[0064] In a possible implementation, the optimal power distribution system planning scheme determining module is used to calculate the commission measure costs corresponding to each of the multiple power distribution system planning schemes based on the second reliability index, specifically including:

[0065] Respectively obtaining corresponding operating cost related parameters from the plurality of power distribution system planning schemes, inputting the operating cost related parameters and the second reliability index into a preset operating cost calculation formula to obtain the operating cost;

[0066] Respectively obtaining corresponding investment cost related parameters from the plurality of power distribution system planning schemes, and inputting the investment cost related parameters into a preset investment cost calculation formula to obtain the investment cost;

[0067] Substituting the investment cost and the operating cost into a preset commission measure cost calculation formula to obtain the commission measure costs corresponding to each of the plurality of power distribution system planning schemes;

[0068] The preset commission measure cost calculation formula is as follows:

[0069] C add =C(I)+C(O);

[0070] The preset investment cost calculation formula is as follows:

[0071]

[0072] The preset operating cost calculation formula is as follows:

[0073]

[0074] In the formula, C add To improve the cost of measures, C(I) is the investment cost, C(O) is the operating cost, L is the line length, C line is the cost of the tie line, in yuan / km, C SOP is the investment cost of the intelligent soft switch, n is the number of intelligent soft switches, η is the line loss rate, r is the discount rate, T is the total service life, O L is the dispatching cost of the tie line, OSOP is the dispatching cost of the intelligent soft switch, μ is the second reliability index corresponding to the distribution system planning scheme, P is the transmission power between the tie line and the intelligent soft switch, S ele is the store price, S sop It is the dispatching unit price of intelligent soft switch.

[0075] The present application also provides a terminal device, including a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, and when the processor executes the computer program, it implements the evaluation method of the distribution system planning scheme as described in any one of the above.

[0076] The present application also provides a computer-readable storage medium, which includes a stored computer program, wherein when the computer program is running, the device where the computer-readable storage medium is located is controlled to execute the evaluation method of the distribution system planning scheme as described in any one of the above.

[0077] Compared with the prior art, the evaluation method, device, equipment and storage medium of a power distribution system planning scheme in the embodiment of the present application have the following beneficial effects:

[0078] By adopting a state enumeration method based on an influence increment method, the reliability of the distribution system is evaluated based on the set of fault states corresponding to the distribution system, the number of components, and the component information corresponding to each component, so as to obtain a first reliability index of the distribution system; for multiple distribution system planning schemes corresponding to the distribution system, by determining the newly added components corresponding to each of the multiple distribution system planning schemes, based on the newly added components, the associated fault state sets associated with the distribution systems of the multiple distribution system planning schemes are determined, which are used to calculate the reliability increment, and subsequently based on the reliability increment and the first reliability index, the second reliability index corresponding to each of the multiple distribution system planning schemes is calculated, which is used to determine the optimal distribution system planning scheme among the multiple distribution system planning schemes, and the distribution system is improved to obtain Improved distribution system; compared with the prior art, when faced with multiple distribution system planning schemes, it is necessary to perform independent and complete state enumeration calculations for each distribution system planning scheme, which has the problem of low evaluation efficiency; the present application studies the fault association states between multiple distribution system planning schemes and the distribution system, and only needs to enumerate the corresponding associated fault scenarios for the newly added components, and generate an associated fault state set, thereby achieving changes in reliability indicators brought about by the newly added components without recalculating the reliability indicators of the entire distribution network system; it can reduce the number of fault states that need to be calculated in detail, avoid repeated enumeration calculations of the reliability of the distribution system in each distribution system planning scheme, and improve the evaluation efficiency of multiple distribution system planning schemes in multiple distribution system planning scheme scenarios. BRIEF DESCRIPTION OF THE DRAWINGS

[0079] Figure 1 It is a flowchart of an embodiment of an evaluation method for a power distribution system planning scheme provided by the present application;

[0080] Figure 2 It is a structural schematic diagram of an embodiment of an evaluation device for a power distribution system planning scheme provided by the present application;

[0081] Figure 3 This is a parallel fault schematic diagram of an embodiment provided by the present application;

[0082] Figure 4 It is a schematic diagram of a grid topology diagram corresponding to each of multiple power distribution system planning schemes of an embodiment provided by the present application;

[0083] Figure 5 is a structural schematic diagram of a power distribution system to be improved according to an embodiment of the present application;

[0084] Figure 6 This is a schematic diagram comparing the fault state enumeration numbers of the state enumeration method and the reliability increment method according to an embodiment of the present application;

[0085] Figure 7 is a schematic diagram of expected unpowered energy EENS of a power distribution system under various schemes of an embodiment provided by the present application;

[0086] Figure 8 It is a PLC schematic diagram of load loss probability of a power distribution system under various schemes of an embodiment provided by the present application;

[0087] Fig. 9 This is a schematic diagram of the annualized cost of the interconnection lines of a power distribution system under various schemes of an embodiment provided by the present application;

[0088] Fig.10 This is a schematic diagram of reducing the annual power outage loss of the power distribution system under various schemes of an embodiment provided by the present application;

[0089] Fig.11 is the reliability benefit of the power distribution system under various schemes of an embodiment provided by the present application;

[0090] Fig.12 It is a structural schematic diagram of a terminal device provided by this application. DETAILED DESCRIPTION

[0091] The following will be combined with the drawings in this application to clearly and completely describe the technical solutions in the embodiments of this application. Obviously, the described embodiments are only part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0092] Example 1, see Figure 1 , Figure 1 is a flow chart of an embodiment of a method for evaluating a power distribution system planning scheme provided by the present application, such as Figure 1 As shown, the method includes steps 101 to 104, which are specifically as follows:

[0093] Step 101: Based on the number of components corresponding to the power distribution system and the component information corresponding to each component, a state enumeration method of an impact increment method is adopted to enumerate a set of fault states corresponding to the power distribution system, and based on the set of fault states, the number of components, and the component information corresponding to each component, a first reliability index of the power distribution system is calculated.

[0094] In the prior art, when calculating the first reliability index of the power distribution system, the traditional state enumeration method is generally used for calculation. The idea is to list all possible fault states of the power distribution system, calculate their occurrence probability and analyze the impact, obtain the expectation, and express the reliability index. The calculation formula for calculating the reliability index based on the traditional state enumeration method is as follows:

[0095] R=∑ s∈Ω I(s)P(s);

[0096]

[0097] In the formula, R is the reliability index, Ω is the set of fault states, s is the fault state, I(s) is the impact quantity under the fault state, P(s) is the probability of the fault state, and a i and u j is the availability and unavailability of components i and j, which is obtained by multiplying the availability and unavailability of each component in the response system state.

