Anchor net cable, W-shaped and T-shaped steel belt and guniting combined supporting process

Through the anchor net cable + W-shaped, T-shaped steel strip + shotcrete combined support technology, the problem that the existing technology cannot meet the tunnel support needs is solved, a more efficient tunnel support effect is achieved, and the stability and safety of the tunnel are ensured. sex.

CN118815501APending Publication Date: 2024-10-22GUIZHOU PANJIANG REFINED COAL
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411041362.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-31
Publication Date
2024-10-22

AI Technical Summary

Technical Problem

The existing support method of anchor rods + anchor net cables cannot meet the support needs of the 1100 substation level power supply tunnel in the first area of ​​the tunnel mining area.

Method used

The anchor net cable + W-type, T-type steel strip + shotcrete combined support technology is used, including support design, temporary support, construction of top anchors and installation of W-shaped steel strips, installation of anchor rods and installation of anchor cables, using specific Specifications of anchor rods, pallets, expanded steel mesh, W-shaped and T-shaped steel strips, and anchoring agents are used to support tunnels through continuous chaining and tensioning methods.

Benefits of technology

It improves the support effect of the roadway, can meet higher support requirements, and ensures the stability and safety of the roadway.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118815501A_ABST
    Figure CN118815501A_ABST
Patent Text Reader

Abstract

The invention discloses an anchor net cable, W-shaped and T-shaped steel belt and guniting combined supporting process which comprises the following steps: (1) supporting design and selection of supporting materials; (2) temporary supporting; (3) constructing a top anchor rod and installing a W-shaped steel belt; (4) mounting side anchor rods; and (5) mounting anchor cables. The supporting effect of the roadway can be improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an anchor net cable+W-shaped and T-shaped steel belt+grouting combined support process, belonging to the technical field of coal mine support. Background Art

[0002] A certain lane is used for horizontal power supply of the 1100 substation in Area 1. The lane is a development lane. Figure 1 As shown in the figure, the tunnel section is a three-center arch section, with a width of 5.7m at the bottom of the wasteland, a height of 3.7m in the middle of the wasteland, and a wasteland cross-sectional area of ​​18.8m. 2 ; Shotcrete thickness is 100mm, net bottom width B = 5.5m, net middle height H = 3.6m, net cross-sectional area S = 17.7m 2 .

[0003] The existing support method of anchor rod + anchor net cable cannot meet the support needs. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide an anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process to solve the technical problems existing in the above-mentioned prior art.

[0005] The technical solution adopted by the present invention is: anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process, including the following steps:

[0006] (1) Support design and selection of support materials;

[0007] (2) Temporary support;

[0008] (3) Construction of top anchor rods and installation of W-shaped steel strips;

[0009] (iv) Install anchor rods;

[0010] (V) Install anchor cables.

[0011] Preferably, the support design is as follows:

[0012] (I) The designed section is a three-center arch section, with a lower width B = 5.7m, a middle height H = 3.7m, and a cross-sectional area S = 18.8m 2 ; The spacing between anchor rods and rows is 900×900mm, the anchor cable specification is φ21.6-6300mm, the spacing between anchor rods and rows is 1800×1800mm, arranged in a “5-0-5” pattern, and 2.78 anchor cables are used per meter for support;

[0013] (ii) The anchor rod is made of φ20HRB335 (grade II) steel bar, right-handed full-threaded anchor rod (equal strength threaded steel anchor rod), 2500mm long;

[0014] (III) Pallet: The anchor pallet adopts a prestressed pallet with specifications of 150×150×10mm (length×width×thickness); the anchor cable pallet adopts a prestressed pallet with specifications of 300×300×14mm (length×width×thickness);

[0015] (IV) Expanded metal parameters: diamond mesh, specification 1700×1100mm, mesh spacing 50×90mm, overlap length 100mm, 14# iron wire double strands twisted to connect the mesh every 200mm at the overlap;

[0016] (V) The width of the W-shaped steel strip coil is 245mm, the thickness of the steel strip coil is 3mm, the length is 3.9m, and the hole spacing is 900mm; the W-shaped steel strip is arranged in full section, and the overlap length is ≥100mm;

[0017] (VI) T-shaped steel strip thickness is 5 mm, width is 170 mm, length is 3.9 m, and hole spacing is 1800 mm;

[0018] (VII) Anchoring agent model: MSK-2380 resin anchoring agent;

[0019] (VIII) Use 1 MSK-2380 resin anchor for each anchor rod, stir for 15-40s, and keep thrust for 30s after stopping; use 2 MSK-2380 resin anchors for each anchor cable, stir for 15-40s, and keep thrust for 30s after stopping;

[0020] (IX) Along the cross-sectional direction of the tunnel, W-shaped steel belts are used in conjunction with anchor rods for continuous interlocking, and along the longitudinal direction of the tunnel, T-shaped steel belts are used in conjunction with anchor cables for continuous interlocking.

