Water and soil conservation method for zoning water conveyance tunnel adit
Through zoning management of the water conveyance tunnel construction area and multiple water and soil conservation measures, including planting trenches, land consolidation, and plant planting, the problems of poor water and soil conservation effects and high costs in the existing technology have been solved, and more efficient soil and water conservation has been achieved. Effect.
Patent Information
- Application Number
- CN202411250967.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-10-22
AI Technical Summary
The lack of targeted measures in the existing technology results in poor soil and water conservation effects and high costs in water conveyance tunnel construction areas.
Divide the construction area according to sections, and adopt engineering water conservation, plant water conservation and temporary water conservation measures, including planting troughs, land consolidation, slag blocking projects, grid slope protection, spreading grass seeds, planting shrubs, trees, vines, and bagged soil blocking , temporary drainage and geotextile covering and other multiple measures.
It achieves targeted soil and water conservation in different areas, improves soil and water conservation effects, reduces costs, and solves the problem of poor soil and water conservation effects.
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of soil and water conservation, in particular to a soil and water conservation method for zoning branch tunnels of a water delivery tunnel. Background Art
[0002] As cities expand, more and more water transfer tunnels are being built. Water transfer tunnels can transport water resources from abundant areas to arid areas or areas in need of replenishment, solve the problem of uneven distribution of water resources, and promote the rational use of water resources and balance supply and demand. In order to prevent soil erosion in the construction area during tunnel construction, soil and water conservation is generally carried out in the construction area to reduce environmental damage to the tunnel area.
[0003] The traditional construction process generally involves simple tree planting and grass seed sowing in the construction area, but lacks systematic and targeted methods, resulting in less than ideal soil and water conservation effects, high investment, and poor results. Summary of the invention
[0004] The purpose of the present invention is to provide a method for soil and water conservation in branch tunnels of a water diversion tunnel, which solves the problem of poor soil and water conservation effect and high cost caused by lack of targeted measures in the prior art.
[0005] The present invention is implemented by the following technical scheme: a soil and water conservation method for zoning branch tunnels of a water diversion tunnel, comprising the following steps: Step 1: Divide the construction area into sections, mainly into the main project area, construction road area, waste dump area, and construction production and living area; Step 2: Carry out engineering water conservation measures, plant water conservation measures and temporary water conservation measures in the above-mentioned areas; Step 3: Post-maintenance.
[0006] In order to better realize the present invention, further, the engineering water conservation measures mainly include: vegetation troughs, land reclamation, slag interception projects, grid slope protection projects, flood discharge channels and drainage ditches, intercepting ditches, horseway drainage ditches, drainage culverts, and sand settling tanks.
[0007] In order to better realize the present invention, further, the plant water conservation measures mainly include: sowing grass seeds, planting shrubs, trees, and vines.
[0008] In order to better realize the present invention, further, the temporary water conservation measures mainly include: bagged soil blocking, bagged soil filling, temporary drainage, temporary greening, and geotextile covering.
[0009] In order to better realize the present invention, further, when the water conservation operation is carried out in the main engineering area, The water conservation measures of the project include land improvement and vegetation troughs; specifically: Step 211: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 212: Set a C20 concrete retaining wall at the foot of the slope and the inner side of the stepped bridleway to form a vegetation trough with a cross-sectional size of 30 cm×30 cm; Step 213, filling the stripped topsoil into the vegetation trough to a filling height of 30 cm; Plant water conservation measures include planting vines; specifically: Step 214, after the construction is completed and the soil is covered, the creeper is planted by cuttings on the side of the slope foot in the trench near the hole, with a spacing of 0.30m; Temporary water conservation measures include bagged soil blocking; specifically: Step 215: bagged soil is used to block the temporary stockpile of tunnel excavation.
[0010] In order to better realize the present invention, further, when the water conservation operation is carried out on the construction road area, The water conservation measures for the project include land improvement; specifically: Step 221: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 222: After the removal of the hardened surface is completed, the area outside the recultivated area is leveled, and after the land leveling is completed, the topsoil is covered with a thickness of 30 cm; Plant water conservation measures include sowing grass seeds and planting shrubs; specifically: Step 223, using a hole-shaped land preparation method to prepare the land; Step 224, planting Pyracantha fortuneana and Blueberry, sowing grass seeds to restore vegetation on the mortar-stone grids on the roadbed slopes, and sowing grass to restore vegetation on the relatively gentle disturbance areas on both sides of the road, and the grass seeds selected are Cynodon dactylon and White Clover; Temporary water conservation measures include bagged soil blocking, temporary drainage, and geotextile covering; specifically: Step 225, using woven earthbags for protection; Step 226, covering the soil pile area or slope with geotextile; Step 227: lay earthen drainage ditches near the construction area and around the office and living area. After excavation, compact the bottom of the drainage ditch and the slopes on both sides.
[0011] In order to better realize the present invention, further, when the water conservation operation is carried out on the waste slag area, The water conservation measures of the project include slag interception engineering, grid slope protection engineering, flood drainage channel and rapid spreading of grass seeds, planting of Dianliu channel, drainage blind ditch, land improvement, intercepting ditch, horse road drainage ditch, drainage culvert; specifically: Step 231, the topsoil of the cultivated land, forest land and garden land within the scope of the waste dump is stripped to a thickness of 30 cm, and the stripped topsoil is transported to the topsoil storage yard for centralized storage; Step 232, the slag retaining wall is determined as a Class 3-4 building according to the level of the slag dump, and a mortar-stone slag retaining wall is set along the lower slope foot of each slag dump for protection; the flood drainage ditch and the surrounding intercepting ditch are designed as Class 3-4 buildings, and the drainage channel is set at the outer edge of the slag dump area of the slag dump; Step 233: after the slag is abandoned, a slag top drainage ditch is arranged on the top of the slag pile slope, and a horseway drainage ditch is arranged on the inner side of each level of the horseway; concrete lattice slope protection is used on the slag pile slope; Step 234: Arrange a stepped drop-off slope at the steep slope section of the surrounding drainage channel, with the drop-off slope being 0.5m high and connected to an energy dissipation pool at the end; Step 235: Level the abandoned slag field platform and the slag pile slope outside the recultivated area. After the land leveling is completed, topsoil is covered in the concrete grid of the leveled platform and slope, with a thickness of 30 cm. Plant water conservation measures include sowing grass seeds and planting trees; specifically: Step 236, restore vegetation on the slag platform by planting mixed trees and grasses, with Bermuda grass and white clover as grass species, and Quercus variabilis, Cinnamomum camphora, and Cypress yunnanensis as trees; Step 237, sowing grass on the basis of the grid structure of the slag field slope, the grass seeds are the same as those on the slag field platform, and the planting method and technical requirements are the same as those on the slag field platform; Temporary water conservation measures include bagged soil filling, temporary drainage, and temporary greening; specifically: Step 238: Arrange a bagged soil retaining wall at the foot of the soil slope of the topsoil storage area; arrange soil intercepting and drainage ditches on the topsoil storage surface, the horse path and the surrounding areas; Step 239: Sprinkle Bermuda grass seeds on the surface of the soil pile for protection.
