Installation and construction process of offshore wind power booster station

By optimizing the base structure and detailed construction plan, the instability problem caused by the failure to consider the seabed geological conditions in the foundation design during the installation of offshore wind power booster stations was solved, achieving efficient installation and long-term stable operation of the structure, and reducing economic and environmental costs. Influence.

CN118774167APending Publication Date: 2024-10-15NANTONG OCEAN WATER CONSTR CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411147594.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-21
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

During the installation and construction of offshore wind power booster stations, the foundation design failed to fully consider the seabed geological conditions and environmental factors, resulting in structural instability and possible settlement or tilt. The project was time-consuming and labor-intensive with a low fault tolerance rate, which may lead to economic losses. .

Method used

Adopt an optimized base structure design, including bottom sinking mechanism, fixing mechanism and stabilizing mechanism. Determine the seabed bearing capacity and settlement characteristics through geological exploration and survey. Select the appropriate foundation construction form and use sand suction pumps and telescopic blocks to ensure the base. Stable installation, and through detailed construction plans and progress management to ensure efficient and safe installation.

Benefits of technology

It improves the structural bearing capacity and stability of the wind power booster station, simplifies the installation process, shortens the construction period, reduces costs and maintenance requirements, extends the service life of the equipment, adapts to the changing marine environment, and reduces the impact on the environment , improving construction efficiency and economic benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774167A_ABST
    Figure CN118774167A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of offshore wind power booster stations, in particular to an installation and construction process of an offshore wind power booster station, which can bring many beneficial effects in installation and construction of the offshore wind power booster station by optimizing a base structure of the wind power booster station. The optimization not only improves the performance of the structure, but also improves the construction efficiency and the reliability of long-term operation. The base has the main beneficial effects that the bearing capacity of the base can be obviously improved by optimizing the base structure, and the weight and dynamic load of the wind turbine generator and the booster station can be ensured to be borne. This reduces safety problems caused by structural instability, such as settling or tilting. The impact of wind power and sea waves in the marine environment can be better resisted, and the stability and disaster resistance of the whole structure are improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore wind power booster stations, and in particular to an installation and construction process of an offshore wind power booster station. Background Art

[0002] The offshore wind power booster station is a key facility in an offshore wind farm. Its main function is to boost the low-voltage electricity generated by offshore wind turbines to high voltage so that it can be efficiently and safely transmitted to the land power grid. The following is a detailed explanation of the offshore wind power booster station: The electricity generated by wind turbines when generating electricity at sea is usually low voltage (such as 690V or 1kV), which is not suitable for long-distance transmission. The main function of the booster station is to boost these low-voltage electricity to a higher voltage level (such as 33kV, 66kV or higher) to reduce the loss during power transmission and improve the transmission efficiency. Offshore wind farms usually consist of multiple wind turbines, and the electricity generated needs to be collected and processed at the booster station. The booster station collects electricity from different wind turbines and uniformly boosts it, so that the electricity from multiple wind turbines can be efficiently transmitted to the land. The booster station is usually equipped with a power dispatching and monitoring system for real-time monitoring of power production, transmission and quality. It can also dispatch and manage the power system to ensure the stability and reliability of power supply. The booster station is equipped with various protection devices and systems to ensure the safety of the power system. This includes overload protection, short circuit protection, lightning protection, etc. to cope with various power failures or unexpected situations.

[0003] Booster stations are usually set up on the seabed foundation, and the foundation structure may include caissons, steel pipe piles or heavy concrete foundations. The foundation design needs to ensure that the booster station can work stably in the harsh marine environment. It includes transformers, cable distribution devices, switchgear, circuit breakers, etc., which are used for actual power boosting and dispatching. These devices are usually installed on the main platform of the booster station. It contains computer control systems, sensors, communication equipment, etc., which are used to monitor the status of the power system in real time, collect and analyze data, and ensure the stability and safety of power. The booster equipment generates heat during operation, so an effective cooling and ventilation system is required to maintain the normal operating temperature of the equipment. Due to the complexity of the offshore environment, the operation and maintenance management of the booster station has certain challenges. Regular inspection, maintenance and repair are necessary measures to ensure the long-term and stable operation of the booster station. The booster station boosts low-voltage electricity to high voltage, reduces power loss during long-distance transmission, and improves the efficiency of the overall power system. Offshore wind power booster stations are an important part of offshore wind farms, supporting large-scale offshore wind energy development, helping to achieve the widespread application of renewable energy and promote the development of a green and low-carbon economy. Through efficient voltage boosting and monitoring systems, the booster station ensures the stability and reliability of power supply and avoids the impact of power fluctuations on the power grid.

[0004] If the foundation design of the offshore wind power booster station installation and construction process fails to fully consider factors such as seabed geological conditions, waves, tides, etc., it may lead to instability of the booster station or even foundation settlement or tilt; the entire project is time-consuming and labor-intensive, and has a low fault tolerance rate. Once a problem occurs, it may cause huge economic losses.

