Construction method for erecting prefabricated box girder of bent frame steel structure system bridge

By using the starting beam platform, gantry crane track foundation and hoop bracket system in the coastal tidal area, combined with the gantry crane and truck crane methods, the problem of prefabricated box girder not being able to fall directly on the top of the pier is solved, and the stable erection and installation of the box girder is achieved. Efficient transportation reduces construction costs and improves efficiency.

CN118792965APending Publication Date: 2024-10-18CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411069281.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-10-18

AI Technical Summary

Technical Problem

When the geological conditions in the coastal tidal flat area are not suitable for erecting floor-standing supports, the prefabricated box beams cannot be directly dropped on the top of the pier, and the traditional beam-on-beam transport method cannot be used to transport the box beams, resulting in increased construction difficulty and reduced cost and efficiency.

Method used

The starting beam platform, gantry crane track foundation and hoop bracket system are used, and the gantry crane and truck crane are used to erect the box girders. The prefabricated box girders are accurately adjusted and connected through the non-landing track foundation and temporary brackets to form a row frame rigid frame system.

Benefits of technology

It reduces construction costs, improves construction efficiency, overcomes the limitations of terrain and geological conditions, and achieves stable erection and subsequent transportation of prefabricated box girders.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118792965A_ABST
    Figure CN118792965A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for erecting a prefabricated box girder of a bent steel structure system bridge. The construction method comprises the following steps: S1, erecting an initial girder lifting platform; s2, a gantry crane starting section track foundation is built; s3, erecting a box girder temporary support; s4, mounting a gantry crane; s5, erecting a box girder; s6, carrying out cast-in-place construction on a flange plate between a pier top cross beam and a box girder; s7, the gantry crane retreats to the initial beam lifting platform along the track; according to the construction method, the construction technical problem of erection of the prefabricated girder of the bent frame steel structure system bridge is solved, the construction cost is reduced, the construction efficiency is improved, erection of the prefabricated box girder of the bent frame steel structure system bridge is achieved, the hoop support system is adopted as a non-landing supporting structure, and the construction cost is reduced. The difficulty that under-bridge topographic and geological conditions are not suitable for erecting a floor stand is overcome, and the box girder is erected in a mode of combining two kinds of large hoisting equipment, namely a gantry crane and a truck crane.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of box girder construction, and in particular to a method for erecting a prefabricated box girder for a bent steel structure bridge. Background Art

[0002] A certain bridge is located in the coastal mudflat area. The geological conditions are weak, the water level changes with the tide, and there is no stable water navigation condition. The structure of the bridge is a two-span one-unit frame rigid frame. The piers are designed as independent cylindrical piers or square piers. There is no cap beam and support designed on the pier top. The main beam is a prefabricated small box beam. The length of the small box beam is less than the pier column spacing. The box beam and the pier column are connected by a wet joint of the cast-in-place beam on the pier top to achieve pier-beam consolidation. The difficulty of this type of project is that the prefabricated box beam cannot be directly placed on the pier top. Temporary brackets are required to support the box beam and serve as cast-in-place beam brackets. In addition, the geological conditions of the coastal mudflat area where the bridge is located are not suitable for the use of ground brackets. The operating area on the pier top is small and there is no cap beam. The bridge erection machine cannot support the legs and move horizontally, so the bridge erection machine cannot be used for erection; the beam transportation channel is limited. Before the construction of the cast-in-place beam is completed, the box beam does not form a reliable connection and force transmission system with the pier column, and the traditional beam transportation method cannot be used to transport the box beam. Summary of the invention

[0003] In order to solve the above problems, the present invention provides a method for erecting prefabricated box beams of a bent steel structure bridge.

[0004] The technical solution adopted by the present invention is:

[0005] A method for erecting a prefabricated box girder of a bent steel structure bridge, comprising the following steps:

[0006] S1. Erection of the starting beam lifting platform: The starting beam lifting platform is a steel structure platform. Conventional methods are used to drive steel pipe piles, install pile top cross beams and Bailey beams, and lay distribution beams and bridge deck systems. The elevation of the starting beam lifting platform is consistent with the bridge deck elevation.

[0007] S2. Construct the track foundation of the starting section of the gantry crane: Construct track steel pipe piles on both sides of the starting lifting beam platform. Construct a steel pile top crossbeam on the top of each row of track steel pipe piles. Construct a gantry crane track foundation steel box beam in the longitudinal direction on the steel pile top crossbeam. Then lay the track on it. Set wheel chocks at both ends of the track to prevent the gantry crane from sliding off the track.

