Pitched roof negative pressure drainage and exhaust structure and construction method

By designing a negative pressure drainage and exhaust structure on the building roof, and using a combination of mesh pipes and drainage components, the problem of insufficient roof drainage effect and waterproof performance in the existing technology is solved, and the effective discharge of water vapor and moisture is achieved, extending the Extends the life of the roof and improves durability.

CN118774341APending Publication Date: 2024-10-15ANHUI WATER CONSERVANCY DEV CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411129288.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

It is difficult for existing building roofs to achieve ideal drainage and waterproof performance under complex and changeable weather conditions, resulting in damage to the waterproof layer, leakage and insufficient overall durability of the roof.

Method used

A slope roof negative pressure drainage and exhaust structure is adopted, including a permeable layer, a waterproof layer, an insulation layer, a concrete protective layer, a brick layer, a pipe component and a drainage component. Through the combination of mesh pipes and downpipes, water collection pipe fittings are used The filter screen and wing ring design of the drainage pipe realize the effective discharge of water vapor and excess moisture.

Benefits of technology

It effectively reduces the damage to the waterproof layer and roof leakage, extends the service life of the roof, and improves the overall durability and living comfort of the building.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774341A_ABST
    Figure CN118774341A_ABST
Patent Text Reader

Abstract

The invention provides a pitched roof negative pressure drainage and exhaust structure which is mainly used for improving the drainage efficiency and the waterproof performance of a pitched roof and enhancing the ventilation and air permeability of the interior of a building. The structure comprises a permeable layer, a waterproof layer, a heat preservation layer, a concrete protection layer, a tile layer, a pipeline assembly, a pipeline assembly and a drainage assembly. The layers are sequentially laid on a concrete roof, downpipes are pre-buried at the bottom, and the water collecting pipe fittings are mutually combined through the through holes to form a net-shaped pipeline which is communicated with the downpipes. The drainage assembly comprises a floor drain and a drainage pipe and is pre-buried in each layer, and the lower end of the drainage pipe extends into the downpipe. The invention further provides a construction method of the pitched roof negative pressure drainage and exhaust structure. The construction method comprises the steps of base layer cleaning, water collecting pipe fitting drilling manufacturing, net-shaped pipeline laying, permeable layer laying, waterproof layer laying, heat preservation layer laying and concrete protection layer laying and drainage assembly installation. The permeable layer is composed of permeable concrete and perlite, the water collecting pipe fitting is a PPR pipe, and the drainage pipe is made of stainless steel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering, and in particular to a negative pressure drainage and exhaust structure for a sloped roof, which is intended to improve the drainage efficiency and waterproof performance of a sloped roof and enhance the ventilation and air permeability inside a building.

[0002] The invention also relates to a method for realizing a negative pressure drainage and exhaust structure for a sloped roof. Background Art

[0003] The existing roofs of construction projects often seep water at individual points in the roof waterproof layer. Water vapor enters the slope layer and is difficult to discharge between the structural plate and the waterproof layer. The thermal expansion and contraction destroy the entire roof waterproof layer. At the same time, the structural plate seeps water due to long-term penetration of water vapor, resulting in the need to re-construct the entire roof, which is costly and difficult to cure.

[0004] The patent with application number CN202010591100.1 discloses a waterproof board, breathable composite energy-saving and ventilated slope roof system and construction process. The slope roof is composed of roof panels, leveling layers, bottom insulation layers, waterproof boards, tile hanging strips and roof tiles from bottom to top. An embedded insulation layer is provided above the bottom insulation layer, and a waterproof layer is provided above the embedded insulation layer. The waterproof layer adopts a waterproof breathable membrane or an aluminum foil reflective membrane. The waterproof board is a corrugated asphalt waterproof board. An arched support is provided between the waterproof board and the embedded insulation layer. A support base is fixed in the embedded insulation layer. The tile hanging strip passes through the waterproof board, the waterproof layer, the arched support in sequence by screws and is finally connected to the support base.

[0005] However, although the above patented technology has adopted drainage and waterproofing measures, it is still difficult to achieve ideal drainage and waterproofing performance under complex and changeable weather conditions. Therefore, there is an urgent need for a slope roof drainage and exhaust system that can effectively solve the above problems and improve the overall durability and living comfort of the building. Summary of the invention

[0006] The purpose of the present invention is to provide a negative pressure drainage and exhaust structure for a sloped roof to solve the problems raised in the above background technology:

[0007] (1) How to allow excess water in the slope layer to be discharged into the downpipe through this structure, effectively reducing the damage to the waterproof layer and the problem of roof leakage.