[0098] In one embodiment, the impact quantity I under the fault state may have multiple types in the process of solving different reliability indicators. For example, when calculating the expected power supply of the system, I represents the system load reduction amount, and when calculating the system load reduction probability index, I represents the load reduction flag; at the same time, when calculating the power outage loss and other node load reduction indicators, I is a matrix composed of the load reduction amounts of each node under the fault state.

[0099] Specifically, when evaluating the power shortage expectation of the system, the impact quantity I usually refers to the load reduction of the system under a specific fault state. This can be obtained by simulating or analyzing the operating state of the system under the fault condition.

[0100] Specifically, when evaluating the load shedding probability of the system, the impact quantity I may represent a binary flag or a logic value, used to indicate whether load shedding has occurred in the system; in this case, the impact quantity I may be a Boolean value or a similar indicator symbol.

[0101] Specifically, when it is necessary to calculate power outage losses or node load reduction indicators, the impact quantity I may be a matrix or vector that describes the load reduction amount of each node under the fault state; in this case, the impact quantity I contains the specific impact of the fault state on each node or area in the system, which usually needs to be obtained through simulation, model calculation or actual data analysis.

[0102] In one embodiment, due to the large scale of distribution system nodes and the complex grid structure, the traditional state enumeration method enumerates a large number of states and has low calculation efficiency. Therefore, in this embodiment, an impact increment method is proposed based on the traditional state enumeration method, and the corresponding first reliability index calculation formula is set based on this method. By reducing the impact of high-order faults on the calculation of reliability indicators, the calculation speed and accuracy of the reliability index are improved.

[0103] In one embodiment, an influence increment method is proposed based on the traditional state enumeration method, and a corresponding first reliability index calculation formula process is described based on the method:

[0104] Taking the two-component power distribution system as an example, the following formula is used:

[0105] Formula (1): R=a1a2I φ +u1a2I1+a1u2I2+u1u2I 12 ;

[0106] Formula (2): R = I φ +u1(I1-I φ )+u2(I2-I φ )+u1u2(I 12 -I1-

[0107] I2+I φ );

[0108] Formula (3):

[0109] Formula (4): R = ΔI φ +u1ΔI1+u2ΔI2+u1u2ΔI 12 ;

[0110] Formula (5): In the formula, a i is the availability of component i, u j is the unavailability rate of component j, u i is the unavailability rate of component i, u i =1-a i , I φ is the impact quantity under the fault-free state, I1 is the impact quantity under the fault of one component, I2 is the impact quantity under the fault of two components, and I 12 is the impact of all failures of components 1 and 2, ΔI s >0 is the impact increment, ΔI φ is the impact increment under the fault-free state, ΔI1 is the impact increment under the fault of 1 component, N is the number of components in the distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, I w is the influence of the fault state w,

[0111] is the k-order subset of s, and w is the system fault state element in the k-order subset of the system fault state s.

[0112] Taking the two-component distribution system as an example, the process of calculating the reliability index of the distribution system using the traditional state enumeration method is as shown in formula (1). By converting the conversion relationship between the availability rate and the unavailability rate of the component u i =1-a i , the component availability in formula (1) is converted to obtain the formula for calculating the reliability index of the distribution system based on the component unavailability rate shown in formula (2). At the same time, by defining the calculation formula of the influence increment (3), the calculation formula of the influence increment is substituted into formula (2), and the reliability calculation formula of the two-component distribution system using the state enumeration method of the influence increment method in formula (4) can be obtained. By induction, the two components in formula (4) are expanded to the distribution system of N components, and the reliability calculation formula of the N-component distribution system using the state enumeration method of the influence increment method in formula (5) is obtained.

[0113] For example, formula (3) is the calculation formula of the impact increment defined by us, where s is the fault state, ns is the number of faulty components in fault state s, and I1-I in formula (2) is φ According to formula (4), it is ΔI1, I 12 -I1-I2+Iφ Corresponding to formula (3) ns = 2, if a three-component distribution system ΔI is involved 123 If , then ΔI 123 =I 123 -I 12 -I 13 -I 23 +I1+I2+I2-I φ , thus forming formula (4), and because the impact quantity I is greater than or equal to 0, and the impact quantity of the second-order fault is greater than the first-order, such as I 12 ≥I1, so I s ≥ΔI s , so ΔI 12 12 ; and because of the ΔI in formula (4) 12 12 , it can be obtained that the impact increment method reduces the proportion of second-order faults in the index; applying it to the N-element distribution system can achieve higher calculation accuracy and improve calculation efficiency by enumerating lower-order faults.

[0114] In one embodiment, based on the above, a first reliability index calculation formula is set, wherein the preset first reliability index calculation formula is as follows:

[0115]

[0116] In the formula, R ex is the first reliability index, N is the number of components in the power distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the power distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, is the k-order subset of fault state s, w is the system fault state element in the k-order subset of system fault state s, I w is the fault state impact quantity corresponding to the system fault state element w.

[0117] In one embodiment, based on the fault state set, the number of components, and component information corresponding to each component, wherein the component information includes component unavailability rate and fault state impact amount.

[0118] ​​Specifically, a first grid topology diagram in the power distribution system is obtained, and based on the first grid topology diagram, the number of components corresponding to the power distribution system and the component information corresponding to each component, and based on the state enumeration method of the impact increment method, a set of fault states in the power distribution system is enumerated, wherein the component information includes component unavailability rate and fault state impact amount.

[0119] Specifically, after obtaining the first grid topology diagram in the distribution system, each node in the diagram is numbered based on the first grid topology diagram, and the node type and load information corresponding to each node are input, which helps to understand the structure of the distribution system and determine the various nodes in the system and their characteristics and load conditions; at the same time, according to the line first and last node numbers of the first grid topology diagram, the line information is compiled, which helps to establish the relationship between the various lines in the distribution system and clarify the connection method and path of the lines in the system; finally, according to the line type and length, the fault state rate is calculated with reference to the standard. By considering the type and length of the line and the relevant calculation method of the reference standard, the fault state rate of each line can be estimated.

[0120] Specifically, for the fault state set, all possible system fault states, such as line disconnection, node failure, etc., can be enumerated according to the first grid topology diagram and component types of the power distribution system.

[0121] Specifically, for the number of components, the number of various components in the power distribution system is counted, including but not limited to transformers, switches, lines, etc.; preferably, the number of components is equivalent to the number of nodes.

[0122] Preferably, the component information also includes component unavailability rate; the component unavailability rate refers to the probability of unavailability of a component under normal operating conditions, which can be estimated based on historical data or information provided by the manufacturer.

[0123] Specifically, the non-fault state impact quantity in the component information refers to the degree of impact of the component on the system when it operates normally, such as the conduction capacity of a transmission line.

