Power distribution network reconstruction method based on double-bus parallel supply system
By introducing a double-bus parallel power supply system and the improved Distflow power flow model into the distribution network, the topology of the distribution network is optimized, the problems of voltage quality and network loss under the access of a high proportion of clean energy are solved, and voltage stability and loss reduction are achieved. effect.
Patent Information
- Application Number
- CN202410818962.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-10-22
AI Technical Summary
The traditional distribution network reconstruction and optimization strategy is difficult to adapt to the development of distribution network with high proportion of clean energy access, and does not consider the impact of source-side fluctuations of the distribution network, making voltage quality and network losses difficult to control.
A distribution network reconstruction method based on dual-bus parallel supply system is adopted. By establishing a time series model that comprehensively considers network losses, wind and light abandonment and switching penalty costs, the improved Distflow power flow model and the second-order cone with phase angle relaxation are used. The convex optimization method is converted into a solvable mixed integer second-order cone programming model to optimize the distribution network topology to reduce voltage fluctuations and network losses.
Under the conditions of high proportion of clean energy access, the dual-bus parallel power supply system can effectively improve voltage quality, reduce line losses, improve distribution network operation economy, and maintain voltage stability in the event of grid-side voltage drops, reducing operating costs.
Smart Images

Figure CN118825985A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of improving distribution network voltage and flexible regulation, and specifically relates to a method analysis of a distribution network reconstruction strategy based on a double busbar parallel supply system under high proportion of clean energy access. Background Art
[0002] As an important part of the power system, the distribution system is facing unprecedented challenges. As one of the main means of optimizing the operation of the distribution network, the distribution network reconstruction changes the topology of the distribution network by switching on and off the section switches and tie switches to reduce network losses, improve voltage quality, and increase power supply reliability. The penetration rate of clean energy in the distribution network has increased sharply, making it increasingly difficult for the optimization strategy of traditional distribution network reconstruction to adapt to the future development of the distribution network.
[0003] The current research on distribution network reconstruction has not considered the impact of fluctuations on the source side of the distribution network. Summary of the invention
[0004] In order to solve the above problems, the present invention provides a distribution network reconstruction method based on a dual busbar parallel supply system under the background of a high proportion of clean energy access to the distribution network. First, a time series model that comprehensively considers network loss costs, wind and solar power abandonment costs, and the minimum switch penalty costs is established; then, in order to improve the solution efficiency, based on the improved Distflow power flow model, a second-order cone convex optimization method with dephasing relaxation is adopted to successfully convert the non-convex mixed integer nonlinear optimization problem into an effectively solvable mixed integer second-order cone programming model; finally, an improved IEEE33-node distribution network is used for example simulation to verify the effectiveness and rationality of the model proposed in the present invention. The specific contents are as follows:
[0005] A distribution network reconstruction method based on a double busbar parallel supply system comprises the following steps:
[0006] Step 1: By analyzing the topological structure and operation principle of the hybrid distribution transformer, a double-bus parallel supply system is obtained, and the output port characteristics of its flexible bus and traditional bus are given;
[0007] Step 2: Based on the output port characteristics, with the goal of minimizing the comprehensive cost of network loss cost, wind and solar power abandonment cost, and section switch operation cost, a distribution network reconstruction model based on the double busbar parallel supply system is established, and its constraints are given;
[0008] Step 3: Based on the improved Distflow power flow model, the given distribution network reconstruction model is linearly transformed using the second-order cone convex optimization method with dephase angle relaxation to obtain the final distribution network reconstruction model based on the double busbar parallel supply system;
[0009] Step 4: Based on the dual-bus parallel supply system, the distribution network reconstruction method is verified by MATLAB simulation in different scenarios. The influence of the dual-bus parallel supply system on the distribution network reconstruction is explored when the grid-side voltage is constant, the grid-side voltage drops by 5%, and the grid-side voltage drops by 10%. It can not only reduce voltage fluctuations and improve power quality, but also reduce network losses and improve the economic efficiency of grid operation.
[0010] As a further improvement of the present invention, the main topology of the double busbar parallel supply system is composed of a traditional transformer (TR) and a PET module. A , W B , W C is the primary winding of TR, and the corresponding input voltages are V A 、V B 、V C ; Winding W b2 , W c2 is the secondary auxiliary winding of TR, and the corresponding auxiliary winding voltages are V b2 、V c2 ; Winding W a1 The secondary side main winding of TR corresponds to the double busbar and the traditional busbar output voltage V a From the above relationship, it can be seen that the output voltage of phase A is supported by the auxiliary windings of the B and C phase PET modules, and the output voltage of the PET module forms a series mode with the secondary main winding of TR, together forming the A phase flexible bus output port, and the port voltage is V aF . Based on the above principle analysis, the voltages of the B and C phase flexible bus terminals are V bF 、V cF As a further improvement of the present invention, the objective function of the distribution network reconstruction model is based on the minimum comprehensive cost of network loss cost, wind and solar power abandonment cost and segmented switch operation cost, and the constraints include node voltage constraint, branch current constraint, DG power constraint, network structure topology constraint, energy storage charging and discharging power constraint, energy storage capacity constraint and node power balance constraint. For the node voltage constraint, based on the voltage flexible regulation capability of the double busbar parallel supply system in the flexible busbar connection mode, the constraint range is improved, thereby improving the voltage regulation capability.
