Anti-seepage structure for soft soil foundation
By arranging anti-seepage insert plates and limiting collars in the composite foundation structure, combined with foundation pile components and mattress layers, the problem of seepage damage caused by soil consolidation and settlement between piles in soft soil foundations is solved, and the stability of the structure is improved. And anti-slip ability, extending service life.
Patent Information
- Application Number
- CN202411042942.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-10-11
AI Technical Summary
In the existing composite foundation structure under soft soil conditions, the consolidation and settlement of the soil between the piles leads to the voiding of the soil between the foundation floor and the piles, forming a channel, which is prone to seepage damage and affects the safety of the overall structure.
Set foundation pile components below the base component and fill the soil between the piles. At least an anti-seepage inserting plate is provided between two adjacent foundation pile components on the upstream side of the foundation to form a dumbbell-shaped anti-seepage closure to prevent water leakage. , and improve the anti-slip stability and anti-seepage effect through the limiting ferrule and mattress layer.
It can effectively prevent penetration damage, improve the stability and anti-skid ability of the overall structure in soft soil foundation, extend the service life, and reduce the cost and construction complexity of the structure.
Smart Images

Figure CN118756741A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to an anti-seepage structure for soft soil foundation. Background Art
[0002] In lakeside and riverside areas, deep soft soil foundations such as silt soil, silt and peat interlayer soil are often encountered. Under this terrain, the foundation requirements for water retaining buildings must not only meet the vertical bearing capacity requirements, but also meet the anti-sliding stability and anti-seepage requirements, making the foundation treatment of water retaining buildings more complicated. Water retaining buildings such as sluices, pumping stations, and flood control walls often use pile foundations, cement mixing pile composite foundations, CFG composite foundations, and pile composite foundations under soft soil foundation conditions.
[0003] Existing composite foundation structures usually include a foundation slab and multiple foundation piles. The foundation piles are set at the bottom of the slab to carry the load, and the soil between the piles is filled around the foundation piles to carry the load together. However, due to the presence of underground seepage in lakeside and riverside areas, when the soil between the piles consolidates and settles, causing the foundation slab and the soil between the piles to become empty, a channel is formed between the foundation slab and the soil between the piles, which is prone to penetration damage and affects the safety of the overall structure. Summary of the invention
[0004] The present invention provides an anti-seepage structure for soft soil foundation, which solves the technical problem that when the soil between piles consolidates and settles, resulting in the void between the foundation bottom plate and the soil between piles, a channel is formed between the foundation bottom plate and the soil between piles, which is prone to seepage damage and affects the safety of the overall structure.
[0005] In view of this, the present invention provides an anti-seepage structure for soft soil foundation, comprising:
[0006] Base components;
[0007] A plurality of pile foundation assemblies are arranged at the bottom of the base assembly, and the plurality of pile foundation assemblies are regularly arranged in an array on a horizontal plane; the bottom of the base assembly and the surrounding sides of the pile foundation assemblies are filled with inter-pile soil;
[0008] Among them, an anti-seepage plug plate is provided between at least two adjacent pile foundation assemblies located on the upstream side of the foundation, which is used to prevent water from leaking into between multiple groups of pile foundation assemblies; the top of the anti-seepage plug plate is connected to the base layer assembly, and the bottom is inserted in the soil between the piles; the two sides of each anti-seepage plug plate are respectively connected to the two adjacent pile foundation assemblies.
[0009] Optionally, the pile foundation assembly includes a limiting ring and a pile foundation; the anti-seepage plug plate is connected to the limiting ring; the top of the limiting ring is connected to the bottom of the base assembly; the top of the pile foundation extends into the limiting ring, and the inner wall of the limiting ring and the surrounding side of the pile foundation are filled with the inter-pile soil; a cushion layer is filled between the base assembly and the top end face of the pile foundation, the base assembly is connected to the pile foundation through the cushion layer, and the cushion layer is located in the limiting ring.