[0008] The purpose of the present invention is to provide a construction method of a negative pressure drainage and exhaust structure for a sloped roof to solve the problems raised in the above background technology:

[0009] (1) How to improve the roof anti-seepage drainage and exhaust technology to effectively drain and exhaust water, reduce the bulging of the waterproof layer, and at the same time inhibit the cracking of the waterproof membrane and roof leakage.

[0010] To achieve the above object, the present invention provides the following technical solutions:

[0011] A negative pressure drainage and exhaust structure for a sloped roof;

[0012] The invention comprises a permeable layer, a waterproof layer, a thermal insulation layer, a concrete protective layer, a brick and tile layer, a pipe assembly, a pipeline assembly and at least one set of drainage assemblies, wherein the permeable layer, the waterproof layer, the thermal insulation layer, the concrete protective layer and the brick and tile layer are sequentially laid on the upper side of the concrete roof, and at least one downpipe is pre-buried in the concrete roof at the bottom of the slope roof, and the pipeline assembly comprises a plurality of water collecting pipes, wherein the side walls of the water collecting pipes are provided with a plurality of through holes, and the plurality of water collecting pipes are combined with each other to form a mesh pipeline covering the slope roof, and the mesh pipeline is pre-buried in the permeable layer, and the mesh pipeline is communicated with the downpipe;

[0013] The drainage assembly corresponds to the downpipe one by one, and the drainage assembly at least includes a floor drain and a drainage pipe. The upper end of the drainage pipe is fixedly connected to the water outlet on the lower side of the floor drain. The floor drain and the upper part of the drainage pipe are pre-buried in the permeable layer, the waterproof layer, the insulation layer, the concrete protective layer and the brick and tile layer. The lower end of the drainage pipe extends into the downpipe from the upper end of the corresponding downpipe.

[0014] Based on the above technical solution, the present invention can also be improved as follows.

[0015] Furthermore, the outer walls of the water collecting pipes of the pipeline assembly are wrapped with filter nets.

[0016] Furthermore, a wing ring is extended outwardly from the outer wall of the drainage pipe in the concrete protective layer.

[0017] Furthermore, the permeable layer is divided into a permeable area close to the mesh pipeline and a remaining conventional area. Perlite is used as a filling material in the conventional area, and permeable concrete is laid in the permeable area.

[0018] Furthermore, the water collecting pipe is made of PPR pipe; the drainage pipe is made of stainless steel.

[0019] After adopting such a structure, the mesh pipe under the waterproof layer adds an exhaust channel through the roof slope layer, and drains away from the gap between the drain pipe and the downpipe, so that the water vapor in the roof structure layer can be discharged in an orderly manner. The water vapor can be discharged in time, which greatly reduces the probability of damage to the roof waterproof layer and slope layer, and prolongs the service life of the roof.

[0020] To achieve the above object, the present invention also provides the following technical solutions:

[0021] A construction method for realizing the above-mentioned negative pressure drainage and exhaust structure for a sloped roof comprises the following steps:

[0022] a) Cleaning and slope adjustment of concrete roof base:

[0023] Clean the base layer, clean up the debris on the concrete roof, and remove the hollow, loose, and peeling parts;

[0024] b) Drilling of water collection pipes:

[0025] The diameter of the water collecting pipe is generally 2.5cm. Drill holes on the four sides of the water collecting pipe at a spacing of 10cm. The diameter of the holes is 5mm. Wrap the filter net around the water collecting pipe.

[0026] c) Laying mesh pipes on the roof:

[0027] According to the architectural drawing of the sloping roof, a distribution map of the mesh pipes is drawn, and an accurate position map is measured on the roof according to the distribution map. The water collecting pipes are laid out according to the layout, and the adjacent water collecting pipes are welded firmly, and the ends of the mesh pipes are connected to the downpipes;

[0028] d) Laying of permeable layer:

[0029] Permeable concrete is laid beside the water collection pipe. The width of the permeable concrete is 0.2 meters. The thickness of the permeable concrete is the same as the diameter of the water collection pipe. The porosity of the permeable concrete is 25%. Then, perlite is laid on the concrete roof outside the permeable concrete area to form a permeable layer.

[0030] e) Lay a waterproof layer, a thermal insulation layer and a concrete protective layer in sequence on the upper side of the permeable layer;

[0031] f) Installation of drainage components:

[0032] The lower part of the drain pipe with the wing ring extends into the rainwater pipe, and the wing ring of the drain pipe is buried in the concrete protective layer on the upper part of the insulation layer;

[0033] g) Lay a brick and tile layer on the upper side of the concrete protective layer to complete the construction of the negative pressure drainage and exhaust structure of the sloping roof.

