Long inclined shaft concrete anti-separation conveying pipeline system

By alternately connecting inclined pipes with an angle between the axis and the flange of 67-78 degrees and ordinary pipes in highly inclined shafts and adding relay hoppers, the problems of pipe blocking and separation during concrete transportation are solved, and the stability and efficiency of the pipeline are achieved. transportation, simplifying the installation and maintenance process.

CN118774948APending Publication Date: 2024-10-15GEZHOUBA GRP NO 2 ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410931291.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

In inclined shafts with a large inclination, pipe blockage, separation of coarse and fine materials, and pipe wear are prone to occur during concrete transportation, and the blockage location is difficult to identify and remove.

Method used

A long inclined shaft anti-separation concrete transportation pipeline system is designed. Inclined pipes with an angle between the axis and the flange of 67-78 degrees are alternately connected with ordinary pipes, a relay hopper is added, and the pipeline is ensured by wear-resistant materials and screw supports. Stability to avoid separation and blockage.

Benefits of technology

It effectively reduces changes in concrete transportation speed, reduces pipeline wear, reduces separation of coarse and fine materials, improves transportation efficiency, simplifies installation and maintenance, reduces operation and maintenance costs, and improves safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774948A_ABST
    Figure CN118774948A_ABST
Patent Text Reader

Abstract

The invention relates to an anti-separation concrete conveying pipeline system for a long inclined shaft, which solves the problems that a pipeline is not wear-resistant, more pipes are blocked and the concrete separation phenomenon is serious. The inclined angle of the long inclined shaft is 50-60 degrees, the shaft of the common pipe is perpendicular to the flange, the included angle between the shaft of the inclined pipe and the flange is 67-78 degrees, the diameters of the common pipe and the inclined pipe are the same, the top of the long inclined shaft is provided with a receiving hopper 3, the receiving hopper 3 is connected with the first common pipe through a transition pipe, the axis of the first common pipe is parallel to the inclined surface of the long inclined shaft, and the other end of the first common pipe is connected with the first inclined pipe. The axis of the first inclined pipe is located below the axis of the first common pipe, the other end of the first inclined pipe is connected with the second common pipe, the other end of the second common pipe is connected with the second inclined pipe, the axis of the second inclined pipe is located above the axis of the second common pipe, and the common pipes and the inclined pipes descend in a circulating mode and recover connection till the bottom of the long inclined shaft is reached.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to an inclined shaft concrete transportation system. Background Art

[0002] Inclined shaft concrete pipeline transportation is often used in some inclined shafts with large inclination angles. The pipeline is composed of the same coaxial standard pipes. Due to the gravity acceleration of concrete in the inclined shaft pipeline with large inclination angles, the speed of concrete is getting faster and faster, resulting in more pipe blockages, serious separation of coarse and fine concrete, and poor wear resistance of the pipeline. It is difficult to determine and clear the blocked pipe location.

[0003] The purpose of the present invention is to provide a long inclined shaft concrete separation prevention pipeline system which has slow concrete transportation speed change, slow pipeline wear, reduced separation of coarse and fine concrete materials, less pipe blockage and is easy to confirm and clear.

[0004] The present invention is achieved in that: A long inclined shaft anti-separation concrete conveying pipeline system includes a receiving hopper and a standard pipe section. The standard pipe section includes an ordinary pipe and an inclined pipe. The axis of the ordinary pipe is perpendicular to the flange, and the angle between the axis of the inclined pipe and the flange is 67-78 degrees. The diameters of the ordinary pipe and the inclined pipe are the same. A receiving hopper 3 is installed on the top of the long inclined shaft. The receiving hopper 3 is connected to the first ordinary pipe 4 through a transition pipe 20. The axis of the first ordinary pipe 4 is parallel to the inclined surface of the long inclined shaft. The other end of the first ordinary pipe 4 is connected to the first inclined pipe 6. The axis of the first inclined pipe 6 is located below the axis of the first ordinary pipe 4. The other end of the first inclined pipe 6 is connected to the second ordinary pipe. The other end of the second ordinary pipe is connected to the second inclined pipe. The axis of the second inclined pipe is located above the axis of the second ordinary pipe. The ordinary pipe and the inclined pipe are connected in a cyclic ups and downs manner as described above until the bottom of the long inclined shaft.

[0005] Two supports 5 are arranged on each standard pipe section, holes are drilled in the ground, and dowels are installed. Screws 16 are welded on the dowels to install the supports 5. Concrete piers 17 are poured around the dowels and screws to be tightly connected to the ground. A circular hoop 13 is used on the upper part of the support 5. Two semicircular hoops are connected to form a full circle by bolts 14. For standard pipe sections closer to the ground, the height of the supports and the mound can be reduced. In order to increase friction, a layer of rubber pads can be added between the hoop and the standard pipe section.

[0006] The inclined tube is made of wear-resistant material.

[0007] There is a relay hopper 8 every 30-60m in the pipeline.

[0008] The thickness of the conveyed concrete does not exceed the axis of the ordinary pipe.

[0009] The axis of the first inclined tube 6 is located below the axis of the first common tube 4, and the maximum distance between the two is 1 / 3-1 / 2 of the tube diameter.

