Fan foundation bearing platform and construction method thereof

By designing the main body and pipe pile structure of the wind turbine foundation cap, and combining the prestressed steel strands to connect the wind turbine tower, the problem of settlement observation and inconvenient tensioning during the construction of the wind turbine foundation cap was solved, and efficient and stable wind power was achieved. Infrastructure construction to meet the construction needs of the seabed silty soft soil environment.

CN118774162APending Publication Date: 2024-10-15CHINA WATER CONSERVANCY & HYDROPOWER NO 9 ENG BUREAU CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411032193.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

It is difficult to record the settlement of the wind turbine after installation in the existing wind turbine foundation cap construction, and the connection point of the prestressed anchor is at the bottom of the gravity cap base, making tensioning construction inconvenient. Moreover, the disclosed cap structure is not designed for the soft silt of the shallow surface layer of the seabed. Optimize the design of the soil area.

Method used

A fan foundation cap is designed, which includes a cap body and pipe piles. The cap body is provided with an installation slot A. The support part and the installation part are annular. A basement is set in the installation slot A, and a formwork and a support frame are set in the basement. The wind turbine tower is connected through prestressed steel strands, and the concrete pouring construction method is used to ensure the accuracy of the settlement observation points and the convenience of construction.

Benefits of technology

It has achieved a high safety level and long service life for the wind turbine foundation cap. The anti-seepage grade is P6 and the construction efficiency is high. It can achieve stable wind power infrastructure construction in the shallow muddy soft soil area of ​​​​the seabed. For example, Goldwind Technology Linquan County Single Qiao Wind Farm can complete the construction of ten wind turbine foundation caps every month.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774162A_ABST
    Figure CN118774162A_ABST
Patent Text Reader

Abstract

The invention discloses a fan foundation bearing platform and a construction method thereof, the fan foundation bearing platform comprises a bearing platform main body and a pipe pile, the bearing platform main body is arranged on a cushion layer, the bearing platform main body is connected with the pipe pile, and a mounting groove A is formed in the bearing platform main body. The bearing platform body comprises a supporting part and a mounting part, the pipe piles are connected with the supporting part, the supporting part and the mounting part are both in a circular ring shape, the inner wall of the supporting part is connected with the mounting part, the section of the supporting part is in a trapezoid shape, the mounting groove A is formed in the mounting part, a basement is arranged in the mounting groove A, and a water collecting pit is formed in the bottom of the mounting groove A. According to the wind turbine foundation platform, pile foundation reinforced concrete is arranged in a hollow mode, and the wind turbine foundation platform and the upper wind turbine tower are connected through prestressed steel strands. The draught fan foundation bearing platform structure is high in safety level, the anti-permeability level is P6, and the service life is long.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of wind power generation, and in particular relates to a wind turbine foundation bearing platform and a construction method thereof. Background Art

[0002] The wind turbine foundation is the fixed end of the wind turbine generator set. Together with the tower, the wind turbine is erected at a height of more than 100 meters. It is an important part to ensure the normal power generation of the wind turbine. The foundation of the wind turbine is usually a reinforced concrete structure, designed in different forms according to the local geological conditions, mainly based on the tower load and the climate environment where the unit is located, combined with the super high-rise building construction specifications.

[0003] The patent document with publication number CN103147456A discloses a prestressed composite pile structure. The structure includes: a gravity bearing base, and also includes: a concrete fixing part and a plurality of flexible anchor cables; the concrete fixing part is arranged underground; the gravity bearing base is arranged on the concrete fixing part; the concrete fixing part and the gravity bearing base are fixedly connected by a plurality of flexible anchor cables. In this invention, there is no connection groove between the neutral bearing base and the wind turbine tower, and the connection point of the prestressed anchor is on the bottom surface of the gravity bearing base, which makes the tensioning construction inconvenient. The construction of the gravity bearing base is to disclose the corresponding settlement observation device, and it is impossible to record the settlement of the wind turbine after installation.

