Test device for testing vehicle
By integrating measurement and fault simulation devices in test equipment, using electronic loads to simulate overload faults of electrical components, and combining with computer systems for data monitoring, the problems of complexity and low efficiency in vehicle testing in the existing technology are solved, and the control of multiple electrical components is realized. Efficient testing of components and batteries.
Patent Information
- Application Number
- CN202411068972.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-10-18
AI Technical Summary
Due to the different power levels and operating conditions of different electrical components, existing vehicle testing equipment makes testing complex and inefficient, and takes up a lot of space.
Design an integrated test equipment that includes a cabinet, a measuring device and a fault simulation device. It simulates overload faults of electrical components through electronic loads, and combines data monitoring and fault judgment with a computer system to achieve simultaneous testing of multiple electrical components and batteries.
It improves the efficiency and space utilization of vehicle testing, can test the fault of electrical components and the status of the battery at the same time, and identify and handle the fault type in a timely manner.
Smart Images

Figure CN118795261A_ABST
Abstract
Description
Technical Field
[0001] This application relates to the field of vehicle testing, and in particular to an integrated testing device for testing vehicles. Background Technology
[0002] After a vehicle is manufactured, it is usually necessary to test various electrical components, such as those related to the key system, remote control functions, and safety performance, in order to determine whether these electrical components can function properly under various conditions.
[0003] However, since different electrical components of a vehicle have different power ratings and need to meet different operating conditions under different conditions, various test benches are usually required to test different electrical components of a vehicle under different conditions. This makes vehicle testing complicated and inefficient, and requires a large test space. Summary of the Invention
[0004] The objective of this application is to provide a vehicle testing device that integrates at least two tests, thereby improving measurement and testing efficiency and saving space occupied by the testing device.
[0005] To achieve the above objectives, this application provides a testing device for testing a vehicle. The vehicle includes multiple electrical components and a first battery. The first battery is configured to supply power to the multiple electrical components, and the electronic control units (ECUs) of the multiple electrical components are electrically connected in parallel to the first battery to form a first control circuit. According to this application, the testing device includes: a cabinet; a first measuring device housed in the cabinet and configured to measure the current and voltage of the ECUs of the multiple electrical components; a fault simulation device housed in the cabinet and having at least one first electronic load, the first electronic load being configured to be connected in series with the ECU of at least one of the multiple electrical components in the first control circuit to simulate an overload fault of the ECU of the at least one electrical component by increasing the current flowing through the ECU; and a computer system communicatively connected to the first measuring device, configured to acquire the current and voltage of the ECUs of the multiple electrical components from the first measuring device, and determine whether each electrical component has malfunctioned based on the current and voltage of the ECUs of the multiple electrical components, and whether the feedback and processing mechanisms of each electrical component under fault conditions are normal.
[0006] In this application, by integrating the first measuring device and the fault simulation device into the same cabinet, a compact testing device can be achieved. This single device can perform multiple tests on a vehicle; specifically, it can test whether multiple electrical components of the vehicle have malfunctioned, and it can test whether the vehicle can identify the fault when these components malfunction. Furthermore, by setting up a computer system that communicates with the first measuring device (and optionally also with the fault simulation device), vehicle test data can be remotely monitored and centrally managed, improving vehicle testing efficiency.
[0007] In some embodiments, the testing equipment may further include a second measuring device housed in a cabinet and communicatively connected to a computer system. This second measuring device is configured to measure the current and voltage of the first battery. In this case, the computer system may also be configured to acquire the current and voltage of the first energy storage device from the second measuring device, and input the current and voltage of the electronic control units of the plurality of electrical components, along with the current and voltage of the first energy storage device, into a preset fault model. This fault model is used to determine whether a vehicle malfunction has occurred and, if so, to identify the type of malfunction.
[0008] By integrating a second measuring device into the testing equipment, the vehicle's first battery, especially the low-voltage battery, can be tested simultaneously to determine whether it is functioning properly. Furthermore, by combining the current and voltage of the electronic control units of the multiple electrical components with the current and voltage of the first accumulator, it is possible to determine whether a vehicle malfunction has occurred and, if so, identify the type of malfunction.
[0009] In some embodiments, the fault simulation apparatus may further include at least one second electronic load. The second electronic load is configured to increase the current flowing through the first battery to simulate an overload fault in the first battery; and / or, the second electronic load is configured to be connected in series with the electronic control unit of at least another electrical component in the first control circuit to simulate an overload fault in the electronic control unit of the at least other electrical component by increasing the current flowing through the electronic control unit of the at least other electrical component. Integrating the second electronic load into the test equipment can further improve the efficiency of fault simulation.
