Power transmission tower surrounding environment monitoring system based on optical identification tag
Through an environmental monitoring system based on optical recognition tags and combined with deep fusion learning technology, the problem of real-time prediction and fault warning of ice coating on transmission towers has been solved, and the safe and stable operation of transmission towers and transmission lines has been achieved.
Patent Information
- Application Number
- CN202411275232.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-12
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-09-12
AI Technical Summary
It is difficult to perform in-depth fusion learning by collecting the icing conditions in the area where the transmission tower is located and combining the historical data of the area with the existing technology. This makes it difficult to provide safety early warning for the impact of the real-time environmental status of the transmission tower, affecting the stable and safe operation of the transmission tower and transmission lines.
An environmental monitoring system around transmission towers based on optical identification tags is adopted, using deep fusion learning technology, combined with real-time snowfall data and historical data, to predict the ice coverage area and thickness of transmission towers, and perform fault status early warning analysis based on historical operating data. Risk assessment and early warning through optical image data monitoring and dynamic decision-making units.
It achieves accurate prediction and early warning of icing conditions and fault conditions of transmission towers and transmission lines, ensuring the safe and stable operation of transmission towers and their lines, and reducing risks to surrounding residents and property.
Smart Images

Figure CN118799818A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of environmental monitoring, and in particular to a system for monitoring the surrounding environment of a transmission tower based on optical identification tags. Background Art
[0002] As the main channel for long-distance transmission of electric energy, the normal operation of transmission lines is the basis for ensuring the safety and stability of the power system, and is also the cornerstone of social and economic development and stability. It undertakes the allocation of energy resources and is an important device for ensuring national energy security and meeting the development of the national economy. Transmission towers are the support points of overhead transmission lines. In real life, it is extremely necessary to conduct safety monitoring of transmission towers, especially in winter. Strong winds and snowfalls will cause ice on the surface of transmission towers, which will lead to overload of transmission towers and transmission lines supported by them. In severe cases, it will cause accidents such as tower collapse and line disconnection, and then cause fires, threatening the safety of life and property of surrounding residents. However, the existing environmental monitoring technology around transmission towers is difficult to predict and analyze the possible ice coverage and safe operation status of transmission towers by collecting the ice coverage in the area where the transmission towers are located and combining the historical data of the area for deep fusion learning, resulting in the impact of the real-time environmental status faced by the transmission towers. It is difficult to conduct safety warnings according to monitoring needs, which is not conducive to ensuring the stability of transmission towers and the safe operation of transmission lines, but also puts residents and property around transmission towers at risk. Summary of the invention
[0003] In view of the above problems existing in the technical field of existing environmental monitoring, the present invention is proposed.
[0004] Therefore, one of the objects of the present invention is to provide a transmission tower surrounding environment monitoring system based on optical identification tags, which utilizes deep fusion learning technology to predict the ice cover area and / or thickness that may be formed on a preset transmission tower and its lines based on the snowfall data obtained by real-time monitoring in a preset area in winter and the historical snowfall data monitored in the area. While making the prediction, it also performs early warning analysis on possible fault conditions of the transmission tower in future periods based on the historical operation data of the transmission tower, and specifies management plans to facilitate the safe and stable operation of the transmission tower and its lines.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: The present invention provides a transmission tower surrounding environment monitoring system based on optical identification tags, comprising: A comprehensive information acquisition module, used to acquire the regional location of the preset transmission tower, as well as the historical ice coverage data of the preset transmission tower in winter and the historical snowfall data of the regional location of the preset transmission tower in winter; An optical image data acquisition module, used to collect ice-covered optical image data of a preset transmission tower area during snowfall, and to collect historical ice-covered optical image data of the area; A data fusion analysis module, which is used to respond to the historical ice cover data and historical snowfall data of the comprehensive information acquisition module and the ice cover optical image data of the optical image data acquisition module, and analyze and compare the optical image data collected in different months of winter at a preset area, generate a data set from the optical image data collected in different months of winter, and collect the optical image data features of the corresponding month in the data set; An image data monitoring unit is used to monitor the optical image data of ice-covered transmission towers in a preset area under different snowfall conditions, and to classify the ice-covered optical image data by labels, and to perform correlation analysis on the snow accumulation area and thickness of the ice-covered optical image data classified by labels, wherein the image data monitoring unit includes a prediction module, an analysis module and a calculation module; The prediction module is used to predict the ice-covered area of the preset transmission tower under different snowfall conditions, and specify the unit snowfall time and the unit monitoring time, and monitor the snowfall data within the unit monitoring time; The analysis module is used to give a change in snow area within the unit time, divide the change, and analyze the increase in snow thickness under different change conditions; The calculation module is used to calculate the time required for the snow thickness to increase with the snowfall time; A dynamic decision-making unit is used to preset the increase value of snow thickness in different time periods according to the change of snowfall amount and / or the predicted snowfall duration. When the snow thickness in the said time period exceeds the preset increase value, the system determines that the preset transmission tower is in a risky operation state and issues an early warning. Otherwise, no determination is made; The monitoring terminal is used to record the communication base stations and / or communication base station operators that match the preset transmission tower, receive the field data uploaded by the collection monitoring point, and update the background data at the same time. When an early warning is issued in the area where the preset transmission tower is located, a request for obtaining information on the early warning status of the transmission tower is initiated to the corresponding communication base stations and / or communication base station operators in the preset monitoring area.