[0010] Optionally, the top of the limiting ring is embedded in the base component.
[0011] Optionally, a plug-in groove is provided on the peripheral side of the limiting ring corresponding to the anti-seepage plug plate, and the peripheral edge of the anti-seepage plug plate is adapted to be plugged into the plug-in groove.
[0012] Optionally, the mattress layer includes at least one of gravel and mud stones.
[0013] Optionally, the horizontal cross-section of the limiting ring is circular or rectangular.
[0014] Optionally, the top of the anti-seepage plug plate is embedded in the base component.
[0015] Optionally, an anti-seepage plug plate is provided between two adjacent pile assemblies located on the upstream side and the downstream side of the foundation.
[0016] Optionally, an anti-seepage plug plate is provided between two adjacent pile assemblies located at the periphery of the foundation.
[0017] Optionally, the base component includes a waterproof base plate and a plain concrete cushion layer arranged in sequence from top to bottom.
[0018] The technical solution of the present invention has the following advantages:
[0019] 1. In the present invention, a foundation pile assembly is arranged below the base assembly and a composite body is formed between the filling piles to form a support structure for supporting the base assembly, so as to facilitate bearing horizontal loads and meet the overall anti-slip stability requirements.
[0020] 2. In the present invention, an anti-seepage plug is provided between at least two adjacent pile assemblies located on the upstream side of the foundation. The anti-seepage plug and the two adjacent pile assemblies together form a dumbbell-shaped anti-seepage closed body, thereby improving the anti-seepage effect. When the consolidation and settlement of the soil between the piles causes the base assembly and the soil between the piles to become hollow, the anti-seepage plug blocks the upstream seepage water from flowing into the channel formed between the base assembly and the soil between the piles, thereby avoiding seepage damage, improving the stability of the overall structure in the soft soil foundation, and thus ensuring the safety of the overall structure and increasing its service life.
[0021] 3. In the present invention, the provision of the anti-seepage plug increases the overall contact area with the soil in the horizontal direction, thereby improving the overall anti-slip ability. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0023] Figure 1 A structural cross-sectional view of the anti-seepage structure for soft soil foundation provided by the present invention at a first viewing angle;
[0024] Figure 2 A structural cross-sectional view of the anti-seepage structure for soft soil foundation according to the first embodiment of the present invention at a second viewing angle;
[0025] Figure 3 A structural cross-sectional view of an anti-seepage structure for soft soil foundation according to a second embodiment of the present invention at a second viewing angle;
[0026] Figure 4 A schematic structural diagram of the connection between the limiting collar and the anti-seepage plug plate provided by the present invention.
[0027] Description of reference numerals:
[0028] 1. Base components; 11. Waterproof bottom plate; 12. Plain concrete cushion layer; 2. Anti-seepage plug plate; 3. Pile assembly; 31. Limiting ring; 32. Pile; 33. Cushion layer; 4. Soil between piles. DETAILED DESCRIPTION
[0029] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0031] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0032] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0033] Example 1
[0034] See also Figures 1 to 4 The present embodiment provides an anti-seepage structure for soft soil foundation, comprising: a base component 1; a plurality of pile foundation components 3, which are arranged at the bottom of the base component 1, and the plurality of pile foundation components 3 are regularly arranged in an array on a horizontal plane; the bottom of the base component 1 and the surrounding sides of the pile foundation components 3 are filled with inter-pile soil 4; wherein, an anti-seepage plug plate 2 is provided between at least two adjacent pile foundation components 3 located on the upstream side of the foundation, for preventing water from leaking into the space between the plurality of pile foundation components 3; the top of the anti-seepage plug plate 2 is connected to the base component 1, and the bottom is inserted into the inter-pile soil 4; the two sides of each anti-seepage plug plate 2 are respectively connected to two adjacent pile foundation components 3.
[0035] It should be noted that the upstream side of the foundation refers to the upstream side of the water flow along the lakeside and riverside areas.
