Super high-rise building main body structure paying-off method
The wire-laying method that combines infrared positioning systems and drones solves the problem of insufficient wire-laying accuracy and flexibility in super-high-rise buildings, achieves high-precision and efficient wire-laying operations, and significantly improves construction quality.
Patent Information
- Application Number
- CN202411166267.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-23
- Publication Date
- 2024-10-18
AI Technical Summary
In the construction of super high-rise buildings, traditional laying-out methods are time-consuming, labor-intensive and prone to errors. Existing laying-out robots lack positioning accuracy and flexibility in complex high-rise environments.
The infrared positioning system is combined with the drone and robotic arm inkjet system. The drone obtains position information in real time, hovers and calculates the distance. The robotic arm adjusts the inkjet position and angle to perform line-laying operations, combined with the automatic obstacle avoidance function. and wireless communication module to achieve high-precision and flexible wire-laying operations.
It improves the accuracy and efficiency of laying out the main structure of the building, reduces manual errors, and ensures construction quality and safety.
Smart Images

Figure CN118793280A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and more specifically to a method for setting out a main structure of a super high-rise building. Background Art
[0002] In the construction process of super high-rise buildings, the layout of the main structure is a crucial link. Traditional layout work mainly relies on manual measurement and layout, which is not only time-consuming and laborious, but also prone to errors, affecting construction accuracy. With the development of building informatization and automation technology, layout robots are gradually used in the field of construction. However, the current layout robots have problems with insufficient positioning accuracy and flexibility when working in complex high-rise environments.
[0003] Therefore, how to provide a method for laying out the main structure of a super high-rise building that can improve positioning accuracy and flexibility is one of the technical problems that urgently need to be solved in this field. Summary of the invention
[0004] In view of this, the present invention provides a method for setting out the main structure of a super high-rise building, the purpose of which is to solve the problems of the prior art.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0006] A method for setting out the main structure of a super high-rise building comprises the following steps:
[0007] Step 1: Layout of infrared positioning system: Arrange multiple infrared positioning markers in the main structure of the building, and install infrared receiving sensors on the drone to form an infrared positioning system for obtaining the location information of the drone in real time;
[0008] Step 2: UAV positioning and distance measurement: Based on the positioning information, the UAV flies to the line-release position according to the preset line-release path, hovers in the air, and obtains its own position in real time through the infrared positioning system to calculate the distance between the target point and the UAV;
[0009] Step 3: Wire laying operation: According to the calculated distance, the inkjet system is controlled by the robot arm to adjust the inkjet position and angle, and the inkjet pressure is controlled as needed to perform the wire laying operation.
[0010] Preferably, the drone has an automatic obstacle avoidance function and can automatically identify and avoid obstacles on site.
[0011] Preferably, the drone is provided with an obstacle avoidance sensor.
[0012] Preferably, the robotic arm has six degrees of freedom for adjusting the pay-off position and angle of the inkjet system.
[0013] Preferably, the inkjet system comprises an ink storage device and a nozzle; the nozzle is connected to the ink storage device; and the nozzle is arranged at the end of the robotic arm.
[0014] Preferably, the inkjet system further comprises a pressure sensor and a controller for controlling the inkjet pressure.
[0015] Preferably, the drone communicates with the base station via a wireless communication module.
[0016] Compared with the prior art, the present invention has achieved the following technical effects: the present invention can perform high-precision positioning and flexible line-laying operations by cooperating with an infrared positioning system, a drone, a robotic arm and an inkjet system, thereby effectively improving the line-laying efficiency and line-laying accuracy of the main structure of the building, and has broad application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic diagram of a process of setting out a main structure of a super high-rise building according to the present invention;
[0018] Figure 2 This is a schematic diagram of the drone and infrared positioning markers;
[0019] Figure 3 Schematic diagram of the drone, robotic arm, and inkjet system;
[0020] In the figure: 1. Infrared positioning mark point; 2. Drone; 3. Robotic arm; 4. Inkjet system; 41. Ink storage device; 42. Printhead. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] Example
[0023] The invention discloses a method for setting out the main structure of a super high-rise building, comprising the following steps:
[0024] Step 1: Arrangement of infrared positioning system: Arrange multiple infrared positioning mark points 1 in the main structure of the building, and install infrared receiving sensors on the drone 2 to form an infrared positioning system for obtaining the position information of the drone 2 in real time; the drone 2 realizes autonomous navigation in the indoor space according to the positioning information, so that it can fly according to the preset line-laying path;
[0025] Step 2, positioning and distance measurement of UAV 2: Based on the positioning information, UAV 2 flies to the line-release position according to the preset line-release path, hovers in the air, and obtains its own position in real time through the infrared positioning system, and calculates the distance between the target point and its own position;
[0026] Step 3, wire laying operation: according to the calculated distance and the preset wire laying drawing, the inkjet system 4 is controlled by the robot arm 3 to adjust the inkjet position and angle, and the inkjet pressure is controlled as needed to perform the wire laying operation to ensure the accuracy of the wire laying.
