Cell load balancing method, device, equipment and computer program product
Through the target policy network trained by the cell distribution topology diagram and historical load data, the cell load is dynamically adjusted, solving the problem of cell load imbalance and improving network resource utilization and user experience.
Patent Information
- Application Number
- CN202410717076.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-04
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-06-04
AI Technical Summary
In the existing technology, unbalanced cell loads lead to low network resource utilization, prolonged handover times for users in high-load cells, increased risk of handover failures, and inaccurate adjustment of preset thresholds, resulting in resource waste.
By obtaining the cell distribution topology structure diagram and historical load data, the target policy network is trained to dynamically predict the cell load situation, determine the target adjustment strategy, avoid cell overload, and maximize resource utilization.
It achieves dynamic balancing of cell loads, reduces the risk of cell overload, improves network resource utilization, and reduces user handover delays and failure risks.
Smart Images

Figure CN118804174A_ABST
Abstract
Description
Technical Field
[0001] The embodiments of the present application relate to the field of communication technology, and in particular, to a cell load balancing method, apparatus, device, and computer program product. Background Art
[0002] In a mobile communication network, different cells may have different loads. Some cells may be heavily loaded, while other cells are relatively lightly loaded. If the load is unbalanced, some cell resources will be over-utilized, while other cell resources will be idle, thus affecting the overall performance of the network and the user experience. Therefore, by achieving cell load balancing, the utilization of network resources can be effectively optimized, the network capacity and coverage can be increased, and the user's communication quality and experience can be improved.
[0003] The methods for achieving cell load balancing can be divided into the following categories:
[0004] (1) Obtaining load information of adjacent cells. When a cell is overloaded, load balancing is performed by moving user equipment to adjacent cells with relatively lighter loads. For example, the mobility parameters that need to be modified are determined based on the load information of the cell and the load information of the adjacent cells, and a parameter modification request is sent to the adjacent cells; and corresponding operations are performed based on the information fed back by the adjacent cells in response to the parameter modification request;
[0005] (2) The predicted load rate of the cell is monitored according to a pre-established prediction model, and users of the cell whose predicted load rate is greater than a first threshold value are switched to the cell whose predicted load rate is less than a second threshold value.
[0006] However, in the related art, performing user switching when the cell is in a high-load state may increase the switching delay and increase the risk of switching failure. In addition, using a preset threshold value for load adjustment may result in a situation where the load rate of some cells is close to the threshold while the load rate of their adjacent cells is very low, resulting in low utilization of network resources. Summary of the invention
[0007] The embodiments of the present application provide a cell load balancing method, apparatus, device and computer program product to at least solve the problem of low utilization of network resources in related solutions.
[0008] In order to solve the above technical problems, this application is implemented as follows:
[0009] In the first aspect, an embodiment of the present application provides a cell load balancing method, comprising: obtaining a pre-constructed cell distribution topology structure diagram, the cell distribution topology structure diagram including multiple cells and adjacency relationships between each of the cells, the adjacency relationship being used to characterize that user equipment switching can occur between cells; determining load forecast data for each of the cells based on historical load data of each of the cells in the cell distribution topology structure diagram; determining a target adjustment strategy for each of the cells based on the load forecast data of each of the cells and a target strategy network to achieve cell load balancing; wherein the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationships between each of the cells in the cell distribution topology structure diagram.
[0010] In the second aspect, an embodiment of the present application provides a cell load balancing device, including: an acquisition module, used to acquire a pre-constructed cell distribution topology structure diagram, the cell distribution topology structure diagram including multiple cells and the adjacency relationship between each of the cells, the adjacency relationship being used to characterize that user equipment switching can occur between cells; a determination module, used to determine the load prediction data of each of the cells based on the historical load data of each of the cells in the cell distribution topology structure diagram; a balancing module, used to determine the target adjustment strategy of each of the cells based on the load prediction data of each of the cells and the target strategy network, so as to achieve cell load balancing; wherein the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology structure diagram.