[0006] As a preferred solution of the present invention, in the data fusion analysis module, the different months are divided into the month with the maximum ice-covered optical image data and the month with the minimum ice-covered optical image data, and the data set of the month with the maximum ice-covered optical image data is divided into a training set, a validation set and a test set, and a data model of the month with the maximum ice-covered optical image data is constructed, and the change characteristics of the ice-covered optical image data of the month are analyzed.
[0007] As a preferred solution of the present invention, based on the changing characteristics of the ice-covered optical image data, the intermediate value image data of the changing characteristics in the month is collected, and the changing pattern of the intermediate value image data to the maximum ice-covered optical image data in the month is analyzed, the changing pattern is uploaded to the data model, and the data model is updated.
[0008] As a preferred solution of the present invention, wherein: obtaining the time period with the most occurrences of the intermediate value image data of the month, dividing the most occurrences of the time period into , and Time period, and the time range represented by each time period is the early, middle and late months of the month respectively, and the minimum snowfall data is preset in the most time period, and the historical maximum intermediate value image data of the most time period is obtained at the same time, when the snowfall data monitored in the time period does not exceed the minimum snowfall data, the system determines that the ice cover data in the time period will not exceed the historical maximum intermediate value image data, otherwise, no determination is made.
[0009] As a preferred solution of the present invention, wherein: in the image data monitoring unit, the label classification is performed according to , , ..., Divide into, Indicates The method further comprises collecting the operating indicators of the preset transmission towers under different label data conditions, and analyzing the correlation between the operating indicators and the changes in the ice-covered optical image data.
[0010] As a preferred solution of the present invention, the dynamic decision unit includes a receiving module and a tracking module, wherein the receiving module is used to receive the transmission tower operation data according to the real-time monitored ice optical image data, and analyze the correlation change between the ice optical image data change and the transmission tower operation data; The tracking module is used to track the maximum change value of the transmission tower operation data in a preset month, the preset month includes the month with the maximum ice optical image data, and collects the ice optical image data features under the condition of the maximum change value of the transmission tower operation data in the preset month, and calculates the influence of the ice optical image data features on the transmission tower operation data, which is calculated according to the following formula: ; In the formula, Indicates that the location of the preset transmission tower is the first in the historically collected operation data. The maximum change value, Indicates the preset transmission tower The first collected data corresponding to the change of its operating data Ice-covered optical image data features, Indicates the number of transmission towers scheduled for the month The difference between the ice cover optical image data collected times.
[0011] As a preferred solution of the present invention, the difference of the collected ice-covered optical image data is divided into steps according to the first maximum difference, the second maximum difference and the third maximum difference, and the snowfall change characteristics of the preset transmission tower area under the three types of difference data are obtained, and the change characteristics are divided into a number of evaluation indicators, and the evaluation indicator data of the preset transmission tower in the said month are statistically obtained, the data is normalized, and the weight of each evaluation indicator is calculated.
