A road slope design method and system based on big data analysis

Through big data analysis, the case library was constructed and multiple rounds of design optimization was carried out, which solved the problem of slope stability assessment and construction matching of traditional design methods in complex geological environments, and achieved efficient and accurate road slope design, reducing construction risks .

CN118761144BActive Publication Date: 2024-11-19HUA HUI ENGINEERING DESIGN GROUP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411252589.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-19
Estimated Expiration
2044-09-09

AI Technical Summary

Technical Problem

Traditional road slope design methods are difficult to evaluate the long-term stability of the slope under complex geological environments, and the design does not match the construction conditions, resulting in increased engineering costs and extended construction cycles.

Method used

Using the road slope design method based on big data analysis, the case library matching design scheme is constructed, grid division, consistency analysis, topology update, compatibility analysis and stability analysis are carried out, and the slope design parameters are adjusted to generate the target design scheme. .

Benefits of technology

It improves the initial efficiency and accuracy of the design, reduces trial and error costs, ensures the stability and reliability of the design plan under specific conditions, significantly reduces the risk of slope instability, and provides scientific construction guidance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118761144B_ABST
    Figure CN118761144B_ABST
Patent Text Reader

Abstract

The present invention discloses a road slope design method and system based on big data analysis, the method includes matching a first slope design scheme from a case library according to geological information and environmental information of the road slope, meshing the road slope line therein, and performing consistency analysis, and performing topological update when the result does not meet the first preset condition; performing compatibility analysis on the updated scheme, and correcting the road slope line to obtain a second slope design scheme; performing stability analysis on the second slope design scheme, and when the result does not meet the second preset condition, determining the difference between the current road slope line and the target stability, determining the slope design parameters that need to be adjusted to correct the second slope design scheme, and generating a target slope design scheme. The present invention improves the design efficiency and accuracy of the road slope line, ensures the slope stability and scheme reliability, provides scientific guidance for subsequent road slope construction, reduces construction risks and improves construction energy efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of road planning and design, and in particular to a road slope design method and system based on big data analysis. Background Art

[0002] In the field of traditional road slope design, designers usually rely on experience and limited field survey data to develop design plans. This method has many limitations when facing complex and changeable geological environments. For example, in the absence of comprehensive historical data support, it is difficult for designers to accurately assess the long-term stability of slopes, especially in earthquake-prone areas, soft soil or areas susceptible to climate change, where the risk of slope instability increases significantly. In addition, traditional design processes often ignore the compatibility between design plans and actual construction conditions, resulting in frequent design changes during construction, which not only increases project costs but also prolongs the construction period. Summary of the invention

[0003] In order to solve at least one of the technical problems mentioned above, the present invention provides a road slope design method and system based on big data analysis.

[0004] In a first aspect, the present invention provides a road slope design method based on big data analysis, the method comprising:

[0005] A case library is constructed based on historical road slope design data, geological information and environmental information of the road slope to be designed are obtained, and a first slope design scheme is matched from the case library based on the geological information and environmental information;

[0006] Meshing the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; performing consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, topologically updating the first slope design scheme;

[0007] Performing a compatibility analysis on the updated first slope design scheme, and correcting the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme;

[0008] Perform stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, determine the difference between the stability of the current road slope line and the target stability. According to the difference, determine the slope design parameters that need to be adjusted to correct the second slope design scheme and generate the target slope design scheme.

[0009] Preferably, matching the first slope design solution from the case library according to the geological information and the environmental information includes:

[0010] According to the nearest neighbor algorithm, the reference cases are matched from the case library according to the geological information of the road slope to be designed, and the nearest neighbor value corresponding to each reference case is obtained;

[0011] Calculate the matching degree between the environmental conditions of each reference case and the environmental information of the road slope to be designed; assign weights to the nearest neighbor value and the matching degree, calculate the weighted score of the nearest neighbor value and the matching degree, and take the case with the highest score as the target case;

[0012] The slope design parameters of the first slope design solution are determined according to the target case, wherein the slope design parameters include slope angle, slope length and slope height.

[0013] Preferably, the consistency analysis of the segmented road slope lines includes:

[0014] Calculate the difference in the elevation of the slope points of two adjacent slope lines and the difference in the vegetation coverage rate of the area where the slope lines are located; if the difference in the elevation of the slope points is less than a preset height, and the difference in the vegetation coverage rate is less than a preset ratio, then determine that the consistency analysis result of the two adjacent slope lines meets the first preset condition.

[0015] Preferably, the topological updating of the first slope design scheme includes:

[0016] Identify the grid area to be adjusted where the difference in elevation between the slope points of two adjacent slope lines is greater than or equal to a preset height, and re-divide the grid area to be adjusted to obtain a target grid area;

[0017] Divide the target grid area into different levels, and make local adjustments to the slope design parameters of different target grid areas according to different levels of difference;

[0018] Based on the local adjustment results, the overall topology of the road slope line is updated.

