Method for efficiently recovering remaining coal pillars from accumulated water in column type residual mining area of freezing room
The accumulated water in the goaf is frozen by artificial refrigeration to form load-bearing ice blocks. Combined with the coal cutter mining technology, the remaining coal pillars in the room-and-pillar goaf are efficiently recovered, which solves the high cost and construction problems of water recovery in the goaf in the existing technology. Difficult problem to achieve safe and efficient coal pillar resource recovery.
Patent Information
- Application Number
- CN202410949466.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-07-16
AI Technical Summary
It is difficult to efficiently recycle the remaining coal pillars filled with water in early room-and-pillar goafs with existing technology, and the common solid waste filling and re-mining methods are costly and difficult to construct.
Artificial refrigeration technology is used to freeze the accumulated water in the goaf, turning the liquid water into ice with load-bearing capacity, forming huge ice blocks to fill the goaf, and setting up mining tunnels and working faces in the frozen ice blocks, and the coal cutters are synchronized Cut coal pillars and ice bodies, and gradually recover the remaining coal pillars.
It achieves efficient mining of room-and-pillar goafs, avoids the difficulty of dealing with large amounts of water at one time, simultaneously solves the problems of fire prevention and gas control, and reduces risks and costs in the coal mining process.
Smart Images

Figure CN118774822A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for efficiently recovering residual coal pillars by freezing accumulated water in a room-and-pillar residual mining area, and belongs to the technical field of coal mining. Background Art
[0002] In recent years, international energy prices have risen sharply, and the supply and demand of coal has continued to be tight. The role of coal as a "ballast stone" in energy security has become more prominent. Shallow high-quality coal resources are decreasing day by day, and the mining of abandoned coal caused by backward mining technology in the early stage has become another important measure to ensure the supply of coal resources after the mining of deep resources. In addition, as the reserves of coal gradually decrease, the contradiction between the unlimited growth of coal demand and the limited nature of non-renewable resources has become increasingly severe. Improving resource recovery rate and building conservation-oriented mining areas have become another important task for coal mining enterprises to ensure supply.
[0003] Limited by history and mining technology, the average recovery rate of many early coal mines did not exceed 30%, and the recovery rate of some small coal mines was only 10% to 20%. Therefore, there are many legacy coal seams destroyed by small coal kilns in existing production mining areas and mines. Among them, the early room-type coal mining method of combined mining and excavation arranged a series of 5-7m coal rooms in the coal seam, and 20-30m coal rooms were left between the coal rooms. While mining the coal resources in the coal rooms, a narrow working face was formed, and generally advanced forward in groups. The coal pillars between the coal rooms serve as the supporting structure of the roof during the room-pillar mining process. After the coal rooms were mined, the coal pillars were abandoned in large quantities, resulting in a large waste of resources. Afterwards, most of the room-pillar goaf was gradually filled with water, and the mechanical properties of the legacy coal pillars gradually deteriorated. The current common solid waste filling and re-mining methods (CN200910258318.9 A solid filling comprehensive mining method for recovering room-type coal pillars; CN201910756396.5 A filling and mining method for recovering coal pillars left in old room-pillar goafs) require the water in the goaf to be pumped out, and after the distribution of the remaining coal pillars is ascertained, the paste material is pumped for filling and the coal pillars are recovered and re-mined. Among them, filling large areas of goafs is costly and difficult to construct. Therefore, it is urgent to find a method that can not only reasonably solve the water accumulation in room-pillar goafs, but also safely, efficiently and economically recover the coal pillars left in room-pillar residual mining areas. Summary of the invention
[0004] In order to solve the above problems, the present invention proposes a method for freezing water in room-and-pillar goaf and efficiently recovering the remaining coal pillars, which is mainly aimed at the efficient recovery of the remaining coal pillars in room-and-pillar goaf that is mostly filled with water; it is mainly suitable for the efficient recovery of the remaining coal pillars of the early and backward room-and-pillar mining method.
[0005] The present invention uses artificial refrigeration technology to freeze the water in the goaf based on the distribution of coal pillar groups and goaf groups in the room-and-pillar goaf, the amount of water accumulated in the goaf, and the range of water accumulated, so that the liquid water becomes ice with a bearing capacity close to that of the coal sample. The frozen ice becomes a filling body to fill the room-and-pillar goaf, and the entire goaf is filled with a huge ice block frozen from the accumulated water. At the same time, this huge ice block forms a cooperative bearing body with the top and bottom plates of the residual mining area, the coal pillars, and the surrounding rocks at the boundary of the goaf, and jointly bears the load transmitted by the overlying rock formation. A mining tunnel and a coal mining working face are set in the ice blocks and the remaining coal pillars formed after freezing, and then the coal cutter synchronously cuts the coal pillars and the ice formed by the freezing of the accumulated water. As the mining working face advances, the accumulated water melted during the cutting process and the accumulated water melted by the ice block fragments during the transportation process after cutting are pumped out, and the coal resources of the remaining coal pillars are recovered. The purpose of efficiently recovering the remaining coal pillars can be achieved without having to deal with a large amount of accumulated water at one time, and the problems of fire prevention and gas control in the mining of the remaining coal can also be solved simultaneously.
