Construction method for protecting building in-situ reservation and foundation pit cover excavation
By using the jacking device to lift the building structure after strengthening the building, setting up supporting piles, and replacing the supporting structure, the problems of building damage and high cost in traditional methods are solved, and the original site of the building is preserved and the underground space is developed.
Patent Information
- Application Number
- CN202410919866.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-10
- Publication Date
- 2024-10-15
AI Technical Summary
The traditional underground development method of protected buildings will cause damage to the building itself during the building translation process, and the construction cost is high.
The construction method of preserving the original site of the building and excavation of the foundation pit is adopted, including reinforcing the building, setting up supporting piles and replacement structures, using jacking devices to lift the building structure, providing working space for the first-floor structural beams and slabs, and ensuring that the design is achieved After the hardness, it falls back to the roof, realizing the development of underground space and the preservation of the original site of the building.
It reduces the damage to the building during the translation process, shortens the construction period, saves the cost, and achieves the protection of the original site of the building and the development of underground space.
Smart Images

Figure CN118774437A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to a construction method for protecting the original site of a building and covering and excavating a foundation pit. Background Art
[0002] Protected buildings are buildings or structures with high historical, scientific and artistic value that are protected as cultural relics. When the underground space of some ancient protected buildings is developed and utilized, the traditional practice is to move the protected buildings to an off-site intermediate site before developing the underground space. After the basement development is completed, the protected buildings are moved back.
[0003] The traditional approach will cause certain damage to the protected building itself during the building translation process, which is not conducive to the protection and repair of the building, and the construction cost is high. Summary of the invention
[0004] In order to overcome the defects of the existing technology, a construction method of retaining the original site of the protected building and covering the foundation pit is provided to solve the problem that the traditional practice of underground development of the protected building will cause certain damage to the protected building itself during the building translation process, which is not conducive to the protection and repair of the building, and the construction cost is high.
[0005] In order to achieve the above-mentioned purpose, a construction method for preserving the original site of a protected building and covering and excavating a foundation pit is provided, comprising the following steps:
[0006] Strengthening of protected buildings;
[0007] A plurality of supporting piles are provided in the foundation at the bottom of the protection building, wherein the plurality of supporting piles are arranged along the circumferential direction of the protection building;
[0008] Installing a support replacement structure at the bottom of the protected building;
[0009] Installing a jacking device between the supporting pile and the support replacement structure;
[0010] constructing a retaining structure in the foundation;
[0011] The lifting device lifts the support replacement structure, and the elevation of the bottom of the protective building structure is equal to the elevation of the top of the top plate of the high-pressure underground structure;
[0012] Excavating the first layer of earthwork of the foundation and constructing the top plate of the underground structure;
[0013] After the top plate reaches the designed hardness, the lifting device lowers the protective building structure so that the top plate is supported by the protective building structure;
[0014] The remaining structures of the underground structure are constructed below the top plate.
[0015] Further, the reinforcement of the protected buildings includes:
[0016] Providing support frames on the outer side of the protection building;
[0017] Providing a supporting steel structure on the inner side of the protection building;
[0018] A tension structure is installed between the supporting bent frame and the supporting steel structure.
[0019] Furthermore, steel sections are installed on the outer side and inner side of the protection building respectively, the tension structure is connected between the steel sections on the inner and outer sides of the protection building, the supporting frame is installed on the steel section on the outer side of the protection building, and the supporting steel structure is installed on the steel section on the inner side of the protection building.
[0020] Furthermore, the plurality of supporting piles are respectively arranged below two opposite sides of the supporting structure, and the jacking devices are respectively installed between the two opposite sides of the supporting structure and the supporting piles.
[0021] Furthermore, the lifting device is a jack.
[0022] Furthermore, when constructing the enclosure structure, column piles are driven into the foundation, and the column piles are supported on the top plate.
[0023] Furthermore, when implementing the step of constructing the remaining structures of the underground structure below the top plate, it includes:
[0024] Excavating the next layer of earthwork of the foundation layer by layer from top to bottom and installing a supporting structure on the inner side of the retaining structure;
[0025] After excavating to the bottom of the foundation pit, constructing the base plate of the underground structure;
[0026] The underground structure is constructed from bottom to top and connected to the top plate.