[0019] Preferably, the compatibility analysis of the updated first slope design scheme includes:

[0020] Using octree coding, all topological relationship feature vectors in the road slope line before and after the topological update are calculated, and the corresponding vector difference is calculated;

[0021] Determine whether there is a zero vector in all vector differences;

[0022] If so, it is determined that the roadside slope lines before and after the topology update meet the compatibility requirements;

[0023] If not, it is determined that the road slope lines before and after the topology update do not meet the compatibility requirements, and the topology barrier types are identified, which include connection type, non-connection type, intersection and overlap type, and crossing type.

[0024] Preferably, the updated road slope lines are corrected according to the compatibility analysis results, including extending, deleting, splitting and displacing intersections of road slope lines with topological obstacle types.

[0025] Preferably, the stability analysis of the second slope design scheme includes:

[0026] The road slope line in the second slope design scheme is divided into The stability of the road slope line is:

[0027] ;

[0028] ;

[0029] In the formula, is the safety factor of the road slope line, , For the The self-weight and horizontal force of the soil strip; for The vertical distance from the point of action to the center of the circle, For the The contact length of the soil strip on the sliding surface, For the The pore water pressure at the bottom of the strip, For the The horizontal length of the slope line. is the internal friction angle of the soil strip, For the The angle between the arc tangent line of the bottom surface of the soil strip and the horizontal line.

[0030] In a second aspect, the present invention further provides a road slope design system based on big data analysis, the system comprising:

[0031] A scheme matching unit is used to build a case library based on historical road slope design data, obtain geological information and environmental information of the road slope to be designed, and match the first slope design scheme from the case library based on the geological information and environmental information;

[0032] A topology updating unit is used to mesh the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; perform consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, perform topology update on the first slope design scheme;

[0033] A slope correction unit is used to perform compatibility analysis on the updated first slope design scheme, and correct the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme;

[0034] The stability analysis unit is used to perform stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, the difference between the stability of the current road slope line and the target stability is determined, and the slope design parameters that need to be adjusted are determined according to the difference to correct the second slope design scheme and generate the target slope design scheme.

[0035] In a third aspect, the present invention further provides an electronic device comprising a processor and a memory, wherein the memory is used to store computer program code, and the computer program code comprises computer instructions. When the processor executes the computer instructions, the electronic device executes the method as described in the first aspect above and any possible implementation thereof.

[0036] In a fourth aspect, the present invention further provides a computer-readable storage medium, wherein a computer program is stored in the computer-readable storage medium, wherein the computer program includes program instructions, and when the program instructions are executed by a processor of an electronic device, the processor executes the method as described in the first aspect above and any possible implementation thereof.

[0037] Compared with the prior art, the present invention has the following beneficial effects:

[0038] 1) The present invention builds a case library based on historical road slope design data, obtains geological information and environmental information of the road slope to be designed, and matches the first slope design scheme from the case library based on the geological information and environmental information, so that the design scheme suitable for specific geological and environmental conditions can be quickly screened out, thereby greatly improving the efficiency of the initial stage of design. At the same time, based on the analysis of a large amount of historical data, the design scheme is more accurate and the trial and error cost is reduced.

[0039] 2) The present invention performs grid division on the road slope line in the first slope design scheme to generate segmented road slope lines in multiple regions; performs consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, performs topological update on the first slope design scheme; after the update, the updated first slope design scheme is also subjected to compatibility analysis, and the updated road slope line is corrected according to the compatibility analysis result to obtain the second slope design scheme. By gridding and segmenting the road slope line in the slope design scheme, not only can the characteristics of each segment be evaluated more carefully, but also targeted optimization and adjustment can be facilitated. For example, when the consistency or compatibility of a segment does not meet the requirements, only the part can be locally adjusted, avoiding large changes in the overall design and realizing refined management of the design. In addition, through consistency analysis, topological update and compatibility analysis, the design scheme can be further optimized to ensure that it is more stable and reliable under specific conditions.

[0040] 3) The present invention also performs a stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, the difference between the stability of the current road slope line and the target stability is determined, and the slope design parameters that need to be adjusted are determined based on the difference to correct the second slope design scheme and generate a target slope design scheme. By performing a stability analysis on the design scheme, potential unstable factors can be effectively identified, and design parameters can be adjusted in a timely manner to ensure the safety of the slope during construction and operation. This method can significantly reduce the risk of slope instability. By ensuring the stability of the slope and the reliability of the scheme, scientific guidance is provided for subsequent road slope construction, reducing construction risks and improving construction energy efficiency.

[0041] It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the disclosure. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the background technology, the drawings required for use in the embodiments of the present invention or the background technology will be described below.