[0004] The patent document with the publication number CN107100193A discloses a construction process for wind turbine caps, and the key points of its technical solution are: field measurement; welding guide plates; making mooring facilities, cable pipes, and installing mooring facilities, anti-collision mechanisms, and cable pipes; making steel casings and installing them on the water; laying the bottom plate, tying the steel bars of the bottom layer of the cap, and pouring the bottom layer concrete; curing the first-phase concrete; cutting off the tension and compression rods, and removing the bottom plate machine truss beams; tying the steel bars of the upper layer and pile top of the cap, and constructing embedded parts; pouring the second-phase concrete of the pile core and the cap; curing the second-phase concrete of the cap; removing the steel casing; cleaning the cap, ancillary facilities and anti-corrosion. This process is used for offshore wind power generation, and the specific structure of the cap is not disclosed. Its construction environment is the soft muddy soil area of ​​the shallow surface of the seabed, which is different from the construction technology field of this application. Summary of the invention

[0005] In order to solve the above technical problems, the present invention provides a wind turbine foundation cap and a construction method thereof.

[0006] The present invention is achieved through the following technical solutions.

[0007] A wind turbine foundation pedestal provided by the present invention comprises a pedestal body and pipe piles, wherein the pedestal body is arranged on a cushion layer, the pedestal body and the pipe piles are connected, and a mounting groove A is arranged on the pedestal body.

[0008] Preferably, the base body includes a supporting part and a mounting part, the pipe pile is connected to the supporting part, the supporting part and the mounting part are both in a circular ring shape, the inner wall of the supporting part is connected to the mounting part, the cross-section of the supporting part is trapezoidal, the mounting groove A is arranged on the mounting part, a basement is arranged in the mounting groove A, and a sump is arranged at the bottom of the mounting groove A.

[0009] Preferably, an installation groove B, a through hole A and a settlement observation point are arranged on the installation part, the installation groove B and the settlement observation point are arranged on the top of the installation part, the installation groove B is arranged between the settlement observation point and the through hole A, the installation groove B is annular, the through hole A is arranged on the side of the installation part close to the installation groove A, and a number of through holes A are arranged in a circular distribution.

[0010] Preferably, a formwork and a support frame are arranged in the basement, the formwork is arranged on the top of the basement, the formwork is connected to the bottom of the basement through the support frame, an anchor plate is arranged on the top of the basement, and spiral reinforcement is arranged on the anchor plate.

[0011] A construction method for a wind turbine foundation cap includes the construction steps of pouring concrete on a cap body and a cushion layer.

[0012] Preferably, the construction of the cushion layer includes the following steps:

[0013] S1: Before the construction of pipe pile burial and cushion layer, the pile foundation construction must be inspected and accepted, the foundation elevation must be re-measured, and the foundation pit must be jointly inspected. The cushion layer construction can begin after the pile foundation test and compaction test reports are issued.

[0014] S2: After the cushion formwork is set up, concrete is poured.

[0015] S4: The cushion layer is poured from low to high. First, pour the concrete of the basement bottom, then pour the bottom part of the support, and finally pour the basement after the pouring is completed.

[0016] S5: Pay attention to the horizontality control of the pouring surface during the pouring of the cushion concrete.

[0017] S6: After the cushion concrete is poured, the surface is roughened and moisturized. At the same time, after the concrete has finally set, measurement and positioning can be started to determine the position of the machine center, the foundation axis and the template edge line to facilitate the next construction process.

[0018] Preferably, in step S1: a joint pit test is performed on the foundation pit. If the construction foundation is a pond pumping, dredging and filling foundation, the filling compaction degree is required to be ≥ 0.95, and the cushion construction is started after the pile foundation test and compaction test reports are issued.

[0019] In step S2: after the cushion formwork is set up, a concrete pump is used for pouring, and the top surface of the cushion is plastered. The plane size of the cushion is 100 mm longer than the plane size of the foundation bottom along all sides. The center of the cushion plane is the center of the fan, and the center deviation is controlled within 10 mm.

[0020] Preferably, the construction of the platform body includes the following steps:

[0021] S1: The main body of the cap is poured in two times. The first pouring is for the basement part, which is poured to the distance from the bottom plate of the support part. The water stop is embedded and fixed before pouring.