[0006] The present invention provides a method for freezing water accumulation in a room-and-pillar residual mining area to efficiently recover the remaining coal pillars, comprising the following steps: (1) Carry out core drilling and peek, and draw the distribution morphology map of the overlying rock strata in the goaf, the coal pillars left in the room-and-pillar goaf, and the goaf in combination with the original geological and technical data of the mine, and the distribution of the coal pillars and goaf groups to guide safe production. At the same time, find out the height, amount and quality of water accumulation in the room-and-pillar goaf to serve the subsequent design of water freezing in the goaf; (2) Comprehensively consider the strength and Mohs hardness of coal samples measured by core drilling of coal pillars left in room-and-pillar goafs, and the strength and Mohs hardness of frozen ice measured by sampling water in room-and-pillar goafs. The room-and-pillar residual mining area is regarded as a complete unmined coal seam. The mechanical parameters of the coal body and ice body are combined to design the mining face for recovering and mining coal pillars left in room-and-pillar residual mining areas, select equipment, design the working face tunnels, and arrange the openings. (3) The existing tunnels in the same layer parallel to the room-and-pillar goaf are used as freezing auxiliary tunnels, and freezing workstations are arranged. A series of horizontal boreholes are drilled from the tunnel wall of the freezing auxiliary tunnel toward the water accumulation area of the goaf, and freezing pipelines are arranged through the boreholes into the water accumulation area of the goaf; when there are no suitable tunnels to choose from in the coal seam where the room-and-pillar goaf is located, tunnels can be selected in the overlying rock strata of the pillar goaf, and a series of vertical boreholes can be drilled from top to bottom. The freezing pipelines are lowered and arranged through the tunnel boreholes in the overlying rock strata into the water accumulation area of the goaf; (4) A freezing workstation is arranged in the freezing auxiliary tunnel set up in step (3). The freezing pipeline is arranged in the water in the room-pillar goaf, and the heat of the water is replaced by circulating brine, so that the water in the room-pillar goaf enters an active freezing period, and the liquid phase water becomes ice with a certain bearing capacity. The temperature range of the frozen ice body in this stage is -20°C to -12°C. The characteristics of water changing with the shape of the container and the expansion of water volume when it freezes are utilized to make it fully connect with the roof while freezing. The ice after the water in the room-pillar goaf is frozen acts as a filling body. At the same time, the remaining coal pillars, collapsed rocks, etc. in the goaf are frozen into a frozen body with the accumulated water. The entire goaf is filled with huge ice blocks formed by the frozen water. The ice body after the water in the room-pillar goaf is frozen, and the top and bottom plates of the room-pillar residual mining area, the remaining coal pillars in the room-pillar goaf to be recovered, and the coal pillars at the boundary of the room-pillar goaf form a cooperative bearing body, which jointly bears the load transmitted by the overlying rock strata. (5) When the accumulated water in step (4) is insufficient to completely reach the top after freezing, water is added through the borehole in step (3) during the freezing process of the accumulated water in step (4) to ensure that the ice body can fully reach the top after the accumulated water in the room-and-pillar goaf is frozen; when the accumulated water in the room-and-pillar goaf completely fills the goaf, the accumulated water in step (4) freezes and expands, and the amount of water in the room-and-pillar goaf is excessive, water is pumped out through the borehole in step (3) to ensure that the ice body can just reach the top after the accumulated water in the room-and-pillar goaf is frozen; (6) After the accumulated water in the room-and-pillar residual mining area is completely frozen, each freezing workstation in step (4) reduces the refrigeration capacity, and the freezing work enters a passive freezing period to ensure that the ice will not thaw and maintain the temperature of the frozen ice body constant at -10°C to -5°C; (7) Then, excavate and arrange transportation and ventilation tunnels in the ice body maintained by passive freezing, use explosion-proof electric heating rods to gradually melt the ice body along the designed central axis of the tunnel, and at the same time extract the water formed by the melting of the ice body. After the tunnel of the designed size is melted in the ice body, a freezing pipeline is laid on the inner wall surface of the tunnel to maintain the freezing of the tunnel surface, avoid the heat radiation generated by the air introduced by the mine ventilation and the transportation of equipment, etc., which may cause the tunnel surface to melt, and ensure that the tunnel maintains the designed shape and size; then, through the tunnel transportation and arrangement of relevant mining equipment, arrange the room-and-pillar goaf coal pillar recovery working face at the designated location, open the cutting eye, and arrange the coal pillar recovery working face; (8) Under passive freezing maintenance, the frozen water and the remaining coal pillars are regarded as a whole. The coal cutter gradually cuts the ice body and coal pillars from the beginning of the cutting eye, and the whole layer is mined to recover the remaining coal; part of the ice body melts during the cutting, and part of the ice body is cut to form ice chips and the coal blocks formed by the cutting are transported together through a scraper conveyor. Pumps and drainage ditches are arranged in the working face and transport tunnel to extract the water formed by the melting of ice chips during the cutting and transportation of the ice body.