[0027] The beneficial effect of the present invention is that the construction method of the present invention for retaining the original site of the protected building and covering the foundation pit, using the support replacement structure and the jacking device, takes the supporting piles as the supporting points, and lifts the protected building as a whole, providing a working space for the first-floor structural beams and slabs (top slabs). After the construction of the first-floor structural beams and slabs is completed, the protected building as a whole is dropped back onto the top slab, and the earthwork and support of the foundation pit under the top slab are constructed normally, so as to achieve the original site retention of the protected building and the development of the underground space. The supporting piles and the surrounding structure provide vertical support for the top slab and the support system in the foundation pit. Taking the supporting piles as the supporting points, the protected building is lifted up as a whole, and after the top slab is constructed and reaches the strength, the protected building as a whole is dropped back onto the top slab, which not only completes the development of the underground space of the protected building, but also achieves the retention of the protected building in the original site.
[0028] The top plate in the construction method of retaining the original site of the protected building and covering the foundation pit of the present invention separates the protected building from the underground foundation pit construction, and the later repair work of the protected building and the underground structure are constructed at the same time, which greatly shortens the construction period and saves construction costs. The top plate can serve as a strong horizontal support to reduce the deformation of the foundation pit.
[0029] Compared to the construction method of moving the protected building to an off-site intermediate site and then developing the underground space and moving the building back after the basement development is completed, the construction method of retaining the protected building on the original site and covering the foundation pit can achieve the retention of the protected building on the original site and the development of the underground space, reduce a large amount of building movement and relocation work, and avoid site problems caused by the off-site intermediate site.
[0030] The construction method of retaining the original site of the protected building and covering and excavating the foundation pit of the present invention reduces the damage to the protected building itself due to the translation of the protected building. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Other features, objects and advantages of the present application will become more apparent by reading the detailed description of non-limiting embodiments made with reference to the following drawings:
[0032] Figures 1 to 6 It is a schematic diagram of the steps of a construction method for retaining the original site of a protected building and covering and excavating a foundation pit according to an embodiment of the present invention.
[0033] Figure 7 This is a schematic diagram of the reinforced state of the protected building according to an embodiment of the present invention. DETAILED DESCRIPTION
[0034] The present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the relevant invention, rather than to limit the invention. It is also necessary to explain that, for ease of description, only the parts related to the invention are shown in the accompanying drawings.
[0035] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0036] Reference Figures 1 to 6 As shown, the present invention provides a construction method for preserving the original site of a protected building and covering and excavating a foundation pit, comprising the following steps:
[0037] S1. Reinforce the protected building 1.
[0038] For details, see Figure 1 and Figure 7 As shown, the reinforcement treatment of the protected building 1 includes:
[0039] S11 , setting a support frame 8 on the outer side of the protection building 1 .
[0040] S12. A supporting steel structure 9 is provided on the inner side of the protected building 1.
[0041] S13, installing the tension structure 10 between the supporting frame and the supporting steel structure.
[0042] As a preferred embodiment, steel sections are installed on the outside and inside of the protective building 1 respectively, the tension structure is tied between the steel sections on the inside and outside of the protective building 1, the supporting frame is installed on the steel sections on the outside of the protective building 1, and the supporting steel structure is installed on the steel sections on the inside of the protective building 1.
[0043] S2. A plurality of supporting piles 2 are provided in the foundation at the bottom of the protected building 1 , and the plurality of supporting piles 2 are arranged along the circumferential direction of the protected building 1 .
[0044] In this embodiment, the supporting piles are anchor piles.
[0045] S3, installing the support replacement structure 3 at the bottom of the protected building 1.
[0046] In this embodiment, see Figure 7 As shown, a plurality of supporting piles 2 are respectively arranged below opposite sides of the supporting structure 3. Lifting devices 4 are respectively installed between the opposite sides of the supporting structure 3 and the supporting piles 2.
[0047] S4. Install the lifting device 4 between the supporting pile 2 and the support replacement structure 3.
[0048] As a preferred implementation, the lifting device 4 is a jack.
[0049] S5. Construct a retaining structure 5 in the foundation.
[0050] When constructing the enclosure structure 5 , column piles 51 are driven into the foundation, and the column piles 51 are supported on the top plate 61 .
[0051] S6. The lifting device 4 lifts the support replacement structure 3 to protect the elevation of the bottom of the building 1 structure to the elevation of the top of the top plate 61 of the high-pressure underground structure.