[0021] Preferably, the steps for constructing the top anchor rod and installing the W-shaped steel belt are as follows:

[0022] (i) When the first W-shaped steel belt and anchor are installed under the onboard temporary support device, the next cycle of steel plate mesh is laid at the end of the steel belt. After the permanent support of the top is completed, the next cycle is cut off. The two side supports lag behind the top plate support by 0.9m;

[0023] (ii) When constructing the top anchor, place the extended support foot of the anchor bolt machine below the anchor bolt machine to be supported, and dig a groove with a depth of not less than 200mm on the bottom plate, and place the extended support foot into the groove;

[0024] (3) The bolter's extended support legs are made of 4-inch steel pipes and are 800-1200mm long;

[0025] (iv) Start the bolter pump station, extend the bolter and place the bolter handle on the workbench;

[0026] (V) During the installation of the anchor bolt machine, more than three persons must cooperate in the operation, and the personnel must obey the arrangements and coordination instructions of the anchor bolt machine operator and ensure that they hold the bolt machine steadily and release it slowly;

[0027] (VI) Hang an anti-swing rope (made of φ6.3mm steel wire rope and steel bar hook) on the left side of the handle, start the anchor bolt machine to construct anchor holes at the overlap position of the steel plate mesh;

[0028] (VII) After drilling an anchor hole, use the anchor to push a section of anchoring agent into the hole, and use the anchor machine to push the anchor into the bottom of the hole and stir for 15-40 seconds. After the anchor solidifies for 30 seconds, withdraw the anchor machine;

[0029] (VIII) Add a steel mesh in front and use 14# iron wire double strands to connect the mesh every 200mm at the overlap; install the W-shaped steel belt on the anchor and tighten the anchor nut;

[0030] (IX) When installing the first anchor rod on the steel belt, more than three persons must work together;

[0031] (10) When the anchor rods are constructed on both sides, after the anchor rod drilling construction is completed and before the anchor rods are installed, the tray and nut are installed at the end of the anchor rods in advance, and they are installed in the anchor rod hammer on the anchor rod machine. The anchor rod machine is extended to push the anchor rod into the bottom of the hole (if the anchor rod tray is skewed near the W-shaped steel belt, the tray must be corrected with tools such as drill rods, and the tray must not be corrected by hand). After the mixing and solidification time is in place, the anchor rod machine is retracted; continue to construct the anchor rod according to this operation;

[0032] (XI) 30 minutes after the anchor construction is completed, use a special torque wrench to tighten the anchor nuts;

[0033] (12) Before tightening the anchor bolt nut, the integrity of the special torque wrench must be checked first, and incomplete casing must not be used;

[0034] (13) During the process of tightening the nut, no one is allowed to be within the rotation range of the handle of the special torque wrench, and the operator must avoid the rotation track of the special torque wrench.

[0035] Preferably, the steps for installing the anchor rod are as follows:

[0036] (1) Connect the auxiliary net to be constructed with the reserved auxiliary net and top net;

[0037] (ii) Use an anchor bolt machine with a drill rod of 1.0m or 2.5m in length to construct the anchor bolt installation holes at the joints of the top net and the side net;

[0038] (iii) Inject a resin roll into the bolt installation hole, pass the bolt through the mesh holes at the overlapped part of the help net, and then connect the bolt with the tray and nut installed to the bolt machine with the bolt hammer. Start the bolt machine to push the bolt into place, rotate and stir while pushing, and stop pushing until the end of the bolt touches the bottom of the hole. Continue to rotate and tighten the nut to make the tray close to the rock surface. Stop the machine and wait for the resin roll to solidify, then withdraw the bolt machine;

[0039] (iv) Construct anchor bolt installation holes one by one according to the steel belt eye spacing, using an anchor bolt machine with a drill rod of 1.0m or 2.5m in length; the foot anchor bolts are constructed using a retractable anchor auxiliary machine in conjunction with an anchor bolt machine, and the angle between the anchor bolt and the rock surface shall not be less than 70°;

[0040] (V) Inject a resin roll into the anchor installation hole, use the anchor hammer to connect the anchor to the anchor machine, start the anchor machine to push the anchor, rotate and stir while pushing, and stop stirring when the end of the anchor touches the bottom of the hole. Then install the anchor tray and nut, and tighten the anchor nut with a special torque wrench after 10 minutes.

[0041] Preferably, the steps for installing the anchor cable are as follows:

[0042] (1) When constructing the top anchor cable, personnel should stand on the tunneling machine and the bolter should use extended support feet;

[0043] (ii) When the bolter uses an extended support foot, a groove of more than 200 mm deep should be dug to bury the bottom of the bolter's outer cylinder into the extended support foot (the length of the bottom of the bolter's outer cylinder entering the extended support foot should not be less than 500 mm);

[0044] (III) When using extended support legs to support the bolter, more than three persons must cooperate in the operation, and two persons must assist the driver in holding the bolter steady during the unloaded extension and retraction process;

[0045] (IV) When disassembling the combined drill rod, the joints must be disassembled with a wrench;

[0046] (V) If the hole for the anchor cable is broken or collapsed, it must be treated or re-drilled to ensure that the hole is in good condition to facilitate the installation of the anchor cable;

[0047] (VI) When inserting the resin anchor into the hole of the anchor cable, if there are small pieces of gangue in the hole, the hole should be cleaned and drilled before inserting the resin anchor. Do not forcefully cut the anchor and push the anchor cable to the bottom of the hole.