[0036] In this embodiment, a foundation pile assembly 3 and a composite body formed between the filling piles are arranged below the base assembly 1 to form a supporting structure for supporting the base assembly 1, so as to facilitate bearing horizontal loads and meet the overall anti-slip stability requirements. At the same time, an anti-seepage plug plate 2 is arranged between at least two adjacent foundation pile assemblies 3 located on the upstream side of the foundation. The anti-seepage plug plate 2 and the two adjacent foundation pile assemblies 3 together form a dumbbell-shaped anti-seepage closed body to improve the anti-seepage effect. When the consolidation and settlement of the soil 4 between the piles causes the base assembly 1 and the soil 4 between the piles to be emptied, the anti-seepage plug plate 2 is used to block the upstream seepage water from flowing into the channel formed between the base assembly 1 and the soil 4 between the piles, so as to avoid penetration damage, improve the stability of the overall structure in the soft soil foundation, and thus ensure the safety of the overall structure and increase the service life. In addition, the setting of the anti-seepage plug plate 2 increases the overall contact area with the soil in the horizontal direction, thereby improving the overall anti-slip ability.
[0037] Example 2
[0038] As a further improvement to Example 1, Figures 1 to 4 As shown, the pile assembly 3 includes a limiting ring 31 and a pile 32; the anti-seepage plug plate 2 is connected to the limiting ring 31; the top of the limiting ring 31 is connected to the bottom of the base assembly 1; the top of the pile 32 extends into the limiting ring 31, and the inner wall of the limiting ring 31 and the surrounding side of the pile 32 are filled with inter-pile soil 4; the base assembly 1 and the top end surface of the pile 32 are filled with a cushion layer 33, the base assembly 1 is connected to the pile 32 through the cushion layer 33, and the cushion layer 33 is located in the limiting ring 31.
[0039] It should be noted that the outer periphery of the limiting ring 31 is filled with the inter-pile soil 4 , that is, the bottom end of the limiting ring 31 is inserted into the inter-pile soil 4 .
[0040] In this embodiment, the base component 1 transmits the vertical bearing force to the foundation pile 32 through the cushion layer 33. The foundation pile 32 can compress the cushion layer 33 upward to deform when transmitting the vertical bearing force, so that it can rely on deformation to adjust to the foundation pile 32 and the soil between the piles 4 to stably bear the load together during the bearing process. It has adjustability. By setting the limiting ring 31 and the cushion layer 33, the vertical load is reasonably distributed between the foundation pile 32 and the soil between the piles 4. At the same time, the cushion layer 33 corresponding to each foundation pile 32 is filled in a limiting ring 31. The cushion layer 33 is limited by the limiting ring 31. The foundation pile 32 fully utilizes the bearing function of the thinner surface soil 4 between the piles. If the surface is not The soil layer can be utilized, and clay soil replacement can be adopted. There is no need to fully spread the cushion layer 33 in the entire foundation range. The composite body composed of the inter-pile soil 4 and the foundation piles 32 is used to bear the horizontal load, meet the overall anti-slip stability requirements, reduce the consumption of cushion layer 33 materials and shorten the construction period. At the same time, the limiting ring 31 plays an anti-seepage role on the outside of the cushion layer 33. When the consolidation and settlement of the inter-pile soil 4 causes the base component 1 and the inter-pile soil 4 to be emptied, the anti-seepage plug plate 2 and the two adjacent limiting rings 31 jointly form a dumbbell-shaped anti-seepage closed body to improve the anti-seepage effect; the limiting ring 31 and the anti-seepage plug plate 2 work together, and form a vertical anti-seepage body with the base component 1 to intercept seepage and avoid seepage damage.
[0041] Specifically, the foundation piles 32 may be rigid piles, which have the advantages of high strength and good stability, and the overall anti-slip ability is further improved by setting rigid piles.
