Variable cross-section pile for karst development site and construction method of variable cross-section pile
By adopting variable cross-section pile structures in karst development sites and using a combination of air bags and cast-in-place steel cages, the problem of concrete flow caused by karst caves has been effectively solved, construction efficiency and quality have been improved, and costs have been reduced.
Patent Information
- Application Number
- CN202411007741.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-10-22
AI Technical Summary
In the construction of karst development sites, due to the random distribution of karst caves, it is difficult for existing technologies to effectively avoid pile quality problems caused by concrete flow, resulting in high construction costs, delays in construction schedules, and potential safety hazards.
A variable cross-section pile structure is adopted, including an upper section of cast-in-place piles and a lower section of precast piles. An air bag is installed in the lower section of precast piles to seal the cave section. The larger diameter of the upper section of cast-in-place piles and the cast-in-place steel cage are used, combined with grouting pipes and exhaust pipes. , to achieve effective isolation and support of caves.
It simplifies the construction process, reduces material consumption, avoids quality problems caused by concrete flow, improves the stability of the pile body and construction efficiency, and reduces costs.
Smart Images

Figure CN118814768A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of construction of karst development sites, and in particular to a variable-section pile for use in karst development sites and a construction method thereof. Background Art
[0002] Karst refers to the general term for the phenomenon and effects of soluble rock layers, such as carbonate rock layers, which are produced by the chemical and physical effects of water, such as grooves, cracks and cavities, and sinkholes and depressions on the ground surface due to the collapse of the cavity roof. It is greatly affected by the flow of groundwater with dissolving capacity (including CO2). The specific scope and degree of erosion are greatly affected by the mineral composition of the rock and the degree of fragmentation caused by the structure. Therefore, the distribution of karst caves cannot be predicted. In pile foundation projects with limestone as the bearing layer, it is necessary to implement advanced drilling to identify the distribution of karst caves to guide pile foundation construction.
[0003] In general, pile foundations in karst development sites pass through caves and ensure that there are no caves within 5 to 6 meters below the pile end. Therefore, the length of the pile foundation entering the rock is generally large. Carbonate rock formations are generally hard, making it difficult to construct holes. In karst development sites, the distribution of caves is usually unpredictable, and there may be connected passages, which can easily lead to over-pouring of pile concrete or even failure to form piles, making construction costs difficult to control. In addition, the presence of caves can easily increase the fluidity of concrete, which can easily cause the quality of the pile body to deteriorate or even break the pile.
[0004] The following methods are usually used to cross the cave section:
[0005] ① Low-grade concrete re-driving method: first make a hole for the pile, pour low-grade concrete to fill the cave, then re-drive the pile and re-pour; this method consumes a lot of concrete, and the re-driving concrete construction is difficult and the drill bit is severely worn.
[0006] ②Sand pouring method: first make a hole for the pile, fill the cave with sand and gravel, then re-drive the pile and re-pour; it cannot completely avoid the pile body quality problems caused by concrete flow.
[0007] ③ Steel casing: Customized steel casing is placed in the cave section to complete the pouring of the entire pile by blocking the flow of concrete into the cave. For example, the anti-collapse impact hole construction method for complex karst sites disclosed in CN201711315383.1 uses steel casing to protect the wall, and uses a small stroke and low impact method to impact and form holes, and uses mud to protect the wall to form holes, so as to achieve construction in geologically complex karst sites, while ensuring the safety of pile driving machinery and operators and the quality of pile foundation. In addition, after the bored pile is poured, the steel casing can be pulled out for reuse. The construction process is cumbersome and still cannot completely avoid the pile body quality problems caused by concrete flow.
[0008] The above conventional methods have complicated construction procedures, great difficulty in drilling holes, and large amounts of concrete to be poured, which can easily cause construction delays and increase the cost of foundation projects. At the same time, due to the presence of karst caves, concrete flow can be easily caused, resulting in pile body quality not meeting requirements or even broken piles, bringing great quality and safety hazards to pile foundation projects.
[0009] CN201811499159.7 discloses a karst cave isolation device and a karst cave isolation method using the device. The method effectively isolates the karst section by respectively setting an upper closed air bag and a lower closed air bag at both ends of the isolation tube body and then inflating the borehole. Due to the randomness of karst distribution, the karst cave cannot be completely identified. This method has the problem of pile quality caused by concrete flow in the later pouring.
