Assembly type reinforced concrete foundation pit supporting system convenient to disassemble and construction method
Through the prefabricated reinforced concrete foundation pit support system that is easy to dismantle, using bar connections and standardized components, the problems of long construction period and difficulty in dismantling of the existing foundation pit support system are solved, and fast, efficient and reliable foundation pit support is achieved. Reduces costs and promotes sustainable development of foundation pit support.
Patent Information
- Application Number
- CN202411214351.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-31
- Publication Date
- 2024-10-18
AI Technical Summary
The existing foundation pit support system has problems such as long construction period, difficult dismantling, short service life, difficulty in recycling, and high cost. In particular, cast-in-place reinforced concrete internal supports under earth pressure cannot meet the needs of efficiency, reliability, and recyclability.
A prefabricated reinforced concrete foundation pit support system that is easy to dismantle is adopted. Through the reinforcing bar connection method of the foundation pit support beam sections and the support eight-shaped beams, it is divided into peripheral standard areas, internal standard areas and non-standard areas. Combined with the use of jacks and pallets, Achieve quick installation and disassembly, adapt to different shapes of foundation pits, adopt full-life design and standardized components to improve reusability.
It significantly shortens the foundation pit support construction period and reduces costs, enables the reusability of foundation pit support beam sections and splayed beams, improves construction speed and economic benefits, adapts to different shapes of foundation pits, and reduces labor and carbon emissions. Implemented the green building concept.
Smart Images

Figure CN118793069A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of building construction, and in particular, relates to an easily dismantled assembled reinforced concrete foundation pit support system and a construction method. Background Art
[0002] In foundation pit engineering projects, foundation pit support plays a vital role. Its main function is to effectively support the surrounding soil and build a stable and reliable support system to ensure the overall stability of the foundation pit.
[0003] In situations where the ground stress is large, cast-in-place reinforced concrete internal support is the best choice. It has the advantages of flexible design, good integrity, high pressure resistance and high reliability. However, it also has the disadvantages of long construction period, difficult demolition, short service life, difficult recycling and high cost.
[0004] In order to overcome the shortcomings of cast-in-place concrete support, prefabricated reinforced concrete support is used in foundation pits with greater ground pressure and square shape. The advantages of prefabricated support beams are easy to dismantle and install, recyclable and reused, and shortening the construction period. Summary of the invention
[0005] The core goal of the present invention is to propose an innovative prefabricated foundation pit support system and its corresponding construction method in response to the significant problems existing in the current foundation pit support system. Through the implementation of the system and method, it is intended to achieve the safety, reliability, efficiency, cost optimization and material recyclability of the foundation pit support process, thereby comprehensively improving the comprehensive benefits of the foundation pit support project.
[0006] The technical solution of the present invention to solve the above technical problems is as follows: The assembled reinforced concrete foundation pit support system that is easy to dismantle is characterized in that the support system includes an outer standard area and an inner standard area; the inner standard area is an orthogonal bracing system composed of a number of foundation pit support beam sections of the same length and cross-sectional size; the surface of the foundation pit support beam section is provided with a beam sleeve, and a side steel plate is provided on the beam sleeve. The pipe walls at both ends of the preset transverse embedded pipe are respectively welded to the hole walls of the side steel plates on both sides to form transverse reinforcement holes, and the end steel plate is provided on the beam sleeve, and the pipe wall at one end of the preset longitudinal embedded pipe is welded to the inner wall of the hole of the end steel plate to form a longitudinal reinforcement hole; When two foundation pit support beam sections are axially connected, the end face steel plates of the two foundation pit support beam sections are seamlessly fitted, the longitudinal reinforcement holes of the two foundation pit support beam sections are aligned one by one, and there are connecting steel bars in the longitudinal reinforcement holes; when four foundation pit support beam sections are cross-connected or three foundation pit support beam sections are T-connected, after the two foundation pit support beam sections are axially connected, they are vertically intersected with another one or two foundation pit support beam sections at the axial connection. At the vertical intersection, the longitudinal reinforcement holes of one or two foundation pit support beam sections are aligned one by one with the transverse reinforcement holes at the axial connection of the two foundation pit support beam sections, and there are connecting steel bars in the transverse reinforcement holes; The area where the support system contacts the crown beam or waist beam is provided with a peripheral standard area, and the peripheral standard area includes N foundation pit support beam sections perpendicular to the crown beam and waist beam and foundation pit support splayed beams arranged on both sides thereof; The foundation pit supporting cross-shaped beams have the same length and cross-sectional dimensions; one end is a right-angle end, and the other end is an oblique angle end; the surface of the foundation pit supporting cross-shaped beam is provided with a cross-shaped beam sleeve, and the oblique angle end is provided with a cross-shaped beam reinforcement hole; The connection between the foundation pit support beam section and the foundation pit support eight-shaped beam includes that after the two foundation pit support beam sections are axially connected, they are butted with the beveled end of the foundation pit support eight-shaped beam at the axial connection, and the connection method is that the eight-shaped beam reinforcement holes are aligned one by one with the transverse reinforcement holes at the axial connection of the two foundation pit support beam sections, and there are connecting steel bars in the transverse reinforcement holes; The outer standard area and the inner standard area are connected by a plurality of foundation pit support beam sections of the same size arranged inside the outer standard area or the inner standard area, so that the outer standard area and the inner standard area are adapted to the corresponding foundation pit size.
[0007] Based on the above technical solution, the present invention can also be improved as follows.
[0008] Preferably, when the outer standard area and the inner standard area are connected by several foundation pit support beam segments of the same length and cross-sectional size and cannot adapt to the foundation pit size, a non-standard area connection is set, and the non-standard area includes non-standard area foundation pit support beam segments that are less than 2 times the length of the foundation pit support beam segments, or includes non-standard area foundation pit support beam segments and foundation pit support beam segments that are less than 2 times the length of the foundation pit support beam segments to adapt to the corresponding foundation pit size, and other settings of the non-standard area foundation pit support beam segments are the same as those of the standard area foundation pit support beam segments.
[0009] Preferably, the crown beam and waist beam are both provided with a pedestal and a corbel, and the foundation pit supporting beam section of the outer standard area is placed on the pedestal fixed on the crown beam or the waist beam; and the foundation pit supporting S-beam of the outer standard area is placed on the pedestal fixed on the corbel; a jack is arranged on the pedestal for lifting and supporting the foundation pit supporting beam section or the foundation pit supporting S-beam; a tray is arranged below the connection of the foundation pit supporting beam section, and the tray is welded to the steel lattice column.
[0010] Preferably, the longitudinal rebar holes are in two rows and the transverse rebar holes are in one row; the distance between the two rows of longitudinal rebar holes is equal to twice the distance between the transverse rebar holes and the end steel plate, the vertical spacing of adjacent longitudinal rebar holes or transverse rebar holes is the same, the distance between the uppermost longitudinal rebar hole and the upper edge of the beam sleeve is equal to the distance between the lowermost transverse rebar hole and the lower edge of the beam sleeve, the spacing between the two rows of S-beam rebar holes is equal to twice the distance between the transverse rebar holes and the end steel plate of the foundation pit supporting beam section, the distance from the uppermost S-beam rebar hole to the upper edge of the foundation pit supporting S-beam is equal to the distance from the uppermost transverse rebar hole to the upper edge of the foundation pit supporting beam section, and the spacing between vertically adjacent S-beam rebar holes is the same as the spacing between vertically adjacent transverse rebar holes.
[0011] Preferably, the diameters of the transverse reinforcing bar insertion holes, the longitudinal reinforcing bar insertion holes and the S-beam reinforcing bar insertion holes are the same.
[0012] Preferably, a first rope threading hole for rope saw cutting is provided on the crown beam, and the first rope threading hole is formed by an L-shaped PVC tube pre-buried in the crown beam, and both ends of the L-shaped PVC tube are open, one end opening is located on the side surface of the crown beam, and the other end opening is located on the top surface of the crown beam; a second rope threading hole for rope saw cutting is provided on the waist beam, and the second rope threading hole is formed by a straight PVC tube vertically pre-buried in the waist beam, and both ends of the straight PVC tube are open, one end opening is located on the top surface of the waist beam, and the other end opening is located on the bottom surface of the waist beam.
[0013] Preferably, the support platform is formed by welding No. 1 steel plate, No. 2 steel plate, No. 3 steel plate and No. 4 steel plate; the No. 1 steel plate and No. 2 steel plate (503) are rectangular in plan shape, the No. 3 steel plate and No. 4 steel plate are trapezoidal in plan shape, and a concave pillow for fixing a jack is welded on the No. 2 steel plate.