[0042] Specifically, this embodiment does not specifically limit the inner diameter of the limiting ring 31. The inner diameter of the limiting ring 31 is larger than the diameter of the foundation pile 32, and the difference between the inner diameter of the limiting ring 31 and the diameter of the foundation pile 32 is 30cm-60cm, ensuring that there is enough space to fill the cushion layer 33 and the inter-pile soil 4. It can be selected to be 30cm, 45cm or 60cm, and the specific selection can be made according to actual conditions.
[0043] Specifically, the present embodiment does not specifically limit the thickness of the limiting ring 31 . The thickness of the limiting ring 31 is greater than or equal to 5 cm to ensure its structural strength and anti-seepage effect. The thickness can be selected according to actual conditions.
[0044] Specifically, the top height of the limiting ring 31 is 15 cm to 35 cm higher than the top of the foundation pile 32 , so as to facilitate filling in the mattress layer 33 . The specific height can be selected according to actual conditions.
[0045] Specifically, the present embodiment does not specifically limit the thickness of the limiting ring 31, and the thickness of the mattress layer 33 is 10 cm-30 cm, which can be selected as 10 cm, 20 cm or 30 cm, and the specific selection can be made according to actual conditions.
[0046] Based on the above implementation, in a preferred implementation, Figure 1 As shown, the top of the limiting ring 31 is embedded in the base component 1.
[0047] In this embodiment, the top of the limiting ring 31 is embedded in the base component 1 to improve its stability and anti-seepage effect, thereby preventing water from leaking into the mattress layer 33 through the gap between the limiting ring 31 and the base component 1.
[0048] Specifically, the length of the top of the limiting ring 31 embedded in the base component 1 is greater than or equal to 5 cm, ensuring the stability and sealing of the connection.
[0049] Based on the above implementation, in a preferred implementation, Figure 4 As shown, a plug-in groove is provided on the peripheral side of the limiting ring 31 corresponding to the anti-seepage plug plate 2, and the peripheral edge of the anti-seepage plug plate 2 is adapted to be plugged into the plug-in groove.
[0050] In this embodiment, by providing a plug-in groove on the limiting ring 31, it is convenient to plug the anti-seepage plug plate 2 between two adjacent limiting rings 31, which is convenient for disassembly and assembly, and improves construction efficiency.
[0051] Based on the above embodiment, in a preferred embodiment, the mattress layer 33 includes at least one of crushed stone and mud stones.
[0052] In this embodiment, the cushion layer 33 is made of at least one of crushed stone and mud stone. It can be non-impermeable crushed stone or mud stone with impermeability, or a combination of the two to transfer vertical loads. It adopts a loose structure with a certain compression deformation capacity, thereby greatly reducing the horizontal load on the top of the pile 32 and making the top displacement of the pile 32 easy to control.
[0053] Based on the above implementation, in a preferred implementation, Figures 2 to 4 As shown, the horizontal cross-section of the limiting ring 31 is circular or rectangular.
[0054] It should be noted that the limiting ring 31 is a hollow cylindrical structure.
[0055] In this embodiment, the shape of the limiting ring 31 is not specifically limited, and its horizontal cross-sectional shape is circular or rectangular, and the shape of the cushion layer 33 changes with the shape of the limiting ring 31 .
[0056] Specifically, the limiting ring 31 is a reinforced concrete limiting ring 31, which further ensures its structural strength and stability.
[0057] Based on the above implementation, in a preferred implementation, Figure 1 As shown, the top of the anti-seepage insert plate 2 is embedded in the base component 1.
[0058] In this embodiment, the top of the anti-seepage insert plate 2 is embedded in the base component 1 to further improve the stability and anti-seepage effect.
[0059] Specifically, the foundation piles 32 may be finished piles, and may be rigid piles such as concrete cast-in-place piles, square piles, prestressed concrete pipe piles, steel pipe piles, or CFG piles. The specific selection may be made according to actual conditions.