[0005] In view of the above situation, in order to overcome the above technical problems, the present invention designs an installation and construction process for an offshore wind power booster station to solve the above technical problems. Summary of the invention

[0006] The technical objectives to be achieved by the present invention are: In order to achieve the above technical objectives, the present invention provides the following technical solutions: An installation and construction process for an offshore wind power booster station comprises the following steps: S1: Preliminary preparation: Use geological exploration vessels to conduct seabed geological surveys, determine the bearing capacity and settlement characteristics of the foundation, evaluate marine environmental factors, formulate corresponding construction plans, draw detailed design drawings based on survey results and technical requirements, and formulate detailed construction schedules; S2: Choose the appropriate foundation construction form: single pile foundation is suitable for shallow water depth and hard seabed, multi-pile foundation is suitable for deep water depth and soft seabed, improve the specific construction process and determine the construction date: S3: The sinking mechanism, fixing mechanism, stabilizing mechanism and installation components are transported to a specific port by a large flatbed truck for preparation. The four sinking mechanisms are arranged in a rectangular shape according to the setting. The fixing mechanism is suspended above the sinking mechanism by a special crane steamer, with the base aligned with the installation slot and the positioning ball located in the packing slot. The fixing mechanism is lowered to achieve preliminary installation; S4: Rotate the upper part of the sinking column to make the positioning ball move to the innermost end of the rotating groove, fill the filler groove with solder, achieve the fixing effect of the sinking mechanism and the fixing mechanism, install the sand suction pump on the sinking column, and connect the inside of the sinking column with the sand outlet pipe set on the sand suction pump; S5: Install the stabilizing mechanism inside the sleeve, extend the telescopic block and snap it into the matching slot to fix it, and transport the entire offshore wind power booster station base formed by the sinking mechanism, the fixing mechanism and the stabilizing mechanism to the designated sea area using a crane ship; S6: The offshore wind power booster station base is slowly placed vertically into the sea. After the bottom sinking mechanism touches the seabed, the sand suction pump starts working to transport the sand under the cavity upward, thereby helping the bottom sinking mechanism to sink further. After the bottom sinking mechanism is buried 10-15m below the seabed plane, the sand suction pump stops working, the telescopic block shrinks, the stabilizing mechanism moves down between the sand and soil, and the telescopic block is extended again. The installation of the offshore wind power booster station base is completed; S7: Use a crane ship to transport the installation components to the top of the offshore wind power booster station base, and use the locking ring and locking block to coordinate the positioning for installation. Use a crane ship to install the offshore wind power booster station on the mounting plate, and the construction of the entire offshore wind power booster station is completed.

[0007] Preferably, the sinking mechanism includes a sinking column, a matching slot, a sand suction pump, a sand outlet pipe, a mounting slot, a filling slot, a rotating slot and a cavity; the sinking column is arranged at the bottom of the sinking mechanism, the matching slot is opened on the side of the sinking column, the sand suction pump is installed on the top of the sinking column, the sand outlet pipe is installed on the top of the sand suction pump, the mounting slot is opened on the top of the sinking column, the filling slot is opened on the inner side of the mounting slot, the rotating slot is opened at the bottom of the filling slot, and the cavity is arranged at the bottom of the sinking column.

[0008] Preferably, the filling grooves are arranged in a circular array, the rotating grooves are arranged in a spiral shape, and the upper end of the rotating groove is connected to the lower end of the filling groove.

[0009] Preferably, the matching slot is configured as a rectangle, and the cross-sectional shape of the cavity is configured as a trapezoid.

[0010] Preferably, the fixing mechanism includes a base, a positioning ball, a bracket, a mounting platform, a reinforcing rib, a locking block and a sleeve; the base is arranged at the bottom of the fixing mechanism, the positioning ball is arranged on the side of the base, the bracket is installed on the top of the base, the mounting platform is installed on the top of the bracket, the reinforcing rib is arranged in the middle of the bracket, the locking block is installed on the top of the mounting platform, and the sleeve is installed below the mounting platform.

[0011] Preferably, the reinforcing ribs are arranged crosswise, and two upper and lower groups of the reinforcing ribs are arranged between the two brackets.

[0012] Preferably, the locking block is configured as an inner and outer ring structure with an annular groove in the middle.

[0013] Preferably, the stabilizing mechanism comprises a limit block, a moving rod, a foundation block and a telescopic block; the limit block is arranged at the upper part of the stabilizing mechanism, the moving rod is installed under the limit block, the foundation block is arranged under the moving rod, and the telescopic block is installed on the side of the foundation block.

[0014] Preferably, the material of the foundation block is set to high-density steel, and the telescopic blocks are arranged in a circular array, and the telescopic blocks can be telescoped in the foundation block.

[0015] Preferably, the mounting assembly comprises a locking ring and a mounting plate, the locking ring is mounted on the locking block, and the mounting plate is mounted on the locking ring.

