Oil well production profile interpretation system and method based on distributed optical fiber sound wave monitoring

Through the distributed optical fiber acoustic wave monitoring system, the FBE-flow chart and data preprocessing module are used to simplify the oil well production profile interpretation process, solve the problems of large calculation amount and low accuracy in the existing technology, and achieve rapid analysis of the oil well production status. , accurate monitoring.

CN118774767AActive Publication Date: 2024-10-15CHINA UNIV OF PETROLEUM (EAST CHINA)

Patent Information

Application Number
CN202410731156.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2024-10-15
Estimated Expiration
2044-06-06

Smart Images

  • Figure CN118774767A_ABST
    Figure CN118774767A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of oil and gas exploitation, and particularly relates to an oil well production profile interpretation system and method based on distributed optical fiber sound wave monitoring, due to the fact that the water content and flow corresponding to measured FBE data are uncertain, an FBE-flow interpretation chart of formation fluid changing along with the flow under different water contents is established, and the flow of the formation fluid can be interpreted according to the FBE-flow interpretation chart. Under the condition that the number of production layers, the well mouth moisture content and the well mouth flow are known, the flow corresponding to the assumed moisture content is calculated based on measured FBE data under a corresponding FBE-flow interpretation chart by assuming the moisture content of each production layer, and then the well mouth moisture content and the flow under the assumed moisture content condition are obtained. And the flow and water content parameters of each production well section are determined by controlling the error between the solved wellhead flow and the detected actual wellhead flow, and underground production profile monitoring and interpretation are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of oil and gas exploitation, and is an oil well production profile interpretation system and method based on distributed optical fiber acoustic wave monitoring. Background Art

[0002] At present, the confirmation of oil well production profile mainly relies on traditional measurement technology and sensors, such as mechanical samplers, rotary sidetracking samplers, temperature and pressure measurement, tracer testing, and different types of flow meters (such as turbine flow meters, electromagnetic flow meters and ultrasonic flow meters). However, traditional electronic instrument logging has technical limitations, such as low spatial resolution and inability to obtain data continuously; susceptible to interference from complex downhole environments; complex technical operations and prone to errors; difficult data analysis and requiring professional knowledge, etc., making it difficult to obtain accurate profile information in real time, thus affecting the monitoring and adjustment of oil well production status.

[0003] With the continuous development of technology, distributed acoustic wave monitoring (DAS) technology plays an increasingly important role in oil well production profile monitoring. Through this technology, acoustic wave signals can be obtained in real time and continuously during the oil well production process, realizing the distributed monitoring of the entire wellbore. This provides new possibilities for real-time and accurate acquisition of oil well production profile information.

[0004] However, the current interpretation methods of oil well production profiles based on distributed fiber optic acoustic wave sensing are still very limited. For example, Chinese patent document CN117266832A (202311488486.3) discloses a method and system for inverting the two-phase flow production profile of oil and gas wells using DAS. According to the original data measured by optical fiber processing, Fourier transform (FFT) is performed in the depth direction and time direction to obtain the frequency wave number slope. According to the slope, the sound velocity can be obtained. In different mixtures, the proportion of oil or water can be obtained according to the empirical formula, and then the oil-water two-phase flow production profile can be obtained. However, if the quality of the field data is not high enough, the above method cannot solve the problem of the sound velocity in the frequency wave number domain converted from the original data; For example, the oil well production profile inversion method based on low-frequency acoustic wave signals and temperature signals disclosed in Chinese patent document CN116677371A (202310817136.0) is complex in technical operation and difficult in data analysis, and there is a problem that the results cannot be obtained in a short time.

[0005] Chinese patent document CN112240196A (201910640705.2) discloses a wellbore production profile monitoring simulation experimental device based on distributed optical fiber sound and temperature monitoring, including: a distributed optical fiber sound and temperature monitoring integrated system, a wellbore and reservoir simulation system, a fluid supply and control system and a liquid collection system; the distributed optical fiber sound and temperature monitoring integrated system is connected to the wellbore and reservoir simulation system through an optical cable outside the tube and an optical cable inside the tube; a left fluid inlet and a right fluid inlet are symmetrically arranged on the axial outer wall of the wellbore and reservoir simulation system, respectively connected to the fluid supply system; the liquid collection system is connected to the wellbore and reservoir simulation system through a drainage pipeline. The above patent can realize continuous and real-time monitoring of the production profile of simulated multi-layer vertical wells, horizontal wells, multi-branch wells and inclined wells, and can also simulate the temperature and sound response of wellbore production under different liquid volumes, different water contents, different temperatures and different production layers, providing technical ideas for wellbore production profile testing. The above patent requires a large number of formation parameters (such as formation thermal diffusivity, specific heat capacity, formation density, etc.) and physical property parameters (including viscosity, density, water content, etc.), and the calculation process is complicated.

[0006] Therefore, the present invention provides a new reliable, simple and efficient method to meet the demand for rapid and accurate confirmation of the production status of oil wells. Summary of the invention

[0007] The main purpose of the present invention is to provide an oil well production profile interpretation system and method based on distributed optical fiber acoustic wave monitoring. The present application can obtain the production profile only by obtaining the wellhead water content, wellhead flow rate and the number of production layer sections. It has low dependence on parameters and small amount of calculation. It is a new flow interpretation method that solves the problem of large amount of calculation and low accuracy in the existing technology of distributed optical fiber in the production profile interpretation.

[0008] The technical problem to be solved by the present invention is achieved by adopting the following technical scheme: an oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring, comprising a casing, an oil pipe, an optical cable and a DAS production profile monitor arranged on the ground, wherein the oil pipe is located in the casing, and the optical cable is arranged in the oil pipe or on the outer wall of the oil pipe or on the outer wall of the casing; the optical cable is lowered into the oil pipe for single measurement, and the permanent type can be lowered outside the oil pipe or the casing, and the lowering position is very free, and the permanent type needs to ensure that the optical cable and the pipeline are tightly fitted;

[0009] The DAS production profile monitor is connected to the optical cable, and the DAS production profile monitor includes a DAS oil well production profile interpretation module;

[0010] The DAS oil well production profile interpretation module is used to process the oil well DAS data acquired in real time by the optical cable to obtain the real-time flow rate and water content of each production layer section of the oil well;

[0011] The DAS oil well production profile interpretation module includes an FBE-flow chart module, a data preprocessing module and an oil well production profile interpretation module;

[0012] The FBE-flow chart module is used to set the FBE-flow interpretation chart of the relationship between FBE data related to the flow of formation fluids and the flow rate corresponding to the flow rate under different water content ratios. When establishing the FBE-flow interpretation chart, the interval of water content ratio between two adjacent charts is the same; the formation fluid is oil and water two phases;

[0013] The data preprocessing module is used to convert the sound data related to the flow of formation fluid entering the wellbore collected during the production process into FBE data to obtain the FBE data of each production layer;

[0014] The oil well production profile interpretation module is used to utilize the sound data processed by the data preprocessing module and, according to the FBE-flow interpretation chart in the FBE-flow chart module, assume the water cut of each production layer under the condition that the number of production layers, the wellhead water cut and the wellhead flow are known, and calculate the flow corresponding to the assumed water cut based on the FBE data of each production layer calculated by the data preprocessing module under the corresponding FBE-flow interpretation chart, thereby obtaining the wellhead water cut and flow under the assumed water cut conditions, and determining the flow and water content parameters of each production well section by controlling the error between the obtained wellhead flow and the actual wellhead flow detected.