[0010] Another example is the backward intermittent controlled pre-grouting construction method for the super-large and super-deep karst cave pile foundation in the karst area disclosed in CN202311133487.6. This method adopts a variable diameter structure and annular airbags, and performs backward intermittent grouting construction into the karst cave through the side-detecting holes one by one, so as to form a consolidation body supporting the karst cave at the bored pile hole in the karst cave. After the subsequent drilling rig drills into the karst cave, it can continue to drill holes on the consolidation body. On the one hand, the consolidation body can limit the leakage of the rig's wall slurry; it is convenient for the bored pile construction; at the same time, the position support of the bored pile in the karst cave can be achieved through the consolidation body; the situation of cave collapse during the bored pile construction is reduced, and the karst cave does not need to be completely filled during grouting in this application, which is conducive to reducing the grouting cost of the karst cave. In the actual implementation process, due to the randomness of karst distribution, the karst cave cannot be completely identified, and this method has concrete flow in the later pouring to cause pile body quality problems.
[0011] The information disclosed in the background technology section is only intended to enhance the understanding of the overall background of the invention and should not be regarded as an admission or any form of suggestion that the information constitutes the prior art already known to a person skilled in the art. Summary of the invention
[0012] In response to the above-mentioned technical problems, the present application provides a variable-section pile for use in karst development sites and a construction method thereof. This method and structure have relatively simple construction procedures, reliable quality, and can effectively save material costs. It can effectively avoid the problems of over-pouring of concrete in karst caves, poor quality of pile body concrete, broken piles, etc. that occur when using conventional cast-in-place pile technology.
[0013] The present application provides a variable cross-section pile for a karst development site, comprising: an upper cast-in-place pile and a lower precast pile; the upper cast-in-place pile and the lower precast pile are arranged in a borehole; the borehole comprises: a precast section arranged in a rock layer, and a cast-in-place section arranged in a soil layer; the upper cast-in-place pile is cast and arranged in the cast-in-place section; the lower precast pile is accommodated and arranged in the precast section; the aperture of the cast-in-place section is larger than the aperture of the precast section; the lower precast pile extends into the cast-in-place section and is connected to the upper cast-in-place pile;
[0014] The lower prefabricated pile passes through the karst cave section, and air bags are arranged in the gap between the lower prefabricated pile and the prefabricated section. The air bags are arranged at intervals above and below the karst cave section and are sealed with the prefabricated section drilling hole;
[0015] Grouting is performed between the lower precast pile outside the airbag and the drilled hole.
[0016] Preferably, the diameter of the upper cast-in-place pile is 0.2 to 1.6 m larger than the diameter of the lower precast pile;
[0017] Preferably, the length of the lower prefabricated pile extending out of the cave section is 0.5 to 1 m;
[0018] Preferably, the distance between the air bag and the cave section is less than or equal to 0.5 m.
[0019] Preferably, it comprises: a plurality of inflatable tubes; one end of the inflatable tube is extended out of the ground, and the other end is connected to the air bag.
[0020] Preferably, it comprises: a plurality of reserved air inlet channels; the reserved air inlet channels are arranged in the lower prefabricated pile; one end of the reserved air inlet channels is connected to the airbag, and the other end of the reserved air inlet channels is connected to one end of the inflation tube.
[0021] Preferably, it comprises: a grouting pipe; one end of the grouting pipe is extended out of the ground, and the other end is connected with the bottom surface of the lower precast pile and the gap at the bottom of the drill hole.
[0022] Preferably, it includes: a reserved grouting channel; the reserved grouting channel is arranged on the side wall of the lower precast pile; one end of the reserved grouting channel is connected to the grouting pipe, and the other end is connected to the bottom surface of the lower precast pile and the drilling gap; the outlet end of the reserved grouting channel is arranged in the outer area of the airbag.
[0023] Preferably, it includes: a check valve and an exhaust pipe; the exhaust pipe and the check valve are arranged in pairs on both sides of the lower precast pile and are respectively arranged below the airbag; the check valve is arranged on the exhaust pipe; the exhaust pipe passes through the side wall of the lower precast pile and is connected to the external gap and the internal cavity of the lower precast pile.
[0024] Preferably, the upper section of the cast-in-place pile comprises: a cast-in-place pile section steel cage; the cast-in-place pile section steel cage is accommodated and arranged in the cast-in-place section; concrete is cast in the cast-in-place section and wraps the cast-in-place pile section steel cage;
[0025] Preferably, the cast-in-place pile segment reinforcement cage is connected to the lower segment precast pile via a connector.