[0011] As a further improvement of the present invention, considering that some constraints in the objective function and the node power balance constraint are nonlinear models, an improved Distflow power flow model is introduced, and a second-order cone convex optimization method with dephasing angle relaxation is used for linear transformation.
[0012] As a further improvement of the present invention, due to the access of a high proportion of clean energy, the clean energy penetration rates are set to 40%, 60% and 80% respectively, and the impact of the double busbar parallel supply system on the distribution network is explored when the grid-side voltage is constant, the grid-side voltage drops by 5%, and the grid-side voltage drops by 10%.
[0013] As a further improvement of the present invention, when the grid-side voltage is in a constant state, the clean energy penetration rate is set to 40%, 60%, and 80%, and the total cost, network loss cost, switching loss, and number of switching times of the distribution network reconstruction under the flexible busbar and traditional busbar connection modes are compared.
[0014] As a further improvement of the present invention, when the grid-side voltage drops by 5%, the clean energy penetration rate is set to 40%, 60%, and 80%, and the total cost, network loss cost, switching loss, and number of switches of the distribution network reconstruction under the flexible bus and traditional bus connection modes are compared. When the clean energy is 40%, the losses of each branch of the traditional bus and the flexible bus are compared.
[0015] As a further improvement of the present invention, when the grid-side voltage drops by 10%, the total cost of distribution network reconstruction, network loss cost, switch loss and number of switches under the two connection modes are compared.
[0016] The beneficial effect of the present invention is that the present invention proposes a distribution network reconstruction method based on a double busbar parallel supply system, which linearizes the reconstruction model by considering the voltage constraint of the double busbar parallel supply system and based on the improved Distflow power flow model. In the scenario of voltage drop of 5% and 10%, the distribution network reconstruction method of the present invention considering the double busbar parallel supply system can better improve the voltage quality, maintain the normal operation of the voltage, reduce the line loss, and improve the economic efficiency of the distribution network operation compared with the distribution network reconstruction under the traditional busbar connection. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a double busbar parallel supply system diagram in the urban medium voltage distribution network of the present invention;
[0018] Figure 2 It is an equivalent circuit diagram of a distribution network including a double busbar parallel supply system of the present invention;
[0019] Figure 3 It is an improved IEEE33 node distribution network diagram containing DG and energy storage of the present invention;
[0020] Figure 4 It is the 24h power distribution diagram of DG and load of the present invention;
[0021] Figure 5 It is a node voltage curve diagram of the distribution network reconstruction based on the double busbar parallel supply system of the present invention at 08:00;
[0022] Figure 6 It is a node voltage curve diagram of the distribution network reconstruction based on the double busbar parallel supply system of the present invention at 14:00;
[0023] Figure 7 is a voltage error curve diagram under different wiring modes of the present invention;
[0024] Figure 8 It is a voltage fluctuation envelope curve diagram under different wiring modes of the present invention;
[0025] Fig. 9 It is the voltage curve diagram of the 18-node distribution network of the present invention;
[0026] Fig.10 It is a comparison diagram of node voltages under two wiring modes of the present invention;
[0027] Fig.11 It is the line active network loss diagram under two wiring modes of the present invention;
[0028] Fig.12 It is a comparison diagram of node voltages under two wiring modes at 14:00 of the present invention. DETAILED DESCRIPTION
[0029] The method of the present invention is described in detail below with reference to the accompanying drawings and specific implementation methods.
[0030] Depend on Figure 1 It can be seen that the main topology of the double busbar parallel supply system is composed of a traditional transformer (TR) and a PET module. A , W B , W C is the primary winding of TR, and the corresponding input voltages are V A 、V B 、V C ; W b2 , W c2 is the secondary auxiliary winding of TR, and the corresponding auxiliary winding voltages are V b2 、V c2 ; W a1 The secondary side main winding of TR corresponds to the double busbar and the traditional busbar output voltage V a From the above relationship, it can be seen that the output voltage of phase A is supported by the auxiliary windings of the B and C phase PET modules, and the output voltage of the PET module forms a series mode with the secondary side main winding of TR, together forming the output port of phase A flexible busbar, and the port voltage is V aF . According to the above principle analysis, the output voltage of phase B is supported by the auxiliary windings of the A and C phase PET modules, and the output voltage of the PET module forms a series mode with the secondary side main winding of TR, together forming the B phase flexible bus output port, and the port voltage is V bFThe output voltage of phase C is supported by the auxiliary windings of the A and B phase PET modules, and the output voltage of the PET module forms a series mode with the secondary main winding of TR, together forming the C phase flexible bus output port, and the port voltage is V cF .
[0031] In order to improve the operational reliability of the double-bus parallel supply system, a bypass switch is installed between the power electronic module and the traditional bus output port. When the bypass switch is disconnected, the double-bus parallel supply system operates in the form of flexible bus connection. When the switch is closed, the double-bus parallel supply system operates in the traditional bus mode, which is similar to the traditional substation bus.
[0032] Based on the above topological structure, the operating principle of the double busbar parallel supply system is analyzed. First, each phase in the three-phase system contains a PET module, and the relationship between its input voltage and output voltage is shown in formula (1).
[0033]
[0034] Where: V in Represents the input voltage of the PET module; V out It is represented by the output voltage of the PET module; D X,n Expressed as the duty cycle of the PET module.
[0035] Depend on Figure 1 The voltage on the output side of the flexible bus is:
[0036]
[0037] Where: ΔV a , ΔV b , ΔV c Respectively represented as A, B, C three-phase PET module output side voltage; V a 、V b 、V c Respectively represent the traditional bus output voltage; V aF 、V bF 、V cF They are respectively represented as the flexible bus output voltage.