[0012] In order to better realize the present invention, further, when the water conservation operation is carried out in the construction, production and living area, The water conservation measures of the project include land reclamation and sand settling ponds; specifically: Step 241: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 242: After the removal of the hardened surface is completed, the construction site outside the reclamation area is leveled, and after the land is leveled, the topsoil is covered with a thickness of about 30 cm; Step 243: At the drainage outlet of the construction production and living area, rainwater is discharged into the downstream ditch. The sand settling tank has a size of 2.0m long, 2.0m wide, and 1.2m deep and is built with C20 concrete; Plant water conservation measures include sowing grass seeds, planting shrubs and trees; and using mixed planting of trees, shrubs and grasses to restore vegetation. Specifically: Step 244, using a hole-shaped land preparation method to prepare the land; Step 245, planting tung oil tree, dung beetle, pyracantha, cypress, bermudagrass and white clover; Temporary water conservation measures include bagged soil filling, temporary drainage, temporary greening, and geotextile covering; specifically: Step 246, using woven earthbags for protection; Step 247, covering the soil pile area or slope with geotextile; Step 228, setting up earthen drainage ditches; Step 249: Sprinkle Bermuda grass seeds nearby for protection.
[0013] Compared with the prior art, the present invention has the following advantages and beneficial effects: (1) The present invention divides the construction area and then takes targeted soil and water conservation measures for different areas, thereby solving the problem of poor soil and water conservation effect and high cost caused by the lack of targeted measures in the prior art, and achieving the purpose of improving the soil and water conservation effect; (2) The present invention solves the problem of poor soil and water conservation effect in the prior art by taking multiple soil and water conservation measures in the working area, thereby achieving the purpose of improving the soil and water conservation effect. DETAILED DESCRIPTION
[0014] In order to make the purpose, process conditions and advantages of the present invention more clearly understood, the present invention is further described in detail in conjunction with the following embodiments, but the embodiments of the present invention are not limited thereto. Without departing from the above-mentioned technical ideas of the present invention, various substitutions and changes are made according to the common technical knowledge and customary means in the field, which should all be included in the scope of the present invention. The specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0015] Embodiment 1: The present embodiment provides a method for soil and water conservation for zoning branch tunnels of a water transfer tunnel, comprising the following steps: zoning the construction area by location, mainly into a main project area, a construction road area, a waste dump area, and a construction production and living area; taking engineering water conservation measures, plant water conservation measures, and temporary water conservation measures for the above-mentioned areas; and post-maintenance.
[0016] Overall, they are: soil and water conservation measures such as vegetation troughs, vegetation restoration, temporary barriers, etc. in the main project area; soil and water conservation measures such as topsoil stripping, vegetation restoration, temporary barriers, and temporary drainage in the construction road area; soil and water conservation measures such as topsoil stripping, slope protection, intercepting drainage ditches, flood drainage ditches, horse paths and slag top drainage ditches, slag retaining walls, energy dissipation pools, topsoil return, and later vegetation restoration measures in the waste dump area; soil and water conservation measures such as topsoil stripping, grit chambers, vegetation restoration, temporary barriers, temporary drainage, and temporary covering in the construction production and living area.
[0017] Embodiment 2: Based on the above embodiments, this embodiment further defines that the engineering water conservation measures mainly include: plant troughs, land reclamation, slag interception engineering, grid slope protection engineering, flood discharge channels and drainage ditches, interception ditches, horseway drainage ditches, drainage culverts, and sand settling ponds; the plant water conservation measures mainly include: sowing grass seeds, planting shrubs, trees, and vines; the temporary water conservation measures mainly include: bagged soil blocking, bagged soil filling, temporary drainage, temporary greening, and geotextile covering. Land reclamation includes: stripping, leveling, and covering.
[0018] When carrying out water conservation operations in the main project area: The water conservation measures of the project include land reclamation and vegetation troughs. Specifically, before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area. Then, to meet the growth needs of climbing plants, C20 concrete retaining ridges are set at the foot of the slope and the inner side of the stepped bridleway to form a vegetation trough with a cross-sectional size of 30cm×30cm. The stripped topsoil is filled into the vegetation trough to a filling height of 30cm.
[0019] Plant water conservation measures include planting vines; specifically: first, after the construction is completed and the soil is covered, creepers are planted by cuttings on the side of the slope foot in the groove beside the hole, with a plant spacing of 0.30m; vines are selected from Grade I and II standards, 1-3 year old seedlings, and the vine length is not less than 0.50m.
[0020] Temporary water conservation measures include bagged soil blocking; specifically: bagged soil is used to block temporary piles of materials for tunnel excavation. The retaining wall is 1.5m high, 0.5m wide at the top, and has an inner and outer slope of 1:1.
[0021] Among them, the excavation of the slope is carried out from top to bottom, and the earthwork construction activities should be avoided on rainy days as much as possible to reduce soil erosion; before the slope excavation, the unstable rock or dangerous rocks should be removed, and the rock-blocking facilities on the top of the slope should be built in advance. The slope protection measures such as spraying concrete, staggered rods, and anchor cables taken on the excavation surface should be implemented in a timely manner to ensure the timeliness of the prevention and control measures, so as to achieve protection while excavating, avoid the exposed edge being in an unprotected state, and avoid increasing soil erosion due to the delay in the construction progress of prevention and control measures; during the earthwork construction process, the amount of explosives should be strictly controlled during the excavation to avoid excessive blasting of the rock mass causing the earthwork "rolling slope" phenomenon. The earthwork and rocks thrown in the area affected by the excavation downslope should be removed in time to protect the surrounding forest and grass vegetation, and the loose rock and soil on the slope should be cleaned in time to keep the slope stable.
[0022] When carrying out water conservation work on the construction road area: The water conservation measures for the project include land improvement. Specifically, the topsoil and loose layers within the construction area are stripped off before construction and piled nearby within the red line of the project area. After the hardened surface is removed, the area outside the recultivated area is leveled. After the land is leveled, the topsoil is covered with a thickness of 30 cm. Plant water conservation measures include sowing grass seeds, planting shrubs, and restoring vegetation by mixing shrubs and grasses; specifically: using pit-shaped land preparation for land preparation, the size of the shrub planting pit is 30cm×30cm; then planting Pyracantha and Blackberry, sowing grass seeds to restore vegetation on the mortar stone grid of the roadbed slope, and sowing grass to restore vegetation in the relatively gentle disturbance areas on both sides of the road. The grass seeds selected are Bermuda grass and White Clover; Pyracantha selects Class I seedlings with a crown width greater than 30cm, and Blackberry selects Class I seedlings with a height greater than 65cm; herbaceous plants select Class I pure varieties with full grains, purity>95%, cleanliness>85%, germination rate>80%, and no diseases and insect pests. The sowing standard is calculated at 80kg / hm2, the sowing ratio is 1:1, and the shrub planting spacing is 30m.
