Pile pulling method for highway anti-collision guardrail pile
By using the pile driving device of soil isolation pipe and hydraulic vibrating hammer, the problem of difficulty in pulling out highway guardrail piles is solved, and efficient pile pulling operation is realized, which is especially suitable for the maintenance of old guardrail piles in cold zone areas.
Patent Information
- Application Number
- CN202411209496.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-10-25
AI Technical Summary
It is difficult to pull out highway guardrail piles, especially in cold areas. Due to the increase in friction and decrease in strength caused by corrosion, a pullout force several times the theoretical calculation value is often required, and the piles are prone to breakage or failure to pull out. Condition.
Use a pile driving device including a guide frame, a hydraulic vibrating hammer, a pile pulling device and a soil isolation pipe. The soil isolation pipe is sleeved on the guardrail pile and driven into the ground to break the adhesion. Then pull out the isolation pipe, and then Use the pile pulling device to gradually pull out the guardrail piles to reduce friction resistance and pulling force.
It greatly reduces the difficulty and required strength of pulling out piles, improves the efficiency of pulling out piles, is suitable for the maintenance of new and old guardrail piles, and reduces the risk of the guardrail piles being pulled off.
Smart Images

Figure CN118835604A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for pulling out highway anti-collision guardrail piles, in particular to a method for pulling out highway anti-collision guardrail piles, and belongs to the technical field of highway maintenance. Background Art
[0002] Expressways are high-grade roads, which refer to roads that can accommodate an average annual day and night passenger car traffic of more than 25,000 vehicles, are dedicated to high-speed driving of cars in separate lanes, and have full access control. Expressways usually have multiple lanes, and a central divider is set to completely separate the traffic in and out, and there are anti-collision guardrails on both sides to prevent vehicles from running off the road to protect vehicles and passengers. Semi-rigid guardrails are the main form of highway anti-collision guardrails, which are easy to carry, easy to install on site, and can produce plastic deformation to absorb the impact kinetic energy of the car during the collision. Semi-rigid guardrails are generally a continuous structure with corrugated steel guardrail panels spliced together and supported by guardrail piles. It uses the deformation of the soil foundation, columns, and beams to absorb the collision energy, and force the out-of-control vehicle to change direction and return to the normal driving direction to reduce the losses caused by the accident.
[0003] Common guardrail piles are mostly galvanized steel pipe structures with diameter specifications of 114 or 140mm. The length is generally 1.85 meters, 1.95 meters, 2 meters, 2.15 meters, and 2.27 meters depending on the requirements. The wall thickness is 4.5mm, and the depth buried in the soil should generally not be less than 40cm. In order to ensure the supporting strength and stability of the guardrail piles, the guardrail piles are generally driven directly into the ground to a set depth by a pile driver. When driving is difficult, drilling or excavation is used to install the guardrail piles. When drilling or excavation is used to install the guardrail piles, after the guardrail piles are positioned, the same material as the roadbed must be used for backfilling and compacting in layers so that they have a density not lower than that of the adjacent original soil.
[0004] The service life of guardrail piles is affected by factors such as material quality, installation quality, environmental conditions, and maintenance status. Generally, the service life of galvanized steel pipe guardrail piles is 10 to 15 years. Data show that by the end of 2023, the mileage of my country's expressways will reach 183,600 kilometers, and the standard spacing of guardrail piles on standard sections is usually 4 meters. Therefore, in addition to replacing guardrail piles damaged by traffic accidents every year, as the operating time of expressways increases, there are still a large number of guardrail piles that need to be replaced and maintained. Because the guardrail piles are deep below the surface, the original piling bonding strength is high (data show that the theoretical calculation of the new roadbed requires about 20.93 tons of pile pulling force), and the rolling vibration generated when vehicles pass through the road surface, the bonding force between the guardrail piles and the roadbed is often much greater than the bonding force when the new roadbed is piled. This makes it difficult to pull out the piles, especially for expressways in cold regions. Chemical reagents are usually used for snow removal or road cleaning. After the chemical reagents penetrate into the roadbed, the surface of the guardrail piles submerged under the roadbed is prone to blistering and rust, increased friction, and even rusting with the roadbed, which increases the difficulty of pulling out the piles. It often takes several times the theoretical calculation value to pull them out, and the guardrail piles often break due to the greatly reduced strength caused by rust, or they cannot be pulled out due to the rust of the guardrail piles and the roadbed. Summary of the invention
[0005] In view of the above problems, the present invention provides a method for pulling out highway anti-collision guardrail piles, which can greatly reduce the difficulty of pulling out piles and thus improve the efficiency of pulling out piles. The method is particularly suitable for pulling out and maintaining old guardrail piles that have reached their service life and need to be replaced.