[0052] S7, excavating the first layer of earthwork of the foundation and constructing the top plate 61 of the underground structure 6.
[0053] S8. After the top plate 61 reaches the designed hardness, the lifting device 4 is lowered to the structure of the protective building 1 so that the top plate 61 is supported on the structure of the protective building 1.
[0054] S9. Construct the remaining structures of the underground structure below the top plate 61.
[0055] Specifically, the steps of constructing the remaining structures of the underground structure below the top plate 61 include:
[0056] S91, excavating the next layer of earthwork of the foundation layer by layer from top to bottom and installing the supporting structure 7 on the inner side of the retaining structure 5.
[0057] S92. After excavating to the bottom of the foundation pit, construct the base plate 62 of the underground structure.
[0058] S93, constructing the underground structure from bottom to top and connecting it to the top plate 61.
[0059] The construction key points of the construction method of the present invention for retaining the original site of the protected building and covering and excavating the foundation pit are:
[0060] 1. Construction of supporting piles, construction of protective building replacement structures, and reinforcement of steel structures.
[0061] 1. Use low-headroom equipment to complete the construction of supporting piles according to the location on the drawing.
[0062] 2. Carry out earthwork excavation indoors and outdoors, and use low-headroom equipment to complete the construction of supporting piles according to the supporting points of the replacement structure. After the supporting piles are cured and formed, complete the construction of the replacement structure of the protective building according to the detailed drawings of the replacement structure.
[0063] 3. The exterior walls of the protected buildings are reinforced with support racks and steel sections, while the interior walls are reinforced with steel sections and supporting steel structures. While reinforcing the structure, the dangerous, redundant and useless components of the protected buildings are removed to reduce the load on the protected buildings themselves.
[0064] 2. Construction of retaining structures and column piles.
[0065] The construction of the enclosure structure and column piles shall be completed according to the enclosure drawings. During the construction period, no significant impact shall be caused to the protected buildings.
[0066] 3. Protect the building's jacking and the construction of the first-floor structural beams and slabs (i.e., top slabs).
[0067] 1. Use the replacement support structure and jacks, take the supporting piles as the supporting points, and lift the protective building as a whole to provide working space for subsequent construction.
[0068] 2. After the overall jacking and lifting of the protected building, quickly complete the first-floor earthwork excavation and the first-floor structural beam and slab (basement top slab) construction according to the basement top slab drawings, and complete the connection with the column piles and supporting piles. The first-floor earthwork excavation is carried out according to the needs of the first-floor structural beam and slab construction.
[0069] 3. A hole is partially left in the top plate of the basement structure to solve the problems of hanging materials and excavation, and waterproof steel plates and steel bars are reserved in the hole. In addition, the car ramp area is constructed in advance to solve the problems of material transportation and excavation.
[0070] 4. Excavation of the next layer of earth, support construction, and base plate construction.
[0071] 1. After the strength of the first-floor structural beams and slabs (top slabs) reaches 100%, use jacks and replacement support structures to lower the entire protected building onto the first-floor structural beams and slabs (top slabs).
[0072] 2. Continue to complete the next layer of earthwork excavation and support construction according to the construction process of earthwork excavation and support construction. During the construction period, attention should be paid to minimizing the impact on the supporting piles and column piles, and the soil around the supporting piles and column piles should be evenly distributed and maintained stable.
[0073] 3. Further complete the base plate construction according to the construction process of earth excavation and base plate construction.
[0074] 5. Support removal and basement structure construction
[0075] 1. After the bottom slab is completed, continue to remove the second support and construct the basement structure upwards. After the B2 floor slab is completed, complete the connection between the B1 floor structural columns and the first floor structural beam slab (basement top slab) as soon as possible to stabilize the basement structure.
[0076] 2. After the basement structure is completed and the strength meets the requirements, the column piles and supporting piles can be removed. The removal should be as symmetrical as possible and static cutting should be used to complete the removal to reduce the impact on the basement structure and protected buildings.
[0077] The construction method of retaining the original site of the protected building and covering the foundation pit of the present invention utilizes a replacement support structure and a jacking device, and uses the supporting piles as support points to jack up and raise the protected building as a whole, thereby providing a working space for the first-floor structural beams and slabs (top slabs). After the construction of the first-floor structural beams and slabs is completed, the protected building as a whole is lowered back onto the top slab, and the foundation pit earthwork and support under the top slab are constructed normally, thereby achieving the original site retention of the protected building and the development of the underground space. The supporting piles and the surrounding structure provide vertical support for the top slab and the support system in the foundation pit. Using the supporting piles as support points, the protected building as a whole is jacked up and raised, and after the top slab is constructed and reaches the required strength, the protected building as a whole is lowered back onto the top slab, thereby not only completing the development of the underground space of the protected building, but also achieving the retention of the protected building at the original site.