[0007] In the above scheme, when each freezing pipeline is arranged in the water accumulated in the room-and-pillar residual mining area, a series of temperature sensors are lowered together with the pipeline and evenly arranged in the water accumulated in the room-and-pillar residual mining area to establish a real-time dynamic detection network to perform real-time detection of the temperature of the water accumulated in the goaf (frozen ice body).
[0008] In the above scheme, step (1) investigates the original geological and technical data of the mine to find out the width and height of the void groups and coal pillar groups in the pillar-type residual mining area, and uses a three-dimensional laser scanner to accurately detect the distribution direction, size and volume of the void groups in the room-pillar type residual mining area, and at the same time, find out the depth, distribution range and volume of the water accumulation in the room-pillar type residual mining area.
[0009] In the above scheme, in step (2), the room-and-pillar residual mining area is regarded as a complete unmined coal seam for mining design, in which the relevant mechanical parameters are comprehensively considered based on the parameters of frozen ice (uniaxial compressive strength 3-6 MPa, Mohs hardness of about 2.8-4) and the mechanical parameters of the coal samples determined by on-site drilling.
[0010] In the above scheme, in step (3), the existing tunnels on the same level as the coal pillar recovery working face tunnels in the parallel room-and-pillar residual mining area are set as freezing auxiliary tunnels, freezing workstations are arranged in the freezing auxiliary tunnels, and freezing pipelines are arranged through the tunnel wall holes of the freezing auxiliary tunnels to the accumulated water in the goaf, wherein the number of tunnel wall holes is determined by the required cooling capacity, the accumulated water volume and the radius of the freezing pipelines. The freezing pipes form a group of closed loops in the accumulated water in the goaf to circulate brine, displace the heat in the accumulated water, and freeze the accumulated water into ice.
[0011] In the above scheme, the model, power and number of freezing equipment in step (4) are determined based on the required cooling capacity calculated from the empty area volume and the water volume of the room-and-pillar residual mining area found in step (2); the brine circulation system uses CaCl2 solution as the refrigerant, and the cooling water circulation system is naturally cooled by digging a water pool; after determining the various freezing parameters, the equipment is tested at a designated location in the underground freezing auxiliary tunnel, and formal construction is carried out after the entire system is operating correctly.
[0012] In the above scheme, the volume of the water after freezing in step (5) expands, and the volume of the ice after freezing is 1.1 times that of the original water. When the water accumulates in the goaf that was not connected to the top, and the distance between the water surface and the top plate accounts for less than 10% of the total height of the goaf, the ice body can fully connect to the top after freezing; when the accumulated water is less and cannot connect to the top after freezing, the amount of ice is increased by artificial water injection to make it connect to the top, thereby filling the entire room-and-pillar type residual mining area void area and supporting the rock layer on the top plate of the residual mining area.
[0013] In the above scheme, after the accumulated water in the room-and-pillar residual mining area in step (6) freezes, the uniaxial compressive strength of the ice body is 3MPa~6MPa under passive freezing maintenance, and the tensile strength is about 1 / 2 of the compressive strength. Under the lateral constraints of the surrounding rock of the underground goaf, the compressive strength of the ice body is 5~10MPa, which is close to the strength of the gangue concrete paste filling material.
[0014] In the above scheme, when the width of the working face is greater than 50m, if it is difficult to completely freeze all the water in the goaf by laying pipes through the tunnel wall drilling holes of the freezing auxiliary tunnel in step (3) to the water in the goaf, an ice body of 10 to 20m can be frozen inward from the boundary surrounding rock of the residual mining area. Then, tunnels are excavated and working faces are arranged in the frozen ice body inside the boundary surrounding rock of the residual mining area; and the excavated transport tunnel is widened, and an auxiliary chamber is excavated in it for the subsequent arrangement of the freezing workstation. The transport tunnel also has the function of a freezing tunnel.