[0124] Specifically, the fault state impact amount in the component information refers to the degree of impact on the system when a component fails, such as the short circuit impact when a line fails.

[0125] In one embodiment, the fault state set, the number of components, the component unavailability rate and the fault state impact amount are input into a preset first reliability index calculation formula to obtain a first reliability index of the power distribution system.

[0126] Step 102: Obtain multiple distribution system planning schemes corresponding to the distribution system, and determine the newly added components corresponding to each of the multiple distribution system planning schemes, enumerate the associated fault scenarios corresponding to the newly added components, and based on the associated fault scenarios, generate an associated fault state set corresponding to each of the multiple distribution system planning schemes.

[0127] In one embodiment, when improving the power distribution system, the existing power distribution system grid is preliminarily analyzed to determine the corresponding parts of the existing power distribution system that need to be improved, and multiple power distribution system planning schemes are set based on the parts that need to be improved.

[0128] In one embodiment, since the number of households corresponding to the obtained distribution system planning scheme may be multiple, if an independent and complete state enumeration calculation is required for each distribution system planning scheme based on the traditional method, some states may be repeatedly enumerated or calculated, resulting in low efficiency in scheme evaluation.

[0129] Since each distribution system planning scheme is an improvement on the original distribution system, in this embodiment, by exploring the relationship between each distribution system planning scheme and the reliability index of the existing distribution system, the number of fault states that need to be calculated in detail is reduced and the calculation efficiency is improved.

[0130] In one embodiment, when exploring the relationship between each power distribution system planning scheme and the reliability index of the existing power distribution system, it is assumed that the original system fault state set is Ω ex Now, k components are added to the original system, and the fault states of these k components are M=2 k indivual, 1≤i≤M, where represents a fault state that includes only the newly added components, All newly added components are faulty.

[0131] Calculation based on union operation It can be seen that it is a new set obtained by taking the union of each element in set A and each element in set B;

[0132]

[0133] In the formula, a i is an element of set A, b i is an element of set B.

[0134] Specifically, based on the above union calculation, the fault state set corresponding to each of the multiple distribution system planning schemes is: Among them, Ω new is the set of fault states corresponding to multiple distribution system planning schemes, Ω exis the fault state set of the power distribution system, Ω add A collection of newly added fault states.

[0135] Specifically, the new system state can be divided into two scenarios according to whether all the newly added components are faulty:

[0136] Scenario 1: All new components fail. The failure status in this scenario is Let the reliability index in this scenario be

[0137] Scenario 2: The newly added component has no fault or is partially faulty. The fault status in this scenario is Let the reliability index in this scenario be

[0138] Specifically, the reliability index of scenario 1 under all failures of newly added components is calculated based on the traditional state enumeration method as follows:

[0139]

[0140] In the formula, Add the reliability index of all components failure in scenario 1, x is the failure state, I x is the impact quantity under fault state x, R ex It is the first reliability indicator of the power distribution system. e∈N u e is the probability of failure of the newly added component, P x is the failure state probability of the original system component corresponding to the failure state.

[0141] Among them, since all the newly added components are faulty, the impact quantity I under the fault state is x The influence quantity of the corresponding fault state in the original power distribution system is the same. Under this fault state, the probability of the fault state of the original power distribution system component P x and the probability of failure of the newly added component ∏ e∈N u e Multiply them together to get the corresponding fault state probabilities of multiple distribution system planning schemes; and since all the newly added systems are faulty, the fault state and impact quantity are the same as the distribution system fault state set Ω ex The probability is the product of the original state probability and the unavailability rate of the newly added components.

[0142] Since any fault state p in multiple distribution system planning schemes can find a fault state q corresponding to it in the original distribution system, the fault state p and the fault state q are called "parallel faults", such as Figure 3 As shown, Figure 3 It is a parallel fault diagram.

[0143] Based on this principle, the reliability index of scenario 2 with no or partial failure of the newly added components is calculated as follows:

[0144] Formula (6):

[0145] Formula (7):

[0146] Formula (8):

[0147] In the formula, I p is the influence of the fault state in fault p, I q is the impact of the corresponding parallel fault, ΔI p is the difference in impact of parallel faults, P p is the probability index of the fault state in fault state p, that is, parallel fault P q The product of the availability rate and unavailability rate of the newly added components, Added reliability indicators for scenario 2 when the component is fault-free or partially faulty.

[0148] Specifically, the formula for calculating the reliability index of the newly added component without fault or partial fault in scenario 2 is shown in formula (8). By substituting formula (6) and formula (7) into formula (8), the equation process of formula (8) can be obtained.

[0149] Specifically, by calculating the reliability index of scenario 1 when all newly added components fail and the reliability index of scenario 2 when the newly added components fail or partially fail, and adding the two together, the reliability index corresponding to each of the multiple distribution system planning schemes can be obtained; as shown below:

[0150] Formula (9): In the formula, R new It is the reliability index under the distribution system planning scheme, that is, the sum of the reliability indexes under the two scenarios.

[0151] Based on the above, it can be known that the relationship between the distribution system planning scheme corresponding to the distribution system and the reliability index of the existing distribution system is to calculate the reliability increment ΔR based on the first reliability index corresponding to the original distribution system, that is, the second reliability index corresponding to each of the multiple distribution system planning schemes is the sum of the first reliability index corresponding to the distribution system and the reliability increment ΔR.

[0152] To calculate the reliability increment ΔR, it is only necessary to calculate the impact difference ΔI of parallel faults. p ≠0, which is called "associated fault", thereby further reducing the number of enumerations.

[0153] Based on the above, in this embodiment, it is only necessary to enumerate the associated fault scenarios corresponding to the newly added components and generate an associated fault state set, thereby realizing the changes in the reliability index brought about by the newly added components without recalculating the reliability index of the entire distribution network system; it can reduce the number of fault states that need to be calculated in detail and improve calculation efficiency.

[0154] In one embodiment, a grid topology diagram corresponding to each of the plurality of power distribution system planning schemes is obtained, and based on the grid topology diagram, all single-component associated fault scenarios and all double-component associated fault scenarios corresponding to the newly added components are enumerated.

[0155] Specifically, the grid topology diagrams corresponding to each of the multiple distribution system planning schemes are traversed to determine all components and their connection relationships in the grid topology diagrams corresponding to each of the multiple distribution system planning schemes, and the component numbers corresponding to each component in all the components are obtained one by one. Based on the component numbers, the newly added components corresponding to each of the multiple distribution system planning schemes are determined.

[0156] Specifically, based on the component number, when determining the new components corresponding to each of the multiple distribution system planning schemes, the first component number corresponding to all components in the distribution system is obtained. When it is detected that the obtained component number does not match the first component code, it is determined that the target component corresponding to the component number is a new component.