[0012] As a preferred solution of the present invention, the Monte Carlo method is used to sample the ice-covered optical image data of the area range involved in the preset transmission tower area in the said month, obtain the ice-covered optical image data of different transmission towers within the said area, and analyze the operating status of the transmission tower under different ice-covered optical image data, and at the same time establish the impact of snowfall data in different months on the transmission tower and reliability evaluation.
[0013] As a preferred solution of the present invention, historical evaluation and comparison are performed on the operating status characteristics of the preset transmission tower corresponding to the sampling data, and different hierarchical management schemes are formulated for different evaluation and comparison result data. Specifically, the evaluation and comparison result data include evaluation and comparison result data of other transmission towers within the preset transmission tower area location range, and data characteristics of the comparison result data are analyzed at the same time.
[0014] As a preferred solution of the present invention, in which: minimum ice-covered optical image data is given in different hierarchical management schemes, and a critical threshold is preset based on the minimum ice-covered optical image data. When the sampling data of the transmission tower area preset in the future time period in the month with the maximum ice-covered optical image data does not exceed the critical threshold, the system determines that the conditions for starting the corresponding hierarchical management scheme have not been met, otherwise, no determination is made.
[0015] Beneficial effects of the present invention: The present invention utilizes deep fusion learning technology to predict the ice cover area and / or thickness that may be formed on a preset transmission tower and its lines based on the snowfall data obtained by real-time monitoring in a preset area in winter and the historical snowfall data monitored in the area. While making the prediction, the present invention performs early warning analysis on possible fault states of the transmission tower in future periods based on the historical operation data of the transmission tower. At the same time, based on the changes in the collected optical image data of the ice covering the transmission tower, the probability of failure of the transmission tower and its lines is judged, and a management plan is specified, thereby facilitating the safe and stable operation of the transmission tower and its lines. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them: Figure 1 It is a schematic diagram of the modular structure of a system for monitoring the surrounding environment of a transmission tower based on optical identification tags according to an embodiment of the present invention; Figure 2 A schematic diagram of a modular structure of a dynamic decision-making unit according to an embodiment of the present invention; Figure 3 A schematic diagram of the network structure of a transmission tower surrounding environment monitoring system based on optical identification tags according to an embodiment of the present invention; Figure 4 A schematic diagram of the system flow structure of an embodiment of the present invention; Numbers in the figure: 110 - comprehensive information acquisition module; 120 - optical image data acquisition module; 130 - data fusion analysis module; 140 - image data monitoring unit; 1401 - prediction module; 1402 - analysis module; 1403 - calculation module; 150 - dynamic decision unit; 1501 - receiving module; 1502 - tracking module; 160 - monitoring terminal. DETAILED DESCRIPTION
[0017] In order to make the purpose, technical solution and advantages of the embodiment of the present invention clearer, the technical solution of the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings of the embodiment of the present invention. Obviously, the described embodiment is a part of the embodiment of the present invention, not all of the embodiments. Based on the described embodiment of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention.
[0018] Since it is difficult for existing technologies to predict and analyze the icing that the transmission tower may encounter and its safe operation status by collecting ice conditions in the area where the transmission tower is located and combining it with historical data in the area for deep fusion learning, it is difficult to issue safety warnings based on monitoring needs for the impact of the real-time environmental conditions faced by the transmission tower. This is not only not conducive to ensuring the stability of the transmission tower and the safe operation of the transmission line, but also puts residents and property around the transmission tower at risk.
[0019] Based on this, the present invention proposes a transmission tower surrounding environment monitoring system based on optical recognition tags, which uses deep fusion learning technology to predict the ice cover area and / or thickness that may be formed on the preset transmission tower and its lines according to the snowfall data obtained by real-time monitoring in the preset area in winter and the historical snowfall data monitored in the area. While making the prediction, it also conducts early warning analysis on the possible fault conditions of the transmission tower in the future period based on the historical operation data of the transmission tower, and specifies a management plan, which is conducive to the safe and stable operation of the transmission tower and its lines.
[0020] The present invention is further described in detail below through embodiments and in conjunction with the accompanying drawings.
