Flexible assembly job shop scheduling method and device and readable storage medium
By improving the artificial bee colony algorithm to construct and solve the scheduling model, the scheduling problem under multi-objective optimization in the flexible assembly workshop is solved, the workshop work efficiency is improved, and the FAJSP problem in complex scenarios is solved.
Patent Information
- Application Number
- CN202410744804.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-11
- Publication Date
- 2024-10-15
AI Technical Summary
Existing algorithms are difficult to effectively solve the two-stage FAJSP problem with transportation and preparation time when dealing with flexible assembly operation workshop scheduling, especially in multi-objective optimization scenarios, resulting in low workshop efficiency.
An improved artificial bee colony algorithm is used to construct a scheduling model based on processing time, assembly time and total energy consumption by obtaining a collection of workpieces, products and machine tools. Strategies such as improved uniform crossover strategy and dynamic neighborhood search are used to solve the scheduling model and determine the workshop Scheduling plan.
It effectively solves the scheduling problem under multi-objective optimization, improves workshop work efficiency, and can efficiently handle FAJSP problems with transportation and preparation time in complex scenarios.
Smart Images

Figure CN118778561A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of general control systems, and in particular to a flexible assembly workshop scheduling method, device and readable storage medium. Background Art
[0002] The Flexible Assembly Job Shop Scheduling Problem (FAJSP) is an important branch of the field of production management and optimization. It involves effective scheduling in a multi-machine and multi-task environment to minimize completion time, cost or energy consumption. This type of problem usually includes two main stages: the first is the classic FAJSP with transportation and preparation time; the second is the process of assembling n workpieces into pr products P on the assembly machine MA. Each product consists of Np workpieces, satisfying ∑Np=n. Product P requires Np workpieces to be assembled after the first stage of processing is completed. If two consecutive operations on the same machine tool belong to two different workpieces, preparation time is required. In addition, the transportation of workpieces between machine tools also consumes energy and time.
[0003] Although there are a variety of heuristic algorithms and meta-heuristic algorithms that can be used to solve FAJSP and FAJSPLE (Flexible Assembly Job Shop Scheduling with Learning Effect), such as genetic algorithms, simulated annealing algorithms, and swarm intelligence-based optimization methods, these methods may still have limitations when facing large-scale or complex situations. Therefore, how to design more effective algorithms to deal with these problems remains a challenging technical problem. Summary of the invention
[0004] The embodiments of the present application provide a flexible assembly job shop scheduling method, device and readable storage medium, which effectively solves the technical problem that the existing algorithms in the related technology are not capable of solving the scheduling under multi-objective optimization, and achieves the technical effect of solving the two-stage FAJSP problem with transportation and preparation time in complex scenarios, thereby improving the work efficiency of the workshop.
[0005] The present application embodiment provides a flexible assembly workshop scheduling method, the flexible assembly workshop scheduling method comprising:
[0006] Obtain a collection of workpieces, a collection of products, and a collection of machine tools;
[0007] Obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets;
[0008] Filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine a scheduling model;
[0009] The scheduling model is solved based on the improved artificial bee colony algorithm to determine the workshop scheduling plan.
[0010] Optionally, the workpiece set includes the total number of workpieces, the workpiece processing sequence and the products to which the workpieces belong, the product set includes the total number of products and the workpiece assembly sequence corresponding to each product, and the machine tool set includes the machine tool types and the total number of machine tools, and the machine tool types include processing machine tools and assembly machine tools.
[0011] Optionally, before the step of obtaining a preset scheduling model framework, the following steps are included:
[0012] Determine assumptions and optimization goals;
[0013] Determine constraints based on process allocation machine tools, process selection machine tools, machine tool processing type constraints, and processing sequence constraints;
[0014] The scheduling model framework is generated according to the assumptions, the optimization objectives and the constraints.
[0015] Optionally, the step of filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine the scheduling model includes:
[0016] Determining parameters to be filled in the scheduling model framework;
[0017] Determine filling data corresponding to the to-be-filled parameters in the workpiece set, the product set, and the machine tool set;
[0018] The filling data is filled into the scheduling model framework in a preset data format to determine the scheduling model.
[0019] Optionally, the step of solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling solution includes:
[0020] Initializing a coding vector of a solution process based on the abstract characteristics corresponding to the scheduling model, wherein the coding vector includes a machine selection vector, a processing sequence vector, and a product allocation vector;
[0021] Determine the update strategy of the employed bee stage as the improved uniform crossover strategy, determine the update strategy of the observer bee stage as the dynamic neighborhood search, and embed the archive set in the scout bee stage to decode the encoding vector;
[0022] The workshop scheduling solution is determined based on the decoding result.
[0023] Optionally, the step of determining the update strategy of the employed bee stage as an improved uniform crossover strategy includes:
[0024] updating the machine selection vector based on a random value;
[0025] Determine the first parent vector and the second parent vector;
[0026] randomly generating a binary code string of a preset length, wherein the preset length is equal to the total number of workpieces;
[0027] determining a first child vector based on the first parent vector and the binary coded string, and determining a second child vector based on the second parent vector and the binary coded string;
[0028] updating the processing sequence vector according to the first sub-vector and the second sub-vector;
[0029] The product allocation vector is determined according to the updated processing sequence vector.
[0030] Optionally, the step of determining that the update strategy of the observation bee stage is a dynamic neighborhood search includes:
[0031] Expand the solution space based on two-point inversion, intra-group exchange, inter-group exchange, two-point insertion, or one-point reallocation.
[0032] Optionally, after the step of solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling solution, the following steps are included:
[0033] Determine the workshop scheduling solution under at least two parameter combinations;
[0034] Determine the result evaluation of the workshop scheduling plan under each of the parameter combinations;
[0035] Based on the result evaluation, the population size of the improved artificial bee colony algorithm is updated and the number of iterations is limited.