[0015] In the above scheme, the passive freezing period in step (6) refers to the freezing effect of the accumulated water in the room-and-pillar residual mining area during the previous active freezing period (the temperature range of the frozen ice body during the active freezing period is -20°C~-12°C), and the liquid water gradually freezes and the freezing is basically completed. At this time, the frozen ice body only needs to maintain the frozen state to ensure that it will not thaw. The temperature of the circulating brine increases, and the temperature range of the frozen ice body increases to -10°C~-5°C, so as to achieve energy saving and economy as much as possible; at the same time, the Mohs hardness of the frozen ice body is reduced, which is conducive to cutting by the coal cutter.
[0016] In the above scheme, the coal cutter described in step (8) gradually cuts the ice body and coal pillars from the beginning of the cutting eye, and the whole layer is mined and the remaining coal pillars are recovered, which means that under the maintenance of passive freezing, the frozen water and the remaining coal pillars are regarded as a whole layer of unmined coal seam, and the coal cutter cuts under the support and protection of hydraulic supports, and the roof collapses as it is mined.
[0017] Beneficial effects of the present invention: (1) The invention determines the feasibility of re-mining the coal pillars left in the room-and-pillar goaf based on the production data and exploration data of the mine, and uses artificial refrigeration to freeze the accumulated water in the room-and-pillar residual mining area, so that the liquid water freezes into solid ice to replace the paste filling material, and the collapsed roof and gangue in the entire goaf are wrapped in the frozen ice body to form a cooperative carrier. The frozen ice fills the entire residual mining area in a full-filling manner, and tunnels are excavated and coal mining working faces are arranged in the frozen ice. After that, the coal cutter cuts the coal pillars and the frozen ice together. As the mining working face advances, the remaining coal pillars are gradually recovered, and the accumulated water melted after cutting is extracted at the same time, so as to achieve the effect of efficiently recovering the remaining coal pillars.
[0018] (2) Compared with the traditional method of recovering coal pillars after mining by filling with solid waste paste materials, there is no need to deal with a large amount of accumulated water in the residual mining area at one time before recovering the coal pillars. Instead, the melted ice chips after cutting are gradually extracted during the mining process, creating conditions for the orderly and efficient utilization of the accumulated water in the goaf.
[0019] (3) The room-and-pillar goaf is filled with frozen ice, and the remaining coal pillars are mined under the support of the frozen ice. The frozen ice filling the goaf can solve the problem of gas prevention and control in the mining of the remaining coal, and the low-temperature environment provided can avoid the frequent fire accidents during the mining of the remaining coal. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 This is a cross-section of the rock formation in the room-and-pillar goaf; Figure 2 This is a schematic diagram of the distribution of coal pillars and goafs left in room-and-pillar goafs; Figure 3 Schematic diagram of the freezing pipeline layout and frozen ice distribution in room-and-pillar goaf areas.
[0021] In the figure: 1—overlying rock strata above the goaf, 2—remaining coal pillars in the room-and-pillar goaf, 3—water accumulation in the room-and-pillar goaf, 4—coal pillars at the boundary of the room-and-pillar goaf; 5—mining tunnel, 6—frozen auxiliary tunnel, 7—freezing workstation, 8—freezing pipeline, 9—ice body after the water in the room-and-pillar goaf has frozen. DETAILED DESCRIPTION
[0022] The present invention is further illustrated by the following examples, but is not limited to the following examples.
[0023] In order to have a clearer understanding of the technical objectives, features and effects of the present invention, a method for freezing accumulated water in room-and-pillar goaf and recovering remaining coal pillars is now further described in detail in conjunction with the accompanying drawings.
[0024] A certain mine is now facing the problem of low resource recovery rate due to exhaustion of resources. It is urgent to seek new methods and ideas to increase the recovery rate and extend the service life of the mine. Recovering the remaining coal pillars of the No. 2 coal seam that was mined in the early room-and-pillar style has become a good solution to the current predicament of the mine. The No. 2 coal seam of the mine is 4.2 meters thick. Due to the constraints of the early backward mining technology, it was mined using the room-and-pillar mining method. During coal mining, coal pillars of different shapes were left between the coal rooms to support the roof. The recovery rate of the entire layer of coal resources was less than 40%. After mining, most of the goaf area was gradually filled with mine water. It is a typical room-and-pillar residual mining area with a large amount of high-quality recoverable coal. Drawing on the traditional paste filling mining method, it is necessary to extract and treat a large amount of accumulated water in the goaf at one time, and then set up a filling pipeline for filling, which increases the cost. It is urgent to find a scientific, efficient and economical coal pillar recovery method. In view of the above situation, the implementation process of the present invention is further described in detail below in conjunction with the accompanying drawings. The specific implementation steps are as follows: (1) Based on the original geological and technical data of the mine, the distribution of coal pillar groups and goaf groups was analyzed, and the overlying rock strata 1 of the goaf, the coal pillars left in the room-and-pillar goaf 2, and the distribution morphology of the goaf were drawn to guide safe production. At the same time, it was found that the height of the water accumulation 3 in the room-and-pillar goaf was 4m, and the amount of water accumulation accounted for 80% of the volume of the goaf in the pillar goaf.