[0015] Preferably, the oil well production profile interpretation module, based on the FBE data of each production layer calculated by the data preprocessing module, assumes the water cut of each section, and interpolates and calculates the flow rate corresponding to each section in the FBE-flow chart. The detailed steps are as follows: arbitrarily assume the water cut of each layer section according to the wellhead water cut, and query the corresponding flow value in the FBE-flow chart corresponding to the assumed water cut of each layer section based on the assumed water cut of each layer section, using the FBE data of each section calculated by the data preprocessing module, that is, find the FBE-flow chart with the same FBE data to determine the corresponding flow value or use the flow values ​​of the FBE-flow interpretation charts corresponding to the two adjacent water cuts to linearly interpolate the flow value corresponding to the assumed water cut in the middle position, that is, use the flow of the shallow layer minus the deep layer in the two layers to obtain the flow rate of each layer section under the assumed water cut; the wellhead water cut is obtained by separating oil, water and impurities on the ground through a centrifuge, measuring the volume of oil and water respectively, and calculating the water cut. Assuming the water content of each layer based on the wellhead water content can converge the results faster;

[0016] The wellhead flow rate Q' under the assumed water content is obtained, and the inflow flow rate q of each layer is obtained by decreasing the layer flow rate i ;

[0017] The built-in algorithm is used to calculate the water content of each layer and the inflow flow rate q of each layer. i Verification includes the following steps:

[0018] 2-1) Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water cut ΔQ = QQ′. In each layer, assume the water cut f′ w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the FBE data in the corresponding FBE-flow chart is Δq i ;

[0019] Δq i The calculation method is as follows: select the flow rate with the minimum water content and the maximum water content in the FBE-flow chart under the corresponding FBE data, perform linear interpolation, and calculate the change in flow rate under unit water content change;

[0020] 2-2) Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively:

[0021]

[0022] Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi The water content assumed for each layer interval;

[0023] 2-3) Combine equations (2) and (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water content to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead, and recalculate the flow error ΔQ; the actual flow rate at the wellhead is obtained by measurement;

[0024] If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content, and the precision ε is preset and can be selected arbitrarily;

[0025] Δq iThe updating method is as follows: by reducing the selection range between the minimum and maximum water content of the FBE-flow chart, a more refined linear interpolation is performed on the flow under the corresponding FBE data to calculate the change in flow under the unit water content change; that is, the water content selection range is gradually reduced during correction, and the assumed water content is ensured to be within the selected range during subsequent selection, and the assumed value is kept at the midpoint of the selection range as much as possible; preferably, when the water content selection range is the corresponding water content interval Δf% when the FBE-flow interpretation chart is established, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i ;

[0026] 2-4) Based on the FBE data calculated for each section and the corrected moisture content f′ wi , find the corresponding flow in the FBE-flow chart;

[0027] If there is no FBE-flow chart for the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, and the flow rate of each layer is calculated by decreasing the flow rate layer by layer. i ;

[0028] 2-5) Output the inflow flow q of each layer segment i and the corrected moisture content f′ wi .

[0029] The preferred method of establishing the FBE-flow interpretation chart of the present invention is: by conducting an oil well simulation fluid flow experiment at different flow rates and different water content ratios in a distributed optical fiber flow monitoring experimental device, the experiment is interval at each N% water content, N is a preset value, the flow rate at this water content is matched with the FBE data extracted from the DAS signal, and a curve corresponding to the FBE data and the flow rate when the water content is determined is fitted, and the FBE-flow interpretation chart is established based on a large amount of experimental data, that is, one water content corresponds to one FBE-flow interpretation chart. The method of establishing the chart by fitting is a prior art and will not be described in detail here.

[0030] Preferably, the distributed optical fiber flow monitoring experimental device comprises a simulated oil pipe, an inner optical fiber arranged in the simulated oil pipe, an outer optical fiber arranged outside the simulated oil pipe, a liquid supply module and a DAS monitor, wherein the inner optical fiber and the outer optical fiber are connected to each other;

[0031] The DAS monitor is connected to the optical fiber inside the pipe or the optical fiber outside the pipe;

[0032] The side wall of the simulated oil pipe is provided with a plurality of production layer simulation holes;

[0033] The liquid supply module is connected to the production layer simulation hole and is used to inject oil well simulation fluids with different flow rates and different water contents into the simulated oil pipe.

[0034] Preferably, the liquid supply module of the present invention comprises a water storage tank, an oil storage tank, a first pump body, a second pump body and a valve group;

[0035] The water storage tank is connected to the inlet of the valve group through the first pump body, the oil storage tank is connected to the inlet of the valve group through the second pump body, and the outlets of the valve group are respectively connected to the production layer simulation holes. The water content is adjusted by the first pump body and the second pump body to achieve uniform mixing of oil and water in the valve body.

[0036] In addition, a gas supply module can also be provided to connect the gas source to the valve group inlet through the pump body, and a flow meter can be provided to detect and control the flow of the gas supply to perform a proportioned mixing of the water-gas two-phase or a proportioned mixing of the oil-gas-water three-phase.

[0037] Preferably, the distributed optical fiber flow monitoring experimental device of the present invention further comprises a waste liquid barrel, and the waste liquid barrel is connected to the outlet of the simulated oil pipe.

[0038] Preferably, in the present invention, the data preprocessing module converts the sound data related to the flow of formation fluid entering the wellbore collected during the production process into FBE data in the following detailed steps:

[0039] 1-1) The collected original DAS signal is filtered to remove the influence of noise, which is accomplished by applying a bandpass filter to select a specific frequency range required for analysis; the bandpass filter described here is an algorithm that allows signals within a specific frequency range to pass through, while blocking (attenuating) signals of other frequencies, which is a prior art and will not be described in detail here;

[0040] 1-2) Convert the time series data into frequency domain data through fast Fourier transform to determine the signal strength at different frequencies;

[0041] 1-3) Select the appropriate frequency band according to the problem to be analyzed;

[0042] 1-4) In the selected frequency band, the sum of the energies of all frequency components calculated as formula (1) is the frequency band energy FBE:

[0043]

[0044] Where E(t) represents the energy of a frequency band with a duration of t, a and b are the low-frequency and high-frequency limits of the selected frequency band, respectively, and s(f) is the Fourier transform result at frequency f.