[0026] Another aspect of the present application further provides a construction method of the variable cross-section pile for a karst development site as described above, comprising the following steps:
[0027] 1) Drill holes at the pile position by pre-drilling, collect soil samples at the pile position by pre-drilling, and find out the distribution thickness of the rock and soil layers at the pile position and the distribution position of the karst section;
[0028] 2) According to the thickness of the rock and soil layer obtained by detection, the length of the lower precast pile is calculated and determined. The length of the lower precast pile must be sufficient to penetrate the cave section and extend 0.5 to 1m;
[0029] 3) According to the distribution of the cave section, determine the location of the airbag on the lower precast pile. The distance between the airbag and the cave section is less than or equal to 0.5m and the airbag is set above and below the cave section. The lower precast pile is provided with a reserved grouting channel, a reserved air intake channel, an exhaust channel, an exhaust pipe, and a check valve;
[0030] 4) The lower precast pile is hoisted and installed in the drilled hole, one end of the grouting pipe installed in the pouring section is connected to the reserved grouting channel, one end of the inflation pipe installed in the pouring section is connected to the reserved air inlet channel, and the top of the lower precast pile is extended into the pouring section to set the connecting piece;
[0031] 5) After the airbag is inflated to the upper and lower areas of the closed cave section, grouting is pressurized into the gap between the lower precast pile and the drilled hole through the grouting pipe until the grouting is completed. The steel cage of the cast-in-place pile section is hoisted to perform solid-liquid concrete pouring of the upper cast-in-place pile to obtain the upper cast-in-place pile.
[0032] Preferably, the other end is obliquely extended toward the side wall of the upper cast-in-place pile;
[0033] Preferably, the lower prefabricated pile is a prefabricated hollow pile; a cavity is arranged inside the prefabricated hollow pile, and the cross section of the cavity is circular or square.
[0034] The beneficial effects of this application include:
[0035] 1) The variable-section piles and construction method thereof provided in the present application for karst development sites, the structure of which is achieved by setting a lower section precast pile in the rock layer section, the lower section precast pile is set through the cave section and air bags are respectively set above and below the cave section to effectively seal the cave section and prevent grouting from seeping out of the cave section. At the same time, the diameter of the upper section cast-in-place pile is larger than the diameter of the lower section precast pile, so that reliable force is obtained and the normal use of the precast pile in the lower section precast pile is guaranteed.
[0036] 2) The variable cross-section piles provided in this application for karst development sites use a prefabricated pile foundation with a smaller cross-sectional area and cooperate with the structure to achieve reliable force while reducing the material aperture and saving resources. The rock section of the structure has a smaller pile hole diameter, low mechanical torque requirements, and reduced construction difficulty, which is conducive to shortening the construction period. The rock section of the structure uses prefabricated piles to avoid the pile quality and broken pile problems of cast-in-place piles.
[0037] 3) The variable cross-section piles provided in this application for karst development sites use isolation air bags and post-grouting in the rock layer section and the cave section, which effectively avoids the problem of over-grouting and the difficulty of karst treatment, strengthens the bonding between the pile body and the rock layer, makes full use of the lateral friction resistance of the rock layer, and saves the loss of concrete materials. During the construction process of this method, large-diameter cast-in-place piles are used in the soil layer section, making full use of the lateral friction resistance of the soil layer. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a schematic diagram of a variable cross-section pile structure for a karst development site provided in an embodiment of the present application;
[0039] Figure 2 is a schematic front and cross-sectional view of a first installation state of a lower prefabricated pile provided in an embodiment of the present application;
[0040] Figure 3 is a front and cross-sectional schematic diagram of a second installation state of a lower prefabricated pile provided in an embodiment of the present application;
[0041] Figure 4 is a cross-sectional view of a lower prefabricated pile provided in an embodiment of the present application;
[0042] Figure 5 It is a schematic diagram of the main cross-section during the construction process of the construction method provided in the embodiment of the present application; a) opening a hole; b) installing the lower precast pile; c) pouring the upper cast-in-place pile;
[0043] Legend:
[0044] Cast-in-place pile section reinforcement cage 1, cast-in-place pile section pile body concrete 2, inflation pipe 3, grouting pipe 4, connecting piece 5, reserved air inlet channel 6, reserved grouting channel 7, air bag 8, reserved exhaust channel 9, check valve 10, precast pile 11, drill hole 12, cave section 13. DETAILED DESCRIPTION
[0045] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0046] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0047] The technical means that are not described in detail in this application and are not used to solve the technical problems of this application are all set according to the common knowledge in the field, and can be implemented in a variety of common knowledge settings.