[0025] (2) Before mining design, the uniaxial compressive strength of the coal pillar 2 left in the room-and-pillar goaf measured by core drilling was 10.6 MPa, and the Mohs hardness was between 1.8 and 2. At the same time, the uniaxial compressive strength of the frozen ice body (under a freezing environment of -10℃~-5℃) was measured to be between 3 MPa and 6 MPa, and the Mohs hardness was between 2.8 and 4 from the water sampled from the room-and-pillar goaf. Taking into account the compressive strength, Mohs hardness and other mechanical parameters of the coal pillar and frozen ice body, the room-and-pillar residual mining area was regarded as a complete unmined coal seam, and the mining design and equipment selection of the mining working face for the recovery of the coal pillar left in the room-and-pillar residual mining area were carried out, and the working face tunnel and opening eye arrangement were designed.
[0026] (3) The working face of the room-and-pillar goaf is 180 m long. It is difficult to freeze all the water 3 in the room-and-pillar goaf by drilling holes through the existing tunnels parallel to the boundary of the room-and-pillar goaf and setting up freezing pipelines 8. Therefore, holes are drilled from the surrounding rock at the boundary of the residual mining area toward the goaf. Part of the water in the goaf is frozen inward from the surrounding rock at the boundary of the residual mining area to form an ice body 20 m wide. After the water in the frozen range is frozen, the temperature of the circulating brine increases in a small range, and the temperature range of the frozen ice body increases from -12°C to -20°C in the active freezing period to -5°C to -10°C.
[0027] (4) Then, the mining tunnel 5 is excavated and arranged in the ice body maintained by the passive freezing in step (3). The ice body is gradually melted along the designed central axis of the tunnel using explosion-proof electric heating rods. At the same time, water formed by the melting of the ice body is extracted to melt the mining tunnel 5 of the designed size in the ice body. Freezing pipelines are laid on the inner wall surface of the mining tunnel 5 to maintain the freezing of the surface of the mining tunnel 5, to prevent the melting of the tunnel surface due to heat radiation such as air introduced by mine ventilation and equipment transportation, and to ensure that the mining tunnel 5 maintains the designed shape and size.
[0028] (5) Widen the transport tunnel excavated in step (4), and excavate an auxiliary chamber on one side thereof for the subsequent arrangement of a freezing workstation 7. One side of the mining tunnel 5 serves as a freezing auxiliary tunnel 6.
[0029] The following reference solutions are provided for the selection and arrangement of freezing equipment: The freezer uses SKD136.1.H screw unit, the design cooling capacity of a single unit is 116960Kcal / h, and the power of a single motor is 114KW; Each refrigeration unit is equipped with a brine circulation pump, IS150-125-315 type, single unit flow rate 200m 3 / h, motor power 37KW; The cooling water circulation pump of the freezing station is IS150-125~315B type, with a single flow rate of 173m 3 / h, motor power 18.5KW; Each freezing station needs to be equipped with a brine circulation pump and a cooling water circulation pump as backup; The main parameters and indicators involved in freezing construction are as follows: Refrigerant: Freon R-22, Refrigeration oil: Hanbell HBR-B03 refrigeration oil, Freezing brine temperature: active period: -25℃~-20℃, passive period: -20℃~-15℃, The average temperature of the water after freezing is -12℃~-8℃. Freezing brine delivery pipe: flexible metal pipe that is resistant to low temperatures.
[0030] The specific freezing parameters and details are as follows: The brine circulation system uses CaCl2 solution as the refrigerant; the cooling water circulation system is cooled naturally by digging a pool; after determining the freezing parameters, the equipment is tested and construction begins after the entire system is running properly.
