A sensor installation device integrating digging, burying and filling and a method of using the same

Through an integrated sensor installation device including a lifting system, a replaceable working part, a frame and a control system, the problems of irregular sensor installation and inaccurate monitoring data in the prior art are solved, and the systematized installation and efficient monitoring of sensors are realized.

CN118774735BActive Publication Date: 2025-04-04JINAN URBAN CONSTRUCTION GROUP CO LTD +1
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410937886.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2025-04-04
Estimated Expiration
2044-07-12

AI Technical Summary

Technical Problem

The existing sensor installation method cannot achieve the excavation-burning-filling work of a set of equipment, which makes it difficult to visually controllable when installing deep sensors, resulting in large disturbances in the geotechnical environment and inaccurate monitoring data.

Method used

It provides a sensor installation device that integrates excavation-burning-filling, including a lifting system, a replaceable working part, a frame and a control system. Through semi-automated operation, the excavation-burning-filling work with the minimum disturbance of the geotechnical environment around the sensor is realized under visual control.

Benefits of technology

The systematized and standardized installation of sensors is realized, reducing the cost of manpower excavation, reducing the risk of monitoring environment changes and data inaccuracy, and improving the reliability of monitoring data.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774735B_ABST
    Figure CN118774735B_ABST
Patent Text Reader

Abstract

The present invention relates to an integrated excavation-burying-backfilling sensor installation device and a method of use, and discloses a sensor burying and backfilling system that can accurately excavate horizontally and vertically, semi-mechanized burying and backfilling, and realize visual integrated control. It specifically includes a chain-guide rail lifting system, an excavation main drill bit, a detailed drilling and excavation structure in the hole, a detailed backfilling structure in the hole, two types of transparent surrounding barrels, a main hole backfilling structure and an integrated control host system. The chain-guide rail lifting system is assembled into a main structure by a splicable frame, and constitutes a lifting and moving system with pulleys, motors, side rails, replaceable top plates and cables. A hole is opened in the middle of the replaceable top plate, and structures such as the excavation main drill bit and the transparent surrounding barrel can be replaced and fixed, and move along the side rail direction driven by the chain-guide rail lifting system and the hydraulic power system. The present invention also discloses a method of using the above-mentioned equipment, which realizes the burying of deep soil sensors with less disturbance, high efficiency, automation, visualization and controllability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of sensor monitoring and mechanical excavation construction, and in particular to a sensor installation device and a method for using the sensor that can reduce the environmental disturbance caused by excessive soil excavation within the sensor installation range and the influence on monitoring data. Background Art

[0002] In recent years, with the vigorous promotion and development of refined civil engineering construction, the characteristics and development trends of geotechnical environment in various stages of engineering construction have also been widely concerned. How to efficiently, reasonably and standardizedly realize the observation and data collection of deep underground environment has become a difficult problem and a technical problem that needs to be improved urgently. There are many types of sensors currently used for deep underground environmental performance monitoring, such as soil pressure monitoring sensors, pore water pressure monitoring sensors, water content monitoring sensors, displacement monitoring sensors, etc. Although different sensors have different shapes and working principles, the methods of burial and data collection have certain similarities.

[0003] At present, in terms of the existing sensor embedding and installation methods, the commonly used method is to directly excavate to the specified depth, then lower the sensor and directly backfill, and the excavation-embedding-filling of the sensor cannot be completed in a complete set. For example, Chen Yong et al. from the Three Gorges University’s invention patent "A sensor embedding device and embedding method thereof" (CN111622198A), Tang Yiqun et al. from Tongji University’s invention patent "A deep soil multiple sensor embedding device and embedding method thereof" (CN109056687A), and An Xiaoyu et al. from the Tianjin Water Transport Engineering Science Research Institute of the Ministry of Transport’s invention patent "Device and method for precise positioning and rapid embedding of micro sensors" (CN109142006A). The above sensor embedding equipment and methods cannot complete the digging-burying-filling work of sensors with a complete set of equipment. It is difficult to achieve visual and controllable mechanized operation when installing deep layers and multiple sets of sensors. Directly lowering and backfilling the soil in the excavated hole will cause excessive disturbance to the soil environment around the sensor, changing the properties and conditions of the original monitoring environment, resulting in inaccurate monitoring data results, which is difficult to meet the needs of geotechnical monitoring. Summary of the invention