[0016] The beneficial effects of the present invention are as follows: 1. The present invention can bring many beneficial effects in the installation and construction of offshore wind power booster stations by optimizing the base structure of the wind power booster station. These optimizations not only improve the performance of the structure, but also improve the construction efficiency and long-term reliability of operation. The following are the main beneficial effects: Optimizing the base structure can significantly improve its bearing capacity, ensuring that it can withstand the weight and dynamic load of the wind turbine and booster station. This reduces safety issues caused by structural instability, such as settlement or tilting. It can better resist the impact of wind and waves in the marine environment, and improve the stability and disaster resistance of the overall structure. The optimized base structure can simplify the installation process and reduce complex construction steps. This makes the installation process more efficient, shortens the construction period, and reduces labor and time costs. The optimized design usually takes into account the problems that may be encountered during the construction process, such as the difficulty of foundation docking, material handling, etc. Improved design can reduce these difficulties and improve the convenience of construction operations. The optimized base structure usually has better durability and corrosion resistance, reducing the maintenance frequency and repair costs in long-term operation. This means less downtime and higher operating efficiency. By improving the stability and durability of the structure, the optimized design can effectively extend the service life of the base. This reduces the frequency of replacements and repairs, thereby reducing overall operating costs.

[0017] 2. Adapt to the changing marine environment: This construction process enables it to better adapt to various marine environmental conditions, such as tidal changes, seabed topography, etc. This ensures that the wind power booster station can operate stably under different environmental conditions. Through this construction process design, the interference of the construction process on the marine environment can be reduced. For example, the optimized base design may reduce the damage to the marine habitat and reduce the negative impact of construction on the environment. This construction process is generally more flexible and can adapt to different water depths and seabed conditions. This enables the wind power booster station to be installed in more locations and expands the construction scope of the wind farm. This construction process takes into account the possible future technical upgrade needs, so that the base structure can support new wind power equipment or upgrades, increasing the adaptability of the system and the possibility of future expansion. The optimized base structure reduces the economic cost of the overall project by improving construction efficiency, reducing maintenance requirements and extending service life. This improves the economic benefits of the wind power booster station project and makes the return on investment more substantial. This construction process can achieve higher stability, safety and efficiency in installation and construction, while reducing long-term operation and maintenance costs. The optimized design not only improves the adaptability and economic benefits of the structure, but also reduces the impact on the environment, providing a solid foundation for the successful implementation of offshore wind power projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0019] The above and other aspects of the present invention will now be described, by way of example only, with reference to the accompanying drawings, in which: Figure 1 It is a schematic diagram of the overall structure of the present invention; Figure 2 It is a schematic diagram of the structure of the sinking mechanism of the present invention; Figure 3 is a cross-sectional view of the sinking mechanism of the present invention; Figure 4 It is a schematic diagram of the fixing mechanism structure of the present invention; Figure 5 is a cross-sectional view of the fixing mechanism of the present invention; Figure 6 It is a schematic diagram of the structure of the stabilizing mechanism of the present invention; Figure 7 It is a schematic diagram of the structure of the installation assembly of the present invention; In the figure: 1. sinking mechanism; 11. sinking column; 12. matching slot; 13. sand suction pump; 14. sand outlet pipe; 15. mounting slot; 16. filling slot; 17. rotating slot; 18. cavity; 2. fixing mechanism; 21. base; 22. positioning ball; 23. bracket; 24. mounting table; 25. reinforcing rib; 26. locking block; 27. sleeve; 3. stabilizing mechanism; 31. limit block; 32. moving rod; 33. foundation block; 34. telescopic block; 4. mounting assembly; 41. locking ring; 42. mounting plate. DETAILED DESCRIPTION

[0020] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0021] like Figure 1-7 As shown, an installation and construction process of an offshore wind power booster station is a complex and meticulous process, involving many technical requirements and construction steps. This process will be described in detail below, including preliminary preparations, selection of foundation construction forms, transportation and preliminary installation of the sinking mechanism 1, fixation of the sinking column 11 and installation of the sand suction pump 13, installation of the stabilizing mechanism 3, positioning and fixing of the base on the seabed, and the final installation of the booster station, including the following steps: S1: Preliminary preparation; Before the construction of the offshore wind power booster station, sufficient preliminary preparation is the key to ensure the smooth progress of the entire project. First of all, it is essential to conduct seabed geological surveys using geological exploration ships. Through seabed geological surveys, the bearing capacity and settlement characteristics of the foundation can be determined, which is crucial for selecting a suitable foundation construction form. In addition, it is necessary to evaluate marine environmental factors such as waves, tides, wind speed, etc., which directly affect the formulation of the construction plan. According to these survey results and technical requirements, drawing detailed design drawings is the next step. The design drawings should not only include the detailed design of the foundation and structure, but also cover the layout of the electrical and mechanical systems. In addition, it is also crucial to formulate a detailed construction schedule to ensure close connection and coordination between various links to avoid delays during construction.