[0010] In some embodiments, a first electronic load may be configured to be connected in series with the electronic control unit of the first electrical component among the plurality of electrical components in a first control circuit, and a second electronic load may be configured to be connected in series with the electronic control unit of the second electrical component among the plurality of electrical components in a first control circuit, wherein the overload current of the first electrical component is less than the overload current of the second electrical component.
[0011] Furthermore, the maximum current of the first electronic load is less than the maximum current of the second electronic load, and the overload current of the first electrical component is less than the maximum current of the first electronic load, while the overload current of the second electrical component is greater than the maximum current of the first electronic load and less than the maximum current of the second electronic load.
[0012] In some embodiments, the vehicle may further include a plurality of additional electrical components and a second battery, the second battery being configured to supply power to the plurality of additional electrical components. The electronic control units (ECUs) of the plurality of additional electrical components are electrically connected in parallel with the second battery to form a second control circuit, wherein the rated voltage of the second battery is greater than the rated voltage of the first battery. Here, a first measuring device is further configured to measure the current and voltage of the ECUs of the plurality of additional electrical components; a second measuring device is further configured to measure the current and voltage of the second battery; and a computer system is further configured to allow the first measuring device to acquire the current and voltage of the ECUs of the plurality of additional electrical components, and based on the current and voltage of the ECUs of the plurality of additional electrical components, determine whether each of the additional electrical components has malfunctioned and determine whether the feedback and processing mechanisms of each of the additional electrical components are normal under fault conditions.
[0013] In some embodiments, the fault simulation device may further include at least one second electronic load. The second electronic load is configured to simulate an overload fault of the first or second battery by increasing the current flowing through the first or second battery; and / or, the second electronic load is configured to be connected in series with the electronic control unit of at least one of the plurality of additional electrical components in a second control circuit to simulate an overload fault of the electronic control unit of the at least one electrical component by increasing the current flowing through the electronic control unit of the at least one electrical component.
[0014] In some embodiments, the current of the first electronic load is adjustable, and the current of the second electronic load is adjustable. Thus, one electronic load can be used to simulate overload faults of multiple different electrical components, thereby enabling the use of as few first and / or second electronic loads as possible.
[0015] Preferably, the fault simulation device may include only one first electronic load and only one second electronic load.
[0016] In some embodiments, the first electronic load may be configured to be selectively connected in series with an electronic control unit of one of the plurality of electrical components in a first control circuit; and the test equipment further includes a switching device electrically connected to a computer system, the first electronic load, and the second electronic load, the computer system being further configured to:
[0017] Control the switching device to connect the first electronic load and the electronic control unit of the electrical component under test among the plurality of electrical components in series in the first control circuit; and
[0018] Adjust the current of the first electronic load to match the overload current of the electrical component under test connected in series with the first electronic load.
[0019] In some embodiments, the fault simulation device may further include a short-circuit and open-circuit simulator configured to short-circuit or open-circuit the circuit between the electronic control unit of at least one electrical component and a first or second battery to simulate a short-circuit or open-circuit fault of the electronic control unit of the at least one electrical component.
[0020] In some embodiments, the testing equipment may further include a data recording device electrically connected to the vehicle's data bus and to a computer system. The data bus is electrically connected to the electronic control unit of the electrical components. The data recording device is housed in a cabinet and configured to record the vehicle's test data. This enables timely recording of test data, facilitating subsequent analysis.
[0021] In some embodiments, the testing equipment may further include a data collection device electrically connected to the vehicle's OBD interface and a computer system. This data collection device is housed in a cabinet and configured to collect diagnostic data from the OBD interface. The computer system is also configured to acquire the diagnostic data from the data collection device and compare the diagnostic data with faults identified based on the current and voltage of the electronic control unit of electrical components and, optionally, the current and voltage of the battery. This allows for a more accurate determination of whether the vehicle is faulty.
[0022] In some embodiments, the testing equipment may further include a charger housed within a cabinet and used to charge the battery. This allows the battery to be charged promptly after overload simulation.
[0023] In some embodiments, the testing equipment can be configured to simultaneously test multiple vehicles and monitor the corresponding test data. This further improves vehicle testing efficiency.
[0024] In some embodiments, the testing equipment may be configured to simultaneously test multiple vehicles in a dormant state to test whether the vehicles function normally after a preset dormant period. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a schematic diagram of a first embodiment of the test equipment according to this application.
[0026] Figure 2 This is a schematic diagram of a second embodiment of the test equipment according to this application.