[0004] In order to solve the problem that the existing technology cannot complete the digging-burying-filling work with a set of equipment, the present invention provides a sensor installation device and a method for using the digging-burying-filling integration. The device and the method for using the device can realize the one-time digging-burying-filling work of sensors at different depths underground with minimal disturbance to the rock and soil environment around the sensor under visual and controllable semi-automatic operation, reduce the cost of manpower excavation, and realize the burying and backfilling of sensors in a standardized and systematic manner. At the same time, the method of burying the sensor in a small hole excavated in the side wall can reduce the amount of excavation and backfilling of soil around the sensor, thereby reducing the changes in the monitoring environment caused by post-construction settlement and insufficient backfill compaction, and the resulting inaccurate monitoring data. It should be noted that the first direction described in the present invention is the moving direction of the excavation main drill bit, and the second direction is the direction of detailed drilling.

[0005] In a first aspect, a sensor installation device for integrated digging, burying and filling includes: a lifting system, a replaceable working part, a frame, and a control system;

[0006] The lifting system is used to drive the replaceable working part in a first direction;

[0007] The frame is used to support the main body of the installation device, and one side is provided with a structure for connecting the replaceable working part;

[0008] The replaceable working part is specifically the main drilling drill bit or the first transparent surrounding barrel or the second transparent surrounding barrel or the detailed drilling and excavation structure in the hole or the detailed backfilling structure in the hole or the main hole backfilling structure;

[0009] The first transparent barrel is internally suspended with an internal hanging support structure of a detailed drilling structure in the hole prefabricated according to the number of sensors to be buried, the interval between burials and the depth of burials; a pair of holes are provided through the side wall of the barrel, and a camera is provided above the hole on one side for observing the excavation of the sensor burial hole; a grooved sharp corner structure is fixed on the lower side of the barrel, and the protruding direction of the sharp corner is on the same vertical line as the opening on the side where the camera is provided. When the first transparent barrel is placed, the grooved sharp corner structure carves a vertical groove on the excavated main hole for placing the sensor connecting line therein;

[0010] The side wall of the second transparent barrel is provided with a vertical slit for the wire to enter and exit; the bottom of the barrel is a sealed inverted T-shaped hole structure, in which a detailed backfill structure is placed for the placement and backfilling of the sensor.

[0011] Based on the above solution, the main excavation drill bit consists of a drill rod and a motor.

[0012] On the basis of the above scheme, the lifting system is specifically a chain-guide rail lifting system;

[0013] The structure for connecting the replaceable working part is specifically a replaceable top plate, and a hole is opened in the middle of the replaceable top plate;

[0014] The top and bottom ends of the frame are each provided with a pulley, the top is provided with a motor and a hydraulic device, and a pair of side surfaces are provided with side rails. The replaceable working part is driven by a chain to move along the side rail direction, and the side rail is used to provide guide support for the drilling of the main drill bit for excavation.

[0015] On the basis of the above scheme, a displacement sensor and a level are provided at the bottom plate of the chain-guide rail lifting system. The displacement sensor detects the drilling and placement depths, and the level detects the posture state.

[0016] Based on the above scheme, the frame is specifically a hollow cubic splicing frame; a groove of a certain depth is provided on the top edge of the frame, and a matching protrusion is provided on the bottom edge, and two adjacent frame structures are spliced ​​and reinforced by connecting parts in combination with the groove and protrusion structure.

[0017] On the basis of the above scheme, the detailed drilling and digging structure in the hole is provided with a corresponding number and interval of fishbone-shaped internal hanging support structures according to the number and interval of buried sensors, and is suspended in the first transparent barrel; at the designed sensor burying place, a lateral extension end is provided corresponding to the through holes of the first transparent barrel, and a retractable drill bit is provided on one side of the sensor burying of each pair of lateral extension ends, and a first jack is provided on the other side. When working, the retractable drill bit and the first jack are extended from the through hole at the same time, and the retractable drill bit excavates the sensor burying hole at the designed position, and at the same time the small jack contacts the opposite side soil wall to provide reaction support force.