[0006] To achieve the above-mentioned purpose, the pile driving and pulling device used in the pile pulling method of the highway anti-collision guardrail pile comprises a guide frame, a hydraulic vibratory hammer, a pile pulling device and a soil isolation pipe, the hydraulic vibratory hammer is installed on the guide frame through a vibratory hammer sliding guide mechanism and a vibratory hammer sliding drive mechanism that are arranged in cooperation; the pile pulling device that cooperates with the hammer head of the hydraulic vibratory hammer can be detachably installed on the hammer head of the hydraulic vibratory hammer, and the pile pulling device is provided with a supporting inner hole structure; the soil isolation pipe comprises a pipe cap and a pipe body, the pipe cap can be detachably installed on the top end of the pipe body, and the pipe cap cooperates with the hammer head of the hydraulic vibratory hammer, the inner diameter of the pipe body is larger than the outer diameter of the guardrail pile, and the bottom end of the pipe body is provided with a cutting edge structure extending downward, and the length dimension of the pipe body along the axial direction is larger than the length dimension of the guardrail pile along the axial direction;
[0007] The method for pulling out the pile of the highway anti-collision guardrail pile specifically comprises the following steps:
[0008] Step 1, driving the soil isolation pipe: first, align the soil isolation pipe with the outside of the guardrail pile to be pulled out, then adjust and control the hydraulic vibration hammer to align the pipe cap of the soil isolation pipe, and then control the hydraulic vibration hammer and the vibration hammer sliding drive mechanism to drive the hydraulic vibration hammer into the ground, and the driving depth of the soil isolation pipe is not less than the buried depth of the guardrail pile to be pulled out;
[0009] Step 2, pull out the soil isolation pipe: after controlling the hydraulic vibratory hammer to rise, install the pile pulling device on the hammer head of the hydraulic vibratory hammer, remove the pipe cap of the soil isolation pipe, control the hydraulic vibratory hammer and the sliding drive mechanism of the vibratory hammer to make the supporting inner hole structure of the pile pulling device extend into the soil isolation pipe, and control the supporting inner hole structure of the pile pulling device to firmly clamp and support it on the inner wall of the soil isolation pipe, and then control the sliding drive mechanism of the vibratory hammer to drive the hydraulic vibratory hammer to move up and completely pull out the soil isolation pipe, and then control the supporting inner hole structure of the pile pulling device to loosen the soil isolation pipe, and remove the soil isolation pipe;
[0010] Step 3, pull out the guardrail pile to be pulled out: control the hydraulic vibratory hammer and the sliding drive mechanism of the vibratory hammer to make the inner hole structure of the pile pulling device extend into the tube of the guardrail pile to be pulled out, and control the inner hole structure of the pile pulling device to firmly clamp and support it on the inner wall of the tube of the guardrail pile to be pulled out, and then control the sliding drive mechanism of the vibratory hammer to drive the hydraulic vibratory hammer to move the pile pulling device upward and completely pull out the guardrail pile to be pulled out.
[0011] As a further improvement scheme of the present invention, the pile driving and pulling device also includes a soil isolation pipe guide device installed on the guide frame through the support frame I, the soil isolation pipe guide device includes a base I and a guide assembly installed on the base I, the base I is provided with a through hole allowing the soil isolation pipe to pass through, and the central axis of the through hole is arranged colinearly with the central axis of the hammer head of the hydraulic vibration hammer, the guide assembly is arranged in multiple groups symmetrically relative to the central axis of the through hole, the guide assembly includes a guide seat, a buffer spring seat, a guide roller and a buffer spring, the guide seat is fixedly installed on the base I, the buffer spring seat is slidably installed on the guide seat, and the sliding direction of the buffer spring seat is arranged opposite to the central axis of the through hole, the guide roller is installed on the buffer spring seat through a roller shaft rolling fit, and the roller surface of the guide roller is a concave roller surface that matches the cylindrical outer surface size of the soil isolation pipe, one end of the buffer spring rests on the buffer spring seat, and the other end rests on the guide seat.
[0012] As a further improvement of the present invention, a spring stiffness adjustment mechanism is provided between the buffer spring and the guide seat.
[0013] As a further improvement scheme of the present invention, the pile driving and pulling device also includes a soil isolation pipe locking device installed on the guide frame through the support frame II, the soil isolation pipe locking device includes a plurality of locking components symmetrically arranged relative to the central axis of the hydraulic vibration hammer head, the locking component includes a base II and a locking claw installed on the base II through a locking claw translation drive mechanism, the translation direction of the locking claw is arranged opposite to the central axis of the hydraulic vibration hammer head, and the locking surface of the locking claw is a concave structure that matches the size of the cylindrical outer surface of the soil isolation pipe.
[0014] As a further improvement of the present invention, an elastic friction pad I is provided on the locking surface of the locking claw.
[0015] As a further improvement scheme of the present invention, the support frame I of the soil isolation pipe guiding device and the support frame II of the soil isolation pipe locking device share the same support frame, the top end of the support frame is hingedly mounted on the bottom end of the guide frame by a hinge shaft arranged in the axial direction along the left and right directions, and a support frame swing control mechanism which can control the support frame to swing along the front and rear directions is also provided between the support frames. When the support frame is completely flipped forward to be in a vertical state, the soil isolation pipe guiding device and the soil isolation pipe locking device make the soil isolation pipe in a vertical state directly below the hammer head of the hydraulic vibration hammer. When the support frame is completely flipped backward to be in a vertical state, the soil isolation pipe guiding device and the soil isolation pipe locking device make the soil isolation pipe in a vertical state located behind the guide frame.