[0011] In a third aspect, an embodiment of the present application provides an electronic device, comprising a processor and a memory, wherein the memory stores programs or instructions that can be run on the processor, and when the program or instructions are executed by the processor, the steps of the method described in the first aspect above are implemented.
[0012] In a fourth aspect, an embodiment of the present application provides a readable storage medium, on which a program or instruction is stored. When the program or instruction is executed by a processor, the steps of the method described in the first aspect above are implemented.
[0013] In a fifth aspect, an embodiment of the present application provides a computer program product, which includes a computer program stored on a non-transitory computer-readable storage medium, and the computer program includes program instructions. When the program instructions are executed by a computer, the computer executes the steps of the method described in the first aspect above.
[0014] In an embodiment of the present application, a pre-constructed cell distribution topology diagram is obtained, and the cell distribution topology diagram includes multiple cells and the adjacency relationship between each cell, and the adjacency relationship is used to characterize that user equipment switching can occur between cells; according to the historical load data of each cell in the cell distribution topology diagram, the load forecast data of each cell is determined; according to the load forecast data of each cell and the target strategy network, the target adjustment strategy of each cell is determined to achieve cell load balancing; wherein, the target strategy network is based on the historical load data of multiple cells and the adjacency relationship between each cell in the cell distribution topology diagram. Trained. In this way, the target adjustment strategy of each cell is determined based on the load forecast data of each cell and the target strategy network, and the load situation of each cell at a future moment can be dynamically predicted and the target adjustment strategy can be determined in time to avoid cell overload. Moreover, the target strategy network is based on the historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology diagram. It can enable the target strategy network to learn the implicit relationship between the cell and the adjacent cell from the cell distribution topology diagram, and determine the target adjustment strategy of each cell based on the load forecast data and the cell topology structure, so that the resource utilization of the entire network is maximized.
[0015] It should be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0017] Figure 1 A schematic diagram of a flow chart of a cell load balancing method provided in an embodiment of the present application is shown;
[0018] Figure 2 A schematic diagram of the structure of a deep learning network model provided in an embodiment of the present application is shown;
[0019] Figure 3 A schematic diagram of a flow chart of a method for determining load forecast data provided in an embodiment of the present application is shown;
[0020] Figure 4 Another schematic diagram of a cell load balancing method provided in an embodiment of the present application is shown;
[0021] Figure 5 A schematic diagram of the structure of a cell load balancing device provided in an embodiment of the present application is shown;
[0022] Figure 6 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application is shown. DETAILED DESCRIPTION
[0023] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, the same numbers in different drawings represent the same or similar elements unless otherwise indicated. The implementations described in the following exemplary embodiments do not represent all implementations consistent with the present application. Instead, they are merely examples of devices and methods consistent with some aspects of the present application as detailed in the appended claims.
[0024] In a mobile communication network, when a cell is overloaded, load balancing can be achieved by moving user equipment to an adjacent cell with a relatively lighter load. However, switching user equipment when the cell is in a high-load state may increase the switching delay and increase the risk of switching failure. In addition, some user equipment in the high-load cell may already have the problem of increased delay before switching.
[0025] The relevant scheme proposes to monitor and adjust the load by establishing a cell load rate prediction model. Although this method can predict the load situation of each cell in advance, the established cell load rate prediction model usually predicts the current load rate by simple linear weighting of the historical load rate and the current load rate, and cannot describe the increasingly complex changes in the cell load rate. In addition, according to the preset threshold, it is determined whether the user equipment needs to be switched. There may be a scenario where the load rate of some cells is close to the threshold, while the load rate of its adjacent cells is very low. Such a scenario is also a waste of network resources in practice.
[0026] In response to the problems in the above-mentioned cell load balancing process, an embodiment of the present application provides a cell load balancing method, which determines the target adjustment strategy of each cell based on the load prediction data of each cell and the target strategy network, so as to dynamically predict the load conditions of each cell at future times and determine the target adjustment strategy in time to avoid cell overload.