[0018] On the basis of the above scheme, the detailed backfill structure in the hole is composed of an L-shaped backfill material bin, a second jack, a third jack, and a feed pipe, and is placed at the bottom of the second transparent barrel;

[0019] The second jack is used to push the L-shaped backfilling bin into the excavated sensor embedding hole;

[0020] The third jack is used to push the sensor into the embedding hole or push the backfill soil into the embedding hole;

[0021] The feed pipe is used to pour the backfill soil material into the L-shaped backfill material bin after the second jack is retracted.

[0022] Based on the above scheme, the main hole backfill structure consists of a top hydraulic device and a compaction hammer. Backfill soil is dropped from the hole, and the hydraulic device drives the compaction hammer to compact the backfill soil poured into the main soil hole layer by layer.

[0023] Based on the above scheme, the installation device also includes an integrated control host system, which is composed of a computer control system, connecting wires and a camera. The connecting wires connect the lifting system, the main excavation drill bit, the detailed drilling and excavation structure in the hole, the detailed backfill structure in the hole, and the main hole backfill structure to the computer control system, and are connected to the cameras installed on the first transparent barrel and the second transparent barrel to control the operation and stop of each component.

[0024] In a second aspect, a method for using a sensor installation device that integrates digging, burying and filling is provided, comprising the following steps:

[0025] Locate the sensor embedding point, assemble the frame body to a sufficient height according to the maximum design embedding depth of the sensor, fix and adjust the bottom, and install the main drill bit for excavation;

[0026] The main drill bit for excavation drills in a first direction, and is taken out and disassembled after the operation is completed;

[0027] Replace the first transparent enclosure barrel, hang the inner hanging support structure of the detailed drilling and excavation structure in the hole prefabricated according to the designed number of sensors, the intervals between them and the depth of the sensors in the first transparent enclosure barrel, and start the lifting system to place the two in the preset burying position;

[0028] Perform drilling operation in the second direction;

[0029] Carry out sensor burying operation;

[0030] Carry out lateral backfilling operations;

[0031] The lifting system lifts the second transparent barrel to the upper buried hole, repeats the above operation until all sensors are installed, and the lifting system lifts the second transparent barrel out of the hole and takes it out;

[0032] Replace the main hole backfill structure, pour the backfill soil into the excavated main hole in small amounts and multiple times, and use the lifting system to put the main hole backfill structure to the appropriate position to compact the backfill soil in the hole;

[0033] After compaction to the standard requirements, lift the main hole backfill structure, pour in a small amount of backfill soil again for compaction, and repeat this operation until the excavation of the main hole is completed and the backfill structure of the main hole is lifted above the ground surface by the lifting system, and the excavation-burying-filling work of the sensor is completed.

[0034] Beneficial effects of the present invention:

[0035] (1) The present invention provides an integrated digging-burying-backfilling sensor installation device and method of use, which can use the same set of equipment to realize the hole digging, burying and backfilling of the sensor at the sensor pre-buried location, so as to systematize and unify the sensor installation process and reduce the inconvenience of different equipment working together.

[0036] (2) The integrated excavation-burying-filling sensor installation device and method of use of the present invention can realize the burial and backfilling of deep underground soil sensors under the control of the integrated control host system while the thrust and drilling speed are controllable and visible, thereby reducing labor costs, avoiding underground operations of personnel, and safely and reasonably realizing the burial and backfilling of underground sensors.

[0037] (3) The present invention provides an integrated excavation-burying-filling sensor installation device and use method, which replaces the traditional method of directly excavating a pilot hole and then lowering the sensor and directly backfilling the soil by excavating a small hole in the side wall to bury the sensor. This can reduce the amount of excavation and backfilling of soil around the sensor, thereby reducing changes in the monitoring environment caused by post-construction settlement and insufficient backfill compaction and the resulting inaccurate monitoring data, thereby maximizing the retention of the shape of the rock and soil around the sensor, making the data more reliable.