[0036] In addition, the present application also proposes a flexible assembly job shop scheduling device, which includes a memory, a processor, and a flexible assembly job shop scheduling program stored in the memory and executable on the processor, and the processor implements the steps of the flexible assembly job shop scheduling method as described above when executing the flexible assembly job shop scheduling program.
[0037] In addition, the present application also proposes a computer-readable storage medium, on which a flexible assembly job shop scheduling program is stored. When the flexible assembly job shop scheduling program is executed by a processor, the steps of the flexible assembly job shop scheduling method described above are implemented.
[0038] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages:
[0039] The method adopts the steps of obtaining a workpiece set, a product set and a machine tool set; obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets; filling the scheduling model framework with the workpiece set, the product set and the machine tool set to determine the scheduling model; solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling plan. Therefore, the technical problem that the existing algorithms in the related technologies are not capable of solving the scheduling under multi-objective optimization is effectively solved, and the technical effect of solving the two-stage FAJSP problem with transportation and preparation time in complex scenarios and improving the work efficiency of the workshop is achieved. BRIEF DESCRIPTION OF THE DRAWINGS
[0040] Figure 1 This is a flow chart of the first embodiment of the method for scheduling a flexible assembly workshop of the present application;
[0041] Figure 2 This is a schematic diagram of a three-dimensional encoding vector in Embodiment 3 of the flexible assembly job shop scheduling method of the present application;
[0042] Figure 3 This is a schematic diagram of the intersection of the first parent vector and the second parent vector in Embodiment 3 of the flexible assembly job shop scheduling method of the present application;
[0043] Figure 4 A schematic diagram of a point reallocation in Embodiment 3 of the flexible assembly job shop scheduling method of the present application;
[0044] Figure 5 This is a schematic diagram of various parameter combinations and calculation results in the fourth embodiment of the flexible assembly workshop scheduling method of the present application;
[0045] Figure 6 This is a schematic diagram of the super volume mean values corresponding to the population size and the number of limited iterations in the fourth embodiment of the flexible assembly job shop scheduling method of the present application;
[0046] Figure 7 A schematic diagram showing the influence trends of the population size and the number of limited iterations in the fourth embodiment of the flexible assembly job shop scheduling method of the present application;
[0047] Figure 8 This is a schematic diagram of the experimental results of four algorithms in the fourth embodiment of the flexible assembly job shop scheduling method of the present application;
[0048] Fig. 9This is a schematic diagram of the variance analysis results of the improved artificial bee colony algorithm and the traditional bee colony algorithm in the fourth embodiment of the flexible assembly job shop scheduling method of the present application;
[0049] Fig.10 This is a schematic diagram of the hardware structure involved in the flexible assembly workshop scheduling equipment embodiment of the present application. DETAILED DESCRIPTION
[0050] In the related art, although there are a variety of heuristic algorithms and meta-heuristic algorithms that can be used to solve FAJSP and FAJSPLE, such as genetic algorithms, simulated annealing algorithms, and optimization methods based on swarm intelligence, these methods may still have limitations when facing large-scale or complex situations. The main technical solutions adopted in the embodiments of the present application are: obtaining a set of workpieces, a set of products, and a set of machine tools; obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time, and total energy consumption as optimization targets; filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine the scheduling model; solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling plan. Thereby achieving the technical effect of solving the two-stage FAJSP problem with transportation and preparation time in complex scenarios and improving workshop work efficiency.
[0051] In order to better understand the above technical solution, exemplary embodiments of the present application will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present application are shown in the accompanying drawings, it should be understood that the present application can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided in order to enable a more thorough understanding of the present application and to fully convey the scope of the present application to those skilled in the art.
[0052] Embodiment 1
[0053] The first embodiment of the present application discloses a flexible assembly workshop scheduling method, referring to Figure 1 , the flexible assembly job shop scheduling method comprises:
[0054] Step S110, obtaining a workpiece set, a product set and a machine tool set.
[0055] In this embodiment, FAJSP embeds two important stages. In the first stage, i.e., a classic n×m FJSP, n workpieces J = {J1, J2, ..., Jn} are processed on m machine tools M = {M1, M2, ..., Mm}, and each workpiece Jj∈J has an operation sequence Oj = {Oj, 1, Oj, 2, ..., Oj, l}, where Oj, l is the lth operation of workpiece Jj, and each operation Oj, l is processed on the set of optional machine tools. The processing time Pj,1,i depends on the machine tool being processed. In the second stage, n workpieces are assembled into pr products P = {P1, P2, ..., Ppr} on the assembly machine MA. Each product Pp consists of Np workpieces, satisfying Product Pp requires Np workpieces to be assembled after the first stage of processing. If two consecutive operations on the same machine tool belong to two different workpieces, preparation time is required. In addition, the transportation of workpieces between machines also consumes energy and time, which is the maximum assembly completion time and total energy consumption.
[0056] Optionally, the workpiece set includes the total number of workpieces, the workpiece processing sequence and the products to which the workpieces belong, the product set includes the total number of products and the workpiece assembly sequence corresponding to each product, and the machine tool set includes the machine tool types and the total number of machine tools, and the machine tool types include processing machine tools and assembly machine tools.
[0057] In this embodiment, at least one workpiece is assembled into a product. The total number of workpieces is the total number of workpieces, the workpiece processing sequence is the processing sequence that the workpiece needs to go through, and the product to which the workpiece belongs is the product corresponding to the workpiece, that is, the workpiece is a part of the product. The total number of products is the total number of products. A product is composed of at least one workpiece, so the workpiece assembly sequence is the assembly sequence of at least one workpiece corresponding to the product. The processing machine tool is used to process the workpiece, and the assembly machine tool is used to assemble the workpiece after processing.