[0048] (VII) After using the anchor cable to push the resin anchor to the bottom of the drill hole, install the anchor cable tray 200-250mm above the tail of the anchor cable, then tighten the anchor and install it into the anchor cable hammer on the anchor bolter, and extend the anchor bolter to make the anchor cable tray close to the T-shaped steel belt; when the anchor bolter extends and pushes the anchor cable into the hole, it should be pushed upward while rotating. When extending, no one should be within 1.5m around the anchor cable tray. When the end tray is not straight, it should be aligned with tools such as drill rods. It is strictly forbidden to align the tray by hand;

[0049] (VIII) When installing resin anchors, tensioning anchor cables, and placing T-shaped steel strips more than 2m above the bottom plate, the operator must stand on the tunneling machine;

[0050] (IX) During operation, two persons pass the jack through the anchor cable and press it against the anchor, then hang the hook on the nearby steel plate net, apply pressure and start tensioning the jack for tensioning;

[0051] (10) During tensioning, after the jack clamps the anchor cable, the person holding the jack and the people below shall be promptly withdrawn to 2 meters away. After the anchor cable is pulled to the specified pre-tightening force and the pressure is maintained, two people shall hold the jack firmly to release the pressure. After loosening, remove the hook and jack;

[0052] (11) The person holding the jack can only stand on the side where the anchor cable needs to be tensioned and must not stand directly below;

[0053] (12) When holding the jack, you can only hold the handle or the side of the tail of the jack. It is strictly forbidden to put your hands between the front end of the jack and the joint of the anchor;

[0054] (13) During the process of tensioning the anchor cable, if the height is not enough, the person holding or supporting the jack must stand on the tunnel boring machine to operate.

[0055] Beneficial effects of the present invention: Compared with the prior art, the present invention proposes a combined support process of anchor mesh cable + W-shaped and T-shaped steel belts + shotcrete, which can improve the support effect of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 It is a cross-sectional diagram of tunnel support.

[0057] Figure 2 yes Figure 1 Enlarged view of part A in the middle.

[0058] Figure 3 This is the side view of the tunnel support.

[0059] The reference numerals in the drawings of the specification include: tunnel 1, T-shaped steel belt 2, anchor rod 3, W-shaped steel belt 4, anchor cable 5. DETAILED DESCRIPTION

[0060] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.

[0061] Embodiment 1:

[0062] The anchor net cable + W-shaped and T-shaped steel belt + shotcrete combined support process includes the following steps:

[0063] (1) Support design and selection of support materials;

[0064] (2) Temporary support;

[0065] (iii) constructing top anchor rods 3 and installing W-shaped steel strips 4;

[0066] (iv) Install the anchor rod 3;

[0067] (V) Install anchor cable 5.

[0068] In this embodiment, the support design is as follows:

[0069] (I) The design of the tunnel 1 section is a three-center arch section. Figure 1-Figure 3 As shown, the lower width B = 5.7m, the middle height H = 3.7m, and the cross-sectional area S = 18.8m 2 ; The spacing between anchor rods 3 is 900×900mm, the specifications of anchor cables 5 are φ21.6-6300mm, the spacing between anchor rods 5 is 1800×1800mm, and the arrangement is "5-0-5". 2.78 anchor cables 5 are used for support per meter;

[0070] (ii) Anchor rod 3 is made of φ20HRB335 (grade II) steel bar and is a right-handed fully threaded anchor rod (equal strength threaded steel anchor rod) with a length of 2500 mm;

[0071] (III) Pallet: The anchor 3 pallet adopts a prestressed pallet with specifications of 150×150×10mm (length×width×thickness); the anchor cable 5 pallet adopts a prestressed pallet with specifications of 300×300×14mm (length×width×thickness);

[0072] (IV) Expanded metal parameters: diamond mesh, specification 1700×1100mm, mesh spacing 50×90mm, overlap length 100mm, 14# iron wire double strands twisted to connect the mesh every 200mm at the overlap;

[0073] (V) The width of the W-shaped steel strip 4 steel coils is 245mm, the thickness of the steel coils is 3mm, the length is 3.9m, and the hole spacing is 900mm; the W-shaped steel strip 4 is arranged in full section, and the overlap length is ≥100mm;

[0074] (vi) T-shaped steel belt 2 has a thickness of 5 mm, a width of 170 mm, a length of 3.9 m, and a hole spacing of 1800 mm;

[0075] (VII) Anchoring agent model: MSK-2380 resin anchoring agent;

[0076] (VIII) Each anchor rod 3 uses 1 MSK-2380 resin anchor, the stirring time is 15-40s, and the thrust is maintained for 30s after stopping; each anchor cable 5 uses 2 MSK-2380 resin anchors, the stirring time is 15-40s, and the thrust is maintained for 30s after stopping;

[0077] (IX) Along the cross-sectional direction of the tunnel 1, W-shaped steel belts 4 are used in conjunction with anchor rods 3 for continuous interlocking, and along the longitudinal direction of the tunnel 1, T-shaped steel belts 2 are used in conjunction with anchor cables 5 for continuous interlocking.