[0027] Figure 3 This is a schematic diagram of a third embodiment of the test equipment according to this application.
[0028] Figure 4 and Figure 5 This is a schematic diagram of a fourth embodiment of the test equipment according to this application.
[0029] Figure 6 This is a schematic diagram of a fifth embodiment of the test equipment according to this application.
[0030] Figure 7 This is a schematic diagram of a switching device according to some embodiments of this application.
[0031] Figure 8 This is a schematic diagram of a sixth embodiment of the test equipment according to this application.
[0032] Figure 9 This is a schematic diagram of a seventh embodiment of the test equipment according to this application.
[0033] Figure 10 This is a schematic diagram of the eighth embodiment of the test equipment according to this application.
[0034] Figure 11 This is a schematic diagram of the ninth embodiment of the test equipment according to this application. Detailed Implementation
[0035] The embodiments of this application will now be clearly and completely described with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of this application, and not all of them. Based on the embodiments of this application, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of this application.
[0036] It should be noted that the terms "first, second, and third" used in the embodiments of this application are merely to distinguish similar objects and do not represent a specific order of objects. It can be understood that "first, second, and third" can be interchanged in a specific order or sequence where permitted.
[0037] As mentioned in the background section, after a vehicle is manufactured, various electrical components typically undergo different tests. For example, some vehicles have a deep sleep function, meaning they can still start and operate normally after long-term storage, such as six months or more. Therefore, a sleep function test needs to be performed on the vehicle before it leaves the factory. This includes measuring the sleep current in the vehicle's sleep or hibernation state to determine whether a malfunction has occurred after long-term storage and whether the malfunction can be identified promptly if it does occur.
[0038] Therefore, this application proposes a testing device that integrates multiple vehicle testing functions.
[0039] Figure 1 A schematic block diagram of a test apparatus 100 for testing a vehicle 200 according to some embodiments of this application is shown.
[0040] The vehicle 200 includes a plurality of electrical components 210 and a first battery 220. The first battery 220 is configured to supply power to the plurality of electrical components 210. Here, for clarity, Figure 1 Electrical components labeled 210, 210a are shown only by way of example. The electronic control units (ECUs) 211 of the plurality of electrical components 210 are electrically connected in parallel to each other to the first battery 220 to form a first control circuit 230.
[0041] In some embodiments of this application, the first battery 220 may be a low-voltage battery, for example, a battery configured with a rated voltage of less than 48V. In a specific example, the first battery is a battery with a rated voltage of 12V or 24V.
[0042] According to an embodiment of this application, the test equipment 100 includes a cabinet 110, a first measuring device 120, a fault simulation device 130, and a computer system 140.
[0043] The cabinet 110 is configured to form a receiving space for at least accommodating the first measuring device 120 and the fault simulation device 130.
[0044] The first measuring device 120 is housed in the cabinet 110 and is equipped with electronic control units 211 for measuring the current and voltage of the plurality of electrical components 210. Here, the first measuring device 120 has a multi-channel, for example, eight-channel analog measuring module, each analog measuring module having a sensor probe for measuring the current and voltage of the electronic control unit 211 of one electrical component 210.
[0045] By setting the first measuring device 120, the fault location of the vehicle can be located, especially which electronic control units or units are involved in the fault.
[0046] The fault simulation device 130 is housed in a cabinet 110 and has at least one first electronic load 131. The first electronic load 131 is configured to be connected in series with the electronic control unit 211a of at least one of the plurality of electrical components 210a in a first control circuit 230 to simulate an overload fault of the electronic control unit of the at least one electrical component by increasing the current flowing through the electronic control unit of the at least one electrical component.
[0047] As can be understood here, an electronic load (E-load) refers to a load that uses electronic components to absorb and consume electrical energy. The electronic load configured according to the embodiments of this application can be used to discharge the vehicle as a whole and / or its individual electrical components, thereby achieving fault injection and simulating electrical faults to test the feedback and emergency handling mechanisms of the vehicle and / or its individual electrical components under fault conditions. On one hand, the electronic load can be connected in series in the control circuit formed by the battery and each electronic control unit, and additional current is supplied to the electronic control unit from the battery ground, thereby increasing the current flowing through the corresponding electronic control unit. This simulates an overload fault in the electronic control unit. On the other hand, the electronic load can also be applied to the battery and discharge the battery, thereby increasing the current flowing through the battery, simulating charging the battery with an increased current.