[0021] Reference Figures 1 to 4 , is an embodiment of the present invention, which provides a transmission tower surrounding environment monitoring system based on optical identification tags, including: The comprehensive information acquisition module 110 is used to obtain the regional location of the preset transmission tower, the historical ice coverage data of the preset transmission tower in winter, and the historical snowfall data of the regional location of the preset transmission tower in winter; It should be noted that in this embodiment, the comprehensive information acquisition module 110 includes a GPS satellite navigation locator and / or a Beidou satellite navigation locator, wherein the comprehensive information acquisition module 110 also includes acquiring the area of the transmission line connected to the preset transmission tower; The optical image data acquisition module 120 is used to collect ice-covered optical image data of a preset transmission tower area during snowfall, and to collect historical ice-covered optical image data of the area; It should be noted that in this embodiment, the ice-covered optical image data is optical image data of ice-covered surface of a preset transmission tower, and also includes optical image data of a transmission line connected thereto; It should also be noted that in this embodiment, the optical image data acquisition module 120 includes a CCD camera and / or an optical camera; The data fusion analysis module 130 is used to respond to the historical ice cover data and the historical snowfall data of the comprehensive information acquisition module 110 and the ice cover optical image data of the optical image data acquisition module 120, and analyze and compare the optical image data collected in different months of winter at the preset area location, generate a data set from the optical image data collected in different months of winter, and collect the optical image data features of the corresponding month in the data set; It should be noted that in this embodiment, different winter months include December, January and February; Specifically, this embodiment further includes analyzing and comparing the optical image data features collected in the corresponding month with the optical image data features collected in other months in the data set, obtaining the associated data features therein, and generating a prediction model by integrating the associated data features; at the same time, using the Q-learning algorithm for reinforcement learning to optimize the prediction model; It should be emphasized in this embodiment that different months are divided into the month with the maximum ice-covered optical image data and the month with the minimum ice-covered optical image data, and the training set, the validation set and the test set are divided based on the data set of the month with the maximum ice-covered optical image data, and the data model of the month with the maximum ice-covered optical image data is constructed, and the change characteristics of the monthly ice-covered optical image data are analyzed at the same time; Among them, based on the change characteristics of the ice-covered optical image data, the median image data of the change characteristics in the month is collected, and the change law of the median image data to the maximum ice-covered optical image data in the month is analyzed, the change law is uploaded to the data model, and the data model is updated; This embodiment further obtains the time period with the most occurrences of the intermediate value image data of the month, and divides the most time period into , and Time period, and the time range represented by each time period is the first, middle and last ten days of the month in sequence, and the minimum snowfall data is preset in the most time period, and the historical maximum intermediate value image data of the most time period is obtained at the same time. When the snowfall data monitored in the time period does not exceed the minimum snowfall data, the system determines that the ice cover data in the time period will not exceed the historical maximum intermediate value image data, otherwise, no determination is made; The image data monitoring unit 140 is used to monitor the optical image data of ice-covered transmission towers in a preset area under different snowfall conditions, classify the optical image data of ice-covered transmission towers by labels, and perform correlation analysis on the snow accumulation area and thickness of the label-classified optical image data of ice-covered transmission towers. The image data monitoring unit 140 includes a prediction module 1401, an analysis module 1402, and a calculation module 1403. This embodiment further illustrates that the tags are classified according to , , ..., Divide into, Indicates The data is labeled and the operation indicators of the preset transmission towers are collected under different label data conditions, and the correlation between the operation indicators and the changes in ice-covered optical image data is analyzed; Among them, the operating indicators include the flashover follow-current value of the insulator placed on the preset transmission tower, and the current, voltage and power of the transmission line connected to the preset transmission tower.