[0078] In this embodiment, a ZLJ-20 airborne temporary support device is used for temporary support.

[0079] (I) Installation of the onboard temporary support device: First remove the two front axles of the lifting cylinder of the cutting part of the excavator and the two connecting pins of the cutting part and the slewing table, then replace them with the extended axles, then install the two front cylinders and the station sleeve (pipe), and finally connect the support frame. During the installation process, install the oil pipeline first to facilitate adjustment.

[0080] (II) Operation procedures of the airborne temporary support device:

[0081] 1. After the excavator completes the cutting operation, the cutting head will fall to the ground.

[0082] 2. Check whether the components and pipelines of each part of the airborne temporary support device are normal.

[0083] 3. Turn the two-position three-way valve to the support position, turn on the switch of the tunnel boring machine pump station, and supply oil to the temporary support device.

[0084] 4. Place the steel belt and steel plate mesh to be supported on the temporary support frame and attract them with magnets. Push the support station sleeve (tube) and the support frame hydraulic control handle forward. Slowly and steadily open the station sleeve (tube) and the support frame from the disassembled state. Open them to the required angle and position, then raise the station pipe until it reaches the upper roof of tunnel 1, and press the steel belt and steel plate mesh onto the upper roof of tunnel 1.

[0085] 5. The top anchor rod 3 and the top steel belt must be constructed in a reliable support location.

[0086] 6. After the construction of anchor rod 3 is completed, first lower the station pipe to the lowest position, then fold the station sleeve (pipe) and the support frame until the support frame falls on the tunnel boring machine, turn off the switch of the tunnel boring machine pump station, and turn the two-position three-way valve to the tunnel boring machine position to make the tunnel boring machine work normally and carry out the next cycle of excavation.

[0087] (III) Maintenance and precautions of airborne temporary support device

[0088] 1. The onboard temporary support device should be equipped with a main driver and two assistant drivers to operate it. The main driver should be the driver of the tunnel boring machine and be responsible for operating the valve. The assistant drivers should be responsible for observation and command, placing the steel belts and steel plate mesh on the top beam frame, etc.

[0089] 2. The onboard temporary support device must be equipped with an onboard methane sensor, which can shut down and lock the tunnel boring machine when the gas exceeds the limit alarm.

[0090] 3. The main driver of the airborne temporary support device should understand the performance characteristics of the machine, be familiar with the operating procedures, master the operating essentials, and have the ability to independently troubleshoot. He can only take up the post after passing the technical training and assessment.

[0091] 4. When the support is opened, the assistant driver should pay attention to whether there are any abnormal phenomena in the joints and pipelines of the support, and whether the steel belt and steel plate mesh are hanging.

[0092] 5. Pay attention to maintaining the oil level in the fuel tank and observe that the oil temperature does not exceed 70℃.

[0093] 6. Fill the shaft with butter before work every day.

[0094] 7. Hydraulic parts must not be disassembled at will, and dirt must be strictly prevented from entering the pipelines and contaminating the hydraulic oil and hydraulic components.

[0095] 8. When the support is tightening the top plate of tunnel 1, the tunnel boring machine must not move. When work is required, the support should be retracted first, and then the tunnel boring machine should be moved.

[0096] 9. When tunnel 1 is too high, leave some residual rock appropriately and place the cutting head on the residual rock to achieve the ideal support effect.

[0097] Note:

[0098] ① When the support is not high enough, you should first lower the support, then raise the gun head, and then raise the support again.

[0099] ② When retracting the support, make sure it is in place to prevent damage to the cylinder piston rod.

[0100] ③ For support with clamps, put all the small cylinders into place after the support is completed to prevent the piston rod from being damaged.

[0101] (IV) After the permanent support is completed, or the operation is stopped for other reasons (drilling, end of shift, maintenance), the loose gangue at the head must be removed, the protective net must be hung at the head and fixed with 3 2.5m long point anchors. There must be no empty side or top. The point anchors must be 3 with a row spacing of 2.0×2.0m.

[0102] In this embodiment, the steps of constructing the top anchor rod 3 and installing the W-shaped steel belt 4 are as follows:

[0103] (i) When the first top W-shaped steel belt 4 and anchor 3 are installed under the onboard temporary support device, the next cycle of steel plate mesh is laid at the end of the steel belt. After the top permanent support is completed, the next cycle is cut off. The two side supports lag behind the top plate support by 0.9m;

[0104] (ii) When constructing the top anchor 3, place the extended support foot of the anchor bolt machine below the anchor bolt machine to be supported, and dig a groove with a depth of not less than 200 mm on the bottom plate, and place the extended support foot into the groove;

[0105] (3) The bolter's extended support legs are made of 4-inch steel pipes and are 800-1200mm long;

[0106] (iv) Start the bolter pump station, extend the bolter and place the bolter handle on the workbench;

[0107] (V) During the installation of the anchor bolt machine, more than three persons must cooperate in the operation, and the personnel must obey the arrangements and coordination instructions of the anchor bolt machine operator and ensure that they hold the bolt machine steadily and release it slowly;