[0048] In embodiments of the invention, an electronic load using a fault simulation device can inject an overload fault into the vehicle and its battery and / or electronic control unit. This eliminates the need for the vehicle's battery itself to provide increased current, does not require a specific state of charge for the battery, and allows testing to be performed, particularly when the vehicle is in a dormant state. Furthermore, it eliminates the need to manipulate or alter the vehicle's battery's electrical output. Exemplarily, the electronic load can be an electronic component that adjusts current by controlling internal power or the conduction of transistors. In particular, the electronic load can operate in a constant current state and maintain its output current at a set value.
[0049] A computer system 140, which is communicatively connected to a first measuring device (and optionally also to a fault simulation device), is configured to acquire the current and voltage of the electronic control units 211 of the plurality of electrical components 210 from the first measuring device 120, and determine whether each electrical component 210 has malfunctioned based on the current and voltage of the electronic control units 211 of the plurality of electrical components 210, and determine whether the feedback and processing mechanism of each electrical component 210 in the fault state is normal.
[0050] In this embodiment, the computer system 140 is communicatively connected to the first measuring device 120 and the fault simulation device 130. The computer system 140 enables remote control of the testing equipment 100.
[0051] In the test equipment 100 provided according to this application, the test efficiency of the test vehicle can be improved by integrating sensor probes for measuring the current and voltage of electrical components and electronic loads for simulating overload faults of electrical components.
[0052] For example, the testing equipment 100 is configured to simultaneously test multiple vehicles and monitor the corresponding test data. In particular, the testing equipment 100 is configured to simultaneously test multiple vehicles in a dormant state to test whether each vehicle is functioning normally after a preset dormant period.
[0053] In a specific example, the test device 100 tests a vehicle in a dormant state as follows: a first measuring device 120 is connected to the electrical components to be measured (DMTs) of the vehicle to measure the current of the electronic control units 211 of each DMT 210 in a dormant state; a computer system 140 obtains the current of the electronic control units 211 of each DMT 210 from the first measuring device 120 and determines whether each current is greater than a corresponding preset threshold. If the current of the electronic control unit 211 of a DMT 210 is greater than its corresponding preset threshold, it is determined that the DMT 210 has malfunctioned; for DMTs 210a that have not malfunctioned, a fault simulation device 130 is connected to the DMT 210a to increase the current flowing through the electronic control unit of the DMT (making the current greater than the corresponding preset threshold) to simulate its overload fault; if the vehicle issues an alarm after injecting an overload fault into the DMT 210a, it indicates that the feedback and processing mechanism of the DMT 210a in the fault state is normal.
[0054] In other embodiments, the testing equipment 100 can also be used to perform relevant tests on a vehicle in a normal state. For example, the vehicle under test can be placed in a virtual normal driving state, and then the testing equipment 100 can be used to perform relevant tests on the vehicle under test.
[0055] In some embodiments, the computer system 140 may include at least: a processing component, RAM, ROM, a communication interface, a memory, and an I / O interface, wherein the processing component, RAM, ROM, communication interface, memory, and I / O interface communicate via a bus.
[0056] In some embodiments, the processing component may be a CPU, GPU, or other chip with computing power. The memory stores various computer programs, such as operating systems and applications, for the processor component to execute, as well as the data required to execute these computer programs. Additionally, any data that needs to be stored locally can be stored in the memory, such as the current and voltage of the electronic control unit 211 of the plurality of electrical components 210 obtained from the first measuring device 120.
[0057] In some embodiments, the I / O interface comprises serial interfaces such as USB, IEEE 1394, or RS-232C; parallel interfaces such as SCSI, IDE, or IEEE 1284; bus interfaces such as CAN or FlexRay; and analog signal interfaces composed of D / A converters and A / D converters. Input devices, such as keyboards, mice, touchscreens, or other control buttons, can be connected to the I / O interface, allowing users to directly input data into the computer system. Additionally, a display with display capabilities, such as an LCD screen, touchscreen, or LED display, can be connected to the I / O interface, enabling the computer system to output data, such as current and voltage, to the display for presentation.
[0058] In some embodiments, the communication interface can be an interface using any known communication protocol. The communication interface communicates with the outside world via a network. The control device can transmit data with any device connected through the network using a specific communication protocol via the communication interface.
[0059] In some embodiments, such as Figure 2 As shown, the test equipment 100 also includes a second measuring device 150 housed in a cabinet 110 and integrated with a computer system 140. The second measuring device 150 is configured to measure the current and voltage of the first battery 220. Here, the computer system 140 is also configured to acquire the current and voltage of the first battery 220 from the second measuring device 150, and input the current and voltage of the electronic control units 211 of the plurality of electrical components 210 and the current and voltage of the first battery 220 into a preset fault model, so as to determine whether a vehicle malfunction has occurred and, if so, identify the type of malfunction when it does occur.