[0022] S2: Choose the right foundation construction form; According to the results of the previous geological survey, choosing the right foundation construction form is the key to ensuring the stability and safety of the booster station. Single pile foundation is suitable for shallower water depths and harder seabeds because of its easy construction and low cost; while multi-pile foundation is suitable for deeper water depths and softer seabeds, which can provide greater bearing capacity and stability. Regardless of which foundation form is chosen, it is necessary to improve the specific construction process, including the setting of pile foundations and the pouring of foundations. Determining the construction date is also an important step, and factors such as weather and tides need to be taken into account to ensure smooth construction.

[0023] S3: Transportation and preliminary installation of the sinking mechanism 1; Next, the sinking mechanism 1, the fixing mechanism 2, the stabilizing mechanism 3 and the installation assembly 4 are transported to a specific port for preparation by a large flatbed truck. The four sinking mechanisms 1 are arranged in a rectangular shape according to the setting, and the fixing mechanism 2 is suspended above the sinking mechanism 1 by a special crane and steamship, wherein the base 21 is aligned with the installation groove 15, and the positioning ball 22 is located in the packing groove 16. The key to this step is to ensure the accurate docking of the fixing mechanism 2 and the sinking mechanism 1 to achieve preliminary installation.

[0024] S4: The bottom sinking column 11 is fixed and installed with the sand suction pump 13; after the preliminary installation is completed, the upper part of the bottom sinking column 11 is rotated so that the positioning ball 22 moves to the innermost end of the rotating groove 17. Next, the solder is filled into the filling groove 16 to achieve a firm fixation of the bottom sinking mechanism 1 and the fixing mechanism 2. Then, the sand suction pump 13 is installed on the top of the bottom sinking column 11, and the interior of the bottom sinking column 11 is connected to the sand outlet pipe 14 provided on the sand suction pump 13. The focus of this step is to ensure the correct installation and connection of the sand suction pump 13 so that it can play a role in the subsequent base positioning process.

[0025] S5: Installation of the stabilizing mechanism 3 and transportation of the base; after the installation of the bottom column 11 and the fixing mechanism 2 is completed, the stabilizing mechanism 3 is installed inside the sleeve 27, ensuring that the extended telescopic block 34 is clamped in the matching slot 12 to achieve fixation. In this way, the base of the offshore wind power booster station formed by the entire bottom sinking mechanism 1, the fixing mechanism 2 and the stabilizing mechanism 3 is preliminarily completed. Use a crane and a ship to transport this base to the designated sea area to ensure that the base can arrive at the construction site smoothly.

[0026] S6: Positioning and fixing the base on the seabed; slowly lower the base of the offshore wind power booster station vertically into the sea until the sinking mechanism 1 touches the seabed. Then, start the sand suction pump 13 to transport the sand below the cavity 18 of the sinking column 11 upward, thereby helping the sinking mechanism 1 to sink further. In this way, the sinking mechanism 1 can be firmly buried 10-15 meters below the seabed plane. When the sinking mechanism 1 reaches the predetermined depth, the sand suction pump 13 stops working. Next, the telescopic block 34 contracts, the stabilizing mechanism 3 moves down between the sand and soil, and the telescopic block 34 is extended again to ensure the stability of the entire base. At this point, the installation of the base of the offshore wind power booster station is basically completed.

[0027] S7: Final installation of the booster station; after the base is stabilized, use a crane and a ship to transport the installation assembly 4 to the top of the offshore wind power booster station base, and install it by coordinating the locking ring 41 and the locking block 26. Then, use a crane and a ship to install the offshore wind power booster station on the mounting plate 42 to ensure its firm connection with the base. The key to this step is to ensure the accurate docking and firm connection of all components to ensure the stability and safety of the entire booster station. At this point, the construction of the entire offshore wind power booster station is completed.

[0028] The installation and construction process of offshore wind power booster stations involves multiple links and steps, and each step is crucial. From preliminary preparations to the selection of foundation construction forms, to the installation of the sinking mechanism 1 and the final installation of the booster station, each step needs to be carried out strictly in accordance with the design requirements and construction specifications. Through scientific and reasonable construction plans and strict construction organization, the safe, stable and efficient operation of offshore wind power booster stations can be ensured. This not only helps to improve the economic benefits of wind power projects, but also provides important guarantees for the development of renewable energy.