[0008] S3. Erection of temporary support for box beam: The bridge structure includes pile foundation, abutment, pier, prefabricated box beam and cast-in-place pier top cross beam. The support adopts hoop support system, which is connected as a whole in the transverse direction of the bridge. The bracket extends to both sides along the longitudinal bridge. The top elevation of the bracket is flush with the bottom elevation of the prefabricated box beam to be erected. The gantry crane track foundation steel box beam is erected in the longitudinal direction of the bridge on the side pier brackets on both sides, and then the track is laid on it;

[0009] S4. Install the gantry crane: Use a truck crane to stand on the starting platform to install the gantry crane. A total of gantry cranes of the same specifications are set up for erecting prefabricated box girders;

[0010] S5, Box girder erection: The beam transporter transports the prefabricated box girder to be erected to the starting beam lifting platform, and the gantry crane moves along the track to the top of the starting beam lifting platform, releases the restraint lock of the beam transporter on the prefabricated box girder, uses the steel bundle to penetrate the bottom to lift the prefabricated box girder, and removes the beam transporter; the gantry crane synchronously moves forward along the track to the erection position of the prefabricated box girder, makes precise longitudinal and transverse adjustments, temporarily places the prefabricated box girder on the temporary box girder bracket, and erects the middle box girder in sequence in a symmetrical order from the center to both sides;

[0011] S6. Cast-in-place construction of flange plates between pier top cross beams and box beams: tie and connect the reserved steel bars, set up formwork, cast the cross beams and flange plates of the middle box beam pier tops, and after the concrete reaches the design strength, tension and grouting of prestressed tendons on the pier tops are performed to form a consolidated connection between the precast box beams and the pier columns. The cross beams on the pier tops enable the precast box beams to form a bent rigid frame system with the pier columns in the longitudinal direction of the bridge, and the cast-in-place flange plates are connected to connect the middle box beams as a whole in the transverse direction of the bridge.

[0012] S7, the gantry crane is withdrawn along the track to the starting beam lifting platform, and the above steps S5 to S6 are repeated to carry out the subsequent erection of prefabricated box beams; after the construction of the cast-in-place pier top cross beam of the middle box beam is completed, the temporary support and the gantry crane track foundation are removed, and they are transferred to the next joint for reuse. After the middle box beam forms a rack rigid frame system, it is used as a beam transportation channel, and the box beam is transported by beam-on-beam transportation. The gantry crane is withdrawn along the track to the top of the middle box beam, and the above steps S5 to S6 are repeated to carry out the subsequent erection of prefabricated box beams;

[0013] S8. Install the side beams, remove the gantry crane track foundation under the side beams, use the beam transporter to transport the side beams to the middle box beam, and place the truck crane on the middle box beam to hoist and erect the side beams. The side beams fall on the temporary brackets beside the piers, and cast-in-place construction of the cross beams and flange plates on the top of the side beam piers on both sides is carried out. After the concrete reaches the designed strength, tensioning and grouting of the prestressed tendons on the top of the side beam piers is carried out. The side beams form a frame rigid frame system in the longitudinal direction of the bridge, and are connected to the middle box beam as a whole in the transverse direction of the bridge to complete the erection of a unit of box beams.

[0014] The starting section gantry crane track foundation in step S2 includes track steel pipe piles, steel pile top cross beams, track foundation steel box beams and tracks. The track steel pipe piles are driven into a certain depth below the riverbed as friction pile foundations. Steel pile top cross beams are set on the track steel pipe piles to support the track foundation steel box beams. Tracks are laid on the track foundation steel box beams. The tracks and the track foundation steel box beams are connected as a whole to facilitate overall turnover and reuse.

[0015] The temporary support for the intermediate box girder in step S3 is a hoop support system, and each pier is provided with a hoop support, which are horizontally connected as a whole.

[0016] The hoop bracket longitudinal bridge extends to both sides, with an extension length of L1, L1>L-L2, wherein the clear span of the bridge is L, and the length of the prefabricated box girder is L2.

[0017] The hoop bracket system is used to temporarily support prefabricated box girders and serve as cast-in-place brackets for pier top beams. The brackets on the side piers are first used as foundation supports for the gantry crane track. After the temporary brackets for the middle box girder are erected, they are used to temporarily support prefabricated box girders and serve as cast-in-place brackets for pier top beams.