[0022] The prediction module 1401 is used to predict the ice-covered area of the preset transmission tower under different snowfall conditions, and specify the unit snowfall time and the unit monitoring time, and monitor the snowfall data within the unit monitoring time; The analysis module 1402 is used to divide the change in snow area given in unit time and analyze the increase in snow thickness under different change conditions; Specifically, in this embodiment, a given snow accumulation area change is divided into a first change, a second change, and a third change, and the snow accumulation area of each change is increased by 10%, and for every 10% increase in the given snow accumulation area, the snow thickness of the preset transmission tower increases by 3-5%, and at the same time, a risk threshold is preset based on the second change. When the snow accumulation area of the preset transmission tower exceeds the risk threshold, the system determines that the transmission tower is in a risky operation state and issues an early warning, otherwise, no determination is made; The calculation module 1403 is used to calculate the time required for the snow thickness to increase with the snowfall time; The dynamic decision unit 150 is used to preset the increase value of snow thickness in different time periods according to the change of snowfall amount and / or the predicted snowfall duration. When the snow thickness in the time period exceeds the preset increase value, the system determines that the preset transmission tower is in a risky operation state and issues an early warning. Otherwise, no determination is made. This embodiment further illustrates that the dynamic decision unit 150 includes a receiving module 1501 and a tracking module 1502, the receiving module 1501 is used to receive the transmission tower operation data according to the real-time monitored ice optical image data, and analyze the correlation change between the ice optical image data change and the transmission tower operation data; It should be noted that in this embodiment, the transmission tower operation data includes measurement data, wherein the measurement data includes insulator temperature, electrical parameters and preset transmission tower pole inclination data; The tracking module 1502 is used to track the maximum change value of the transmission tower operation data in the preset month, the preset month includes the month with the maximum ice optical image data, and collect the ice optical image data features under the condition of the maximum change value of the transmission tower operation data in the month, and calculate the influence of the ice optical image data features on the transmission tower operation data, which is calculated according to the following formula: ; In the formula, Indicates that the location of the preset transmission tower is the first in the historically collected operation data. The maximum change value, Indicates the preset transmission tower The first collected data corresponding to the change of its operating data Ice-covered optical image data features, Indicates the number of transmission towers scheduled for the month The difference of ice cover optical image data collected in times; At the same time, based on the above, this embodiment divides the difference of the collected ice-covered optical image data into steps according to the first maximum difference, the second maximum difference and the third maximum difference, obtains the snowfall change characteristics of the preset transmission tower area under the three types of difference data, and divides the change characteristics into several evaluation indicators, calculates the evaluation indicator data of the preset transmission tower in the month, normalizes the data, and calculates the weight of each evaluation indicator; The monitoring terminal 160 is used to record the communication base stations and / or communication base station operators that match the preset transmission towers, receive the field data uploaded by the collection monitoring points, and update the background data at the same time. When an early warning is issued in the area where the preset transmission tower is located, an information acquisition request for the early warning status of the transmission tower is initiated to the corresponding communication base stations and / or communication base station operators in the preset monitoring area.
[0023] Among them, on the basis of the above, this embodiment also includes a further implementation plan: using the Monte Carlo method to sample the ice-covered optical image data of the area range involved in the preset transmission tower area in month, obtaining the ice-covered optical image data of different transmission towers within the area range, and analyzing the operating status of the transmission tower under different ice-covered optical image data, and at the same time establishing the impact of snowfall data in different months on the transmission tower and reliability evaluation.
[0024] Furthermore, historical evaluation and comparison are performed on the operating status characteristics of the preset transmission towers corresponding to the sampled data, and different hierarchical management plans are formulated for different evaluation and comparison result data. Specifically, the evaluation and comparison result data include the evaluation and comparison result data of other transmission towers within the preset transmission tower area location range, and the data characteristics of the comparison result data are analyzed at the same time.
[0025] Specifically, the minimum ice-covered optical image data is given in different hierarchical management schemes, and a critical threshold is preset based on the minimum ice-covered optical image data. When the sampling data of the preset transmission tower area in the future time period in the month with the maximum ice-covered optical image data does not exceed the critical threshold, the system determines that the conditions for starting the corresponding hierarchical management scheme have not been met, otherwise, no determination is made.
[0026] In summary, the present invention uses deep fusion learning technology to predict the ice cover area and / or thickness that may be formed on the preset transmission tower and its lines based on the snowfall data obtained by real-time monitoring in the preset area in winter and the historical snowfall data monitored in the area. While making the prediction, the present invention performs early warning analysis on the possible fault conditions of the transmission tower in the future period based on the historical operation data of the transmission tower. At the same time, based on the changes in the collected optical image data of the ice covering the transmission tower, the probability of failure of the transmission tower and its lines is judged, and a management plan is specified, which is conducive to the safe and stable operation of the transmission tower and its lines.
[0027] In the above embodiments, it can be implemented in whole or in part by software, hardware, firmware or any combination thereof. When implemented using software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, the process or function according to the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable devices. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium.
[0028] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine different embodiments or examples described in this specification and the features of different embodiments or examples, unless they are contradictory.