[0058] As an optional implementation, relevant information of workpieces, products and machine tools is collected from the production line. In addition to the above-mentioned total number of workpieces, workpiece processing sequence and the products to which the workpieces belong, the total number of products and the workpiece assembly sequence corresponding to each product, the machine tool type and the total number of machine tools, the acquired information also includes the machine tool number, product number, workpiece number, operation number, machine tool position number, process number of workpiece j, the lth process of workpiece j, the processing time of process Oj,l on machine tool i, the preparation time of workpiece j and workpiece h on machine tool i, the preparation time between product p and product s, the transportation time of workpiece j from machine tool k to machine tool i, the assembly time of product p, the unit energy consumption of process Oj,l on machine tool i, the assembly energy consumption of product p, the total energy consumption of workpiece j, the processing completion time of process Oj,l, the start assembly time of product p, and the assembly completion time of product p.
[0059] Step S120, obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets.
[0060] In this embodiment, after obtaining the above information from the production line, a preset scheduling model framework is obtained in the database. The scheduling model framework simultaneously optimizes the maximum completion time and total energy consumption. The maximum completion time includes processing time, assembly time and transportation time.
[0061] Step S130 , filling the scheduling model framework according to the workpiece set, the product set, and the machine tool set, to determine the scheduling model.
[0062] In this embodiment, a scheduling model corresponding to the current processing scenario is generated according to the scheduling model framework, that is, the information obtained on the production line is filled into the scheduling model framework.
[0063] As an optional implementation, determine the parameters to be filled in the scheduling model framework; determine the filling data corresponding to the parameters to be filled in the workpiece set, the product set and the machine tool set; fill the filling data into the scheduling model framework in a preset data format to determine the scheduling model.
[0064] In the scheduling model framework, the parameters to be filled include the processing time, assembly time, transportation time and energy consumption of each workpiece. These parameters are the basis for building the scheduling model. According to the collected data, the corresponding filling data is extracted from the workpiece set, product set and machine tool set. For example, for each workpiece, its processing time is obtained from the process table; the assembly time and transportation time are measured or estimated according to the actual situation of the production line; the energy consumption is calculated according to the energy consumption standard and actual operation of the equipment. The determined filling data is filled into the scheduling model framework according to the preset data format. When all the parameters to be filled are correctly filled into the scheduling model framework, a complete scheduling model is obtained, which reflects the various constraints and goals in the actual production environment.
[0065] Step S140, solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling plan.
[0066] In this embodiment, first, the population is initialized. This includes randomly generating initial solutions and constructing an initial population based on these initial solutions. For each individual, three different methods (global selection, local selection, and random selection) are used to initialize the machine selection vector (MS), the operation sequence vector (OS) is randomly generated, and the product allocation vector (PA) is generated based on the OS. The improved artificial bee colony algorithm is an improved multi-objective artificial bee colony algorithm.
[0067] Among them, MOABC (Multi-Objective Artificial Bee Colony) adopts a three-dimensional encoding mechanism, which represents machine selection (MS), operation sequence (OS) and product arrangement (PA). This encoding method can better fit the characteristics of the FAJSP problem. In the employed bee stage, the modified uniform crossover strategy (MUX) is used to cross the OS, and the mutation strategy based on the critical path is combined to improve the population diversity and accelerate the convergence speed. In the observation bee stage, the dynamic neighborhood search (DNS) strategy is introduced, which includes five different neighborhood structures (such as two-point inversion TPIV, exchange IGS-I, inter-group exchange IGS-II, two-point insertion TPIS and one-point reallocation OPR). Through the above neighborhood structure, the solution space is effectively explored and utilized, the local search ability of the algorithm is enhanced, and then the scheduling model is solved to determine the workshop scheduling plan, including but not limited to the workpieces processed by each machine tool, the order of processing workpieces, and the assembly order of products.
[0068] Furthermore, in order to enhance the local search capability and avoid falling into the local optimum, the simulated annealing (SA) algorithm is embedded in MOABC as a local search strategy.
[0069] The method adopts the steps of obtaining a workpiece set, a product set and a machine tool set; obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets; filling the scheduling model framework with the workpiece set, the product set and the machine tool set to determine the scheduling model; solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling plan. Therefore, the technical problem that the existing algorithms in the related technologies are not capable of solving the scheduling under multi-objective optimization is effectively solved, and the technical effect of solving the two-stage FAJSP problem with transportation and preparation time in complex scenarios and improving the work efficiency of the workshop is achieved.
[0070] Based on the first embodiment, the second embodiment of the present application proposes a flexible assembly workshop scheduling method, before step S120, including:
[0071] Step S210, determining assumptions and optimization goals.
[0072] Step S220 , determining constraint conditions based on the process allocation machine tool, process selection machine tool, machine tool processing type constraints, and processing sequence constraints.
[0073] Step S230, generating the scheduling model framework according to the assumptions, the optimization objectives and the constraints.
[0074] In this embodiment, the assumption is the preset condition of the processing scenario to which the model is applicable. The optimization target is the optimization target parameter corresponding to the model and the parameter approach direction. The constraint conditions of the model include but are not limited to the process allocation machine tool, process selection machine tool, machine tool processing type constraint and processing sequence constraint.
[0075] As an optional implementation, before starting to build the scheduling model, some basic assumptions are first clarified, such as the processing procedures of each workpiece and the required machine tool type. At the same time, optimization goals are set, such as minimizing the total processing time, total assembly time or total energy consumption of the workpiece. According to the actual production environment, various constraints are determined, for example, each machine tool can only process one process at a time; different processes of the same workpiece cannot be performed continuously on the same machine tool; there are preparation time requirements between certain processes, etc. Combining the assumptions, optimization goals and constraints, a preliminary scheduling model framework is constructed. After determining the scheduling model framework, the specific parameters in the framework are filled according to the specific workpiece set, product set and machine tool set, such as the processing time, assembly time and transportation time of each workpiece. In the scheduling model framework, the parameters to be filled include the processing time, assembly time, transportation time and energy consumption of each workpiece. These parameters are the basis for building the scheduling model. According to the collected data, the corresponding filling data is extracted from the workpiece set, product set and machine tool set. For example, for each workpiece, its processing time can be obtained from the process table; the assembly time and transportation time can be measured or estimated based on the actual situation of the production line; the energy consumption can be calculated based on the energy consumption standard and actual operation of the equipment. The determined filling data is filled into the scheduling model framework according to the preset data format. When all the parameters to be filled are correctly filled into the scheduling model framework, a complete scheduling model can be obtained.