[0060] For example, a preset fault model is pre-stored in the memory of the computer system 140. This fault model describes the relationship between the current and voltage (or the power calculated from the current and voltage) of the electronic control unit 211 of each electrical component 210 and the current and voltage (or the power calculated from the current and voltage) of the first energy storage unit 220 and the fault type. That is, by inputting the current and voltage (or the power calculated from the current and voltage) of the electronic control unit 211 of each electrical component 210 and the current and voltage (or the power calculated from the current and voltage) of the first energy storage unit 210 into the fault model, the fault model can output whether the vehicle is faulty and the fault type when the fault occurs.
[0061] In some implementations, the second measuring device 150 has a multi-channel, for example, eight-channel measuring module, each measuring module having a sensor probe for measuring the current and voltage of the energy storage device.
[0062] In some embodiments, the first electronic load 131 is also configured to simulate an overload fault of the first battery by increasing the current flowing through the first battery 220.
[0063] In some alternative embodiments, such as Figure 3 As shown, the fault simulation device 130 also includes at least one second electronic load 132. The second electronic load 132 is configured to simulate an overload fault of the first battery 220 by increasing the current flowing through the first battery 220.
[0064] Alternative or additional land, such as Figure 3 As shown, the second electronic load 132 is configured to be connected in series with the electronic control unit 211b of at least another electrical component 210b in the first control circuit 230 to simulate an overload fault of the electronic control unit of the at least other electrical component 210b by increasing the current flowing through the electronic control unit 211b of the at least other electrical component 210b.
[0065] As some implementation methods, such Figure 3 As shown, the first electronic load 131 is configured to be connected in series with the electronic control unit 211a of the first electrical component 210a among the plurality of electrical components 210 to the first control circuit 230, and the second electronic load 132 is configured to be connected in series with the electronic control unit 211b of the second electrical component 210b among the plurality of electrical components 210 to the first control circuit 230, wherein the overload current of the first electrical component 210a (or the minimum current that causes the first electrical component 210a to overload) is less than the overload current of the second electrical component 210b (or the minimum current that causes the second electrical component 210b to overload).
[0066] Preferably, the maximum current of the first electronic load 131 is less than the maximum current of the second electronic load 132, and the overload current of the first electrical component 210a is less than the maximum current of the first electronic load 131, while the overload current of the second electrical component 210b is greater than the maximum current of the first electronic load 121 and less than the maximum current of the second electronic load 132.
[0067] In some embodiments, the current of the first electronic load 131 is adjustable. Alternatively or additionally, the current of the second electronic load 132 is also adjustable. Thus, overload faults of multiple electrical components with different load currents can be simulated using a single first electronic load.
[0068] In some embodiments, the fault simulation device 130 includes only one first electronic load and only one second electronic load. In other embodiments, multiple first electronic loads and / or multiple second electronic loads may be provided.
[0069] In some embodiments, such as Figure 4 and Figure 5 As shown, the first electronic load 131 is configured to be selectively connected in series with one of the plurality of electrical components, such as the electronic control unit 211a of one of the first electrical components 210a, in the first control circuit 230. Here, the test equipment also includes a switching device 160 electrically connected to the computer system 140 and electrically connected to the first electronic load. The computer system 140 is further configured to: control the switching device 160 to connect the first electronic load 131 in series with the electronic control unit of each of the first electrical components 210a to the first control circuit 230; and adjust the current of the first electronic load 131 to accommodate the overload current of the electrical component under test connected in series with the first electronic load 131, thereby simulating an overload fault of the electrical component under test. That is, the first electronic load 131 can be used to simulate an overload fault of at least one of the first electrical components 210a.
[0070] Alternative or additional land, such as Figure 6 As shown, the second electronic load 132 is configured to be selectively connected in series with the electronic control unit of one of the second electrical components 210b in the first control circuit 230. The computer system 140 is further configured to: control the switching device 160 to connect the second electronic load 132 in series with the electronic control unit of the electrical component under test in the second electrical component 210b in the first control circuit 130; and adjust the current of the second electronic load 132 to accommodate the overload current of the electrical component under test connected in series with the second electronic load 132. In other words, the second electronic load 132 can be used to simulate an overload fault of at least one of the second electrical components 210b.
[0071] In some embodiments, the overload current of each first electrical component 210a is less than the overload current of each second electrical component 210b. Preferably, the overload current of each first electrical component 210a is less than the maximum current of the first electronic load 131, while the overload current of each second electrical component 210b is greater than the maximum current of the first electronic load 131 and less than the maximum current of the second electronic load 132.