[0022] S2: Before tying the reinforcement of the main body of the foundation, the construction joints need to be roughened, and the cement slurry and loose sand and gravel on the concrete surface need to be cleaned, and 6mm waterproof mortar should be applied on the water-facing surface;

[0023] S3: Before pouring the second concrete, lay a layer of cement mortar of the same grade with a thickness of 2-3cm on the joint surface, and tamp the concrete near the construction joint carefully during pouring;

[0024] S4: The second time, the bottom plate of the support part is poured first. When pouring, the concrete first covers the bottom and exceeds the height of the bottom plate of the support part by 0.6-1.1m. Then the concrete is poured on the bottom plate of the support part;

[0025] S5: When pouring the base plate, the material should be evenly distributed along the main body of the cap, and the interval between distribution should not exceed 55 minutes. The main body of the cap should be poured before the initial setting of the next layer of concrete.

[0026] S6: Placing concrete in layers on the main body of the foundation in a cycle, with an interval of no more than 55 minutes. Placing a layer of concrete before the initial setting of the next layer of concrete and vibrating it well;

[0027] S7: After the pouring height of the main body of the cap exceeds the height of the bottom plate by 0.8-1.1m, the concrete is placed in a cyclic layer between the main body of the cap and the slope-reduction surface until the pouring of the slope-reduction surface is completed. The interval time should be controlled when placing the concrete. The upper layer of concrete should be placed and vibrated before the initial setting of the next layer of concrete. It should be noted that the slope-reduction surface has an inclined surface. When placing the upper layer of concrete, wait until the surface of the lower layer of concrete has a little initial setting time before pouring the upper layer of concrete from the inside to the outside;

[0028] S8: Concrete vibration uses an inserted vibrating rod, which is required to be inserted quickly and pulled out slowly. During the vibration process, the vibrating rod is pulled up and down to make the concrete compact. The insertion points should be uniform, and the distance between the insertion points is generally controlled at 400-600mm, and the distance from the formwork is 200mm; the insertion points are in a single row and column form, and the vibration time is controlled at 20-30s;

[0029] S9: Concrete should be evenly distributed around the main body of the foundation, and the concrete around the anchor plate should be vibrated;

[0030] S10: The wind turbine foundation concrete is finished twice. When the concrete is poured to a height higher than the design elevation, the surface is scraped and smoothed. When the concrete is close to initial setting, the concrete surface is smoothed a second time.

[0031] Preferably, when pouring on a slope, if the slump is too large and the material cannot be piled up, the material should be stopped at that location, and vibration should be performed again when the lower layer of material can be piled up, but the interval time should not exceed 30 minutes;

[0032] The upper layer of concrete should be poured before the next layer of concrete begins to set. The vibrator should be inserted more than 50mm into the next layer of concrete. The concrete should be vibrated twice within the vibration limit and concrete seepage should be removed in time.

[0033] Preferably, the main body concrete of the wind turbine foundation should be poured continuously without leaving construction joints. In extreme cases, if construction joints are required, dowel bars should be reserved in the poured concrete, inserted 400mm into the poured concrete, and arranged in a plum blossom shape with a spacing of 500mm.

[0034] The beneficial effects of the present invention are:

[0035] The wind turbine foundation pedestal of the present invention adopts a hollow setting of pile foundation reinforced concrete, and uses prestressed steel strands to connect the wind turbine foundation pedestal and the upper wind turbine tower. The wind turbine foundation pedestal has a high structural safety level, a P6 anti-seepage level, and a long service life. The construction of this wind turbine foundation pedestal in the Danqiao Wind Farm in Linquan County, Goldwind Technology has shown high efficiency, and ten wind turbine foundation pedestals can be completed per month. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a schematic diagram of the main structure of the present invention;

[0037] Figure 2 It is a schematic diagram of the top view of the structure of the present invention;

[0038] Figure 3 It is a schematic diagram of the basement structure of the present invention;