[0023] Temporary water conservation measures include bagged soil blocking, temporary drainage, and geotextile covering; specifically: in order to prevent soil and water loss caused by the temporary excavation of earth and stone during the construction process due to the failure to backfill in time, woven earth bags are used for protection at this stage. The cross-section of the woven bag retaining wall is trapezoidal, with a top width of 0.5m, a height of 1.0m, and a slope ratio of 1:1. The temporary stockpile of tunnel excavation is blocked by bagged soil, with a retaining wall height of 1.5m, a top width of 0.5m, and an inner and outer slope of 1:1; geotextiles are used to cover the soil pile area or slope; earth drainage ditches are laid near the construction area and around the office and living area. The earth drainage ditch adopts a trapezoidal cross-section with a cross-section size of 0.4m×0.4m (bottom width×depth) and a slope of 1:1. After excavation, the bottom of the drainage ditch and the slopes on both sides are compacted.
[0024] When carrying out water conservation operations on the above-mentioned waste dump area: The water conservation measures of the project include slag interception projects, grid slope protection projects, flood drainage channels and rapid spreading of grass seeds, planting of Dianliu troughs, drainage blind ditches, land reclamation, intercepting ditches, horse road drainage ditches, and drainage culverts; specifically: first, the topsoil of cultivated land, woodland, and garden land within the area of the waste dump is stripped with a stripping thickness of 30cm, and the stripped topsoil is transported to the topsoil storage site for centralized storage; the slag retaining wall is determined as a level 3 to 4 building according to the level of the waste dump, and a mortar-laid stone slag retaining wall is set along the lower slope foot of each waste dump for protection. The cross-sectional dimensions of the slag retaining wall are generally: top width 1m, maximum wall height 2.5 to 8m, inner wall slope ratio 1:0.5, outer wall slope ratio 1:0.2; the wall is equipped with 10cmx10cm drainage holes, the row spacing is 2mx2m, and the plum blossom shape is arranged. The masonry mortar uses M7.5 cement mortar; then the slag dump flood discharge facilities are designed according to the 3-4 level buildings, and the flood control standard adopts a 30-50 year recurrence period, that is, the retaining wall and drainage channel are designed according to the corresponding gully and the 30-50 year recurrence period flood standard; there are two types of retaining walls: mortar masonry retaining wall and rolled earth and rock retaining wall. The maximum height is less than 10m, generally using mortar masonry retaining wall, and the height is greater than 10m, generally using rolled earth and rock retaining wall. Among them, the mortar masonry retaining wall has a top width of 1m, a maximum wall height of 7m, an inner wall slope ratio of 1:0.5, and an outer wall ratio of 1:02; the rolled earth and rock retaining wall has a top width of 4m, a maximum wall height of 10m, an upstream side wall slope ratio of 1:2.0, and dry block stone slope protection is used in the later stage, and the downstream side wall slope ratio is 1:1.8, mainly using earth and stone excavated from engineering buildings for filling. The drainage channel is set at the outer edge of the slag dump area to divert the upstream water to the downstream gully. The cross-sectional dimensions are 0.6m×0.8m~0.8m×1.4m (bottom width×height). The gentle slope section of the drainage channel adopts M7.5 mortar masonry, and the steep slope section adopts C25 reinforced concrete. The engineering quantity of related engineering measures such as intercepting drainage ditches, retaining walls, drainage channels, drainage blind ditches, etc. involved in the waste dump shall be subject to the professional construction. After the waste dump is completed, the slag top drainage ditch is arranged on the top of the slag dump slope. The slag top drainage ditch is a trapezoidal cross-section with a cross-sectional dimension of 0.4m×0.6m (width×depth), a slope ratio of 1:0.5, a longitudinal slope of 0.5% at the bottom of the ditch (drainage to the surrounding intercepting ditches), a lining thickness of 0.3m, and is built with M7.5 mortar masonry. After the slag is piled, a drainage ditch is arranged on the inner side of each level of the slag. The drainage ditch is a rectangular section with a section size of 0.3m×0.3m (width×depth), a lining thickness of 0.3m, and is built with M7.5 mortar masonry. After the slag is piled and leveled, a concrete lattice slope protection is used on the slag slope. The lattice grid size is 3.0mx3.0m, the center angle is 90%, the concrete skeleton size is 0.3m×0.4m (width×depth), and a 0.1m high drainage ridge is set on the outer edge of the skeleton to collect water on the slope and collect it in the drainage ditch at the foot of the slope. A 0.5m wide concrete cap and foot trough are arranged at the top and foot of the slope, and a PVC drainage pipe with a diameter of φ80mm is arranged.In order to reduce the potential energy of water flow, a stepped drop is arranged in the steep slope section of the surrounding drainage channel. The drop is 0.5m high and connected to the energy dissipation pool at the end. It is built with C20 concrete. After the slag is piled, the platform and slope of the slag dump outside the recultivated area are leveled. After the land is leveled, the topsoil is covered in the concrete grid of the leveled platform and slope, with a thickness of 30cm.
[0025] Plant water conservation measures include sowing grass seeds and planting trees; specifically: based on the conditions of the slag site, the slag site platform is restored with mixed trees and grasses. After the slag site platform is covered with soil, the grass is first sown with a mixed ratio of 1:1. The planting method is broadcasting with a broadcast density of 80kg / hm2. The seeds are soaked with water retaining agent before broadcasting and covered with 2cm of soil after broadcasting. Two types of trees are selected for interplanting on the slag site platform. The tree species are cork oak, winter melon / cinnamomum camphora, and Yunnan cypress. The tree rows are arranged in a "pin" shape. The tree land preparation specifications are 60cm×60cm, the row spacing is 2.0m×2.0m, and 2,500 trees are planted per hectare. The seedlings meet the requirements of the "Main Afforestation Tree Species and Seedlings" (DB6000). Then, on the basis of the grid layout on the slope of the slag dump, grass is sown. The grass seeds, planting methods and technical requirements are the same as those on the slag dump platform. The trees are selected to be Class I seedlings with a height greater than 1.5m and a ground diameter greater than 2.0cm. The herbaceous plants are selected to have full grains, purity >95%, cleanliness >85%, germination rate >80%, and Class I pure varieties without diseases and insect pests.