[0157] In one embodiment, after the newly added element is determined, the newly added element is marked; specifically, the marking process is to adjust the target color of the newly added element displayed in the grid topology diagram so as to intuitively determine the newly added element in the grid topology diagram; Figure 4 As shown, Figure 4 It is a schematic diagram of the grid topology corresponding to multiple distribution system planning schemes.

[0158] Specifically, all single-element associated fault scenarios and all dual-element associated fault scenarios are fault conditions associated with these newly added components after the newly added components are introduced; this classification helps to simplify the enumeration of fault states in a complex power distribution system.

[0159] Specifically, the single component associated fault scenario is a situation where a component fails, including a fault in a radial branch of a newly added component and a fault in a trunk line on both sides of the newly added component.

[0160] Specifically, the dual-element associated fault scenario is a situation where two elements fail, including a combined failure of a newly added element and an associated fault element in the single-element associated fault scenario.

[0161] Preferably, if the fault scenario consists of newly added components and original components, and the fault of the newly added components does not belong to the associated fault under the single-component associated fault scenario, and is independent of the original components of the fault scenario, that is, the fault impact quantity of the dual-component associated fault scenario is the sum of the fault impact quantities of the two single-component associated fault scenarios, then the dual-component associated fault scenario does not belong to the associated fault scenario.

[0162] In one embodiment, based on topological analysis, fault traversal is performed on the grid topology diagrams corresponding to each of the plurality of power distribution system planning schemes, and all single-element associated fault scenarios and all double-element associated fault scenarios corresponding to the newly added elements are enumerated.

[0163] In one embodiment, based on all the single-component fault scenarios and all the dual-component fault scenarios, associated fault state sets corresponding to each of the plurality of power distribution system planning schemes are determined.

[0164] Specifically, all single-element fault scenarios and all dual-element fault scenarios are added together to obtain associated fault state sets corresponding to each of the multiple power distribution system planning schemes.

[0165] Step 103: quantify the associated fault state set to obtain reliability increments corresponding to each of the multiple power distribution system planning schemes, and calculate second reliability indicators corresponding to each of the multiple power distribution system planning schemes based on the reliability increments and the first reliability indicator.

[0166] In one embodiment, when calculating the reliability increment based on the associated fault state set, the parallel fault impact difference and the target fault state probability corresponding to each target fault state in the associated fault state set are obtained, and the parallel fault impact difference, the target fault state probability and the associated fault state set are substituted into a preset reliability increment calculation formula to obtain the reliability increment corresponding to each of the multiple distribution system planning schemes.

[0167] In one embodiment, based on formula (9) in step 102 above, the reliability increment calculation formula is set as follows:

[0168]

[0169] Where ΔR is the reliability increment, Ω ex is the fault state set corresponding to the power distribution system, is the associated fault state set corresponding to the distribution system planning scheme, y is the target fault state in the associated fault state set, A fault condition in which a new component is included in the power distribution system planning scheme. The distribution system planning includes M-1 fault states of the newly added components, M is the fault state corresponding to k newly added components, and M=2k , ΔI y is the parallel fault impact difference corresponding to the target fault state, P y is the target failure state probability.

[0170] In one embodiment, when calculating the second reliability indicators corresponding to each of the multiple distribution system planning schemes based on the reliability increment and the first reliability indicator, the reliability increment and the first reliability indicator are added to obtain the second reliability indicators corresponding to each of the multiple distribution system planning schemes.

[0171] Step 104: Based on the second reliability index, determine the optimal distribution system planning scheme among the multiple distribution system planning schemes, and improve the distribution system based on the optimal distribution system planning scheme to obtain an improved distribution system.

[0172] In one embodiment, when determining the optimal distribution system planning scheme among the multiple distribution system planning schemes based on the second reliability index, the reliability cost and commission measure cost corresponding to each of the multiple distribution system planning schemes are calculated based on the second reliability index, and the reliability commission benefits corresponding to each of the multiple distribution system planning schemes are determined based on the reliability cost and commission measure cost; and the optimal distribution system planning scheme among the multiple distribution system planning schemes is determined based on the reliability commission benefits.

[0173] In one embodiment, since improving the reliability of the power distribution system can reduce power outage losses, including production and business interruptions, equipment damage, and impacts on user satisfaction and reputation. The reduction of these power outage losses will bring significant economic benefits. Therefore, in this embodiment, the power outage losses corresponding to the power distribution system planning scheme are calculated to determine the reliability cost corresponding to the power distribution system planning scheme.

[0174] In one embodiment, when calculating the reliability cost corresponding to the distribution system planning scheme based on the second reliability index, the second reliability index is input into a preset power outage loss calculation formula to obtain a power outage loss value, and the power outage loss value is used as the reliability cost corresponding to the distribution system planning scheme.

[0175] Specifically, before inputting the second reliability index into the preset power outage loss calculation formula to obtain the power outage loss value, it is also necessary to obtain the improved distribution system parameters corresponding to each of the multiple distribution system planning schemes, wherein the improved distribution system parameters include but are not limited to the number of system nodes, that is, the number of system components, the number of node type system fault states corresponding to each node, and the expected power shortage of the load node.

[0176] Specifically, since the reliability index of the distribution system usually includes multiple different indicators, each indicator measures the reliability of the system from a different perspective; these indicators can help power companies and system operators evaluate and improve the performance of the system; when calculating the power outage loss in this embodiment, the second reliability indicator selected is the second reliability indicator of the node under the fault state, which refers to the load reduction probability of the load node.

[0177] In one embodiment, the preset power outage loss calculation formula is as follows:

[0178]

[0179] In the formula, C save is the power outage loss, bus is the number of system nodes, state is the number of system fault states, BusPLC is the second reliability indicator of the node under a certain fault state, which refers to the load reduction probability of the load node, BusType is the node type, including commercial, industrial, and residential loads, f(BusPLC, BusType) is the power outage loss function under different load types and different power outage times, in yuan / kW, and BusLCsum is the expected power shortage of the load node.

[0180] In one embodiment, when calculating the commission measure costs corresponding to each of the multiple distribution system planning schemes based on the second reliability index, the operating cost-related parameters corresponding to each of the multiple distribution system planning schemes are respectively obtained from the multiple distribution system planning schemes, and the operating cost-related parameters and the second reliability index are input into a preset operating cost calculation formula to obtain the operating cost; the investment cost-related parameters corresponding to each of the multiple distribution system planning schemes are respectively obtained from the multiple distribution system planning schemes, and the investment cost-related parameters are input into a preset investment cost calculation formula to obtain the investment cost; the investment cost and the operating cost are substituted into the preset commission measure cost calculation formula to obtain the commission measure cost corresponding to each of the multiple distribution system planning schemes.