[0010] The receiving hopper 3 and the relay hopper 8 are connected to the common pipe through a transition pipe 20. The transition pipe has a first flow limiting plate 19 or a second flow limiting plate 18 covering the upper semicircle of the common pipe inlet. The first flow limiting plate 19 is connected to the side wall of the hopper 3, and the second flow limiting plate 18 is connected to the side wall of the relay hopper 8.

[0011] The present invention arranges an inclined pipe with an axis and flange angle of 67º to 78º in the pipeline. The axis of the ordinary pipe cyclically descends and recovers, which changes the speed and direction of the concrete downward movement, reduces the concrete sliding speed, and avoids the separation of coarse and fine materials in the concrete. At the same time, due to the small deflection angle, the entire pipeline adopts a "semi-flow" method, and concrete is not easy to block the pipe, ensuring that the entire pipeline is not easy to block the pipe and runs smoothly. There is a relay hopper 8 every 30-60m in the pipeline, which makes it easy to determine the location of the pipe blockage and clear the blockage.

[0012] The present invention has the following advantages: (1) By connecting the ordinary pipe with the descender-inclined pipe and adding a relay hopper, the concrete pipeline of the large-angle inclined shaft can be transported over a longer distance, effectively preventing the aggregate separation of concrete during pipeline transportation, ensuring the quality of concrete, and reducing the wear of ordinary pipes.

[0013] (2) The present invention adopts a half-pipe to transport concrete, which makes the pipe less likely to be blocked, thereby improving the concrete transport efficiency.

[0014] (3) The present invention is simple to manufacture and install, does not require special operators to operate during use, has low requirements for operation and maintenance personnel, and has low manufacturing, installation and use costs.

[0015] (4) The present invention has a high safety redundancy, and two safety measures, namely, connecting bolts between piers and pipe sections, ensure that the pipe will not shift or slip during operation.

[0016] (5) The present invention adopts bolt connection between pipe sections, and the pipe and the pier are also bolted. There is a relay hopper every 30-60m. When concrete blockage occurs, it is easy to find. It only needs to open the pipe section where the blockage occurs, which is easy to inspect and repair, reducing the labor intensity of maintenance and operation personnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a structural diagram of the present invention.

[0018] Figure 2 This is a schematic diagram of standard segment connection.

[0019] Figure 3 This is a schematic diagram of the inclined pipe installation.

[0020] Figure 4 This is the support structure diagram.

[0021] Figure 5Schematic diagram of lowering and restoring the axis of a common pipe.

[0022] Figure 6 This is a schematic diagram of the inclined pipe axis deviating from the ordinary pipe axis by a maximum of 1 / 2 pipe diameter.

[0023] Figure 7 This is the structural diagram of the hopper and relay hopper. DETAILED DESCRIPTION

[0024] A long inclined shaft anti-separation concrete conveying pipeline system includes a receiving hopper and a standard pipe section. The standard pipe section includes an ordinary pipe and an inclined pipe. The axis of the ordinary pipe is perpendicular to the flange, and the angle between the axis of the inclined pipe and the flange is 67-78 degrees. The diameters of the ordinary pipe and the inclined pipe are the same. A receiving hopper 3 is installed on the top of the long inclined shaft. The receiving hopper 3 is connected to the first ordinary pipe 4 through a transition pipe 20. The axis of the first ordinary pipe 4 is parallel to the inclined surface of the long inclined shaft. The other end of the first ordinary pipe 4 is connected to the first inclined pipe 6. The axis of the first inclined pipe 6 is located below the axis of the first ordinary pipe 4. The other end of the first inclined pipe 6 is connected to the second ordinary pipe. The other end of the second ordinary pipe is connected to the second inclined pipe. The axis of the second inclined pipe is located above the axis of the second ordinary pipe. The ordinary pipe and the inclined pipe cyclically descend and restore the connection as described above until the bottom of the long inclined shaft.

[0025] Two supports 5 are arranged on each standard pipe section, holes are drilled in the ground, and dowels are installed. Screws 16 are welded on the dowels to install the supports 5. Concrete piers 17 are poured around the dowels and screws to be tightly connected to the ground. A circular hoop 13 is used on the upper part of the support 5. Two semicircular hoops are connected to form a full circle by bolts 14. For standard pipe sections closer to the ground, the height of the supports and the piers 17 can be lowered. In order to increase friction, a layer of rubber pads can be added between the hoop and the standard pipe section.

[0026] The inclined tube is made of wear-resistant material.

[0027] There is a relay hopper 8 every 30-60m in the pipeline.

[0028] The thickness of the conveyed concrete does not exceed the axis of the ordinary pipe.

[0029] The axis of the first inclined tube 6 is located below the axis of the first common tube 4, and the maximum distance between the two is 1 / 3-1 / 2 of the tube diameter.

[0030] The receiving hopper 3 and the relay hopper 8 are connected to the common pipe through a transition pipe 20. The transition pipe has a first flow limiting plate 19 or a second flow limiting plate 18 covering the upper semicircle of the common pipe inlet. The first flow limiting plate 19 is connected to the side wall of the hopper 3, and the second flow limiting plate 18 is connected to the side wall of the relay hopper 8.