[0045] The present invention also discloses a method for interpreting oil well production profile based on distributed optical fiber acoustic wave monitoring, comprising the following steps:

[0046] S1. Setting an FBE-flow interpretation chart of the relationship between FBE data related to formation fluid flow and flow rate corresponding to flow rate changes under different water content ratios in the FBE-flow chart module;

[0047] S2. Using a data preprocessing module, the sound data related to the flow of formation fluids entering the wellbore collected during the production process is converted into FBE data to obtain FBE data for each production layer;

[0048] S3, using the sound data processed by the data preprocessing module through the oil well production profile interpretation module and the FBE-flow interpretation chart in the FBE-flow chart module, using the built-in algorithm to determine the fluid flow and water content data of each production layer section;

[0049] S3.1. Based on the FBE data of each production layer calculated by the data preprocessing module, the water cut of each section is assumed, and the corresponding flow rate is interpolated and calculated in the FBE-flow chart. Specifically, the water cut of each layer section is arbitrarily assumed according to the wellhead water cut. Based on the assumed water cut of each layer section, the FBE data of each section calculated by the data preprocessing module is used to query the corresponding flow value in the FBE-flow chart corresponding to the assumed water cut of each layer section, or the flow values ​​of the two adjacent water cut corresponding FBE-flow interpretation charts are used to linearly interpolate the flow value corresponding to the assumed water cut in the middle position, so as to obtain the flow rate of each layer section under the assumed water cut;

[0050] The wellhead flow rate Q' under the assumed water content is obtained, and the inflow flow rate q of each layer is obtained by decreasing the layer flow rate i ;

[0051] S3.2. Use the built-in algorithm to calculate the water content of each layer and the inflow flow rate q of each layer. i Verification includes the following steps:

[0052] S3.2.1. Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water content, ΔQ = QQ′. In each layer, assume that the water content is f′. w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the corresponding FBE data is Δq i ;

[0053] Δq iThe calculation method is as follows: select the minimum water content and the maximum water content in the FBE-flow chart under the corresponding FBE data, that is, the calculated FBE data, perform linear interpolation, and calculate the change in flow under unit water content change; that is, gradually reduce the water content selection range during correction, and ensure that the assumed water content is within the selected range during subsequent selections, and try to make the assumed value at the midpoint of the selected range;

[0054] S3.2.2. Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively:

[0055]

[0056] Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi The water content assumed for each layer interval;

[0057] S3.2.3, combine equation (2) and equation (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water content to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead to recalculate the flow error ΔQ;

[0058] If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content, and the precision ε is preset and can be selected arbitrarily;

[0059] Δq i The updating method is as follows: by narrowing the selection range between the minimum and maximum water content of the FBE-flow chart, a more precise linear interpolation is performed on the flow under the corresponding FBE data, so as to calculate the change in flow under the change of unit water content; after narrowing the value range, a more precise linear interpolation operation can be performed;

[0060] S3.2.4. Based on the FBE data calculated for each segment and the corrected moisture content f′ determined wi , find the corresponding flow in the FBE-flow chart;

[0061] If there is no FBE-flow chart of the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, that is, the flow value corresponding to the FBE data is found in the FBE-flow charts of the two adjacent water contents, and then the interpolation calculation is performed. For example, if the water content is 83%, the water content charts of 80% and 85% are selected, and the corresponding values ​​are respectively queried, and then the flow corresponding to the water content of 83% is interpolated and calculated, and the inflow flow q of each layer is calculated by decreasing the flow layer by layer i ;

[0062] S3.2.5. Output the inflow flow rate q of each layer segment i and the corrected moisture content f′ wi .

[0063] Preferably, the method for establishing the FBE-flow interpretation chart of the present invention is as follows: by conducting an oil well simulation fluid flow experiment at different flow rates and different water cuts in a distributed optical fiber flow monitoring experimental device, the experiment is intervalled at every N% water cut, N is a preset value, the flow rate at this water cut is matched with the FBE data extracted from the DAS signal, a curve corresponding to the FBE data and the flow rate when the water cut is determined is fitted, and an FBE-flow interpretation chart is established based on a large amount of experimental data, that is, one water cut corresponds to one FBE-flow interpretation chart.

[0064] Preferably, in step S3.2.3, when the water content selection range is the corresponding water content interval Δf% when establishing the FBE-flow interpretation chart, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i .

[0065] Compared with the prior art, the present invention has the following beneficial effects:

[0066] 1. Provide a flow rate and water content chart and interpretation method for each underground production well section based on distributed fiber optic acoustic wave monitoring. Since the water content and flow rate corresponding to the measured FBE data are uncertain, by establishing an FBE-flow interpretation chart of the formation fluid with flow rate changes under different water cuts, under the condition of known number of production layers, wellhead water cut and wellhead flow rate, by assuming the water cut of each production layer, the flow rate corresponding to the assumed water cut is calculated based on the measured FBE data under the corresponding FBE-flow interpretation chart, and then the wellhead water cut and flow rate under the assumed water cut conditions are obtained. By controlling the error between the obtained wellhead flow rate and the actual wellhead flow rate detected, the flow rate and water content parameters of each production well section are determined, and underground production profile monitoring and interpretation are realized.

[0067] 2. The production profile monitoring method provided by the present invention can obtain the flow rate and water content parameters of each production well section in real time.

[0068] 3. The production profile monitoring method provided by the present invention reduces the skill requirements for on-site operators, simplifies the operation process, and is easy to implement on-site.

[0069] 4. The production profile monitoring method provided by the present invention can effectively reduce the cost of oil well monitoring and production profile analysis. BRIEF DESCRIPTION OF THE DRAWINGS

[0070] Figure 1 It is a schematic diagram of a specific implementation method of the oil well production profile interpretation method based on distributed optical fiber acoustic wave sensing of the present invention;

[0071] Figure 2 It is a structural schematic diagram of an oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring in an embodiment of the present invention;

[0072] Figure 3 It is a schematic diagram of the structure of a distributed optical fiber flow monitoring experimental device in an embodiment of the present invention;

[0073] In the figure, 1DAS production profile monitor, 2optical cable, 3wellhead, 4production layer section I, 5production layer section II, 6production layer section III, 7casing, 8tubing, 9artificial bottom hole, 10optical fiber counterweight;

[0074] 100 simulated oil pipes, 101 production layer simulated holes, 200 optical fibers inside the pipes, 300 optical fibers outside the pipes, 400 liquid supply modules, 500 DAS monitors, 600 waste liquid barrels;

[0075] 401 water storage tank, 402 oil storage tank, 403 first pump body, 404 second pump body, 405 valve group, 406 first flow meter, 407 second flow meter. DETAILED DESCRIPTION

[0076] The present invention is described in detail below in conjunction with the embodiments and the accompanying drawings, but is not limited thereto. In the present invention, "each section", "each section", "layer section", "production layer section" and "production well section" have the same meaning.