[0038] (4) The sensor installation device for integrated digging, burying and filling of the present invention can be adjusted arbitrarily to achieve precise depth excavation in the horizontal and vertical directions. It can be used for both vertical excavation and horizontal excavation, and is easy to operate. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] The present invention has the following accompanying drawings:

[0040] Figure 1 It is a schematic diagram of the splicable frame of the present invention;

[0041] Fig. 2 is a schematic diagram of the main hole excavation of the present invention;

[0042] FIG3 is a schematic diagram of excavation of a pre-buried hole for a sensor according to the present invention;

[0043] FIG4 is a schematic diagram of sensor installation and backfilling according to the present invention;

[0044] FIG5 is a schematic diagram of the main hole backfilling of the present invention;

[0045] Reference numerals:

[0046] 1. Frame body; 2. Connecting bolts; 3. Connecting nuts; 4. Embedding protrusions; 5. Embedding grooves; 6. Replaceable top plate with a hole in the middle; 7. Main drill motor; 8. Main drill rod; 9. Side rails; 10. Level; 11. Displacement sensor; 12. Chain; 13. Bottom pulley; 14. Top pulley; 15. Pulley power motor; 16. Connecting wires; 17. Connecting wires; 18. Computer control system; 19. Fixed base; 20. Lateral support rods; 21. Support fixed end; 22. Moving rollers; 23. A transparent barrel; 24. Grooved sharp-angle structure; 25. Fixing bolts; 26. Pinhole camera of the first barrel; 27. Internal supporting structure; 28. Retractable drill bit; 29. ​​First jack; 30. Second transparent barrel; 31. Sensor wire inlet and outlet groove; 32. Pinhole camera of barrel B; 33. Inverted T-shaped hole structure; 34. Sensor pre-buried hole; 35. L-shaped backfilling bin; 36. Second jack; 37. Third jack; 38. Sensor; 39. Feeding pipe; 40. Compacting hammer; 41. Top hydraulic device. DETAILED DESCRIPTION

[0047] The present invention mainly solves the problem of inaccurate monitoring data caused by factors such as large disturbance of geotechnical environment, insufficient backfill compaction, post-construction settlement and soil loss caused by the traditional installation method of direct excavation and landfilling during the installation of sensors required for underground geotechnical environment monitoring, as well as the problem that the underground sensor excavation-burying-filling process cannot be completed in a good system. It mainly uses semi-automatic, controllable and visible mechanical equipment to excavate a small pre-buried hole of the same size as the sensor towards the intact soil side wall after the main hole is excavated, and then the sensor is placed and mechanized backfilling is carried out to reduce the disturbance of the soil environment in the sensor contact interface, and the whole process is mechanized, controllable and visible, which improves the standardization of sensor burial work and the quality and accuracy of monitoring data.

[0048] To make the objects, advantages and features of the present invention more apparent, the following Figure 1 -5 and the specific implementation mode (longitudinal excavation) further describe the present invention in detail, and the horizontal excavation mode can be achieved by making corresponding adjustments to the longitudinal excavation mode.

[0049] The integrated digging-burying-filling sensor installation device consists of a chain-guide rail lifting system, an excavation main drill bit, a first transparent surrounding barrel, a second transparent surrounding barrel, a detailed drilling and digging structure in the hole, a detailed backfilling structure in the hole, a main hole backfilling structure and an integrated control host system.

[0050] The integrated digging-burying-filling sensor installation device can semi-automatically bury and backfill sensors deep in the vertical direction with reduced disturbance, and can also bury and backfill sensors horizontally or at a certain angle to realize the collection of different types of data. The integrated digging-burying-filling equipment controlled by the integrated control host system can bury and backfill sensors deep in the underground soil under the condition that the thrust and drilling speed are controllable and visible.