[0108] (VI) Hang an anti-swing rope (made of φ6.3mm steel wire rope and steel bar hook) on the left side of the handle, start the anchor bolt machine to construct anchor holes at the overlap position of the steel plate mesh;

[0109] (VII) After drilling a hole for an anchor rod 3, use the anchor rod 3 to push a section of anchoring agent into the hole, and use an anchor bolter to push the anchor rod 3 into the bottom of the hole and stir for 15-40 seconds. After the anchoring agent solidifies for 30 seconds, withdraw the anchor bolter;

[0110] (VIII) Add a steel plate mesh forward and use 14# iron wire double strands to connect the mesh every 200mm at the overlap; install the W-shaped steel belt 4 on the anchor rod 3 and tighten the nuts of the anchor rod 3;

[0111] (IX) When installing the first anchor rod 3 on the steel belt, more than 3 persons must work together;

[0112] (J) When the anchor rod 3 is continued to be constructed on both sides, after the drilling construction of the anchor rod 3 is completed, before installing the anchor rod 3, a tray and a nut are installed at the end of the anchor rod 3 in advance, and it is installed in the anchor hammer on the anchor machine, and the anchor machine is extended to push the anchor rod 3 into the bottom of the hole (if the tray of the anchor rod 3 is skewed when it is pushed near the W-shaped steel belt 4, the tray must be corrected with a tool such as a drill rod, and the tray must not be corrected by hand), and the anchor machine is retracted after the mixing and solidification time is in place; continue to construct the anchor rod 3 according to this operation;

[0113] (XI) 30 minutes after the construction of anchor rod 3 is completed, use a special torque wrench to tighten the nut of anchor rod 3;

[0114] (XII) Before tightening the anchor bolt 3 nut, you must first check the integrity of the special torque wrench and do not use an incomplete casing;

[0115] (13) During the process of tightening the nut, no one is allowed to be within the rotation range of the handle of the special torque wrench, and the operator must avoid the rotation track of the special torque wrench.

[0116] In this embodiment, the steps for installing the anchor rod 3 are as follows:

[0117] (1) Connect the auxiliary net to be constructed with the reserved auxiliary net and top net;

[0118] (ii) Use an anchor bolt machine with a drill rod of 1.0m or 2.5m in length to construct the anchor bolt installation holes at the joints of the top net and the side net;

[0119] (iii) Inject a resin roll into the bolt installation hole, pass the bolt 3 through the mesh of the overlapping part of the auxiliary net, and then connect the bolt 3 with the tray and nut installed to the bolt machine with the bolt hammer, start the bolt machine to push the bolt 3 into place, rotate and stir while pushing, stop pushing until the end of the bolt 3 touches the bottom of the hole, continue to rotate and tighten the nut to make the tray close to the rock surface, stop the machine and wait for the resin roll to solidify, and then withdraw the bolt machine;

[0120] (IV) Construct the anchor bolt installation holes one by one according to the steel belt eye spacing, and use an anchor bolt machine with a drill rod of 1.0m and 2.5m in length for construction. The foot anchor 3 is constructed with a retractable anchor auxiliary machine in combination with an anchor bolt machine, and the angle between the anchor 3 and the rock surface shall not be less than 70°;

[0121] (V) Inject a resin roll into the anchor installation hole, use the anchor hammer to connect the anchor 3 to the anchor machine, start the anchor machine to push the anchor 3, rotate and stir while pushing, and stop stirring when the end of the anchor 3 touches the bottom of the hole, then install the anchor 3 tray and nut, and tighten the anchor 3 nut with a special torque wrench after 10 minutes.

[0122] In this embodiment, the steps for installing the anchor cable 5 are as follows:

[0123] (i) When constructing the top anchor cable 5, personnel stand on the tunneling machine and the bolter should use extended support feet;

[0124] (ii) When the bolter uses an extended support foot, a groove of more than 200 mm deep should be dug to bury the bottom of the bolter's outer cylinder into the extended support foot (the length of the bottom of the bolter's outer cylinder entering the extended support foot should not be less than 500 mm);

[0125] (III) When using extended support legs to support the anchor bolt machine, more than three persons must cooperate in the operation, and two persons must cooperate with the driver to hold the anchor bolt machine steady during the unloaded extension and retraction process.

[0126] (IV) When disassembling the combined drill rod, the joints must be disassembled with a wrench.

[0127] (V) If the hole of the anchor cable 5 is broken or collapsed, it must be processed or re-drilled to ensure that the hole is in good condition to facilitate the installation of the anchor cable 5.

[0128] (VI) When loading the resin anchor into the hole of the anchor cable 5, if there are small pieces of gangue in the hole, the hole must be cleaned and drilled before loading the resin anchor. Do not forcibly cut the anchor and push the anchor cable 5 to the bottom of the hole.