[0076] As an alternative implementation, FAJSP is determined to meet the following assumptions: Each machine tool can only process one operation at a time. The processing time and assembly time are fixed, and the requirements for the final product are specified in advance. The processing and assembly phases are independent of each other, and assembly can only be performed after all operations of the same product have been processed. All machines are continuously available, regardless of interruptions. Different operations have different preparation times, and if the operations of a workpiece are processed continuously on the same machine tool, the preparation time is 0. If two operations of a workpiece are processed on the same machine tool, the transportation time is 0.
[0077] Determine the optimization target as Min{C max ,TEC}.
[0078] The constraint conditions are determined as follows:
[0079]
[0080] X j,l,h,z ,Y j,l,i,k ∈{0,1} (3-21)
[0081] Among them, constraint (3-2) ensures that each process is assigned to one machine tool as much as possible, that is, the process allocation constraint. Constraints (3-3) to (3-5) indicate that the process selects a machine tool from the set of processable machine tools, that is, the process selection constraint. Constraints (3-6) and (3-7) determine that if Oj,l is processed on machine tool i, then Oj,l-1 is processed on machine tool k, that is, the machine tool processing type constraint. Constraint (3-8) takes into account the transportation and preparation time, and the next process must be carried out after the previous process is completed, that is, the processing order constraint. Constraints (3-9) and (3-10) force each machine tool to process only one process at a time. Constraint (3-11) specifies the minimum start time of the assembly stage. Constraint (3-12) represents the completion time of the product. Constraint (3-13) clarifies the assembly order of product s and product p. Constraints (3-14) to (3-16) specify the predecessor and successor restrictions of the product. Constraints (3-17) and (3-18) calculate the total energy consumption of the optimization objective. Constraint (3-19) represents the maximum assembly completion time limit, and constraint (3-20) forces continuous variables to take positive values. Constraint (3-21) is a variable value constraint.
[0082] Where i is the machine tool number, i=1, 2, ..., m. s, p is the product number, s, p=1, 2, ..., pr. j, h is the workpiece number, j, h=1, 2, ..., n. l, z is the operation number. f, k is the position number of the machine tool. n is the total number of workpieces. m is the total number of machine tools. pr is the total number of products. nj is the number of processes of workpiece j. Oj, l is the lth process of workpiece j. Pj, l, i is the processing time of process Oj, l on machine tool i. Si, h, j is the preparation time of workpiece j and workpiece h on machine tool i. SPp, s is the preparation time between product p and product s. Tj, k, i is the transportation time of workpiece j from machine tool k to machine tool i. Ap is the assembly time of product p. UECj, l, i is the unit energy consumption of process Oj, l on machine tool i. AECp is the assembly energy consumption of product p. ECj is the total energy consumption of workpiece j. Cj,l is the processing completion time of process Oj,l. STp is the start assembly time of product p. CAp is the assembly completion time of product p. TEC is the total energy consumption. Cmax is the maximum assembly completion time. M is a large positive number. Xj,l,h,z is 1 when Oj,l is processed after Oh,z, otherwise it is 0. Yj,l,i,k is 1 when Oj,l is processed on machine tool i and Oj,l-1 is processed on machine tool k, otherwise it is 0. Yj,p is 1 when workpiece j is a part of product p, otherwise it is 0. Zs,p is 1 when product s is assembled before product p, otherwise it is 0.
[0083] Finally, based on the determined assumptions, optimization objectives, and constraints, a scheduling model framework is generated.
[0084] By adopting the method of determining assumptions and optimization goals, determining constraints based on process allocation of machine tools, process selection of machine tools, machine tool processing type constraints and processing sequence constraints, and generating the scheduling model framework according to the assumptions, the optimization goals and the constraints, the technical problem that the existing algorithms in related technologies are not capable of solving scheduling under multi-objective optimization is effectively solved, and the technical effect of solving the two-stage FAJSP problem with transportation and preparation time in complex scenarios and improving the work efficiency of the workshop is achieved.
[0085] Based on the above embodiments, the third embodiment of the present application proposes a flexible assembly workshop scheduling method, step S140, including:
[0086] Step S310, initializing the encoding vector of the solution process based on the abstract characteristics corresponding to the scheduling model, wherein the encoding vector includes a machine selection vector, a processing sequence vector, and a product allocation vector.
[0087] In this embodiment, the abstract characteristics are the characteristics corresponding to the scheduling model. To summarize the two characteristics of the two-stage FAJSP, first, parts are produced in a decentralized manner and products are assembled in a centralized manner. Second, the assembly process begins immediately after all parts belonging to the same product are completed in the processing stage. Based on the above characteristics, two characteristics and two quantitative methods of FAJSP are extracted. The first characteristic:
[0088]
[0089] Among them, Num p i represents the number of parts belonging to product p when processed in machine tool i, and np is the number of parts of product p. The two Cmax obtained by integrating the first characteristic into FAJSP are 114 for a and 154 for b. It can be seen that the completion time of the scheduling sequence in b increases due to the violation of the first characteristic, resulting in all parts belonging to the same product being processed serially.
