System and method for fracturing coal body by integrating pumping and injection

By alternately performing high-pressure and high-concentration gas fracturing and positive and negative pressure alternating stress fatigue fracturing in underground coal mine drilling, and using an integrated pumping and injection cracking coal system, the problem of low gas drainage efficiency caused by low coal seam permeability is solved. The gas drainage concentration and efficiency have been improved.

CN118774940APending Publication Date: 2024-10-15XUZHOU UNIV OF TECH +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411218298.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-02
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

Due to the low permeability of coal seams in underground gas drainage boreholes in my country's coal mines, the gas drainage concentration decreases, making it difficult to continuously flow into the boreholes, and the continuous influx of outside air results in low gas drainage efficiency.

Method used

By alternately carrying out high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing and gas displacement in the borehole, the pumping and injection integrated coal mass cracking system is used, and through the coordinated work of the pumping and injection mechanism and the driving mechanism, Realize the cracking and gas displacement of coal around the borehole, and increase the cracking range of the borehole.

Benefits of technology

It effectively improves the single-hole gas drainage concentration and efficiency, extends the gas drainage time, improves the gas drainage efficiency, and has the advantages of simple process, convenient operation, and low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774940A_ABST
    Figure CN118774940A_ABST
Patent Text Reader

Abstract

The invention discloses a system and a method for fracturing a coal body by integrating pumping and injecting, the system comprises a pumping and injecting mechanism and a driving mechanism, when the system is used, two gas extraction drill holes are firstly constructed, the two drill holes are respectively connected with a gas suction port and a gas outlet of the pumping and injecting mechanism, and then the pumping and injecting mechanism and the driving mechanism cooperatively work; gas desorbed in one drill hole is pumped out and injected into the other drill hole, after a period of time, the gas and the other drill hole are exchanged, and the exchange cycle is repeated for multiple times, so that coal bodies around the two drill holes alternately achieve high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing and the process of displacing gas with gas. The range of coal body cracking by drilling can be effectively widened, and finally the purpose of improving the single-hole gas extraction concentration and efficiency is achieved in the mode of coal body cracking by drilling and extraction and injection integration; in addition, the method has the advantages of simple process, convenience in operation and low cost.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a system and method for pumping and injecting integrated fractured coal bodies, belonging to the technical field of coal seam permeability enhancement and gas extraction. Background Art

[0002] Gas extraction is a fundamental measure to prevent and control coal mine gas accidents. Only when a large amount of gas is extracted can the danger of protrusion and gas over-limit problems be alleviated and eliminated. Coal mine underground gas extraction drilling has been widely used in the coal mining industry due to its advantages of simple construction and low cost. It is estimated that the current drilling volume for underground gas extraction in my country's coal mines has exceeded 150 million m / year. Despite this, the permeability of coal seams in my country is generally low, resulting in a period of drilling and extraction of coal seam gas. The coal body gas far away from the borehole is difficult to flow into the borehole continuously under the action of the extraction negative pressure. At the same time, the coal body gas near the borehole is quickly exhausted, and the outside air continues to flow into the borehole, resulting in a decrease in the gas extraction concentration. Therefore, there is an urgent need for a system and method that can effectively increase the range of coal body fracture caused by drilling, thereby improving the concentration and efficiency of gas extraction from a single hole, which is the research direction required by the present invention. Summary of the invention

[0003] In view of the problems existing in the above-mentioned prior art, the present invention provides a system and method for coal body fracturing by integrated extraction and injection. By subjecting the boreholes to alternate high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing, and gas displacement, the range of coal body fracturing by drilling can be effectively increased, thereby improving the gas extraction concentration and efficiency of a single hole.