[0027] Figure 1A flow chart of a cell load balancing method provided in an embodiment of the present application is shown. The execution subject of the method may be a terminal device or a server, wherein the terminal device may be a device such as a personal computer, or a mobile terminal device such as a mobile phone or a tablet computer, and the terminal device may be a terminal device used by a user. The server may be an independent server, or a server cluster composed of multiple servers, and the server may be a background server of a certain business, or a background server of a certain platform or application (such as an intelligent scheduling platform, a cell load balancing system, etc.). In the embodiment of the present application, the execution subject is taken as an example to illustrate. For the case of a terminal device, it can be processed according to the following related content, which will not be repeated here. As shown in the figure, the method 100 may include the following steps:
[0028] S101: Acquire a pre-constructed cell distribution topology structure diagram, wherein the cell distribution topology structure diagram includes a plurality of cells and adjacency relationships between the cells.
[0029] The adjacency relationship is used to indicate that user equipment switching can occur between cells.
[0030] In the specific implementation, firstly, a cell distribution topology diagram is constructed. Specifically, each cell in the defined area is regarded as a graph node v i If user equipment switching can occur between cell i and cell j, then the graph node v is considered i and graph node v j There is an undirected edge e between ij Based on this criterion, we can get a topological undirected graph Then, obtain the cell distribution topology diagram The topological structure undirected graph includes multiple cells and the adjacency relationship between each cell.
[0031] Here, whether user equipment switching can occur between cell i and cell j can be determined by obtaining the neighboring cell list of the current cell i, or by determining whether user equipment switching can occur between cell i and cell j according to a pre-configured load balancing strategy.
[0032] S102: Determine load prediction data for each of the cells according to historical load data of each of the cells in the cell distribution topology diagram.
[0033] The historical load data may include historical graph data at multiple time points, each of which is a graph of each node v in the cell distribution topology structure diagram. iThe characteristic vector may specifically include a PRB (Physical Resource Block) utilization rate of a GBR (Guaranteed Bit Rate) service, a PRB utilization rate of a non-GBR service, a PRB utilization rate of a signaling bearer, a PRB utilization rate of a common channel, and the like.
[0034] In a specific implementation, the feature vectors of all cells in the target area at the previous t time points (with 15-minute intervals), that is, t historical graph data, can be obtained. The load conditions of each cell at the next time point are predicted based on the t historical graph data.
[0035] In a possible implementation, in the above S102, determining the load prediction data of each cell according to the historical load data of each cell in the cell distribution topology structure diagram includes:
[0036] Obtain historical load data of each of the cells in the cell distribution topology diagram, wherein the historical load data includes load data of each of the cells at multiple time points; input the load data of each of the cells at multiple time points into a deep learning network, obtain the dependency relationship between the load data of each of the cells at multiple time points through the deep learning network, and predict the load prediction data of each of the cells at the next time point.
[0037] In the specific implementation, a deep learning framework (such as TensorFlow, PyTorch, etc.) can be used to build a deep learning network (Temporal Convolutional Network, TCN) model, such as Figure 2 As shown, the TCN network model can be composed of multiple residual blocks of different scales. By inputting the historical graph data at multiple time points into the TCN network model, the TCN network model obtains the dependency between the load data of each cell at multiple time points, and predicts the load prediction data of each cell at the next time point.
[0038] In a possible implementation, in order to improve the prediction accuracy of the TCN network model, the actual load data of each cell in the cell distribution topology diagram at the next time point can be obtained; and the historical load data can be updated according to the actual load data.
[0039] In an exemplary embodiment, if Figure 3 As shown, the load forecast data determination method may specifically include the following steps:
[0040] Step 301: Obtain a cell distribution topology diagram;
[0041] Step 302: Acquire the previous t historical graph data, wherein the historical graph data includes the load data of each cell in the cell distribution topology structure diagram at t time points;
[0042] Step 303: input the first t historical graph data into the TCN network model;
[0043] Step 304: Obtain load forecast data of each cell at time point t+1 through TCN network model prediction;
[0044] Step 305: Get the real load data of each cell at time point t+1, and return to step 302, update the historical graph data, and input the TCN network to predict the load data at the next moment again, and repeat this cycle.