[0181] Specifically, the operating cost related parameters include but are not limited to the discount rate of the distribution network line, the total service life, the dispatching cost of the tie line and the dispatching cost of the intelligent soft switch, the line loss rate, the transmission power of the tie line and the intelligent soft switch, the store price and the dispatching unit price of the intelligent soft switch.

[0182] Specifically, the investment cost related parameters include but are not limited to the line length of the distribution network, the tie line cost, the investment cost of the intelligent soft switch, and the number of intelligent soft switches.

[0183] In one embodiment, the preset commission measure cost calculation formula is as follows:

[0184] C add =C(I)+C(O).

[0185] In one embodiment, the preset investment cost calculation formula is as follows:

[0186]

[0187] In one embodiment, the preset operating cost calculation formula is as follows:

[0188]

[0189] In the formula, C add To improve the cost of measures, C(I) is the investment cost, C(O) is the operating cost, L is the line length, C line is the cost of the tie line, in yuan / km, C SOP is the investment cost of the intelligent soft switch, n is the number of intelligent soft switches, η is the line loss rate, r is the discount rate, T is the total service life, O L is the dispatching cost of the tie line, O SOP is the dispatching cost of the intelligent soft switch, μ is the second reliability index corresponding to the distribution system planning scheme, P is the transmission power between the tie line and the intelligent soft switch, S ele is the store price, S sop It is the dispatching unit price of intelligent soft switch.

[0190] In one embodiment, when determining the reliability commission benefits corresponding to each of the multiple distribution system planning schemes based on the reliability cost and the commission measure cost, the first difference between the reliability cost and the commission measure cost is calculated, and the first difference is used as the reliability commission benefits corresponding to each of the multiple distribution system planning schemes.

[0191] In one embodiment, when obtaining the reliability commission benefits corresponding to each of a plurality of distribution system planning schemes and determining the optimal distribution system planning scheme based on the reliability commission benefits, the reliability commission benefits corresponding to each of the plurality of distribution system planning schemes are compared to determine the target distribution system planning scheme corresponding to the highest value of the reliability improvement benefit, and the target distribution system planning scheme is used as the optimal distribution system planning scheme of the distribution system, and is used to improve the distribution system to obtain an improved distribution system, which can comprehensively consider reliability and economic factors, accurately evaluate the cost-benefit of different distribution system planning schemes, and thus quickly determine the optimal distribution system planning scheme.

[0192] An evaluation method for a power distribution system planning scheme provided in this embodiment is verified by using an improved power distribution system calculation example, as follows:

[0193] The distribution system of the example includes 101 nodes, 68 feeders, 34 load nodes, 30 distribution transformers, circuit breakers and disconnect devices. The data are all from RBTSBus6. The average failure rate of the line is set to 0.014 times / year·meter, the MTTR is 5h, and the average failure rate of the transformer is 0.014 times / year, and the MTTR is 15h. The SOP price is 20,000 yuan / unit, the price of the three-phase AC cable is about 330,000 yuan / Km, and the SOP dispatch fee is 100 yuan / kW. In order to conduct reliability and economic coordination analysis, this paper sets: the planning period is 20 years, the inflation rate is 0.02, the nominal interest rate is 0.05, and the electricity purchase price is 0.5 yuan / kWh; Figure 5 As shown, Figure 5 It is a structural diagram of the power distribution system to be improved.

[0194] Taking the installation of tie lines and SOP equipment as an example, the candidate nodes that can be modified are selected, namely nodes 8, 24, 27, 45, 58, 74, 77, and 95 in the figure. After traversal, there are 28 modification schemes in total. The distances between the candidate nodes are shown in Table 1. Table 1 is a schematic table of the distances between the candidate nodes.

[0195] Table 1:

[0196] First Node End Node length First Node End Node length 8 24 0.467641 27 74 1.373695 8 27 0.555324 27 77 1.461378 8 45 1.08142 27 58 0.906054 8 74 1.929019 27 95 1.987474 8 77 2.016701 45 74 0.847599 8 58 1.461378 45 77 0.935282 8 95 2.542797 45 58 0.379958 24 27 0.087683 45 95 1.461378 24 45 0.613779 74 77 0.087683 24 74 1.461378 74 58 0.467641 24 77 1.549061 74 95 0.613779 24 58 0.993737 77 58 0.555324 24 95 2.075157 77 95 0.526096 27 45 0.526096 58 95 1.08142

[0197] For the tie line added between nodes 8 and 74, the number of state enumerations required is as follows: Figure 6 As shown, Figure 6 This is a schematic diagram comparing the fault state enumeration number of the state enumeration method and the reliability increment method; it can be seen that the incremental calculation method greatly reduces the number of states that need to be calculated.

[0198] like Figure 7 As shown, Figure 7 This is a schematic diagram of the expected unpowered power EENS of the distribution system under various schemes. The reliability index selected in this figure is the expected unpowered power EENS of the distribution system. Figure 8 As shown, Figure 8 It is a schematic diagram of the load loss probability PLC of the distribution system under various schemes, where the expected unpowered energy EENS and the load loss probability PLC are different types of reliability indicators.

[0199] like Fig. 9 As shown, Fig. 9 It is a schematic diagram of the annualized cost of the interconnection line of the distribution system under various schemes; Fig.10 As shown, Fig.10 is a schematic diagram of the reduction of annual power outage losses of the distribution system under various schemes; the comprehensive consideration of the two can obtain the total benefits of improving marginal costs and reliability under various modification schemes, such as Fig.11As shown, Fig.11 is the reliability benefit of the distribution system under various schemes.

[0200] Depend on Figure 7 and Figure 8 As shown in the figure, based on the detailed analysis of EENS and PLC indicators, we draw the following conclusions: Among the 28 modification schemes, the scheme with the lowest EENS value is Scheme 22, whose EENS value is 10.5029; this means that Scheme 22 is the best in reducing system power outage time and can significantly improve system reliability; on the other hand, for the scheme with the lowest PLC value, Scheme 25 performs best, and its PLC value is 3.51E-05; Scheme 25 is the best in reducing the probability of system failure, and the system operation stability is higher; therefore, we need to consider from an economic perspective, fully consider the improvement cost and operating cost increase brought about by reliability improvement measures, as well as the reduction of power outage losses brought about by the improvement of distribution system reliability, obtain the reliability improvement benefits, and select the optimal improvement scheme.