[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: a pumping and injection integrated coal fracture system, comprising a pumping and injection mechanism, a driving mechanism, a first connecting pipe, a second connecting pipe, a first sealing pipe and a second sealing pipe; The pumping mechanism comprises a container tank, a piston and a transmission rod. The container tank is cylindrical and has a pumping space inside. The piston is installed in the container tank and can slide and seal along the axial direction of the container tank. One end of the transmission rod is connected to the piston, and the other end extends out of the container tank and is connected to the driving mechanism. An air intake port and an air outlet are provided on the container tank. Both the air intake port and the air outlet are connected to the pumping space. The air intake port is provided with a first one-way valve so that the gas passing through the air intake port can only flow into the pumping space in one direction. The air outlet is provided with a second one-way valve so that the gas passing through the air outlet can only flow out of the pumping space in one direction. The two ends of the first connecting pipe are respectively connected to the air intake port and the first sealing pipe, and the two ends of the second connecting pipe are respectively connected to the air intake port and the second sealing pipe. The driving mechanism is used to apply force to the transmission rod, thereby causing the transmission rod and the piston to reciprocate in the container tank to adjust the size of the extraction space; when the extraction space becomes larger, gas is extracted through the air intake port, the first connecting pipe and the first sealing pipe; when the extraction space becomes smaller, gas is discharged through the air outlet port, the second connecting pipe and the second sealing pipe, and this reciprocating cycle is repeated to realize the integrated extraction and injection process.

[0005] Furthermore, the driving mechanism includes a housing, a rotating cam and a pneumatic joint. The housing is located below the container tank. The rotating cam is installed in the housing through a pneumatic wheel. The other end of the transmission rod extends from the top of the housing and contacts the rotating cam. The pneumatic wheel drives the rotating cam to rotate. The raised portion of the rotating cam can push the transmission rod and the piston to reduce the pumping space during the process of rotating from the lowest point to the highest point, thereby realizing the process of exhausting gas. When the raised portion rotates from the highest point to the lowest point, the transmission rod and the piston fall under the combined action of gravity and the air pressure of the desorbed gas in the borehole connected to the air intake port to increase the pumping space, thereby realizing the process of extracting gas. Such a cyclic reciprocating motion realizes the alternating continuous pumping and injection. The pneumatic joint is connected to an external air source to provide rotational power to the pneumatic wheel. The pneumatic joint is equipped with a second control valve for controlling the on-off of the pneumatic joint and the external air source.

[0006] Furthermore, a first control valve is installed near the connection between the first sealing pipe and the first connecting pipe. The first control valve is added to control the opening and closing of the first sealing pipe.

[0007] Furthermore, a third control valve is installed near the connection between the second sealing pipe and the second connecting pipe. The third control valve is added to control the opening and closing of the second sealing pipe.

[0008] The working method of the above-mentioned pumping and injection integrated coal fracture system comprises the following specific steps: Step 1: construct gas extraction boreholes according to the requirements of underground gas extraction in coal mines, select two gas extraction boreholes as the first borehole and the second borehole, and seal the boreholes using a high-pressure grouting method, so that the first sealing tube and the second sealing tube are installed in the first borehole and the second borehole respectively; Step 2: Connect the first sealing tube to the air inlet through the first connecting tube, and connect the second sealing tube to the air outlet through the second connecting tube to complete the system connection work; Step 3: The driving mechanism applies force to the transmission rod, so that the transmission rod and the piston reciprocate to adjust the size of the extraction space; when the extraction space becomes larger, the gas in the first borehole is extracted through the air intake, the first connecting pipe and the first sealing pipe; when the extraction space becomes smaller, the gas in the extraction space is injected into the second borehole through the air outlet, the second connecting pipe and the second sealing pipe, and the reciprocating cycle is repeated to realize continuous extraction of the gas in the first borehole, and the gas is continuously injected into the second borehole by the extraction mechanism to perform gas pressure fracturing and gas displacement of the surrounding coal body, and the duration is 4 to 5 hours; Step 4: After completion, the first connecting pipe is disconnected from the air intake port and connected to the air outlet port, the second connecting pipe is disconnected from the air outlet port and connected to the air intake port, and step 3 is repeated to realize continuous extraction of gas in the second borehole, and the gas is continuously injected into the first borehole through the pumping mechanism to perform gas pressure fracturing and gas displacement of the surrounding coal body; Step 5: Repeat steps 3 and 4 multiple times, so that the first borehole and the second borehole alternately realize high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing, and gas displacement. After completion, the first borehole and the second borehole are connected to the underground gas extraction pipeline network for gas extraction.