[0045] S103: Determine a target adjustment strategy for each cell according to the load prediction data and the target strategy network of each cell to achieve cell load balancing.
[0046] Among them, the target strategy network is trained based on the historical load data of multiple cells and the adjacent relationship between each cell in the cell distribution topology structure diagram; the target adjustment strategy may include adjusting the cell's own center carrier channel number, adjusting the cell antenna height, adjusting the cell antenna direction angle, adjusting the cell electronic downtilt angle, adjusting the cell mechanical downtilt angle, adjusting the cell built-in downtilt angle and other strategies for adjusting key parameters for wireless network optimization.
[0047] In a specific implementation, the target strategy network is trained based on the historical load data of multiple cells and the adjacent relationship between each cell in the cell distribution topology diagram, so that the target strategy network can learn the implicit relationship between the cell and the adjacent cell from the cell distribution topology diagram, and determine the target adjustment strategy of each cell according to the load prediction data of each cell and the cell distribution topology structure, so as to achieve cell load balancing. In an exemplary embodiment, Figure 4 As shown, after the above step 304, it also includes: Step 306: The reinforcement learning model adjusts the cell parameters according to the load forecast data and the target strategy network, and then obtains the real load data of each cell at the time point t+1.
[0048] In a possible implementation, the target policy network may be trained in the following manner:
[0049] Obtain first load data of a target cell among the multiple cells at a target time point; determine adjacent cells of the target cell according to the cell distribution topology structure diagram; pre-train a pre-constructed strategy network according to the first load data of the target cell and the second load data of the adjacent cells at the target time point to obtain a reward value of the strategy network, and update network parameters of the strategy network with the goal of maximizing the reward value to obtain the target strategy network.
[0050] In the specific implementation, each community is regarded as an intelligent agent, and the relationship between intelligent agents is represented by an undirected graph. To indicate that if there is an edge between nodes, it means that the agents can perceive each other's status and make decisions. In an exemplary embodiment, cell i first perceives the predicted load status s of itself and its neighboring cells at the target time point t. i,t , the predicted load state s i,t It consists of the first load data of cell i at the target time point t and the second load data of all adjacent cells at the target time point t; the agent takes action a according to its own and adjacent agent load rates and strategy π i,t , that is, the cell parameters are adjusted; after the environment perceives the actions of all agents, the state changes, and the environment gives feedback on the selected actions and gives a reward value r t ; The agent adjusts the network parameters of the policy network according to the reward value to obtain the target policy network. Among them, the predicted load state s i,t It can be expressed as:
[0051] s i,t =[x i ,x j1 ,…,x jn ];
[0052] Among them, j 1 ,…,j n are the indices of all neighboring agents of agent i, x i is the feature vector of the graph node; the action a taken by the agent i,t , including the adjustment of six parameters: the center carrier channel number, antenna height, antenna direction angle, electronic downtilt angle, mechanical downtilt angle, and built-in downtilt angle.
[0053] In a possible implementation, the pre-training of a pre-constructed policy network according to the first load data of the target cell and the second load data of the adjacent cell at the target time point to obtain a reward value of the policy network includes:
[0054] The first load data and the second load data are input into a pre-constructed strategy network to obtain the parameter adjustment strategy of the target cell; and the reward value of the strategy network is determined according to the parameter adjustment strategy of the target cell and a preset reward function.
[0055] In a specific implementation, the first load data and the second load data are input into a pre-constructed strategy network, and the strategy network outputs a parameter adjustment strategy for the target cell (for example, adjusting its own center carrier channel number, antenna height, antenna azimuth, electronic downtilt angle, mechanical downtilt angle, built-in downtilt angle, etc.), and evaluates the quality of the strategy adopted by the target cell through a reward function to obtain a reward value; the calculated reward value is then fed back to the strategy network, and the strategy network can adjust its own network parameters according to the reward value.