[0016] As an embodiment of the present invention, the inner hole structure of the pile pulling device includes a central connecting shaft, a curved clamping plate and a connecting rod. The central connecting shaft and the curved clamping plate are both vertically arranged, and the curved clamping plate is symmetrically arranged in multiple pieces relative to the center axis of the central connecting shaft. The arc-shaped outer surface of the curved clamping plate is the clamping surface, and an elastic friction pad II is fixed on the clamping surface. The two ends of the connecting rod are respectively hingedly connected to the inner surface of the curved clamping plate and the central connecting shaft, and the connecting rod is parallelly arranged in multiple pieces up and down. The central connecting shaft, the curved clamping plate and the connecting rod together form a parallelogram structure, and the inner circle radius b of the soil isolation pipe or guardrail pile and the length dimension l of the connecting rod meet Where f is the friction coefficient between the elastic friction pad II and the inner tube surface of the soil isolation pipe or guardrail pile.
[0017] As a further improvement of the present invention, a traction component is provided on the connecting rod or the curved clamping plate.
[0018] As a further improvement of the present invention, an angle limiting structure is provided at the hinged position of the connecting rod and the central connecting shaft, which allows the connecting rod to swing within a range of 0 to 90 degrees.
[0019] As a further improvement of the present invention, the cutting edge structure of the tube body is a sawtooth cutting edge structure including a plurality of cutting edges arranged symmetrically with respect to the center.
[0020] Compared with the prior art, the method for pulling out highway anti-collision guardrail piles comprises the following steps: before pulling out the guardrail piles, firstly, a soil isolation tube is sleeved on the guardrail piles to be pulled out, and the tube is driven into the ground to a depth not less than the buried depth of the guardrail piles to be pulled out, so that the guardrail piles to be pulled out are isolated from the soil around them, and the stable adhesion and bonding state between the guardrail piles to be pulled out and the soil around them is broken, and then the soil isolation tube is pulled out. When pulling out the soil isolation tube, since the soil isolation tube is sleeved on the guardrail piles to be pulled out, and the gap between the soil isolation tube and the guardrail piles to be pulled out is small, the friction resistance between the inner tube surface of the soil isolation tube and the soil is small, thereby greatly reducing the pulling force required to pull out the soil isolation tube, and the pulling out of the soil isolation tube is easy. When the guardrail piles to be pulled out are pulled out after the soil isolation pipe, the stable adhesion between the guardrail piles to be pulled out and the surrounding soil has been broken. Therefore, the mass of the soil attached to the guardrail piles to be pulled out can be greatly reduced, and the large friction resistance between the soil and the guardrail piles to be pulled out can be basically eliminated, thereby greatly reducing the pulling force required for pile pulling and preventing the guardrail piles to be pulled out from being broken. It is not only suitable for pile pulling operations on guardrail piles with complete morphology, but also for pile pulling operations on damaged guardrail piles such as broken piles, old piles with severe pile corrosion, etc. It is especially suitable for pile pulling and maintenance operations on old guardrail piles that have reached their service life and need to be replaced. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a right side structural schematic diagram of the pile driving and pulling device of the present invention;
[0022] Figure 2 It is a structural schematic diagram of the soil isolation pipe guiding device and the soil isolation pipe locking device of the present invention sharing the same supporting frame, wherein (a) is a structural schematic diagram of the supporting frame being flipped toward the rear of the guiding frame to be in a horizontal state, and (b) is a structural schematic diagram of the supporting frame being flipped toward the rear of the guiding frame to be against the back of the guiding frame;
[0023] Figure 3 It is a schematic diagram of the structure of the soil isolation pipe of the present invention;
[0024] Figure 4 It is a structural schematic diagram of the soil isolation pipe guide device of the present invention;
[0025] Figure 5 It is a structural schematic diagram of the soil isolation pipe locking device of the present invention;
[0026] Figure 6 It is a schematic structural diagram of the pile pulling device of the present invention;
[0027] Figure 7 yes Figure 6 Top view of the .
[0028] In the figure: 1. guide frame, 2. soil isolation pipe, 21. pipe cap, 22. pipe body, 3. soil isolation pipe guide device, 31. guide roller, 32. roller shaft, 33. buffer spring seat, 34. buffer spring, 35. spring stiffness adjustment mechanism, 36. base I, 37. guide seat, 4. soil isolation pipe locking device, 41. base II, 42. locking claw, 43. locking claw translation drive mechanism, 44. elastic friction pad I, 5. hydraulic vibration hammer, 6. pile pulling device, 61. central connecting shaft, 62. curved clamping plate, 63. connecting rod, 64. elastic friction pad II, 65. traction component, 66. angle limiting structure. DETAILED DESCRIPTION
[0029] The present invention will be further described below in conjunction with the accompanying drawings.