[0072] In other embodiments, the first electronic load 131 is used to simulate an overload fault of any electrical component 210, while the second electronic load 132 is used to simulate an overload fault of the first battery 220.
[0073] In a specific example, such as Figure 7As shown, the switching device 160 includes multiple switches S1-S4. When an overload fault simulation is required for the second electrical component 210a1, the computer system 140 controls the switching device 160 to close switch S1 and open switches S2, S3, and S4, thereby connecting the first electronic load 131 and the electronic control unit 211a1 of the second electrical component 210a1 in series across the two ends of the first battery 220. When an overload fault simulation is required for the second electrical component 210a2, the computer system 140 controls the switching device 160 to close switch S2 and open switches S1, S3, and S4, thereby connecting the first electronic load 131 and the electronic control unit 211a2 of the second electrical component 210a2 in series across the two ends of the first battery 220. When it is necessary to simulate an overload fault for the second electrical component 210a3, the computer system 140 controls the switch S3 of the switching device 160 to close, while switches S1, S2 and S4 are opened, so that the first electronic load 131 and the electronic control unit 211a3 of the second electrical component 210a2 are connected in series to the two ends of the first battery 220.
[0074] In some embodiments, such as Figure 8 As shown, the vehicle also includes a plurality of additional electrical components 240 and a second battery 250. The second battery 250 is configured to supply power to the plurality of additional electrical components 240, and the electronic control units 241 of the plurality of additional electrical components 240 are electrically connected in parallel with each other to the second battery 250 to form a second control circuit 260. The rated voltage of the second battery is greater than the rated voltage of the first battery; for example, the rated voltage of the first battery is 12V, while the rated voltage of the second battery is 24V. Here, the first measuring device 120 is also configured to measure the current and voltage of the electronic control units 241 of the plurality of additional electrical components 240; the second measuring device 150 is also configured to measure the current and voltage of the second battery 250. Accordingly, the computer system 140 is also configured to acquire the current and voltage of the electronic control unit 241 of the plurality of additional electrical components 240 from the first measuring device 120, and determine whether each of the additional electrical components has malfunctioned based on the current and voltage of the electronic control unit of the plurality of additional electrical components, and determine whether the feedback and processing mechanism of each of the additional electrical components in the fault state is normal.
[0075] In some embodiments, such as Figure 9As shown, the fault simulation device 130 further includes at least one second electronic load 132. The second electronic load 132 is configured to be connected in series with the electronic control unit 241 of at least one of the plurality of additional electrical components 240 in a second control circuit 260 to simulate an overload fault of the electronic control unit of the at least one electrical component by increasing the current flowing through the electronic control unit of the at least one electrical component. And / or, the second electronic load 132 is configured to simulate an overload fault of the first battery 220 or the second battery 250 by increasing the current flowing through the first battery 220 or the second battery 250.
[0076] In other embodiments, the first electronic load 131 is further configured to increase the current flowing through the first battery 220 to simulate an overload fault of the first battery. The second electronic load 132 is further configured to increase the current flowing through the second battery 250 to simulate an overload fault of the second battery. Preferably, the maximum current of the first electronic load is less than the maximum current of the second electronic load.
[0077] Similarly, the current of the first electronic load 131 and the current of the second electronic load 132 are both adjustable. In particular, the fault simulation device 130 includes only one first electronic load and only one second electronic load.
[0078] As one implementation, the first electronic load 131 is configured to be selectively connected in series with the electronic control unit of one of the plurality of electrical components 210 into the first control circuit 230, and the second electronic load 132 is configured to be selectively connected in series with the electronic control unit of one of the plurality of other electrical components 240 into the second control circuit 260. The test equipment 100 also includes a switching device electrically connected to the computer system 140, the first electronic load 131, and the second electronic load 132. Here, the computer system 140 is further configured to: control the switching device to connect the first electronic load 131 in series with the electronic control unit of the electrical component under test among the plurality of electrical components 220 into the first control circuit 230; and adjust the current of the first electronic load 131 to accommodate the overload current of the electrical component under test connected in series with the first electronic load. The computer system 140 is also configured to: control the switching device to connect the second electronic load 132 in series with the electronic control unit of the electrical component under test in the plurality of other electrical components 240 in the second control circuit 260; and adjust the current of the second electronic load 132 to adapt to the overload current of the electrical component under test connected in series with the second electronic load.