[0201] By observation Fig. 9 — Fig.11 It can be found that the 8th improvement plan has the lowest annual cost for the interconnection line, but the reduction in power outage losses is also small. Therefore, although this modification plan has benefits in reliability and economy, it is still not the optimal plan. On the contrary, the 22nd plan has a higher annual modification cost, but because the reliability of the large load nodes is significantly improved under this modification plan, the annual power outage loss reduction is significantly increased, and the comprehensive reliability benefit is the highest. Therefore, the 22nd modification plan is the optimal plan.

[0202] Example 2, see Figure 2 , Figure 2 is a structural schematic diagram of an embodiment of an evaluation device for a power distribution system planning scheme provided by the present application, such as Figure 2 As shown, the device includes a first reliability index calculation module 201, an associated fault state set determination module 202, a second reliability index calculation module 203 and an optimal distribution system planning scheme determination module 204, which are specifically as follows:

[0203] The first reliability index calculation module 201 is used to enumerate the set of fault states corresponding to the power distribution system based on the number of components corresponding to the power distribution system and the component information corresponding to each component, using the state enumeration method of the influence increment method, and calculate the first reliability index of the power distribution system based on the set of fault states, the number of components, and the component information corresponding to each component;

[0204] The associated fault state set determination module 202 is used to obtain multiple power distribution system planning schemes corresponding to the power distribution system, determine the newly added components corresponding to each of the multiple power distribution system planning schemes, enumerate the associated fault scenarios corresponding to the newly added components, and generate the associated fault state sets corresponding to each of the multiple power distribution system planning schemes based on the associated fault scenarios;

[0205] The second reliability index calculation module 203 is used to quantify the associated fault state set to obtain the reliability increments corresponding to each of the multiple power distribution system planning schemes, and calculate the second reliability index corresponding to each of the multiple power distribution system planning schemes based on the reliability increments and the first reliability index;

[0206] The optimal power distribution system planning scheme determining module 204 is used to determine the optimal power distribution system planning scheme among the multiple power distribution system planning schemes based on the second reliability index, and improve the power distribution system based on the optimal power distribution system planning scheme to obtain an improved power distribution system.

[0207] In one embodiment, the first reliability index calculation module 201 is used to calculate the first reliability index of the power distribution system based on the fault state set, the number of components, and the component information corresponding to each component, specifically including: based on the fault state set, the number of components, and the component information corresponding to each component, wherein the component information includes component unavailability rate and fault state impact amount; inputting the fault state set, the number of components, the component unavailability rate and the fault state impact amount into a preset first reliability index calculation formula to obtain the first reliability index of the power distribution system; wherein the preset first reliability index calculation formula is as follows:

[0208]

[0209] In the formula, R ex is the first reliability index, N is the number of components in the power distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the power distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, is the k-order subset of fault state s, w is the system fault state element in the k-order subset of system fault state s, I w is the fault state impact quantity corresponding to the system fault state element w.

[0210] In one embodiment, the associated fault state set determination module 202 is used to enumerate the associated fault scenarios corresponding to the newly added components, and based on the associated fault scenarios, generate the associated fault state sets corresponding to each of the multiple distribution system planning schemes, specifically including: obtaining the grid topology diagrams corresponding to each of the multiple distribution system planning schemes, and based on the grid topology diagrams, enumerating all single-component associated fault scenarios and all dual-component associated fault scenarios corresponding to the newly added components; based on all the single-component fault scenarios and all the dual-component fault scenarios, determining the associated fault state sets corresponding to each of the multiple distribution system planning schemes.

[0211] In one embodiment, the second reliability index calculation module 203 is used to quantify the associated fault state set to obtain the reliability increments corresponding to each of the multiple distribution system planning schemes, specifically including: obtaining the parallel fault impact difference and the target fault state probability corresponding to each target fault state in the associated fault state set, substituting the parallel fault impact difference, the target fault state probability and the associated fault state set into a preset reliability increment calculation formula to obtain the reliability increment corresponding to each of the distribution system planning schemes, wherein the reliability increment calculation formula is as follows:

[0212]

[0213] Where ΔR is the reliability increment, Ω ex is the fault state set corresponding to the power distribution system, is the associated fault state set corresponding to the distribution system planning scheme, y is the target fault state in the associated fault state set, A fault condition in which a new component is included in the power distribution system planning scheme. The distribution system planning includes M-1 fault states of the newly added components, M is the fault state corresponding to k newly added components, and M=2 k , ΔI y is the parallel fault impact difference corresponding to the target fault state, P y is the target failure state probability.

[0214] In one embodiment, the optimal distribution system planning scheme determination module 204 is used to determine the optimal distribution system planning scheme among the multiple distribution system planning schemes based on the second reliability index, specifically including: calculating the reliability cost and commission measure cost corresponding to each of the multiple distribution system planning schemes based on the second reliability index, and determining the reliability commission benefits corresponding to each of the multiple distribution system planning schemes based on the reliability cost and commission measure cost; and determining the optimal distribution system planning scheme among the multiple distribution system planning schemes based on the reliability commission benefits.

[0215] In one embodiment, the optimal power distribution system planning scheme determination module 204 is used to calculate the reliability cost corresponding to each of the multiple power distribution system planning schemes based on the second reliability index, specifically including: inputting the second reliability index into a preset power outage loss calculation formula to obtain a power outage loss value, and using the power outage loss value as the reliability cost corresponding to each of the multiple power distribution system planning schemes; wherein the preset power outage loss calculation formula is as follows:

[0216]

[0217] In the formula, C save is the power outage loss, bus is the number of system nodes, state is the number of system fault states, BusPLC is the second reliability indicator of the node under a certain fault state, which refers to the load reduction probability of the load node, BusType is the node type, including commercial, industrial, and residential loads, f(BusPLC, BusType) is the power outage loss function under different load types and different power outage times, in yuan / kW, and BusLCsum is the expected power shortage of the load node.

[0218] In one embodiment, the optimal distribution system planning scheme determination module 204 is used to calculate the commission measure cost corresponding to each of the multiple distribution system planning schemes based on the second reliability index, specifically including: obtaining the corresponding operating cost related parameters from the multiple distribution system planning schemes, inputting the operating cost related parameters and the second reliability index into a preset operating cost calculation formula to obtain the operating cost; obtaining the corresponding investment cost related parameters from the multiple distribution system planning schemes, inputting the investment cost related parameters into a preset investment cost calculation formula to obtain the investment cost; substituting the investment cost and the operating cost into the preset commission measure cost calculation formula to obtain the commission measure cost corresponding to each of the multiple distribution system planning schemes; wherein the preset commission measure cost calculation formula is as follows:

[0219] C add =C(I)+C(O);

[0220] The preset investment cost calculation formula is as follows:

[0221]

[0222] The preset operating cost calculation formula is as follows:

[0223]

[0224] In the formula, C addTo improve the cost of measures, C(I) is the investment cost, C(O) is the operating cost, L is the line length, C line is the cost of the tie line, in yuan / km, C SOP is the investment cost of the intelligent soft switch, n is the number of intelligent soft switches, η is the line loss rate, r is the discount rate, T is the total service life, O L is the dispatching cost of the tie line, O SOP is the dispatching cost of the intelligent soft switch, μ is the second reliability index corresponding to the distribution system planning scheme, P is the transmission power between the tie line and the intelligent soft switch, S ele is the store price, S sop It is the dispatching unit price of intelligent soft switch.