[0014] Preferably, the No. 1 steel plate used for welding the pedestal is embedded in the crown beam or waist beam, steel bars are welded on the No. 1 steel plate, the steel bars are perpendicular to the plate surface of the No. 1 steel plate, the embedded direction of the steel bars is perpendicular to the side of the crown beam or waist beam, and is fixed to the steel cage of the crown beam or waist beam with steel wire, the corbel is in the shape of a straight triangular prism, the corbel is arranged on the crown beam or waist beam, and a No. 1 steel plate is embedded in the position of the corbel.
[0015] Preferably, the branches of the steel lattice column are angle steels, and the tie materials are steel plates, on which a pallet is welded. The pallet consists of a panel and eight triangular steel plates. No tie materials are welded within a distance above the pallet that is not the first support and is the same height as the foundation pit support beam section, and four branch members in this range are reinforced with four angle steels; the first support is directly placed on the pallet at the top of the steel lattice column, and the non-first support is placed on the pallet after passing through the steel lattice column.
[0016] The construction method of the assembled reinforced concrete foundation pit support system which is easy to dismantle comprises the following steps: 10. The construction method of the easily dismantled assembled reinforced concrete foundation pit support system according to any one of claims 1 to 9 is characterized in that it comprises the following steps: 1) After the holes are drilled, support piles, column piles and steel lattice columns are formed; 2) After roughening the pile heads of the supporting piles, the steel bars of the crown beam are tied. While tying the steel bars, the first rope hole of the crown beam is pre-buried. The first rope hole is fixed with a steel wire. The first rope hole is set 2.5m-5m from the corner point of the foundation pit, and then another first rope hole is set every 2.5m-5m, and sealed with plaster. Subsequently, the steel bars are welded on the No. 1 steel plate, and the welded steel bars are fixed on the steel cage of the crown beam, while ensuring that the No. 1 steel plate fits the side of the crown beam. 3) Carry out formwork work for the crown beam and the corbels on the crown beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction; 4) Excavate to the bottom elevation of the first inner support beam; to facilitate welding of the tray on the steel lattice column, the steel lattice column position should be excavated at least 1 m deeper; to facilitate welding of the cap on the crown beam, the cap position should be excavated at least 1 m deeper; 5) Welding trays on steel lattice columns; 6) Use a crane to transport the foundation pit support beam section and the foundation pit support eight-shaped beam to the designed position, analyze the pressure borne by the horizontal foundation pit support beam section and the longitudinal foundation pit support beam section, first assemble the foundation pit support beam section and the foundation pit support eight-shaped beam in the middle position in the direction of greater pressure, and assemble the pair of supports from the middle to both ends; first install the foundation pit support beam section of the pair of supports located in the inner standard area, then assemble the non-standard area foundation pit support beam section of the pair of supports located in the non-standard area, then assemble the foundation pit support beam section of the pair of supports located in the outer standard area, and then assemble The pair of supports is located in the foundation pit support eight-shaped beam of the outer standard area. After the construction of the pair of supports is completed, the foundation pit support beam sections of the supports in the direction with less pressure on both sides are assembled, and then the two adjacent supports in the direction with greater pressure are assembled, and then the foundation pit support beam sections in the direction with less pressure on both sides are assembled, and the operation is repeated until the assembly construction of all the foundation pit support beam sections and the foundation pit support eight-shaped beams of the first inner support is completed, and the foundation pit support beam sections are placed on the pallet at all the beam-column nodes of the first inner support; 7) Use the No. 1 steel plate pre-buried on the crown beam or the corbel of the crown beam to weld the cap. The foundation pit support beam section at the edge and the foundation pit support eight-shaped beam are placed on the cap at one end. Place a jack on the concave pillow of the cap, and extend the jack to form the first internal support; 8) Excavate to the bottom elevation of the second inner support beam; to facilitate welding of the tray on the steel lattice column, the steel lattice column position should be excavated at least 1m deeper; to facilitate welding of the cap on the crown beam, the cap position should be excavated at least 1m deeper; 9) Welding trays on steel lattice columns; 10) Carry out roughening treatment on the supporting piles, tie the steel bars of the waist beam, and pre-embed the second rope hole. The second rope hole is fixed with steel wire. The second rope hole is set from 2.5m-5m away from the corner point of the foundation pit, and a second rope hole is set every 2.5m-5m, and sealed with gypsum; then, weld steel bars on the No. 1 steel plate, and fix these welded steel bars on the steel cage of the waist beam; 11) Carry out formwork work for the waist beam and the corbels on the waist beam, pour concrete after the formwork is completed, and carry out subsequent construction after the concrete curing is completed; 12) Use a crane to transport the foundation pit support beam section and the foundation pit support eight-shaped beam to the designed position, analyze the pressure borne by the horizontal foundation pit support beam section and the longitudinal foundation pit support beam section, first assemble the foundation pit support beam section and the foundation pit support eight-shaped beam in the middle position in the direction of greater pressure, assemble the pair of supports from the middle to both ends, first install the foundation pit support beam section in the inner standard area, then assemble the non-standard area foundation pit support beam section in the non-standard area, then assemble the foundation pit support beam section in the outer standard area, and then assemble the pair of supports. The pit support eight-shaped beams are located in the outer standard area. After the construction of the pair of supports is completed, the pit support beam sections on both sides of the support with less pressure are assembled, and then the two adjacent supports with greater pressure are assembled, and then the pit support beam sections on both sides of the support with less pressure are assembled. Repeat the operation until all the pit support beam sections and pit support eight-shaped beams of the second inner support are assembled and constructed. At all the beam-column nodes of the second inner support, the pit support beam sections pass through the steel lattice columns and are placed on the pallet; 13) Use the No. 1 steel plate pre-buried on the crown beam or the corbel of the crown beam to weld the cap. The foundation pit support beam section at the edge and the foundation pit support eight-shaped beam are placed on the cap at one end. Place a jack on the concave pillow of the cap, and extend the jack to form the second inner support; 14) Repeat the steps 8), 9), 10), 11), 12), and 13) to complete the construction of the remaining internal supports below the second internal support; 15) After the installation of the last support is completed, pour the foundation slab.
[0017] Compared with the prior art, the technical solution of this application has the following beneficial technical effects: (1) The present invention provides an assembled reinforced concrete foundation pit support system that is easy to dismantle, and adopts foundation pit support beam sections and foundation pit support cross-beams as support components for internal support, thereby eliminating the processes of steel cage binding and concrete curing for the internal support of the foundation pit, shortening the construction period of the internal support of the foundation pit, greatly saving time and labor costs, and reducing the cost of foundation pit support.
[0018] (2) The present invention divides the foundation pit into three parts: an outer standard area, a non-standard area, and an inner standard area, wherein the non-standard area may not exist, so that the present invention can adapt to foundation pits of different shapes, has broad application prospects, and good economic and social benefits.
[0019] (3) The present invention provides a construction method for an easy-to-dismantle assembled reinforced concrete foundation pit support system. The foundation pit support beam sections are connected to the foundation pit support eight-shaped beams and the foundation pit support beam sections are connected to the foundation pit support eight-shaped beams by inserting reinforcement. This not only greatly speeds up the construction speed of the foundation pit internal support, but also facilitates the subsequent dismantling of the internal support.
[0020] (4) The present invention uses foundation pit support beam sections and foundation pit support cross-shaped beams as support components for internal support. The components of the internal support are connected by dowel bars, which is very suitable for the occasion where the support only bears axial force. After use, the foundation pit support beam sections and foundation pit support cross-shaped beams can be completely recycled, which is a successful implementation of the green building concept in the field of foundation pit support. The foundation pit support beam sections and foundation pit support cross-shaped beams can be reused, which greatly reduces the single cost of the foundation pit internal support, and is a major breakthrough in the circular economy in foundation pit support.
[0021] (5) The cross-sectional dimensions of the foundation pit support beam sections and the foundation pit support cross-shaped beams of the present invention are the same, which realizes the standardization of the foundation pit support beam sections and the foundation pit support cross-shaped beams, making the foundation pit support beam sections and the foundation pit support cross-shaped beams not only convenient for transportation, assembly, and dismantling, but also better for reuse. The standardization can be within the scope of a foundation pit, a region, a province, or even the whole country. The larger the scope of standardization, the higher the economic and social benefits.
[0022] (6) The present invention adopts a full-life design concept, and pre-buries rope holes in the crown beam and waist beam of the foundation pit. During the rope saw cutting and removal process of the crown beam and waist beam of the foundation pit, drilling is avoided, which speeds up the removal of the crown beam and waist beam of the foundation pit, saves the removal cost, reduces labor costs, reduces carbon emissions, and implements the concept of green building.