[0030] like Figure 1 As shown, the pile driving and pulling device used in the pile pulling method of the highway anti-collision guardrail pile includes a guide frame 1, a hydraulic vibratory hammer 5, a pile pulling device 6 and a soil isolation pipe 2. The guide frame 1 can be flipped to a vertical state, and the hydraulic vibratory hammer 5 is installed on the guide frame 1 through a vibratory hammer sliding guide mechanism and a vibratory hammer sliding drive mechanism that are arranged in cooperation. The vibratory hammer sliding guide mechanism can be a guide groove and guide block structure that are arranged in cooperation, or it can be other guiding lifting structures such as a guide rail and guide wheel structure that are arranged in cooperation. The vibratory hammer sliding drive mechanism can be a telescopic cylinder transmission structure, or it can be a gear including a driving motor. The gear rack transmission structure and other lifting drive structures can realize the lifting action of the hydraulic vibratory hammer 5 on the guide frame 1 by controlling the action of the vibratory hammer sliding drive mechanism. The vibratory hammer sliding guide mechanism and the vibratory hammer sliding drive mechanism are both prior art and will not be described in detail here. The pile pulling device 6 matched with the hammer head of the hydraulic vibratory hammer 5 can be detachably installed on the hammer head of the hydraulic vibratory hammer 5. The pile pulling device 6 is provided with a supporting inner hole structure that can be clamped and supported on the inner wall of the guardrail pile or the soil isolation pipe 2. The pile pulling device 6 with the supporting inner hole structure is prior art and will not be described in detail here. Figure 3 As shown, the soil isolation pipe 2 includes a pipe cap 21 and a pipe body 22. The pipe cap 21 is detachably mounted on the top end of the pipe body 22, and the pipe cap 21 cooperates with the hammer head of the hydraulic vibration hammer 5. The inner diameter of the pipe body 22 is slightly larger than the outer diameter of the guardrail pile. The inner diameter of the pipe body 22 may be slightly larger than the outer diameter of the guardrail pile by 10 to 30 mm. The bottom end of the pipe body 22 is provided with a cutting edge structure extending downward. The cutting edge structure may be a sawtooth cutting edge structure including a plurality of centrally symmetrical cutting edges, or may be other cutting edge structures such as an oblique cutting edge structure formed by cutting an inclined cutting surface inclined to the axial direction of the pipe body 22. The length dimension of the pipe body 22 along the axial direction is greater than the length dimension of the guardrail pile along the axial direction.
[0031] The method for pulling out the pile of the highway anti-collision guardrail pile specifically comprises the following steps:
[0032] Step 1, drive in the soil isolation pipe: first align the soil isolation pipe 2 and sleeve it on the outside of the guardrail pile to be pulled out, then adjust and control the hydraulic vibratory hammer 5 to align the pipe cap 21 of the soil isolation pipe 2, then control the hydraulic vibratory hammer 5 and the vibratory hammer sliding drive mechanism to drive the hydraulic vibratory hammer 5 to drive the soil isolation pipe 2 into the ground, and the driving depth of the soil isolation pipe 2 is not less than the burial depth of the guardrail pile to be pulled out. After the soil isolation pipe 2 is driven into the ground under the vibration impact of the hydraulic vibratory hammer 5, the guardrail pile to be pulled out and the surrounding soil will be isolated, and the stable adhesion between the guardrail pile to be pulled out and the surrounding soil will be broken.
[0033] Step 2, pull out the soil isolation pipe: after controlling the hydraulic vibratory hammer 5 to rise, install the pile pulling device 6 on the hammer head of the hydraulic vibratory hammer 5, remove the pipe cap 21 of the soil isolation pipe 2, control the hydraulic vibratory hammer 5 and the vibratory hammer sliding drive mechanism to make the inner hole support structure of the pile pulling device 6 extend into the soil isolation pipe 2, and control the inner hole support structure of the pile pulling device 6 to firmly clamp and support on the inner wall of the soil isolation pipe 2, then control the vibratory hammer sliding drive mechanism to make the hydraulic vibratory hammer 5 drive the pile pulling device 6 to move upward and completely pull out the soil isolation pipe 2, then control the inner hole support structure of the pile pulling device 6 to loosen the soil isolation pipe 2, and remove the soil isolation pipe 2.
[0034] Step 3, pull out the guardrail pile to be pulled out: control the hydraulic vibratory hammer 5 and the sliding drive mechanism of the vibratory hammer to make the inner hole structure of the pile pulling device 6 extend into the pipe of the guardrail pile to be pulled out, and control the inner hole structure of the pile pulling device 6 to firmly clamp and support it on the inner wall of the pipe of the guardrail pile to be pulled out, and flexibly place the inner hole structure of the pile pulling device 6 on the wall surface of the inner wall of the guardrail pile to be pulled out that is not corroded to increase the friction force, and then control the sliding drive mechanism of the vibratory hammer to make the hydraulic vibratory hammer 5 drive the pile pulling device 6 to move up and completely pull out the guardrail pile to be pulled out. After the soil isolation pipe 2 is driven in and pulled out, the firmly bonded state between the guardrail pile to be pulled out and the soil around it is broken, so that not only the mass of the soil attached to the guardrail pile to be pulled out can be greatly reduced, but also the large friction resistance between the soil and the guardrail pile to be pulled out can be basically eliminated, thereby greatly reducing the pulling force required for pile pulling and preventing the guardrail pile to be pulled out from being broken.