[0026] Temporary water conservation measures include bagged soil filling, temporary drainage, and temporary greening; specifically: in accordance with the principle of "blocking first and abandoning later", before the soil is piled, a bagged soil retaining wall is arranged at the foot of the soil slope in the topsoil storage yard. The retaining wall is 1.5m high, 0.5m wide at the top, and the inner and outer slopes are 1:1. In order to prevent precipitation from eroding the temporary topsoil, it is planned to arrange soil interception and drainage ditches on the top surface, horse trails and surrounding areas of the topsoil storage yard. The soil interception and drainage ditches adopt a trapezoidal cross-section with a cross-section size of 0.3m×0.3m (bottom width×ditch depth), a slope of 1:1, and a longitudinal slope of 1% (the steep slope section is consistent with the original ground). Considering that the topsoil has been stored for a long time, it is planned to sow Cynodon dactylon seeds on the surface of the soil pile for protection, with a sowing amount of 80kg / hm2.
[0027] When carrying out water conservation operations in the construction, production and living areas, The water conservation measures of the project include land reclamation and grit chambers; specifically, humus topsoil is reserved for later vegetation restoration. Before construction, the topsoil and loose layers within the construction area are separated and piled nearby within the red line of the project area. The separated topsoil is used for vegetation restoration. After the hardened surface is demolished, the land outside the reclamation area is leveled. After the land is leveled, the topsoil is covered with topsoil, with a thickness of about 30 cm. At the drainage outlet of the production and living area, rainwater is discharged into the downstream ditch. The grit chamber is 2.0 m long, 2.0 m wide and 1.2 m deep, and is built with C20 concrete.
[0028] Plant water conservation measures include sowing grass seeds, planting shrubs and trees; after deducting the area of the recultivated area from the construction production and living area, the area will be restored with mixed trees, shrubs and grasses and mixed shrubs and grasses after the construction facilities are removed; before carrying out soil and water conservation afforestation, necessary land improvement must be carried out on the afforestation site to improve the site conditions in order to increase the survival rate of afforestation and promote the growth of forests and grasses. The afforestation land preparation for this project adopts the pit-shaped land preparation method, in which the specifications of the tree planting pit are 60cm×60cm, and the specifications of the shrub planting pit are 30cm×30cm. Among the afforestation tree species, trees (Cassia truncatula, Sophora japonica) are selected as Class I seedlings with a height greater than 1.5m and a ground diameter greater than 2.0cm. Pyracantha and Morus alba are selected as Class I seedlings with a crown width greater than 30cm. Herbaceous plants are selected as Class I pure varieties with full grains, purity >95%, cleanliness >85%, germination rate >80%, and no diseases or insect pests. The sowing standard is calculated as 80kg / hm2, the sowing ratio is 1:1, and the row spacing of mixed plantings of trees and shrubs is 2.0×2.0m.
[0029] Temporary water conservation measures include bagged soil filling, temporary drainage, temporary greening, and geotextile covering; specifically: In order to prevent soil and water loss caused by the temporary excavation of earth and stone during the construction of production and living facilities due to the failure to backfill in time, woven earth bags are considered for protection at this stage. The cross-section of the woven bag retaining wall is trapezoidal, with a top width of 0.5m, a bottom width of 2.5m, a height of 2.0m, and a slope ratio of 1:0.5. In order to prevent soil and water loss caused by the temporary excavation of earth and stone during the construction of the production and living area due to the failure to backfill in time, geotextiles are covered on the soil pile area or slope. In order to prevent erosion by rainfall and surface runoff, earth drainage ditches are planned to be laid near the construction area and around the office and living area. The earth drainage ditch adopts a trapezoidal cross-section with a cross-section size of 0.4m×0.4m (bottom width×depth) and a slope of 1:1. After excavation, the bottom of the drainage ditch and the slopes on both sides are compacted.
[0030] Later maintenance includes: removing weeds, applying herbicides, pruning according to gardening methods, cultivation, regular watering and irrigation, fertilizing twice a year, applying pesticides and controlling pests and diseases, taking measures to prevent human damage and livestock trampling and gnawing, timely replanting of dead, damaged or lost trees and flowers, keeping the planting area clean, regularly sweeping and removing garbage, and protecting the topsoil.
[0031] Embodiment 3: Based on the above embodiment, this embodiment further defines the construction process of soil and water conservation engineering, specifically including: 1.1 Land consolidation project Land remediation includes stripping of topsoil, site leveling, and covering. All obstacles in the excavation site, such as trees, stumps, old buildings, etc., are removed, and waste materials such as cultivated soil, garbage, and turf are removed and transported to the designated location; after completion, the topsoil is stripped, excavated and stripped directly with an excavator, and transported to the designated location by car for stacking.
[0032] The vegetation clearing on the surface of each construction site and waste dump area must be extended to the outside of the maximum excavation edge or the building foundation edge (or fill slope foot line). The vegetation clearing of protective engineering should extend the scope of tree roots to the outside of the maximum construction excavation edge, fill line or building foundation. After the topsoil is stripped, the location of tree felling and root digging and the relatively concave and convex areas are leveled, and the construction is carried out by excavators. After the construction is completed, the waste dump needs to be covered with soil and recultivated.
[0033] 1.2 Earthwork excavation ⑴ Construction preparation Be familiar with the design drawings, and use the total station to re-survey, identify and add piles along the entire line according to the given control piles in the design. After verifying the ground line, conduct measurement and layout of individual projects.
[0034] ⑵ Earth excavation ① Construction method Earth excavation is carried out in layers from top to bottom using a 1.6m3 backhoe, with a layer thickness of 3 to 4m. Isolated rocks are excavated by blasting with a hand drill and shallow holes. The 1.6m3 backhoe is used to load dump trucks with waste materials and transport them to the waste dump. The usable materials can be transported to the roadbed filling area.
[0035] ② Construction process Construction layout → layered excavation → earthwork transportation → side ditch excavation → slope trimming → road trench leveling and compaction.
[0036] ③Construction technology A. Construction layout Before construction, use the total station to lay out the center line of the structure and the excavation side line B. Layered excavation After the topsoil of the excavation area is cleaned, according to the terrain conditions, thin layers are excavated by bulldozers downhill, and hard soil and thick layers are excavated in layers with backhoes.
[0037] C. Earthwork For soil and soft rock sections within 50m, bulldozers are used for direct transportation. For sections above 50m, bulldozers are used for aggregate loading and dump truck transportation or backhoes are used for direct loading. Waste materials are transported to the waste dump designated by the engineer, and usable materials are transported to the roadbed filling area.
[0038] 1.3 Construction of mortar-laid rubble drainage ditch (1) Construction preparation Before construction, the roadbed center line of the ditch, the main axis of the foundation, the axis of the wall, the starting and ending points of the ditch and the cross section, and the excavation line of the foundation pit should be accurately marked out, indicated with lime lines, and secured with thin iron wire or wooden stakes.
[0039] Clean the area within the ditch, remove organic matter and tree roots and weeds, appropriately extend the cleaning range at both ends of the ditch, reasonably arrange the stockpile yard and construction site, and do a good job of temporary drainage of the site.