[0029] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include at least one of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0030] Any process or method description in the flow chart or otherwise described herein can be understood to represent a module, fragment or portion of a code including one or more executable instructions for implementing the steps of a specific logical function or process. And the scope of the preferred embodiment of the present application includes other implementations, in which the functions may not be performed in the order shown or discussed, including in a substantially simultaneous manner or in a reverse order according to the functions involved.
[0031] The logic and / or steps represented in the flowchart or otherwise described herein, for example, can be considered as an ordered list of executable instructions for implementing logical functions, which can be embodied in any computer-readable medium for use by an instruction execution system, apparatus or device (such as a computer-based system, a system including a processor or other system that can fetch instructions from an instruction execution system, apparatus or device and execute instructions), or used in combination with these instruction execution systems, apparatuses or devices.
[0032] It should be understood that the various parts of the present application can be implemented with hardware, software, firmware or a combination thereof. In the above embodiments, multiple steps or methods can be implemented with software or firmware stored in a memory and executed by a suitable instruction execution system. All or part of the steps of the above embodiment method can be completed by instructing the relevant hardware through a program, which can be stored in a computer-readable storage medium, and when the program is executed, it includes one of the steps of the method embodiment or a combination thereof.
[0033] In addition, each functional unit in each embodiment of the present application can be integrated into a processing module, or each unit can exist physically separately, or two or more units can be integrated into one module. The above-mentioned integrated module can be implemented in the form of hardware or in the form of a software functional module. If the above-mentioned integrated module is implemented in the form of a software functional module and sold or used as an independent product, it can also be stored in a computer-readable storage medium. The storage medium can be a read-only memory, a disk or an optical disk, etc.
[0034] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. A transmission tower surrounding environment monitoring system based on optical identification tags, characterized in that: include: A comprehensive information acquisition module, used to acquire the regional location of the preset transmission tower, as well as the historical ice coverage data of the preset transmission tower in winter and the historical snowfall data of the regional location of the preset transmission tower in winter; An optical image data acquisition module, used to collect ice-covered optical image data of a preset transmission tower area during snowfall, and to collect historical ice-covered optical image data of the area; A data fusion analysis module, which is used to respond to the historical ice cover data and historical snowfall data of the comprehensive information acquisition module and the ice cover optical image data of the optical image data acquisition module, and analyze and compare the optical image data collected in different months of winter at a preset area, generate a data set from the optical image data collected in different months of winter, and collect the optical image data features of the corresponding month in the data set; An image data monitoring unit is used to monitor the optical image data of ice-covered transmission towers in a preset area under different snowfall conditions, and to classify the ice-covered optical image data by labels, and to perform correlation analysis on the snow accumulation area and thickness of the ice-covered optical image data classified by labels, wherein the image data monitoring unit includes a prediction module, an analysis module and a calculation module; The prediction module is used to predict the ice-covered area of the preset transmission tower under different snowfall conditions, and specify the unit snowfall time and the unit monitoring time, and monitor the snowfall data within the unit monitoring time; The analysis module is used to give a change in snow area within the unit time, divide the change, and analyze the increase in snow thickness under different change conditions; The calculation module is used to calculate the time required for the snow thickness to increase with the snowfall time; A dynamic decision-making unit is used to preset the increase value of snow thickness in different time periods according to the change of snowfall amount and / or the predicted snowfall duration. When the snow thickness in the said time period exceeds the preset increase value, the system determines that the preset transmission tower is in a risky operation state and issues an early warning. Otherwise, no determination is made; The monitoring terminal is used to record the communication base stations and / or communication base station operators that match the preset transmission tower, receive the field data uploaded by the collection monitoring point, and update the background data at the same time. When an early warning is issued in the area where the preset transmission tower is located, a request for obtaining information on the early warning status of the transmission tower is initiated to the corresponding communication base stations and / or communication base station operators in the preset monitoring area.
2. A transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 1, characterized in that: In the data fusion and analysis module, the different months are divided into the month with the maximum ice-covered optical image data and the month with the minimum ice-covered optical image data, and the training set, the validation set and the test set are divided based on the data set of the month with the maximum ice-covered optical image data, and a data model of the month with the maximum ice-covered optical image data is constructed, and the change characteristics of the ice-covered optical image data of the month are analyzed.