[0079] In other embodiments, the first electronic load 131 is used to simulate an overload fault of either electrical component 210 or 240, while the second electronic load 132 is used to simulate an overload fault of either the first battery 220 or the second battery 250.
[0080] In some embodiments, such as Figure 10 As shown, the fault simulation device 130 also includes a short-circuit and open-circuit simulator 133, which is configured to short-circuit or open-circuit the circuit between the electronic control unit 211 of at least one electrical component 210 and the first battery 210 and / or between the electronic control unit 241 of at least one electrical component 240 and the second battery 250, to simulate a short-circuit or open-circuit fault in the electronic control unit of the electrical component. Figure 10 As shown, the short-circuit and open-circuit simulator 133 is currently connected across one of the electronic control units 211 to either disconnect the electronic control unit 211 from the control circuit 230 or short-circuit the electronic control unit 211 at both ends.
[0081] In some embodiments, such as Figure 11 As shown, the test equipment 100 also includes a data recording device 170 electrically connected to a data bus 270 of the vehicle 200 and to a computer system 140. The data bus 270 is electrically connected to the electronic control units of various electrical components. The data recording device 170 is housed in a cabinet 110 and is configured to record test data of the vehicle 200.
[0082] Alternatively or additionally, the test equipment 100 also includes a data collection device 180 electrically connected to the OBD interface 280 of the vehicle 200 and the computer system 140. The data collection device 180 is housed in a cabinet 110 and configured to collect diagnostic data from the OBD interface 280. The computer system 140 is also configured to acquire diagnostic data from the data collection device 180 and compare the diagnostic data with faults identified by the current and voltage of the electronic control unit based on electrical components and, optionally, the current and voltage of the battery, to determine whether a fault has actually occurred in the vehicle.
[0083] When a vehicle malfunctions or its system parameters are defective, the vehicle can self-diagnose the fault location and record the fault time. It can then analyze and determine the fault, storing the fault codes and descriptions using dedicated software, and managing the vehicle's test data. The stored fault codes and descriptions, i.e., diagnostic data, can be retrieved through the vehicle's OBD interface 280.
[0084] Alternatively or additionally, the test equipment 100 also includes a charger 190. This charger 190 is housed in a cabinet 110 and is used to charge the batteries 220 and / or 250. This allows the batteries to be charged promptly after an overload fault simulation to compensate for the power consumed during the simulation.
[0085] In some embodiments not shown, the test device 100 may also include a power supply for powering the test device 100.
[0086] In some embodiments not shown, the test equipment 100 may also include an oscilloscope for measuring the current and voltage of the battery 220 and / or the battery 250.
[0087] All features or combinations of features mentioned above in the specification, drawings and claims may be used in any combination or individually, as long as they are meaningful within the scope of this application and do not contradict each other.
[0088] The above description is merely a preferred embodiment of this application and does not limit the patent scope of this application. All equivalent modifications made based on the inventive concept of this application and the contents of the specification and drawings of this application, or direct / indirect applications in other related technical fields, are included within the patent protection scope of this application.
Claims
1. A test device for testing a vehicle, wherein: The vehicle comprises a plurality of electrical components and a first battery, the first battery being configured to supply power to the plurality of electrical components, the electronic control units of the plurality of electrical components being electrically connected to the first battery in parallel to form a first control circuit, the test device comprising: Cabinet; a first measuring device housed in the cabinet and configured to measure current and voltage of electronic control units of the plurality of electrical components; a fault simulation device, housed in the cabinet and having at least one first electronic load, the first electronic load being configured to be connected in series with an electronic control unit of at least one of the plurality of electrical components into the first control circuit, so as to simulate an overload fault of the electronic control unit of the at least one electrical component by increasing a current flowing through the electronic control unit of the at least one electrical component; and A computer system communicatively connected to the first measuring device is configured to obtain currents and voltages of electronic control units of the multiple electrical components from the first measuring device, and determine whether a fault occurs in each of the electrical components based on the currents and voltages of the electronic control units of the multiple electrical components and determine whether the feedback and processing mechanisms of each of the electrical components in a fault state are normal.
2. The test device according to claim 1, wherein: The testing device further comprises a second measuring device housed in the cabinet and communicatively connected to the computer system, the second measuring device being configured to measure the current and voltage of the first storage battery; and The computer system is also configured to obtain the current and voltage of the first energy accumulator from the second measuring device, and input the current and voltage of the electronic control unit of the multiple electrical components and the current and voltage of the first energy accumulator into a preset fault model, so as to determine whether the vehicle fails and identify the fault type when the vehicle fails through the fault model.