[0090] Second characteristic:
[0091] L={L1,L2,…,L p} (3.23)
[0092]
[0093] PA={P(1),P(2),…,P(p)} (3.25)
[0094] Among them, L = {L1, L2, ..., LP} is the sequence of the final processed parts of the product, and PA = {P (1), P (2), ..., P (p)} is the assembly sequence. When the final processed parts belonging to product p are processed in the first stage, they are immediately ready for assembly. In the example of the second characteristic, the two Cmax obtained are c is 114 and d is 131. d violates the second characteristic and causes Cmax to increase.
[0095] In the traditional ABC, the initial solution is randomly generated in the search space and the food source is updated. new represents the new solution, x b is the best solution, x w is the worst solution. is a random number between [0, 1].
[0096] Considering the first and second characteristics mentioned above, the 3D coding vector is divided into three parts: Machine Selection (MS), Operation Sequence (OS), and Product Arrangement (PA). MS records the machine tool assigned to each workpiece, and OS consists of two vectors: the first vector records the processing order of all workpieces, and each symbol indicating a workpiece is repeated n times. j times; the second vector records the product to which the workpiece belongs, corresponding to the first vector, and the lengths of both vectors are PA represents the assembly sequence of all products.
[0097] In one example, referring to Figure 2 , including 5 machine tools, 7 workpieces and 2 products. The parts of products P1 and P2 are {J2, J3, J5}, {J1, J4, J6, J7} respectively. In MS, the second number is 3, which means O 1,2 The third machine is assigned to the optional machine set. For OS, the first scheduled operation is O, which belongs to product P2. 6,1 , the last operation is O 7,2 , the first number in PA is 1, meaning product P1 is assembled first.
[0098] As an optional implementation, global selection, local selection and / or random selection are adopted for the initial MS. Then, a random generation method is adopted for the OS. Finally, the PA sequence is generated according to the OS.
[0099] Step S320, determining the update strategy of the employed bee stage as the improved uniform crossover strategy, determining the update strategy of the observer bee stage as the dynamic neighborhood search, and embedding the archive set in the scout bee stage to decode the encoding vector.
[0100] In this embodiment, the decoding process needs to consider the first characteristic as well as the second characteristic. During decoding, the OS is converted into a series of operations, each process is assigned to the selected machine tool, and finally each target value is calculated according to its rules. After initializing the three-dimensional code, different update strategies are adopted for the employed bees, observation bees, and scout bees to expand the solution space and optimize the target value.
[0101] Optionally, in step S320, the step of determining that the update strategy of the employed bee stage is an improved uniform crossover strategy specifically includes:
[0102] Step S321, updating the machine selection vector based on a random value.
[0103] In this embodiment, the employed bees are searching for specific food sources locally to produce better food sources. In order to improve the diversity of the population, the crossover mutation operator is introduced in combination with the characteristics of the two-stage FAJSP. After that, the employed bees obtain a new food source and then use the greedy strategy to decide whether the new solution replaces the old solution. The mutation update strategy for MS is to randomly select a position in the MS vector and then replace it with another available machine tool.
[0104] In the hired bee phase, the machine selection vector is first updated based on random values. This step is to ensure that each workpiece can be assigned to a different machine tool, thereby avoiding the waste of preparation time caused by continuous processing of the same workpiece on the same machine tool.
[0105] Step S322, determining a first parent vector and a second parent vector;
[0106] Step S323, randomly generating a binary code string of a preset length, wherein the preset length is equal to the total number of workpieces;
[0107] Step S324, determining a first child vector based on the first parent vector and the binary coded string, and determining a second child vector based on the second parent vector and the binary coded string;
[0108] Step S325 , updating the processing sequence vector according to the first sub-vector and the second sub-vector.
[0109] In this embodiment, steps S322-S325 are the OS update process in the hired bee stage.
[0110] Determine the first and second parent vectors. These two vectors are derived from the two best performing solutions in the current iteration. They will be used in the subsequent crossover operation to generate new solutions. Then, randomly generate a binary coded string of a preset length, which is equal to the total number of artifacts. This string will be used as part of the crossover operation to determine the child vectors together with the parent vector. The first child vector is determined based on the first parent vector and the binary coded string, and the second child vector is determined based on the second parent vector and the same binary coded string. The crossover operation is performed by combining the genes in the parent vectors with the binary coded string. Based on the two child vectors obtained, update the processing sequence vector. This step involves adjusting the processing order of the artifacts to ensure that each artifact can be processed in the optimal order.
[0111] For example, refer to Figure 3, OS adopts the modified uniform crossover strategy (Modified Uniform Crossover, MUX). For the first parent vector P1, another second parent vector P2 is randomly selected to cross with it. A binary encoding string R of length L is randomly generated, where L is equal to the number of artifacts of all products. The genes with a value of 1 in P1 are copied to the first sub-vector C1, and the genes with a value of 1 in P2 are copied to the second sub-vector C2. After removing the genes copied to C2 in P1, the remaining genes are copied to C2 in sequence. Similarly, after removing the genes copied to C1 in P2, the remaining gene sequences are copied to C1.
[0112] Step S326, determining the product allocation vector according to the updated processing sequence vector.
[0113] Finally, the product allocation vector is determined based on the updated processing sequence vector. This step ensures that each product is correctly assigned to the corresponding machine tool for assembly.
[0114] Optionally, in step S320, the archive set is embedded in the scout bee stage.
[0115] If a food source is not optimized after a predetermined number of experiments (Limit), it will be abandoned. Usually, the scout bees will randomly initialize the abandoned food source, or randomly select a new solution from the updated food source to replace it, but the new solution cannot provide better information for the population.
[0116] To improve this process, in this embodiment, MOABC embeds an archive set, which stores multiple high-quality solutions in one run. A solution is randomly selected from the archive set and the TPIS operation is performed multiple times to replace the food sources that exceed the "Limit".
[0117] Optionally, in step S320, the step of determining that the update strategy of the observation bee stage is a dynamic neighborhood search specifically includes:
[0118] Step S326, expanding the solution space based on two-point reversal, intra-group exchange, inter-group exchange, two-point insertion, or one-point reallocation.