[0225] In one embodiment, the optimal distribution system planning scheme determination module 204 is used to determine the reliability commission benefits corresponding to each of the multiple distribution system planning schemes based on the reliability cost and the commission measure cost, specifically including: calculating the first difference between the reliability cost and the commission measure cost, and using the first difference as the reliability commission benefit corresponding to each of the multiple distribution system planning schemes.

[0226] The above-mentioned distribution system planning scheme evaluation device can implement the distribution system planning scheme evaluation method of the above-mentioned method embodiment. The options in the above-mentioned method embodiment are also applicable to this embodiment and will not be described in detail here.

[0227] Fig.12 A schematic diagram of the structure of a terminal device. Fig.12 As shown, the terminal device 12 of this embodiment includes: at least one processor 1201 ( Fig.12 Only one is shown in the figure) a processor, a memory 1202, and a computer program 1203 stored in the memory 1202 and executable on at least one processor 1201, and when the processor 1201 executes the computer program 1203, the steps in any of the above method embodiments are implemented.

[0228] The terminal device 12 may be a computing device such as a smart phone, a laptop, a tablet computer, and a desktop computer. The terminal device may include but is not limited to a processor 1201 and a memory 1202. Those skilled in the art will appreciate that Fig.12 It is only an example of the terminal device 12 and does not constitute a limitation on the terminal device 12. It may include more or fewer components than shown in the figure, or a combination of certain components, or different components, for example, it may also include input and output devices, network access devices, etc.

[0229] The processor 1201 may be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA), or other programmable logic devices, discrete gate or transistor logic devices, discrete hardware components, etc. A general-purpose processor may be a microprocessor or any conventional processor, etc.

[0230] In some embodiments, the memory 1202 may be an internal storage unit of the terminal device 12, such as a hard disk or memory of the terminal device 12. In other embodiments, the memory 1202 may also be an external storage device of the terminal device 12, such as a plug-in hard disk, a smart memory card (SmartMediaCard, SMC), a secure digital (SecureDigital, SD) card, a flash card (FlashCard), etc. equipped on the terminal device 12. Further, the memory 1202 may also include both an internal storage unit of the terminal device 12 and an external storage device. The memory 1202 is used to store an operating system, an application program, a boot loader (BootLoader), data, and other programs, such as program codes of computer programs, etc. The memory 1202 may also be used to temporarily store data that has been output or is to be output.

[0231] In addition, an embodiment of the present application further provides a computer-readable storage medium, which stores a computer program. When the computer program is executed by a processor, the steps in any of the above method embodiments are implemented.

[0232] In several embodiments provided in the present application, it is understood that each box in the flow chart or block diagram can represent a module, a program segment or a part of a code, and a module, a program segment or a part of a code includes one or more executable instructions for realizing a specified logical function. It should also be noted that in some alternative implementations, the functions marked in the box can also occur in a different order from that marked in the accompanying drawings. For example, two consecutive boxes can actually be executed substantially in parallel, and they can sometimes also be executed in the opposite order, depending on the functions involved.

[0233] If the function is implemented in the form of a software function module and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can essentially be embodied in the form of a software product, or in other words, the part that contributes to the prior art or the part of the technical solution. The computer software product is stored in a storage medium, including a number of instructions for a terminal device to execute all or part of the steps of each embodiment method of the present application. The aforementioned storage medium includes: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), disk or optical disk and other media that can store program code.

[0234] In summary, the present application provides an evaluation method, device, equipment and storage medium for a distribution system planning scheme, which adopts a state enumeration method of an impact increment method, and calculates a first reliability index of a distribution system based on the enumerated fault state set, the number of components, and the component information corresponding to each component of the distribution system; obtains newly added components corresponding to each of multiple distribution system planning schemes of the distribution system, and enumerates associated fault scenarios corresponding to the newly added components to generate an associated fault state set; quantifies the associated fault state set to obtain a reliability increment corresponding to each of multiple distribution system planning schemes, and calculates a second reliability index corresponding to each of the multiple distribution system planning schemes based on the reliability increment and the first reliability index; is used to determine the optimal distribution system planning scheme, and improve the distribution system to obtain an improved distribution system; compared with the prior art, the present application can improve the evaluation efficiency of multiple distribution system planning schemes.

[0235] The above is only a preferred implementation of the present application. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present application. These improvements and substitutions should also be regarded as the scope of protection of the present application.

Claims

1. A method for evaluating distribution system planning schemes, It is characterized in that include: Based on the number of components corresponding to the power distribution system and the component information corresponding to each component, a state enumeration method of an influence increment method is adopted to enumerate a set of fault states corresponding to the power distribution system, and based on the set of fault states, the number of components, and the component information corresponding to each component, a first reliability index of the power distribution system is calculated; Acquire multiple power distribution system planning schemes corresponding to the power distribution system, determine newly added components corresponding to each of the multiple power distribution system planning schemes, enumerate associated fault scenarios corresponding to the newly added components, and generate associated fault state sets corresponding to each of the multiple power distribution system planning schemes based on the associated fault scenarios; Quantifying the associated fault state set to obtain reliability increments corresponding to each of the plurality of power distribution system planning schemes, and calculating second reliability indicators corresponding to each of the plurality of power distribution system planning schemes based on the reliability increments and the first reliability indicator; Based on the second reliability index, an optimal power distribution system planning scheme among the multiple power distribution system planning schemes is determined, and the power distribution system is improved based on the optimal power distribution system planning scheme to obtain an improved power distribution system.

2. A method for evaluating a power distribution system planning scheme as claimed in claim 1, It is characterized in that Calculating a first reliability index of the power distribution system based on the fault state set, the number of components, and component information corresponding to each component specifically includes: Based on the fault state set, the number of components, and component information corresponding to each component, wherein the component information includes component unavailability rate and fault state impact amount; The fault state set, the number of components, the component unavailability rate and the fault state impact amount are input into a preset first reliability index calculation formula to obtain a first reliability index of the power distribution system; wherein the preset first reliability index calculation formula is as follows: In the formula, R ex is the first reliability index, N is the number of components in the power distribution system, s is the fault state, Ω is the set of fault states, A is the set of all components in the power distribution system, is the k-order subset of A, i is the i-th element, u i is the component unavailability rate of the i-th component, ΔI s is the impact increment, n s is the number of faulty components in fault state s, is the k-order subset of fault state s, w is the system fault state element in the k-order subset of system fault state s, I w is the fault state impact quantity corresponding to the system fault state element w.