[0043] The drawings herein are incorporated into the specification and constitute a part of the specification. These drawings illustrate embodiments consistent with the present disclosure and are used to illustrate the technical solutions of the present disclosure together with the specification.

[0044] Figure 1 A schematic diagram of a process flow of a road slope design method based on big data analysis provided by an embodiment of the present invention;

[0045] Figure 2 The embodiment of the present invention provides Figure 1 Schematic diagram of the process of the sub-steps of step S10;

[0046] Figure 3 The embodiment of the present invention provides Figure 1 Schematic diagram of the process of the sub-steps of step S20;

[0047] Figure 4 A schematic diagram of the structure of a road slope design system based on big data analysis provided in an embodiment of the present invention. DETAILED DESCRIPTION

[0048] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] The terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or devices.

[0050] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.

[0051] In addition, in order to better illustrate the present invention, numerous specific details are provided in the following specific embodiments. It should be understood by those skilled in the art that the present invention can be implemented without certain specific details. In some examples, methods, means, components and circuits well known to those skilled in the art are not described in detail in order to highlight the subject matter of the present invention.

[0052] In the traditional road slope design process, there are still problems such as insufficient data utilization, low design efficiency, and unreasonable scheme design leading to disconnection from the actual construction process. To this end, the present invention provides a road slope design method based on big data analysis, which can build a case library and intelligently match the initial design scheme, and then through grid analysis and iterative optimization, consider the slope consistency, updated compatibility and stability, thereby improving the design efficiency and accuracy of the road slope line, ensuring the slope stability and scheme reliability, providing scientific guidance for subsequent road slope construction, reducing construction risks and improving construction energy efficiency.

[0053] See also Figure 1 , Figure 1 The following is a flow chart of a road slope design method based on big data analysis provided by an embodiment of the present invention. Figure 1 As shown, the method includes:

[0054] S10, constructing a case library based on historical road slope design data, obtaining geological information and environmental information of the road slope to be designed, and matching a first slope design solution from the case library based on the geological information and environmental information.

[0055] When building a case library, it is necessary to collect a large amount of historical road slope design data, including geological information, slope parameters such as angle, length and height, materials used, design methods, construction details, and subsequent monitoring data and feedback. After obtaining these data, they should be cleaned and standardized to ensure data quality and provide convenience for subsequent calls.

[0056] After building the case library, first obtain the road design task data of the current project, and obtain the geological information and environmental information of the road slope to be designed. The geological information mainly includes soil type, rock properties, groundwater level, stratigraphic structure, earthquake intensity and other information, and the environmental information mainly includes climate conditions, vegetation coverage, topography and surrounding human activities. After obtaining the geological information and environmental information, match the first slope design plan from the case library according to the geological information and environmental information.

[0057] See also Figure 2 In one embodiment, matching the first slope design solution from the case library according to the geological information and the environmental information comprises the following sub-steps:

[0058] S101. According to the nearest neighbor algorithm, reference cases are matched from a case library according to the geological information of the road slope to be designed, and the nearest neighbor value corresponding to each reference case is obtained.

[0059] The kNN algorithm is an instance-based learning method for classification and regression. The basic idea is: given a training data set, for any input instance, find the k training instances closest to the instance in the feature space, and then predict the target value based on the information of these k neighbors. In classification tasks, the majority voting method is usually used; in regression tasks, it may be the average or weighted average of the target values ​​of these k neighbors.

[0060] Clustering algorithm is an unsupervised learning method whose goal is to group similar data points into the same cluster. Common clustering algorithms include K-means, hierarchical clustering, DBSCAN, etc.

[0061] In this step, the nearest neighbor algorithm is first used to find the most similar reference case from the existing case library based on the geological information of the road slope to be designed (such as soil type, rock properties, groundwater level, etc.). The nearest neighbor algorithm will find one or more cases that are closest to the geological characteristics of the current project. Preferably, a clustering algorithm can also be used in other scenarios. The clustering algorithm will classify the cases based on the similarity of geological information and select the most suitable category as a reference.

[0062] S102, calculating the matching degree between the environmental conditions of each reference case and the environmental information of the road slope to be designed; assigning weights to the nearest neighbor value and the matching degree, calculating the weighted score of the nearest neighbor value and the matching degree, and taking the case with the highest score as the target case.

[0063] For each reference case, the algorithm also calculates a "nearest neighbor value", which is the distance to the k value, preferably the Euclidean distance. The nearest neighbor value quantifies the similarity between the case and the geological information of the slope to be designed. The smaller the value, the higher the similarity. After calculating the nearest neighbor value, it is also necessary to assign a weight to the nearest neighbor value to reflect the importance of geological conditions in slope design.