[0077] like Figure 2 As shown, an oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring includes a casing 7, an oil pipe 8, an optical cable 2 and a DAS production profile monitor 1 arranged on the ground, wherein the oil pipe 8 is located in the casing 7, and the optical cable 2 is arranged in the oil pipe 8 or on the outer wall of the oil pipe 8 or on the outer wall of the casing 7. An optical fiber counterweight 10 is arranged below the optical cable 2. It is ensured that the optical fiber remains vertical and does not shake after being lowered, otherwise the spatial position of the downhole optical cable will be inaccurately calibrated, resulting in errors in the final result. The optical cable 2 is an armored optical cable.

[0078] The DAS production profile monitor 1 is connected to the optical cable 2 , and the DAS production profile monitor 1 includes a DAS oil well production profile interpretation module.

[0079] The DAS oil well production profile interpretation module is used to process the oil well DAS data acquired in real time by the optical cable to obtain the real-time flow rate and water content of each production layer section of the oil well.

[0080] Specifically, obtaining oil well DAS data under a certain working system includes:

[0081] 1) After arriving at the well site, confirm that the well to be tested meets the logging conditions, and use an optical time domain reflectometer on the ground to test the optical fiber in the armored optical cable to ensure that it is continuous without breakpoints and that the quality meets the normal working requirements.

[0082] 2) During the test construction, the instrument lowering speed shall not exceed 3000m / h. The lowering speed shall be slowed down when approaching abnormal points such as the downhole reducer, bottom ball (reverse circulation valve), bell mouth, cross, tail pipe, etc. During the lowering process, always observe the tension indicator, depth indicator and wellhead conditions. If any obstruction is found, stop the machine in time.

[0083] 3) During measurement, the distributed acoustic sensor on the ground remains turned on to continuously detect the status of the optical cable in real time, obtain the sound vibration signal distributed along the oil pipe 8 or the wellbore trajectory, and save the data in the ground storage device at the same time, and monitor it in real time on the ground monitoring screen to observe whether there are any abnormal conditions. If there are any abnormal conditions, they should be dealt with immediately.

[0084] 4) During the measurement process, check the quality of logging data. If it does not meet the on-site quality control requirements, perform additional measurements.

[0085] The DAS oil well production profile interpretation module comprises an FBE-flow chart module, a data preprocessing module and an oil well production profile interpretation module.

[0086] The FBE-flow chart module is used to set an FBE-flow interpretation chart of the relationship between FBE data related to formation fluid flow and flow rate corresponding to flow rate changes under different water content ratios.

[0087] The data preprocessing module is used to convert the sound data related to the flow of formation fluid entering the wellbore collected during the production process into FBE data to obtain the FBE data of each production layer.

[0088] The oil well production profile interpretation module is used to use the sound data processed by the data preprocessing module and determine the fluid flow and water content data of each production layer segment using a built-in algorithm based on the FBE-flow interpretation chart in the FBE-flow chart module.

[0089] The specific method is as follows:

[0090] According to the FBE data of each production layer calculated by the data preprocessing module, the water content of each section is assumed, and the flow corresponding to each section is interpolated and calculated in the FBE-flow chart. The detailed steps are as follows: the water content of each layer is arbitrarily assumed according to the wellhead water content, and the water content of each layer is assumed, and the FBE data of each section calculated by the data preprocessing module is used to query the corresponding flow value in the FBE-flow chart corresponding to the assumed water content of each layer, or the flow value of the FBE-flow interpretation chart corresponding to the two adjacent water content is used to linearly interpolate the flow value corresponding to the assumed water content in the middle position, so as to obtain the flow of each layer under the assumed water content. In the present invention, the water content of each production section can be arbitrarily assumed, but when actually assuming, it is better to increase, decrease or equal based on the wellhead water content, and it is also possible to use empirical formula assumptions. For example, the FBE-flow chart in this embodiment includes 0-100% water content, with intervals of 5% water content, a total of 21 charts, each chart is the corresponding relationship between FBE data and flow under the water content condition, one is 21 charts, and two charts are fitted, one inside the oil pipe 8 and one outside the oil pipe 8, and the chart is selected according to the position of the optical fiber. When there is no corresponding chart for the assumed water content, two charts adjacent to the assumed water content are used, and a flow is queried in the two charts using the same FBE data, and then the two flows are interpolated to calculate the flow under the current assumed water content.

[0091] The wellhead flow rate Q' is obtained under the assumed water content, and the flow rate of each layer is reduced layer by layer to obtain the inflow flow rate q i The FBE data of each layer segment can be obtained by calculation, but the data corresponds to the total flow of the layer segment, that is, the sum of the inflow flow of the layer segment and the flow of deeper layers. The production profile requires the inflow flow of each layer segment, so after obtaining the flow value, it is necessary to subtract it from the deep flow value to obtain the inflow flow of the layer segment.

[0092] The built-in algorithm is used to calculate the water content of each layer and the inflow flow rate q of each layer. i Verification includes the following steps:

[0093] 2-1) Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water cut ΔQ = QQ′. In each layer, assume the water cut f′ w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the FBE data in the corresponding FBE-flow chart is Δq i .

[0094] Δq iThe calculation method is as follows: select the flow rate with the minimum water content and the maximum water content under the corresponding FBE data in the FBE-flow chart, perform linear interpolation, and calculate the change in flow rate under unit water content change.

[0095] 2-2) Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively:

[0096]

[0097] Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi is the assumed moisture content for each layer.

[0098] 2-3) Combine equations (2) and (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water cut to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead to recalculate the flow error ΔQ.

[0099] If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content. The precision ε is preset and can be selected arbitrarily.

[0100] Δq i The updating method is as follows: by narrowing the selection range between the minimum and maximum water cuts of the FBE-flow chart, a more precise linear interpolation of the flow is performed under the corresponding FBE data to calculate the change in flow under unit water cut change; that is, the water cut selection range is gradually reduced during correction, and the assumed water cut is ensured to be within the selected range during subsequent selections, and the assumed value is kept at the midpoint of the selection range as much as possible.

[0101] 2-4) Based on the FBE data calculated for each section and the corrected moisture content f′ wi , find the corresponding flow in the FBE-Flow Chart.