[0051] like Figure 1 The spliced ​​frame is a cubic hollow steel frame structure, a groove of a certain depth is provided on the top edge of the frame, and a protrusion matching it is provided on the bottom edge. Two adjacent frame structures are spliced ​​and reinforced by the groove and protrusion structure with bolts and nuts, thereby forming a main frame support structure of the sensor installation device of any height. In addition, a pair of side surfaces of the frame structure are provided with lateral guide rail structures to provide guide support for the drilling of the main drill bit for excavation.

[0052] The main excavation drill bit is composed of a drill rod and a motor, fixed on a replaceable top plate with a central opening, and moves along the side rails of the chain-guide rail lifting system driven by the drilling power.

[0053] As shown in Figures 2 (a)-2 (c), the chain-guide rail lifting system: the main frame support structure is assembled from a splicable frame. The support mechanism can not only complete the vertical excavation work, but also can be adjusted to any angle in the horizontal direction for excavation. The support structure and the pulleys, motors, side rails, replaceable top plates and chains on both sides of the bottom constitute a lifting and moving system. The middle opening of the replaceable top plate, the replaceable fixed excavation main drill bit, the detailed drilling and excavation structure in the hole, the detailed backfilling structure in the hole, the first transparent enclosure barrel, the second transparent enclosure barrel, the main hole backfilling structure, and move along the side rail direction driven by the chain-guide rail lifting system and the hydraulic power system. The bottom plate of the chain-guide rail lifting system is provided with a displacement sensor and a level meter to monitor the horizontal state of the system and the depth of drilling and placement. It should be pointed out that Figure 2 (c) shows the state of the installation device when it is excavating horizontally. Those skilled in the art can read the longitudinal excavation implementation method in this specification and make corresponding adjustments to achieve horizontal excavation.

[0054] As shown in Figures 3 (a) and 3 (b), the first transparent barrel is fixed at the top to a replaceable top plate with a hole in the middle of the chain-guide lifting system, and the lower part extends into the excavated main hole. The side walls of the barrel are penetrated with pairs of holes at intervals according to the installation positions of the sensors. A pinhole camera is provided above the hole on one side to observe the excavation of the sensor embedding hole. A grooved sharp-angle structure is fixed to the lower side of the first transparent barrel by a bolt structure. The protruding direction of the sharp corner is on the same vertical line as the hole on the side where the pinhole camera is provided. When the first transparent barrel is lowered, the grooved sharp-angle structure can carve a vertical groove on the excavated main hole, into which the sensor connecting line can be placed.

[0055] As shown in Figures 3(c) and 3(d), the second transparent barrel is fixed at the top to a replaceable top plate with a hole in the middle of the chain-guide lifting system, and the lower part extends into the excavated main hole. The side wall of the barrel is provided with a vertical slit for the wire to enter and exit. The bottom of the barrel is a sealed inverted T-shaped hole structure, in which a detailed backfill structure is placed for the placement and backfilling of sensors, and it is lifted step by step from bottom to top to complete the buried work of sensors at different depths.

[0056] As shown in Figures 4 (a)-4 (c), the detailed drilling and excavation structure in the hole is designed with a corresponding number and spacing of fishbone-shaped internal hanging support structures according to the number and spacing of buried sensors, which are suspended in the first transparent barrel. At the designed sensor burying location, corresponding to the through holes of the first transparent barrel, lateral extension ends are provided. A retractable drill bit is provided on one side of the sensor burying location of each pair of lateral extension ends, and a first jack (small jack) is provided on the other side. When working, the retractable drill bit and the small jack are extended from the through hole at the same time. The retractable drill bit excavates the sensor burying hole at the designed position, and the small jack contacts the opposite side soil wall to provide reaction support force.