[0064] Next, the system calculates the degree of match between the environmental conditions of each reference case, such as climate, vegetation cover, topography, and human activities, and the environmental information of the road slope to be designed. This step also assigns weights to the degree of match, which reflects the importance of the environmental conditions in the slope design. The system then adds the weighted scores of the nearest neighbor and the degree of match to obtain a total score. The reference case with the highest total score will be selected as the "target case."

[0065] S103. Determine slope design parameters of the first slope design solution according to the target case, wherein the slope design parameters include slope angle, slope length, and slope height.

[0066] Finally, based on the selected target case, the specific parameters of the first slope design solution can be determined, including but not limited to:

[0067] Slope angle: determines the steepness of the slope and directly affects the stability of the slope.

[0068] Slope length: affects the overall size of the slope and potential landslide risk.

[0069] Slope height: closely related to slope stability, drainage requirements and landscape impact.

[0070] Therefore, through the case-based learning and analysis method of this embodiment, the experience and data of past projects can be fully utilized to improve the accuracy and efficiency of road slope design for new projects, while reducing the risks caused by improper design, and can effectively improve the quality and feasibility of the design solution.

[0071] S20, gridding the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; performing consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, performing topological update on the first slope design scheme;

[0072] The roadside slope lines in the first slope design solution are meshed to generate segmented roadside slope lines for multiple areas. This process involves dividing the continuous slope lines into a series of smaller, more manageable segments for more detailed design, analysis, and construction.

[0073] When dividing, the size and shape of the grid need to be determined. The grid can be square, rectangular or irregularly shaped to adapt to the terrain. When choosing the size of the grid, the characteristics of the slope, potential geological risks, engineering difficulty and construction requirements should be taken into account. Smaller grids can be preferred to provide more detailed analysis. Then, using GIS (Geographic Information System) software, the slope is divided according to the predetermined grid size and shape. The software usually has automatic grid division function, but it may also be necessary to manually adjust the boundaries to ensure that the grid reasonably covers the entire slope area and there are no gaps or overlaps between grids. For each grid, the road slope lines inside it are extracted to form independent segmented road slope lines. Usually, this step involves simplification or refinement of the original slope lines to ensure that the segmented lines are clear, coherent and represent the actual situation of the slope within the grid.

[0074] After the grid is divided and the segmented road slope lines are determined, a consistency analysis is further required. In one embodiment, the consistency analysis of the segmented road slope lines includes:

[0075] Calculate the difference in the elevation of the slope points of two adjacent slope lines and the difference in the vegetation coverage rate of the area where the slope lines are located; if the difference in the elevation of the slope points is less than a preset height, and the difference in the vegetation coverage rate is less than a preset ratio, then determine that the consistency analysis result of the two adjacent slope lines meets the first preset condition.

[0076] Specifically, the consistency analysis may include the following steps:

[0077] 1) Obtain data: including the elevation data of the slope point, the vegetation coverage data of the area where the slope line is located, and the preset height difference threshold and vegetation coverage difference threshold.

[0078] 2) Calculate the difference: For each pair of adjacent slope points, calculate their elevation difference; for each pair of adjacent slope lines, calculate their vegetation coverage difference.

[0079] 3) Consistency analysis: Check whether the elevation difference of each pair of adjacent slope points is less than the preset elevation difference threshold; at the same time, check whether the vegetation coverage difference of each pair of adjacent slope lines is less than the preset vegetation coverage difference threshold. If both of the above conditions are met at the same time, it is considered that the consistency analysis result of the slope line meets the first preset condition and no topology update is required; otherwise, an update is required.

[0080] See also Figure 3 In one embodiment, the topological updating of the first slope design scheme includes:

[0081] S201, identifying a grid area to be adjusted where the difference in elevation between slope points of two adjacent slope lines is greater than or equal to a preset height, and re-dividing the grid area to be adjusted to obtain a target grid area.

[0082] In this step, the grid area to be adjusted is first identified, the elevation difference between all adjacent slope points is calculated, and the slope points with elevation difference greater than or equal to the preset height are screened out. The grid area where these points are located is regarded as the grid area to be adjusted. Further, the grid is re-divided, that is, the identified grid area to be adjusted is re-divided so that the refined grid obtains a more detailed terrain description, or the grid shape is adjusted to better adapt to terrain changes.

[0083] S202, dividing the target grid areas into difference levels, and locally adjusting the slope design parameters of different target grid areas according to different difference levels.

[0084] The difference level is divided according to the elevation difference within the target grid area. Different levels usually represent different terrain complexity or risk levels.

[0085] S203: Based on the local adjustment result, the road slope line is updated with overall topology.

[0086] For target grid areas with different difference levels, different slope design parameters are used for local adjustments, such as local changes in slope angles, drainage system design, reinforcement measures, etc. Finally, the locally adjusted slope design parameters are integrated into the overall road slope line design, and the overall slope design scheme is updated to ensure that it meets safety and stability requirements.