[0040] (2) Foundation pit excavation The foundation pit is mainly excavated manually, and the size, shape and depth of each part are constructed according to the design requirements. The excavation size of the foundation pit should meet the requirements of foundation construction. For some irregular but stable rocks in the foundation pit, they can be skipped and not excavated or built according to the design requirements.
[0041] (3) Masonry technology The strength of the stone used for masonry shall meet the requirement of not less than 30MPa, the minimum size of the stone shall not be less than 30cm, and 7.5 mortar shall be used for masonry. The mortar shall be mixed with a small mortar mixer and transported to the masonry site by a wheelbarrow for a short distance. The construction mix ratio shall be mixed in accordance with the specifications and test requirements.
[0042] When mortaring facing stones, first estimate the shape and size of the stones required according to the conditions of the joints, then select the stones, and conduct trial masonry without mortar. Then, find the large edges and corners in the stones that are in the way according to the trial masonry conditions, knock them off with a sledgehammer, hit the small edges and corners with a small hammer, and chisel the protruding parts that are not level on the bottom or affect the upper masonry with a chisel, then spread the mortar, turn the stones back, and use a small crowbar to adjust the stones so that the mortar joints on both sides are appropriate. If the stone is small, tap it gently with a hammer, and if the stone is large, rub it left and right with your hands to squeeze the mortar joints.
[0043] After the completion of the foundation pit, the longitudinal axis of the base shall be combined with the cross-section to re-inspect, the foundation pit shall be cleaned according to the design and specification requirements, the elevation, flatness, cross-sectional dimensions, and base bearing capacity shall be self-checked, and the top elevation of the base shall be controlled by hanging lines. Only after inspection and verification and approval by the supervising engineer can the ditch be built.
[0044] Layered masonry is used during masonry. When masonry blocks on the upper layer are laid, vibration of the lower layer blocks should be avoided. When masonry work is resumed after interruption, the surface of the masonry layer that has been laid should be cleaned and moistened. Each stone should be paved with mortar first, and then the stone pieces should be placed. After kneading it left and right for a few times, it should be tapped with a hammer to squeeze the mortar below and make it dense. The squeezed mortar should be scraped up and reused. The natural shape of the stone pieces should be used to make them interlaced and connected together, with the large surface facing down, staggered, tightly overlapped, and the stones staggered to avoid vertical seams and wall clamping. The stone pieces are separated by mortar to ensure that the mortar is full. Tie stones should also be set, and they should be evenly distributed and staggered to ensure the quality of the masonry and the smoothness and beauty of the linear shape. Strictly control the slope rate, surface flatness and cross-sectional dimensions.
[0045] If the backfill of the wall is made of crushed stone soil, it can only be carried out after the strength of the masonry mortar reaches more than 75%.
[0046] (4) Pointing The exposed surface of the masonry is grooved in the form of concave joints. If there is no groove reserved on the wall, use nails or chisels to open the joints before grouting. After the concave joints are opened, use a wire brush to brush away the slurry and dirt on the masonry surface with water, and sprinkle the grooves to moisten them. If the original base slurry is insufficient, it should be filled with mortar first, and then grouting should be done.
[0047] (5) Health preservation When new masonry work is completed or when work is finished, the masonry must be covered with soaked sacks and watered within 10 to 12 hours after completion. The curing time should be no less than 7 to 14 days. The covering must be kept moist during curing. During the first 3 days, water at least every 3 hours during the day and at least once at night, and then water at least 3 times every day and night.
[0048] 1.4 Construction of mortar-laid rubble retaining wall (1) Construction preparation When laying bricks, the lines must be hung on two poles or samples. The outer lines should be straight and neat, with the slopes gradually reduced. The inner lines can be roughly smooth. The poles should be frequently corrected during the laying process to ensure that the dimensions of each part of the masonry meet the requirements of the drawings. When the wall foundation is directly placed on the natural foundation, it should be inspected and approved by the supervising engineer before laying bricks. When there is seepage water, it should be removed in time to prevent the foundation from being damaged by water before the mortar is initially set.
[0049] (2) Construction plan When the wall foundation is a soft soil layer and cannot guarantee the strength required by the drawings, the supervision engineer shall approve the widening of the foundation or other measures. The depth of the retaining wall foundation for flooded or riverside roadbeds shall comply with the requirements of the drawings and shall not be less than 0.5m below the scour line. When the wall foundation is set on the horizontal slope of the rock, the surface weathering layer shall be removed and made into a step shape. The height-to-width ratio of the steps shall not be greater than 2:1, and the width of the steps shall not be less than 0.5m. When the ground slopes longitudinally along the length of the wall, steps shall be made longitudinally according to the requirements of the drawings. When laying the first layer of the foundation, the base is a concrete foundation, and its surface should be cleaned and moistened first, and then masonry should be laid with mortar.
[0050] When masonry work is interrupted and then resumed, the surface of the masonry layer should be cleaned and moistened. Masonry should be laid separately with mortar, and the lower layer should not be vibrated when laying the upper layer. Stones should not be thrown, rolled, turned over or knocked on the completed masonry. After the masonry is completed, the joints should be pointed. The segmentation position of the working section should be at the expansion joint and settlement joint, and the horizontal joints of each section should be consistent. When laying in sections, the height difference between adjacent sections should not exceed 1.2m. The excavation and backfilling of the wall foundation groove should comply with the requirements of the design drawings and specifications. The settlement joints, expansion joints, waterproof layers, and drainage holes of the wall should be set in accordance with the drawings or according to the instructions of the supervising engineer.
[0051] (3) Notes Before laying, each stone should be washed with clean water and thoroughly saturated, and the cushion layer should also be clean and moist. All stones should be placed on fresh mortar, and all joints should be filled with mortar before the mortar solidifies, and the stones should be fixed in place. The vertical joints should be filled with mortar by first applying mortar to the sides of the already laid stones, and then laying the next adjacent stone with side pressure; the mortar can be poured after the stones are in place. If the stones are loose or the joints are cracked, the stones should be lifted, the cushion mortar and the joint mortar should be cleaned, and then the stones should be re-laid on the new mortar.
[0052] The exposed joints should be hooked before the mortar solidifies, and the depth of the hooking should not be less than 20mm. If conditions do not permit, the mortar should be hooked to a depth of not less than 20mm before the mortar solidifies to prepare for the subsequent hooking.
[0053] After the masonry is completed, it should be cured within 7-14 days, depending on the type of cement and climate conditions. All mortar joints should be filled with mortar.
[0054] 1.5 Concrete construction Concrete in soil and water conservation projects mainly refers to sedimentation tanks, etc.