[0039] Figure 4 It is a structural schematic diagram of installing a wind turbine tower according to the present invention;

[0040] Figure 5 It is a schematic diagram of the position of the water stop of the present invention;

[0041] Figure 6 It is a construction schematic diagram of the present invention;

[0042] In the figure: 1-cap pedestal body, 11-installation groove A, 12-collection pit, 2-pile, 3-cushion, 4-support part, 5-installation part, 51-installation groove B, 52-through hole A, 53-settlement observation point, 6-basement, 61-formwork, 62-support frame, 63-anchor plate, 64-spiral reinforcement, 7-waterstop, 8-wind turbine tower, 9-prestressed steel strand. DETAILED DESCRIPTION

[0043] The technical solution of the present invention is further described below, but the scope of protection claimed is not limited to the description.

[0044] Example:

[0045] like Figures 1 to 6 As shown, a wind turbine foundation pedestal includes a pedestal body 1 and pipe piles 2. The pedestal body 1 is arranged on a cushion layer 3, the pedestal body 1 and the pipe piles 2 are connected, and an installation groove A11 is arranged on the pedestal body 1.

[0046] The base body 1 includes a supporting part 4 and a mounting part 5, the pipe pile 2 is connected to the supporting part 4, the supporting part 4 and the mounting part 5 are both in a circular ring shape, the inner wall of the supporting part 4 is connected to the mounting part 5, the cross-section of the supporting part 4 is trapezoidal, the mounting groove A11 is arranged on the mounting part 5, a basement 6 is arranged in the mounting groove A11, and a sump 12 is arranged at the bottom of the mounting groove A11.

[0047] The mounting portion 5 is provided with a mounting groove B51, a through hole A52 and a settlement observation point 53. The mounting groove B51 and the settlement observation point 53 are arranged on the top of the mounting portion 5. The mounting groove B51 is arranged between the settlement observation point 53 and the through hole A52. The mounting groove B51 is annular and is used for installing the wind turbine tower 8. The through hole A52 is arranged on the mounting portion 5 on the side close to the mounting groove A11. A number of through holes A52 are arranged in a circular distribution. The through hole A52 is used for passing the prestressed steel strand 9 and is connected to the anchor plate 63.

[0048] A formwork 61 and a support frame 62 are set in the basement 6, and the formwork 61 and the support frame 62 are both made of steel. The formwork 61 is set on the top of the basement 6, and the formwork 61 is connected to the bottom of the basement 6 through the support frame 62. An anchor plate 63 is set on the top of the basement 6, and spiral ribs 64 are set on the anchor plate 63. A through hole A52 runs through the top of the basement 6, and the anchor plate 63 is set at the through hole A52. The prestressed steel strand 9 is connected to the anchor plate 63 and fixed by the spiral ribs 64. The prestressed steel strand 9 is extended into the basement 6 and connected to the anchor plate 63, which facilitates workers to carry out tensioning construction in the basement 6, and the anchor plate 63 and the spiral ribs 64 play a role in dispersing tension, thereby preventing cracks near the connection of the prestressed steel strand 9 and increasing the service life.

[0049] A construction method for a wind turbine foundation cap includes the steps of pouring a cap body 1 and a cushion layer 3 using concrete.

[0050] The construction of the cushion layer 3 comprises the following steps:

[0051] S1: Carry out the buried construction of pipe pile 2, the concrete strength grade is C15, the cushion thickness is 100mm, the relative elevation of the cushion bottom elevation is -2.6m, the circle with a middle diameter of 9.54m, the relative elevation of the cushion bottom elevation is -4.2m. Before the construction of cushion 3, the pile foundation construction of pipe pile 2 must be inspected and accepted, the foundation elevation must be re-measured, and the foundation pit must be jointly inspected. The cushion construction will start after the pile foundation test and compaction test reports are issued.

[0052] S2: After the cushion layer 3 formwork is set up, concrete is poured.

[0053] S4: The cushion layer 3 is poured from low to high. First, the concrete of the bottom surface of the basement 6 is poured, and then the annular part of the bottom surface of the support part 4 with a diameter of 11.2m to 20.2m is poured. After the pouring is completed, the basement 6 is poured last.