[0031] (6) In the freezing auxiliary tunnel 6 set up in step (5), several groups of freezing workstations 7 are arranged along the direction of the mining face according to the freezing construction plan. Through the freezing pipeline 8 arranged in the water 3 in the room-pillar goaf, the heat of the water is replaced by circulating brine, so that the water 3 in the room-pillar goaf enters the active freezing period, and the liquid water becomes ice with a certain bearing capacity, and the temperature range of the frozen ice body is maintained at -12°C to -20°C; by utilizing the characteristics of water changing with the shape of the container and the expansion of water volume when it freezes, it is fully connected to the top while freezing, and the ice body 9 after the water in the room-pillar goaf is frozen acts as a filling body. At the same time, the coal pillars 2 left in the room-pillar goaf, collapsed and collapsed rocks, etc. are all frozen into ice blocks. The entire goaf is filled with huge ice blocks frozen by the water. The ice body 9 after the water in the room-pillar goaf is frozen, together with the top and bottom plates of the room-pillar residual mining area, the coal pillars 2 left in the room-pillar goaf to be recovered, and the coal pillars 4 at the boundary of the room-pillar goaf form a whole with a certain bearing capacity.
[0032] (7) The amount of water accumulated in the room-and-pillar goaf accounts for 80% of the volume of the pillar goaf. During the freezing process of the accumulated water in step (5), the volume expands by 1.1 times. The amount of water accumulated in the room-and-pillar goaf is insufficient. Water is supplemented by drilling holes in step (3) to ensure that the ice body 9 just touches the top after the water accumulated in the room-and-pillar goaf freezes.
[0033] (8) After the accumulated water in the room-and-pillar goaf is completely frozen and solidified, the freezing station 7 arranged along the direction of the coal mining face in step (5) reduces the refrigeration capacity, and the freezing work enters a passive freezing period to ensure that the ice will not thaw and maintain the temperature of the frozen ice body constant at -10°C to -5°C; (9) Thereafter, under passive freezing, the excavation and arrangement of the transport and ventilation tunnels in step (4) are checked and improved, the relevant mining equipment is transported and arranged through the tunnels, and the coal pillar recovery working face of the room-and-pillar goaf is opened at the designated location, and the coal pillar recovery working face is arranged.
[0034] (10) Under the passive freezing maintenance, the ice body 9 after the water in the room-and-pillar goaf is frozen and the coal pillar 2 left in the room-and-pillar goaf is regarded as a whole. The coal cutter gradually cuts the ice body and the coal pillar from the beginning of the cutting eye, and the whole layer is mined to recover the remaining coal. As the mining face advances, the roof rock layer collapses as it is mined.
[0035] (11) Part of the ice melts during cutting, and part of the ice is cut into ice chips which are transported together with the coal blocks formed by cutting through a scraper conveyor. Part of the cut ice chips gradually melt during the transportation process. Pumps and drainage ditches are arranged in the working face and transport lanes to extract the water formed by the melted ice chips during the cutting and transportation of the ice.
Claims
1. A method for freezing water in room-and-pillar residual mining areas to efficiently recover the remaining coal pillars, characterized in that The following steps are involved: (1) Carry out core drilling and peek, and draw the distribution morphology map of the overlying rock strata in the goaf, the coal pillars left in the room-and-pillar goaf, and the goaf in combination with the original geological and technical data of the mine, and the distribution of the coal pillars and goaf groups to guide safe production. At the same time, find out the height, amount and quality of water accumulation in the room-and-pillar goaf to serve the subsequent design of water freezing in the goaf; (2) Comprehensively consider the strength and Mohs hardness of coal samples measured by core drilling of coal pillars left in room-and-pillar goafs, and the strength and Mohs hardness of frozen ice measured by sampling water in room-and-pillar goafs. The room-and-pillar residual mining area is regarded as a complete unmined coal seam. The mechanical parameters of the coal body and ice body are combined to design the mining face for recovering and mining coal pillars left in room-and-pillar residual mining areas, select equipment, design the working face tunnels, and arrange the openings. (3) The existing tunnels in the same layer parallel to the room-and-pillar goaf are used as freezing auxiliary tunnels, and freezing workstations are arranged. A series of horizontal boreholes are drilled from the tunnel wall of the freezing auxiliary tunnel toward the water accumulation area of the goaf, and freezing pipelines are arranged through the boreholes into the water accumulation area of the goaf; when there are no suitable tunnels to choose from in the coal seam where the room-and-pillar goaf is located, tunnels can be selected in the overlying rock strata of the pillar goaf, and a series of vertical boreholes can be drilled from top to bottom. The freezing pipelines are lowered and arranged through the tunnel boreholes in the overlying rock strata into the water accumulation area of the goaf; (4) A freezing workstation is arranged in the freezing auxiliary tunnel set up in step (3). The freezing pipeline is arranged in the water in the room-pillar goaf, and the heat of the water is replaced by circulating brine, so that the water in the room-pillar goaf enters an active freezing period, and the liquid phase water becomes ice with bearing capacity. The temperature range of the frozen ice body in this stage is -20°C to -12°C. The characteristics of water changing with the shape of the container and the