3. The test device according to claim 1 or 2, wherein: The fault simulation device further comprises at least one second electronic load; Wherein, the second electronic load is configured to simulate an overload fault of the first storage battery by increasing a current flowing through the first storage battery; and / or Wherein, the second electronic load is configured to be connected in series with the electronic control unit of at least another electrical component among the multiple electrical components to the first control circuit, so as to simulate an overload fault of the electronic control unit of the at least another electrical component by increasing the current flowing through the electronic control unit of the at least another electrical component.
4. The test device according to claim 3, wherein: The first electronic load is configured to be connected in series with an electronic control unit of a first electrical component among the plurality of electrical components to the first control circuit, and the second electronic load is configured to be connected in series with an electronic control unit of a second electrical component among the plurality of electrical components to the first control circuit, wherein an overload current of the first electrical component is smaller than an overload current of the second electrical component; Preferably, the maximum current of the first electronic load is smaller than the maximum current of the second electronic load, and the overload current of the first electrical component is smaller than the maximum current of the first electronic load, while the overload current of the second electrical component is larger than the maximum current of the first electronic load and smaller than the maximum current of the second electronic load.
5. The test device according to claim 2, wherein: The vehicle further comprises a plurality of further electrical components and comprises a second battery, the second battery being configured to supply power to the plurality of further electrical components, the electronic control units of the plurality of further electrical components being electrically connected to the second battery in parallel with each other to form a second control circuit, wherein the rated voltage of the second battery is greater than the rated voltage of the first battery; The first measuring device is further arranged to measure current and voltage of electronic control units of the plurality of further electrical components; The second measuring device is further configured to measure the current and voltage of the second battery; and The computer system is also configured to obtain the current and voltage of the electronic control units of the multiple additional electrical components from the first measuring device, and based on the current and voltage of the electronic control units of the multiple additional electrical components, determine whether each of the additional electrical components has a fault and determine whether the feedback and processing mechanism of each of the additional electrical components in a fault state is normal.
6. The test device according to claim 5, wherein: The fault simulation device further comprises at least one second electronic load; Wherein, the second electronic load is configured to simulate an overload fault of the first storage battery or the second storage battery by increasing a current flowing through the first storage battery or the second storage battery; and / or The second electronic load is configured to be connected in series with the electronic control unit of at least one electrical component among the multiple other electrical components to the second control circuit, so as to simulate an overload fault of the electronic control unit of the at least one electrical component by increasing the current flowing through the electronic control unit of the at least one electrical component.
7. The test device according to any one of claims 1 to 6, wherein: The current of the first electronic load is adjustable, and / or the current of the second electronic load is adjustable; Preferably, the fault simulation device includes only one first electronic load and only one second electronic load.
8. The test device according to claim 7, wherein: The first electronic load is configured to be selectively connected in series with an electronic control unit of one of the plurality of electrical components into the first control circuit; The test device further comprises a switching device electrically connected to the computer system and to the first electronic load, and the computer system is further configured to: controlling the switching device so as to connect the first electronic load and the electronic control unit of the electrical component to be tested among the plurality of electrical components in series to the first control circuit; and The current of the first electronic load is adjusted to adapt to the overload current of the electrical component to be tested connected in series with the first electronic load.
9. The test device according to any one of claims 1 to 8, wherein: The fault simulation device also includes a short circuit and open circuit simulator, which is configured to short-circuit or open circuit the circuit between the electronic control unit of at least one electrical component and the first battery or the second battery to simulate a short circuit fault or open circuit fault of the electronic control unit of the at least one electrical component.
10. The test device according to any one of claims 1 to 9, wherein: The test equipment further comprises a data recording device electrically connected to a data bus of the vehicle and to the computer system, the data bus being electrically connected to an electronic control unit of the electrical component, the data recording device being housed in the cabinet and being configured to record test data of the vehicle; and / or The test equipment further comprises a data collection device electrically connected to the OBD interface of the vehicle and the computer system, the data collection device being housed in the cabinet and configured to collect diagnostic data from the OBD interface, the computer system being further configured to obtain the diagnostic data from the data collection device and compare the diagnostic data with a fault identified based on the current and voltage of the electronic control unit of the electrical component and optionally the current and voltage of the battery; and / or The testing device further includes a charger housed in the cabinet and used for charging the battery.
11. The test device according to any one of claims 1 to 10, wherein: The test equipment is configured to simultaneously test a plurality of vehicles and monitor corresponding test data; In particular, the testing device is configured to simultaneously test a plurality of vehicles in a dormant state to test whether the vehicles are normal after being dormant for a preset time.