3. A transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 2, characterized in that: Based on the changing characteristics of the ice-covered optical image data, the intermediate value image data of the changing characteristics in the month is collected, and the changing pattern of the intermediate value image data to the maximum ice-covered optical image data in the month is analyzed, the changing pattern is uploaded to the data model, and the data model is updated.
4. A transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 3, characterized in that: Obtain the time period with the most median image data of the month, and divide the most median time period into , and Time period, and the time range represented by each time period is the early, middle and late months of the month respectively, and the minimum snowfall data is preset in the most time period, and the historical maximum intermediate value image data of the most time period is obtained at the same time, when the snowfall data monitored in the time period does not exceed the minimum snowfall data, the system determines that the ice cover data in the time period will not exceed the historical maximum intermediate value image data, otherwise, no determination is made.
5. The transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 1, characterized in that: In the image data monitoring unit, the labels are classified according to , , ..., Divide into, Indicates The method further comprises collecting the operating indicators of the preset transmission towers under different label data conditions, and analyzing the correlation between the operating indicators and the changes in the ice-covered optical image data.
6. The transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 2, characterized in that: The dynamic decision-making unit includes a receiving module and a tracking module, wherein the receiving module is used to receive the transmission tower operation data according to the real-time monitored ice optical image data, and analyze the correlation change between the ice optical image data change and the transmission tower operation data; The tracking module is used to track the maximum change value of the transmission tower operation data in a preset month, the preset month includes the month with the maximum ice optical image data, and collects the ice optical image data features under the condition of the maximum change value of the transmission tower operation data in the preset month, and calculates the influence of the ice optical image data features on the transmission tower operation data, which is calculated according to the following formula: ; In the formula, Indicates that the location of the preset transmission tower is the first in the historically collected operation data. The maximum change value, Indicates the preset transmission tower The first collected data corresponding to the change of its operating data Ice-covered optical image data features, Indicates the number of transmission towers scheduled for the month The difference between the ice cover optical image data collected times.
7. A transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 6, characterized in that: The difference of the collected ice-covered optical image data is divided into a step-by-step manner according to the first maximum difference, the second maximum difference and the third maximum difference, and the snowfall change characteristics of the preset transmission tower area under the three types of difference data are obtained, and the change characteristics are divided into a number of evaluation indicators, and the evaluation indicator data of the preset transmission tower in the month are statistically calculated, the data is normalized, and the weight of each evaluation indicator is calculated.
8. The transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 6, characterized in that: The Monte Carlo method is used to sample the ice-covered optical image data of the area covered by the preset transmission tower area in the said month, to obtain the ice-covered optical image data of different transmission towers within the said area, and to analyze the operating status of the transmission towers under different ice-covered optical image data. At the same time, the influence of snowfall data in different months on the transmission tower and the reliability evaluation are established.
9. The transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 8, characterized in that: A historical evaluation and comparison is performed on the operating status characteristics of the preset transmission tower corresponding to the sampling data, and different hierarchical management schemes are formulated for different evaluation and comparison result data. Specifically, the evaluation and comparison result data include evaluation and comparison result data of other transmission towers within the preset transmission tower area location range, and data characteristics of the comparison result data are analyzed at the same time.
10. The transmission tower surrounding environment monitoring system based on optical identification tags as claimed in claim 9, characterized in that: The minimum ice-covered optical image data is given in different hierarchical management schemes, and a critical threshold is preset based on the minimum ice-covered optical image data. When the sampling data of the transmission tower area preset in the future time period in the month with the maximum ice-covered optical image data does not exceed the critical threshold, the system determines that the conditions for starting the corresponding hierarchical management scheme have not been met, otherwise, no determination is made.
Citation Information
Patent Citations
Power transmission line icing risk early warning method and device, medium and electronic equipment
CN112541636A
Disaster prediction method and system for power transmission line, and storage medium
CN118134107A
Method for identifying disasters through deep learning in power transmission corridor operation area
CN118537753A
Early warning method for icefall-caused moraine lake outburst disasters
US11645900B1
Cited By
Method and device for maintaining ice and snow test road
CN121685455A
A method and apparatus for maintaining an ice and snow testing road
CN121685455B