[0035] In the process of driving the soil isolation pipe 2, in order to avoid interference between the soil isolation pipe 2 and the guardrail pile to be pulled out due to eccentric loading, as a further improvement of the present invention, Figure 1 As shown, the pile driving and pulling device also includes a soil isolation pipe guide device 3 installed on the guide frame 1 through the support frame I, as shown in FIG. Figure 4As shown, the soil isolation pipe guide device 3 includes a base Ⅰ36 and a guide component installed on the base Ⅰ36. The base Ⅰ36 is provided with a through hole that allows the soil isolation pipe 2 to pass through, and the central axis of the through hole is arranged in a colinear manner with the central axis of the hammer head of the hydraulic vibration hammer 5. The guide component is symmetrically arranged in multiple groups (two groups are shown in the figure) relative to the central axis of the through hole. The guide component includes a guide seat 37, a buffer spring seat 33, a guide roller 31 and a buffer spring 34. The guide seat 37 is fixedly installed on the base Ⅰ36, the buffer spring seat 33 is slidably installed on the guide seat 37, and the sliding direction of the buffer spring seat 33 is arranged opposite to the central axis of the through hole. The guide roller 31 is rollingly installed on the buffer spring seat 33 through the roller shaft 32, and the roller surface of the guide roller 31 is a concave roller surface that matches the cylindrical outer surface size of the soil isolation pipe 2. One end of the buffer spring 34 rests on the buffer spring seat 33, and the other end rests on the guide seat 37. Before the soil isolation tube 2 is sleeved on the outside of the guardrail pile to be pulled out, the soil isolation tube 2 is first inserted into the through hole of the base Ⅰ36 so that the soil isolation tube 2 is clamped on the roller surface of the guide roller 31. At this time, the soil isolation tube 2 causes the buffer spring 34 to be in a compressed state through the guide roller 31. The guide components arranged in multiple groups symmetrically at the center provide a balanced clamping force to the soil isolation tube 2 through their respective buffer springs 34 at the same time. This balanced clamping force can automatically center the soil isolation tube 2 and avoid unbalanced loading during the process of controlling the hydraulic vibration hammer 5 to drive the soil isolation tube 2 into the ground. In order to facilitate the adjustment of the clamping force and effectively buffer the vibration impact of the hydraulic vibration hammer 5 on the entire pile driving and pulling device when it is working, a spring stiffness adjustment mechanism 35 can also be provided between the buffer spring 34 and the guide seat 37. The spring stiffness adjustment mechanism 35 can be as follows Figure 4 The thread shown is matched with an adjusting bolt installed on the guide seat 37, the end of the adjusting bolt is connected to the buffer spring 34, and the axial direction of the adjusting bolt corresponds to the sliding direction of the buffer spring seat 33. After the soil isolation pipe 2 is inserted into the through hole of the base Ⅰ36, the stiffness of the buffer spring 34 can be adjusted by tightening or loosening the adjusting bolt, thereby adjusting the size of the clamping force; the spring stiffness adjustment mechanism 35 can also be a structure of a matching locating pin and a plurality of pin-stop locating holes arranged at intervals corresponding to the sliding direction of the buffer spring seat 33. After the locating pin is inserted into the pin-stop locating hole, it is connected to the buffer spring 34. The stiffness of the buffer spring 34 can be adjusted by inserting the locating pin into the pin-stop locating holes at different positions, thereby adjusting the size of the clamping force. The setting of the soil isolation pipe guide device 3 is also applicable when driving new guardrail piles. By adjusting the stiffness of the buffer spring 34 through the spring stiffness adjustment mechanism 35 and making the guide roller 31 clamped on the guardrail pile, a balanced clamping force can be provided to the guardrail pile. Manual support by the operator is no longer required, which can reduce labor intensity and increase operation safety.
[0036] In order to achieve stable positioning of the soil isolation pipe 2 when not in use, as a further improvement of the present invention, Figure 1 As shown, the pile driving and pulling device also includes a soil isolation pipe locking device 4 installed on the guide frame 1 through the support frame II, such as Figure 5 As shown, the soil isolation pipe locking device 4 includes multiple locking components (two groups are shown in the figure) that are centrally symmetrically arranged relative to the central axis of the hammer head of the hydraulic vibration hammer 5. The locking component includes a base II 41 and a locking claw 42 installed on the base II 41 through a locking claw translation driving mechanism 43. The translation direction of the locking claw 42 is arranged directly opposite to the central axis of the hammer head of the hydraulic vibration hammer 5, and the locking surface of the locking claw 42 is a concave structure that matches the cylindrical outer surface size of the soil isolation pipe 2. The locking claw translation driving mechanism 43 can be a telescopic cylinder transmission structure or a gear rack transmission structure including a driving motor. Other translation driving structures, such as a gear rack transmission structure, can be achieved by controlling the action of the locking claw translation driving mechanism 43 to control the locking claw 42 to translate close to the soil isolation pipe 2 for locking or to translate away from the soil isolation pipe 2 for loosening. The soil isolation pipe 2 can be firmly positioned by the soil isolation pipe locking device 4 when not in use, and the soil isolation pipe 2 can be prevented from slipping when the guide frame 1 is erected. In order to achieve stable locking of the locking claw 42 , an elastic friction pad I 44 for ensuring the friction between the locking claw 42 and the soil isolation pipe 2 may also be provided on the locking surface of the locking claw 42 .