[0018] The gantry crane track foundation is a non-ground track foundation. The starting section track is located on both sides of the starting beam lifting platform, and the track at the bridge position is located on the side pier supports on both sides of the starting bridge. The gantry crane crosses the bridge deck horizontally and moves along the track in the longitudinal direction of the bridge to carry out beam lifting, beam moving and beam erection operations to complete the erection and installation of the middle box girder.

[0019] In step S4, the box girder is lifted by the steel bundle penetration bottom protection method. Circular holes are reserved on the flange plates of the prefabricated box girder for passing the steel bundles. The reserved holes are located close to the web of the box girder. When passing the steel bundles, rubber pads are placed at the corners of the box girder to prevent the steel bundles from damaging the corners of the box girder. The steel bundles are then lowered through the bottom plate and passed through the reserved holes on the flange plates on both sides of the prefabricated box girder to complete the lifting and bundling.

[0020] The beneficial effects of the invention: The invention solves the construction technical difficulties in the erection of prefabricated main beams of a bent steel structure system bridge, reduces construction costs, improves construction efficiency, realizes the erection of prefabricated box beams of a bent steel structure system bridge, adopts a hoop bracket system as a non-ground support structure, overcomes the difficulty that the terrain and geological conditions under the bridge are not suitable for setting up ground brackets, and adopts a combination of two large-scale lifting equipment, a gantry crane and a truck crane, to erect the box beam. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a top view of the starting lifting beam platform of the present invention.

[0022] Figure 2 It is the left view of the starting lifting beam platform of the present invention.

[0023] Figure 3 It is a top view of the gantry crane track of the present invention.

[0024] Figure 4 It is the left view of the gantry crane track of the present invention.

[0025] Figure 5 It is a top view of the clamp support system of the present invention.

[0026] Figure 6 It is a left view of the clamp support system of the present invention.

[0027] Figure 7It is a front view of the gantry crane lifting beam operation of the present invention.

[0028] Figure 8 It is a left view of the gantry crane lifting beam operation of the present invention.

[0029] Fig. 9 It is the front view of the operation of the gantry hanger beam of the present invention.

[0030] Fig.10 It is the front view of the beam casting operation of the present invention.

[0031] Fig.11 The figure is a top view of the automobile hanger beam of the present invention.

[0032] Fig.12 It is the front view of the automobile hanger beam operation of the present invention.

[0033] Fig.13 It is a construction flow chart of the present invention.

[0034] Among them: 1-starting lifting beam platform; 1.1-steel pipe pile; 1.2-pile top beam; 1.3-Bailey beam; 1.4-distribution beam; 1.5-bridge deck system; 2-gantry crane track foundation; 2.1-track steel pipe pile; 2.2-steel pile top beam; 2.3-track foundation steel box beam; 2.4-track; 2.5-wheel chock; 3-hoop bracket system; 3.1-hoop bracket; 3.2-bracket; 4-pile foundation; 5-cap; 6-pier column; 7-prefabricated box beam; 8-pier top beam; 9-gantry crane; 10-steel bundle; 11-truck crane; 12-beam transporter. DETAILED DESCRIPTION

[0035] A method for erecting a prefabricated box girder of a bent steel structure bridge, comprising the following steps:

[0036] S1. Erection of the starting beam lifting platform: The starting beam lifting platform 1 is a steel structure platform. Conventional methods are used to drive steel pipe piles 1.1, install pile top cross beams 1.2 and Bailey beams 1.3, and pave distribution beams 1.4 and bridge deck systems 1.5. The elevation of the starting beam lifting platform 1 is consistent with the elevation of the bridge deck.

[0037] S2. Driving the track foundation of the starting section of the gantry crane: The track foundation 2 of the starting section of the gantry crane includes track steel pipe piles 2.1, steel pile top cross beams 2.2, track foundation steel box beams 2.3 and tracks 2.4. The track steel pipe piles 2.1 are driven into a certain depth below the riverbed as friction pile foundations. The steel pile top cross beams 2.2 are set on the track steel pipe piles 2.1 to support the track foundation steel box beams 2.3. The track 2.4 is laid on the track foundation steel box beams 2.3. .4 is connected with the track foundation steel box beam 2.3 as a whole, which is convenient for overall turnover and reuse. Track steel pipe piles 2.1 are driven on both sides of the starting beam lifting platform 1, with 2 piles in each row. A steel pile top cross beam 2.2 is set on the top of the track steel pipe pile 2.1. A gantry crane track foundation steel box beam 2.3 is set on the steel pile top cross beam 2.2 in the longitudinal direction of the bridge, and then a track 2.4 is laid on it. Wheel blocks 2.5 are set at both ends of the track 2.4 to prevent the gantry crane 9 from sliding out of the track 2.4;