[0034] After adopting this method, the mesh pipe is used as a drainage and exhaust channel. The vertical and horizontal spacing of the mesh pipe is 6m, and it is made to be vertically and horizontally connected and connected to the downspout. The waterproof layer is not closed at the junction of the permeable concrete and the drainage pipe, so that excess water vapor can be discharged from here. In order to isolate rainwater and prevent rainwater from backflowing from the empty space, a drainage pipe with a wing ring is inserted into the downspout. The wing ring is buried in the concrete protective layer on the waterproof layer. A gap should be left between the drainage pipe and the downspout. The water and steam entering the negative pressure drainage and exhaust structure of the slope roof are discharged through the annular gap, while preventing rainwater from flowing into the drainage and exhaust duct. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 It is a cross-sectional view of a schematic diagram of an embodiment of the negative pressure drainage and exhaust structure for a sloped roof.

[0036] Figure 2 yes Figure 1 Magnified image of .

[0037] Figure 3 It is a top view of a schematic diagram of an embodiment of the negative pressure drainage and exhaust structure for a sloped roof (the waterproof layer, thermal insulation layer, concrete protective layer, and brick and tile layer are omitted in the figure).

[0038] Description of the numbers in the figure:

[0039] Concrete roof - 100; downspout - 110; permeable layer - 200; perlite - 210; permeable concrete - 220; waterproof layer - 300; insulation layer - 400; water collection pipe - 511; mesh pipe - 510; floor drain - 610; drainage pipe - 620; wing ring - 621; concrete protective layer - 700; brick and tile layer - 800. DETAILED DESCRIPTION

[0040] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention, so the present invention is not limited by the specific implementation disclosed below.

[0041] The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementations.

[0042] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items.

[0043] See also Figures 1 to 3 .

[0044] The negative pressure drainage and exhaust structure of the slope roof includes a permeable layer 200, a waterproof layer 300, an insulation layer 400, a concrete protective layer 700, a brick and tile layer 800, a pipe assembly, a pipeline assembly and a plurality of drainage assemblies.

[0045] The concrete roof 100 at the bottom of the sloping roof is pre-buried with multiple downpipes 110. The pipeline assembly includes a number of water collecting pipes 511. The water collecting pipes 511 are made of PPR pipes. The side walls of the water collecting pipes 511 are provided with a number of through holes. The outer walls of the water collecting pipes 511 are wrapped with filter nets. The multiple water collecting pipes 511 are combined to form a mesh pipeline 510 covering the sloping roof. The mesh pipeline 510 is pre-buried in the permeable layer 200, and the mesh pipeline 510 is communicated with the downpipes 110.

[0046] The permeable layer 200, the waterproof layer 300, the thermal insulation layer 400, the concrete protective layer 700 and the brick and tile layer 800 are laid in sequence on the upper side of the concrete roof 100. The permeable layer 200 is divided into a permeable area close to the mesh pipe 510 and the remaining conventional area. The filling material of the conventional area is perlite 210, and permeable concrete 220 is laid in the permeable area.

[0047] The width of the permeable concrete 220 is 0.2 meters. The laying thickness of the permeable concrete 220 is the same as the diameter of the water collecting pipe 511, and the porosity of the permeable concrete 220 is 25%.

[0048] The drainage component corresponds to the downpipe 110 one by one, and the drainage component at least includes a floor drain 610 and a drainage pipe 620. The drainage pipe 620 is made of stainless steel. The upper end of the drainage pipe 620 is fixedly connected to the water outlet on the lower side of the floor drain 610. A wing ring 621 extends outward from the upper outer wall of the drainage pipe 620. The floor drain 610 and the upper part of the drainage pipe 620 are pre-buried in the permeable layer 200, the waterproof layer 300, the insulation layer 400, the concrete protective layer 700 and the brick and tile layer 800. The upper end face of the floor drain 610 is on the brick and tile layer 800. The lower end of the drainage pipe 620 extends into the downpipe 110 from the corresponding upper end of the downpipe 110, and there is a gap between the lower outer wall of the drainage pipe 620 and the inner wall of the downpipe 110.

[0049] The construction method for realizing the above-mentioned negative pressure drainage and exhaust structure of the slope roof comprises the following steps:

[0050] a) Cleaning and slope adjustment of 100% concrete roof base:

[0051] Clean the base layer, clean up the debris on the concrete roof 100, scrape off the hollow, loose and peeling parts, clean the oil stains, rust, etc. with a wire brush, sandpaper or organic solvent, and then fill the gap with 1:3 cement mortar.