[0037] In order to facilitate folding and storage and avoid position interference of the soil isolation pipe 2 when pulling out the guardrail pile to be pulled out, as a further improvement scheme of the present invention, Figure 1 , Figure 2 As shown, the support frame I of the soil isolation pipe guide device 3 and the support frame II of the soil isolation pipe locking device 4 share the same support frame, the top of the support frame is hingedly installed on the bottom end of the guide frame 1 through a hinge shaft arranged in the left and right direction in the axial direction, and a support frame swing control mechanism that can control the support frame to swing in the front and rear directions is also provided between the support frame and the guide frame 1. When the support frame is completely turned out to the front and in a vertical state, the soil isolation pipe guide device 3 and the soil isolation pipe locking device 4 make the soil isolation pipe 2 in a vertical state directly below the hammer head of the hydraulic vibration hammer 5. When the support frame is completely flipped backwards and is in a vertical state, the soil isolation pipe guiding device 3 and the soil isolation pipe locking device 4 make the soil isolation pipe 2 in a vertical state behind the guide frame 1. The support frame swing control mechanism can be a telescopic cylinder structure, or a rotary motor structure arranged at the hinge axis position or other swing control structures. During the operation of driving in and pulling out the soil isolation pipe, the support frame swing control mechanism can be controlled to make the support frame in a vertical state, thereby making the soil isolation pipe 2 in a vertical state. Before pulling out the guardrail pile to be pulled out, Figure 2 (a) Figure 2As shown in (b), the support frame swing control mechanism can be controlled to make the support frame swing toward the rear of the guide frame 1 and abut against the back of the guide frame 1, so that the soil isolation pipe 2 makes way and is located on the back of the guide frame 1.
[0038] As an embodiment of the pile pulling device 6 of the present invention, the inner hole structure of the pile pulling device 6 is a parallelogram structure, that is, Figure 6 , Figure 7 As shown, the inner hole structure of the pile pulling device 6 includes a central connecting shaft 61, a curved clamping plate 62 and a connecting rod 63. The central connecting shaft 61 and the curved clamping plate 62 are both vertically arranged, and the curved clamping plate 62 is symmetrically arranged in multiple pieces relative to the central axis of the central connecting shaft 61. The arc-shaped outer surface of the curved clamping plate 62 is a clamping surface, and an elastic friction pad II 64 is fixedly arranged on the clamping surface. The two ends of the connecting rod 63 are respectively hingedly connected to the inner surface of the curved clamping plate 62 and the central connecting shaft 61, and the connecting rod 63 is arranged in multiple pieces in parallel up and down. The central connecting shaft 61, the curved clamping plate 62 and the connecting rod 63 together form a parallelogram structure, and the inner circle radius b of the soil isolation pipe 2 or the guardrail pile and the length dimension l of the connecting rod 63 meet Wherein f is the friction coefficient between the elastic friction pad II 64 and the inner tube surface of the soil isolation pipe 2 or the guardrail pile. When this dimensional relationship is met and the angle between the upper surface of the connecting rod 63 and the central connecting shaft 61 is acute, the curved clamping plate 62 can be firmly supported and in a self-locking state. When using the pile pulling device 6 to pull out the soil isolation pipe 2 or the guardrail pile to be pulled out, the connecting rod 63 can be pulled upward first to make the curved clamping plate 62 close to the central connecting shaft 61 and then send the pile pulling device 6 with the curved clamping plate 62 gathered into the soil isolation pipe 2 or the pipe of the guardrail pile to be pulled out, and the pulling force of the pulling connecting rod 63 is removed. The curved clamping plate 62 can be pressed against the inner wall of the pipe under the action of its own gravity. When the vibration hammer sliding drive mechanism is controlled to move so that the hydraulic vibration hammer 5 drives the pile pulling device 6 to move upward, the curved clamping plate 62 is in a self-locking state after being firmly supported. The greater the upward pulling force, the greater the self-locking force of the curved clamping plate 62, thereby achieving a firm support of the curved clamping plate 62 and driving the soil isolation pipe 2 or the guardrail pile to be pulled up. In order to facilitate the control of the gathering of the curved clamping plate 62, a traction component 65 can be provided on the connecting rod 63 or the curved clamping plate 62. The traction component 65 can be a traction wire structure or other traction structures such as a traction rod structure. In order to avoid the angle between the upper surface of the connecting rod 63 and the central connecting shaft 61 being an obtuse angle, which makes the self-locking of the curved clamping plate 62 ineffective, an angle limiting structure 66 that can limit the downward swing of the connecting rod 63 can also be provided at the hinge position of the connecting rod 63 and the central connecting shaft 61. The angle limiting structure 66 can be other angle limiting structures 66 such as a limiting boss structure or a limiting block structure. The angle limiting structure 66 can limit the swing of the connecting rod 63 within the range of 0 to 90 degrees. If a greater friction force is to be achieved, the vertical size of the pile pulling device 6 can be increased according to the same topological structure.