[0038] S3. Erection of temporary support for box beam: The bridge structure includes pile foundation 4, pedestal 5, pier 6, prefabricated box beam 7 and cast-in-place pier top cross beam 8. The support adopts hoop support system 3, which is connected as a whole in the transverse direction of the bridge. Bracket 3.2 extends to both sides along the longitudinal bridge. The top surface elevation of bracket 3.2 is flush with the bottom elevation of the prefabricated box beam 7 to be erected. Gantry crane track foundation steel box beam 2.3 is erected in the longitudinal direction of the bridge on the side pier brackets on both sides, and then the track 2.4 is laid on it; the temporary support for the middle box beam is the hoop support system 3, and each pier The column 6 is provided with a hoop bracket 3.1, which is horizontally connected as a whole; the hoop bracket 3.1 extends longitudinally to both sides of the bridge, and the extension length is L1, L1>L-L2, wherein the clear span of the bridge is L, and the length of the prefabricated box beam 7 is L2; ​​the hoop bracket system 3 is used to temporarily support the prefabricated box beam 7 and serve as a cast-in-place bracket for the pier top cross beam 8, and the brackets on the side piers on both sides are first used as the support for the gantry crane track foundation 2, and after the temporary bracket of the middle box beam is erected, it is used to temporarily support the prefabricated box beam 7 and serve as a cast-in-place bracket for the pier top cross beam 8;

[0039] S4, installing the gantry crane: using a truck crane to stand on the starting platform to install the gantry crane 9, a total of two gantry cranes 9 of the same specifications are set up for erecting the prefabricated box beam 7;

[0040] S5, box girder erection: the beam transport vehicle 12 transports the prefabricated box girder 7 to be erected to the starting beam lifting platform 1, and the two gantry cranes 9 move along the track 2.4 to the top of the starting beam lifting platform 1, release the restraint lock of the beam transport vehicle 12 on the prefabricated box girder 7, use the steel bundle 10 to perforate the bottom to lift the prefabricated box girder 7, and remove the beam transport vehicle 12; the two gantry cranes 9 move forward synchronously along the track 2.4 to the erection position of the prefabricated box girder 7, make precise longitudinal and transverse adjustments, and temporarily install the prefabricated box girder 7. The steel bundle 10 is placed on the temporary support of the box beam, and the middle box beams are erected in a symmetrical order from the center to both sides; the box beam is lifted by the bottom-covering method of the steel bundle 10, and a circular hole is reserved on the flange plate of the prefabricated box beam 7 for passing the steel bundle 10. The reserved hole is located close to the web of the box beam. When passing the steel bundle 10, rubber is padded at the corner of the box beam to prevent the steel bundle 10 from damaging the corner of the box beam. The steel bundle 10 is then lowered through the bottom plate and passed through the reserved holes on the flange plates on both sides of the prefabricated box beam 7 to complete the lifting and bundling;

[0041] S6, cast-in-place construction of flange plates between pier top cross beam and box beam: tie and connect reserved steel bars, set up formwork, cast the middle box beam pier top cross beam 8 and flange plates, and after the concrete reaches the design strength, perform pier top prestressed tendon tensioning and grouting operations to form a consolidated connection between the prefabricated box beam 7 and the pier column 6. The pier top cross beam 8 enables the prefabricated box beam 7 to form a bent rigid frame system with the pier column 6 in the longitudinal direction of the bridge. The cast-in-place flange plate connection enables the middle box beam to be connected as a whole in the transverse direction of the bridge;

[0042] S7, the gantry crane 9 is returned along the track 2.4 to the starting beam lifting platform 1, and the above steps S5 to S6 are repeated to erect the subsequent prefabricated box beam 7; after the construction of the cast-in-place pier top cross beam 8 of the middle box beam is completed, the temporary support and the gantry crane track foundation 2 are removed, and they are transferred to the next joint for reuse. After the middle box beam forms a bent frame rigid frame system, it is used as a beam transportation channel, and the box beam is transported by beam-on-beam transportation. The gantry crane 9 is returned along the track 2.4 to the top of the middle box beam, and the above steps S5 to S6 are repeated to erect the subsequent prefabricated box beam 7;

[0043] S8. Install the side beams, remove the gantry crane track foundation 2 under the side beams, use the beam transporter 12 to transport the side beams to the middle box beam, and use two truck cranes 11 to stand on the middle box beam to hoist and erect the side beams. The side beams fall on the temporary brackets 3.2 beside the piers, and cast-in-place construction of the cross beams 8 and flange plates on the top of the side beam piers on both sides is carried out. After the concrete reaches the design strength, the prestressed tendons on the top of the side beam piers are tensioned and grouting operations are carried out. The side beams form a frame rigid frame system in the longitudinal direction of the bridge, and are connected to the middle box beam as a whole in the transverse direction of the bridge to complete the erection of a unit of box beams.