[0057] As shown in Figures 4 (c)-4 (k), the detailed backfilling structure in the hole is composed of an L-shaped backfilling bin, a second jack, and a third jack, and is placed at the bottom of the second transparent enclosure. After being lowered to the designated position by the chain-guide lifting system, the second jack first pushes the L-shaped backfilling bin into the excavated sensor burying hole, and then the third jack pushes the sensor lowered into the bin into the burying hole, and then the third jack is retracted and put into the discharge pipe, and the backfill soil is poured into the bin by the discharge pipe, and the backfill soil is pushed into the burying hole by the third jack and compacted by static pressure until the burying hole is backfilled. Finally, the discharge pipe is retracted, and the second jack drives the L-shaped backfilling bin to retract from the vicinity of the burying hole into the second transparent enclosure. The detailed backfilling in a hole is completed, and the lifting system lifts the second transparent enclosure to the upper burying hole, and repeats the above operation. This operation can realize the burying of soil backfilling, steel needle insertion and cement sealing sensors.

[0058] As shown in Figures 5(a) and 5(b), the main hole backfill structure is composed of a top hydraulic device and a compaction hammer. When all sensor holes are buried and backfilled, the main hole backfill structure is replaced and installed in the middle of the replaceable top plate. Backfill soil is lowered from the hole opening. The hydraulic device drives the compaction hammer to compact the backfill soil poured into the main hole layer by layer until the compaction requirements are met and the main hole backfill is completed. Then, the backfill soil is lifted up to the outside of the hole opening layer by layer.

[0059] The integrated control host system is composed of a computer control system, connecting wires and cameras. The connecting wires connect the chain-guide lifting system, the main excavation drill bit, the detailed drilling and excavation structure in the hole, the detailed backfill structure in the hole, and the main hole backfill structure to the computer control system, and are connected to the cameras installed on the first and second transparent barrels to control the operation and stop of each component, thereby realizing visible and controllable underground sensor burial work.

[0060] The operation and application of the present invention in the vertical direction specifically includes the following steps:

[0061] Step 1: Push the chain-guide lifting system to the sensor embedding point, assemble the splicable frame body 1 to a sufficient height according to the maximum design embedding depth of the sensor, fix the bottom and adjust the level, debug the displacement sensor 11 and return it to zero, install the main drill rod 8 together with the main drill motor 7 into the hole in the middle of the replaceable top plate 6 with a hole in the middle, and connect the connecting wire 17 to the junction box of the integrated control host system;

[0062] Step 2: The computer control system 18 of the integrated control host system starts the equipment, so that the main drill rod 8 drills vertically downward along the side rail 9, and the displacement sensor 11 monitors the depth of the drill bit moving downward until the preset drilling depth is reached, the rotation drilling of the main drill rod 8 is stopped, and the chain-guide lifting system is used to lift it outside the excavation main hole, and the main drill rod 8 in the middle of the replaceable top plate is taken out together with the main drill motor 7;

[0063] Step 3: Place the first transparent enclosure barrel 23 in the middle of the replaceable top plate 6 with a hole in the middle, hang the inner hanging support structure 27 of the detailed drilling structure in the hole prefabricated according to the number of sensors, the interval and the depth of the sensors in the first transparent enclosure barrel 23, start the chain-guide rail lifting system to lower the two to the preset embedding position, control the retractable drill bit 28 and the small jack 29 to extend from the through hole of the first transparent enclosure barrel 23 at the same time, and the retractable drill bit 28 digs the sensor pre-buried hole 34 at the designed position, and the first jack 29 contacts the opposite side soil wall to provide a reaction support force until the drilling depth of the retractable drill bit 28 meets the requirements, then stop drilling, and retract the retractable drill bit 28 and the first jack 29 to the first transparent enclosure barrel 23, and lift them out of the hole by the chain-guide rail lifting system, and take them out from the middle of the replaceable top plate 6 with a hole in the middle;