[0087] It is understandable that after the update, the consistency analysis should be performed again to ensure that the consistency requirements of the road slope lines of different sections can meet the first preset condition, so as to enter the operation of step S30.

[0088] S30, performing compatibility analysis on the updated first slope design scheme, and correcting the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme;

[0089] After the topology is updated, some incompatibilities may usually occur, namely topological obstacles, including connection type, non-connection type, intersection and overlap type, and crossing type. In order to ensure the accuracy of the slope design, this embodiment will perform a compatibility analysis on the first slope design scheme after the topology update. Once a topological obstacle is found, the road slope line will be corrected in time to avoid some repeated intersections, wrong connection of the start and end points, and crossing problems.

[0090] In one embodiment, the compatibility analysis of the updated first slope design scheme includes:

[0091] Using octree coding, all topological relationship feature vectors in the road slope line before and after the topological update are calculated, and the corresponding vector difference is calculated;

[0092] Determine whether there is a zero vector in all vector differences;

[0093] If so, it is determined that the roadside slope lines before and after the topology update meet the compatibility requirements;

[0094] If not, it is determined that the road slope lines before and after the topology update do not meet the compatibility requirements, and the topology barrier types are identified, which include connection type, non-connection type, intersection and overlap type, and crossing type.

[0095] Specifically, the implementation of this embodiment may include the following steps:

[0096] 1) Octree coding calculation: Convert the road slope lines before and after the topology update into octree coding format, so that each slope line segment can be represented as a series of octree nodes, which describe the position and topological relationship of the slope line in three-dimensional space. This process may require discretizing the slope line into multiple small segments, each of which corresponds to one or more octree nodes.

[0097] 2) Calculate the topological relationship feature vector: Based on the octree encoding, calculate the topological relationship feature vector of each small slope line. These vectors contain the topological relationship information such as connection, adjacency, intersection and inclusion between the slope lines. The feature vector can be a quantitative indicator, such as distance, angle or overlapping area, or a qualitative label, such as "connected", "adjacent" or "intersection".

[0098] 3) Calculate vector difference: Compare the eigenvectors of the slope line before and after the topological update, and calculate the corresponding vector difference, that is, the result of subtracting the vector before the update from the vector after the update.

[0099] 4) Zero vector judgment: Check whether there is a zero vector in all calculated vector differences, that is, the topological relationship of a certain slope line section has not changed before and after the update.

[0100] 5) Compatibility judgment:

[0101] 5.1) If there is a zero vector, it means that the update does not destroy the original topological relationship and meets the compatibility requirements.

[0102] 5.2) If there is no zero vector, that is, all vector differences are non-zero, it means that the update has changed the topological relationship of at least one section of the slope line and does not meet the compatibility requirements.

[0103] 6) Identify topological obstacle types: For situations that do not meet compatibility requirements, further analyze the vector difference to identify the specific topological obstacle types, including:

[0104] 6.1) Connection type: The slope lines that should have been connected are no longer connected, or unnecessary connections are added.

[0105] 6.2) Non-connected type: The originally separated slope lines are accidentally connected, or the slope lines that should be connected are not connected.

[0106] 6.3) Cross-overlap type: There is an unnecessary crossing or overlap between the slope lines.

[0107] 6.4) Crossing type: The slope line inappropriately crosses other important structures or areas, such as buildings, rivers or protected areas.

[0108] In one embodiment, the updated road slope lines are corrected according to the compatibility analysis results, including extending, deleting, splitting and displacing intersections of road slope lines with topological obstacle types.

[0109] For example, when there are no compatibility issues before and after the update, no additional processing is required. The second slope design scheme can be obtained after the topological update of the first slope design scheme; if there are compatibility issues, the obstacle type needs to be identified first. If a connection obstacle occurs, the slope line can be corrected by extending, splitting, deleting, or displacing the intersection. If a non-connection obstacle occurs, the slope line can be corrected by extending or displacing the intersection. If a cross-overlap obstacle occurs, the slope line can be corrected by deleting, splitting, or displacing the intersection. If a crossing obstacle occurs, the slope line can be corrected by extending, splitting, deleting, or displacing the intersection.

[0110] In summary, this embodiment uses octree encoding and topological relationship feature vectors to provide a systematic and quantitative compatibility analysis method that can effectively detect the impact of topological updates on slope line design. It helps to ensure that design changes do not inadvertently destroy the original relationship between the slope line and other infrastructure or natural environment, and can also identify and resolve potential conflicts or problems in a timely manner, thereby improving the design accuracy of the slope line.

[0111] S40, performing stability analysis on the second slope design scheme, and when the stability does not meet the second preset condition, determining the difference between the stability of the current road slope line and the target stability, determining the slope design parameters that need to be adjusted according to the difference to correct the second slope design scheme, and generating a target slope design scheme.