[0054] S5: During the pouring of the concrete of the cushion layer 3, pay attention to the horizontal control of the pouring surface to provide favorable conditions for the later installation of steel bars.

[0055] S6: After the concrete pouring of cushion layer 3 is completed, the surface is roughened and moisturized. At the same time, after the concrete has finally set, measurement and positioning can be started to determine the position of the machine center, the foundation axis and the template edge line, so as to facilitate the construction of the next process.

[0056] In step S1: a joint test is conducted on the foundation pit. If the construction foundation is a pond pumping and desilting foundation, the replacement compaction degree is required to be ≥ 0.95. The cushion construction is started after the pile foundation test and compaction test reports are issued.

[0057] In step S2: after the cushion layer 3 formwork is set up, a concrete pump is used for pouring, and the top surface of the cushion layer is plastered. The plane size of the cushion layer is 100 mm longer than the plane size of the foundation bottom along all sides. The center of the cushion layer plane is the center of the fan, and the center deviation is controlled within 10 mm.

[0058] The construction of the platform body 1 includes the following steps:

[0059] S1: The concrete of the main body 1 of the foundation is poured twice. The first pouring is for the basement 6, which is poured to 20cm from the bottom of the bottom plate of the support part 4. Figure 5 At the bottom of the 200mm mark, a rubber water stop 7 is embedded and fixed before pouring. Concrete is poured twice to produce gaps, and a rubber water stop 7 is set between the gaps to prevent water from penetrating through the gaps;

[0060] S2: To facilitate construction, the construction joints need to be roughened before the reinforcement of the main body 1 of the cap is tied. Roughening can make the contact surface of the two poured concretes better bonded, and the cement slurry and loose sand and gravel on the concrete surface should be cleaned. 6mm waterproof mortar should be applied on the water-facing surface.

[0061] S3: Before pouring the second concrete, lay a layer of cement mortar of the same grade with a thickness of 2-3cm on the joint surface, and tamp the concrete near the construction joint carefully during pouring;

[0062] S4: The second time, the bottom plate of the support part 4 is poured first. When pouring the support part 4, the concrete first covers the bottom and exceeds the height of the bottom plate of the support part 4 by 0.6-1.1m. Then the concrete is poured to the bottom plate of the support part 4;

[0063] S5: When pouring the bottom slab, the material should be evenly distributed along the main body of the cap 1. The interval between distribution should not exceed 55 minutes. The main body of the cap 1 should be poured before the initial setting of the next layer of concrete.

[0064] S6: Placing concrete in a cyclic layer on the foundation body 1, with an interval of no more than 55 minutes, and placing a layer of concrete before the next layer of concrete begins to set and vibrating it;

[0065] S7: After the pouring height of the main body 1 of the pedestal exceeds the height of the bottom plate by 0.8-1.1m, the concrete is placed in a cyclic layer between the main body 1 of the pedestal and the slope-reduction surface until the pouring of the slope-reduction surface is completed. The interval time should be controlled when placing the concrete, and the upper layer of concrete should be placed and vibrated before the next layer of concrete begins to set. It should be noted that the slope-reduction surface has an inclined surface. When placing the upper layer of material, it is necessary to wait until the surface of the lower layer of concrete has a little initial setting time before pouring the upper layer of concrete from the inside to the outside; during pouring, a dedicated person is assigned to monitor the changes in the formwork, embedded pipes, limit embedded parts, leveling embedded parts, and steel bars. If any problems are found, they must be dealt with in a timely manner. When pouring concrete, the formwork should be prevented from displacement or tilting to avoid leakage; the slope-reduction surface is the inclined surface of the support part 4;