[0023] (7) The present invention places a jack as a supporting medium between the inner support and the crown beam or the waist beam. The installation position of the jack provides sufficient gap for the assembly of beam sections, which is convenient for the beam sections to be assembled into a whole through the insertion of reinforcement. After the jack is lifted, the installation gap can be quickly eliminated, so that the support beam is quickly stressed. Adjusting multiple jacks together can make the stress and deformation of the support beam close to each other, avoiding excessive local stress and deformation, and achieving visualization of the support pressure. The pressure of the jack can be adjusted at any time, making the foundation pit support more reliable and controllable.
[0024] (8) The idea provided by the present invention will lead to the creation of a new leasing business, namely, the business of leasing foundation pit support beam sections and foundation pit support cross beams in a certain region or city; the present invention also provides more method options for foundation pit support design. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 Schematic diagram of standard-sized supports for prefabricated reinforced concrete foundation pit support systems for easy dismantling; Figure 2 Schematic diagram of the support of non-standard size for the prefabricated reinforced concrete foundation pit support system to facilitate dismantling; Figure 3 This is a schematic diagram of the reinforcement structure of the foundation pit support beam section; Figure 4 This is a schematic diagram of the reinforcement structure of the S-shaped beam supporting the foundation pit; Figure 5 The schematic diagram of the beam sleeve structure of the foundation pit supporting beam section; Figure 6 A schematic diagram of the structure of the splayed beam sleeve for supporting the splayed beam in the foundation pit; Figure 7 It is the overall structural diagram of the beam section in the non-standard area; Figure 8 This is a schematic diagram of the first support node structure; Fig. 9 This is a schematic diagram of the first supporting edge structure; Fig.10 This is a schematic diagram of the application of beam sections in non-standard areas; Fig.11 It is a schematic diagram of the lower support node structure; Fig.12 It is a schematic diagram of the lower support edge structure; Fig.13 This is a schematic diagram of the position of the crown beam cap; Fig.14 This is a schematic diagram of the position of the waist beam cap; Fig.15 This is a schematic diagram of the support plane layout in the foundation pit of Example 1; Fig.16This is a schematic diagram of the support plane layout in the foundation pit of Example 2; Fig.17 This is a schematic diagram of the support plane layout in the foundation pit of Example 3.
[0026] In the figure: 1. Foundation pit support beam section; 101. Longitudinal reinforcement hole; 102. Horizontal reinforcement hole; 103. Beam sleeve; 103-1. Side steel plate; 103-2. End steel plate; 2. Foundation pit support cross-beam; 201. Cross-reinforcement hole of cross-beam; 202. Cross-beam sleeve; 3-1. First rope hole; 3-2. Second rope hole; 4. Jack; 5. Cap; 501. No. 1 steel plate; 502 , steel bar; 503, No. 2 steel plate; 504, No. 3 steel plate; 505, No. 4 steel plate; 506, concave pillow; 6, waist beam; 7, corbel; 8, crown beam; 9, steel lattice column; 10, tray; 10-1, panel; 10-2, triangular steel plate; 11, non-standard area foundation pit support beam section; 12, connecting steel bar; 13, support pile; A, outer standard area; B, inner standard area; C, non-standard area. (The thick solid line in the figure is the area dividing line, which divides the support in the foundation pit into two parts: the outer standard area A and the inner standard area B, or divides the support in the foundation pit into three parts: the outer standard area A, the inner standard area B, and the non-standard area C.) DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention (the top support is the first support, and the second support, the third support, and the bottom support of the bottom layer are sequentially obtained).
[0028] In the embodiment, Figure 1-17 Provided is an assembled reinforced concrete foundation pit support system that is easy to dismantle, characterized in that the support system comprises an outer standard area A and an inner standard area B; the inner standard area is an orthogonal bracing system composed of a plurality of foundation pit support beam segments (1) of the same length and cross-sectional size; beam sleeves 103 are provided at both ends of the foundation pit support beam segment 1, side steel plates 105 are provided on the beam sleeves 103, transverse reinforcement holes 102 are provided on the side steel plates 105, and end face steel plates 104 are provided at both ends of the foundation pit support beam segment 1, and longitudinal reinforcement holes 101 are provided on the end face steel plates 104; When two foundation pit support beam segments 1 are axially connected, the end face steel plates 104 of the two foundation pit support beam segments 1 are seamlessly fitted, the longitudinal reinforcing bar holes 101 of the two foundation pit support beam segments 1 are aligned one by one, and there are connecting steel bars 12 in the longitudinal reinforcing bar holes 101; when four foundation pit support beam segments 1 are cross-connected or three foundation pit support beam segments 1 are T-connected, after two foundation pit support beam segments 1 are axially connected, they are vertically intersected with another one or two foundation pit support beam segments 1 at the axial connection, and at the vertical intersection, the longitudinal reinforcing bar holes 101 of one or two foundation pit support beam segments 1 are aligned one by one with the transverse reinforcing bar holes 102 at the axial connection of the two foundation pit support beam segments 1, and there are connecting steel bars 12 in the transverse reinforcing bar holes 102; The area where the support system contacts the crown beam 8 or the waist beam 6 is provided with a peripheral standard area, and the peripheral standard area includes N foundation pit support beam segments 1 perpendicular to the crown beam 8 and the waist beam 6 and the foundation pit support S-shaped beams 2 arranged on both sides thereof; The foundation pit supporting cross-beam 2 has the same length and cross-sectional size; one end is a right-angle end and the other end is an oblique end, the right-angle end is provided with a cross-beam sleeve 202, and the oblique end is provided with a cross-beam reinforcement hole 201; The connection between the foundation pit support beam section 1 and the foundation pit support eight-shaped beam 2 includes that after the two foundation pit support beam sections 1 are axially connected, they are butted with the beveled ends of the foundation pit support eight-shaped beam 2 at the axial connection, and the connection method is: the eight-shaped beam reinforcement holes 201 are aligned one by one with the transverse reinforcement holes 102 at the axial connection of the two foundation pit support beam sections 1, and there are connecting steel bars 12 in the transverse reinforcement holes 102; The outer standard area A and the inner standard area B are connected by a number of foundation pit support beam sections 1 of the same size arranged inside the outer standard area A or the inner standard area B, so that the outer standard area A and the inner standard area B can adapt to the corresponding foundation pit size.
[0029] When the outer standard area A and the inner standard area B are connected by several foundation pit support beam segments 1 with the same length and cross-sectional size and cannot adapt to the size of the foundation pit, a non-standard area C is set for connection. The non-standard area C includes a non-standard area foundation pit support beam segment 11 that is less than twice the length of the foundation pit support beam segment 1, or includes a non-standard area foundation pit support beam segment 11 that is less than twice the length of the foundation pit support beam segment 1 and a foundation pit support beam segment 1, so as to adapt to the corresponding foundation pit size. The other settings of the non-standard area foundation pit support beam segment 11 are the same as those of the standard area foundation pit support beam segment 1.
[0030] The crown beam 8 and the waist beam 6 are both provided with a pedestal 5 and a corbel 7; the foundation pit supporting beam section 1 of the outer standard area is placed on the pedestal 5 fixed on the crown beam 8 or the waist beam 6; and the foundation pit supporting S-beam 2 of the outer standard area is placed on the pedestal 5 fixed on the corbel 7; a jack 4 is provided on the pedestal 5 for lifting and supporting the foundation pit supporting beam section 1 or the foundation pit supporting S-beam 2; a pallet 10 is provided below the connection of the foundation pit supporting beam section 1, and the pallet 10 is welded to the steel lattice column 9.
[0031] The longitudinal rebar insertion holes 101 are in two rows, and the transverse rebar insertion holes 102 are in one row; the distance between the two rows of longitudinal rebar insertion holes 101 is equal to twice the distance between the transverse rebar insertion holes 102 and the end steel plate 104, the vertical spacing of adjacent longitudinal rebar insertion holes 101 or transverse rebar insertion holes 102 is the same, the distance between the uppermost longitudinal rebar insertion hole 101 and the upper edge of the beam sleeve 103 is equal to the distance between the lowermost transverse rebar insertion hole 102 and the lower edge of the beam sleeve 103, the spacing between the two rows of S-shaped beam rebar insertion holes 201 is equal to twice the distance between the transverse rebar insertion holes 102 and the end steel plate 104 of the foundation pit supporting beam section 1, the distance from the uppermost S-shaped beam rebar insertion hole 201 to the upper edge of the foundation pit supporting S-shaped beam 2 is equal to the distance from the uppermost transverse rebar insertion hole 102 to the upper edge of the foundation pit supporting beam section 1, and the spacing between vertically adjacent S-shaped beam rebar insertion holes 201 is the same as the spacing between vertically adjacent transverse rebar insertion holes 102.