[0038] The voltage at the output side of the converter can be calculated by formula (3):
[0039]
[0040] Where: (D A1 , D A2 )、(D B1 , D B2 )、(D C1 , D C2) represent the duty cycle of the three-phase PET modules A, B, and C, respectively, and their value range is (-1,1); V a2 、V b2 、V c2 They are respectively represented as the input side voltage of the auxiliary winding on the secondary side of the transformer.
[0041]
[0042]
[0043] Where: n T1 It is expressed as the ratio of the number of turns of the primary winding to the secondary winding of the transformer; n T2 It is expressed as the turns ratio of the transformer primary main winding to the secondary auxiliary winding.
[0044] Thus, the theoretical transformation ratio of the flexible busbar can be obtained as
[0045]
[0046] Where: V X represents the output voltage of a conventional busbar of a certain phase, where X∈(A, B, C); V xF represents the output voltage of a phase flexible bus, where x∈(a, b, c); D X1 , D X2 Indicates the duty cycle of a certain phase PET module; n s Indicates the theoretical transformation ratio of the flexible busbar; n T1 It is expressed as the ratio of the number of turns of the primary winding to the secondary winding of the transformer; n T2 It is expressed as the turns ratio of the transformer primary main winding to the secondary auxiliary winding;
[0047] When the duty cycle D X,n = 0 or bypass switch S p-a When the PET module is shut down, n s =n T1 , at this time, the double busbar parallel supply system operates in TR mode, that is, the traditional busbar operation mode; when D x,n When ≠0, the double busbar parallel supply system operates in the flexible busbar connection mode.
[0048] In order to better analyze the reconstruction of the distribution network of the double bus parallel supply system, the distribution network containing the double bus parallel supply system DBPS is modeled and analyzed to obtain the equivalent circuit diagram of the distribution network, including power supply point 1 and power supply point 2. The double bus parallel supply system and nodes k1, k2...k n ,like Figure 2 As shown. S1 、v S2is the voltage of the power supply point in the distribution network; Δu is the voltage flexible control range in the flexible busbar connection mode; S point1 , S point2 are the powers of power source point 1 and power source point 2 respectively; k1, k2, k n They are the nodes of the distribution network respectively; S1, S2, S i are the powers flowing between adjacent nodes; S 1L , S 2L , S nL are the loads required for each node; n Tx is the turns ratio of the traditional power frequency transformer in the dual busbar parallel supply system; Z Tx is the equivalent impedance of the x-phase traditional power frequency transformer in the double busbar parallel supply system; Z PET-x is the equivalent impedance of module PET-x; Z DBPS is the equivalent impedance of the double busbar parallel supply system; u PET-x is the output voltage of the PET-x module.
[0049] Before the flexible transformation of the distribution network, that is, without adding the double busbar and supply system DBPS, the power provided by power points 1 and 2 to the load, that is, the power distribution before the transformation is:
[0050] Z DBPS =Z Tx +Z PET-x (7)
[0051]
[0052]
[0053] Among them, Z1, Z2, Z L is the impedance of each line segment; Z ∑ * is the conjugate of the total impedance of the power line; v N is the rated voltage of the network. From the above formula, we can see that the power of the power source point in the distribution network consists of two parts, namely, the power source point voltage difference and the circulating power part. Therefore, it can be seen that the flexible regulation of the network flow can be achieved by regulating the voltage of the power source point in the distribution network through the double busbar parallel supply system.
[0054] After adding double busbars to the distribution network and supplying the system DBPS, the power provided by power points 1 and 2 to the load, that is, the power distribution after transformation, is:
[0055]
[0056]
[0057] It can be seen from the above formula that the voltage regulation capability based on the double-busbar parallel supply system can achieve the purpose of changing the power flow distribution in the distribution network, which provides a theoretical basis for the distribution network reconstruction of the double-busbar parallel supply system.
[0058] With the goal of minimizing the operating cost of the distribution network and taking into account the consumption of clean energy, the present invention proposes a distribution network reconstruction model considering the dual-bus parallel supply system under the background of high-proportion clean energy access. The objective function of this model is to minimize the comprehensive operating cost of the distribution network, taking into account the network loss cost, wind and solar power abandonment, and segmented switch operation cost. The calculation method of the objective function is shown in formula (12).
[0059] minf=k1f loss +k2f DGabd +k3f switch (12)
[0060] Where: k1, k2, k3 are the network loss cost coefficient, wind and solar abandonment cost coefficient, and section switch operation cost coefficient respectively. loss 、f DGabd 、f switch They are network loss, amount of wind and solar power curtailment, and number of section switches.
[0061] The specific calculation method of network loss, wind and solar power curtailment and the number of section switch operations in formula (12) is as follows.
[0062]
[0063] Where: I ij,t is the effective value of the current flowing through branch ij at time t; R ij is the resistance of branch ij; △t is the difference between two adjacent moments, which takes a value of 1; i and j represent two adjacent nodes, i is the parent node, j is the child node, and t represents the value at a certain moment within 24 hours.
[0064]
[0065] Where: T is the duration of distribution network reconstruction; Ψwind and Ψpv represent the node sets of wind power and photovoltaic units connected to the distribution network respectively; They are respectively represented as the output power of wind power and photovoltaic units at node i at time t; They represent the actual power injected into node i by wind power and photovoltaic generators at time t respectively.