[0048] See also Figures 1 to 4 The variable cross-section pile for karst development sites provided in the present application includes: an upper cast-in-place pile and a lower precast pile, wherein the upper cast-in-place pile is arranged in the soil layer, the lower precast pile is arranged in the rock layer, and the top of the lower precast pile extends into the soil layer and into the upper cast-in-place pile. In a specific embodiment, considering the hole-forming capacity of commonly used construction equipment, the pile diameter of the upper cast-in-place pile is 0.2 to 1.6 m larger than the pile diameter of the lower precast pile. To form a variable diameter structure.
[0049] The lower precast pile is installed in the bored precast section and extends into the bored cast-in-place section; the upper cast-in-place pile is installed in the bored cast-in-place section; the hole diameter of the bored precast section is smaller than the hole diameter of the bored cast-in-place section.
[0050] The lower precast pile is extended out of the karst cave section 13 , and one end of the lower precast pile extends out of the karst cave section 13 and a gap between the end and the drill hole 12 is filled with concrete slurry.
[0051] Air bags 8 are respectively arranged on the lower precast piles at intervals of the cave sections 13. The arrangement of the air bags 8 can prevent the poured slurry from entering the cave section 13 and leaking out, which will reduce the installation reliability of the lower precast piles. At the same time, by arranging the air bags 8 on the upper part of the cave section 13, it can be prevented that the concrete slurry poured in the upper cast-in-place piles enters the cave section 13 and overflows, affecting the force reliability of the upper cast-in-place piles. At the same time, by arranging the lower precast piles through the cave section 13, reliable support force can be obtained in this area to ensure the stability of the piles.
[0052] In a specific embodiment, the length of the lower precast pile extending out of the cave section 13 can be calculated according to design requirements, and specifically, the length can be 0.5 to 1 m. In this case, the reliability of the grouting of the lower precast pile and the borehole 12 that meets the use requirements can be obtained.
[0053] In a specific embodiment, the distance between the airbag 8 and the cave section 13 is less than 0.5 m. This arrangement can ensure that the extended section of the lower precast pile is reliably stressed and the column is reliably stressed.
[0054] In a specific embodiment, a connector 5 is provided on the connection interface between the upper cast-in-place pile and the lower precast pile to achieve reliable connection of the pile column after the diameter change.
[0055] In a specific embodiment, a cast-in-place pile segment reinforcement cage 1 is arranged in the bored cast-in-place segment, and concrete slurry is poured into the bored cast-in-place segment, thereby forming an upper segment cast-in-place pile.
[0056] In a specific embodiment, it includes: an air filling pipe 3 and a grouting pipe 4; the air filling pipe 3 and the grouting pipe 4 are accommodated in the borehole 12, and the air filling pipe 3 is connected with the air bag 8 to realize the inflation of the air bag 8 in the borehole 12 from the ground. The grouting pipe 4 extends out of the bottom of the lower precast pile, and a reserved grouting channel 7 is set on the ground of the lower precast pile. Through the grouting pipe 4, concrete slurry can be poured into the gap between the precast column section and the borehole 12 below the air bag 8 below the cave section 13.
[0057] In a specific embodiment, a cavity is provided in the hollow interior of the lower precast pile, which can be used to receive the gas generated when the extended section of the lower precast pile is poured with grout.
[0058] In a specific embodiment, the lower precast pile is provided with a reserved exhaust channel 9, an exhaust pipe, and a check valve 10 in pairs near the air bag 8; the exhaust pipe is provided in the reserved exhaust channel 9, and the check valve 10 is provided on the exhaust pipe. When the pile is lowered, the check valve is opened to facilitate the gas to enter the hollow cavity of the lower precast pile from the gap between the lower precast pile and the drill hole 12.
[0059] In a specific embodiment, the installation holes of the upper cast-in-place piles and the lower prefabricated piles are pile holes, which are formed by rotary drilling.
[0060] In a specific embodiment, the lengths of the prefabricated section and the cast section are determined by advance drilling, and the pile diameter is determined by calculation according to the load and formation parameters using existing methods.
[0061] The depth of the cave section 13 and the soil layer depth in the borehole 12 are obtained by using advance drilling, and the length of the precast section and the cast section in the borehole 12 is calculated based on the detection results. The positions of the grouting pipe channel and the exhaust pipe channel set on the rock section of the precast pile passing through the cave section 13 are determined, and the position of the exhaust pipe channel is reserved.