[0032] The diameters of the transverse reinforcing bar insertion holes 102, the longitudinal reinforcing bar insertion holes 101 and the cross-beam reinforcing bar insertion holes 201 are the same.
[0033] The crown beam 8 is provided with a first rope threading hole 3-1 for rope saw cutting. The first rope threading hole 3-1 is formed by an L-shaped PVC pipe pre-buried in the crown beam 8. Both ends of the L-shaped PVC pipe are open, one end is located on the side of the crown beam 8, and the other end is located on the top surface of the crown beam 8; the waist beam 6 is provided with a second rope threading hole 3-2 for rope saw cutting. The second rope threading hole 3-2 is formed by a straight PVC pipe vertically pre-buried in the waist beam 6. Both ends of the straight PVC pipe are open, one end is located on the top surface of the waist beam 6, and the other end is located on the bottom surface of the waist beam 6. The straight PVC pipe is pre-buried on the side of the waist beam 6 close to the supporting pile 13.
[0034] The base 5 is formed by welding No. 1 steel plate 501, No. 2 steel plate 503, No. 3 steel plate 504, and No. 4 steel plate 505. The planar shapes of No. 1 steel plate 501 and No. 2 steel plate 503 are rectangular, the planar shapes of No. 3 steel plate 504 and No. 4 steel plate 505 are trapezoidal, and a concave pillow 506 for fixing the jack 4 is welded on No. 2 steel plate 503.
[0035] The No. 1 steel plate 501 used for welding the base 5 is embedded in the crown beam 8 or the waist beam 6, and the steel bar 502 is welded on the No. 1 steel plate 501. The steel bar 502 is perpendicular to the plate surface of the No. 1 steel plate 501. The embedded direction of the steel bar 502 is perpendicular to the side of the crown beam 8 or the waist beam 6, and is fixed to the steel cage of the crown beam 8 or the waist beam 6 with steel wire. The corbel 7 is in the shape of a straight triangular prism, and the corbel 7 is arranged on the crown beam 8 or the waist beam 6. The No. 1 steel plate 501 is embedded in the position of the corbel 7.
[0036] The branches of the steel lattice column 9 are angle steels, and the tie materials are steel plates, on which a pallet 10 is welded. The pallet 10 is composed of a panel 10-1 and eight triangular steel plates 10-2. No tie materials are welded within a distance at the same height as the foundation pit support beam section 1 above the pallet that is not the first support, and angle steels are used for reinforcement. The foundation pit support beam section 1 of the first support is directly placed on the pallet 10 welded to the steel lattice column 9, and the foundation pit support beam section 1 of the non-first support passes through the steel lattice column 9 and is placed on the pallet 10 welded to the steel lattice column 9.
[0037] The construction method of the assembled reinforced concrete foundation pit support system which is easy to dismantle comprises the following steps: 1) After the holes are drilled, support piles 13, column piles, and steel lattice columns 9 are formed; 2) After the pile heads of the support piles 13 are roughened, the steel bars of the crown beam 8 are tied; while tying the steel bars, the first rope threading hole 3-1 of the crown beam 8 is pre-buried, the first rope threading hole 3-1 is fixed by a steel wire, and the first rope threading hole 3-1 is set 2.5 m-5 m from the corner point of the foundation pit, and then another first rope threading hole 3-1 is set every 2.5 m-5 m, and sealed with plaster; then, the steel bars 502 are welded on the No. 1 steel plate 501, and the welded steel bars 502 are fixed on the steel cage of the crown beam 8, while ensuring that the No. 1 steel plate 501 fits the side of the crown beam 8; 3) Carry out formwork work for the crown beam 8 and the corbel 7 on the crown beam 8. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction; 4) Excavate to the bottom elevation of the first inner support beam; to facilitate welding of the tray 10 on the steel lattice column 9, the steel lattice column 9 is excavated at least 1 m deeper; to facilitate welding of the cap 5 on the crown beam 8, the cap 5 is excavated at least 1 m deeper; 5) Welding the tray 10 onto the steel lattice column 9; 6) Use a crane to transport the foundation pit support beam section 1 and the foundation pit support cross-beam 2 to the designed position, analyze the pressure borne by the horizontal foundation pit support beam section 1 and the longitudinal foundation pit support beam section 1, first assemble the foundation pit support beam section 1 and the foundation pit support cross-beam 2 of the middle position of the brace in the direction of greater pressure, and assemble the brace from the middle to both ends; first install the foundation pit support beam section 1 of the pair of braces located in the internal standard area A, then assemble the non-standard area foundation pit support beam section 11 of the pair of braces located in the non-standard area C, and then assemble the foundation pit support beam section 1 of the pair of braces located in the outer standard area B, and then Assemble the pit support S-shaped beam 2 of the pair of supports located in the outer standard area B. After the construction of the pair of supports is completed, assemble the pit support beam segments 1 on both sides of the support in the direction of less pressure, and then assemble the two adjacent supports in the direction of greater pressure, and then assemble the pit support beam segments 1 on both sides of the support in the direction of less pressure, and repeat the operation until the assembly construction of all the pit support beam segments 1 and the pit support S-shaped beam 2 of the first inner support is completed, and the pit support beam segments 1 are placed on the pallet 10 at all the beam-column nodes of the first inner support; 7) Use the No. 1 steel plate pre-buried on the crown beam 8 or the corbel 7 of the crown beam 8 to weld the cap 5, the foundation pit support beam section 1 at the edge and the foundation pit support cross-shaped beam 2 are both placed on the cap 5 at one end, and the jack 4 is placed on the concave pillow 506 of the cap 5, and the jack 4 is extended to form the first inner support; 8) Excavate to the bottom elevation of the second inner support beam; to facilitate welding of the tray 10 on the steel lattice column 9, the steel lattice column 9 is excavated at least 1m deeper; to facilitate welding of the cap 5 on the crown beam 8, the cap 5 is excavated at least 1m deeper; 9) Welding the tray 10 on the steel lattice column 9; 10) Perform roughening treatment on the support pile 13, perform steel bar binding work on the waist beam 6, perform pre-embedding work on the second rope threading hole 3-2, the second rope threading hole 3-2 is fixed by a steel wire, and the second rope threading hole 3-2 is set from 2.5 m to 5 m away from the corner point of the foundation pit, and a second rope threading hole 3-2 is set every 2.5 m to 5 m, and sealed with gypsum; then, weld steel bars 502 on the No. 1 steel plate 501, and fix these welded steel bars 502 on the steel cage of the waist beam 6; 11) Carry out formwork work for the waist beam 6 and the corbel 7 on the waist beam 6, pour concrete after the formwork is completed, and carry out subsequent construction after the concrete curing is completed; 12) Use a crane to transport the foundation pit support beam section 1 and the foundation pit support cross-beam 2 to the designed position, analyze the pressure borne by the horizontal foundation pit support beam section 1 and the longitudinal foundation pit support beam section 1, first assemble the foundation pit support beam section 1 and the foundation pit support cross-beam 2 of the middle position of the brace in the direction of greater pressure, and assemble the brace from the middle to both ends, first install the foundation pit support beam section of the pair of braces located in the inner standard area A, then assemble the non-standard area foundation pit support beam section 11 of the pair of braces located in the non-standard area C, and then assemble the foundation pit support beam section 1 of the pair of braces located in the outer standard area B, and then assemble the After the construction of the pit support S-shaped beam 2 located in the outer standard area B is completed, the pit support beam segments 1 on both sides of the pit support in the direction with less pressure are assembled, and then the two adjacent supports in the direction with greater pressure are assembled, and then the pit support beam segments 1 on both sides of the pit support in the direction with less pressure are assembled, and the operation is repeated until the assembly construction of all the pit support beam segments 1 and the pit support S-shaped beam 2 of the second inner support is completed. At all the beam-column nodes of the second inner support, the pit support beam segments 1 pass through the steel lattice columns 9 and are placed on the pallet 10; 13) The cap 5 is welded by using the No. 1 steel plate 501 pre-buried on the crown beam 8 or the corbel 7 of the crown beam 8. The foundation pit support beam section 1 and the foundation pit support cross beam 2 at the edge are both placed on the cap 5 at one end. The jack 4 is placed on the concave pillow 506 of the cap 5, and the jack 4 is extended to form the second inner support; 14) Repeat the steps 8), 9), 10), 11), 12), and 13) to complete the construction of the remaining internal supports below the second internal support; 15) After the installation of the last support is completed, pour the foundation slab.