[0052] The protruding roof structure (columns, chimneys, parapets, etc.) and the corners of the leveling layer (water outlets, slopes, etc.) are all made into arc shapes. The leveling layer must have sufficient strength to be flat, hard and clean.

[0053] b) Drilling of water collecting pipe 511:

[0054] The diameter of the water collecting pipe 511 is generally 2.5 cm. Holes are drilled on the four sides of the water collecting pipe 511 at intervals of 10 cm. The diameter of the holes is 5 mm. A filter net is wrapped around the water collecting pipe 511.

[0055] c) Laying mesh pipes 510 on the roof:

[0056] According to the sloping roof architectural drawing, a distribution map of the mesh pipe 510 is drawn, and an accurate position map is measured on the roof based on the distribution map. The water collecting pipes 511 are arranged according to the layout, and adjacent water collecting pipes 511 are welded firmly. The ends of the mesh pipes 510 are connected to the downpipes 110.

[0057] d) Laying of the water-permeable layer 200:

[0058] The permeable concrete 220 is laid beside the water collecting pipe 511. The width of the permeable concrete 220 is 0.2 meters. The laying thickness of the permeable concrete 220 is the same as the diameter of the water collecting pipe 511. The porosity of the permeable concrete 220 is 25%. Perlite 210 is then laid on the concrete roof 100 outside the area where the permeable concrete 220 is laid to finally form a permeable layer 200.

[0059] e) A waterproof layer 300 , a thermal insulation layer 400 and a concrete protective layer 700 are sequentially laid on the upper side of the water-permeable layer 200 , and the waterproof layer 300 is a general waterproof membrane.

[0060] f) Installation of drainage components:

[0061] The diameter of drain pipe 620 is slightly smaller than that of downpipe 110. The length of drain pipe 620 is 50 cm, the width of wing ring 621 is 5 cm, the thickness of drain pipe 620 and wing ring 621 is 2 mm, the wing ring 621 and drain pipe 620 are fully welded on both sides, the wing ring 621 is 3 cm away from the top of drain pipe 620, the diameter of downpipe 110 is 10 cm, and the diameter of drain pipe 620 is 8 cm.

[0062] The lower part of the drain pipe 620 with the wing ring 621 extends into the rainwater pipe, and the wing ring 621 of the drain pipe 620 is buried in the concrete protective layer 700 on the upper part of the insulation layer 400. In order to prevent the concentric circle of the rainwater pipe from being displaced and the position from being difficult to retain during the construction of the roof structure layer, the sleeve should be installed in advance when the slope layer is made on the roof, and the horizontal position and reserved height of the sleeve should be positioned.

[0063] g) Lay a brick and tile layer 800 on the upper side of the concrete protective layer 700 to complete the construction of the negative pressure drainage and exhaust structure of the slope roof.

[0064] The mesh pipe 510 is used as a channel for drainage and exhaust. The mesh pipe 510 has a vertical and horizontal spacing of 6m. It is made to be vertically and horizontally connected and connected to the downspout. The waterproof layer 300 is not closed at the junction of the permeable concrete 220 and the drain pipe 620, so that excess water vapor can be discharged from here. In order to isolate rainwater and prevent rainwater from flowing back from the empty space, a drain pipe 620 with a wing ring 621 is inserted into the downspout 110. The wing ring 621 is buried in the concrete protective layer 700 on the waterproof layer 300. A gap should be left between the drain pipe 620 and the downspout 110. The water and steam entering the negative pressure drainage and exhaust structure of the slope roof are discharged through the annular gap, while preventing rainwater from flowing into the drainage and exhaust duct.

[0065] The economic benefit analysis table of the construction method of the negative pressure drainage and exhaust structure of the slope roof and the traditional roof construction method is as follows:

[0066]

[0067]

[0068] As can be seen from the table above, without considering the cost of repair and rework in the later stage of traditional roof construction, the cost of this construction method is slightly lower than that of traditional roof construction methods; however, this construction method is a one-time investment, which completely prevents water from leaking into the roof and causing water to be unable to be drained. After being exposed to the sun, the water vapor in the roof layer is more difficult to control, which will cause the roofing roll to bulge. The most important thing is to provide conditions for the next construction process and prevent future troubles; compared with the cost of repairing hidden dangers in the later stage, this construction method is more economical.