[0102] If there is no FBE-flow chart for the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, and the flow rate of each layer is calculated by decreasing the flow rate layer by layer. i .

[0103] 2-5) Output the inflow flow q of each layer segment i and the corrected moisture content f′ wi .

[0104] The method for establishing the FBE-flow interpretation chart is as follows: by conducting oil well simulated fluid flow experiments at different flow rates and different water cuts in a distributed optical fiber flow monitoring experimental device, the water cut needs to be fixed and experiments are conducted at different flow rates. The experiment is intervals of every N% water cut, N is a preset value, and the flow rate at this water cut is matched with the FBE data extracted from the DAS signal, and a curve corresponding to the FBE data and the flow rate when the water cut is determined is fitted. Based on a large amount of experimental data, an FBE-flow interpretation chart is established, that is, one water cut corresponds to one FBE-flow interpretation chart.

[0105] In step 2-3), when the water content selection range is the corresponding water content interval Δf% when establishing the FBE-flow interpretation chart, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i .

[0106] like Figure 3 As shown, the distributed optical fiber flow monitoring experimental device includes a simulated oil pipe 100, an in-pipe optical fiber 200 arranged in the simulated oil pipe 100, an out-pipe optical fiber 300 arranged outside the simulated oil pipe, a liquid supply module 400 and a DAS monitor 500.

[0107] The DAS monitor 500 is connected to the optical fiber 200 inside the pipe and the optical fiber 300 outside the pipe. The optical fiber 200 inside the pipe and the optical fiber 300 outside the pipe are connected to each other. Specifically, the optical fiber is installed close to the inner and outer walls of the pipe to be tested, that is, the simulated oil pipe 100. The optical fiber passes through the pipe from the inside of the pipe and then goes back from the outside to achieve simultaneous measurement of the sound signals of the inner and outer walls of the pipe, so as to fit two FBE-flow interpretation charts on the outside and inside of the oil pipe, because it is necessary to compare the two sets of data monitored by the optical fiber 200 inside the pipe and the optical fiber 300 outside the pipe, and control variables by simultaneous implementation. One side of the optical fiber is connected to the DAS monitor 500, and the other side is processed by the tail end processing device. The tail end needs to be processed, otherwise a stable and clear signal cannot be obtained. There will be a continuous and strong signal at the tail end to disturb all signals. The tail end processing device and processing method are existing technologies and will not be described here.

[0108] The simulated oil pipe 100 is provided with a plurality of production layer simulation holes 101 on the side wall, and each production layer simulation hole 101 is provided with a screen. The simulated oil pipe 100 uses three 7 / 8in oil pipe tail ends spliced ​​with three 1m long equal-sized screens, the injection ports, i.e. the production layer simulation holes 101, are spaced 4m apart, the three injection ports are located in the middle of the three screens, the screens are connected by equal-sized oil pipes, and the outer layer uses 5 1 / 2in casings, and the annulus at both ends of the screens is sealed with a packer to ensure that when the fluid is injected, there is only radial injection from the injection port to the oil pipe, and there is no axial flow between multiple injection ports.

[0109] The liquid supply module 400 is connected to the production layer simulation hole 101, and is used to inject oil well simulation fluids with different flow rates and different water contents into the simulated oil pipe. The oil well simulation fluid is the formation fluid. The FBE-flow interpretation chart obtained in the experiment corresponds to the single-layer situation. The multi-layer injection and replacement of the injection port in the experiment are to obtain the influence of adjacent layers on a single layer in the multi-layer situation, so as to obtain a more accurate interpretation chart in the single-layer situation.

[0110] The liquid supply module 400 includes a water storage tank 401 , an oil storage tank 402 , a first pump body 403 , a second pump body 404 and a valve group 405 .

[0111] The water storage tank 401 is connected to the inlet of the valve group 405 through the first pump body 403, and a first flow meter 406 is provided between the first pump body 403 and the valve group 405. The oil storage tank 402 is connected to the inlet of the valve group 405 through the second pump body 404, and a second flow meter 407 is provided between the second pump body 404 and the valve group 405. The outlets of the valve group 405 are respectively connected to the production layer simulation holes 101. The flow rate of the liquid is adjusted by controlling the first pump body 403 and the second pump body 404, and the mixing of oil and water is achieved in the valve group 405. In the actual experimental process, after the water content is proportioned, different flow rates are continuously monitored when the water content remains unchanged.

[0112] In this embodiment, Figure 3 As shown, three production layer simulation holes 101 are provided, and the oil well simulation fluid is mixed in the valve group 405 and then enters the pipeline to be tested through three screen pipes at different positions.

[0113] The first pump body 403 and the second pump body 404 are both vertical centrifugal pumps with a maximum flow rate of 360m 3 ·d-1, controlled by a variable frequency speed regulator, meets the flow regulation requirements in the experiment; the first flow meter 406 and the second flow meter 407 are both electromagnetic flow meters with a measurement accuracy of 0.24m 3 d-1, measuring range is 0-480m 3 ·d-1, meet the maximum flow requirement of the experiment.

[0114] The distributed optical fiber flow monitoring experimental device also includes a waste liquid barrel 600, which is connected to the outlet of the simulated oil pipe 100. The waste liquid barrel 600 is provided with an oil outlet and a water outlet respectively connected to the oil storage tank 402 and the water storage tank 401. After the waste liquid is precipitated, oil and water are separated in the waste liquid barrel 600, and the oil and water can be recovered to the water storage tank 401 and the oil storage tank 402 respectively for recycling, thereby reducing the experimental cost. The water storage tank 401, the oil storage tank 402 and the waste liquid barrel 600 are transparent plastic boxes with a capacity of 1000L, and the fluid conditions in the boxes can be observed in real time.

[0115] The detailed steps of converting the sound data related to the flow of formation fluid into the wellbore collected during the production process into FBE data by the data preprocessing module are as follows:

[0116] 1-1) The collected original DAS signal is filtered to remove the influence of noise. This is done by applying a bandpass filter to select the specific frequency range required for analysis. Different analysis requirements include sand production, wellbore leak detection, fracture parameter interpretation, production profile interpretation, etc. Different frequency ranges are selected according to different requirements. For different requirements, the main frequency bands containing their information are also different, but there will be overlaps. Therefore, for frequency band selection, it is a matter that relies heavily on experience and theory. For the same problem, different people may select different frequency band ranges.

[0117] 1-2) Through fast Fourier transform, the time series data is converted into frequency domain data to determine the signal strength at different frequencies.

[0118] 1-3) Select the appropriate frequency band according to the problem to be analyzed. For example, if analyzing low-frequency acoustic activity, consider selecting a frequency band of 0-10 Hz. Because only the production profile problem needs to be analyzed, the selected frequency band is fixed and the same as the frequency band selected when the FBE-flow chart is established. It can be understood that the FBE-flow chart is established only to solve this problem.