[0009] Furthermore, the multiple times in step five is 8 to 12 times.

[0010] Compared with the prior art, the present invention first constructs two gas extraction boreholes, and connects the two boreholes to the air intake and air outlet of the extraction and injection mechanism respectively, then the extraction and injection mechanism and the driving mechanism work together to extract the desorbed gas in one of the boreholes and inject it into the other borehole. After a period of time, the two are exchanged, and the exchange cycle is repeated many times, so that the coal bodies around the two boreholes alternately realize high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing (that is, it is affected by negative pressure during extraction and by positive pressure during injection, and the positive and negative pressure alternating stress effects are alternately realized), and the process of gas displacing gas is carried out, which can effectively increase the range of coal body fracturing caused by drilling holes, and finally achieve the purpose of improving the gas extraction concentration and efficiency of a single hole by fracturing the coal body through drilling, extraction and injection. In addition, the present invention also has the advantages of simple process, convenient operation and low cost. BRIEF DESCRIPTION OF THE DRAWINGS

[0011] Figure 1 It is a schematic diagram of the overall layout of the present invention.

[0012] In the figure: 1, coal seam; 2, first borehole; 3, first sealing pipe; 4, first control valve; 5, first connecting pipe; 6, air intake; 7, first non-return valve; 8, container tank; 9, piston; 10, transmission rod; 11, rotating cam; 12, second control valve; 13, pneumatic joint; 14, air outlet; 15, second non-return valve; 16, second connecting pipe; 17, third control valve; 18, second sealing pipe; 19, second borehole. DETAILED DESCRIPTION

[0013] The present invention will be further described below.

[0014] like Figure 1 As shown, a system for pumping and injecting integrated coal fracture includes a pumping and injecting mechanism, a driving mechanism, a first connecting pipe 5, a second connecting pipe 16, a first sealing pipe 3 and a second sealing pipe 18; The pumping mechanism includes a container tank 8, a piston 9 and a transmission rod 10. The container tank 8 is cylindrical, and a pumping space is provided in the container tank 8. The piston 9 is installed in the container tank 8 and can slide and seal along the axial direction of the container tank 8. One end of the transmission rod 10 is connected to the piston 9, and the other end extends out of the container tank 8 and is connected to the driving mechanism. The container tank 8 is provided with an air intake port 6 and an air outlet 14, both of which are connected to the pumping space. The air intake port 6 is equipped with a first one-way valve 7, so that the gas passing through the air intake port 6 can only flow into the pumping space in one direction; the air outlet 14 is equipped with a second one-way valve 15, so that the gas passing through the air outlet 14 can only flow out of the pumping space in one direction; the two ends of the first connecting pipe 5 are respectively connected to the air intake port 6 and the first sealing pipe 3, and the two ends of the second connecting pipe 16 are respectively connected to the air intake port 6 and the second sealing pipe 18; the first sealing pipe 3 is equipped with a first control valve 4 near the connection with the first connecting pipe 5. The first control valve 4 is added to control the on and off of the first sealing pipe 3. The second sealing pipe 18 is provided with a third control valve 17 near the connection with the second connecting pipe 16. The third control valve 17 is provided to control the opening and closing of the second sealing pipe 18.

[0015] The driving mechanism is used to apply force to the transmission rod 10, so that the transmission rod 10 and the piston 9 reciprocate in the container tank 8 to adjust the size of the extraction space; when the extraction space becomes larger, the gas is extracted through the air intake port 6, the first connecting pipe 5 and the first sealing pipe 3; when the extraction space becomes smaller, the gas is discharged through the air outlet 14, the second connecting pipe 16 and the second sealing pipe 18, and this reciprocating cycle is repeated to realize the integrated extraction and injection process.