[0064] Step 4: Place the second transparent barrel 30 with the detailed backfill structure in the hole on the bottom in the middle of the replaceable top plate 6 with a hole in the middle, and lower it to the deepest position of the sensor pre-buried hole 34 by the chain-guide lifting system. First, the second jack 36 pushes the L-shaped backfill bin 35 into the excavated sensor pre-buried hole 34, and then the third jack 37 pushes the sensor 38 lowered into the bin into the sensor pre-buried hole 34, then the third jack 37 is retracted and put into the discharge pipe 39, and the backfill soil is poured into the L-shaped backfill bin 35 by the discharge pipe 39, and the second jack 36 is used to The backfill soil is pushed into the sensor pre-buried hole 34 and compacted by static pressure until the sensor pre-buried hole 34 is backfilled. Finally, the feed pipe 39 is retracted, and the second jack 36 drives the L-shaped backfill material bin 35 to retract from the vicinity of the sensor pre-buried hole 34 into the second transparent enclosure 30. After the backfilling of the details in one hole is completed, the chain-guide lifting system is used to lift the second transparent enclosure 30 to the upper buried hole. The above operation is repeated until all underground sensors are installed. The chain-guide lifting system is used to lift the second transparent enclosure 30 out of the hole and take it out from the middle of the replaceable top plate 6 with a hole in the middle.

[0065] Step 5: Place the main hole backfill structure in the middle of the replaceable top plate, pour the backfill soil into the excavated main hole in small amounts and multiple times, lower the main hole backfill structure by the chain-guide rail lifting system until it is suitable, start the top hydraulic device 41 to drive the compaction hammer 40 to compact the backfill soil in the hole, and after compaction to the standard requirements, lift the main hole backfill structure upward, pour a small amount of backfill soil again for compaction, and repeat this operation until the excavated main hole is backfilled. The main hole backfill structure is lifted above the ground surface by the chain-guide rail lifting system, and the digging, burying and filling work of the underground sensor is completed;

[0066] Step 6: Arrange and recover all lines, excavation equipment and integrated control host system, and operate the next sensor embedding point.

[0067] The above implementation modes are only used to illustrate the present invention, but not to limit the present invention. Ordinary technicians in the relevant technical field can make various changes and modifications without departing from the essence and scope of the present invention. Therefore, all equivalent technical solutions also belong to the scope of the present invention, and the patent protection scope of the present invention should be defined by the claims. The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

Claims

1. A sensor installation device integrating digging, burying and filling, characterized in that: include: Lifting system, replaceable working parts, frame, control system; The lifting system is used to drive the replaceable working part in a first direction; The frame is used to support the main body of the installation device, and one side is provided with a structure for connecting the replaceable working part; The replaceable working part specifically includes a main excavation drill bit, a first transparent surrounding barrel, a second transparent surrounding barrel, a detailed drilling and excavation structure in the hole, a detailed backfilling structure in the hole, and a main hole backfilling structure; The first transparent barrel is internally suspended with an internal hanging support structure of a detailed drilling structure in the hole prefabricated according to the number of sensors to be buried, the interval between burials and the depth of burials; a pair of holes are provided through the side wall of the barrel, and a camera is provided above the hole on one side for observing the excavation of the sensor burial hole; a grooved sharp corner structure is fixed on the lower side of the barrel, and the protruding direction of the sharp corner is on the same vertical line as the opening on the side where the camera is provided. When the first transparent barrel is placed, the grooved sharp corner structure carves a vertical groove on the excavated main hole for placing the sensor connecting line therein; The side wall of the second transparent enclosure barrel is provided with a vertical slit for the wire to enter and exit; the bottom of the enclosure barrel is a bottom-sealed inverted T-shaped hole structure, and a detailed backfilling structure is placed in the inverted T-shaped hole structure for placing and backfilling the sensor; The detailed drilling and digging structure in the hole is provided with a corresponding number and interval of fishbone-shaped internal hanging support structures according to the number and interval of buried sensors, and is suspended in the first transparent enclosure barrel; at the designed buried position of the sensor, a lateral extension end is provided corresponding to the through holes of the first transparent enclosure barrel, and a retractable drill bit is provided on one side of the buried sensor of each pair of lateral extension ends, and a first jack is provided on the other side. When working, the retractable drill bit and the first jack are extended from the through hole at the same time, and the retractable drill bit digs the sensor buried hole at the designed position, and at the same time, the small jack contacts the opposite side soil wall to provide reaction support force; The detailed backfill structure in the hole is composed of an L-shaped backfill material bin, a second jack, a third jack, and a feed pipe, and is placed at the bottom of the second transparent barrel; The second jack is used to push the L-shaped backfilling bin into the excavated sensor embedding hole; The third jack is used to push the sensor into the embedding hole or push the backfill soil into the embedding hole; The feed pipe is used to pour the backfill soil into the L-shaped backfill material bin after the second jack is retracted; The main hole backfill structure is composed of a top hydraulic device and a compaction hammer. Backfill soil is dropped from the hole, and the hydraulic device drives the compaction hammer to compact the backfill soil poured into the main hole layer by layer.