[0056] The above-mentioned determining the reward value of the strategy network according to the parameter adjustment strategy of the target cell and the preset reward function includes:
[0057] Obtain the load data of each cell and the number of user equipment switchings after adjusting the parameters of the target cell based on the parameter adjustment strategy; determine the load balancing degree according to the load data of each cell, and the load balancing degree is used to characterize the degree of balance of the load of each cell; determine the reward value of the strategy network according to the load balancing degree and the inverse of the number of user equipment switchings.
[0058] In the specific implementation, the reward function setting rules are as follows:
[0059] a) The action should be chosen so that the load of each cell tends to be balanced;
[0060] b) The choice of action cannot result in too many switching times, otherwise it will increase energy consumption.
[0061] The load balancing degree may be the variance, standard deviation, average value, etc. of the load of each cell. The embodiment of the present application determines the maximum difference of the average load index of each cell according to the load data of each cell, and determines the load balancing degree according to the maximum difference. In an exemplary embodiment, the reward value r t The calculation formula is:
[0062]
[0063] Among them, ρ i is the average load index of agent i, specifically, it can be obtained by summing the PRB utilization rate in the feature vector, and S is the number of user switchings that occur in the entire area after parameter adjustment. The strategy is modeled as a random function π:s 1 ×s 2 ×…×sn →A, parameterize the strategy through deep neural network to improve the generalization ability of the model.
[0064] The embodiment of the present application provides a method for cell load balancing, obtaining a pre-constructed cell distribution topology structure diagram, the cell distribution topology structure diagram includes multiple cells, and the adjacency relationship between each cell, the adjacency relationship is used to characterize that user equipment switching can occur between cells; according to the historical load data of each cell in the cell distribution topology structure diagram, the load forecast data of each cell is determined; according to the load forecast data of each cell and the target strategy network, the target adjustment strategy of each cell is determined to achieve cell load balancing; wherein, the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationship between each cell in the cell distribution topology structure diagram. In this way, the target adjustment strategy of each cell is determined based on the load forecast data of each cell and the target strategy network, and the load situation of each cell at a future moment can be dynamically predicted and the target adjustment strategy can be determined in time to avoid cell overload. Moreover, the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology structure diagram, which enables the target strategy network to learn the implicit relationship between the cell and the adjacent cell from the cell distribution topology structure diagram, and determine the target adjustment strategy of each cell based on the load forecast data and the cell topology structure, so that the resource utilization of the entire network is maximized.
[0065] Figure 5 The structure diagram of the cell load balancing device provided in the embodiment of the present application is shown. The cell load balancing device can be implemented as follows: Figure 1 or Figure 4 In the embodiment shown, all or part of the contents, the cell load balancing device 500 includes:
[0066] The acquisition module 510 is used to acquire a pre-constructed cell distribution topology structure diagram, wherein the cell distribution topology structure diagram includes multiple cells and adjacency relationships between the cells, wherein the adjacency relationships are used to indicate that user equipment switching can occur between the cells;
[0067] A determination module 520, configured to determine load prediction data of each of the cells according to historical load data of each of the cells in the cell distribution topology diagram;
[0068] The balancing module 530 is used to determine the target adjustment strategy of each cell according to the load prediction data and the target strategy network of each cell to achieve cell load balancing; wherein the target strategy network is trained based on the historical load data of multiple cells and the adjacent relationship between each cell in the cell distribution topology diagram.
[0069] In a possible implementation, the determining module 520 includes:
[0070] A data acquisition unit, configured to acquire historical load data of each of the cells in the cell distribution topology diagram, wherein the historical load data includes load data of each of the cells at multiple time points;
[0071] A load prediction unit is used to input the load data of each of the cells at multiple time points into a deep learning network, obtain the dependency between the load data of each of the cells at multiple time points through the deep learning network, and predict the load prediction data of each of the cells at the next time point.
[0072] The determination module 520 further includes:
[0073] The data updating unit is used to obtain the real load data of each cell in the cell distribution topology diagram at the next time point; and update the historical load data according to the real load data.