[0078] The top plate in the construction method of retaining the original site of the protected building and covering the foundation pit of the present invention separates the protected building from the underground foundation pit construction, and the later repair work of the protected building and the underground structure are constructed at the same time, which greatly shortens the construction period and saves construction costs. The top plate can serve as a strong horizontal support to reduce the deformation of the foundation pit.
[0079] Compared to the construction method of moving the protected building to an off-site intermediate site and then developing the underground space and moving the building back after the basement development is completed, the construction method of retaining the protected building on the original site and covering the foundation pit can achieve the retention of the protected building on the original site and the development of the underground space, reduce a large amount of building movement and relocation work, and avoid site problems caused by the off-site intermediate site.
[0080] The construction method of retaining the original site of the protected building and covering and excavating the foundation pit of the present invention reduces the damage to the protected building itself due to the translation of the protected building.
[0081] The above description is only a preferred embodiment of the present application and an explanation of the technical principles used. Those skilled in the art should understand that the scope of the invention involved in the present application is not limited to the technical solution formed by a specific combination of the above technical features, but should also cover other technical solutions formed by any combination of the above technical features or their equivalent features without departing from the inventive concept. For example, the above features are replaced with (but not limited to) technical features with similar functions disclosed in the present application.
Claims
1. A construction method for preserving the original site of a protected building and covering and excavating a foundation pit, characterized in that: The following steps are involved: Strengthening of protected buildings; A plurality of supporting piles are provided in the foundation at the bottom of the protection building, wherein the plurality of supporting piles are arranged along the circumferential direction of the protection building; Installing a support replacement structure at the bottom of the protected building; Installing a jacking device between the supporting pile and the support replacement structure; constructing a retaining structure in the foundation; The lifting device lifts the support replacement structure, and the elevation of the bottom of the protective building structure is equal to the elevation of the top of the top plate of the high-pressure underground structure; Excavating the first layer of earthwork of the foundation and constructing the top plate of the underground structure; After the top plate reaches the designed hardness, the lifting device lowers the protective building structure so that the top plate is supported by the protective building structure; The remaining structures of the underground structure are constructed below the top plate.
2. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 1 is characterized in that: Strengthening of protected buildings includes: Providing support frames on the outer side of the protection building; Providing a supporting steel structure on the inner side of the protection building; A tension structure is installed between the supporting bent frame and the supporting steel structure.
3. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 2 is characterized in that: Steel sections are installed on the outer side and inner side of the protection building respectively, the tension structure is connected between the steel sections on the inner and outer sides of the protection building, the supporting frame is installed on the steel section on the outer side of the protection building, and the supporting steel structure is installed on the steel section on the inner side of the protection building.
4. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 1 is characterized in that: The plurality of supporting piles are respectively arranged below two opposite sides of the supporting structure, and the jacking devices are respectively installed between the two opposite sides of the supporting structure and the supporting piles.
5. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 4 is characterized in that: The lifting device is a jack.
6. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 1 is characterized in that: When constructing the enclosure structure, column piles are driven into the foundation, and the column piles are supported on the top plate.
7. The construction method for preserving the original site of the protected building and covering the foundation pit according to claim 1 is characterized in that: When implementing the step of constructing the remaining structures of the underground structure below the top plate, it includes: Excavating the next layer of earthwork of the foundation layer by layer from top to bottom and installing a supporting structure on the inner side of the retaining structure; After excavating to the bottom of the foundation pit, constructing the base plate of the underground structure; The underground structure is constructed from bottom to top and connected to the top plate.
Citation Information
Patent Citations
Construction method for increasing to build multi-storey basement to original building
CN101397852A
Old building demolition-free two-increase renovation construction process
CN107642252A
Method of excavating foundation ditch in situ and additionally arranging underground structure below existing building
CN110878562A
Method for creating construction site for developing underground space under existing building group
CN111075224A
Method for constructing foundation pit in situ and newly adding underground structure below existing preserved building
CN111335670A