[0038] Embodiment 1: like Fig.15 As shown in the figure, a rectangular foundation pit has a size of 148 m long and 80 m wide. The internal support is arranged in a tic-tac-toe pattern, with 4 horizontal braces and 8 vertical braces. The designed internal support of the foundation pit is 4 layers. The sizes of the foundation pit support beam sections are all the same, with a cross-sectional size of 1000 mm wide and 800 mm high. The length of the foundation pit support beam section is 5000 mm. The sizes of the foundation pit support S-shaped beams are all the same, with a cross-sectional size of 1000 mm wide and 800 mm high. The angle of the bevel end is 45° and the length is 6.98 m.
[0039] 1) The designed diameter of the supporting pile is 1.5 m, and the diameter of the column pile is 1.8 m. The supporting piles and column piles are bored by rotary drilling. The rotary drilling piles are bored by mud wall protection. In order to avoid the collapse of the top of the pile hole, a long steel casing is set on the upper part. The steel cage of the supporting pile is transported to the pile hole by a truck crane and a crawler crane. The steel cage is lowered by the crawler crane, and the guide tube is installed to cast concrete. According to the segmentation of the casing, the casing is pulled out while pouring. When the guide tube is lifted, it vibrates up and down to make the concrete dense. The columns are angle steel lattice columns, the branches of the steel lattice columns are L75×8 angle steel, the tie materials are 1 cm thick No. 45 steel, the cross-sectional dimensions of the steel lattice columns are length × width of 1.2 m × 1.2 m, and no steel plates are set at the intersection of the lower supports of the steel lattice columns within a height range of 80 cm. After the steel lattice columns and the column pile reinforcement cages are welded and fixed, they are lowered to the designed elevation. The steel lattice column piles are grouted with conduit and filled with soil after grouting. Multiple rotary pile drivers can be used for simultaneous construction until the support piles and column piles are all completed.
[0040] 2) The cross-sectional dimensions of the crown beam are 1.2 m × 1 m in width × height. The pile heads of the supporting piles are roughened. After the roughening is completed, the crown beam reinforcement cage is tied. An L-shaped PVC plastic pipe with a diameter of 20 mm is embedded in the crown beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. When embedding, the PVC pipe is sealed with gypsum and embedded vertically near the outer edge of the crown beam. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. A HRB400 steel bar with a diameter of 20 mm is welded on one side of the No. 1 steel plate. According to the internal support design drawing, the steel plate is placed in the correct position. The No. 1 steel plate is close to the inner edge of the crown beam. The No. 1 steel bar welded on the No. 1 steel plate is tied to the reinforcement cage of the crown beam with steel wire.
[0041] 3) Carry out formwork work for the crown beam and the corbels on the crown beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0042] 4) Excavate to the bottom elevation of the first inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0043] 5) According to the bottom elevation of the first support, a pallet is welded on the steel lattice column. A 2 cm thick Q390 steel plate is welded on the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded on the panel and the other right-angle side is welded on the steel lattice column.
[0044] 6) Complete the prefabrication of foundation pit support beam sections and foundation pit cross-beams in the factory, and transport them to the site for installation after prefabrication; use a crane to transport the foundation pit support beam sections and foundation pit support cross-beams to the designed position, and use inserted reinforcement to connect the supporting components; first assemble the foundation pit support beam sections and foundation pit support cross-beams of the middle longitudinal braces, and after the construction of the longitudinal braces is completed, assemble the foundation pit support beam sections of the transverse braces on both sides, and then assemble the two adjacent longitudinal braces of the longitudinal brace, and then assemble the foundation pit support beam sections of the transverse braces on both sides, and repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the first inner support is completed.
[0045] 7) After all the foundation pit supporting beam sections and foundation pit supporting S-beams are installed, the pedestal is welded at the embedded steel plate of the crown beam. The pedestal bottom plate, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the pedestal are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the pedestal bottom plate to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The supporting beam sections and S-beams at the edge are placed on the pedestal at one end, and the YDC4600 jack is placed on the pedestal. The jack is extended to complete the first support.
[0046] 8) Excavate to the bottom elevation of the second inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0047] 9) According to the bottom elevation of the second support, a 2 cm thick Q390 steel plate is welded to the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded to the panel and the other right-angle side is welded to the steel lattice column.
[0048] 10) The cross-sectional dimensions of the waist beam are 1 m × 1 m in width × height. The underground continuous wall is roughened. After the roughening is completed, the waist beam reinforcement cage is tied. A straight PVC plastic pipe with a diameter of 20 mm is embedded in the waist beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. The PVC pipe is sealed with gypsum during embedding. It is vertically embedded in the waist beam near the underground continuous wall. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. One side of the No. 1 steel plate is welded with a HRB400 steel bar with a diameter of 20 mm. According to the internal support design drawing, the steel plate is placed in the correct position, the steel plate is close to the inner edge of the waist beam, and the steel bars welded on the steel plate are tied to the steel cage of the waist beam with steel wire.
[0049] 11) Carry out formwork work on the waist beam and the corbels on the waist beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0050] 12) Use a crane to transport the foundation pit support beam sections and foundation pit support cross-beams to the designed position, and use inserted bars to connect the support components; first assemble the foundation pit support beam sections and foundation pit support cross-beams of the middle longitudinal brace. After the construction of the longitudinal brace is completed, assemble the foundation pit support beam sections of the transverse braces on both sides, and then assemble the two adjacent longitudinal braces of the longitudinal brace. Then assemble the foundation pit support beam sections of the transverse braces on both sides. Repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the second inner support is completed.
[0051] 13) After all the foundation pit support beam sections and foundation pit support S-beams of the second support are installed, the cap is welded at the embedded No. 1 steel plate of the waist beam. The base plate of the cap, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the cap are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the base plate to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The support beam sections and S-beams at the edge are placed on the cap at one end, and the YDC4600 jack is placed on the cap. The jack is extended to complete the second support.
[0052] 14) Repeat steps 8), 9), 10), 11), 12), and 13) to complete the installation of the third and fourth supports.
[0053] 15) After the fourth support is installed, pour the foundation slab.
[0054] Example 2 like Fig.16 As shown in the figure, a rectangular foundation pit has a size of 146 m long and 78 m wide. The internal support is arranged in a tic-tac-toe pattern, with 4 horizontal braces and 8 vertical braces. The designed internal support of the foundation pit is 4 layers. The sizes of the foundation pit support beam sections are all the same. The cross-sectional dimensions of the foundation pit support beam sections in the standard area are 1000 mm wide and 800 mm high, and the length of the foundation pit support beam sections is 5000 mm. The sizes of the foundation pit support S-shaped beams are all the same. The cross-sectional dimensions of the foundation pit support S-shaped beams are 1000 mm wide and 800 mm high, the angle of the bevel end is 45°, and the length is 6.98 m. There are two rows of longitudinally parallel non-standard area beam sections and two rows of transversely parallel non-standard area beam sections. The cross-sectional dimensions of the non-standard area beam sections are 1000 mm wide and 800 mm high, and the length of the foundation pit support beam sections is 4000 mm.
[0055] 1) The designed diameter of the supporting pile is 1.5 m, and the diameter of the column pile is 1.8 m. The supporting piles and column piles are bored by rotary drilling. The rotary drilling piles are bored by mud wall protection. In order to avoid the collapse of the top of the pile hole, a long steel casing is set on the upper part. The steel cage of the supporting pile is transported to the pile hole by a truck crane and a crawler crane. The steel cage is lowered by the crawler crane, and the guide tube is installed to cast concrete. According to the segmentation of the casing, the casing is pulled out while pouring. When the guide tube is lifted, it vibrates up and down to make the concrete dense. The columns are angle steel lattice columns, the branches of the steel lattice columns are L75×8 angle steel, the tie materials are 1 cm thick No. 45 steel, the cross-sectional dimensions of the steel lattice columns are length × width of 1.2 m × 1.2 m, and no steel plates are set at the intersection of the lower supports of the steel lattice columns within a height range of 80 cm. After the steel lattice columns and the column pile reinforcement cages are welded and fixed, they are lowered to the designed elevation. The steel lattice column piles are grouted with conduit and filled with soil after grouting. Multiple rotary pile drivers can be used for simultaneous construction until the support piles and column piles are all completed.
[0056] 2) The cross-sectional dimensions of the crown beam are 1.2 m × 1 m in width × height. The pile heads of the supporting piles are roughened. After the roughening is completed, the crown beam reinforcement cage is tied. An L-shaped PVC plastic pipe with a diameter of 20 mm is embedded in the crown beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. When embedding, the PVC pipe is sealed with gypsum and embedded vertically near the outer edge of the crown beam. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. A HRB400 steel bar with a diameter of 20 mm is welded on one side of the No. 1 steel plate. According to the internal support design drawing, the steel plate is placed in the correct position. The No. 1 steel plate is close to the inner edge of the crown beam. The No. 1 steel bar welded on the No. 1 steel plate is tied to the reinforcement cage of the crown beam with steel wire.
