Improved warehouse jumping method for efficient and high-quality construction of ultra-long concrete structure
By adopting an improved warehouse jumping method in the ultra-long concrete structure, pouring is divided into three time periods and using corner cuts to form a third pouring warehouse, which solves the problem of stress concentration, improves construction quality and safety, and simplifies the process. and reduce costs.
Patent Information
- Application Number
- CN202411128231.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-16
- Publication Date
- 2024-10-25
AI Technical Summary
In the construction of ultra-long concrete structures, the existing jumping method causes stress concentration in the concrete at the connecting corners, leading to structural damage.
Using the improved warehouse jumping method, the first, second and third pouring warehouses are formed by dividing the pouring into three time periods. The third pouring warehouse is formed by cutting the adjacent corners of the first and second pouring warehouses. Incorporate waterstops and restraints to ensure adequate setting and stress relief of the concrete.
The stress concentration problem is significantly improved, the risk of concrete damage is reduced, the construction quality and structural safety are improved, the construction process is simplified, and the cost and difficulty are reduced.
Smart Images

Figure CN118835798A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of building construction, and in particular to an improved skipping method for efficient and high-quality construction of ultra-long concrete structures. Background Art
[0002] The skip bin method is used in the construction of an ultra-long concrete structure. The skip bin method is an intermittent concrete pouring method that divides the concrete into multiple small blocks (called "bins") for gradual pouring and segmented construction, rather than pouring the entire area at one time. Each "bin" needs a certain interval after pouring, and the adjacent bins are poured after the concrete has initially solidified.
[0003] However, in the skipping bin method in the prior art, when the concrete pouring is too long, the connecting corners of adjacent cells in each bin are prone to stress concentration reaction due to temperature effects and other problems during pouring, resulting in damage to the poured concrete. Therefore, in order to improve this phenomenon, an improved skipping bin method for efficient and high-quality construction of ultra-long concrete structures is proposed. Summary of the invention
[0004] In view of this, it is necessary to provide an improved skipping method for efficient and high-quality construction of ultra-long concrete structures to solve the stress concentration at the connecting corners of adjacent communities, so as to solve the above problems.
[0005] The embodiment of the present application provides an improved skipping method for efficient and high-quality construction of ultra-long concrete structures, the steps comprising:
[0006] Set up the construction area;
[0007] performing a pre-processing process to form a construction area including a plurality of construction blocks arranged side by side and in parallel;
[0008] Setting up a first concrete slab side formwork at the boundary of the construction area and performing preliminary construction in the casting area;
[0009] The construction blocks are poured at intervals and divided into three time periods for batch pouring to form three pouring bins; the three pouring bins include: a first pouring bin, a second pouring bin and a third pouring bin formed by the cut corners of the adjacent construction block corners of the first pouring bin and the second pouring bin.
[0010] In at least one embodiment of the present application, the step of "casting the construction block at intervals and casting in three time periods to form three casting bins" includes:
[0011] In a first time period, pouring the construction blocks spaced longitudinally and transversely to form the first pouring bin;
[0012] In the second time period, the construction blocks spaced apart in the longitudinal and transverse directions are cast to form a second casting bin interlaced with the first casting bin.
[0013] In at least one embodiment of the present application, the step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes:
[0014] In a third time period, a third casting bin formed by the cut corners of the first casting bin and the second casting bin adjacent to the corners of the construction blocks is cast.
[0015] In at least one embodiment of the present application, the step of "casting the construction blocks longitudinally and transversely at intervals in the first time period to form the first casting bin" includes:
[0016] Before the first casting bin is cast, a second concrete slab side form is erected at the boundary of the construction block;
[0017] A first concrete slab corner cutting mold is erected on the construction block corner cutting and connected to the second concrete slab side mold to form a first compartment plate.
[0018] In at least one embodiment of the present application, the step of "casting the construction blocks longitudinally and transversely at intervals in the first time period to form the first casting bin" further includes:
[0019] Water-stopping members are provided at the boundaries of the construction areas of the first casting bin and the second casting bin to provide water-stopping measures and limiting members are provided to limit the lateral direction of the boundary concrete.
[0020] In at least one embodiment of the present application, the step of "in a second time period, pouring the construction blocks at intervals in the longitudinal and transverse directions to form a second pouring bin staggered with the first pouring bin" includes:
[0021] Before pouring the second pouring bin, the boundary of the first pouring bin is used as the side form of the third concrete slab;
[0022] A second concrete slab corner cutting mold is set up at the corner of the construction block and connected to the boundary of the first casting bin to form a second partition slab.
[0023] In at least one embodiment of the present application, the step of "in the third time period, pouring a third pouring bin composed of the cut corners of the first pouring bin and the second pouring bin adjacent to the corners of the construction block" includes:
[0024] The four corners formed by the cutting corners of the first concrete slab and the cutting corners of the second concrete slab form a rectangle, which is the third casting area of the third casting bin.
[0025] In at least one embodiment of the present application, the step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes:
[0026] The pouring time in adjacent time periods must be greater than 7 days.