[0129] (VII) After using the anchor cable 5 to push the resin anchor to the bottom of the drill hole, install the anchor cable tray 200-250mm above the tail of the anchor cable 5, then tighten the anchor and install it into the anchor hammer on the anchor bolt machine, and extend the anchor bolt machine to make the anchor cable tray close to the T-shaped steel belt 2; when the anchor bolt machine extends and pushes the anchor cable 5 into the hole, it should be pushed upward while rotating. When extending it, no one should be within 1.5m around the anchor cable tray. When the end tray is not straight, it should be aligned with tools such as drill rods. It is strictly forbidden to align the tray by hand.

[0130] (VIII) When installing resin anchor, tensioning anchor cable 5 and upper T-shaped steel belt 2 more than 2m above the bottom plate, the operator must stand on the tunnel boring machine.

[0131] (IX) During operation, two persons pass the jack through the anchor cable 5 and press it against the anchor, then hang the hook on the nearby steel plate net, apply pressure and start tensioning the jack for tensioning.

[0132] (10) During tensioning, after the jack clamps the anchor cable 5, the personnel holding the jack and the personnel below shall be promptly withdrawn to 2 meters away. After the anchor cable 5 is pulled to the specified pre-tightening force and the pressure is maintained, two people shall hold the jack steadily to relieve the pressure. After it is loosened, the hook and jack shall be removed.

[0133] (XI) The person holding the jack can only stand on the side where the anchor cable 5 needs to be tensioned to operate, and must not stand directly below.

[0134] (12) When holding the jack, you can only hold the handle or the side of the tail of the jack. It is strictly forbidden to put your hands between the front end of the jack and the joint of the anchor.

[0135] (XIII) During the tensioning of the anchor cable 5, if the height is not enough, the personnel holding and supporting the jack must stand on the tunnel boring machine to operate.

[0136] Permanent support precautions:

[0137] (I) Construction requirements for anchor cable 5: It should be driven vertically into the rock surface, with an angle of not less than 75° with tunnel 1, 2 sections of anchoring agent should be used, the mixing time should be 15-40 seconds (including the mixing time during the process of pushing anchor cable 5 to the bottom of the hole), the thrust should be maintained for 30 seconds when stopped, and the exposed length should be 150-250mm; it must be tightened with a hydraulic tensioning jack, and the pre-tightening force should not be less than 40MPa.

[0138] (II) Construction requirements for anchor 3: Anchor 3 should be driven into the rock surface vertically, with an angle of not less than 75° with tunnel 1, one section of anchoring agent should be used, the mixing time should be 15-40 seconds (including the mixing time during the process of pushing anchor 3 to the bottom of the hole), the machine should be stopped to maintain the thrust for 30 seconds, the exposed length should be 10-100mm, and it must be driven at the overlap of the steel mesh.

[0139] (III) Overlap length of steel mesh: 100mm, and 14 # The iron wires are interlaced and twisted to form a network; the nuts of anchor rod 3 must be tightened with a special torque wrench, and the tightening torque of the nuts must not be less than 400N·m.

[0140] (IV) Anchor cables 5 with exposed length of 250mm-600mm and tension force less than 40MPa need to be re-installed. If the tension force reaches 40MPa, the excess length should be cut and the exposed length should be greater than 600mm and re-installed. Anchor rods 3 with tightening torque less than 400N·m should be re-installed. When cutting the extra-long anchor cables 5, a safety officer must be present to supervise on site.

[0141] (V) The steel mesh shall be laid from the top plate of tunnel 1 to the 3 anchor rods on both sides that are closest to the bottom plate. The steel mesh must be laid flat, straight and close to the rock surface.

[0142] (VI) Anchor rods 3 (anchor cables 5) must be driven into the holes of steel belts. If an anchor rod 3 (anchor cable 5) fails or the hole of the anchor rod 3 (anchor cable 5) is broken or collapsed, additional anchor rods 3 (anchor cables 5) must be driven next to it for support. The additional anchor rods 3 (anchor cables 5) do not need to be driven into the holes of steel belts, but the steel belts must be pressed.

[0143] (VII) During support, after drilling a hole for installing an anchor rod 3 (or anchor cable 5), a resin roll for one hole must be installed to anchor an anchor rod 3 (or anchor cable 5).

[0144] (VIII) Before tensioning the anchor cable 5, the hole mouth must be leveled, the pallet anchor must be placed, and then the tensioning jack must be installed for tensioning.

[0145] (IX) When prestressing the anchor cable 5, it must be tensioned in stages and the tensioning stroke at one time shall not exceed 150mm. During tensioning, the jack and the anchor cable 5 must be kept in the same straight line.

[0146] (10) During the construction process, if the roof of tunnel 1 is broken or the geological structure is broken, and the on-site support cannot meet the support requirements, the support form shall be modified in time according to the on-site conditions, and safety technical measures shall be prepared separately.

[0147] (XI) During the construction of point anchoring and permanent support, personnel must stand under the permanent support. Workers are strictly prohibited from facing away from the front. They should be able to observe the situation of the front support from the standing position. It is strictly prohibited to work with an empty top.

[0148] (XII) The top anchor rod 3 is closely followed by the head-on support, and the anchor cable 5 lags behind the head-on support by no more than 5m. When the pressure in the tunnel 1 is high or the surrounding rock is broken, the top anchor rod 3 and the anchor cable 5 must be closely followed by the head-on support.