[0029] like Figure 2-3As shown, the sinking mechanism 1 is an important component of the installation of the offshore wind power booster station, and its design includes multiple key components to ensure its stability and functionality. Specifically, the sinking mechanism 1 includes a sinking column 11, a matching slot 12, a sand suction pump 13, a sand outlet pipe 14, an installation slot 15, a filling slot 16, a rotating slot 17 and a cavity 18. The sinking column 11 is the core component of the sinking mechanism 1, which is arranged at the bottom of the sinking mechanism 1 to provide the main support and stability. The matching slot 12 is opened on the side of the sinking column 11, and is intended to be fixed with other structural components to ensure the stability and consistency of the overall structure. The sand suction pump 13 is installed above the sinking column 11, responsible for sucking in the sand on the seabed and discharging it through the sand outlet pipe 14. The sand outlet pipe 14 is installed above the sand suction pump 13, connecting the sand suction pump 13 and the internal channel of the sinking column 11, ensuring that the sand is smoothly discharged from the inside of the sinking column 11, and assisting the sinking process of the sinking column 11. The mounting groove 15 is located above the sinking column 11 and is used to place and fix other mounting components 4. The filling groove 16 is opened on the inner side of the mounting groove 15 and is designed to be filled with solder or other fixing materials to ensure the tight connection and firmness between the mounting component 4 and the sinking column 11. The rotating groove 17 is located at the bottom of the filling groove 16. Through the cooperation of the rotation and positioning ball 22, the precise positioning and fixation of the sinking column 11 are achieved. The cavity 18 is set at the bottom of the sinking column 11 as an auxiliary channel for the operation of the sand suction pump 13. When the sand suction pump 13 is working, the sand in the cavity 18 is sucked in and discharged through the sand outlet pipe 14, helping the sinking column 11 to further sink to the deep seabed to reach a predetermined depth and stability.

[0030] like Figure 2As shown, the filling groove 16 is arranged in a circular array, the rotating groove 17 is arranged in a spiral shape, and the upper end of the rotating groove 17 is connected to the lower end of the filling groove 16. The arrangement of the filling groove 16 in a circular array helps to evenly distribute the solder or other filling materials. This uniform distribution can ensure that the connection between the sinking mechanism 1 and the fixing mechanism 2 is more stable. Whether it is welding or other forms of filling materials, the design of the circular array can make the material evenly fill every corner of the connection part, prevent local stress concentration caused by uneven filling, thereby improving the overall strength and durability of the structure. The spiral design of the rotating groove 17 provides precise adjustment and positioning capabilities. By rotating, the positioning ball 22 can move in the spiral groove to achieve the effect of precise positioning. This is crucial to ensure the precise docking of the sinking column 11 during the installation process. The design of the spiral groove makes the positioning process smoother and more controllable, avoiding positioning errors caused by sudden movement or pauses. This precise positioning helps to improve installation efficiency and accuracy, ensuring that the sinking mechanism 1 can be accurately positioned. The design that the upper end of the rotating groove 17 is connected to the lower end of the filling groove 16 further enhances the fixing effect. After the filling groove 16 is filled with materials, these materials can penetrate into the spiral groove through the connection part of the rotating groove 17, increasing the contact area and bonding force of the connection surface. This not only improves the firmness of the fixation, but also makes the entire connection structure more compact and stable.

[0031] like Figure 2 As shown, the mating slot 12 is set to a rectangular shape, and the rectangular slot has a large contact area, which can provide stronger bite force and stability when combined with the corresponding mating parts. This shape helps to resist multi-directional forces and prevent the structure from being displaced or deformed when subjected to external forces. The rectangular slot is simple in shape and easy to process and manufacture. The standardized rectangular design makes the manufacturing process more efficient and reduces complex processing steps and costs. The rectangular slot design is concise and easy to align during installation. The trapezoidal cross-section has a wider bottom and a narrower top. This design can provide a larger base area, help to disperse and carry more pressure and weight, thereby improving the stability of the overall structure. During the operation of the sand suction pump 13, the trapezoidal cross-section cavity 18 can help the sand to be discharged smoothly. The trapezoidal design makes it easier for sand to slide under gravity and be sucked away from the wider bottom, reducing the risk of blockage and accumulation. The trapezoidal cross-section can effectively prevent the structure from sliding or floating, especially when the seabed is uneven or tilted. The wider bottom provides better grip and anti-slip ability to ensure that the sinking mechanism 1 is stably fixed on the seabed.

[0032] like Figure 4-5As shown, the fixing mechanism 2 is an important part of the offshore wind power booster station. It is exquisitely designed, reasonably structured, and contains multiple key components to ensure the stability and reliability of the installation. Specifically, the fixing mechanism 2 includes a base 21, a positioning ball 22, a bracket 23, a mounting platform 24, a reinforcing rib 25, a locking block 26, and a sleeve 27. The base 21 is the basic part of the fixing mechanism 2, which is arranged at the bottom of the fixing mechanism 2 and provides support and stability for the entire mechanism. The positioning ball 22 is arranged on the side of the base 21, and through rotation and positioning, it can achieve precise docking and fixation with other components to ensure that it can be quickly and accurately positioned during the installation process. The bracket 23 is installed on the top of the base 21 to play a role of connection and support. The bracket 23 not only supports the upper structure, but also effectively disperses and transfers the load to enhance the overall stability. The mounting platform 24 is located above the bracket 23 and is the core installation platform of the fixing mechanism 2, which is used to install and fix other important components. The reinforcing rib 25 is arranged in the middle part of the bracket 23, mainly used to enhance the strength and rigidity of the bracket 23. The design of the reinforcing rib 25 can effectively prevent the bracket 23 from deforming under stress, thereby improving the durability and safety of the structure. The locking block 26 is installed on the mounting platform 24, and through the locking mechanism, ensures the firm connection between the mounting platform 24 and the upper structure. The sleeve 27 is installed under the mounting platform 24, and through the cooperation with the base 21 and the bracket 23, a complete fixing system is formed. The design of the sleeve 27 enables the fixing mechanism 2 to better adapt to different installation environments and requirements, providing flexible installation options.