[0044] The temporary support for the intermediate box girder in step S3 is a hoop support system 3, and each pier 6 is provided with a hoop support 3.1, which are horizontally connected as a whole.

[0045] The gantry crane track foundation 2 is a non-ground track foundation. The starting section track 2.4 is located on both sides of the starting beam lifting platform 1, and the bridge position track 2.4 is located on the side pier supports on both sides of the starting bridge. The gantry crane 9 crosses the bridge deck horizontally and moves along the track 2.4 in the longitudinal direction of the bridge to carry out beam lifting, beam shifting and beam erection operations to complete the erection and installation of the intermediate box girder.

[0046] The construction method is a flow operation, and the working procedures are as follows: the gantry crane 9 erects the middle box girder, constructs the middle box girder, the pier top cross beam 8 and the flange plate, the truck crane 11 erects the side box girder, constructs the side box girder pier top cross beam 8 and the flange plate. After completing one operation section, the clamp bracket and the gantry crane track rotate and move forward.

[0047] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.

[0048] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In the description of the present invention, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0049] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection, an electrical connection, or communication with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements, unless otherwise clearly defined. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0050] The embodiments of the present invention are described in detail above, but the contents described are only preferred embodiments of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A method for erecting a prefabricated box girder of a bent steel structure bridge, characterized in that: The steps are: S1. Erection of the starting beam lifting platform: The starting beam lifting platform (1) is a steel structure platform. Conventional methods are used to drive steel pipe piles (1.1), install pile top cross beams (1.2) and Bailey beams (1.3), and lay distribution beams (1.4) and bridge deck systems (1.5). The elevation of the starting beam lifting platform (1) is consistent with the elevation of the bridge deck. S2. Constructing the track foundation of the starting section of the gantry crane: Constructing track steel pipe piles (2.1) on both sides of the starting beam platform (1), with 2 piles in each row, constructing a steel pile top cross beam (2.2) on top of the track steel pipe piles (2.1), constructing a gantry crane track foundation steel box beam (2.3) on the steel pile top cross beam (2.2) in the longitudinal direction, and then laying the track (2.4) thereon, and setting wheel blocks (2.5) at both ends of the track (2.4) to prevent the gantry crane (9) from sliding off the track (2.4); S3. Erection of temporary support for box beam: the bridge structure includes pile foundation (4), cap (5), pier column (6), prefabricated box beam (7) and cast-in-place pier top cross beam (8). The support adopts hoop support system (3), which is connected as a whole in the transverse direction of the bridge. The bracket (3.2) extends to both sides along the longitudinal direction of the bridge. The top surface elevation of the bracket (3.2) is flush with the bottom elevation of the prefabricated box beam (7) to be erected. The gantry crane track foundation steel box beam (2.3) is erected in the longitudinal direction of the bridge on the side pier brackets on both sides, and then the track (2.4) is laid thereon; S4, installing the gantry crane: using a truck crane to stand on the starting platform to install the gantry crane (9), and a total of two gantry cranes (9) of the same specification are provided for erecting the prefabricated box beam (7); S5, box girder erection: the beam transport vehicle (12) transports the prefabricated box girder (7) to be erected to the starting beam lifting platform (1), and the two gantry cranes (9) move along the track (2.4) to the top of the starting beam lifting platform (1), release the restraint lock of the beam transport vehicle (12) on the prefabricated box girder (7), use the steel bundle (10) to perforate the bottom to lift the prefabricated box girder (7), and remove the beam transport vehicle (12); the two gantry cranes (9) move forward synchronously along the track (2.4) to the erection position of the prefabricated box girder (7), perform precise longitudinal and transverse adjustments, temporarily place the prefabricated box girder (7) on the temporary box girder support, and erect the middle box girder in sequence in a symmetrical order from the center to both sides; S6, cast-in-place construction of flange plates between pier top cross beam and box beam: tie and connect the reserved steel bars, set up formwork, cast the intermediate box beam pier top cross beam (8) and flange plates, and after the concrete reaches the designed strength, tension and grouting of prestressed tendons at the pier top are performed to form a consolidated connection between the precast box beam (7) and the pier column (6). The pier top cross beam (8) enables the precast box beam (7) to form a bent rigid frame system with the pier column (6) in the longitudinal direction of the bridge. The cast-in-place flange plates are connected to connect the intermediate box beams in the transverse direction of the bridge as a whole. S7, the gantry crane (9) is returned along the track (2.4) to the starting beam lifting platform (1), and the above steps S5 to S6 are repeated to erect the subsequent prefabricated box beam (7); after the construction of the cast-in-place pier top cross beam (8) of the middle box beam is completed, the temporary support and the gantry crane track foundation (2) are removed, and they are transferred to the next joint for reuse. After the middle box beam forms a bent frame rigid frame system, it is used as a beam transportation channel, and the box beam is transported by beam-on-beam transportation. The gantry crane (9) is returned along the track (2.4) to the top of the middle box beam, and the above steps S5 to S6 are repeated to erect the subsequent prefabricated box beam (7); S8, installing the side beams, removing the gantry crane track foundation (2) under the side beams, transporting the side beams to the middle box beams by means of a beam transport vehicle (12), and erecting the side beams by means of two truck cranes (11) standing on the middle box beams, and placing the side beams on temporary brackets (3.2) beside the piers, and carrying out cast-in-place construction of the cross beams (8) and flange plates on the top of the side beam piers on both sides, and tensioning and grouting of the prestressed tendons on the top of the side beam piers after the concrete reaches the design strength, forming a bent frame rigid frame system in the longitudinal direction of the bridge, and connecting with the middle box beams in the transverse direction of the bridge as a whole, and completing the erection of a unit of box beams.

2. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 1 is characterized in that: In step S2, the starting section gantry crane track foundation (2) comprises a track steel pipe pile (2.1), a steel pile top cross beam (2.2), a track foundation steel box beam (2.3) and a track (2.4). The track steel pipe pile (2.1) is driven into a certain depth below the riverbed as a friction pile foundation. A steel pile top cross beam (2.2) is set on the track steel pipe pile (2.1) to support the track foundation steel box beam (2.3). The track (2.4) is laid on the track foundation steel box beam (2.3). The track (2.4) and the track foundation steel box beam (2.3) are connected as a whole to facilitate overall turnover and repeated use.

3. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 1 is characterized in that: The temporary support for the intermediate box girder in step S3 is a hoop support system (3), and each pier (6) is provided with a hoop support (3.1), which are laterally connected as a whole.

4. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 3 is characterized in that: The hoop support (3.1) extends longitudinally to both sides of the bridge, with an extension length of L1, L1>L-L2, wherein the clear span of the bridge is L, and the length of the prefabricated box girder (7) is L2.

5. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 3 is characterized in that: The hoop support system (3) is used to temporarily support the prefabricated box beam (7) and serve as a cast-in-place support for the pier top cross beam (8). The supports on the side piers on both sides are first used as supports for the gantry crane track foundation (2). After the temporary support for the middle box beam is erected, it is used to temporarily support the prefabricated box beam (7) and serve as a cast-in-place support for the pier top cross beam (8).

6. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 5, characterized in that: The gantry crane track foundation (2) is a non-ground track foundation, the starting section track (2.4) is respectively located on both sides of the starting beam lifting platform (1), and the bridge position track (2.4) is respectively located on the side pier brackets on both sides of the starting bridge. The gantry crane (9) crosses the bridge deck horizontally and moves along the track (2.4) in the longitudinal direction of the bridge to carry out beam lifting, beam shifting and beam erection operations, thereby completing the erection and installation of the intermediate box beam.

7. The method for erecting prefabricated box beams of a bent steel structure bridge according to claim 1, characterized in that: In the step S5, the steel bundle (10) is perforated to lift the box beam by the bottom-covering method. A circular hole is reserved in the flange plate of the prefabricated box beam (7) for passing the steel bundle (10). The reserved hole is located close to the web of the box beam. When passing the steel bundle (10), rubber is padded at the corner of the box beam to prevent the steel bundle (10) from damaging the corner of the box beam. The steel bundle (10) is then lowered through the bottom plate and passed through the reserved holes in the flange plates on both sides of the prefabricated box beam (7), completing the lifting and bundling.