[0055] The formwork is assembled by steel formwork and wooden formwork, and the formwork is erected according to the concrete structure and system; the formwork is reinforced by Φ48 steel pipe rack, anchor bar external support, and inclined tension inside the formwork; concrete tank trucks are used for transportation, and concrete is mixed from the nearest concrete mixing station; different ways of entering the warehouse are adopted on site according to the location and structure of the concrete, including direct entry, shuttle trough entry, pump entry, and manual entry, to prevent aggregate separation during entry.
[0056] 1.6 Concrete culvert burial ⑴ Trench excavation and foundation treatment ① According to the design plan and pipeline routing, use machinery to dig trenches to the ground elevation of the pipeline. Before excavation, you should carefully study and review the drawings, master the relevant data, and accurately carry out the measurement work according to the project situation.
[0057] ② According to the conditions of the construction site and the form of the pipe joint, the form of the pipeline foundation should be checked. Before the construction of the pipeline foundation, the axis position must be checked and the elevation must be checked to see if it is consistent with the design plan.
[0058] ③First pour the concrete flat base, and when the flat base strength is greater than or equal to 5.0MPa, you can stabilize the pipe, pour the pipe seat and cement mortar strip. This method is generally suitable for construction in rainy seasons or poor foundation conditions.
[0059] ⑵Key points of pipeline foundation construction ① Before pouring concrete in the foundation, the elevation of the foundation surface must be strictly controlled. The allowable deviation is no more than 10mm below the design elevation, but not higher than the design elevation. It must be reviewed according to the design elevation and axis.
[0060] ② Be sure to inspect the tank carefully and remove all debris, silt and water inside the tank.
[0061] ③ Check whether the elevation of the template meets the design requirements and whether the bracket is stable.
[0062] ④ Check whether the workability of the concrete mixture meets the design requirements, usually using a slump meter and a Vebe consistency meter for testing.
[0063] ⑤ Check whether the cross-sectional dimensions of each part of the poured concrete foundation meet the design requirements.
[0064] ⑥ Do not immerse in water within 12 hours after concrete pouring to prevent deformation of the pipeline due to an unstable foundation.
[0065] ⑦ Check whether the hardened concrete surface has been roughened before continuing to pour concrete, and whether the loose stones on the surface have been removed and put into the covering layer.
[0066] ⑧ It is prohibited to pour concrete in the open air on rainy days. If concrete has already been poured, it should be covered in time to prevent rainwater from washing away the newly poured concrete.
[0067] ⑨ When pouring pipe seat concrete, if the pipe diameter is greater than 700mm, construction workers are required to enter the pipe and smooth the inner seam of the pipe seat.
[0068] ⑩ Check whether the construction workers cover and sprinkle water on the concrete surface within 12 hours after the concrete pouring is completed (no less than 7d for ordinary cement and no less than 14d for other cements).
[0069] ⑶Pipeline installation ① Technical requirements for pipeline installation and construction: A. Before laying the pipeline, the pipeline foundation must be strictly inspected for quality and the axis position, line shape, and elevation must be checked to see if they are consistent with the design elevation.
[0070] B. The pads used to stabilize the pipes should be prefabricated according to the design and placed accurately. If triangular pads are used, the inclined surface should be used as the bottom, and a layer of mortar should be applied to enhance the stability of the pipes.
[0071] C. When stabilizing the pipe on a flat base or pad, after the pipe is stabilized, prefabricated wedges can be used to clamp both sides of the pipe. After the pipe is stabilized, the concrete pipe seat should be poured in time.
[0072] D. Before installing the pipeline, the quality of the pipe must be checked, such as: pipe segment size, roundness, appearance and internal quality, etc.
[0073] E. The pipes should be arranged from downstream to upstream, with the socket facing upstream. The pipe joints should not be damaged during installation, the sealing rubber rings should not be dragged or twisted, and the gap between the sockets should be uniform and not greater than 9mm.
[0074] Strictly control the elevation and direction of the pipe sections, ensure that adjacent pipe sections are padded firmly and stably, and reverse slope is strictly prohibited.
[0075] F. Crane lowering pipes: When using a crane to lower pipes, first survey the site and determine the distance between the crane and the edge of the trench based on the trench depth, soil quality, and other conditions.
[0076] G. Manual pipe lowering: Manual pipe lowering generally adopts the rope-pressing pipe lowering method, that is, a large rope is put on each end of the pipe. When lowering the pipe, the lower half of the rope is stepped on with the foot, and it is anchored with a rod if necessary. The upper half of the rope is pulled by hand and pulled with a crowbar. The two sets of ropes are used with the same force, and the pipe is slowly lowered into the trench under the command. When the rope-pressing pipe lowering method is adopted for reinforced concrete pipes with a diameter greater than 900mm, a pipe column should be buried, the lower half of the rope is fixed to the pipe column, and the upper half is wrapped around the pipe column to control the lowering of the pipe.
[0077] H. To facilitate the rotation of pipes or the installation of rigging in the trough, wooden boards or square timbers can be placed at the bottom of the trough when lowering pipes. When lowering pipes on a concrete foundation or a gravel trough, straw bags or wooden boards should be placed to prevent damage to the pipes.
[0078] ②Key points of pipeline installation and construction: A. Check whether the pipe joints used meet the design requirements and check the quality certificate of the pipe joints.
[0079] B. Construction workers are required not to damage the pipe joints during transportation and roughening. Damaged pipe joints are prohibited from use.
[0080] C. Check whether the debris and accumulated water on the foundation surface have been cleared before installing the pipe joint. When using rollers or pipe transport vehicles to transport pipes in a trench that has not been leveled, wooden boards should be laid at the bottom of the trench.
[0081] Randomly check whether the quality of the rubber ring meets the requirements.
[0082] ⑷Pipeline interface ① Rigid interface A. Pipeline interfaces are usually made of cement mortar, which are suitable for flat-end pipes, tongue-and-groove pipes, and socket-and-spigot pipes.
[0083] B. The material should be 42.5 grade cement, the sand particle size should be less than 2mm, the mud content should not be greater than 2%, and the interface cement mortar can adopt a cement: sand mix ratio with a mass ratio of 1:2.5, and the water-cement ratio should not be greater than 0.5.
[0084] C. The ends of the pipe joints must be cleaned and roughened before connection, and the joints must be moistened with water.
[0085] D. Pipes with a diameter greater than or equal to 700mm. When the pipe gap exceeds 10mm, a support should be placed at the top of the pipe gap inside the pipe before applying the tape. Fill the mortar from the outside, then remove the inner support and smooth it. Do not fill the pipe gap with debris such as gravel, broken bricks, and wood chips.
[0086] Before applying cement mortar, clean the pipe mouth and apply a layer of cement mortar.
[0087] E. Wire mesh cement mortar tape should be rust-free, oil-free and meet the design requirements, and the wire mesh should be cut into the required size before use.