[0119] 1-4) Within the selected frequency band, the sum of the energies of all frequency components calculated as formula (1) is the frequency band energy (FBE):

[0120]

[0121] In formula (1), E(t) represents the frequency band energy with a duration of t, a and b are the low-frequency and high-frequency limits of the selected frequency band, respectively, and s(f) is the Fourier transform result at frequency f. FBE data is the characteristic frequency band energy, also known as frequency band energy. This data contains a large amount of information. Most of the analysis of DAS collected data requires the calculation of FBE data and then the analysis of FBE data. For example, low-frequency FBE data contains information such as fluid flow, while higher frequency FBE data can reflect information including sand production at the bottom of the well and leakage.

[0122] A method for interpreting oil well production profiles based on distributed fiber optic acoustic wave monitoring. The sound signal reflected by the optical fiber is interpreted and processed using the DAS production profile interpretation module to ultimately obtain the real-time flow and water content of each production layer of the oil well. Figure 1 As shown, the following steps are included:

[0123] S1. In the FBE-flow chart module, an FBE-flow interpretation chart is set to show the relationship between FBE data related to formation fluid flow and flow rate as the flow rate changes under different water content ratios.

[0124] S2. Use the data preprocessing module to convert the sound data related to the flow of formation fluid entering the wellbore collected during the production process into FBE data to obtain the FBE data of each production layer.

[0125] S3. The oil well production profile interpretation module uses the sound data processed by the data preprocessing module and the FBE-flow interpretation chart in the FBE-flow chart module to determine the fluid flow and water content data of each production layer using a built-in algorithm.

[0126] S3.1. Based on the FBE data of each production layer calculated by the data preprocessing module, the water cut of each section is assumed, and the corresponding flow rate is interpolated and calculated in the FBE-flow chart. Specifically, the water cut of each layer section is arbitrarily assumed according to the wellhead water cut. Based on the assumed water cut of each layer section, the FBE data of each section calculated by the data preprocessing module is used to query the corresponding flow value in the FBE-flow chart corresponding to the assumed water cut of each layer section, or the flow values ​​of the two adjacent water cut corresponding FBE-flow interpretation charts are used to linearly interpolate the flow value corresponding to the assumed water cut in the middle position.

[0127] The wellhead flow rate Q' is obtained under the assumed water content, and the flow rate of each layer is reduced layer by layer to obtain the inflow flow rate q i ;

[0128] S3.2. Use the built-in algorithm to calculate the water content of each layer and the inflow flow rate q of each layer. iVerification includes the following steps:

[0129] S3.2.1. Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water content, ΔQ = QQ′. In each layer, assume that the water content is f′. w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the corresponding FBE data is Δq i .

[0130] Δq i The calculation method is as follows: select the flow rates with the minimum and maximum water content in the FBE-flow chart under the corresponding FBE data, perform linear interpolation, and calculate the change in flow rate under unit water content change; that is, gradually reduce the water content selection range during correction, and ensure that the assumed water content is within the selected range during subsequent selections, and try to make the assumed value at the midpoint of the selected range.

[0131] S3.2.2. Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively:

[0132]

[0133] Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi is the assumed moisture content for each layer.

[0134] S3.2.3, combine equation (2) and equation (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water cut to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead to recalculate the flow error ΔQ.

[0135] If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content. The precision ε is preset and can be selected arbitrarily.

[0136] Δq iThe updating method is as follows: by narrowing the selection range between the minimum and maximum water cuts of the FBE-flow chart, a more refined linear interpolation of the flow is performed under the corresponding FBE data to calculate the change in flow per unit water cut change.

[0137] S3.2.4. Based on the FBE data calculated for each segment and the corrected moisture content f′ determined wi , find the corresponding flow in the FBE-Flow Chart.

[0138] If there is no FBE-flow chart for the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, and the flow rate of each layer is calculated by decreasing the flow rate layer by layer. i .

[0139] S3.2.5. Output the inflow flow rate q of each layer segment i and the corrected moisture content f′ wi .

[0140] The method for establishing the FBE-flow interpretation chart is as follows: by conducting oil well simulated fluid flow experiments at different flow rates and different water cuts in a distributed optical fiber flow monitoring experimental device, the experiment is intervalled at every N% water cut, N is a preset value, the flow rate at this water cut is matched with the FBE data extracted from the DAS signal, and a curve corresponding to the FBE data and the flow rate when the water cut is determined is fitted, and an FBE-flow interpretation chart is established based on a large amount of experimental data, that is, one water cut corresponds to one FBE-flow interpretation chart.

[0141] In step S3.2.3, when the water content selection range is the corresponding water content interval Δf% when establishing the FBE-flow interpretation chart, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i .

[0142] Application Example 1

[0143] like Figure 2 As shown, when the monitoring method of the present invention is applied to long-term real-time monitoring of oil well production profiles, the specific steps are as follows:

[0144] Step 1: Determine the length of the production string according to the process. Ensure that the length of the optical cable 2 exceeds the deepest production layer or can extend to the bottom of the artificial well 9. Connect the optical fiber counterweight 10 to the end of the optical cable 2; fix the portion of the optical cable 2 that is shorter than the oil pipe 8 to the oil pipe 8. The fixing method can be clamped, welded or prefabricated optical cable troughs according to the on-site conditions; lower the optical cable 2 into the well along with the production string, that is, inside the casing 7.

[0145] Step 2: The upper end of the optical cable 2 passes through the wellhead 3 and is connected to the DAS production profile monitor 1 placed on the ground.

[0146] Step 3: Calibrate the spatial position of the downhole optical cable, and obtain production layer segment I4, production layer segment II5, and production layer segment III6 in this application example.

[0147] Step 4: Start production and start the DAS production profile monitor 1.

[0148] Step 5: Observe the sound data displayed by the display system in the DAS production profile monitor 1, and start recording the sound data after the data stabilizes.

[0149] Step 6: Use the DAS oil well production profile interpretation module built into the computer control and display system of the DAS production profile monitor 1 to interpret the sound data recorded in step 5 in real time to obtain the fluid flow and water content data of the oil well production layer.

[0150] Step 7: Change the working system, repeat steps 5 and 6, and obtain the fluid flow and water content data of the production layer of the oil well under different working systems.

[0151] Application Example 2

[0152] like Figure 2 As shown, when the system of the present invention is applied to real-time monitoring of oil well production profiles, the specific steps are as follows:

[0153] Step 1: Determine the length of the production string according to the process, and ensure that the length of the optical cable 2 exceeds the deepest production layer; connect the optical fiber counterweight 10 to the end of the optical cable 2; and lower the optical cable 2 into the well along with the oil pipe 8. For long-term monitoring, the optical cable 2 is fixed outside the oil pipe 8 and lowered. For short-term monitoring, it is generally lowered directly from the oil pipe 8, because the oil casing annulus is often equipped with packers, etc., which makes it inconvenient to lower.