[0074] In a possible implementation, the equalization module 530 is configured to train the target policy network in the following manner:
[0075] Acquire first load data of a target cell among the multiple cells at a target time point;
[0076] Determining adjacent cells of the target cell according to the cell distribution topology structure diagram;
[0077] According to the first load data of the target cell and the second load data of the adjacent cell at the target time point, a pre-constructed policy network is pre-trained to obtain a reward value of the policy network, and the network parameters of the policy network are updated with the goal of maximizing the reward value to obtain the target policy network.
[0078] In a possible implementation, the balancing module 530, when used to pre-train a pre-constructed policy network according to the first load data of the target cell and the second load data of the adjacent cell at the target time point to obtain a reward value of the policy network, is specifically used to:
[0079] Inputting the first load data and the second load data into a pre-constructed policy network to obtain a parameter adjustment policy for the target cell;
[0080] The reward value of the strategy network is determined according to the parameter adjustment strategy of the target cell and a preset reward function.
[0081] The balancing module 530, when used to adjust the policy and the preset reward function according to the parameter of the target cell to determine the reward value of the policy network, is specifically used to:
[0082] Obtaining load data of each cell and the number of times user equipment switching occurs after adjusting the parameters of the target cell based on the parameter adjustment strategy;
[0083] Determine a load balance degree according to the load data of each cell, wherein the load balance degree is used to characterize the degree of balance of the loads of each cell;
[0084] The reward value of the policy network is determined according to the load balancing degree and the inverse of the number of times the user equipment switching occurs.
[0085] The embodiment of the present application provides a cell load balancing device, including: an acquisition module, a determination module and a balancing module; the acquisition module acquires a pre-constructed cell distribution topology structure diagram, the cell distribution topology structure diagram includes multiple cells and the adjacency relationship between each of the cells, and the adjacency relationship is used to characterize that user equipment switching can occur between cells; the determination module determines the load prediction data of each of the cells according to the historical load data of each of the cells in the cell distribution topology structure diagram; the balancing module determines the target adjustment strategy of each cell according to the load prediction data of each of the cells and the target strategy network to achieve cell load balancing; wherein the target strategy network is obtained by training based on the historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology structure diagram. In this way, the target adjustment strategy of each cell is determined according to the load prediction data of each cell and the target strategy network, so that the load situation of each cell at a future moment can be dynamically predicted and the target adjustment strategy can be determined in time to avoid cell overload. Moreover, the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology diagram. The target strategy network can learn the implicit relationship between the cell and the adjacent cells from the cell distribution topology diagram, and determine the target adjustment strategy for each cell according to the load forecast data and the cell topology structure, so as to maximize the resource utilization of the entire network.
[0086] Figure 6The hardware structure diagram of the electronic device provided by the embodiment of the present application is shown. Referring to the figure, at the hardware level, the electronic device 600 includes a processor 610, and optionally, an internal bus 620, a network interface 630, and a memory 640. Among them, the memory 640 may include a memory 641, such as a high-speed random access memory (Random-Access Memory, RAM), and may also include a non-volatile memory 642 (non-volatile memory), such as at least one disk storage, etc. Of course, the electronic device may also include hardware required for other services.
[0087] The processor 610, the network interface 630 and the memory may be connected to each other via an internal bus 620, which may be an Industry Standard Architecture (ISA) bus, a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus, etc. The bus may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, only one bidirectional arrow is used in the figure, but it does not mean that there is only one bus or one type of bus.
[0088] The memory 640 stores programs. Specifically, the programs may include program codes, and the program codes include computer operation instructions. The memory 640 may include a memory 641 and a non-volatile memory 642, and provide instructions and data to the processor 610.
[0089] The processor 610 reads the corresponding computer program from the non-volatile memory 642 into the memory and then runs it, forming a device for locating the target user at the logical level. The processor 610 executes the program stored in the memory and specifically performs: Figure 1 or Figure 4 The method disclosed in the illustrated embodiment realizes the functions and beneficial effects of each method described in the foregoing method embodiments, which will not be described in detail here.