[0039] Before the pile extraction operation of the highway anti-collision guardrail pile is carried out, the soil isolation tube 2 is firstly put on the guardrail pile to be extracted and driven into the ground to a depth not less than the buried depth of the guardrail pile to be extracted, so that the guardrail pile to be extracted and the surrounding soil are isolated and the stable adhesion state between the guardrail pile to be extracted and the surrounding soil is broken, and then the soil isolation tube 2 is pulled out. When the soil isolation tube 2 is pulled out, since the soil isolation tube 2 is put on the guardrail pile to be extracted and the gap between the soil isolation tube 2 and the guardrail pile is small, the friction resistance between the inner tube surface of the soil isolation tube 2 and the soil is small, thereby greatly reducing the pile extraction force required to pull out the soil isolation tube 2, and the soil is pulled out. When the guardrail piles to be pulled out are pulled out after the isolation pipe 2, the stable adhesion between the guardrail piles to be pulled out and the soil around them has been broken. Therefore, the mass of the soil attached to the guardrail piles to be pulled out can be greatly reduced, and the large friction resistance between the soil and the guardrail piles to be pulled out can be basically eliminated, thereby greatly reducing the pulling force required for pulling out the piles and preventing the guardrail piles to be pulled out from being broken. It is not only suitable for pulling out guardrail piles with complete morphology, but also for pulling out damaged guardrail piles such as broken piles, old piles with severe pile corrosion, etc. It is particularly suitable for pulling out and maintaining old guardrail piles that have reached their service life and need to be replaced.
Claims
1. A method for pulling out a highway anti-collision guardrail pile, characterized in that: The pile driving and pulling device used comprises a guide frame (1), a hydraulic vibrating hammer (5), a pile pulling device (6) and a soil isolation pipe (2); the hydraulic vibrating hammer (5) is installed on the guide frame (1) through a vibrating hammer sliding guide mechanism and a vibrating hammer sliding drive mechanism; the pile pulling device (6) matched with the hammer head of the hydraulic vibrating hammer (5) is detachably installed on the hammer head of the hydraulic vibrating hammer (5), and the pile pulling device (6) is provided with an inner hole support structure; the soil isolation pipe (2) comprises a pipe cap (21) and a pipe body (22); the pipe cap (21) is detachably installed on the top of the pipe body (22), and the pipe cap (21) is matched with the hammer head of the hydraulic vibrating hammer (5); the inner diameter of the pipe body (22) is larger than the outer diameter of the guardrail pile, and the bottom end of the pipe body (22) is provided with a cutting edge structure extending downward, and the length of the pipe body (22) along the axial direction is larger than the length of the guardrail pile along the axial direction; The method for pulling out the pile of the highway anti-collision guardrail pile specifically comprises the following steps: Step 1, driving the soil isolation pipe: firstly align the soil isolation pipe (2) and sleeve it on the outside of the guardrail pile to be pulled out, then adjust and control the hydraulic vibration hammer (5) to align the pipe cap (21) of the soil isolation pipe (2), then control the hydraulic vibration hammer (5) and the vibration hammer sliding drive mechanism to drive the hydraulic vibration hammer (5) to drive the soil isolation pipe (2) into the ground, and the driving depth of the soil isolation pipe (2) is not less than the buried depth of the guardrail pile to be pulled out; Step 2, pulling out the soil isolation pipe: after controlling the hydraulic vibration hammer (5) to rise, the pile pulling device (6) is installed on the hammer head of the hydraulic vibration hammer (5), and after removing the pipe cap (21) of the soil isolation pipe (2), the hydraulic vibration hammer (5) and the vibration hammer sliding drive mechanism are controlled to move so that the supporting inner hole structure of the pile pulling device (6) extends into the soil isolation pipe (2), and the supporting inner hole structure of the pile pulling device (6) is controlled to be firmly clamped and supported on the inner wall of the soil isolation pipe (2), and then the vibration hammer sliding drive mechanism is controlled to move so that the hydraulic vibration hammer (5) drives the pile pulling device (6) to move upward and completely pull out the soil isolation pipe (2), and then the supporting inner hole structure of the pile pulling device (6) is controlled to loosen the soil isolation pipe (2), and the soil isolation pipe (2) is removed; Step 3, pulling out the guardrail pile to be pulled out: controlling the hydraulic vibratory hammer (5) and the sliding drive mechanism of the vibratory hammer to move so that the supporting inner hole structure of the pile pulling device (6) extends into the pipe of the guardrail pile to be pulled out, and controlling the supporting inner hole structure of the pile pulling device (6) to firmly clamp and support it on the inner wall of the pipe of the guardrail pile to be pulled out, and then controlling the sliding drive mechanism of the vibratory hammer to move so that the hydraulic vibratory hammer (5) drives the pile pulling device (6) to move upward and completely pull out the guardrail pile to be pulled out.