[0088] F. After the tape is applied, carry out curing. Remove the formwork after 4 to 6 hours at room temperature to protect the tape from damage, and continue curing after removing the formwork.
[0089] ②Flexible interface A. Before the connection, the inside of the socket and the outside of the plug should be cleaned, and the rubber ring should be put on the end of the plug. The rubber ring should be kept flat and without distortion.
[0090] B. When installing the interface, the pushing and pulling speed should be slow, and a dedicated person should be assigned to check the position of the rubber ring. If it is found that the position is uneven, the pushing and pulling should be stopped, and then continued after adjustment. When the rubber ring reaches the predetermined position on the working surface of the socket, the pushing and pulling should be stopped, and the interface should be locked immediately with a machine. No less than 2 interfaces should be locked continuously.
[0091] ⑸ Backfill around the pipeline After the main structure of the pipeline project is inspected and qualified, soil and rocks should be backfilled in time, and qualified soil and rock sources should be selected. The range from the bottom of the trench to 50cm above the top of the pipe shall not contain organic matter, frozen soil, bricks and stones larger than 10cm, and other hard blocks. It is strictly forbidden to backfill silt, humus, abandoned soil, and soil with too high water content in the earthwork backfill. Soil should be backfilled on both sides of the trench at the same time, and the height difference on both sides shall not exceed 30cm.
[0092] 1.7 Concrete grid slope protection The concrete grid slope protection is used for slag body slope protection. A expansion joint is set every 20m in the grid. The expansion joint is 25cm wide and filled with foam plastic. The grid beam concrete for the slope protection of the slag storage yard is carried out after the construction of the footing mortar masonry retaining wall at the bottom of the slag yard is completed and the slag is abandoned.
[0093] ⑴ Measurement and setting out: according to the design requirements, the plane position and elevation of the lattice beam, top and edging are set out. After measurement and positioning, the construction rope is used to make the final control of the grid position.
[0094] (2) Lattice trenching: Due to the small cross-section of the lattice, it can only be excavated by manual excavation. The width of the artificial trench is 45cm and the height is 30cm. When excavating, make sure that the excavation depth meets the design requirements. ⑶ Formwork processing and steel bar binding: The formwork is made of wood formwork, which is processed and assembled at the production site and then transported to the site for installation. The formwork is assembled with 2m*0.3m plates. After the steel bars are made at the production site, they are transported to the site for binding. Rust and sticky mud must be cleaned before the steel bars are put into the mold. After the steel bars are tied, the hidden project acceptance must be carried out, and the lattice beam can be cast only after passing the acceptance.
[0095] ⑷ Pouring: According to the design requirements, a 25mm deformation joint is set for every 20 meters of slope protection, and a Φ80PVC drainage pipe is arranged. After the concrete is centrally mixed at the mixing station according to the C20 mix ratio, it is transported to the site by concrete tank trucks and poured manually, and then vibrated with an inserted vibrator.
[0096] ⑸ Maintenance: Concrete maintenance should be carried out by sprinkling water 12 to 24 hours after pouring, and the maintenance time should not be less than 7 days.
[0097] 1.8 Green Protection Project Grass seeds shall be sown on the access road to the construction branch tunnel, the slag yard, and the slopes of the living camp. According to the design drawings, the grass seeds sown in this section are mainly bermudagrass and white clover, and the shrub species include mulberry, dwarf lily, tung oil tree, and pyracantha. The number of grass seed fixed points per unit area is 80kg / hm2, and it is sown at a ratio of 1:1. Plant trees, shrubs, and climbing plants in the project area as shown in the drawings or as instructed by the supervisor. The tree species planted in this section include cork oak, camphor, Yunnan cypress, and winter melon; climbing plants include creeper. Mixed seedlings are planted at a ratio of 1:1. The number of fixed points per unit area of trees and shrubs in the production and living area is 1250 plants / hm2, and the number of fixed points per unit area of trees and shrubs in the slag yard area is 2500 plants / hm2.
[0098] 1.9 Construction technology of sowing grass seeds Construction process: excavation and laying of topsoil → fine leveling of the site → application of base fertilizer → seed soaking → manual sowing → watering → light rolling → covering with ground film → later maintenance When sowing grass seeds, you can first mix the grass seeds with a small amount of mature soil or fine sand, and then sow them. The mixing ratio depends on the actual situation on site to ensure that the grass seeds can completely cover the slope.
[0099] When sowing grass, the seeds can be divided into two parts, one part is sown vertically and the other part is sown horizontally, so that the seeds can be evenly distributed on the slope.
[0100] After sowing, use a spike rake to gently rake the slope surface to fully mix the seeds with the soil, then press it down appropriately or cover it with mulch. After sowing, spray water continuously to keep the soil surface moist. Do not flood with water.
[0101] 1.10 Tree Planting Construction Technology Construction process: tree hole location → sapling transportation and pruning → base fertilizer application → planting → filling and watering → light rolling → later maintenance Planting and backfilling should be carried out by experienced workers in accordance with normal practices. Plants should be planted vertically, 20 to 30 mm deeper than the planting depth in the nursery. Trees and shrubs should be inspected and approved by the supervisor before planting.
[0102] Before planting, soak the shrubs in rooting water and treat them with water-retaining agents, and compact the soil after planting.
[0103] After planting shrubs and trees, the pit should be filled with soil and compacted in time, and watered frequently to keep the pit moist until the shrubs and trees germinate and survive.
[0104] For planted slopes, check whether the slopes are intact after heavy rain. If local collapse or cracking is found, remedial measures should be taken in time to prevent the disease from spreading.
[0105] Plant shrubs in the position required by the design. The planting method is "one lift, two steps, three soiling". The planting depth is generally 3-5cm deeper than the original soil. Shrubs are planted by hole planting, spot sowing and cuttings. Each plant has no less than 4 branches, and one plant is planted in one hole. For seedling planting, uniform planting or multiple varieties are planted alternately. When seedlings are planted alternately, they should be staggered, orderly, uniform and beautiful, not messy, and the tree species should be changed at a certain distance.
[0106] Before planting, check the specifications of the planting holes, then water the bottom of the holes, and cover the holes with soil after all the water has penetrated. The first watering should be thorough, and the second watering should be done after 4-5 days, and the third watering should be done within 10 days. The number of watering should be increased in the dry and rainless season, and the dead and missing seedlings should be replanted in the spring of the first year. After the construction of the green channel is completed, maintenance and management should be carried out according to the design requirements to ensure the survival of the plants.
[0107] The soil that does not meet the requirements is removed and replaced with planting soil suitable for plant growth. The soil is transported by dump trucks and construction is carried out by manual labor in conjunction with bulldozers or excavators. The crushed stones are manually inlaid according to the design requirements.
[0108] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the protection scope of the present invention.