[0066]
[0067] Where: Ω is the set of distribution network branches; α ij,0 , α ijThey represent the switch status of branch ij before and after the reconstruction of the distribution network, 1 indicates that the switch of branch ij is closed, and 0 indicates that the switch of branch ij is open.
[0068] (1) Node voltage constraints
[0069]
[0070] Where: They represent the upper and lower limits of the voltage amplitude at node i, U i,t It is represented by the voltage amplitude of node i at time t, U 1,t It is expressed as the voltage amplitude of node 1 at time t, and Δu represents the voltage flexible control range of the double busbar parallel supply system under the flexible busbar connection mode.
[0071] (2) Branch current constraints
[0072]
[0073] Where: I ij,t represents the current flowing through branch ij at time t, It indicates the maximum value of the current allowed to flow through branch ij.
[0074] (3) DG power constraints
[0075]
[0076] Where: P DG,i,t and Q DG,i,t are the active output and reactive output of DG at node i at time t respectively; and are the lower limits of active and reactive output of DG at node i at time t, respectively; and are the upper limits of active and reactive output of DG at node i in the tth period, respectively.
[0077] (4) Network structure topology constraints
[0078]
[0079] Where: f s,i It is represented by the virtual power emitted by node i; f l,i It is represented as the virtual load of node i, which is generally 1; f ij,t It is expressed as the virtual power flowing through branch ij at time t.
[0080] (5) Energy storage charging and discharging power constraints
[0081]
[0082] Where: They represent the energy storage charging and discharging status at node i in the tth period respectively; They represent the energy storage charging and discharging power at node i in the tth period respectively; They represent the maximum value of energy storage charging and discharging power respectively.
[0083] (6) Energy storage capacity constraints
[0084]
[0085]
[0086] Where: is the ESS power connected to node i at time t; η is the self-discharge rate of ESS; η ch , η dis They represent the energy storage charging and discharging efficiency respectively; They represent the maximum and minimum capacity limits of energy storage at node i respectively.
[0087] (7) Node power balance constraints
[0088]
[0089]
[0090] Where: P i It is represented by the active power flowing into node i from the branch connected to node i; P i,DG , Q i,DG They represent the active and reactive power injected into node i by distributed generation respectively; P i,L , Q i,L They are respectively represented as the active and reactive power of the load at node i; U i , U j Represented as the voltage of node i and j respectively; G ij , B ij They represent the conductance and susceptance of branch ij respectively; n represents the total number of branches connected to node i; δ ij It is expressed as the phase angle difference between nodes i and j.
[0091] Some of the constraints in the above objective function and node power balance constraint are nonlinear models with strong non-convexity and are difficult to solve. Based on the Distflow power flow constraint, the present invention adopts the second-order cone convex optimization method with dephase angle relaxation for linear transformation. Since the network topology changes continuously during the distribution network reconstruction, the branch switch state α is introduced. ijBy improving the Distflow power flow model, the following power flow equation applicable to distribution network reconstruction is obtained:
[0092]
[0093]
[0094]
[0095]
[0096] Where: P ij,t , Q ij,t They are respectively represented as the active and reactive power flowing through branch ij at time t; P j,t , Q j,t They represent the active and reactive power injected into node j at time t respectively; P ik,t , Q ik,t They are respectively represented as the active and reactive power flowing through branch jk at time t; r ij 、x ij They are respectively represented as the resistance and conductance of branch ij; α jk Indicates the switch status of branch jk; γ(j) represents the set of parent nodes and child nodes of node j;
[0097] U i,t It is represented by the voltage amplitude of node i at time t; U j,t represents the voltage amplitude of node j at time t; I ij,t is the effective value of the current flowing through branch ij at time t; Ω is the set of distribution network branches; α ij It represents the switch state of branch ij after the distribution network is reconfigured.
[0098] Equations (30)-(33) are improved Distflow power flow models, which are still non-convex and difficult to guarantee convergence. Therefore, they are transformed into convex second-order cone constraints. Eliminating the square terms of equations (30), (31), (32), and (33), we obtain:
[0099]
[0100]
[0101]
[0102] When branch ij is in the disconnected state, equations (18) and (19) will no longer apply. Therefore, the large M method is used to relax the constraint so that it is applicable to all distribution network branches, and the following is obtained:
[0103] m ij =(1-α ij )M (37)
[0104]
[0105]
[0106] Taking the IEEE-33 node distribution system as an example, the distribution network example of the present invention is modified. The network structure of the example is as follows: Figure 3 As shown, grid and line parameters are shown in references. Five DG units are set in the 33-node distribution network, and the parameters are shown in Table 1; one energy storage is added at each node number 7 and 25, and the upper and lower limits of energy storage charging and discharging power are set to 0.2MW, the upper and lower limits of energy storage capacity are set to 0.8MWh and 0.15MWh respectively, the charging and discharging efficiency are 0.9 and 0.85 respectively, and the initial state of charge is set to 0.3MWh; a capacitor bank is added at node number 33, the reactive compensation capacity of a single capacitor is 0.15Mvar, and the maximum number of switchable capacitors is 5; Figure 3 In the figure, the dotted line is the tie switch, the solid line is the branch, WT1, WT2, WT3 represent wind turbine No. 1, wind turbine No. 2, and wind turbine No. 3 respectively; PV1 and PV2 represent photovoltaic unit No. 1 and photovoltaic unit No. 2 respectively; ES1 and ES2 represent energy storage device No. 1 and energy storage device No. 2 respectively; CB and FB represent the abbreviations of traditional busbar and flexible busbar respectively; DBPS is a double busbar parallel supply system; PET is a power electronic module. Assume that all DG units and loads of the same type obey Figure 4 The power curve is shown.