[0027] In this embodiment, the drone 2 has an automatic obstacle avoidance function, which can automatically identify and avoid obstacles on site, thereby ensuring flight safety and the continuity of the line-laying work.
[0028] In this embodiment, the drone 2 is provided with an obstacle avoidance sensor.
[0029] In this embodiment, the robot arm 3 has six degrees of freedom, and can flexibly adjust the line-laying position and angle of the inkjet system 4 to ensure that the inkjet system can lay out the line accurately.
[0030] In this embodiment, the inkjet system 4 includes an ink storage device 41 and a nozzle 42; the ink storage device 41 is arranged on the robot arm 3, and is used to store the ink required for inkjet; the nozzle 42 is connected to the ink storage device 41; the nozzle 42 is arranged at the end of the robot arm 3, and the uniform spraying of ink is achieved by controlling the inkjet pressure.
[0031] In this embodiment, the ink storage device 41 adopts a sealed design to prevent ink leakage; the nozzle 42 adopts a high-precision nozzle design to ensure the clarity and consistency of the ink line.
[0032] In this embodiment, the inkjet system 4 also includes a pressure sensor and a controller, which can automatically adjust the inkjet pressure according to demand to achieve adjustment of different line widths and line depths, thereby ensuring the accuracy of line placement.
[0033] In this embodiment, the drone 2 communicates with the base station through a wireless communication module to achieve position data transmission, path planning and command sending, status monitoring and feedback functions.
[0034] In this embodiment, the UAV 2 transmits its own position information to the base station through the wireless communication module in real time. The base station processes and stores the received position data, calculates the flight path of the UAV according to the current position of the UAV 2 and the preset line-laying path, and sends navigation instructions to the UAV 2 through the wireless communication module. During the flight, the UAV 2 transmits its own status information (such as battery power, flight speed, etc.) to the base station in real time, and the base station monitors and provides feedback to ensure the safe flight of the UAV 2.
[0035] In some other embodiments, the infrared indoor positioning system can be further combined with visual positioning and super-tube positioning technology to improve positioning accuracy.
[0036] The present invention can effectively solve the problem of being unable to walk due to the on-site materials being piled up by using drones. The drones can fly flexibly in complex high-rise environments to avoid the influence of material accumulation on the laying-out work.
[0037] The drone of the present invention has an automatic obstacle avoidance function, and can identify and avoid obstacles such as steel bars and frames at the construction site, thereby ensuring the safety and continuity of the line-laying process.
[0038] The present invention realizes high-precision positioning through an infrared positioning system, and combines the flexible operation of a mechanical arm with the high-precision laying-out of an inkjet system, thereby significantly improving the efficiency and accuracy of the laying-out work, reducing manual errors, and improving construction quality.
[0039] The above description is only a preferred embodiment of the present invention and does not limit the technical scope of the present invention. Therefore, any slight modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A method for setting out the main structure of a super high-rise building. It is characterized in that The following steps are involved: Step 1: Arrangement of infrared positioning system: Arrange multiple infrared positioning mark points (1) in the main structure of the building, and install infrared receiving sensors on the drone (2), which together constitute an infrared positioning system for obtaining the position information of the drone (2) in real time; Step 2, positioning and distance measurement of the UAV (2): Based on the positioning information, the UAV (2) flies to the line-release position according to the preset line-release path, hovers in the air, and obtains its own position in real time through the infrared positioning system, and calculates the distance between the target point and the UAV (2); Step 3: Wire laying operation: According to the calculated distance, the inkjet system (4) is controlled by the robot arm (3) to adjust the inkjet position and angle, and the inkjet pressure is controlled as required to carry out the wire laying operation.
2. A method for laying out the main structure of a super high-rise building according to claim 1, It is characterized in that The unmanned aerial vehicle (2) has an automatic obstacle avoidance function and can automatically identify and avoid obstacles on site.
3. A method for setting out the main structure of a super high-rise building according to claim 2, It is characterized in that The drone (2) is provided with an obstacle avoidance sensor.
4. A method for setting out the main structure of a super high-rise building according to claim 1, It is characterized in that The mechanical arm (3) has six degrees of freedom, which are used to adjust the line-laying position and angle of the inkjet system (4).
5. A method for setting out the main structure of a super high-rise building according to claim 1, It is characterized in that The inkjet system (4) comprises an ink storage device (41) and a nozzle (42); the nozzle (42) is connected to the ink storage device (41); and the nozzle (42) is arranged at the end of the mechanical arm (3).
6. A method for setting out the main structure of a super high-rise building according to claim 5, It is characterized in that The inkjet system (4) also includes a pressure sensor and a controller for controlling the inkjet pressure.
7. A method for setting out the main structure of a super high-rise building according to claim 1, It is characterized in that The unmanned aerial vehicle (2) communicates with the base station via a wireless communication module.
Citation Information
Patent Citations
Automatic paying-off system and method
CN115233996A
Unmanned aerial vehicle projection pay -off
CN207082019U
Marking using Drone and Construction Method Thereof
KR1020160142461A