Claims
1. A method for soil and water conservation for branch tunnels of a water diversion tunnel, characterized in that: The following steps are involved: Step 1: Divide the construction area into sections, mainly into the main project area, construction road area, waste dump area, and construction production and living area; Step 2: Carry out engineering water conservation measures, plant water conservation measures and temporary water conservation measures in the above-mentioned areas; Step 3: Post-maintenance.
2. A method for soil and water conservation for branch tunnels of a water diversion tunnel according to claim 1, characterized in that: The water conservation measures of the project mainly include: vegetation troughs, land reclamation, slag interception projects, grid slope protection projects, flood discharge channels and drainage ditches, intercepting ditches, horse trail drainage ditches, drainage culverts, and grit chambers.
3. A method for soil and water conservation for zoning branch tunnels of a water diversion tunnel according to claim 2, characterized in that: The plant water conservation measures mainly include: sowing grass seeds, planting shrubs, trees and vines.
4. A method for soil and water conservation for branch tunnels of a water diversion tunnel according to claim 3, characterized in that: The temporary water conservation measures mainly include: bagged soil blocking, bagged soil filling, temporary drainage, temporary greening, and geotextile covering.
5. A method for soil and water conservation for branch tunnels of a water diversion tunnel according to claim 4, characterized in that: When carrying out water conservation operations in the main project area, The water conservation measures of the project include land improvement and vegetation troughs; specifically: Step 211: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 212: Set a C20 concrete retaining wall at the foot of the slope and the inner side of the stepped bridleway to form a vegetation trough with a cross-sectional size of 30 cm×30 cm; Step 213, filling the stripped topsoil into the vegetation trough to a filling height of 30 cm; Plant water conservation measures include planting vines; specifically: Step 214, after the construction is completed and the soil is covered, the creeper is planted by cuttings on the side of the slope foot in the trench near the hole, with a spacing of 0.30m; Temporary water conservation measures include bagged soil blocking; specifically: Step 215: bagged soil is used to block the temporary stockpile of tunnel excavation.
6. A method for soil and water conservation for branch tunnels of a water diversion tunnel according to claim 4, characterized in that: When carrying out water conservation work on the construction road area, The water conservation measures for the project include land improvement; specifically: Step 221: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 222: After the removal of the hardened surface is completed, the area outside the recultivated area is leveled, and after the land leveling is completed, the topsoil is covered with a thickness of 30 cm; Plant water conservation measures include sowing grass seeds and planting shrubs; specifically: Step 223, using a hole-shaped land preparation method to prepare the land; Step 224, planting Pyracantha fortuneana and Blueberry, sowing grass seeds to restore vegetation on the mortar-stone grids on the roadbed slopes, and sowing grass to restore vegetation on the relatively gentle disturbance areas on both sides of the road, and the grass seeds selected are Cynodon dactylon and White Clover; Temporary water conservation measures include bagged soil blocking, temporary drainage, and geotextile covering; specifically: Step 225, using woven earthbags for protection; Step 226, covering the soil pile area or slope with geotextile; Step 227: lay earthen drainage ditches near the construction area and around the office and living area. After excavation, compact the bottom of the drainage ditch and the slopes on both sides.
7. A method for soil and water conservation for branch tunnels of a water diversion tunnel according to claim 4, characterized in that: When carrying out water conservation operations on the above-mentioned waste dump area, The water conservation measures of the project include slag interception engineering, grid slope protection engineering, flood drainage channel and rapid spreading of grass seeds, planting of Dianliu channel, drainage blind ditch, land improvement, intercepting ditch, horse road drainage ditch, drainage culvert; specifically: Step 231, the topsoil of the cultivated land, forest land and garden land within the scope of the waste dump is stripped to a thickness of 30 cm, and the stripped topsoil is transported to the topsoil storage yard for centralized storage; Step 232, the slag retaining wall is determined as a Class 3-4 building according to the level of the slag dump, and a mortar-stone slag retaining wall is set along the lower slope foot of each slag dump for protection; the flood drainage ditch and the surrounding intercepting ditch are designed as Class 3-4 buildings, and the drainage channel is set at the outer edge of the slag dump area of the slag dump; Step 233: after the slag is abandoned, a slag top drainage ditch is arranged on the top of the slag pile slope, and a horseway drainage ditch is arranged on the inner side of each level of the horseway; concrete lattice slope protection is used on the slag pile slope; Step 234: Arrange a stepped drop-off slope at the steep slope section of the surrounding drainage channel, with the drop-off slope being 0.5m high and connected to an energy dissipation pool at the end; Step 235: Level the abandoned slag field platform and the slag pile slope outside the recultivated area. After the land leveling is completed, topsoil is covered in the concrete grid of the leveled platform and slope, with a thickness of 30 cm. Plant water conservation measures include sowing grass seeds and planting trees; specifically: Step 236, restore vegetation on the slag platform by planting mixed trees and grasses, with Bermuda grass and white clover as grass species, and Quercus variabilis, Cinnamomum camphora, and Cypress yunnanensis as trees; Step 237, sowing grass on the basis of the grid structure of the slag field slope, the grass seeds are the same as those on the slag field platform, and the planting method and technical requirements are the same as those on the slag field platform; Temporary water conservation measures include bagged soil filling, temporary drainage, and temporary greening; specifically: Step 238: Arrange a bagged soil retaining wall at the foot of the soil slope of the topsoil storage area; arrange soil intercepting and drainage ditches on the topsoil storage surface, the horse path and the surrounding areas; Step 239: Sprinkle Bermuda grass seeds on the surface of the soil pile for protection.
8. A method for soil and water conservation for zoning branch tunnels of a water diversion tunnel according to claim 4, characterized in that: When carrying out water conservation operations in the construction, production and living areas, The water conservation measures of the project include land reclamation and sand settling ponds; specifically: Step 241: Before construction, the topsoil and loose layers within the construction area are stripped and piled nearby within the red line of the project area; Step 242: After the removal of the hardened surface is completed, the construction site outside the reclamation area is leveled, and after the land is leveled, the topsoil is covered with a thickness of about 30 cm; Step 243: At the drainage outlet of the construction production and living area, rainwater is discharged into the downstream ditch. The sand settling tank has a size of 2.0m long, 2.0m wide, and 1.2m deep and is built with C20 concrete; Plant water conservation measures include sowing grass seeds, planting shrubs and trees; and using mixed planting of trees, shrubs and grasses to restore vegetation. Specifically: Step 244, using a hole-shaped land preparation method to prepare the land; Step 245, planting tung oil tree, dung beetle, pyracantha, cypress, bermudagrass and white clover; Temporary water conservation measures include bagged soil filling, temporary drainage, temporary greening, and geotextile covering; specifically: Step 246, using woven earthbags for protection; Step 247, covering the soil pile area or slope with geotextile; Step 228, setting up earthen drainage ditches; Step 249: Sprinkle Bermuda grass seeds nearby for protection.