[0119] In the classic ABC, the bees select a food source according to the percentage of the amount of the food source to the total nectar amount. In this case, the time complexity is high, so in this embodiment, the DNS strategy is introduced to ensure that each iteration moves in a better direction.
[0120] The core idea of DNS is to achieve dynamic adjustment from neighborhood structure to neighborhood structure, in which five different neighborhood structures are embedded, namely two-point inversion (TPIV), swap (intra-groupswap, IGS-I, inter-group swap, IGS-II), two-point insertion (TPIS) and one-point reassignment (OPR). TPIV is applied to OS and PA vectors. First, two different positions in OS are randomly selected, and then the genes between the two positions are reversed one by one, while the corresponding genes in PA are changed.
[0121] IGS-I exchanges two different operations within the same group. IGS-II randomly selects two different products and exchanges the operations at the corresponding positions. TPIS randomly selects a gene at a position in OS and inserts it into another random position. Figure 4 , the OPR randomly selects a location in the OS and then reallocates a machine tool from the optional machine tool set.
[0122] Step S330: determining the workshop scheduling plan based on the decoding result.
[0123] As an optional implementation, when solving the scheduling model based on the improved artificial bee colony algorithm, a coding vector is first initialized. This coding vector consists of three parts: a machine selection vector, a processing sequence vector, and a product allocation vector. MS is used to record the machine tool assigned to each workpiece; OS records the processing sequence of all workpieces, where each symbol indicating the workpiece is repeated nj times; PA represents the assembly sequence of all products. In the employed bee stage, an improved uniform crossover strategy is used to cross the OS to generate a new solution. The update strategy of the observation bee stage is dynamic neighborhood search, which can explore more solution spaces. The scout bee stage embeds an archive set to store excellent solutions in the iterative process to avoid premature convergence. Then, the coding vector is decoded according to its rules to obtain a specific workshop scheduling plan. Finally, based on the decoding results, the quality of each solution is evaluated, and the optimal or approximately optimal scheduling plan is selected as the final solution.
[0124] Based on the above embodiments, a fourth embodiment of the present application proposes a flexible assembly workshop scheduling method, which after step S140 includes:
[0125] Step S410, determining the workshop scheduling solution under at least two parameter combinations.
[0126] In this embodiment, the two parameters are the population size (PS) and the limited number of iterations (Ln).
[0127] At least two parameter combinations consisting of population size and limited number of iterations are determined respectively, and a corresponding workshop scheduling solution under each combination is determined.
[0128] Step S420, determining the result evaluation of the workshop scheduling plan under each of the parameter combinations.
[0129] After determining the workshop scheduling plan corresponding to each parameter combination, each workshop scheduling plan is evaluated to determine the result evaluation of the workshop scheduling plan under each parameter combination.
[0130] Step S430: updating the population size of the improved artificial bee colony algorithm and limiting the number of iterations based on the evaluation result.
[0131] In this embodiment, the result evaluations corresponding to the scheduling plans of various workshops are compared to determine the optimal solution of the parameter combination under the current processing scenario, and then the population size of the improved artificial bee colony algorithm and the number of iterations are limited by the optimal solution.
[0132] As an optional implementation, at least two different parameter combinations are selected to generate a shop scheduling solution. In this embodiment, the population size (PS) and the number of iterations (Ln) are selected as parameters. Two or more different parameter combinations of population size and number of iterations are determined respectively. For example, different combinations such as (PS1, Ln1) and (PS2, Ln2) are selected. For each parameter combination, the improved artificial bee colony algorithm is used to solve the corresponding shop scheduling problem and determine the corresponding shop scheduling solution. The results of the shop scheduling solution under each parameter combination are evaluated. This is done by comparing the performance indicators of each solution, such as minimizing the total processing time, total assembly time, total transportation time and total energy consumption of the workpiece. The population size (PS) and the number of iterations (Ln) of the improved artificial bee colony algorithm are updated according to the results of the result evaluation. Specifically, if the shop scheduling solution under a certain parameter combination performs well, then increase the population size under the parameter combination or allow more iterations to obtain a better solution.
[0133] By repeatedly iterating the above steps, the optimal parameter combination for the current processing scenario is finally found, thereby obtaining the best workshop scheduling plan and algorithm operating parameters.
[0134] Exemplarily, this section selects two parameters of MOABC, namely, population size (PS) and limit number of iterations (Ln), where PS∈{50, 100, 150, 200}, Ln∈{5, 10, 15, 20, 30}. In order to perform fair parameter tuning, each parameter combination is run independently with MOABC, and HV values are collected to evaluate the results. Figure 5The parameter combinations and calculation results are given, and the average value of each parameter HV (Avg_HV) is as follows Figure 6 As shown, Figure 7 The influence trend of the two parameters is shown. The larger the PS value, the more computing resources are consumed. If the PS value is too small, the local search ability of the algorithm decreases. Based on the above analysis, PS = 100 and Ln = 5 are selected as the final parameter results.
[0135] In this embodiment, in order to evaluate the effectiveness of MOABC, the experimental part generates 30 test cases of different scales. The number of workpieces is n∈{10, 20, 30, 40, 50, 60, 70, 80, 90, 100}, the number of processing machines is m∈{3, 5, 7}, and there is only one assembly machine. The processing time Pj,l,i∈[10, 35), transportation time Tj,k,i∈[5, 15), preparation time Si,h,j∈[15, 20) in the first stage, assembly time Ap∈[0, 20), preparation time SPp,s∈[5, 25). To ensure fairness, each case is run 10 times separately, and the stop standard of CPU=30s is set uniformly.
[0136] Hypervolume (HV), Inverted Generational Distance (IGD) and Relative Percentage Increase (RPI) were used in the experiment.