3. A method for evaluating a power distribution system planning scheme as claimed in claim 1, It is characterized in that Enumerating the associated fault scenarios corresponding to the newly added components, and generating the associated fault state sets corresponding to the multiple power distribution system planning schemes based on the associated fault scenarios, specifically including: Obtaining grid topology diagrams corresponding to each of the plurality of power distribution system planning schemes, and enumerating all single-element associated fault scenarios and all double-element associated fault scenarios corresponding to the newly added components based on the grid topology diagrams; Based on the all single-component fault scenarios and the all dual-component fault scenarios, associated fault state sets corresponding to the multiple power distribution system planning schemes are determined.

4. A method for evaluating a power distribution system planning scheme as claimed in claim 1, It is characterized in that The associated fault state set is quantified to obtain the reliability increments corresponding to the multiple power distribution system planning schemes, specifically including: Obtain the parallel fault impact difference and the target fault state probability corresponding to each target fault state in the associated fault state set, substitute the parallel fault impact difference, the target fault state probability and the associated fault state set into a preset reliability increment calculation formula, and obtain the reliability increments corresponding to each of the multiple distribution system planning schemes, wherein the reliability increment calculation formula is as follows: Where ΔR is the reliability increment, Ω ex is the fault state set corresponding to the power distribution system, is the associated fault state set corresponding to the distribution system planning scheme, y is the target fault state in the associated fault state set, A fault condition in which a new component is included in the power distribution system planning scheme. The distribution system planning includes M-1 fault states of the newly added components, M is the fault state corresponding to k newly added components, and M=2 k , ΔI y is the parallel fault impact difference corresponding to the target fault state, P y is the target failure state probability.

5. A method for evaluating a power distribution system planning scheme as claimed in claim 1, It is characterized in that Determining the optimal power distribution system planning scheme among the multiple power distribution system planning schemes based on the second reliability index specifically includes: Based on the second reliability index, calculate the reliability cost and commission measure cost corresponding to each of the plurality of distribution system planning schemes, and based on the reliability cost and commission measure cost, determine the reliability commission benefits corresponding to each of the plurality of distribution system planning schemes; Based on the reliability commission benefit, determine the optimal distribution system planning scheme among the multiple distribution system planning schemes.

6. A method for evaluating a power distribution system planning scheme as claimed in claim 5, It is characterized in that Calculating the reliability costs corresponding to each of the plurality of power distribution system planning schemes based on the second reliability index specifically includes: The second reliability index is input into a preset power outage loss calculation formula to obtain a power outage loss value, and the power outage loss value is used as the reliability cost corresponding to each of the multiple distribution system planning schemes; wherein the preset power outage loss calculation formula is as follows: In the formula, C save is the power outage loss, bus is the number of system nodes, state is the number of system fault states, BusPLC is the second reliability indicator of the node under a certain fault state, which refers to the load reduction probability of the load node, BusType is the node type, including commercial, industrial, and residential loads, f(BusPLC, BusType) is the power outage loss function under different load types and different power outage times, in yuan / kW, and BusLCsum is the expected power shortage of the load node.

7. A method for evaluating a power distribution system planning scheme as claimed in claim 5, It is characterized in that Calculating the commission measure costs corresponding to each of the plurality of power distribution system planning schemes based on the second reliability index specifically includes: Respectively obtaining corresponding operating cost related parameters from the plurality of power distribution system planning schemes, inputting the operating cost related parameters and the second reliability index into a preset operating cost calculation formula to obtain the operating cost; Respectively obtaining corresponding investment cost related parameters from the plurality of power distribution system planning schemes, and inputting the investment cost related parameters into a preset investment cost calculation formula to obtain the investment cost; Substituting the investment cost and the operating cost into a preset commission measure cost calculation formula to obtain the commission measure costs corresponding to each of the plurality of power distribution system planning schemes; The preset commission measure cost calculation formula is as follows: C add =C(I)+C(O); The preset investment cost calculation formula is as follows: The preset operating cost calculation formula is as follows: In the formula, C add To improve the cost of measures, C(I) is the investment cost, C(O) is the operating cost, L is the line length, C line is the cost of the tie line, in yuan / km, C SOP is the investment cost of the intelligent soft switch, n is the number of intelligent soft switches, η is the line loss rate, r is the discount rate, T is the total service life, O L is the dispatching cost of the tie line, O SOP is the dispatching cost of the intelligent soft switch, μ is the second reliability index corresponding to the distribution system planning scheme, P is the transmission power between the tie line and the intelligent soft switch, S ele is the store price, S sop It is the dispatching unit price of intelligent soft switch.

8. An evaluation device for a power distribution system planning scheme, It is characterized in that include: A first reliability index calculation module, an associated fault state set determination module, a second reliability index calculation module and an optimal distribution system planning scheme determination module; The first reliability index calculation module is used to enumerate the set of fault states corresponding to the power distribution system based on the number of components corresponding to the power distribution system and the component information corresponding to each component, using the state enumeration method of the influence increment method, and calculate the first reliability index of the power distribution system based on the set of fault states, the number of components, and the component information corresponding to each component; The associated fault state set determination module is used to obtain multiple power distribution system planning schemes corresponding to the power distribution system, determine the newly added components corresponding to each of the multiple power distribution system planning schemes, enumerate the associated fault scenarios corresponding to the newly added components, and generate the associated fault state sets corresponding to each of the multiple power distribution system planning schemes based on the associated fault scenarios; The second reliability index calculation module is used to quantify the associated fault state set to obtain the reliability increments corresponding to each of the multiple power distribution system planning schemes, and calculate the second reliability index corresponding to each of the multiple power distribution system planning schemes based on the reliability increments and the first reliability index; The optimal distribution system planning scheme determination module is used to determine the optimal distribution system planning scheme among the multiple distribution system planning schemes based on the second reliability index, and improve the distribution system based on the optimal distribution system planning scheme to obtain an improved distribution system.

9. A terminal device, It is characterized in that The method comprises a processor, a memory, and a computer program stored in the memory and configured to be executed by the processor, wherein when the processor executes the computer program, the method for evaluating the distribution system planning scheme according to any one of claims 1 to 7 is implemented.

10. A computer-readable storage medium, It is characterized in that The computer-readable storage medium includes a stored computer program, wherein when the computer program is executed, the device where the computer-readable storage medium is located is controlled to execute the evaluation method for the distribution system planning scheme according to any one of claims 1 to 7.