[0090] The above application Figure 1 or Figure 4The method disclosed in the illustrated embodiment can be applied to the processor 610 or implemented by the processor 610. The processor 610 may be an integrated circuit chip with signal processing capabilities. In the implementation process, each step of the above method can be completed by the hardware integrated logic circuit or software instructions in the processor 610. The above processor 610 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application-specific integrated circuit (ASIC), a field-programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components. The methods, steps and logic block diagrams disclosed in the embodiments of the present application can be implemented or executed. The general-purpose processor can be a microprocessor or the processor can also be any conventional processor, etc. The steps of the method disclosed in the embodiments of the present application can be directly embodied as a hardware decoding processor for execution, or a combination of hardware and software modules in the decoding processor for execution. The software module can be located in a storage medium mature in the art such as a random access memory, a flash memory, a read-only memory, a programmable read-only memory, or an electrically erasable programmable memory, a register, etc. The storage medium is located in the memory, and the processor reads the information in the memory and completes the steps of the above method in combination with its hardware.
[0091] The computer device can also execute the methods described in the foregoing method embodiments, and realize the functions and beneficial effects of the methods described in the foregoing method embodiments, which will not be repeated here.
[0092] Of course, in addition to software implementation methods, the electronic device of the present application does not exclude other implementation methods, such as logic devices or a combination of software and hardware, etc. That is to say, the execution subject of the following processing flow is not limited to each logic unit, but can also be hardware or logic devices.
[0093] The embodiment of the present application also provides a computer-readable storage medium, wherein the computer-readable medium stores one or more programs, and when the one or more programs are executed by an electronic device including multiple application programs, the electronic device executes Figure 1 or Figure 4 The method disclosed in the illustrated embodiment realizes the functions and beneficial effects of each method described in the foregoing method embodiments, which will not be described in detail here.
[0094] The computer-readable storage medium includes a read-only memory (ROM), a random access memory (RAM), a magnetic disk or an optical disk, etc.
[0095] Furthermore, an embodiment of the present application also provides a computer program product, the computer program product comprising a computer program stored on a non-transitory computer-readable storage medium, the computer program comprising program instructions, and when the program instructions are executed by a computer, the following process is implemented: Figure 1 or Figure 4 The method disclosed in the illustrated embodiment realizes the functions and beneficial effects of each method described in the foregoing method embodiments, which will not be described in detail here.
[0096] The embodiments of the present application can be applied to various electronic device collaboration or interconnection scenarios, including: collaboration and interconnection between mobile phones and laptops / tablet computers; collaboration and interconnection between mobile terminals and smart TVs / displays; collaboration and interconnection between mobile phones or tablet computers and in-car entertainment systems; collaboration and interconnection between mobile terminals and smart conference systems, etc., so as to meet the needs of users in various scenarios such as smart homes, smart offices, and smart travel.
[0097] In short, the above is only a preferred embodiment of the present application and does not limit the protection scope of the present application. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
[0098] The systems, devices, modules or units described in the above embodiments may be implemented by computer chips or entities, or by products with certain functions. A typical implementation device is a computer. Specifically, the computer may be, for example, a personal computer, a laptop computer, a cellular phone, a camera phone, a smart phone, a personal digital assistant, a media player, a navigation device, an email device, a game console, a tablet computer, a wearable device, or a combination of any of these devices.
[0099] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.
[0100] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0101] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the system embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.
Claims
1. A cell load balancing method, characterized in that: include: Acquire a pre-constructed cell distribution topology structure diagram, wherein the cell distribution topology structure diagram includes a plurality of cells and an adjacency relationship between the cells, wherein the adjacency relationship is used to indicate that user equipment switching can occur between the cells; Determine load forecast data for each of the cells according to historical load data of each of the cells in the cell distribution topology diagram; According to the load forecast data and target strategy network of each of the cells, a target adjustment strategy for each cell is determined to achieve cell load balancing; wherein the target strategy network is trained based on historical load data of multiple cells and the adjacency relationship between each of the cells in the cell distribution topology diagram.