[0066] S8: Concrete vibration uses an inserted vibrating rod. During vibration, it is required to insert quickly and pull out slowly. The purpose of inserting quickly is to prevent the bubbles in the lower concrete from being unable to be discharged after the upper concrete is vibrated and compacted, and the purpose of pulling out slowly is to allow the concrete to fill the voids caused by the rod. During the vibration process, the vibrating rod is pulled up and down to make the concrete compacted. The insertion points should be uniform, and the distance between the insertion points is generally controlled at 400-600mm, and the distance from the formwork is 200mm. The insertion points should be in a single row and column form, and should not be mixed with the staggered type to avoid missing vibration. The vibration point time should be well controlled, not too long or too short, and the vibration point time should be controlled at 20-30s, until the concrete surface is slurry, no bubbles appear, and the concrete no longer sinks;

[0067] S9: Concrete should be evenly poured around the main body of the cap 1, and the concrete around the anchor plate should be vibrated to ensure density. Special attention should be paid to the deviation of the reserved pipeline of the prestressed steel strand during pouring;

[0068] S10: The wind turbine foundation concrete adopts secondary finishing. When the concrete is poured to a height higher than the design elevation, the surface is scraped and pressed with a coarse trowel. When the concrete is close to initial setting, the concrete surface is smoothed for a second time to increase the flatness of the concrete and make the concrete surface layer fully dense and consistent with the underlying layer again, so as to eliminate the maximum possibility of surface cracks caused by water absorption and hardening during the process of concrete from initial setting to final setting. When smoothing and smoothing, covering and curing should be carried out simultaneously, and the entire smoothing should be completed before the final setting of the concrete.

[0069] When pouring on a slope, if the slump is too large and the material cannot be piled up, the material should be stopped at that location and vibrated again when the lower layer of material can be piled up. However, the interval time should not exceed 30 minutes.

[0070] The upper layer of concrete should be poured before the next layer of concrete begins to set. The vibrator should be inserted more than 50mm into the next layer of concrete. The concrete should be vibrated twice within the vibration limit and concrete seepage should be removed in time to improve the bond strength between the steel bars and concrete, prevent cracks, reduce internal microcracks, and enhance the density of concrete. During vibration, the vibrator must not touch the steel bars, formwork, or embedded pipes, and vibration must not be missed or over-vibrated.

[0071] The main concrete of the wind turbine foundation should be poured continuously without construction joints. In extreme cases, when the concrete supply is insufficient and continuous pouring is not possible, construction joints can be left to avoid cold joints. If construction joints are required, Φ20 dowels with a length of 800mm should be reserved in the poured concrete, inserted 400mm into the poured concrete, and arranged in a plum blossom shape with a spacing of 500mm; a set of dowels should be prepared in advance before pouring concrete. When problems with concrete supply are predicted, dowels should be inserted in time within the initial setting time of the cement used (determined according to tests, and should not exceed 2 hours if there is no test data);

[0072] The pouring time of concrete for a single wind turbine foundation pedestal should not exceed 16 hours. Avoid construction in direct sunlight or when the temperature drops suddenly. When the maximum daytime temperature is greater than 30°C, avoid pouring during the high temperature period at noon or taking temperature control measures.

[0073] The construction temperature control of the platform body 1 includes:

[0074] 1. The temperature rise of the concrete casting body based on the mold entry temperature should not be greater than 50℃;

[0075] 2. The temperature difference between the inside and outside of the concrete casting (excluding the equivalent temperature of concrete shrinkage) should comply with the requirements of Table 5.3.3 of GB / T 51028 Technical Specifications for Temperature Measurement and Control of Mass Concrete;

[0076] 3. The cooling rate of the concrete casting should not be greater than 2.0℃ / d;

[0077] 4. When removing the insulation cover, the temperature difference between the concrete casting surface and the atmosphere should not be greater than 20°C;

[0078] 5. The temperature of the main concrete of the foundation is controlled at 5-25℃;

[0079] 6. After the concrete pouring is completed, the temperature difference between the inside and outside of the concrete is required to be ≤25℃.

[0080] The wind turbine foundation pedestal and its construction method of the present invention are applied to the Danqiao wind farm of Linquan County, Jinfeng Technology, Fuyang City, Anhui Province. The total installed capacity of the wind farm is 150MW, and 30 wind turbines with a single unit capacity of 5.0MW are installed. The hub height of the wind turbine unit is 160m, the impeller diameter is 191m, and a mixed tower structure is adopted. The wind farm is about 30km long from east to west, about 30km wide from north to south, and has a total area of ​​about 500km 2 .