expansion of water volume when it freezes are utilized to make it fully connected to the top while freezing. The ice after the water in the room-pillar goaf is frozen acts as a filling body. At the same time, the remaining coal pillars, collapsed rocks, etc. in the goaf are frozen into a frozen body with the accumulated water. The entire goaf is filled with huge ice blocks formed by the frozen water. The ice body after the water in the room-pillar goaf is frozen, and the top and bottom plates of the room-pillar residual mining area, the coal pillars in the room-pillar goaf to be recovered, and the coal pillars at the boundary of the room-pillar goaf form a cooperative bearing body, which jointly bears the load transmitted by the overlying rock strata. (5) When the accumulated water in step (4) is insufficient to completely reach the top after freezing, water is added through the borehole in step (3) during the freezing process of the accumulated water in step (4) to ensure that the ice body can fully reach the top after the accumulated water in the room-and-pillar goaf is frozen; when the accumulated water in the room-and-pillar goaf completely fills the goaf, the accumulated water in step (4) freezes and expands, and the amount of water in the room-and-pillar goaf is excessive, water is pumped out through the borehole in step (3) to ensure that the ice body can just reach the top after the accumulated water in the room-and-pillar goaf is frozen; (6) After the accumulated water in the room-and-pillar residual mining area is completely frozen, each freezing workstation in step (4) reduces the refrigeration capacity, and the freezing work enters a passive freezing period to ensure that the ice will not thaw and maintain the temperature of the frozen ice body constant at -10°C to -5°C; (7) Then, excavate and arrange transportation and ventilation tunnels in the ice body maintained by passive freezing, use explosion-proof electric heating rods to gradually melt the ice body along the designed central axis of the tunnel, and at the same time extract the water formed by the melting of the ice body. After the tunnel of the designed size is melted in the ice body, a freezing pipeline is laid on the inner wall surface of the tunnel to maintain the freezing of the tunnel surface, avoid the melting of the tunnel surface caused by the air introduced by the mine ventilation and the heat radiation generated by the equipment transportation, and ensure that the tunnel maintains the designed shape and size; then, through the tunnel transportation and arrangement of relevant mining equipment, arrange the room-and-pillar goaf coal pillar recovery working face at the designated location, open the cutting eye, and arrange the coal pillar recovery working face; (8) Under passive freezing maintenance, the frozen water and the remaining coal pillars are regarded as a whole. The coal cutter gradually cuts the ice body and coal pillars from the beginning of the cutting eye, and the whole layer is mined to recover the remaining coal; part of the ice body melts during the cutting, and part of the ice body is cut to form ice chips and the coal blocks formed by the cutting are transported together through a scraper conveyor. Pumps and drainage ditches are arranged in the working face and transport tunnel to extract the water formed by the melting of ice chips during the cutting and transportation of the ice body.
2. The method for efficiently recovering the remaining coal pillars by freezing the accumulated water in the room-and-pillar residual mining area according to claim 1 is characterized in that: When each freezing pipeline is arranged in the water accumulated in the room-and-pillar residual mining area, a series of temperature sensors will be lowered together with the pipeline and evenly arranged in the water accumulated in the room-and-pillar residual mining area to establish a real-time dynamic detection network to conduct real-time detection of the temperature of the water accumulated in the goaf or the frozen ice body.
3. The method for efficiently recovering the remaining coal pillars by freezing the accumulated water in the room-and-pillar residual mining area according to claim 1 is characterized in that: Step (1) by investigating the original geological and technical data of the mine, the width and height of the empty area group and the coal pillar group in the pillar residual mining area are determined, and a three-dimensional laser scanner is used to accurately detect the distribution direction, size and volume of the empty area group in the room-pillar residual mining area, and at the same time, the depth, distribution range and volume of the water accumulation in the room-pillar residual mining area are determined; In step (2), the room-and-pillar residual mining area is regarded as a complete unmined coal seam for mining design, wherein the relevant mechanical parameters are comprehensively considered based on the parameters of the frozen ice and the mechanical parameters of the coal sample determined by on-site drilling; the parameters of the frozen ice are: uniaxial compressive strength of 3-6 MPa, and Mohs hardness of 2.8-4.
4. The method for efficiently recovering residual coal pillars by freezing water in room-and-pillar residual mining areas according to claim 1, characterized in that: In step (3), the existing tunnels on the same level as the tunnels for coal pillar recovery working face in the parallel room-and-pillar residual mining area are set as freezing auxiliary tunnels, freezing workstations are arranged in the freezing auxiliary tunnels, and freezing pipelines are arranged through the tunnel wall holes of the freezing auxiliary tunnels into the accumulated water in the goaf, wherein the number of tunnel wall holes is determined by the required cooling capacity, the accumulated water volume and the radius of the freezing pipelines. The freezing pipes form a group of closed loops in the accumulated water in the goaf to circulate brine, displace the heat in the accumulated water, and freeze the accumulated water into ice.