[0057] 3) Carry out formwork work for the crown beam and the corbels on the crown beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0058] 4) Excavate to the bottom elevation of the first inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0059] 5) According to the bottom elevation of the first support, a pallet is welded on the steel lattice column. A 2 cm thick Q390 steel plate is welded on the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded on the panel and the other right-angle side is welded on the steel lattice column.
[0060] 6) Complete the prefabrication of foundation pit support beam sections, foundation pit cross-beams and non-standard area beam sections in the factory, and transport them to the site for installation after prefabrication; use a crane to transport the foundation pit support beam sections and foundation pit support cross-beams to the designed position, and use inserted reinforcement to connect the supporting components; first assemble the foundation pit support beam sections and foundation pit support cross-beams of the middle longitudinal braces, and after the construction of the longitudinal braces is completed, assemble the foundation pit support beam sections of the transverse braces on both sides, and then assemble the two adjacent longitudinal braces to the longitudinal brace, and then assemble the foundation pit support beam sections of the transverse braces on both sides, and repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the first inner support is completed.
[0061] 7) After all the foundation pit supporting beam sections, foundation pit supporting S-beams and non-standard area beam sections are installed, the cap is welded at the embedded steel plate of the crown beam. The base plate of the cap, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the cap are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the base plate to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The supporting beam sections and S-beams at the edge are placed on the cap at one end, and the YDC4600 jack is placed on the cap. The jack is extended to complete the first support.
[0062] 8) Excavate to the bottom elevation of the second inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0063] 9) According to the bottom elevation of the second support, a 2 cm thick Q390 steel plate is welded to the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded to the panel and the other right-angle side is welded to the steel lattice column.
[0064] 10) The cross-sectional dimensions of the waist beam are 1 m × 1 m in width × height. The underground continuous wall is roughened. After the roughening is completed, the waist beam reinforcement cage is tied. A straight PVC plastic pipe with a diameter of 20 mm is embedded in the waist beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. The PVC pipe is sealed with gypsum during embedding. It is vertically embedded in the waist beam near the underground continuous wall. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. One side of the No. 1 steel plate is welded with a HRB400 steel bar with a diameter of 20 mm. According to the internal support design drawing, the steel plate is placed in the correct position, the steel plate is close to the inner edge of the waist beam, and the steel bars welded on the steel plate are tied to the steel cage of the waist beam with steel wire.
[0065] 11) Carry out formwork work on the waist beam and the corbels on the waist beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0066] 12) Use a crane to transport the foundation pit support beam section, foundation pit support eight-shaped beam, and non-standard area beam section to the designed position, and use inserted reinforcement to connect the support components; first assemble the foundation pit support beam section and the foundation pit support eight-shaped beam of the middle longitudinal brace. After the construction of the longitudinal brace is completed, assemble the foundation pit support beam section of the transverse brace on both sides, and then assemble the two adjacent longitudinal braces of the longitudinal brace, and then assemble the foundation pit support beam section of the transverse brace on both sides. Repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the second inner support is completed.
[0067] 13) After all the foundation pit support beam sections, foundation pit support S-beams and non-standard area beam sections of the second support are installed, the pedestal is welded at the embedded No. 1 steel plate of the waist beam. The bottom plate of the pedestal, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the pedestal are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the bottom plate of the pedestal to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The support beam sections and S-beams at the edge are placed on the pedestal at one end. The YDC4600 jack is placed on the pedestal, and the jack is extended to complete the second support.
[0068] 14) Repeat steps 8), 9), 10), 11), 12), and 13) to complete the installation of the third and fourth supports.
[0069] 15) After the fourth support is installed, pour the foundation slab.
[0070] Example 3 like Fig.17As shown in the figure, an L-shaped foundation pit has an upper length of 163 m, an upper length of 79 m on the left, a lower length of 40 m on the left, a right length of 119 m, a lower length of 106 m on the left, and a lower length of 57 m on the right. The inner support of the foundation pit is arranged in a tic-tac-toe pattern, with 6 horizontal braces and 9 vertical braces. The designed inner support of the foundation pit is 3 layers. The dimensions of the foundation pit support beam sections are all the same. The cross-sectional dimensions of the foundation pit support beam sections in the standard area are 1000 mm wide and 800 mm high, and the length of the foundation pit support beam sections is 5000 mm. The dimensions of the foundation pit support eight-shaped beams are all the same. The cross-sectional dimensions of the foundation pit support eight-shaped beams are 1000 mm wide and 800 mm high, the angle of the bevel end is 45°, and the length is 6.98 m. There is a row of horizontally parallel non-standard area beam sections. The cross-sectional dimensions of the non-standard area beam sections are 1000 mm wide and 800 mm high, and the length of the foundation pit support beam sections is 3000 mm.
[0071] 1) The designed diameter of the supporting pile is 1.5 m, and the diameter of the column pile is 1.8 m. The supporting piles and column piles are bored by rotary drilling. The rotary drilling piles are bored by mud wall protection. In order to avoid the collapse of the top of the pile hole, a long steel casing is set on the upper part. The steel cage of the supporting pile is transported to the pile hole by a truck crane and a crawler crane. The steel cage is lowered by the crawler crane, and the guide tube is installed to cast concrete. According to the segmentation of the casing, the casing is pulled out while pouring. When the guide tube is lifted, it vibrates up and down to make the concrete dense. The columns are angle steel lattice columns, the branches of the steel lattice columns are L75×8 angle steel, the tie materials are 1 cm thick No. 45 steel, the cross-sectional dimensions of the steel lattice columns are length × width of 1.2 m × 1.2 m, and no steel plates are set at the intersection of the lower supports of the steel lattice columns within a height range of 80 cm. After the steel lattice columns and the column pile reinforcement cages are welded and fixed, they are lowered to the designed elevation. The steel lattice column piles are grouted with conduit and filled with soil after grouting. Multiple rotary pile drivers can be used for simultaneous construction until the support piles and column piles are all completed.
[0072] 2) The cross-sectional dimensions of the crown beam are 1.2 m × 1 m in width × height. The pile heads of the supporting piles are roughened. After the roughening is completed, the crown beam reinforcement cage is tied. An L-shaped PVC plastic pipe with a diameter of 20 mm is embedded in the crown beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. When embedding, the PVC pipe is sealed with gypsum and embedded vertically near the outer edge of the crown beam. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. A HRB400 steel bar with a diameter of 20 mm is welded on one side of the No. 1 steel plate. According to the internal support design drawing, the steel plate is placed in the correct position. The No. 1 steel plate is close to the inner edge of the crown beam. The No. 1 steel bar welded on the No. 1 steel plate is tied to the reinforcement cage of the crown beam with steel wire.
[0073] 3) Carry out formwork work for the crown beam and the corbels on the crown beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0074] 4) Excavate to the bottom elevation of the first inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0075] 5) According to the bottom elevation of the first support, a pallet is welded on the steel lattice column. A 2 cm thick Q390 steel plate is welded on the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded on the panel and the other right-angle side is welded on the steel lattice column.
[0076] 6) Complete the prefabrication of foundation pit support beam sections, foundation pit cross-beams and non-standard area beam sections in the factory, and transport them to the site for installation after prefabrication; use a crane to transport the foundation pit support beam sections and foundation pit support cross-beams to the designed position, and use inserted reinforcement to connect the supporting components; first assemble the foundation pit support beam sections and foundation pit support cross-beams of the middle longitudinal braces, and after the construction of the longitudinal braces is completed, assemble the foundation pit support beam sections of the transverse braces on both sides, and then assemble the two adjacent longitudinal braces to the longitudinal brace, and then assemble the foundation pit support beam sections of the transverse braces on both sides, and repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the first inner support is completed.
[0077] 7) After all the foundation pit supporting beam sections, foundation pit supporting S-beams and non-standard area beam sections are installed, the cap is welded at the embedded steel plate of the crown beam. The base plate of the cap, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the cap are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the base plate to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The supporting beam sections and S-beams at the edge are placed on the cap at one end, and the YDC4600 jack is placed on the cap. The jack is extended to complete the first support.
[0078] 8) Excavate to the bottom elevation of the second inner support; to facilitate welding of the tray on the steel lattice column, excavate 1 m deeper at the steel lattice column; to facilitate welding of the pedestal on the crown beam, excavate 1 m deeper at the pedestal.
[0079] 9) According to the bottom elevation of the second support, a 2 cm thick Q390 steel plate is welded to the steel lattice column to form a pallet panel with a plane size of 1.5 m × 1.5 m. Eight 2 cm thick Q390 isosceles right-angle steel plates are selected, and the length of their right-angle sides is 30 cm. One right-angle side is welded to the panel and the other right-angle side is welded to the steel lattice column.