[0149] (13) During the support process, a dedicated person must be assigned to observe the mountain and to check the top of the mountain at any time. If there is any danger, personnel must be evacuated immediately and work can only be continued after the hidden danger has been eliminated.

[0150] (XIV) When erecting the mesh, 2 to 3 people are required to work together. The workers must wear gloves, cooperate with each other, lift steadily and put down gently, and do not put their hands into the interface of the mesh to prevent scratches.

[0151] (15) Strengthen the management of the roof. During the operation, knock on the roof at any time to find all the hanging holes of active waste rock. Set up temporary support and strictly prohibit the operation of the roof without any gap.

[0152] (XVI) Anchor net cable spraying tunnel 1 support parameters reference table 1.

[0153] Table 1 Anchor mesh cable spraying tunnel 1 support parameter reference table

[0154]

[0155] The above description is only a specific implementation mode of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the present invention, which should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.

Claims

1. Anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process, characterized by: The following steps are involved: (1) Support design and selection of support materials; (2) Temporary support; (3) Construction of top anchor rods and installation of W-shaped steel strips; (iv) Install anchor rods; (V) Install anchor cables.

2. The anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process according to claim 1 is characterized by: The support design is as follows: (I) The designed section is a three-center arch section, with a lower width B = 5.7m, a middle height H = 3.7m, and a cross-sectional area S = 18.8m 2 ; The spacing between anchor rods and rows is 900×900mm, the anchor cable specification is φ21.6-6300mm, the spacing between anchor rods and rows is 1800×1800mm, arranged in a "5-0-5" pattern, and 2.78 anchor cables are used per meter for support; (ii) The anchor rod is made of φ20HRB335 (grade II) steel bar, right-handed full-threaded anchor rod (equal strength threaded steel anchor rod), 2500mm long; (III) Pallet: The anchor pallet adopts a prestressed pallet with specifications of 150×150×10mm (length×width×thickness); the anchor cable pallet adopts a prestressed pallet with specifications of 300×300×14mm (length×width×thickness); (IV) Expanded metal parameters: diamond mesh, specification 1700×1100mm, mesh spacing 50×90mm, overlap length 100mm, 14# iron wire double strands twisted to connect the mesh every 200mm at the overlap; (V) The width of the W-shaped steel strip coil is 245mm, the thickness of the steel strip coil is 3mm, the length is 3.9m, and the hole spacing is 900mm; the W-shaped steel strip is arranged in full section, and the overlap length is ≥100mm; (vi) The thickness of the T-shaped steel strip is 5 mm, the width is 170 mm, the length is 3.9 m, and the hole spacing is 1800 mm; (vii) The anchoring agent model is: MSK-2380 resin anchoring agent; (VIII) Use 1 MSK-2380 resin anchor for each anchor rod, stir for 15-40s, and keep thrust for 30s after stopping; use 2 MSK-2380 resin anchors for each anchor cable, stir for 15-40s, and keep thrust for 30s after stopping; (IX) Along the cross-sectional direction of the tunnel, W-shaped steel belts are used in conjunction with anchor rods for continuous interlocking, and along the longitudinal direction of the tunnel, T-shaped steel belts are used in conjunction with anchor cables for continuous interlocking.

3. The anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process according to claim 1 is characterized by: The steps for constructing the top anchor and installing the W-shaped steel belt are as follows: (i) When the first W-shaped steel belt and anchor are installed under the onboard temporary support device, the next cycle of steel plate mesh is laid at the end of the steel belt. After the permanent support of the top is completed, the next cycle is cut off. The two side supports lag behind the top plate support by 0.9m; (ii) When constructing the top anchor, place the extended support foot of the anchor bolt machine below the anchor bolt machine to be supported, and dig a groove with a depth of not less than 200mm on the bottom plate, and place the extended support foot into the groove; (3) The bolter's extended support legs are made of 4-inch steel pipes and are 800-1200mm long; (iv) Start the bolter pump station, extend the bolter and place the bolter handle on the workbench; (V) During the installation of the anchor bolt machine, more than three persons must cooperate in the operation, and the personnel must obey the arrangements and coordination instructions of the anchor bolt machine operator and ensure that they hold the bolt machine steadily and release it slowly; (VI) Hang an anti-swing rope (made of φ6.3mm steel wire rope and steel bar hook) on the left side of the handle, start the anchor bolt machine to construct anchor holes at the overlap position of the steel plate mesh; (VII) After drilling an anchor hole, use the anchor to push a section of anchoring agent into the hole, and use the anchor machine to push the anchor into the bottom of the hole and stir for 15-40 seconds. After the anchor solidifies for 30 seconds, withdraw the anchor machine; (VIII) Add a steel mesh in front and use 14# iron wire double strands to connect the mesh every 200mm at the overlap; install the W-shaped steel belt on the anchor and tighten the anchor nut; (IX) When installing the first anchor rod on the steel belt, more than three persons must work together; (10) When the anchor rods are constructed on both sides, after the anchor rod drilling construction is completed and before the anchor rods are installed, the tray and nut are installed at the end of the anchor rods in advance, and they are installed in the anchor rod hammer on the anchor rod machine. The anchor rod machine is extended to push the anchor rod into the bottom of the hole (if the anchor rod tray is skewed near the W-shaped steel belt, the tray must be corrected with tools such as drill rods, and the tray must not be corrected by hand). After the mixing and solidification time is in place, the anchor rod machine is retracted; continue to construct the anchor rod according to this operation; (XI) 30 minutes after the anchor construction is completed, use a special torque wrench to tighten the anchor nuts; (12) Before tightening the anchor bolt nut, the integrity of the special torque wrench must be checked first, and incomplete casing must not be used; (13) During the process of tightening the nut, no one is allowed to be within the rotation range of the handle of the special torque wrench, and the operator must avoid the rotation track of the special torque wrench.