[0062] Place the connectors between the precast piles and the cast-in-place piles. The grouting pipes and exhaust pipes must be made of materials that meet the watertight and airtight pressure requirements, and the reserved channels of the lower precast piles and the pores of the pipes must be sealed.
[0063] See also Figure 5 Another aspect of the present application further provides a construction process of the above structure, comprising the following steps:
[0064] 1) Pre-drilling is performed at the pile position to open a borehole 12, and soil samples are collected at the pile position through pre-drilling to find out the distribution thickness of the rock layer and soil layer at the pile position and the distribution position of the karst section 13;
[0065] 2) According to the thickness of the rock and soil layer obtained by detection, the length of the lower precast pile is calculated and determined. The length of the lower precast pile must be sufficient to penetrate the cave section 13 and extend 0.5 to 1 m;
[0066] 3) According to the distribution of the cave section 13, determine the position of the airbag 8 above the lower precast pile and the reserved position of the grouting channel for the installation of the grouting pipe 4; the airbag 8 is located in the upper and lower sections outside the cave section 13, and the distance between the airbag 8 and the cave section 13 is less than or equal to 0.5m. After the airbag 8 is inflated, it has the effect of isolating the cave section 13, effectively preventing the injection slurry from seeping out of the cave section 13.
[0067] A reserved grouting channel 7 is arranged on the bottom surface of the lower precast pile, one end of which is located at the bottom of the lower precast pile. A reserved exhaust channel 9, an exhaust pipe and a check valve 10 are arranged close to the air bag 8 so as to facilitate the exhaust of the gas in the gap between the lower precast pile and the drill hole 12.
[0068] 4) Complete the installation of the grouting pipe 4 and the inflation pipe 3, the inflation pipe 3 is symmetrically arranged on both sides of the grouting pipe 4 and arranged in the drilled hole 12, and the connecting piece 5 is made;
[0069] 5) After the pile hole construction of the upper and lower sections is completed and the precast pile 11 set in the rock section 13 is hoisted and placed, multiple connectors 5 are set on the top of the precast pile 11; one end of the connector 5 is connected to the precast pile 11, and the other end of the connector 5 is obliquely extended to the steel bar set on the side wall of the upper section of the cast-in-place pile. The connector 5 with this structure can effectively, steadily and reliably transfer the load of the variable diameter section to the lower section precast pile with a smaller diameter, ensuring the force reliability of the structure.
[0070] In a specific embodiment, the connecting member 5 is a steel cage structure, and a steel plate is arranged on the end surface where the steel cage is connected to the precast pile 11 to obtain a reliable stress-bearing surface. The steel bars on the other open end of the steel cage extend obliquely toward the upper side wall of the cast-in-place pile.
[0071] 6) Inflate and pressurize each air bag 8 through the air intake pipe set in the reserved air intake channel 6, and each air bag 8 expands to the upper and lower areas of the closed cave section 13, and pressurizes and grouts the bottom of the borehole 12 through the grouting pipe 4 installed in the grouting channel. When the grouting slurry fills the gap, the grouting is stopped by the grouting pipe 4 and the exhaust pipes and check valves on both sides of the lower precast pile;
[0072] 7) The upper steel cage 1 is hoisted and the upper concrete is poured to obtain the pile body concrete 2 of the cast-in-place pile segment.
[0073] In a specific embodiment, according to engineering requirements, the pile body of the rock formation precast pile 11 can be a hollow circular cross-section pipe pile or a hollow square cross-section pile.
[0074] This method can reduce the diameter of the drill hole 12 in the rock section while obtaining reliable strength for use, and at the same time use the airbag 8 to effectively seal the cave section 13 area, thereby avoiding the problem of grout overflowing through the cave section 13 and causing a decrease in structural strength.
[0075] Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments, or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A variable cross-section pile for karst development sites, It is characterized in that include: The upper section has cast-in-place piles and the lower section has precast piles; The upper section cast-in-place pile and the lower section precast pile are arranged in the borehole; the borehole includes: a precast section arranged in the rock layer and a cast-in-place section arranged in the soil layer; The upper cast-in-place piles are cast in the cast-in-place section; the lower precast piles are accommodated in the precast section; the hole diameter of the cast-in-place section is larger than the hole diameter of the precast section; the lower precast piles extend into the cast-in-place section and are connected to the upper cast-in-place piles; The lower prefabricated pile passes through the karst cave section (13), and an air bag (8) is arranged in the gap between the lower prefabricated pile and the prefabricated section. The air bags (8) are arranged at intervals above and below the karst cave section (13) and are sealed with the prefabricated section borehole; Grouting is performed between the lower prefabricated pile outside the air bag (8) and the drill hole (12).