5. The method for efficiently recovering the remaining coal pillars by freezing the accumulated water in the room-and-pillar residual mining area according to claim 4 is characterized in that: When the width of the working face is greater than 50m, and it is difficult to completely freeze all the water in the goaf by drilling holes in the wall of the freezing auxiliary tunnel in step (3) and laying pipelines to the water in the goaf, it is possible to freeze 10 to 20m of ice inward from the boundary rock of the residual mining area; then, tunnels are excavated and the working face is arranged in the frozen ice inside the boundary rock of the residual mining area; and the excavated transport tunnel is widened, and an auxiliary chamber is excavated in it for the subsequent arrangement of the freezing workstation. The transport tunnel also has the function of a freezing tunnel.
6. The method for efficiently recovering the remaining coal pillars by freezing the accumulated water in the room-and-pillar residual mining area according to claim 1 is characterized in that: The model, power and number of freezing equipment in step (4) are determined based on the required cooling capacity calculated from the empty area volume and the water volume of the empty area in the room-and-pillar residual mining area found in step (2); the brine circulation system uses CaCl2 solution as the refrigerant, and the cooling water circulation system is naturally cooled by digging a water pool; after determining the various freezing parameters, the equipment is tested at a designated location in the underground freezing auxiliary tunnel, and formal construction begins after the entire system is operating correctly.
7. The method for efficiently recovering residual coal pillars by freezing water in room-and-pillar residual mining areas according to claim 1, characterized in that: In step (5), the volume of water expands after freezing, and the volume of ice after freezing is 1.1 times that of the original water. When the water accumulates in the goaf that was not connected to the roof, and the distance between the water surface and the roof accounts for less than 10% of the total height of the goaf, the ice body can fully connect to the roof after freezing. When the accumulated water is less and cannot connect to the roof after freezing, artificial water injection is used to increase the amount of ice so that it can connect to the roof, thereby filling the entire room-and-pillar residual mining area and supporting the rock layer on the roof of the residual mining area.
8. The method for efficiently recovering residual coal pillars by freezing water in room-and-pillar residual mining areas according to claim 1, characterized in that: After the accumulated water in the room-and-pillar residual mining area in step (6) freezes, the uniaxial compressive strength of the ice body is 3MPa~6MPa under passive freezing maintenance, and the tensile strength is about 1 / 2 of the compressive strength. The compressive strength of the ice body is 5~10MPa under the lateral constraints of the surrounding rock of the underground goaf.
9. The method for efficiently recovering the remaining coal pillars by freezing the accumulated water in the room-and-pillar residual mining area according to claim 8, characterized in that: The passive freezing period in step (6) refers to the freezing effect of the accumulated water in the room-and-pillar residual mining area during the previous active freezing period. The liquid water gradually freezes and the freezing is basically completed. At this time, the frozen ice body only needs to maintain the frozen state to ensure that it will not thaw. The temperature of the circulating brine increases, and the temperature range of the frozen ice body increases to -10°C ~ -5°C. At the same time, the Mohs hardness of the frozen ice body is reduced, which is conducive to cutting by the coal cutter.
10. The method for efficiently recovering residual coal pillars by freezing water in room-and-pillar residual mining areas according to claim 1, characterized in that: The coal cutter described in step (8) gradually cuts the ice body and coal pillars from the beginning of the cutting eye, and the whole layer is mined and the remaining coal pillars are recovered. This means that under the maintenance of passive freezing, the frozen water and the remaining coal pillars are regarded as a whole layer of unmined coal seam. The coal cutter cuts under the support and protection of hydraulic supports, and the roof collapses as it is mined.
Citation Information
Patent Citations
Freezing-type stone door cross-measure coal uncovering method based on hydraulic seam cutting
CN104213921A
Liquid nitrogen freezing-type rock cross-cut coal uncovering method
CN107605484A
Method for freezing accumulated water between tool post type residual mining area coal pillars to conduct ascending repeated mining of overhead coal seam
CN110761791A
Segmented space-field post back-filling mining method for artificially-frozen back-filling body
CN110792471A
Method for re-mining goaf upper coal seam by segmentally freezing accumulated water in roof caving tool pillar type residual mining area
CN110847954A
Cited By
Strip type mining and space comprehensive utilization method for end slope coal pressing of strip mine
CN119333141A
Strip coal pillar filling and recycling method based on goaf water freezing
CN119825457A
Judgment method for connectivity of roadways in monoclinic room and pillar type water-filling re-mining area
CN119878167A
Gob-side entry retaining short working face coal seam floor high confined water freezing outburst prevention control method
CN119914287A