[0016] The driving mechanism can be implemented by an existing push-pull oil cylinder or a push-pull air cylinder. As an improvement of the present invention, in order to save energy consumption, the following driving mechanism is adopted, which only applies thrust during gas injection, and does not need to apply force during gas extraction, thereby reducing energy consumption; the driving mechanism includes a shell, a rotating cam 11 and a pneumatic joint 13, the shell is located below the container tank 8, the rotating cam 11 is installed in the shell through a pneumatic wheel, the other end of the transmission rod 10 extends from the top of the shell and contacts the rotating cam 11, the pneumatic wheel drives the rotating cam 11 to rotate, and the raised portion of the rotating cam 11 can push the transmission rod 10 and the piston 9 to reduce the extraction space during the process of rotating from the lowest point to the highest point, thereby realizing the process of exhausting gas, when the raised portion rotates from the highest point to the lowest point, the transmission rod 10 and the piston 9 fall under the combined action of gravity and the air pressure of the desorbed gas in the borehole connected to the air intake port 6 to increase the extraction space, thereby realizing the process of gas extraction, and such a cyclic reciprocating motion realizes the alternating continuous extraction and injection, and the pneumatic joint 13 is connected to an external air source to provide rotational power to the pneumatic wheel. The pneumatic joint 13 is equipped with a second control valve 12 for controlling the connection between the pneumatic joint 13 and the external air source. In order to ensure that the piston falls smoothly after each thrust is applied, the sum of the gravity of the transmission rod 10 and the piston 9 is determined to be 1.5 to 2 times the static friction between the piston 9 and the container 8.

[0017] The working method of the above-mentioned pumping and injection integrated coal fracture system comprises the following specific steps: Step 1: construct gas extraction boreholes according to the requirements of underground coal mine gas extraction, select two gas extraction boreholes, namely the first borehole 2 and the second borehole 19, and use high-pressure grouting method to seal the boreholes, so that the first sealing tube 3 and the second sealing tube 18 are installed in the first borehole 2 and the second borehole 19 respectively; Step 2: Connect the first sealing tube 3 to the air inlet 6 through the first connecting tube 5, connect the second sealing tube 18 to the air outlet 14 through the second connecting tube 16, and connect the pneumatic joint 13 to the downhole compressed air system to complete the system connection work; Step 3: First open the first control valve 4 and the third control valve 17, then open the second control valve 12, and under the action of the wind pressure of the underground air pressure system, start the pneumatic wheel to drive the rotating cam 11 to rotate, and then push the transmission rod 10 and the piston 9 to reciprocate to adjust the size of the pumping space; when the pumping space becomes larger, the gas in the first borehole 2 is extracted through the air intake 6, the first connecting pipe 5 and the first sealing pipe 3; when the pumping space becomes smaller, the gas in the pumping space is injected into the second borehole 19 through the air outlet 14, the second connecting pipe 16 and the second sealing pipe 18, and the reciprocating cycle is repeated to realize the continuous extraction of the gas in the first borehole 2, and the gas is continuously injected into the second borehole 19 by the pumping mechanism to perform gas pressure fracturing and gas displacement of the surrounding coal body, and the duration is 4 to 5 hours; Step 4: After completion, the first connecting pipe 5 is disconnected from the air inlet 6 and connected to the air outlet 14, the second connecting pipe 16 is disconnected from the air outlet 14 and connected to the air inlet 6, and step 3 is repeated to realize continuous extraction of gas in the second borehole 19, and to continuously inject gas into the first borehole 2 through the pumping mechanism to perform gas pressure fracturing and gas displacement process on the surrounding coal body; Step 5: Repeat steps 3 and 4 8 to 12 times, so that the first borehole 2 and the second borehole 19 alternately realize high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing, and gas displacement. After completion, the first borehole 2 and the second borehole 19 are connected to the underground gas extraction pipeline network for gas extraction.