2. The variable cross-section pile for karst development sites according to claim 1, It is characterized in that The diameter of the upper cast-in-place pile is 0.2 to 1.6 m larger than the diameter of the lower precast pile; Preferably, the length of the lower prefabricated pile extending out of the cave section (13) is 0.5 to 1 m; Preferably, the distance between the air bag (8) and the cave section (13) is less than or equal to 0.5 m.
3. The variable cross-section pile for karst development sites according to claim 1, It is characterized in that include: A plurality of inflatable tubes (3); one end of the inflatable tube (3) is extended out of the ground, and the other end is connected to the air bag (8).
4. The variable cross-section pile for karst development sites according to claim 3, It is characterized in that include: A plurality of reserved air inlet channels (6); the reserved air inlet channels (6) are arranged in the lower prefabricated pile; one end of the reserved air inlet channels (6) is connected to the air bag (8), and the other end of the reserved air inlet channels (6) is connected to one end of the inflation tube (3).
5. The variable cross-section pile for karst development sites according to claim 1, It is characterized in that include: A grouting pipe (4); one end of the grouting pipe (4) is extended out of the ground, and the other end is connected with the bottom surface of the lower precast pile and the gap at the bottom of the drill hole (12).
6. The variable cross-section pile for karst development sites according to claim 5, It is characterized in that include: A reserved grouting channel (7) is provided on the side wall of the lower precast pile; one end of the reserved grouting channel (7) is connected to the grouting pipe (4), and the other end is connected to the gap between the bottom surface of the lower precast pile and the borehole (12); the outlet end of the reserved grouting channel (7) is provided in the outer area of the air bag (8).
7. The variable cross-section pile for karst development sites according to claim 1, It is characterized in that include: A check valve (10) and an exhaust pipe; the exhaust pipe and the check valve (10) are arranged in pairs on both sides of the lower precast pile and are respectively arranged below the airbag (8); the check valve (10) is arranged on the exhaust pipe; the exhaust pipe is arranged through the side wall of the lower precast pile and communicates with the external gap and the internal cavity of the lower precast pile.
8. The variable cross-section pile for karst development sites according to claim 1, It is characterized in that The upper section of the cast-in-place pile comprises: a cast-in-place pile section steel cage (1); the cast-in-place pile section steel cage (1) is accommodated and arranged in the cast-in-place section; concrete is cast in the cast-in-place section and wraps the cast-in-place pile section steel cage (1); Preferably, the cast-in-place pile segment reinforcement cage (1) is connected to the lower segment prefabricated pile via a connecting piece (5).
9. A construction method for variable cross-section piles used in karst development sites as claimed in any one of claims 1 to 8, It is characterized in that The following steps are involved: 1) Drill holes at the pile position by pre-drilling, collect soil samples at the pile position by pre-drilling, and find out the distribution thickness of the rock and soil layers at the pile position and the distribution position of the karst section; 2) According to the thickness of the rock and soil layer obtained by detection, the length of the lower precast pile is calculated and determined. The length of the lower precast pile must be sufficient to penetrate the cave section and extend 0.5 to 1m; 3) According to the distribution of the cave section, determine the location of the airbag on the lower precast pile. The distance between the airbag and the cave section is less than or equal to 0.5m and the airbag is set above and below the cave section. The lower precast pile is provided with a reserved grouting channel, a reserved air intake channel, an exhaust channel, an exhaust pipe, and a check valve; 4) The lower precast pile is hoisted and installed in the drilled hole, one end of the grouting pipe installed in the pouring section is connected to the reserved grouting channel, one end of the inflation pipe installed in the pouring section is connected to the reserved air inlet channel, and the top of the lower precast pile is extended into the pouring section to set the connecting piece; 5) After the airbag is inflated to the upper and lower areas of the closed cave section, grouting is pressurized into the gap between the lower precast pile and the drilled hole through the grouting pipe until the grouting is completed. The steel cage of the cast-in-place pile section is hoisted to perform solid-liquid concrete pouring of the upper cast-in-place pile to obtain the upper cast-in-place pile.
10. The method according to claim 9, It is characterized in that One end of the connecting piece is connected to the lower precast pile, and the other end is obliquely extended to the side wall of the upper cast-in-place pile; Preferably, the lower prefabricated pile is a prefabricated hollow pile; a cavity is arranged inside the prefabricated hollow pile, and the cross section of the cavity is circular or square.