[0154] Step 2: The upper end of the optical cable 2 passes through the wellhead 3 and is connected to the DAS production profile monitor 1 placed on the ground.

[0155] Step 3: Calibrate the spatial position of the downhole optical cable, and obtain, in this application example, production layer section I4, production layer section II5, and production layer section III6.

[0156] Step 4: Start production and start the DAS production profile monitor 1.

[0157] Step 5: Observe the sound data displayed by the display system in the DAS production profile monitor 1, and start recording the sound data after the data stabilizes.

[0158] Step 6: Use the DAS oil well production profile interpretation module built into the computer control and display system of the DAS production profile monitor 1 to interpret the sound data recorded in step 5 in real time to obtain the fluid flow and water content data of the oil well production layer.

[0159] Step 7: Change the working system, repeat steps 5 and 6, and obtain the fluid flow and water content data of the production layer of the oil well under different working systems.

[0160] Step 8: After the test is completed, the DAS production profile monitor 1 is turned off, and the optical cable 2 is removed from the oil pipe 8 to complete the real-time monitoring of the oil well production profile.

Claims

1. An oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring, characterized in that: It includes a casing, an oil pipe, an optical cable and a DAS production profile monitor arranged on the ground, wherein the oil pipe is located in the casing, and the optical cable is arranged in the oil pipe or on the outer wall of the oil pipe or on the outer wall of the casing; The DAS production profile monitor is connected to the optical cable, and the DAS production profile monitor includes a DAS oil well production profile interpretation module; The DAS oil well production profile interpretation module is used to process the oil well DAS data acquired in real time by the optical cable to obtain the real-time flow rate and water content of each production layer section of the oil well; The DAS oil well production profile interpretation module includes an FBE-flow chart module, a data preprocessing module and an oil well production profile interpretation module; The FBE-flow chart module is used to set an FBE-flow interpretation chart of the relationship between FBE data related to formation fluid flow and flow rate corresponding to flow rate changes under different water content ratios; The data preprocessing module is used to convert the sound data related to the flow of formation fluid entering the wellbore collected during the production process into FBE data to obtain the FBE data of each production layer; The oil well production profile interpretation module is used to utilize the sound data processed by the data preprocessing module and, according to the FBE-flow interpretation chart in the FBE-flow chart module, assume the water cut of each production layer under the condition that the number of production layers, the wellhead water cut and the wellhead flow are known, and calculate the flow corresponding to the assumed water cut based on the FBE data of each production layer calculated by the data preprocessing module under the corresponding FBE-flow interpretation chart, thereby obtaining the wellhead water cut and flow under the assumed water cut conditions, and determining the flow and water content parameters of each production well section by controlling the error between the obtained wellhead flow and the actual wellhead flow detected.

2. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 1 is characterized in that: The oil well production profile interpretation module interpolates and calculates the flow rate corresponding to each section in the FBE-flow chart based on the FBE data of each production layer calculated by the data preprocessing module, assuming the water cut of each section. The detailed steps are as follows: arbitrarily assume the water cut of each layer section, and based on the assumed water cut of each layer section, use the FBE data of each section calculated by the data preprocessing module to query the corresponding flow value in the FBE-flow chart corresponding to the assumed water cut of each layer section, or use the flow values ​​of the two adjacent water cut corresponding FBE-flow interpretation charts to linearly interpolate the flow value corresponding to the assumed water cut in the middle position, and then obtain the flow rate of each layer section under the assumed water cut; The wellhead flow rate Q' under the assumed water content is obtained, and the inflow flow rate q of each layer is obtained by decreasing the flow rate layer by layer. i ; The built-in algorithm is used to calculate the water content of each layer and the inflow flow rate q of each layer. i Verification includes the following steps: 2-1) Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water content ΔQ = Q-Q'. In each layer, assume the water content f' w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the FBE data in the corresponding FBE-flow chart is Δq i ; Δq i The calculation method is as follows: select the flow rate with the minimum water content and the maximum water content in the FBE-flow chart under the corresponding FBE data, perform linear interpolation, and calculate the change in flow rate under unit water content change; 2-2) Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively: Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi The water content assumed for each layer interval; 2-3) Combine equations (2) and (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water content to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead to recalculate the flow error ΔQ; If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content, and the precision ε is preset and can be selected arbitrarily; Δq i The updating method is: by narrowing the selection range between the minimum and maximum water content of the FBE-flow chart, a more refined linear interpolation of the flow is performed under the corresponding FBE data to calculate the change in flow under unit water content change; preferably, when the water content selection range is the corresponding water content interval Δf% when establishing the FBE-flow interpretation chart, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i ; 2-4) Based on the FBE data calculated for each section and the corrected moisture content f′ wi , find the corresponding flow in the FBE-flow chart; If there is no FBE-flow chart for the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, and the flow rate of each layer is calculated by decreasing the flow rate layer by layer. i ; 2-5) Output the inflow flow q of each layer segment i and the corrected moisture content f′ wi .

3. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 1 is characterized in that: The method for establishing the FBE-flow interpretation chart is as follows: by conducting oil well simulated fluid flow experiments at different flow rates and different water cuts in a distributed optical fiber flow monitoring experimental device, the experiment is intervalled at every N% water cut, N is a preset value, the flow rate at this water cut is matched with the FBE data extracted from the DAS signal, and a curve corresponding to the FBE data and the flow rate when the water cut is determined is fitted, and an FBE-flow interpretation chart is established based on a large amount of experimental data, that is, one water cut corresponds to one FBE-flow interpretation chart.

4. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 3 is characterized in that: The distributed optical fiber flow monitoring experimental device comprises a simulated oil pipe, an inner optical fiber arranged in the simulated oil pipe, an outer optical fiber arranged outside the simulated oil pipe, a liquid supply module and a DAS monitor, wherein the inner optical fiber and the outer optical fiber are connected to each other; The DAS monitor is connected to the optical fiber inside the pipe or the optical fiber outside the pipe; The side wall of the simulated oil pipe is provided with a plurality of production layer simulation holes; The liquid supply module is connected to the production layer simulation hole and is used to inject oil well simulation fluids with different flow rates and different water contents into the simulated oil pipe.

5. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 4 is characterized in that: The liquid supply module includes a water storage tank, an oil storage tank, a first pump body, a second pump body and a valve group; The water storage tank is connected to the inlet of the valve group through the first pump body, the oil storage tank is connected to the inlet of the valve group through the second pump body, and the outlets of the valve group are respectively connected to the production layer simulation holes.

6. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 5 is characterized in that: The distributed optical fiber flow monitoring experimental device also includes a waste liquid bucket, which is connected to the simulated oil pipe outlet.

7. The oil well production profile interpretation system based on distributed optical fiber acoustic wave monitoring according to claim 1 is characterized in that: The detailed steps of converting the sound data related to the flow of formation fluid into the wellbore collected during the production process into FBE data by the data preprocessing module are as follows: 1-1) filtering the collected raw DAS signal to remove the influence of noise, which is done by applying a bandpass filter to select the specific frequency range required for analysis; 1-2) Convert the time series data into frequency domain data through fast Fourier transform to determine the signal strength at different frequencies; l-3) Select the appropriate frequency band according to the problem to be analyzed; 1-4) In the selected frequency band, the sum of the energies of all frequency components calculated as formula (1) is the frequency band energy FBE: Where E(t) represents the energy of a frequency band with a duration of t, a and b are the low-frequency and high-frequency limits of the selected frequency band, respectively, and s(f) is the Fourier transform result at frequency f.

8. A method for interpreting oil well production profile based on distributed optical fiber acoustic wave monitoring, characterized in that: The following steps are involved: S1. Setting an FBE-flow interpretation chart of the relationship between FBE data related to formation fluid flow and flow rate corresponding to flow rate changes under different water content ratios in the FBE-flow chart module; S2. Using a data preprocessing module, the sound data related to the flow of formation fluids entering the wellbore collected during the production process is converted into FBE data to obtain FBE data for each production layer; S3, using the sound data processed by the data preprocessing module through the oil well production profile interpretation module and the FBE-flow interpretation chart in the FBE-flow chart module, using the built-in algorithm to determine the fluid flow and water content data of each production layer section; S3.

1. Based on the FBE data of each production layer calculated by the data preprocessing module, the water cut of each section is assumed, and the corresponding flow rate is calculated by interpolation in the FBE-flow chart. Specifically, the water cut of each layer section is assumed arbitrarily, and based on the assumed water cut of each layer section, the FBE data of each section calculated by the data preprocessing module is used to query the corresponding flow value in the FBE-flow chart corresponding to the assumed water cut of each layer section, or the flow values ​​of the two adjacent water cut corresponding FBE-flow interpretation charts are used to linearly interpolate the flow value corresponding to the assumed water cut in the middle position, so as to obtain the flow rate of each layer section under the assumed water cut; The wellhead flow rate Q' under the assumed water content is obtained, and the inflow flow rate q of each layer is obtained by decreasing the flow rate layer by layer. i ; S3.

2. Use the built-in algorithm to calculate the water content of each layer and the inflow flow rate q of each layer. i Verification includes the following steps: S3.2.

1. Calculate the error between the actual wellhead flow and the wellhead flow under the current assumed water content, ΔQ = Q-Q'. In each layer, assume that the water content is f' w The actual moisture content f w The error between i , the change in flow rate when the water content increases or decreases by 1% under the corresponding FBE data is Δq i ; Δq i The calculation method is as follows: select the flow rate with the minimum water content and the maximum water content in the FBE-flow chart under the corresponding FBE data, perform linear interpolation, and calculate the change in flow rate under unit water content change; S3.2.

2. Establish the assumed flow error equation and water content error equation, which are equation (2) and equation (3) respectively: Where n is the number of production intervals, f w0 is the water content at the wellhead, f wi The water content assumed for each layer interval; S3.2.3, combine equation (2) and equation (3) and solve to obtain the error x of each segment i , and further calculate the corrected moisture content f′ of each layer wi =f wi +x i , and then query the FBE-flow chart according to the corrected water content to obtain the sum of the flow rates of each layer, and compare it with the actual flow rate at the wellhead to recalculate the flow error ΔQ; If ΔQ / Q<ε, the accuracy is met and the iteration is stopped and the corrected moisture content f′ of each layer is output. wi , or when the water content selection range is the water content interval Δf% corresponding to the establishment of the FBE-flow interpretation chart, stop the iteration, otherwise update Δq i , and return to step 2-1) to continue to correct the moisture content, and the precision ε is preset and can be selected arbitrarily; Δq i The updating method is as follows: by narrowing the selection range between the minimum and maximum water content of the FBE-flow chart, a more refined linear interpolation of the flow is performed under the corresponding FBE data, so as to calculate the change in flow under unit water content change; S3.2.

4. Based on the FBE data calculated for each segment and the corrected moisture content f′ determined wi , find the corresponding flow in the FBE-flow chart; If there is no FBE-flow chart for the corresponding water content, the flow corresponding to the adjacent water content is used to interpolate and calculate the flow at this water content, and the flow rate of each layer is calculated by decreasing the flow rate layer by layer. i ; S3.2.

5. Output the inflow flow rate q of each layer segment i and the corrected moisture content f′ wi .

9. The method for interpreting oil well production profile based on distributed optical fiber acoustic wave monitoring according to claim 8, characterized in that: The method for establishing the FBE-flow interpretation chart is as follows: by conducting oil well simulated fluid flow experiments at different flow rates and different water cuts in a distributed optical fiber flow monitoring experimental device, the experiment is intervalled at every N% water cut, N is a preset value, the flow rate at this water cut is matched with the FBE data extracted from the DAS signal, and a curve corresponding to the FBE data and the flow rate when the water cut is determined is fitted, and an FBE-flow interpretation chart is established based on a large amount of experimental data, that is, one water cut corresponds to one FBE-flow interpretation chart.

10. The method for interpreting oil well production profile based on distributed optical fiber acoustic wave monitoring according to claim 8, characterized in that: In step S3.2.3, when the water content selection range is the corresponding water content interval Δf% when establishing the FBE-flow interpretation chart, When the water cut interval is less than Δf%, the FBE-flow interpretation chart is used to re-update Δq i .

Citation Information

Patent Citations

  • Modeling and management of reservoir systems with material balance groups

    CN101548264A

  • Production profile monitoring method based on distributed optical fiber sound monitoring and distributed optical fiber temperature monitoring

    CN110344815A

  • Shaft production profile monitoring simulation experiment device and method based on distributed optical fiber sound and temperature monitoring

    CN112240196A

  • Production logs from distributed acoustic sensors

    US20180045040A1

Cited By

  • Low-yield well distributed optical fiber sound wave wellbore flow interpretation system and method based on thermal excitation

    CN120537543A

  • A low producing well distributed fiber optic acoustic wellbore flow interpretation system and method based on thermal stimulation

    CN120537543B

  • Shaft sand migration monitoring experiment system based on distributed optical fiber sound wave sensing and migration speed prediction method

    CN121298192A

  • Distributed optical fiber sound wave sensing liquid production profile logging data quality control method

    CN122672117A