[0107] Table 1DG installation nodes and type parameters
[0108]
[0109] In order to explore the impact of the dual-bus parallel supply system on the distribution network when the grid-side voltage is constant, a comparative analysis is conducted on the following two operating modes: distribution network reconstruction under traditional bus connection and distribution network reconstruction under flexible bus connection. The distribution network is reconstructed and optimized when the clean energy penetration rate is 40%, 60%, and 80%, respectively. The solution results are shown in Tables 2 and 3.
[0110] Table 2 Model solution results under traditional busbar
[0111]
[0112] Table 3 Model solution results under flexible busbar
[0113]
[0114] It can be seen from Tables 2 and 3 that when the clean energy penetration rate is 60%, the network loss costs in both wiring modes are minimal. This shows that when the clean energy penetration rate increases from 40% to 60%, the clean energy connected to the system is fully absorbed, which reduces the network loss costs within a day. However, when the clean energy penetration rate increases from 60% to 80%, the network loss costs increase significantly. This is because as the proportion of clean energy access increases, the power on the transmission line increases, resulting in an increase in system network losses.
[0115] Comparing the cost parameters under different connection modes in Table 2 and Table 3, when the clean energy penetration rate is 40%, the network loss cost of the flexible bus is 43.7 yuan less than that of the traditional bus; when the clean energy penetration rate is 60%, the network loss cost of the flexible bus is 14.8 yuan less than that of the traditional bus; when the clean energy penetration rate is 80%, the network loss cost of the flexible bus is 12.7 yuan less than that of the traditional bus. The network loss cost of the distribution network reconstruction under the flexible bus connection is lower at different clean energy penetration rates, which shows that the flexible bus system has a higher energy transmission efficiency in absorbing a high proportion of clean energy. Comparing the number of switches in the distribution network reconstruction under different clean energy penetration rates under the two connection modes, the switch operation frequency under the flexible bus connection is generally higher than that of the traditional bus, which shows that the flexible bus connection mode improves the regulation ability of the distribution network.
[0116] In order to verify that when the grid-side voltage is constant, the voltage of each node of the distribution network is in a stable state under the traditional busbar and flexible busbar connection modes, the load underestimation time (08:00) and load peak time (14:00) are selected as examples to explore the impact of the double busbar parallel supply system on the voltage quality during the load peak and load underestimation period. The simulation results are as follows Figure 5 and Figure 6 .
[0117] Figure 5 The node voltage curve of the distribution network reconstructed based on the double busbar parallel supply system at 08:00 is: Figure 6 The node voltage curve of the distribution network reconstructed based on the double busbar parallel supply system at 14:00. Considering that the voltage quality standard of my country's urban medium-voltage distribution network is ±7%, Figure 5 and Figure 6 It can be seen that under the two connection modes, the voltage of each node of the distribution network is in a stable state at both the load valley moment and the load peak moment.
[0118] In order to verify the flexible control capability of the flexible busbar on voltage, two indicators are defined: daily voltage (the mean value of voltage indicator within 24 hours) and voltage fluctuation (the standard deviation of voltage indicator within 24 hours). Figure 7 and Figure 8They are respectively the voltage error curve under different connection modes within 24 hours when the clean energy penetration rate is 40% and the voltage fluctuation range under different connection modes. Figure 7 and Figure 8 It can be seen that although the voltage fluctuations in both wiring modes are within the allowable range, the voltage fluctuations at nodes 11 to 18 in the flexible busbar wiring mode are significantly smaller than those in the traditional busbar wiring mode.
[0119] The above results show that the reconstruction of the distribution network of the double-bus parallel supply system based on a high proportion of clean energy access can reduce network losses, improve node voltage quality, and suppress voltage fluctuations throughout the day.
[0120] In order to explore the operation of the double busbar parallel supply system distribution network reconstruction when the grid-side voltage drops within the allowable range of the urban distribution network voltage quality, the clean energy penetration rate is set to 40% and the grid-side voltage drops to 5%. The simulation results are as follows: Figures 9 to 11 shown.
[0121] Fig. 9 This is the 24h voltage curve of 18 nodes. Fig. 9 It can be seen that when the grid voltage drops by 5%, under the traditional busbar connection mode, the voltage of 18 nodes during the heavy load period (12:00-23:00) drops by more than 7%, especially at 20:00, the voltage drops to 10%, and it is difficult to guarantee the voltage quality. However, under the flexible busbar connection mode, the node voltage remains stable within 24 hours, and the voltage fluctuation range is 3%. In summary, when the grid voltage drops by less than 5%, the traditional busbar connection mode can meet the network voltage quality requirements during the load valley period, but during the peak load period, the voltage quality is difficult to guarantee. The flexible busbar connection mode is not affected and can still guarantee normal operation, that is, the dual busbar parallel supply system has a good voltage flexibility regulation capability when the grid voltage drops in a small range.