[0112] Specifically, the stability analysis of the second slope design scheme includes:

[0113] The road slope line in the second slope design scheme is divided into The stability of the road slope line is:

[0114] ;

[0115] ;

[0116] In the formula, is the safety factor of the road slope line, , For the The self-weight and horizontal force of the soil strip; for The vertical distance from the point of action to the center of the circle, For the The contact length of the soil strip on the sliding surface, For the The pore water pressure at the bottom of the strip, For the The horizontal length of the slope line. is the internal friction angle of the soil strip, For the The angle between the arc tangent line of the bottom surface of the soil strip and the horizontal line.

[0117] It can be understood that conducting stability analysis on the second slope design and making corrections based on the analysis results until the target stability is achieved is an iterative optimization design process.

[0118] In a specific implementation, when conducting stability analysis, basic data can be collected first, including parameters such as soil or rock type, water content, porosity, shear strength, and geometric and hydrological conditions such as slope height, slope, and groundwater level. Then, based on the above data, a mechanical model of the slope is established using the finite element method (FEM), discrete element method (DEM) or other suitable numerical simulation methods. The model should take into account factors such as the physical and mechanical properties of the slope material, the slope shape, and groundwater flow. Furthermore, based on the above formula, the safety factor of the slope is calculated by numerical simulation. , It is a key indicator for measuring slope stability. The safety factor is the ratio of the force of the slope resisting sliding to the force causing sliding. Generally, a safety factor greater than 1 indicates that the slope is stable, and less than 1 indicates instability. In this embodiment, a preset safety value is set to determine whether the stability requirement is met.

[0119] If the calculated safety factor is lower than the preset safety value, that is, the second preset condition is not met, the difference between the current safety factor and the target safety factor needs to be calculated. Then, according to the size and direction of the difference, the slope design parameters that need to be adjusted are determined. Possible adjustments include but are not limited to:

[0120] Changing the slope: Slowing down the slope can increase stability.

[0121] Add supporting structures: such as anchor rods, retaining walls or anti-slide piles to enhance the resistance of the slope.

[0122] Improve drainage system: reduce groundwater pressure and increase soil shear strength.

[0123] Change the slope surface cover: Cover the slope surface with a more stable material.

[0124] Modify the slope profile shape: such as stepped slope or graded slope to distribute stress.

[0125] Based on the above possible adjustment methods, the second slope design is revised, and then the stability analysis of the revised slope design is performed again to calculate the new safety factor. The target slope design is generated by repeating the iterative process until the final stability meets the second preset condition. At this point, the designer can use it as part of the construction drawing to guide the actual slope construction and reinforcement work.

[0126] Therefore, by conducting stability analysis on the design scheme, potential unstable factors can be effectively identified, and design parameters can be adjusted in a timely manner to ensure the safety of the slope during construction and operation. By ensuring the stability of the slope and the reliability of the scheme, scientific guidance can be provided for subsequent road slope construction, reducing construction risks and improving construction energy efficiency.

[0127] In summary, the method provided by the embodiment of the present invention can at least achieve the following effects:

[0128] 1) The present invention builds a case library based on historical road slope design data, obtains geological information and environmental information of the road slope to be designed, and matches the first slope design scheme from the case library based on the geological information and environmental information, so that the design scheme suitable for specific geological and environmental conditions can be quickly screened out, thereby greatly improving the efficiency of the initial stage of design. At the same time, based on the analysis of a large amount of historical data, the design scheme is more accurate and the trial and error cost is reduced.

[0129] 2) The present invention performs grid division on the road slope line in the first slope design scheme to generate segmented road slope lines in multiple regions; performs consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, performs topological update on the first slope design scheme; after the update, the updated first slope design scheme is also subjected to compatibility analysis, and the updated road slope line is corrected according to the compatibility analysis result to obtain the second slope design scheme. By gridding and segmenting the road slope line in the slope design scheme, not only can the characteristics of each segment be evaluated more carefully, but also targeted optimization and adjustment can be facilitated. For example, when the consistency or compatibility of a segment does not meet the requirements, only the part can be locally adjusted, avoiding large changes in the overall design and realizing refined management of the design. In addition, through consistency analysis, topological update and compatibility analysis, the design scheme can be further optimized to ensure that it is more stable and reliable under specific conditions.

[0130] 3) The present invention also performs a stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, the difference between the stability of the current road slope line and the target stability is determined, and the slope design parameters that need to be adjusted are determined based on the difference to correct the second slope design scheme and generate a target slope design scheme. By performing a stability analysis on the design scheme, potential unstable factors can be effectively identified, and design parameters can be adjusted in a timely manner to ensure the safety of the slope during construction and operation. This method can significantly reduce the risk of slope instability. By ensuring the stability of the slope and the reliability of the scheme, scientific guidance is provided for subsequent road slope construction, reducing construction risks and improving construction energy efficiency.