2. The sensor installation device of the digging-burying-filling integration according to claim 1, characterized in that: The main excavation drill bit is composed of a drill rod and a motor.

3. The sensor installation device of the digging-burying-filling integration as claimed in claim 1, characterized in that: The lifting system is specifically a chain-guide rail lifting system; The structure for connecting the replaceable working part is specifically a replaceable top plate, and a hole is opened in the middle of the replaceable top plate; The top and bottom ends of the frame are each provided with a pulley, the top is provided with a motor and a hydraulic device, and a pair of side surfaces are provided with side rails. The replaceable working part is driven by a chain to move along the side rail direction, and the side rail is used to provide guide support for the drilling of the main drill bit for excavation.

4. The sensor installation device of the digging-burying-filling integration as claimed in claim 3, characterized in that: A displacement sensor and a level meter are arranged at the bottom plate of the chain-guide rail lifting system. The displacement sensor detects the drilling and placement depths, and the level meter detects the posture state.

5. The sensor installation device of the digging-burying-filling integration as claimed in claim 3, characterized in that: The frame is specifically a cubic hollow splicable frame; a groove is provided on the top edge of the frame, and a protrusion matching the groove is provided on the bottom edge, and two adjacent frame structures are spliced ​​and reinforced by connecting parts in combination with the groove and protrusion structure.

6. A sensor installation device for integrated digging, burying and filling as claimed in any one of claims 1 to 5, characterized in that: The installation device also includes an integrated control host system, which is composed of a computer control system, connecting wires and cameras. The connecting wires connect the lifting system, the main excavation drill bit, the detailed drilling and excavation structure in the hole, the detailed backfill structure in the hole, and the main hole backfill structure to the computer control system, and are connected to the cameras installed on the first transparent barrel and the second transparent barrel to control the operation and stop of each component.

7. A method for using the sensor installation device for digging, burying and filling as claimed in claim 1, characterized in that: The steps include: Locate the sensor embedding point, assemble the frame body to a sufficient height according to the maximum design embedding depth of the sensor, fix and adjust the bottom, and install the main drill bit for excavation; The main drill bit for excavation drills in a first direction, and is taken out and disassembled after the operation is completed; Replace the first transparent enclosure barrel, hang the inner hanging support structure of the detailed drilling and excavation structure in the hole prefabricated according to the designed number of sensors, the intervals between them and the depth of the sensors in the first transparent enclosure barrel, and start the lifting system to place the two in the preset burying position; Perform drilling operation in the second direction; Carry out sensor burying operation; Carry out backfilling operations; The lifting system lifts the second transparent barrel to the upper buried hole, and repeats the operation until all sensors are installed. The lifting system then lifts the second transparent barrel out of the hole and takes it out. Replace the main hole backfill structure, pour the backfill soil into the excavated main hole in small amounts and multiple times, and use the lifting system to put the main hole backfill structure to the backfill position to compact the backfill soil in the hole; After compaction to the standard requirements, lift the main hole backfill structure, pour in a small amount of backfill soil again for compaction, and repeat this operation until the excavation of the main hole is completed and the backfill structure of the main hole is lifted above the ground surface by the lifting system, and the excavation-burying-filling work of the sensor is completed.

Citation Information

Patent Citations

  • Deep soil various sensor embedding device and embedding method thereof

    CN109056687A

  • Device and method for accurate positioning and quick burial of microsensor

    CN109142006A

  • Intensity distribution test device for deep-hole drilling rock and earth mass

    CN103760005A

  • Sensor embedding device and embedding method thereof

    CN111622198A