[0033] like Figure 4 As shown, the reinforcing ribs 25 are cross-arranged, and the cross-arranged reinforcing ribs 25 form a grid structure, which can effectively disperse and withstand stress from all directions. The setting of the upper and lower groups of reinforcing ribs 25 further enhances the overall rigidity, making the bracket 23 more stable when bearing vertical and horizontal loads, preventing deformation or displacement. The cross-reinforcing ribs 25 and the upper and lower groups of designs increase the wind resistance and earthquake resistance of the structure. In the harsh marine environment, the impact of wind and waves is large. This design can effectively resist the effects of these external forces and ensure the stability of the fixing mechanism 2. The upper and lower groups of cross-reinforcing ribs 25 can evenly distribute the load to the entire structure, avoid local stress concentration, thereby reducing the risk of material fatigue and damage, and extending the service life of the equipment. The upper and lower groups of reinforcing ribs 25 are arranged between the two brackets 23.

[0034] like Figure 5As shown, the locking block 26 is configured as an inner and outer ring structure with an annular groove in the middle. The inner and outer ring structure provides a double-layer locking mechanism, which enhances the firmness of the locking block 26. The inner ring and the outer ring work together to better fix the mounting platform 24 and the upper structure to prevent loosening and displacement. The design of the annular groove enables the locking block 26 to be automatically aligned and positioned during the installation process. The groove can accommodate the locking ring 41 to ensure that the various components can be accurately aligned during installation, thereby improving the overall installation accuracy and efficiency. The design of the inner and outer ring structure and the annular groove is not only convenient for initial installation, but also helps with subsequent disassembly and maintenance. Through the annular groove, the locking block 26 can be operated more conveniently, necessary adjustments or replacements can be made, and the maintenance process can be simplified. The annular groove can effectively disperse the stress of the locking part and prevent material damage caused by stress concentration. The double-layer locking design of the inner and outer ring structure makes the stress distribution more uniform, further improving the durability and safety of the structure.

[0035] like Figure 6 As shown, the stabilizing mechanism 3 includes a limit block 31, a moving rod 32, a foundation block 33 and a telescopic block 34; the limit block 31 is arranged at the upper part of the stabilizing mechanism 3, the moving rod 32 is installed under the limit block 31, the foundation block 33 is arranged under the moving rod 32, and the telescopic block 34 is installed on the side of the foundation block 33.

[0036] The material of the foundation block 33 is set to high-density steel, which has excellent strength and rigidity, so that it can withstand large loads and pressures. In the stabilizing mechanism 3, the foundation block 33, as a key supporting component, needs to withstand stress from all directions. The high-strength characteristics of high-density steel can ensure that the foundation block 33 will not be deformed or damaged during long-term use, thereby improving the stability of the entire stabilizing mechanism 3. High-density steel has high corrosion resistance and wear resistance, which is particularly important for marine environments such as offshore wind power booster stations. The salt and moisture in the marine environment have a great corrosive effect on metal materials. The corrosion resistance of high-density steel can effectively extend the service life of the foundation block 33 and reduce the frequency of maintenance and replacement.

[0037] The telescopic blocks 34 are arranged in a circular array and can be telescoped in the foundation block 33. On the one hand, the telescopic blocks 34 can enhance the stability of the overall structure during the installation process. On the other hand, after the installation is completed, the telescopic blocks 34 can be extended into the seabed to enhance stability.

[0038] like Figure 7 As shown, the mounting assembly 4 includes a locking ring 41 and a mounting plate 42 . The locking ring 41 is mounted on the locking block 26 , and the mounting plate 42 is mounted on the locking ring 41 .

[0039] In the working process of the present invention, before construction, the first step is to use a geological survey ship to conduct a seabed geological survey. Through this survey, the bearing capacity and settlement characteristics of the foundation are determined. At the same time, marine environmental factors such as waves, tides and wind speed are evaluated. Based on these data, a corresponding construction plan is formulated. Next, according to the survey results and technical requirements, detailed design drawings are drawn up, and a detailed construction schedule is formulated to ensure the smooth progress of the entire project.

[0040] According to the results of the seabed geological survey, select the appropriate foundation construction form. Single pile foundation is suitable for shallower water depths and harder seabeds, while multi-pile foundation is suitable for deeper water depths and softer seabeds. After selecting the foundation form, perfect the specific construction process and determine the construction date to ensure that all links are connected in an orderly manner.