[0137] HV can be calculated by (3-27):
[0138]
[0139] Where δ is the Lebesgue measure, S is the non-dominated solution set, and vi represents the hypervolume consisting of the reference point and the i-th non-dominated individuals. The larger the HV value, the better the performance of the algorithm.
[0140] IGD is calculated by (3-28):
[0141]
[0142] Where P and P* represent the PFknown and PFtrue solution sets, respectively, represents the scale of P*, and represents the closest Euclidean distance between P and P* in the target space. The smaller the IGD, the better the algorithm performance.
[0143] RPI is calculated by (3-29):
[0144]
[0145] Where Fc is the best value generated by the specified algorithm, and Fb is the best value of all algorithms. The smaller the RPI, the better the current algorithm results.
[0146] Furthermore, to verify the effectiveness of the various improved parts of MOABC, this embodiment provides three variants of MOABC: (1) ABC1: classic ABC; (2) ABC2: improved initialization strategy; (3) ABC3: improved DNS. After 10 independent runs using the same test case, the experimental comparison results are listed in Figure 8 In the comparison table, the second column contains the case entries, with two numbers indicating the number of workpieces and machines, for example, the first case has 10 workpieces and 3 machines, while the last one has 100 workpieces and 7 machines. Fig. 9 The RPI variance analysis results (ANOVA) of HV and IGD are shown. It can be seen from the figure that the p-value is close to 0, so the performance of MOABC is significantly better than the other three algorithms.
[0147] By adopting the method of determining the workshop scheduling scheme under at least two parameter combinations, determining the result evaluation of the workshop scheduling scheme under each parameter combination, and updating the population size of the improved artificial bee colony algorithm and limiting the number of iterations based on the result evaluation, more personalized parameter combinations can be determined for different processing scenarios as the algorithm is continuously executed, thereby improving the flexibility and accuracy of the algorithm application.
[0148] The present application also proposes a flexible assembly workshop scheduling device, referring to Fig.10 , Fig.10 A schematic diagram of the structure of a flexible assembly workshop scheduling device in the hardware operating environment involved in the embodiment of the present application.
[0149] like Fig.10As shown, the flexible assembly workshop scheduling device may include: a processor 1001, such as a central processing unit (CPU), a communication bus 1002, a user interface 1003, a network interface 1004, and a memory 1005. Among them, the communication bus 1002 is used to realize the connection and communication between these components. The user interface 1003 may include a display screen (Display), an input unit such as a keyboard (Keyboard), and the optional user interface 1003 may also include a standard wired interface and a wireless interface. The network interface 1004 may optionally include a standard wired interface and a wireless interface (such as a wireless fidelity (WIreless-FIdelity, WI-FI) interface). The memory 1005 may be a high-speed random access memory (Random Access Memory, RAM) memory, or a stable non-volatile memory (Non-Volatile Memory, NVM), such as a disk memory. The memory 1005 may also be a storage device independent of the aforementioned processor 1001.
[0150] Those skilled in the art will understand that Fig.10 The structure shown in the figure does not constitute a limitation on the flexible assembly job shop scheduling equipment, and may include more or less components than shown in the figure, or combine certain components, or arrange the components differently.
[0151] Optionally, the memory 1005 is electrically connected to the processor 1001 , and the processor 1001 may be used to control the operation of the memory 1005 , and may also read data in the memory 1005 to implement flexible assembly job shop scheduling.
[0152] Alternatively, if Fig.10 As shown, the memory 1005 as a storage medium may include an operating system, a data storage module, a network communication module, a user interface module, and a flexible assembly job shop scheduling program.
[0153] Optionally, in Fig.10 In the flexible assembly job shop scheduling device shown, the network interface 1004 is mainly used for data communication with other devices; the user interface 1003 is mainly used for data interaction with the user; the processor 1001 and the memory 1005 in the flexible assembly job shop scheduling device of the present application can be set in the flexible assembly job shop scheduling device.
[0154] like Fig.10 As shown, the flexible assembly shop scheduling device calls the flexible assembly shop scheduling program stored in the memory 1005 through the processor 1001, and executes the relevant steps of the flexible assembly shop scheduling method provided in the embodiment of the present application:
[0155] Obtain a collection of workpieces, a collection of products, and a collection of machine tools;
[0156] Obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets;
[0157] Filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine a scheduling model;
[0158] The scheduling model is solved based on the improved artificial bee colony algorithm to determine the workshop scheduling plan.
[0159] Optionally, the processor 1001 can call the flexible assembly job shop scheduling program stored in the memory 1005, and also perform the following operations: the workpiece set includes the total number of workpieces, the workpiece processing sequence and the products to which the workpieces belong, the product set includes the total number of products and the workpiece assembly sequence corresponding to each product, the machine tool set includes the machine tool type and the total number of machine tools, and the machine tool type includes processing machine tools and assembly machine tools.
[0160] Optionally, the processor 1001 may call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0161] Determine assumptions and optimization goals;
[0162] Determine constraints based on process allocation machine tools, process selection machine tools, machine tool processing type constraints, and processing sequence constraints;
[0163] The scheduling model framework is generated according to the assumptions, the optimization objectives and the constraints.
[0164] Optionally, the processor 1001 may call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0165] Determining parameters to be filled in the scheduling model framework;
[0166] Determine filling data corresponding to the to-be-filled parameters in the workpiece set, the product set, and the machine tool set;
[0167] The filling data is filled into the scheduling model framework in a preset data format to determine the scheduling model. Optionally, the processor 1001 can call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0168] Initializing a coding vector of a solution process based on the abstract characteristics corresponding to the scheduling model, wherein the coding vector includes a machine selection vector, a processing sequence vector, and a product allocation vector;
[0169] Determine the update strategy of the employed bee stage as the improved uniform crossover strategy, determine the update strategy of the observer bee stage as the dynamic neighborhood search, and embed the archive set in the scout bee stage to decode the encoding vector;
[0170] The workshop scheduling solution is determined based on the decoding result.