[0031] The receiving hopper 1 receives materials from the mixer truck. The receiving hopper is large at the top and small at the bottom. It is welded from ordinary steel plates. The lower part of the receiving hopper is a transition pipe section with a flange welded to the standard pipe section. The wear-resistant inclined pipe 6 has two installation methods, which are opposite to each other, to ensure that after docking with the standard pipe section, it will not raise or lower the entire pipeline.

[0032] A relay hopper 8 is arranged every 10 standard sections. The relay hopper is the same as the receiving hopper. When installed, one side is on the ground (inner surface of the inclined shaft), and the discharge port must match the rear chute. The ordinary pipe 4 is 5m long and has flanges welded at both ends.

[0033] The angle between the axis of the wear-resistant inclined tube 6 and the flange is 78°, the round tube and the flange are beveled, the flange 12 is beveled and welded to the inclined round tube as a whole, and the weld needs to be fully penetrated. The round tube of the wear-resistant inclined tube is quenched and heat treated to improve the hardness and wear resistance of the inner surface of the tube.

[0034] Two supports 15 are arranged on each standard pipe section, and the supports 15 are drilled with holes in the ground. Install dowel bars, and weld screws 16 on the dowel bars to install the steel supports 15. The cast concrete pier 17 is tightly connected to the ground. The upper part of the support 15 adopts a circular hoop, and the two semicircular hoops 13 are connected to form a full circle by bolts 14. For standard pipe sections closer to the ground, the height of the supports and piers can be reduced. In order to increase friction, a layer of rubber pad 11 can be added between the hoop and the steel pipe.

[0035] like Figure 5 , Figure 6 As shown, the first and second inclined pipes 6 and 7 are manufactured in the same manner, and only have different positions during installation. They are installed symmetrically to the standard pipe sections and matched in pairs, which plays the role of slowing down the concrete, allowing the standard pipes to be repeatedly arranged up and down on the theoretical center line, thereby reducing the manufacturing and installation costs.

[0036] like Figure 7 As shown, the flow limiting plates installed on the receiving hopper and the relay hopper respectively block part of the cement concrete from flowing down the chute, ensuring the "semi-flow" state of the cement concrete in the chute and preventing the occurrence of pipe blockage.

Claims

1. A long inclined shaft anti-separation concrete delivery pipeline system, including a receiving hopper and a standard pipe section, characterized in that: The inclination angle of the long inclined shaft is 50° to 60°. The standard pipe section includes a common pipe and an inclined pipe. The axis of the common pipe (4) is perpendicular to the flange. The angle between the axis of the inclined pipe (6) and the flange (12) is 67-78 degrees. The diameters of the common pipe and the inclined pipe are the same. A receiving hopper (3) is installed at the top of the long inclined shaft. The receiving hopper is connected to the first common pipe through a transition pipe. The axis of the first common pipe is parallel to the inclined surface of the long inclined shaft. The other end of the first common pipe is connected to the first inclined pipe. The axis of the first inclined pipe is located below the axis of the first common pipe. The other end of the first inclined pipe is connected to the second common pipe. The other end of the second common pipe is connected to the second inclined pipe. The axis of the second inclined pipe is located above the axis of the second common pipe. The common pipe and the inclined pipe are cyclically descended and restored to the bottom of the long inclined shaft as described above. There is a relay hopper (8) every 30-60m in the pipeline.

2. The long inclined shaft anti-separation concrete delivery pipeline system according to claim 1 is characterized in that: Two supports (5) are arranged on each standard pipe section, holes are drilled in the ground, dowels are installed, screws (16) are welded on the dowels to install the supports, concrete piers (17) are poured around the dowels and screws to be tightly connected to the ground, a circular hoop (13) is used on the upper part of the support, and two semicircular hoops are connected to form a full circle by bolts (14). For standard pipe sections closer to the ground, the height of the supports and the mound can be reduced. In order to increase friction, a rubber pad is provided between the hoop and the standard pipe section.

3. According to the long inclined shaft anti-separation concrete delivery pipeline system according to claim 1, it is characterized in that: The inclined tube is made of wear-resistant material.

4. According to the long inclined shaft anti-separation concrete delivery pipeline system according to claim 1, it is characterized in that: The thickness of the conveyed concrete does not exceed the axis of the ordinary pipe.

5. According to the long inclined shaft anti-separation concrete delivery pipeline system according to claim 1, it is characterized in that: The axis of the first inclined tube is located below the axis of the first common tube, and the maximum distance between the two is 1 / 3-1 / 2 of the tube diameter.

6. The long inclined shaft anti-separation concrete delivery pipeline system according to claim 1 is characterized in that: The receiving hopper (3) and the relay hopper (8) are connected to the common pipe via a transition pipe (20). The transition pipe has a first flow limiting plate (19) or a second flow limiting plate (18) covering the upper semicircle of the entrance of the common pipe. The first flow limiting plate is connected to the side wall of the hopper, and the second flow limiting plate is connected to the side wall of the relay hopper.