[0069] The above is only one embodiment of the present invention. It should be pointed out that a person skilled in the art may make several modifications and improvements without departing from the principle of the present invention, and these should also be regarded as falling within the scope of protection of the present invention.

Claims

1. A negative pressure drainage and exhaust structure for a sloped roof, characterized by: The invention comprises a permeable layer (200), a waterproof layer (300), a thermal insulation layer (400), a concrete protective layer (700), a brick and tile layer (800), a pipe assembly, a pipeline assembly and at least one set of drainage assemblies, wherein the permeable layer (200), the waterproof layer (300), the thermal insulation layer (400), the concrete protective layer (700) and the brick and tile layer (800) are sequentially laid on the upper side of a concrete roof (100), and at least one downpipe (110) is pre-buried in the concrete roof (100) at the bottom of the sloping roof, and the pipeline assembly comprises a plurality of water collecting pipe pieces (511), a plurality of through holes are opened on the side wall of the water collecting pipe piece (511), and the plurality of water collecting pipe pieces (511) are combined to form a mesh pipeline (510) covering the sloping roof, and the mesh pipeline (510) is pre-buried in the permeable layer (200), and the mesh pipeline (510) is communicated with the downpipe (110); The drainage assembly corresponds to the downpipe (110) one by one, and the drainage assembly at least comprises a floor drain (610) and a drainage pipe (620). The upper end of the drainage pipe (620) is fixedly connected to the water outlet at the lower side of the floor drain (610). The upper parts of the floor drain (610) and the drainage pipe (620) are pre-buried in a permeable layer (200), a waterproof layer (300), a thermal insulation layer (400), a concrete protective layer (700) and a brick and tile layer (800). The lower end of the drainage pipe (620) extends from the upper end of the corresponding downpipe (110) into the downpipe (110).

2. The negative pressure drainage and exhaust structure for sloped roof according to claim 1 is characterized by: The outer wall of the water collecting pipe (511) of the pipeline assembly is wrapped with a filter screen.

3. The negative pressure drainage and exhaust structure for sloped roof according to claim 1 is characterized by: The outer wall of the drainage pipe (620) located in the concrete protective layer (700) is provided with a wing ring (621) extending outward.

4. The negative pressure drainage and exhaust structure for sloped roof according to claim 1 is characterized by: The permeable layer (200) is divided into a permeable area close to the mesh pipeline (510) and a remaining conventional area. The conventional area is filled with perlite (210), and permeable concrete (220) is laid in the permeable area.

5. The negative pressure drainage and exhaust structure for sloped roof according to claim 1 is characterized by: The water collecting pipe (511) is made of PPR pipe; the drainage pipe (620) is made of stainless steel.

6. A construction method for realizing the negative pressure drainage and exhaust structure of a sloped roof according to any one of claims 1 to 5, comprising the following steps: a) Cleaning and slope adjustment of concrete roof (100): Cleaning the base layer, cleaning the debris on the concrete roof (100), and removing the hollow, loose, and peeling parts; b) Drilling of water collecting pipe (511): The diameter of the water collecting pipe (511) is generally 2.5 cm. Holes are drilled on the four sides of the water collecting pipe (511) at intervals of 10 cm. The diameter of the holes is 5 mm. A filter screen is wrapped around the water collecting pipe (511). c) Laying mesh pipes (510) on the roof: According to the architectural drawing of the sloping roof, a distribution map of the mesh pipeline (510) is drawn, and an accurate position map is measured on the roof according to the distribution map, and water collecting pipes (511) are arranged according to the layout, and adjacent water collecting pipes (511) are firmly welded, and the ends of the mesh pipeline (510) are connected to the downpipe (110); d) Laying of the permeable layer (200): The permeable concrete (220) is laid beside the water collecting pipe (511), the width of the permeable concrete (220) is 0.2 meters, the laying thickness of the permeable concrete (220) is the same as the diameter of the water collecting pipe (511), and the porosity of the permeable concrete (220) is 25%. Then, perlite (210) is laid on the concrete roof (100) outside the area where the permeable concrete (220) is laid, and finally a permeable layer (200) is formed; e) laying a waterproof layer (300), a thermal insulation layer (400) and a concrete protective layer (700) in sequence on the upper side of the permeable layer (200); f) Installation of drainage components: The lower part of the drainage pipe (620) with the wing ring (621) extends into the rainwater pipe, and the wing ring (621) of the drainage pipe (620) is buried in the concrete protective layer (700) on the upper part of the insulation layer (400); g) Lay a brick and tile layer (800) on the upper side of the concrete protective layer (700) to complete the construction of the negative pressure drainage and exhaust structure of the slope roof.