[0041] A large flatbed truck is used to transport the sinking mechanism 1, the fixing mechanism 2, the stabilizing mechanism 3 and the installation assembly 4 to a specific port. The four sinking mechanisms 1 are arranged in a rectangular shape according to the setting. The fixing mechanism 2 is suspended above the sinking mechanism 1 by a special crane and a steamship, with the base 21 aligned with the installation groove 15 and the positioning ball 22 located in the packing groove 16. The initial installation is achieved by lowering the fixing mechanism 2.

[0042] The upper part of the bottom sinking column 11 is rotated to move the positioning ball 22 to the innermost end of the rotating groove 17. The solder is filled into the filling groove 16 to achieve the fixing effect of the bottom sinking mechanism 1 and the fixing mechanism 2. The sand suction pump 13 is installed on the bottom sinking column 11, and the inside of the bottom sinking column 11 is connected to the sand outlet pipe 14 on the sand suction pump 13 to ensure the smooth progress of subsequent work.

[0043] The stabilizing mechanism 3 is installed inside the sleeve 27, and the extended telescopic block 34 is ensured to be clamped in the matching clamping groove 12 to achieve fixation. Then, the entire base formed by the sinking mechanism 1, the fixing mechanism 2 and the stabilizing mechanism 3 is transported to the designated sea area by crane and ship for offshore installation.

[0044] The base is slowly lowered vertically into the sea. When the sinking mechanism 1 touches the seabed, the sand suction pump 13 is started. The sand under the cavity 18 is transported upward to help the sinking mechanism 1 to sink further. After the sinking mechanism 1 is buried 10-15 meters below the seabed, the sand suction pump 13 is stopped. The telescopic block 34 is retracted, the stabilizing mechanism 3 moves down between the sand and soil, and the telescopic block 34 is extended again to complete the stable installation of the base.

[0045] The installation assembly 4 is transported to the top of the base by a crane and a ship, and the installation is achieved by coordinating and positioning the locking ring 41 and the locking block 26. Finally, the offshore wind power booster station is installed on the mounting plate 42 by a crane and a ship, ensuring that all parts are firmly connected. At this point, the construction of the entire offshore wind power booster station is completed.

[0046] The above-disclosed technical features are not limited to the combination with other features disclosed, and those skilled in the art may also make other combinations between the technical features according to the disclosed purpose, so as to achieve the purpose of the present disclosure. The description herein is provided to enable those of ordinary skill in the art to implement or use the present disclosure. It will be obvious to those of ordinary skill in the art that various modifications to the present disclosure will be apparent, and the general principles defined herein may be applied to other variations without departing from the scope of the present disclosure. Therefore, the present disclosure is not limited to the examples and designs described herein, but should be given the broadest scope consistent with the principles and novel features disclosed herein. Although one or more exemplary embodiments of the present disclosure have been described with reference to the accompanying drawings, those of ordinary skill in the art will understand that various changes in form and detail may be made therein without departing from the spirit and scope of the present disclosure as defined in the appended claims. Although the present disclosure has been described in detail above with general descriptions and specific embodiments, it is obvious to those skilled in the art that some modifications or improvements may be made thereto based on the embodiments of the present disclosure. Therefore, these modifications or improvements made without departing from the spirit of the present disclosure are all within the scope of protection claimed by the present disclosure. The foregoing is merely an excerpt from the disclosure that these modifications may be made to the invention in light of the above detailed description. The terms used in the appended claims should not be construed to limit the invention to the specific embodiments disclosed in the specification. Instead, the scope of the invention will be determined entirely by the appended claims, which will be interpreted in accordance with established principles of claim interpretation.