[0131] See also Figure 4 In one embodiment, the present invention further provides a road slope design system based on big data analysis, the system comprising:

[0132] A scheme matching unit 100 is used to build a case library based on historical road slope design data, obtain geological information and environmental information of the road slope to be designed, and match a first slope design scheme from the case library based on the geological information and environmental information;

[0133] The topology updating unit 200 is used to perform grid division on the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; perform consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, perform topology update on the first slope design scheme;

[0134] The slope correction unit 300 is used to perform compatibility analysis on the updated first slope design scheme, and correct the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme;

[0135] The stability analysis unit 400 is used to perform stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, the difference between the stability of the current road slope line and the target stability is determined, and the slope design parameters that need to be adjusted are determined according to the difference to correct the second slope design scheme, thereby generating a target slope design scheme.

[0136] It can be understood that the functions or modules included in the system provided in this embodiment can be used to execute the method described in the above method embodiment. Its specific implementation can refer to the description of the above method embodiment. For the sake of brevity, it will not be repeated here.

[0137] The present invention also provides an electronic device, comprising: a processor and a memory, wherein the memory is used to store computer program code, the computer program code includes computer instructions, and when the processor executes the computer instructions, the electronic device executes a method as described in any possible implementation manner.

[0138] The present invention also provides a computer-readable storage medium, in which a computer program is stored. The computer program includes program instructions. When the program instructions are executed by a processor of an electronic device, the processor executes a method as described in any possible implementation manner.

[0139] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.

[0140] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments, and will not be repeated here. Those skilled in the art can also clearly understand that the descriptions of the various embodiments of the present invention have different focuses. For the convenience and brevity of description, the same or similar parts may not be repeated in different embodiments. Therefore, for parts not described or not described in detail in a certain embodiment, refer to the records of other embodiments.

[0141] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0142] In the above embodiments, it can be implemented in whole or in part by software, hardware, firmware or any combination thereof. When implemented by software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, the process or function described in the embodiment of the present invention is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium or transmitted through the computer-readable storage medium. The computer instructions can be transmitted from a website site, computer, server or data center to another website site, computer, server or data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) means. The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or data center that includes one or more available media integrated. The available medium may be a magnetic medium (eg, a floppy disk, a hard disk, a magnetic tape), an optical medium (eg, a digital versatile disc (DVD)), or a semiconductor medium (eg, a solid state disk (SSD)).

[0143] A person skilled in the art can understand that to implement all or part of the processes in the above-mentioned embodiments, the processes can be completed by a computer program to instruct the relevant hardware, and the program can be stored in a computer-readable storage medium. When the program is executed, it can include the processes of the above-mentioned method embodiments. The aforementioned storage medium includes: a read-only memory (ROM) or a random access memory (RAM), a magnetic disk or an optical disk, and other media that can store program codes.

Claims

1. A road slope design method based on big data analysis, characterized in that: The method comprises: A case library is constructed based on historical road slope design data, geological information and environmental information of the road slope to be designed are obtained, and a first slope design scheme is matched from the case library based on the geological information and environmental information; The matching of the first slope design scheme from the case library according to the geological information and the environmental information includes: According to the nearest neighbor algorithm, the reference cases are matched from the case library according to the geological information of the road slope to be designed, and the nearest neighbor value corresponding to each reference case is obtained; Calculate the matching degree between the environmental conditions of each reference case and the environmental information of the road slope to be designed; assign weights to the nearest neighbor value and the matching degree, calculate the weighted score of the nearest neighbor value and the matching degree, and take the case with the highest score as the target case; Determine the slope design parameters of the first slope design scheme according to the target case, wherein the slope design parameters include slope angle, slope length and slope height; Meshing the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; performing consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, topologically updating the first slope design scheme; The consistency analysis of the segmented road slope line includes: Calculate the difference in elevation of slope points of two adjacent slope lines and the difference in vegetation coverage of the area where the slope lines are located; if the difference in elevation of the slope points is less than a preset height, and the difference in vegetation coverage is less than a preset ratio, then determine that the consistency analysis result of the two adjacent slope lines meets the first preset condition; The topological updating of the first slope design scheme includes: Identify the grid area to be adjusted where the difference in elevation between the slope points of two adjacent slope lines is greater than or equal to a preset height, and re-divide the grid area to be adjusted to obtain a target grid area; Divide the target grid area into different levels, and make local adjustments to the slope design parameters of different target grid areas according to different levels of difference; Based on the local adjustment results, the overall topology of the road slope line is updated; Performing a compatibility analysis on the updated first slope design scheme, and correcting the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme; The compatibility analysis of the updated first slope design scheme includes: Using octree coding, all topological relationship feature vectors in the road slope line before and after the topological update are calculated, and the corresponding vector difference is calculated; Determine whether there is a zero vector in all vector differences; If so, it is determined that the roadside slope lines before and after the topology update meet the compatibility requirements; If not, it is determined that the road slope lines before and after the topology update do not meet the compatibility requirements, and the topology barrier types are identified, which include connection type, non-connection type, intersection overlap type, and crossing type; Perform stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, determine the difference between the stability of the current road slope line and the target stability. According to the difference, determine the slope design parameters that need to be adjusted to correct the second slope design scheme and generate the target slope design scheme.