[0081] The wind turbine foundation adopts a pile reinforced concrete hollow foundation, and prestressed steel strands are used to connect the upper wind turbine tower and the wind turbine foundation pedestal. The design service life of the wind turbine foundation pedestal structure is 50 years, and the structural safety level is level one. The wind turbine foundation has a diameter of 20m and a height of 3m, including 0.5m to 0.8m above ground, 2.5m underground, and the basement is 1.6m below the foundation. The strength grade of the pedestal body and the settlement observation concrete is C40 (level one), the impermeability grade is P6, and the cushion layer uses C15 concrete.

Claims

1. A wind turbine foundation bearing platform, characterized in that: It comprises a support body (1) and a pipe pile (2), wherein the support body (1) is arranged on a cushion layer (3), the support body (1) and the pipe pile (2) are connected, and a mounting groove A (11) is arranged on the support body (1).

2. A wind turbine foundation support according to claim 1, characterized in that: The support platform body (1) comprises a support portion (4) and a mounting portion (5), the pipe pile (2) is connected to the support portion (4), the support portion (4) and the mounting portion (5) are both in annular shape, the inner wall of the support portion (4) is connected to the mounting portion (5), the cross section of the support portion (4) is trapezoidal, a mounting groove A (11) is arranged on the mounting portion (5), a basement (6) is arranged in the mounting groove A (11), and a sump (12) is arranged at the bottom of the mounting groove A (11).

3. A wind turbine foundation support according to claim 2, characterized in that: The mounting portion (5) is provided with a mounting groove B (51), a through hole A (52) and a settlement observation point (53); the mounting groove B (51) and the settlement observation point (53) are arranged on the top of the mounting portion (5); the mounting groove B (51) is arranged between the settlement observation point (53) and the through hole A (52); the mounting groove B (51) is annular; the through hole A (52) is arranged on a side of the mounting portion (5) close to the mounting groove A (11); and a plurality of through holes A (52) are arranged in a circular distribution.

4. A wind turbine foundation support according to claim 2, characterized in that: A template (61) and a support frame (62) are arranged in the basement (6); the template (61) is arranged on the top of the basement (6); the template (61) is connected to the bottom of the basement (6) through the support frame (62); an anchor plate (63) is arranged on the top of the basement (6); and spiral ribs (64) are arranged on the anchor plate (63).

5. A construction method for a wind turbine foundation cap according to any one of claims 1 to 4, characterized in that: The method comprises the construction steps of pouring concrete on a cap body (1) and a cushion layer (3).

6. The construction method of a wind turbine foundation cap according to claim 1, characterized in that: The construction of the cushion layer (3) comprises the following steps: S1: Before the construction of the buried pipe pile (2) and the cushion layer (3), the pile foundation construction of the pipe pile (2) must be inspected and accepted, the foundation elevation must be re-measured, and the foundation pit must be jointly inspected. The cushion layer construction can begin after the pile foundation test and compaction test reports are issued as qualified. S2: After the cushion layer (3) formwork is set up, concrete is poured; S4: The cushion layer (3) is poured from low to high, first pouring the concrete of the bottom surface of the basement (6), then pouring a part of the bottom surface of the support part (4), and finally pouring the basement (6) after the pouring is completed; S5: During the pouring of the concrete of the cushion layer (3), pay attention to the horizontality control of the pouring surface; S6: After the concrete pouring of the cushion layer (3) is completed, the surface is roughened and moisturized. At the same time, after the concrete has finally set, measurement and positioning can be started to determine the position of the machine center, the foundation axis and the template edge line, so as to facilitate the construction of the next process.

7. A construction method for a wind turbine foundation cap as claimed in claim 6, characterized in that: In the step S1: a joint test is conducted on the foundation pit. If the construction foundation is a foundation for pond pumping, dredging and filling, the filling compaction degree is required to be ≥ 0.