4. The anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process according to claim 1 is characterized in that: The steps for installing the anchor rod are as follows: (1) Connect the auxiliary net to be constructed with the reserved auxiliary net and top net; (ii) Use an anchor bolt machine with a drill rod of 1.0m or 2.5m in length to construct the anchor bolt installation holes at the joints of the top net and the side net; (iii) Inject a resin roll into the bolt installation hole, pass the bolt through the mesh holes at the overlapped part of the help net, and then connect the bolt with the tray and nut installed to the bolt machine with the bolt hammer. Start the bolt machine to push the bolt into place, rotate and stir while pushing, and stop pushing until the end of the bolt touches the bottom of the hole. Continue to rotate and tighten the nut to make the tray close to the rock surface. Stop the machine and wait for the resin roll to solidify, then withdraw the bolt machine; (iv) Construct anchor bolt installation holes one by one according to the steel belt eye spacing, using an anchor bolt machine with a drill rod of 1.0m or 2.5m in length; the foot anchor bolts are constructed using a retractable anchor auxiliary machine in conjunction with an anchor bolt machine, and the angle between the anchor bolt and the rock surface shall not be less than 70°; (V) Inject a resin roll into the anchor installation hole, use the anchor hammer to connect the anchor to the anchor machine, start the anchor machine to push the anchor, rotate and stir while pushing, and stop stirring when the end of the anchor touches the bottom of the hole. Then install the anchor tray and nut, and tighten the anchor nut with a special torque wrench after 10 minutes.

5. The anchor net cable + W-shaped, T-shaped steel belt + shotcrete combined support process according to claim 1 is characterized in that: The steps for installing the anchor cable are as follows: (i) When constructing the top anchor cable, personnel stand on the tunnel boring machine, and the bolter should use the extended support foot; (ii) When the bolter uses the extended support foot, a groove more than 200 mm deep should be dug to bury the bottom of the bolter's outer cylinder into the extended support foot (the length of the bottom of the bolter's outer cylinder entering the extended support foot should not be less than 500 mm); (III) When using extended support legs to support the bolter, more than three persons must cooperate in the operation, and two persons must assist the driver in holding the bolter steady during the unloaded extension and retraction process; (iv) When disassembling the combined drill rod, the joints must be disassembled with a wrench; (V) If the hole for the anchor cable is broken or collapsed, it must be treated or re-drilled to ensure that the hole is in good condition to facilitate the installation of the anchor cable; (vi) When loading the resin anchor into the hole of the anchor cable, if there are small pieces of gangue in the hole, the resin anchor should be loaded after cleaning the hole. Do not forcibly cut the anchor to push the anchor cable to the bottom of the hole; (vii) After using the anchor cable to push the resin anchor to the bottom of the hole, install the anchor cable tray 200-250mm above the tail of the anchor cable, then tighten the anchor and load it into the anchor cable hammer on the anchor bolter, and extend the anchor bolter to make the anchor cable tray close to the T-shaped steel belt; when the anchor bolter is extended to push the anchor cable into the hole, it should be pushed upward while rotating. When extending, no one should be within 1.5m around the anchor cable tray. When the end tray is not straight, it should be aligned with tools such as drill rods. It is strictly forbidden to align the tray by hand; (VIII) When installing resin anchors, tensioning anchor cables, and placing T-shaped steel strips more than 2m above the bottom plate, the operator must stand on the tunneling machine; (IX) During operation, two persons pass the jack through the anchor cable and press it against the anchor, then hang the hook on the nearby steel plate net, apply pressure and start tensioning the jack for tensioning; (10) During tensioning, after the jack clamps the anchor cable, the person holding the jack and the people below shall be promptly withdrawn to 2 meters away. After the anchor cable is pulled to the specified pre-tightening force and the pressure is maintained, two people shall hold the jack firmly to release the pressure. After loosening, remove the hook and jack; (11) The person holding the jack can only stand on the side where the anchor cable needs to be tensioned and must not stand directly below; (12) When holding the jack, you can only hold the handle or the side of the tail of the jack. It is strictly forbidden to put your hands between the front end of the jack and the joint of the anchor; (13) During the process of tensioning the anchor cable, if the height is not enough, the person holding or supporting the jack must stand on the tunnel boring machine to operate.