[0018] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A system for pumping and injecting integrated coal fracture, characterized in that: It includes an injection mechanism, a driving mechanism, a first connecting pipe, a second connecting pipe, a first sealing pipe and a second sealing pipe; The pumping mechanism comprises a container tank, a piston and a transmission rod. The container tank is cylindrical and has a pumping space inside. The piston is installed in the container tank and can slide and seal along the axial direction of the container tank. One end of the transmission rod is connected to the piston, and the other end extends out of the container tank and is connected to the driving mechanism. An air intake port and an air outlet are provided on the container tank. Both the air intake port and the air outlet are connected to the pumping space. The air intake port is provided with a first one-way valve so that the gas passing through the air intake port can only flow into the pumping space in one direction. The air outlet is provided with a second one-way valve so that the gas passing through the air outlet can only flow out of the pumping space in one direction. The two ends of the first connecting pipe are respectively connected to the air intake port and the first sealing pipe, and the two ends of the second connecting pipe are respectively connected to the air intake port and the second sealing pipe. The driving mechanism is used to apply force to the transmission rod, thereby causing the transmission rod and the piston to reciprocate in the container tank to adjust the size of the extraction space; when the extraction space becomes larger, gas is extracted through the air intake port, the first connecting pipe and the first sealing pipe; when the extraction space becomes smaller, gas is discharged through the air outlet port, the second connecting pipe and the second sealing pipe, and this reciprocating cycle is repeated to realize the integrated extraction and injection process.

2. The system for pumping and injecting integrated coal fracture according to claim 1, characterized in that: The driving mechanism includes a shell, a rotating cam and a pneumatic joint. The shell is located below the container tank. The rotating cam is installed in the shell through a pneumatic wheel. The other end of the transmission rod extends from the top of the shell and contacts the rotating cam. The pneumatic wheel drives the rotating cam to rotate, thereby pushing the transmission rod and the piston to reciprocate. The pneumatic joint is connected to an external air source to provide rotational power to the pneumatic wheel.

3. The system for pumping and injecting integrated coal fracture according to claim 1, characterized in that: The first sealing pipe is provided with a first control valve near the connection with the first connecting pipe.

4. The system for pumping and injecting integrated coal fracture according to claim 1, characterized in that: The second sealing pipe is provided with a third control valve near the connection with the second connecting pipe.

5. The system for pumping and injecting integrated fractured coal body according to claim 2, characterized in that: The pneumatic joint is equipped with a second control valve for controlling the connection and disconnection between the pneumatic joint and the external air source.

6. A method for operating the pumping-injection integrated coal fracture system according to any one of claims 1 to 5, characterized in that: The specific steps are: Step 1: construct gas extraction boreholes according to the requirements of underground gas extraction in coal mines, select two gas extraction boreholes as the first borehole and the second borehole, and seal the boreholes using a high-pressure grouting method, so that the first sealing tube and the second sealing tube are installed in the first borehole and the second borehole respectively; Step 2: Connect the first sealing tube to the air inlet through the first connecting tube, and connect the second sealing tube to the air outlet through the second connecting tube to complete the system connection work; Step 3: The driving mechanism applies force to the transmission rod, so that the transmission rod and the piston reciprocate to adjust the size of the extraction space; when the extraction space becomes larger, the gas in the first borehole is extracted through the air intake, the first connecting pipe and the first sealing pipe; when the extraction space becomes smaller, the gas in the extraction space is injected into the second borehole through the air outlet, the second connecting pipe and the second sealing pipe, and the reciprocating cycle is repeated to realize continuous extraction of the gas in the first borehole, and the gas is continuously injected into the second borehole by the extraction mechanism to perform gas pressure fracturing and gas displacement of the surrounding coal body, and the duration is 4 to 5 hours; Step 4: After completion, the first connecting pipe is disconnected from the air intake port and connected to the air outlet port, the second connecting pipe is disconnected from the air outlet port and connected to the air intake port, and step 3 is repeated to realize continuous extraction of gas in the second borehole, and the gas is continuously injected into the first borehole through the pumping mechanism to perform gas pressure fracturing and gas displacement of the surrounding coal body; Step 5: Repeat steps 3 and 4 multiple times, so that the first borehole and the second borehole alternately realize high-pressure and high-concentration gas fracturing, positive and negative pressure alternating stress fatigue fracturing, and gas displacement. After completion, the first borehole and the second borehole are connected to the underground gas extraction pipeline network for gas extraction.

7. The working method according to claim 6, characterized in that: The multiple times in step 5 is 8 to 12 times.