[0171] Optionally, the processor 1001 may call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0172] updating the machine selection vector based on a random value;
[0173] Determine the first parent vector and the second parent vector;
[0174] randomly generating a binary code string of a preset length, wherein the preset length is equal to the total number of workpieces;
[0175] determining a first child vector based on the first parent vector and the binary coded string, and determining a second child vector based on the second parent vector and the binary coded string;
[0176] updating the processing sequence vector according to the first sub-vector and the second sub-vector;
[0177] The product allocation vector is determined according to the updated processing sequence vector.
[0178] Optionally, the processor 1001 may call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0179] Expand the solution space based on two-point inversion, intra-group exchange, inter-group exchange, two-point insertion, or one-point reallocation.
[0180] Optionally, the processor 1001 may call the flexible assembly job shop scheduling program stored in the memory 1005, and further perform the following operations:
[0181] Determine the workshop scheduling solution under at least two parameter combinations;
[0182] Determine the result evaluation of the workshop scheduling plan under each of the parameter combinations;
[0183] Based on the result evaluation, the population size of the improved artificial bee colony algorithm is updated and the number of iterations is limited.
[0184] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0185] The present application is described with reference to flowcharts and / or block diagrams of methods, devices (systems) and computer program products according to embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0186] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0187] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0188] It should be noted that in the claims, any reference signs placed between brackets shall not be construed as limiting the claims. The word "comprising" does not exclude the presence of components or steps not listed in the claims. The word "a" or "an" preceding a component does not exclude the presence of a plurality of such components. The present application may be implemented by means of hardware comprising several different components and by means of a suitably programmed computer. In a unit claim enumerating several means, several of these means may be embodied by the same item of hardware. The use of the words first, second, and third etc. does not indicate any order. These words may be interpreted as names.
[0189] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.
[0190] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims
1. A flexible assembly workshop scheduling method, characterized in that: The flexible assembly job shop scheduling method comprises: Obtain a collection of workpieces, a collection of products, and a collection of machine tools; Obtaining a preset scheduling model framework, wherein the scheduling model framework is based on processing time, assembly time, transportation time and total energy consumption as optimization targets; Filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine a scheduling model; The scheduling model is solved based on the improved artificial bee colony algorithm to determine the workshop scheduling plan.
2. The flexible assembly workshop scheduling method according to claim 1, characterized in that: The workpiece set includes the total number of workpieces, the workpiece processing sequence and the products to which the workpieces belong; the product set includes the total number of products and the workpiece assembly sequence corresponding to each product; the machine tool set includes the machine tool type and the total number of machine tools; the machine tool type includes processing machine tools and assembly machine tools.
3. The flexible assembly workshop scheduling method according to claim 1, characterized in that: Before the step of obtaining the preset scheduling model framework, the following steps are included: Determine assumptions and optimization goals; Determine constraints based on process allocation machine tools, process selection machine tools, machine tool processing type constraints, and processing sequence constraints; The scheduling model framework is generated according to the assumptions, the optimization objectives and the constraints.
4. The flexible assembly workshop scheduling method according to claim 1, characterized in that: The step of filling the scheduling model framework with the workpiece set, the product set, and the machine tool set to determine the scheduling model comprises: Determining parameters to be filled in the scheduling model framework; Determine filling data corresponding to the to-be-filled parameters in the workpiece set, the product set, and the machine tool set; The filling data is filled into the scheduling model framework in a preset data format to determine the scheduling model.
5. The flexible assembly workshop scheduling method according to claim 1, characterized in that: The step of solving the scheduling model based on the improved artificial bee colony algorithm to determine the workshop scheduling plan includes: Initializing a coding vector of a solution process based on the abstract characteristics corresponding to the scheduling model, wherein the coding vector includes a machine selection vector, a processing sequence vector, and a product allocation vector; Determine the update strategy of the employed bee stage as the improved uniform crossover strategy, determine the update strategy of the observer bee stage as the dynamic neighborhood search, and embed the archive set in the scout bee stage to decode the encoding vector; The workshop scheduling solution is determined based on the decoding result.
6. The flexible assembly workshop scheduling method according to claim 5, characterized in that: The step of determining the update strategy of the employed bee stage as an improved uniform crossover strategy includes: updating the machine selection vector based on a random value; Determine the first parent vector and the second parent vector; randomly generating a binary code string of a preset length, wherein the preset length is equal to the total number of workpieces; determining a first child vector based on the first parent vector and the binary coded string, and determining a second child vector based on the second parent vector and the binary coded string; updating the processing sequence vector according to the first sub-vector and the second sub-vector; The product allocation vector is determined according to the updated processing sequence vector.
7. The flexible assembly workshop scheduling method according to claim 5, characterized in that: The step of determining that the update strategy of the observation bee stage is a dynamic neighborhood search comprises: Expand the solution space based on two-point inversion, intra-group exchange, inter-group exchange, two-point insertion, or one-point reallocation.
8. The flexible assembly workshop scheduling method according to claim 1, characterized in that: After the step of solving the scheduling model based on the improved artificial bee colony algorithm and determining the workshop scheduling plan, the method includes: Determine the workshop scheduling solution under at least two parameter combinations; Determine the result evaluation of the workshop scheduling plan under each of the parameter combinations; Based on the result evaluation, the population size of the improved artificial bee colony algorithm is updated and the number of iterations is limited.
9. A flexible assembly workshop scheduling device, characterized in that: The method comprises a memory, a processor and a flexible assembly job shop scheduling program stored in the memory and executable on the processor. When the processor executes the flexible assembly job shop scheduling program, the steps of the flexible assembly job shop scheduling method as described in any one of claims 1 to 8 are implemented.
10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a flexible assembly job shop scheduling program, and when the flexible assembly job shop scheduling program is executed by a processor, the steps of the flexible assembly job shop scheduling method according to any one of claims 1 to 8 are implemented.