2. The method according to claim 1, characterized in that: Determining the load prediction data of each of the cells according to the historical load data of each of the cells in the cell distribution topology structure diagram includes: Acquire historical load data of each of the cells in the cell distribution topology diagram, wherein the historical load data includes load data of each of the cells at multiple time points; The load data of each of the cells at multiple time points are input into a deep learning network, and the dependency relationship between the load data of each of the cells at multiple time points is obtained through the deep learning network, and the load prediction data of each of the cells at the next time point is predicted.
3. The method according to claim 2, characterized in that After determining the parameter adjustment strategy of each target cell according to the load forecast data of each cell and the target strategy network, the method further includes: Obtaining the actual load data of each cell in the cell distribution topology diagram at the next time point; The historical load data is updated according to the actual load data.
4. The method according to claim 1, characterized in that: The target policy network is trained as follows: Acquire first load data of a target cell among the multiple cells at a target time point; Determining adjacent cells of the target cell according to the cell distribution topology structure diagram; According to the first load data of the target cell and the second load data of the adjacent cell at the target time point, a pre-constructed policy network is pre-trained to obtain a reward value of the policy network, and the network parameters of the policy network are updated with the goal of maximizing the reward value to obtain the target policy network.
5. The method according to claim 4, characterized in that The pre-training of a pre-constructed policy network according to the first load data of the target cell and the second load data of the adjacent cell at the target time point to obtain a reward value of the policy network includes: Inputting the first load data and the second load data into a pre-constructed policy network to obtain a parameter adjustment policy for the target cell; The reward value of the strategy network is determined according to the parameter adjustment strategy of the target cell and a preset reward function.
6. The method according to claim 5, characterized in that The step of determining the reward value of the strategy network according to the parameter adjustment strategy of the target cell and a preset reward function includes: Obtaining load data of each cell and the number of times user equipment switching occurs after adjusting the parameters of the target cell based on the parameter adjustment strategy; Determine a load balance degree according to the load data of each cell, wherein the load balance degree is used to characterize the degree of balance of the loads of each cell; The reward value of the policy network is determined according to the load balancing degree and the inverse of the number of times the user equipment switching occurs.
7. A cell load balancing device, characterized in that: include: An acquisition module, used to acquire a pre-constructed cell distribution topology structure diagram, wherein the cell distribution topology structure diagram includes a plurality of cells and an adjacency relationship between the cells, wherein the adjacency relationship is used to indicate that user equipment switching can occur between the cells; A determination module, configured to determine load prediction data of each of the cells according to historical load data of each of the cells in the cell distribution topology diagram; The balancing module is used to determine the target adjustment strategy of each cell according to the load prediction data and the target strategy network of each cell to achieve cell load balancing; wherein the target strategy network is trained based on the historical load data of multiple cells and the adjacency relationship between each cell in the cell distribution topology diagram.
8. An electronic device, characterized in that: The electronic device comprises a processor and a memory, wherein the memory stores a program or instruction that can be run on the processor, and when the program or instruction is executed by the processor, the steps of the method according to any one of claims 1 to 6 are implemented.
9. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a program or instruction, and when the program or instruction is executed by a processor, the steps of the method according to any one of claims 1 to 6 are implemented.
10. A computer program product, comprising a computer program stored on a non-transitory computer-readable storage medium, wherein the computer program comprises program instructions, and when the program instructions are executed by a computer, the computer is caused to perform the steps of the method according to any one of claims 1 to 6.
Citation Information
Patent Citations
Method for achieving dynamic load balancing in heterogeneous network
CN103763747A
Load balancing method and system and network equipment
CN105472660A
Cell pre-load balancing method and apparatus
CN107396376A
Cell load balancing method, device, equipment and computer storage medium
CN115134824A
Short-term traffic flow prediction method based on integrated graph convolutional neural network
CN117593877A
Cited By
Cell switching method and device oriented to load balancing, equipment and storage medium
CN119277462A