[0060] Based on the above implementation, in a preferred implementation, Figure 2 As shown, an anti-seepage plug plate 2 is provided between two adjacent pile assemblies 3 located at the upstream side and the downstream side of the foundation.
[0061] In this embodiment, an anti-seepage plug plate 2 is provided between two adjacent pile assemblies 3 located on the upstream side and the downstream side of the foundation, thereby increasing the anti-seepage area and further improving the anti-seepage effect and the ability to bear horizontal loads.
[0062] As a convertible implementation method, it can also be, for example Figure 3 As shown, an anti-seepage plug plate 2 is provided between two adjacent pile assemblies 3 located at the periphery of the foundation.
[0063] In this embodiment, an anti-seepage plug plate 2 is provided between two adjacent pile assemblies 3 located at the periphery of the foundation, which increases the anti-seepage area, further improves the anti-seepage effect and the ability to withstand horizontal loads, and avoids leakage damage.
[0064] Based on the above implementation, in a preferred implementation, Figure 1 As shown, the base component 1 includes a waterproof base plate 11 and a plain concrete cushion layer 12 which are arranged in sequence from top to bottom.
[0065] Specifically, the plain concrete cushion layer 12 is provided to isolate the pile assembly 3, so that the surface is flat and convenient for construction, and the waterproof bottom plate 11 and the pile assembly 3 are connected at the same time. In addition, the waterproof bottom plate 11 is provided on the top of the plain concrete cushion layer 12 for waterproofing, thereby further improving the anti-seepage effect.
[0066] Specifically, the top of the limiting ring 31 is embedded in the plain concrete cushion layer 12. In the specific construction, the top of the limiting ring 31 can be cast together with the plain concrete cushion layer 12, so that the top of the limiting ring 31 is embedded in the plain concrete cushion layer 12, and the construction method is simple.
[0067] Specifically, the top of the anti-seepage plug plate 2 is embedded in the plain concrete cushion layer 12. In the specific construction, after the limiting ring 31 is installed, the periphery of the two sides of the anti-seepage plug plate 2 can be aligned with the plug-in groove on the limiting ring 31, and it can be inserted into the plug-in groove to complete the installation of the anti-seepage plug plate 2. At this time, when pouring the plain concrete cushion layer 12, the anti-seepage plug plate 2 connected to the limiting ring 31 can be poured together, so that the top of the anti-seepage plug plate 2 is embedded in the plain concrete cushion layer 12, and the construction method is simple.
[0068] The specific working principle of the anti-seepage structure for soft soil foundation provided in this embodiment is as follows: a foundation pile assembly 3 is arranged below the base assembly 1 and a composite body is formed between the filled piles to bear the horizontal load and meet the overall anti-slip stability requirements. The foundation pile assembly 3 is composed of a limiting ring 31, a cushion layer 33 and a foundation pile 32. The plain concrete cushion layer 12 transmits the vertical bearing force to the foundation pile 32 through the cushion layer 33. The foundation pile 32 can compress the cushion layer 33 upward to deform when transmitting the vertical bearing force, so that the foundation pile 32 and the soil between the piles 4 can bear the load stably by deformation during the bearing process, and the foundation pile 32 and the soil between the piles 4 can bear the load stably together, and the foundation pile 32 and the soil between the piles 4 can bear the load stably. The foundation pile 32 and the soil between the piles 4 can bear the load stably by deformation ... Under the conditions of demand, the laying amount of the cushion layer 33 can be reduced, thereby saving resources and shortening the construction period. The anti-seepage plug plate 2 and the two adjacent limiting rings 31 together form a dumbbell-shaped anti-seepage closed body to improve the anti-seepage effect. At the same time, under the synergistic effect of the limiting ring 31, the foundation pile 32, the cushion layer 33, the anti-seepage plug plate 2 and the soil between the piles 4, it is guaranteed to meet various performance requirements of the foundation, thereby ensuring the safe and stable operation of the anti-seepage structure, avoiding the consolidation and settlement of the soil between the piles 4 causing the base component 1 and the soil between the piles 4 to be emptied and causing seepage damage, improving the stability of the overall structure in the soft soil foundation, thereby ensuring the overall safety and increasing the service life, meeting the vertical bearing capacity, overall anti-slip stability, settlement control and anti-seepage requirements of the water retaining building under the conditions of deep soft soil foundation, and the structure is simple, does not require the setting of a vertical anti-seepage wall and a full cushion layer 33, has a low cost, and has a high application prospect. The invention solves the technical problem that when the soil 4 between piles consolidates and settles, resulting in the foundation bottom plate and the soil 4 between piles being emptied, a channel is formed between the foundation bottom plate and the soil 4 between piles, which is prone to penetration damage and affects the safety of the overall structure.