2. The road slope design method based on big data analysis according to claim 1 is characterized in that: The updated road slope lines are corrected according to the compatibility analysis results, including extending, deleting, splitting and displacing intersections of road slope lines with topological obstacle types.

3. The road slope design method based on big data analysis according to claim 1 is characterized in that: The stability analysis of the second slope design scheme includes: The road slope line in the second slope design scheme is divided into The stability of the road slope line is: ; ; In the formula, is the safety factor of the road slope line, , For the The self-weight and horizontal force of the soil strip; for The vertical distance from the point of action to the center of the circle, For the The contact length of the soil strip on the sliding surface, For the The pore water pressure at the bottom of the strip, For the The horizontal length of the slope line. is the internal friction angle of the soil strip, For the The angle between the arc tangent line of the bottom surface of the soil strip and the horizontal line.

4. A road slope design system based on big data analysis, characterized in that: The system comprises: A scheme matching unit is used to build a case library based on historical road slope design data, obtain geological information and environmental information of the road slope to be designed, and match the first slope design scheme from the case library based on the geological information and environmental information; The matching of the first slope design scheme from the case library according to the geological information and the environmental information includes: According to the nearest neighbor algorithm, the reference cases are matched from the case library according to the geological information of the road slope to be designed, and the nearest neighbor value corresponding to each reference case is obtained; Calculate the matching degree between the environmental conditions of each reference case and the environmental information of the road slope to be designed; assign weights to the nearest neighbor value and the matching degree, calculate the weighted score of the nearest neighbor value and the matching degree, and take the case with the highest score as the target case; Determine the slope design parameters of the first slope design scheme according to the target case, wherein the slope design parameters include slope angle, slope length and slope height; A topology updating unit is used to mesh the road slope lines in the first slope design scheme to generate segmented road slope lines in multiple regions; perform consistency analysis on the segmented road slope lines, and when the consistency analysis result does not meet the first preset condition, perform topology update on the first slope design scheme; The consistency analysis of the segmented road slope line includes: Calculate the difference in elevation of slope points of two adjacent slope lines and the difference in vegetation coverage of the area where the slope lines are located; if the difference in elevation of the slope points is less than a preset height, and the difference in vegetation coverage is less than a preset ratio, then determine that the consistency analysis result of the two adjacent slope lines meets the first preset condition; The topological updating of the first slope design scheme includes: Identify the grid area to be adjusted where the difference in elevation between the slope points of two adjacent slope lines is greater than or equal to a preset height, and re-divide the grid area to be adjusted to obtain a target grid area; Divide the target grid area into different levels, and make local adjustments to the slope design parameters of different target grid areas according to different levels of difference; Based on the local adjustment results, the overall topology of the road slope line is updated; A slope correction unit is used to perform compatibility analysis on the updated first slope design scheme, and correct the updated road slope line according to the compatibility analysis result to obtain a second slope design scheme; The compatibility analysis of the updated first slope design scheme includes: Using octree coding, all topological relationship feature vectors in the road slope line before and after the topological update are calculated, and the corresponding vector difference is calculated; Determine whether there is a zero vector in all vector differences; If so, it is determined that the roadside slope lines before and after the topology update meet the compatibility requirements; If not, it is determined that the road slope lines before and after the topology update do not meet the compatibility requirements, and the topology barrier types are identified, which include connection type, non-connection type, intersection overlap type, and crossing type; The stability analysis unit is used to perform stability analysis on the second slope design scheme. When the stability does not meet the second preset condition, the difference between the stability of the current road slope line and the target stability is determined, and the slope design parameters that need to be adjusted are determined according to the difference to correct the second slope design scheme and generate the target slope design scheme.

5. An electronic device, characterized in that: include: A processor and a memory, wherein the memory is used to store computer program codes, wherein the computer program codes include computer instructions, and when the processor executes the computer instructions, the electronic device executes the road slope design method based on big data analysis as described in any one of claims 1 to 3.

6. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, which includes program instructions. When the program instructions are executed by a processor of an electronic device, the processor executes the road slope design method based on big data analysis as described in any one of claims 1 to 3.