2. The method for pulling out a highway anti-collision guardrail pile according to claim 1, characterized in that: The pile driving and pulling device also includes a soil isolation pipe guide device (3) installed on the guide frame (1) through a support frame I. The soil isolation pipe guide device (3) includes a base I (36) and a guide assembly installed on the base I (36). The base I (36) is provided with a through hole that allows the soil isolation pipe (2) to pass through, and the central axis of the through hole is arranged in a colinear manner with the central axis of the hammer head of the hydraulic vibration hammer (5). The guide assembly is arranged in a plurality of groups symmetrically with respect to the central axis of the through hole. The guide assembly includes a guide seat (37), a buffer spring seat (33), a guide roller (31) and a buffer spring seat (34). The guide seat (37) is fixedly mounted on the base I (36), the buffer spring seat (33) is slidably mounted on the guide seat (37), and the sliding direction of the buffer spring seat (33) is arranged to be opposite to the central axis of the through hole, the guide roller (31) is rollingly mounted on the buffer spring seat (33) through a roller shaft (32), and the roller surface of the guide roller (31) is a concave roller surface that matches the cylindrical outer surface size of the soil isolation pipe (2), and one end of the buffer spring (34) is against the buffer spring seat (33), and the other end is against the guide seat (37).
3. The method for pulling out a highway anti-collision guardrail pile according to claim 2, characterized in that: A spring stiffness adjustment mechanism (35) is provided between the buffer spring (34) and the guide seat (37).
4. The method for pulling out a highway anti-collision guardrail pile according to claim 2, characterized in that: The pile driving and pulling device also includes a soil isolation pipe locking device (4) installed on the guide frame (1) through a support frame II. The soil isolation pipe locking device (4) includes a plurality of locking components that are centrally symmetrically arranged relative to the central axis of the hammer head of the hydraulic vibration hammer (5). The locking components include a base II (41) and a locking claw (42) installed on the base II (41) through a locking claw translation drive mechanism (43). The translation direction of the locking claw (42) is arranged to face the central axis of the hammer head of the hydraulic vibration hammer (5), and the locking surface of the locking claw (42) is a concave structure that matches the size of the cylindrical outer surface of the soil isolation pipe (2).
5. The method for pulling out a highway anti-collision guardrail pile according to claim 4, characterized in that: An elastic friction pad I (44) is arranged on the locking surface of the locking claw (42).
6. The method for pulling out a highway anti-collision guardrail pile according to claim 4, characterized in that: The support frame I of the soil isolation pipe guide device (3) and the support frame II of the soil isolation pipe locking device (4) share the same support frame. The top end of the support frame is hingedly mounted on the bottom end of the guide frame (1) via a hinge shaft arranged in the axial direction along the left and right directions. A support frame swing control mechanism capable of controlling the support frame to swing in the front-back direction is also arranged between the support frame and the guide frame (1). When the support frame is completely turned forward to be in a vertical state, the soil isolation pipe guide device (3) and the soil isolation pipe locking device (4) make the soil isolation pipe (2) in a vertical state directly below the hammer head of the hydraulic vibration hammer (5). When the support frame is completely turned backward to be in a vertical state, the soil isolation pipe guide device (3) and the soil isolation pipe locking device (4) make the soil isolation pipe (2) in a vertical state located behind the guide frame (1).
7. The method for pulling out a highway anti-collision guardrail pile according to any one of claims 1 to 6, characterized in that: The supporting inner hole structure of the pile pulling device (6) comprises a central connecting shaft (61), a curved clamping plate (62) and a connecting rod (63). The central connecting shaft (61) and the curved clamping plate (62) are both arranged vertically, and the curved clamping plate (62) is arranged in a plurality of symmetrical positions relative to the central axis of the central connecting shaft (61). The arc-shaped outer surface of the curved clamping plate (62) is a clamping surface, and an elastic friction pad II (64) is fixedly arranged on the clamping surface. The two ends of the connecting rod (63) are respectively hingedly connected to the inner surface of the curved clamping plate (62) and the central connecting shaft (61), and the connecting rod (63) is arranged in a plurality of parallel positions up and down. The central connecting shaft (61), the curved clamping plate (62) and the connecting rod (63) together form a parallelogram structure. The inner radius b of the soil isolation pipe (2) or the guardrail pile and the length dimension l of the connecting rod (63) meet the requirements. Wherein f is the friction coefficient between the elastic friction pad II (64) and the inner tube surface of the soil isolation tube (2) or the guardrail pile.
8. The method for pulling out a highway anti-collision guardrail pile according to claim 7, characterized in that: A traction component (65) is provided on the connecting rod (63) or the curved surface clamping plate (62).
9. The method for pulling out a highway anti-collision guardrail pile according to claim 7, characterized in that: An angle limiting structure (66) is provided at the hinged position between the connecting rod (63) and the central connecting shaft (61), which enables the connecting rod (63) to swing within a range of 0 to 90 degrees.
10. The method for pulling out a highway anti-collision guardrail pile according to any one of claims 1 to 6, characterized in that: The cutting edge structure of the tube body (22) is a sawtooth cutting edge structure comprising a plurality of cutting edges arranged symmetrically with respect to the center.
Citation Information
Cited By
Novel mounting device for mounting steel stand column
CN119737084A