95. The cushion construction is started after the pile foundation test and compaction test reports are issued and qualified; In step S2: after the cushion layer (3) formwork is set up, a concrete pump is used to pour the concrete, and the top surface of the cushion layer is plastered. The cushion layer plane size is 100 mm longer than the foundation bottom plane size along all sides. The center of the cushion layer plane is the center of the fan, and the center deviation is controlled within 10 mm.

8. The construction method of a wind turbine foundation cap according to claim 6, characterized in that: The construction of the platform body (1) comprises the following steps: S1: The concrete of the main body of the foundation (1) is poured in two times. The first pouring is for the basement (6) part, which is poured to the distance from the bottom plate of the support part (4). Before pouring, the water stop (7) is embedded and fixed; S2: Before tying the steel bars of the main body of the foundation (1), the construction joints need to be roughened, the cement slurry and loose sand and gravel on the concrete surface need to be cleaned, and 6mm waterproof mortar should be applied on the water-facing surface; S3: Before pouring the second concrete, lay a layer of cement mortar of the same grade with a thickness of 2-3cm on the joint surface, and tamp the concrete near the construction joint carefully during pouring; S4: The second time, the bottom plate of the support part (4) is poured first. When pouring, the concrete first covers the bottom and exceeds the height of the bottom plate of the support part (4) by 0.6-1.1m. Then, the concrete is poured on the bottom plate of the support part (4); S5: When pouring the base plate, the concrete should be evenly distributed along the main body of the cap (1) in a circular manner, with the interval between distribution not exceeding 55 minutes. The pouring of the main body of the cap (1) should be started before the next layer of concrete of the main body of the cap (1) begins to set; S6: Placing concrete on the main body of the foundation (1) in a cyclical manner, with an interval of no more than 55 minutes, placing a layer of concrete before the next layer of concrete begins to set and vibrating the concrete; S7: After the pouring height of the main body of the cap (1) exceeds the height of the bottom plate by 0.8-1.1m, the concrete is placed in a cyclic layer between the main body of the cap (1) and the slope-reduction surface until the pouring of the slope-reduction surface is completed. The interval time during the placing of the concrete should be well controlled. The upper layer of concrete should be placed and vibrated before the initial setting of the next layer of concrete. It should be noted that the slope-reduction surface has an inclined surface. When placing the upper layer of concrete, the upper layer of concrete should be poured from the inside to the outside only after the surface of the lower layer of concrete has a certain initial setting time. S8: Concrete vibration uses an inserted vibrating rod, which is required to be inserted quickly and pulled out slowly. During the vibration process, the vibrating rod is pulled up and down to make the concrete vibrated and compacted. The insertion points should be uniform, and the distance between the insertion points is generally controlled at 400-600mm, and the distance from the formwork is 200mm; the insertion points are in a single row and column form, and the vibration time is controlled at 20-30s; S9: Concrete should be evenly poured around the main body of the cap (1), and the concrete around the anchor plate should be vibrated. S10: The wind turbine foundation concrete is finished twice. When the concrete is poured to a height higher than the design elevation, the surface is scraped and smoothed. When the concrete is close to initial setting, the concrete surface is smoothed a second time.

9. A construction method for a wind turbine foundation cap as claimed in claim 8, characterized in that: When pouring on a slope, if the slump is too large and the material cannot be piled up, the material should be stopped at that location and vibrated again when the lower layer of material can be piled up. However, the interval time should not exceed 30 minutes. The upper layer of concrete should be poured before the next layer of concrete begins to set. The vibrator should be inserted more than 50mm into the next layer of concrete. The concrete should be vibrated twice within the vibration limit and concrete seepage should be removed in time.

10. A construction method for a wind turbine foundation cap as claimed in claim 8, characterized in that: The main concrete of the wind turbine foundation should be poured continuously without leaving construction joints. In extreme cases, if construction joints are required, dowel bars should be reserved in the poured concrete, inserted 400mm into the poured concrete, and arranged in a plum blossom shape with a spacing of 500mm.