[0122] Fig.10 The voltage box line diagram of 18 nodes in two 24h wiring modes. It can be seen from the figure that the minimum node voltage in the flexible busbar wiring mode is 0.989, and the voltage fluctuation range is 3%. The maximum node voltage in the traditional busbar wiring mode is 0.952, and the voltage fluctuation range is 5%. This is because the voltage regulation capability of the flexible busbar can reduce voltage fluctuations and improve the network voltage quality.
[0123] Fig.11This is a comparison of the losses of each branch of the traditional busbar and the flexible busbar when the clean energy penetration rate is 40% and the grid-side voltage drops by 5%. It can be seen from the figure that the active power loss in each period after reconstruction is significantly reduced in the flexible busbar connection mode compared with the traditional busbar, especially in the period from 12:00 to 22:00 (peak load period). The flexible busbar connection mode reduces the line loss in the distribution network by improving the voltage quality of each node.
[0124] Table 4 Model solution results of traditional busbar with 5% grid-side voltage drop
[0125]
[0126] When the grid voltage drops by 5%, the calculation results of each fee in the flexible bus mode are the same as those in Table 3. It can be seen from Tables 3 and 4 that when the clean energy penetration rate increases from 40% to 80%, the system network loss costs in the flexible bus connection mode are reduced by 102.1, 57.1, and 49.1 yuan respectively compared with the traditional bus connection mode, and the total costs are reduced by 72.1, 57.1, and 49.1 yuan respectively. This shows that when the grid voltage drops within 5%, the flexible bus can reduce the network loss during the network reconstruction process and reduce the system operation cost at different clean energy penetration rates.
[0127] The above results show that when the grid-side voltage drop depth is 5%, the voltage of each node can still ensure the voltage quality at low load moments after the distribution network is reconstructed under the traditional busbar connection mode, but the voltage quality is difficult to ensure at peak load moments. However, under the flexible busbar connection mode, it is not affected, and the voltage of each node can still operate within the normal range, and the network loss cost during reconstruction can be reduced.
[0128] In order to explore the operation of the double busbar parallel supply system distribution network reconstruction when the grid-side voltage drops beyond the allowable range of the urban distribution network voltage quality, the clean energy penetration rate is set to 40% and the grid-side voltage drops to 10%. The simulation results are as follows: Fig.12 shown.
[0129] Fig.12 The following is a comparison of the probability density of node voltages under the two wiring modes at 14:00. It can be seen from the figure that the mean values of node voltages under the flexible busbar wiring and traditional busbar wiring modes are 1.0037 and 0.8815, respectively, and the standard deviations are 0.0066 and 0.0076. The overall fluctuation of node voltage under the flexible busbar is small and within the allowable voltage range; due to a 10% drop in grid-side voltage and peak load, the voltage of each node under the traditional busbar cannot meet its own voltage regulation needs through distribution network reconstruction and on-site compensation of capacitor banks, and the voltage quality is seriously reduced.
[0130] Table 5 Model solution results of traditional busbar with 10% grid-side voltage drop
[0131]
[0132] It can be seen from Tables 3 and 5 that when the clean energy penetration rate increases from 40% to 80%, the daily network loss costs in the flexible busbar connection mode are reduced by 140.7, 107.1, and 92.1 yuan respectively compared with the traditional busbar connection mode, and the total costs are reduced by 140.7, 107.1, and 92.1 yuan respectively. This shows that when the grid-side voltage drops within 10%, the flexible busbar can reduce the network loss in the network reconstruction process and reduce the system operation cost under different clean energy penetration rates.
[0133] The above results show that: in the traditional busbar connection mode, when the grid-side voltage drop range increases, the total system operating cost continues to increase; while compared with the traditional busbar, when the grid-side voltage increases from 5% to 10%, the total operating cost saved by the system is also increasing. This is because the flexible busbar compensates the voltage of each node, improves the voltage quality, and reduces the network loss cost.
Claims
1. A distribution network reconstruction method based on a double busbar parallel supply system, characterized in that: The following steps are involved: Step 1: By analyzing the topological structure and operation principle of the hybrid distribution transformer, a double-bus parallel supply system is obtained, and the output port characteristics of its flexible bus and traditional bus are given; Step 2: Based on the output port characteristics, with the goal of minimizing the comprehensive cost of network loss cost, wind and solar power abandonment cost, and section switch operation cost, a distribution network reconstruction model based on the double busbar parallel supply system is established, and its constraints are given; Step 3: Based on the improved Distflow power flow model, the given distribution network reconstruction model is linearly transformed using the second-order cone convex optimization method with dephase angle relaxation to obtain the final distribution network reconstruction model based on the double busbar parallel supply system; Step 4: Perform MATLAB simulation on the distribution network reconstruction method based on the double-bus parallel supply system in different scenarios; explore the impact of the double-bus parallel supply system on the distribution network reconstruction under flexible bus and traditional bus connection modes when the grid-side voltage is constant, the grid-side voltage drops by 5%, and the grid-side voltage drops by 10%. This can not only reduce voltage fluctuations and improve power quality, but also reduce network losses and improve the economic efficiency of grid operation.
2. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 1, characterized in that: The topology of the double busbar parallel supply system is composed of a traditional transformer TR and a PET module; the winding W A , W B , W C is the primary winding of TR, and the corresponding input voltages are V A 、V B 、V C ; Winding W b2 , W c2 is the secondary auxiliary winding of TR, and the corresponding auxiliary winding voltages are V b2 、V c2 ; Winding W a1 The secondary side main winding of TR corresponds to the double busbar and the traditional busbar output voltage V a The output voltage of phase A is supported by the auxiliary windings of the B and C phase PET modules, and the output voltage of the PET module forms a series mode with the secondary side main winding of TR, together forming the output port of phase A flexible busbar, and the port voltage is V aF Similarly, the voltages of the flexible bus terminals of phases B and C are V bF 、V cF .
3. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 2, characterized in that: In the PET module, the relationship between the input voltage and the output voltage is shown in the following formula: Where: V in Represents the input voltage of the PET module; V out It is represented by the output voltage of the PET module; D X,n It is expressed as the duty cycle of the PET module; Flexible bus output voltage: Where: ΔV a , ΔV b , ΔV c Respectively represent the output side voltage of the A, B, and C phase PET modules; V a 、V b 、V c Respectively represent the traditional bus output voltage; V aF 、V bF 、V cF They are respectively represented as the flexible bus output voltage; Converter output voltage: Where: (D A1 , D A2 )、(D B1 , D B2 )、(D C1 , D C2 ) represent the duty cycle of the A, B, and C phase PET modules, respectively, and their value range is (-1,1); V a2 、V b2 、V c2 They are respectively represented as the input side voltage of the auxiliary winding on the secondary side of the transformer; Where: n T1 It is expressed as the ratio of the number of turns of the primary winding to the secondary winding of the transformer; n T2 It is expressed as the turns ratio of the transformer primary main winding to the secondary auxiliary winding; The theoretical transformation ratio of the flexible busbar is obtained as follows: Where: V X represents the output voltage of a conventional busbar of a certain phase, where X∈(A, B, C); V xF represents the output voltage of a phase flexible bus, where x∈(a, b, c); D X1 , D X2 Indicates the duty cycle of a certain phase PET module; n s Indicates the theoretical transformation ratio of the flexible busbar; n T1 It is expressed as the ratio of the number of turns of the primary winding to the secondary winding of the transformer; n T2 It is expressed as the turns ratio of the transformer primary main winding to the secondary auxiliary winding; When the duty cycle D X,n = 0 or bypass switch S p-a When the PET module is shut down, n s =n T1 , at this time, the double busbar parallel supply system operates in TR mode, that is, the traditional busbar operation mode; when D x,n When ≠0, the double busbar parallel supply system operates in the flexible busbar connection mode; The distribution network including the double busbar parallel supply system is modeled and analyzed to obtain an equivalent circuit diagram of the distribution network, including power supply point 1 and power supply point 2, between which the double busbar parallel supply system and nodes k1, k2, ..., k n ; Among them, v S1 、v S2 is the voltage of the power supply point in the distribution network; Δu is the voltage flexible control range in the flexible busbar connection mode; S point1 , S point2 are the powers of power source point 1 and power source point 2 respectively; k1, k2, k n They are the nodes of the distribution network respectively; S1, S2, S i are the powers flowing between adjacent nodes; S 1L , S 2L , S nL are the loads required for each node; n Tx is the turns ratio of the traditional power frequency transformer in the dual busbar parallel supply system; Z Tx is the equivalent impedance of the x-phase traditional power frequency transformer in the double busbar parallel supply system; Z PET-x is the equivalent impedance of module PET-x; Z DBPS is the equivalent impedance of the double busbar parallel supply system; u PET-x is the output voltage of the PET-x module; Before the flexible transformation of the distribution network, that is, without adding the double busbar parallel supply system, the power provided by power points 1 and 2 to the load, that is, the power distribution before the transformation is: WITH DBPS =Z Tx +Z PET-x Among them, Z1, Z2, Z L is the impedance of each line segment; Z ∑ * is the conjugate of the total impedance of the power line; v N is the rated voltage of the network; from the above formula, we know that the power of the power source point in the distribution network consists of two parts, namely, the voltage difference of the power source point and the circulating power part; therefore, the voltage of the power source point in the distribution network can be flexibly regulated by the double busbar parallel supply system; After adding the double busbar system to the distribution network, the power provided by power source point 1 and power source point 2 to the load, that is, the power distribution after transformation is: It can be seen from the above formula that the voltage regulation capability based on the double-busbar parallel supply system can achieve the purpose of changing the power flow distribution in the distribution network, which provides a theoretical basis for the distribution network reconstruction of the double-busbar parallel supply system.
4. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 1, characterized in that: The objective function of the distribution network reconstruction model is to minimize the comprehensive cost of network loss cost, wind and solar power abandonment cost, and section switch operation cost. The constraints include node voltage constraint, branch current constraint, DG power constraint, network structure topology constraint, energy storage charging and discharging power constraint, energy storage capacity constraint, and node power balance constraint. For the node voltage constraint, based on the voltage flexible regulation capability of the double busbar parallel supply system in the flexible busbar connection mode, the constraint range is improved, thereby improving the voltage regulation capability.
5. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 4, characterized in that: The objective function is calculated as follows: minf=k1f loss +k2f DGabd +k3f switch Where: k1, k2, k3 are the network loss cost coefficient, wind and solar abandonment cost coefficient, and section switch operation cost coefficient respectively; f loss 、f DGabd 、f switch They are network loss, amount of wind and solar power curtailment, and number of section switches; The specific calculation method of network loss, wind and solar curtailment and the number of section switch operations in the above formula is as follows; Where: I ij,t is the effective value of the current flowing through branch ij at time t; R ij is the resistance of branch ij, △t is the difference between two adjacent moments, and its value is 1; i and j represent two adjacent nodes, i is the parent node, j is the child node, and t represents the value at a certain moment within 24 hours; Where: T is the duration of distribution network reconstruction; Ψwind and Ψpv represent the node sets of wind power and photovoltaic units connected to the distribution network respectively; They are respectively represented as the output power of wind power and photovoltaic units at node i at time t; They represent the actual power injected into node i by wind power and photovoltaic units at time t respectively; Where: Ω is the set of distribution network branches; α ij,0 , α ij They represent the switch status of branch ij before and after the reconstruction of the distribution network, 1 indicates that the switch of branch ij is closed, and 0 indicates that the switch of branch ij is open.
6. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 4, characterized in that: The node voltage constraint, branch current constraint, DG power constraint, network structure topology constraint, energy storage charging and discharging power constraint, energy storage capacity constraint and node power balance constraint are respectively: Node Voltage Constraints U 1,t =U 1,t +Δu Where: They represent the upper and lower limits of the voltage amplitude at node i, U i,t It is represented by the voltage amplitude of node i at time t, U 1,t It is represented by the voltage amplitude of node 1 at time t, and Δu represents the voltage flexible control range of the double busbar parallel supply system in the flexible busbar connection mode; Branch current constraint Where: I ij,t represents the current flowing through branch ij at time t, Indicates the maximum value of the current allowed to flow through branch ij; DG power constraints Where: P DG,i,t and Q DG,i,t are the active output and reactive output of DG at node i at time t respectively; and are the lower limits of active and reactive output of DG at node i at time t, respectively; and are the upper limits of active and reactive output of DG at node i in the tth period, respectively; Network structure topology constraints Where: f s,i It is represented by the virtual power emitted by node i; f l,i It is represented as the virtual load of node i, and its value is 1; f ij,t It is expressed as the virtual power flowing through branch ij at time t, α ij It represents the switch state of branch ij after the distribution network is reconfigured; Energy storage charging and discharging power constraints Where: They represent the energy storage charging and discharging status at node i in the tth period respectively; They represent the energy storage charging and discharging power at node i in the tth period respectively; Respectively represent the maximum value of energy storage charging and discharging power; Energy storage capacity constraints Where: is the ESS power connected to node i at time t; η is the self-discharge rate of ESS; η ch , η dis They represent the energy storage charging and discharging efficiency respectively; They represent the maximum and minimum capacity limits of energy storage at node i respectively; Node power balance constraints Where: P i It is represented by the active power flowing into node i from the branch connected to node i; P i,DG , Q i,DG They represent the active and reactive power injected into node i by distributed generation respectively; P i,L , Q i,L They are respectively represented as the active and reactive power of the load at node i; U i , U j Represented as the voltage of node i and j respectively; G ij , B ij They represent the conductance and susceptance of branch ij respectively; n represents the total number of branches connected to node i; δ ij It is expressed as the phase angle difference between nodes i and j.
7. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 1, characterized in that: The improved Distflow power flow model is introduced, and the second-order cone convex optimization method with dephasing angle relaxation is used for linear transformation. Specifically, the branch switch state α is introduced ij By improving the Distflow power flow model, the following power flow equation applicable to distribution network reconstruction is obtained: Where: P ij,t , Q ij,t They are respectively represented as the active and reactive power flowing through branch ij at time t; P j,t , Q j,t They represent the active and reactive power injected into node j at time t respectively; P ik,t , Q ik,t They are respectively represented as the active and reactive power flowing through branch jk at time t; r ij 、x ij They are respectively represented as the resistance and conductance of branch ij; α jk Indicates the switch status of branch jk; γ(j) represents the set of parent nodes and child nodes of node j; U i,t It is represented by the voltage amplitude of node i at time t; U j,t represents the voltage amplitude of node j at time t; I ij,t is the effective value of the current flowing through branch ij at time t; Ω is the set of distribution network branches; α ij It represents the switch state of branch ij after the distribution network is reconfigured; Equations (30)-(33) are improved Distflow power flow models, which are still non-convex and difficult to guarantee convergence. Therefore, they are transformed into convex second-order cone constraints. make Eliminating the square term of the power flow equation, we get: When branch ij is in the disconnected state, the node voltage constraint and branch current constraint are no longer applicable. Therefore, the large M method is used to relax the constraint so that it is applicable to all distribution network branches, and the following is obtained: m ij =(1-a ij )M 8. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 1, characterized in that: Due to the high proportion of clean energy access, the clean energy penetration rates are set to 40%, 60% and 80% respectively, and the impact of the double busbar parallel supply system on the distribution network is explored when the grid voltage is constant, the grid voltage drops by 5%, and the grid voltage drops by 10%.
9. A distribution network reconstruction method based on a double busbar parallel supply system according to claim 8, characterized in that: When the grid-side voltage is constant, the clean energy penetration rate is set to 40%, 60%, and 80%, and the total cost, network loss cost, switch loss, and number of switches of the distribution network reconstruction under the flexible busbar and traditional busbar connection modes are compared; when the grid-side voltage drops by 5%, the clean energy penetration rate is set to 40%, 60%, and 80%, and the total cost, network loss cost, switch loss, and number of switches of the distribution network reconstruction under the flexible busbar and traditional busbar connection modes are compared. When the clean energy is 40%, the losses of each branch of the traditional busbar and the flexible busbar are compared; When the grid-side voltage drops by 10%, the total cost of distribution network reconstruction, network loss cost, switching loss and switching times under the two connection modes are compared.