Claims

1. An installation and construction process for an offshore wind power booster station, It is characterized in that The following steps are involved: S1: Preliminary preparation: Use geological exploration vessels to conduct seabed geological surveys, determine the bearing capacity and settlement characteristics of the foundation, evaluate marine environmental factors, formulate corresponding construction plans, draw detailed design drawings based on survey results and technical requirements, and formulate detailed construction schedules; S2: Choose the appropriate foundation construction form: single pile foundation is suitable for shallow water depth and hard seabed, multi-pile foundation is suitable for deep water depth and soft seabed, improve the specific construction process and determine the construction date: S3: The sinking mechanism (1), the fixing mechanism (2), the stabilizing mechanism (3) and the installation assembly (4) are transported to a specific port for preparation by a large flatbed truck, the four sinking mechanisms (1) are arranged in a rectangular shape according to the setting, and the fixing mechanism (2) is suspended above the sinking mechanism (1) by a special crane steamer, wherein the base (21) is aligned with the installation groove (15), the positioning ball (22) is located in the packing groove (16), and the fixing mechanism (2) is lowered to achieve preliminary installation; S4: Rotate the upper part of the bottom sinking column (11) so that the positioning ball (22) moves to the innermost end of the rotating groove (17), fill the filling groove (16) with solder, achieve the fixing effect of the bottom sinking mechanism (1) and the fixing mechanism (2), install the sand suction pump (13) on the top of the bottom sinking column (11), and connect the interior of the bottom sinking column (11) and the sand outlet pipe (14) provided on the top of the sand suction pump (13); S5: installing the stabilizing mechanism (3) inside the sleeve (27), extending the telescopic block (34) to snap into place inside the matching slot (12) to achieve fixation, and transporting the offshore wind power booster station base formed by the entire sinking mechanism (1), the fixing mechanism (2) and the stabilizing mechanism (3) to a designated sea area using a crane ship; S6: The offshore wind power booster station base is slowly lowered vertically into the sea. After the bottom sinking mechanism (1) contacts the seabed, the sand suction pump (13) starts working to transport the sand below the cavity (18) upward, thereby helping the bottom sinking mechanism (1) to sink further. After the bottom sinking mechanism (1) is buried 10-15 m below the seabed, the sand suction pump (13) stops working, the telescopic block (34) contracts, the stabilizing mechanism (3) moves down between the sand and soil, and the telescopic block (34) is extended again. The installation of the offshore wind power booster station base is completed. S7: Use a crane ship to transport the installation assembly (4) to the top of the offshore wind power booster station base, and the locking ring (41) and the locking block (26) cooperate to position and install. Use the crane ship to install the offshore wind power booster station on the installation plate (42), and the construction of the entire offshore wind power booster station is completed.

2. According to claim 1, an installation and construction process for an offshore wind power booster station, Features: The bottom sinking mechanism (1) comprises a bottom sinking column (11), a matching slot (12), a sand suction pump (13), a sand outlet pipe (14), a mounting slot (15), a filling slot (16), a rotating slot (17) and a cavity (18); the bottom sinking column (11) is arranged at the bottom of the bottom sinking mechanism (1), the matching slot (12) is arranged on the side of the bottom sinking column (11), the sand suction pump (13) is installed on the top of the bottom sinking column (11), the sand outlet pipe (14) is installed on the top of the sand suction pump (13), the mounting slot (15) is arranged on the top of the bottom sinking column (11), the filling slot (16) is arranged on the inner side of the mounting slot (15), the rotating slot (17) is arranged at the bottom of the filling slot (16), and the cavity (18) is arranged at the bottom of the bottom sinking column (11).

3. According to claim 2, an installation and construction process for an offshore wind power booster station, Features: The filling grooves (16) are arranged in a circular array, the rotating grooves (17) are arranged in a spiral shape, and the upper end of the rotating grooves (17) is connected to the lower end of the filling grooves (16).

4. According to claim 2, an installation and construction process for an offshore wind power booster station, Features: The matching slot (12) is configured as a rectangle, and the cross-sectional shape of the cavity (18) is configured as a trapezoid.

5. According to claim 1, an installation and construction process for an offshore wind power booster station, Features: The fixing mechanism (2) comprises a base (21), a positioning ball (22), a bracket (23), a mounting platform (24), a reinforcing rib (25), a locking block (26) and a sleeve (27); the base (21) is arranged at the bottom of the fixing mechanism (2), the positioning ball (22) is arranged on the side of the base (21), the bracket (23) is mounted on the top of the base (21), the mounting platform (24) is mounted on the top of the bracket (23), the reinforcing rib (25) is arranged in the middle of the bracket (23), the locking block (26) is mounted on the top of the mounting platform (24), and the sleeve (27) is mounted on the bottom of the mounting platform (24).

6. The installation and construction process of an offshore wind power booster station according to claim 5, Features: The reinforcing ribs (25) are arranged in a cross-like manner, and two upper and lower groups of reinforcing ribs (25) are arranged between the two brackets (23).

7. The installation and construction process of an offshore wind power booster station according to claim 5, Features: The locking block (26) is configured as an inner and outer ring structure, with an annular groove provided in the middle.

8. The installation and construction process of an offshore wind power booster station according to claim 1, Features: The stabilizing mechanism (3) comprises a limit block (31), a moving rod (32), a foundation block (33) and a telescopic block (34); the limit block (31) is arranged on the upper part of the stabilizing mechanism (3), the moving rod (32) is installed below the limit block (31), the foundation block (33) is arranged below the moving rod (32), and the telescopic block (34) is installed on the side of the foundation block (33).

9. The installation and construction process of an offshore wind power booster station according to claim 8, Features: The material of the foundation block (33) is set to high-density steel, and the telescopic blocks (34) are arranged in a circular array, and the telescopic blocks (34) can be telescoped in the foundation block (33).

10. The installation and construction process of an offshore wind power booster station according to claim 1, Features: The mounting assembly (4) comprises a locking ring (41) and a mounting plate (42), wherein the locking ring (41) is mounted on the locking block (26), and the mounting plate (42) is mounted on the locking ring (41).