[0069] Obviously, the above embodiments are merely examples for the purpose of clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived therefrom are still within the scope of protection of the invention.
Claims
1. An anti-seepage structure for soft soil foundation, characterized in that: include: Base component (1); A plurality of pile foundation assemblies (3) are arranged at the bottom of the base assembly (1), and the plurality of pile foundation assemblies (3) are regularly arranged in an array on a horizontal plane; the bottom of the base assembly (1) and the surrounding sides of the pile foundation assemblies (3) are filled with inter-pile soil (4); An anti-seepage plug plate (2) is provided between at least two adjacent pile assemblies (3) located on the upstream side of the foundation, for preventing water from leaking between the multiple groups of pile assemblies (3); the top of the anti-seepage plug plate (2) is connected to the base assembly (1), and the bottom is inserted into the inter-pile soil (4); and both sides of each anti-seepage plug plate (2) are respectively connected to the two adjacent pile assemblies (3).
2. The anti-seepage structure for soft soil foundation according to claim 1, characterized in that: The pile foundation component (3) comprises a limiting ring (31) and a pile foundation (32); the anti-seepage plug plate (2) is connected to the limiting ring (31); the top of the limiting ring (31) is connected to the bottom of the base component (1); the top of the pile foundation (32) extends into the limiting ring (31), and the inner side wall of the limiting ring (31) and the surrounding side of the pile foundation (32) are filled with the inter-pile soil (4); a cushion layer (33) is filled between the top end surface of the base component (1) and the pile foundation (32), and the base component (1) is connected to the pile foundation (32) through the cushion layer (33), and the cushion layer (33) is located in the limiting ring (31).
3. The anti-seepage structure for soft soil foundation according to claim 2, characterized in that: The top of the limiting ring (31) is embedded in the base component (1).
4. The anti-seepage structure for soft soil foundation according to claim 2, characterized in that: The peripheral side of the limiting ring (31) is provided with a plug-in groove corresponding to the anti-seepage plug plate (2), and the peripheral edge of the anti-seepage plug plate (2) is adapted to be plugged into the plug-in groove.
5. The anti-seepage structure for soft soil foundation according to claim 2, characterized in that: The mattress layer (33) includes at least one of crushed stone and mud stones.
6. The anti-seepage structure for soft soil foundation according to claim 2, characterized in that: The horizontal cross-section of the limiting collar (31) is circular or rectangular.
7. The anti-seepage structure for soft soil foundation according to claim 1, characterized in that: The top of the anti-seepage plug plate (2) is embedded in the base component (1).
8. The anti-seepage structure for soft soil foundation according to claim 1, characterized in that: An anti-seepage plug plate (2) is provided between two adjacent pile assemblies (3) located on the upstream side and the downstream side of the foundation.
9. The anti-seepage structure for soft soil foundation according to claim 1, characterized in that: An anti-seepage plug plate (2) is provided between two adjacent foundation pile assemblies (3) located at the periphery of the foundation.
10. The anti-seepage structure for soft soil foundation according to any one of claims 1 to 9, characterized in that: The base component (1) comprises a waterproof base plate (11) and a plain concrete cushion layer (12) which are arranged in sequence from top to bottom.