[0080] 10) The cross-sectional dimensions of the waist beam are 1 m × 1 m in width × height. The underground continuous wall is roughened. After the roughening is completed, the waist beam reinforcement cage is tied. A straight PVC plastic pipe with a diameter of 20 mm is embedded in the waist beam as a rope threading hole for subsequent demolition. One pipe is embedded every 3 m. The PVC pipe is sealed with gypsum during embedding. It is vertically embedded in the waist beam near the underground continuous wall. The No. 1 steel plate is a Q390 steel plate with a length of 1 m, a height of 1 m and a thickness of 2 cm. One side of the No. 1 steel plate is welded with a HRB400 steel bar with a diameter of 20 mm. According to the internal support design drawing, the steel plate is placed in the correct position, the steel plate is close to the inner edge of the waist beam, and the steel bars welded on the steel plate are tied to the steel cage of the waist beam with steel wire.
[0081] 11) Carry out formwork work on the waist beam and the corbels on the waist beam. After the formwork is completed, pour concrete. After the concrete is cured, carry out subsequent construction.
[0082] 12) Use a crane to transport the foundation pit support beam section, foundation pit support eight-shaped beam, and non-standard area beam section to the designed position, and use inserted reinforcement to connect the support components; first assemble the foundation pit support beam section and the foundation pit support eight-shaped beam of the middle longitudinal brace. After the construction of the longitudinal brace is completed, assemble the foundation pit support beam section of the transverse brace on both sides, and then assemble the two adjacent longitudinal braces of the longitudinal brace, and then assemble the foundation pit support beam section of the transverse brace on both sides. Repeat the operation until the construction of the 4 transverse braces and 8 longitudinal braces of the second inner support is completed.
[0083] 13) After all the foundation pit support beam sections, foundation pit support S-beams and non-standard area beam sections of the second support are installed, the pedestal is welded at the embedded No. 1 steel plate of the waist beam. The bottom plate of the pedestal, i.e. the No. 2 steel plate, is made of Q390 rectangular steel plate with a thickness of 2 cm, a length of 2 m and a width of 1 m, which is welded on the embedded No. 1 steel plate. The No. 3 and No. 4 steel plates of the pedestal are made of Q390 steel plates with a thickness of 2 cm and a width of 20 cm. One end is welded to the No. 1 steel plate and the other end is welded to the No. 2 steel plate. Finally, a jack is welded on the bottom plate of the pedestal to fix the concave pillow. The steel thickness of the concave pillow is 1 cm, and the steel material is No. 45 steel. The support beam sections and S-beams at the edge are placed on the pedestal at one end. The YDC4600 jack is placed on the pedestal, and the jack is extended to complete the second support.
[0084] 14) Repeat steps 8), 9), 10), 11), 12), and 13) to complete the installation of the third support.
[0085] 15) After the third support is installed, pour the foundation slab.
[0086] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements. Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. The prefabricated reinforced concrete foundation pit support system that is easy to dismantle is characterized by: The support system comprises an outer standard area (A) and an inner standard area (B); the inner standard area is an orthogonal bracing system composed of a plurality of foundation pit support beam sections (1) of the same length and cross-sectional size; a beam sleeve (103) is provided on the surface of the foundation pit support beam section (1); a side steel plate (103-1) is provided on the beam sleeve (103); the pipe walls at both ends of a preset transverse pre-buried pipe are respectively welded to the hole walls of the side steel plates (103-1) on both sides to form transverse reinforcement holes (102); an end steel plate (103-2) is provided on the beam sleeve (103); the pipe wall at one end of a preset longitudinal pre-buried pipe is welded to the inner wall of the hole of the end steel plate (103-2) to form a longitudinal reinforcement hole (101); When two foundation pit support beam segments (1) are axially connected, the end steel plates (103-2) of the two foundation pit support beam segments (1) are seamlessly attached, the longitudinal reinforcement holes (101) of the two foundation pit support beam segments (1) are aligned one by one, and the longitudinal reinforcement holes (101) contain connecting steel bars (12); when four foundation pit support beam segments (1) are connected in a cross shape or three foundation pit support beam segments (1) are connected in a T shape, after the two foundation pit support beam segments (1) are axially connected, they are vertically connected with another one or two foundation pit support beam segments (1) at the axial connection, and at the vertical intersection, the longitudinal reinforcement holes (101) of one or two foundation pit support beam segments (1) are aligned one by one with the transverse reinforcement holes (102) at the axial connection of the two foundation pit support beam segments (1), and the transverse reinforcement holes (102) contain connecting steel bars (12); An outer standard area is set in the area where the support system contacts the crown beam (8) or the waist beam (6), and the outer standard area includes N foundation pit support beam sections (1) perpendicular to the crown beam (8) and the waist beam (6) and foundation pit support crossbeams (2) arranged on both sides thereof; The foundation pit supporting cross-shaped beam (2) has the same length and cross-sectional dimensions; one end is a right-angle end and the other end is an oblique-angle end; the surface of the foundation pit supporting cross-shaped beam (2) is provided with a cross-shaped beam sleeve (202), and the oblique-angle end is provided with a cross-shaped beam reinforcement hole (201); The connection between the foundation pit support beam section (1) and the foundation pit support cross-beam (2) comprises that after the two foundation pit support beam sections (1) are axially connected, they are butted with the beveled ends of the foundation pit support cross-beam (2) at the axial connection, and the connection method is as follows: the cross-beam reinforcement holes (201) are aligned one by one with the transverse reinforcement holes (102) at the axial connection of the two foundation pit support beam sections (1), and connecting steel bars (12) are arranged in the transverse reinforcement holes (102); The outer standard area (A) and the inner standard area (B) are connected by a plurality of foundation pit support beam sections (1) of the same size arranged inside the outer standard area (A) or the inner standard area (B); so that the outer standard area (A) and the inner standard area (B) are adapted to the corresponding foundation pit size.
2. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: When the outer standard area (A) and the inner standard area (B) are connected by a plurality of foundation pit support beam segments (1) of the same length and cross-sectional size and cannot adapt to the size of the foundation pit, a non-standard area (C) is set for connection. The non-standard area (C) includes a non-standard area foundation pit support beam segment (11) less than twice the length of the foundation pit support beam segment (1), or includes a non-standard area foundation pit support beam segment (11) less than twice the length of the foundation pit support beam segment (1) and a foundation pit support beam segment (1) to adapt to the corresponding foundation pit size. The other settings of the non-standard area foundation pit support beam segment (11) are the same as those of the standard area foundation pit support beam segment (1).
3. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The crown beam (8) and the waist beam (6) are both provided with a cap (5) and a corbel (7); the foundation pit support beam section (1) of the outer standard area is placed on the cap (5) fixed to the crown beam (8) or the waist beam (6); and the foundation pit support cross-beam (2) of the outer standard area is placed on the cap (5) fixed to the corbel (7); a jack (4) is provided on the cap (5) for lifting and supporting the foundation pit support beam section (1) or the foundation pit support cross-beam (2); a tray (10) is provided below the connection of the foundation pit support beam section (1), and the tray (10) is welded to the steel lattice column (9).
4. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The longitudinal reinforcement holes (101) are in two rows, and the transverse reinforcement holes (102) are in one row; the distance between the two rows of longitudinal reinforcement holes (101) is equal to twice the distance between the transverse reinforcement holes (102) and the end steel plate (103-2); the vertical spacing between adjacent longitudinal reinforcement holes (101) or transverse reinforcement holes (102) is the same; the distance between the uppermost longitudinal reinforcement hole (101) and the upper edge of the beam sleeve (103) is equal to the distance between the lowermost transverse reinforcement hole (102) and the lower edge of the beam sleeve (103); The spacing between the two rows of the bar insertion holes (201) of the eight-shaped beams is equal to twice the distance between the transverse bar insertion holes (102) and the end surface steel plate (103-2) of the foundation pit support beam section (1), the distance between the uppermost bar insertion hole (201) of the eight-shaped beam and the upper edge of the foundation pit support eight-shaped beam (2) is equal to the distance between the uppermost transverse bar insertion hole (102) and the upper edge of the foundation pit support beam section (1), and the spacing between the vertically adjacent bar insertion holes (201) and the vertically adjacent transverse bar insertion holes (102) are the same.
5. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The diameters of the transverse reinforcement insertion holes (102), the longitudinal reinforcement insertion holes (101) and the cross-beam reinforcement insertion holes (201) are the same.
6. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The crown beam (8) is provided with a first rope threading hole (3-1) for rope saw cutting. The first rope threading hole (3-1) is formed by an L-shaped PVC pipe pre-buried in the crown beam (8). The L-shaped PVC pipe is open at both ends, one end of the opening is located on the side of the crown beam (8), and the other end of the opening is located on the top surface of the crown beam (8); the waist beam (6) is provided with a second rope threading hole (3-2) for rope saw cutting. The second rope threading hole (3-2) is formed by a straight PVC pipe vertically pre-buried in the waist beam (6). The straight PVC pipe is open at both ends, one end of the opening is located on the top surface of the waist beam (6), and the other end of the opening is located on the bottom surface of the waist beam (6).
7. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 3 is characterized in that: The support platform (5) is formed by welding a first steel plate (501), a second steel plate (503), a third steel plate (504), and a fourth steel plate (505); the first steel plate (501) and the second steel plate (503) are rectangular in plan view, the third steel plate (504) and the fourth steel plate (505) are trapezoidal in plan view, and a concave pillow (506) for fixing the jack (4) is welded on the second steel plate (503).
8. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 7 is characterized in that: The No. 1 steel plate (501) used for welding the cap (5) is embedded in the crown beam (8) or the waist beam (6), and the steel bars (502) are welded on the No. 1 steel plate (501). The steel bars (502) are perpendicular to the plate surface of the No. 1 steel plate (501). The embedding direction of the steel bars (502) is perpendicular to the side of the crown beam (8) or the waist beam (6), and the steel bars (502) are fixed to the steel cage of the crown beam (8) or the waist beam (6) with steel wires. The corbel (7) is in the shape of a straight triangular prism. The corbel (7) is arranged on the crown beam (8) or the waist beam (6), and the No. 1 steel plate (501) is embedded in the position of the corbel (7).
9. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 3 is characterized in that: The branch members of the steel lattice column (9) are angle steels, and the tie members are steel plates, on which a tray (10) is welded. The tray (10) is composed of a panel (10-1) and eight triangular steel plates (10-2). No tie members are welded within a distance equal to the height of the foundation pit support beam section (1) above the tray that is not the first support, and four angle steels are used to reinforce the four branch members in this range. The first support is directly placed on the tray (10) at the top of the steel lattice column (9), and the non-first support passes through the steel lattice column (9) and is placed on the tray (10).
10. The construction method of the easily dismantled assembled reinforced concrete foundation pit support system according to any one of claims 1 to 9, characterized in that: The following steps are involved: 1) After the hole is drilled, support piles (13), column piles, and steel lattice columns (9) are formed; 2) After roughening the pile heads of the support piles (13), the steel bars of the crown beam (8) are tied; while tying the steel bars, the first rope threading hole (3-1) of the crown beam (8) is pre-buried, the first rope threading hole (3-1) is fixed by a steel wire, and the first rope threading hole (3-1) is set 2.5 m to 5 m from the corner point of the foundation pit, and then another first rope threading hole (3-1) is set every 2.5 m to 5 m, and the holes are sealed with plaster; then, steel bars (502) are welded on the No. 1 steel plate (501), and the welded steel bars (502) are fixed on the steel cage of the crown beam (8), while ensuring that the No. 1 steel plate (501) fits the side of the crown beam (8); 3) Formwork work is performed on the crown beam (8) and the corbel (7) on the crown beam (8). After the formwork is completed, concrete is poured. After the concrete is cured, subsequent construction is performed; 4) Excavate to the bottom elevation of the first inner support beam; to facilitate welding of the tray (10) on the steel lattice column (9), the excavation depth at least 1 m is increased at the location of the steel lattice column (9); to facilitate welding of the cap (5) on the crown beam (8), the excavation depth at least 1 m is increased at the location of the cap (5); 5) Welding a tray (10) onto the steel lattice column (9); 6) Use a crane to transport the foundation pit support beam section (1) and the foundation pit support cross-beam (2) to the designed position, analyze the pressure bearing size of the horizontal foundation pit support beam section (1) and the longitudinal foundation pit support beam section (1), first assemble the foundation pit support beam section (1) and the foundation pit support cross-beam (2) of the middle position of the pair of supports in the direction of greater pressure, and assemble the pair of supports from the middle to both ends; first install the foundation pit support beam section (1) of the pair of supports located in the inner standard area (A), then assemble the non-standard area foundation pit support beam section (11) of the pair of supports located in the non-standard area (C), and then assemble the foundation pit support beam section (11) of the pair of supports located in the outer standard area (B). ), then assemble the pit support eight-shaped beam (2) of the pair of supports located in the outer standard area (B), after the construction of the pair of supports is completed, assemble the pit support beam segments (1) of the supports in the direction of less pressure on both sides, then assemble the two adjacent supports in the direction of greater pressure, and then assemble the pit support beam segments (1) of the supports in the direction of less pressure on both sides, repeat the operation until the assembly construction of all the pit support beam segments (1) and the pit support eight-shaped beam (2) of the first inner support is completed, and the pit support beam segments (1) are placed on the pallet (10) at all the beam-column nodes of the first inner support; 7) Using a No. 1 steel plate pre-buried on the crown beam (8) or the corbel (7) of the crown beam (8), a cap (5) is welded, the foundation pit support beam section (1) at the edge and the foundation pit support cross beam (2) are both placed on the cap (5) at one end, a jack (4) is placed on the concave pillow (506) of the cap (5), and the jack (4) is extended to form a first internal support; 8) Excavate to the bottom elevation of the second inner support beam; to facilitate welding of the tray (10) on the steel lattice column (9), the excavation depth at least 1 m is increased at the location of the steel lattice column (9); to facilitate welding of the cap (5) on the crown beam (8), the excavation depth at least 1 m is increased at the location of the cap (5); 9) Welding a tray (10) onto the steel lattice column (9); 10) Performing roughening treatment on the support pile (13), performing steel bar binding work on the waist beam (6), and pre-embedding work on the second rope threading hole (3-2), the second rope threading hole (3-2) is fixed by a steel wire, and the second rope threading hole (3-2) is set from 2.5 m to 5 m away from the corner point of the foundation pit, and a second rope threading hole (3-2) is set every 2.5 m to 5 m, and sealed with plaster; then, welding steel bars (502) on the No. 1 steel plate (501), and fixing the welded steel bars (502) on the steel cage of the waist beam (6); 11) Formwork work is performed on the waist beam (6) and the upper corbel (7) of the waist beam (6), and after the formwork is completed, concrete is poured, and after the concrete is cured, subsequent construction is performed; 12) Use a crane to transport the foundation pit support beam section (1) and the foundation pit support cross-beam (2) to the designed position, analyze the pressure bearing of the horizontal foundation pit support beam section (1) and the longitudinal foundation pit support beam section (1), first assemble the foundation pit support beam section (1) and the foundation pit support cross-beam (2) of the middle position of the pair of supports in the direction of greater pressure, assemble the pair of supports from the middle to both ends, first install the foundation pit support beam section of the pair of supports located in the inner standard area (A), then assemble the non-standard area foundation pit support beam section (11) of the pair of supports located in the non-standard area (C), then assemble the foundation pit support beam section (1) of the pair of supports located in the outer standard area (B), and then assemble The pit support beam (2) is provided with the pair of supports located in the outer standard area (B). After the pair of supports is constructed, the pit support beam segments (1) on both sides of the pair of supports with less pressure are assembled, and then the two pairs of supports adjacent to the pair of supports with greater pressure are assembled, and then the pit support beam segments (1) on both sides of the pair of supports with less pressure are assembled, and the operation is repeated until the assembly construction of all the pit support beam segments (1) and the pit support beam (2) of the second inner support is completed. At all the beam-column nodes of the second inner support, the pit support beam segments (1) pass through the steel lattice columns (9) and are placed on the pallet (10); 13) The cap (5) is welded by using a No. 1 steel plate (501) pre-buried on the crown beam (8) or the corbel (7) of the crown beam (8), one end of the foundation pit support beam section (1) and the foundation pit support cross beam (2) at the edge are both placed on the cap (5), a jack (4) is placed on the concave pillow (506) of the cap (5), and the jack (4) is extended to form a second inner support; 14) Repeat the steps 8), 9), 10), 11), 12), and 13) to complete the construction of the remaining internal supports below the second internal support; 15) After the installation of the last support is completed, pour the foundation slab.
Citation Information
Cited By
Deep foundation pit concrete steel support combined structure and construction method thereof
CN118997179A
Fabricated reinforced concrete-steel structure foundation pit supporting system and dismantling method
CN119777388A
Intelligent supporting system close to existing structure foundation pit and construction method
CN120119656A
An intelligent support system and construction method for foundation pits close to existing structures
CN120119656B
Shallow foundation pit partition active regulation and control supporting structure and construction method
CN120250671A