[0027] In at least one embodiment of the present application, the step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes:
[0028] The sides of the construction blocks are equal in length, and the size of the cut corners is less than 1 / 2 of the side length of the construction blocks.
[0029] In at least one embodiment of the present application, the step of "implementing a pretreatment process" includes:
[0030] Implement processes such as foundation leveling, cushion layer pouring, waterproofing construction, boundary line measurement, and line laying.
[0031] The improved skipping method for efficient and high-quality construction of ultra-long concrete structures provided above has the following beneficial effects:
[0032] The third pouring bin, which is composed of the corner cuts of adjacent blocks, significantly improves the stress concentration problem in the construction of ultra-long concrete structures. During the pouring process, this design can effectively disperse the stress that may have been highly concentrated in the corners to a larger area, thereby greatly reducing the risk of concrete damage due to stress concentration and ensuring construction quality and structural safety.
[0033] The intermittent pouring method is adopted, and the pouring process is divided into three time periods for pouring in batches. This not only ensures the full solidification and strength development of the concrete, but also allows each warehouse of concrete to have enough time to release internal stress and stabilize temperature before pouring, thus avoiding problems such as large temperature gradient and stress concentration caused by continuous pouring. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] Figure 1 A schematic diagram of the pouring area described in the present application performing pouring in the first pouring bin in the first time period;
[0035] Figure 2 A schematic diagram of the pouring area described in the present application performing pouring in the second pouring bin in the second time period;
[0036] Figure 3 A schematic diagram of the pouring area described in the present application performing pouring in the third pouring bin in the third time period;
[0037] Figure 4 A schematic diagram showing the pouring of the pouring area described in this application;
[0038] Figure 5 for Figure 3 A partial enlarged view of the middle AA;
[0039] Figure 6 A step-by-step diagram of the improved skip-bin method for efficient and high-quality construction of ultra-long concrete structures;
[0040] Main component symbols
[0041] 100. Casting area; 110. First concrete slab side form; 10. First casting bin; 11. Second concrete slab side form; 12. First concrete slab corner cut form; 13. First partition plate; 20. Second casting bin; 21. Third concrete slab side form; 22. Second partition plate; 30. Third casting bin; 31. Third casting area; F1. Longitudinal; F2. Transverse; 200. Improved skipping bin method for efficient and high-quality construction of ultra-long concrete structures. DETAILED DESCRIPTION
[0042] The embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments.
[0043] It should be noted that when a component is considered to be "connected" to another component, it may be directly connected to the other component or there may be a central component at the same time. When a component is considered to be "located on" another component, it may be directly located on the other component or there may be a central component at the same time. The terms "top", "bottom", "upper", "lower", "left", "right", "front", "back", and similar expressions used herein are for illustrative purposes only.
[0044] Some embodiments of the present application are described in detail below in conjunction with the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.
[0045] See also Figure 1-Figure 6 The embodiment of the present application provides an improved skipping method 200 for efficient and high-quality construction of ultra-long concrete structures, the steps comprising:
[0046] S10: Set up the construction area;
[0047] S20: performing a pre-processing process to form a construction area including a plurality of construction blocks arranged side by side and in parallel;
[0048] S30: erecting a first concrete slab side form 110 at the boundary of the construction area, and performing preliminary construction in the casting area 100;
[0049] S40: pouring the construction block at intervals, and pouring in batches in three time periods to form three pouring bins;
[0050] The three casting bins include: a first casting bin 10 , a second casting bin 20 , and a third casting bin 30 formed by cutting corners of the first casting bin 10 and the second casting bin 20 adjacent to the construction block corners.
[0051] Specifically, the pretreatment steps include foundation leveling, cushion pouring, waterproofing construction, boundary measurement, layout, etc. These steps together constitute the preparatory work before construction.
[0052] Ground leveling ensures that the ground is level and provides a stable foundation for concrete pouring.
[0053] The cushion layer is poured on the foundation to enhance the bearing capacity of the foundation and prevent cracks caused by direct contact between the concrete and the foundation.
[0054] Waterproof construction carries out waterproofing treatment on the cushion layer to prevent groundwater penetration and protect the concrete structure.
[0055] Edge measurement and layout accurately measure and mark the construction boundary to provide an accurate basis for subsequent construction.
[0056] Each step in the pretreatment process is to pave the way for subsequent construction and ensure the quality and progress of construction. In particular, waterproofing construction and edge measurement are directly related to the durability and accuracy of the concrete structure.
[0057] On the boundary of the pre-processed construction area, set up the concrete slab side formwork to support and fix the shape and size of the concrete when pouring.
[0058] As the template for concrete pouring, the stability and accuracy of the side formwork directly affect the appearance and quality of the concrete structure. By accurately setting up the side formwork, the flatness and verticality of the concrete slab can be ensured, reducing the subsequent repair work.
[0059] In the pouring area 100, preliminary construction such as steel bar binding, hole reservation, and pipeline and embedded parts burying is carried out.
[0060] According to the design requirements, various types of steel bars in the concrete slab are tied to form a steel skeleton to enhance the bearing capacity and crack resistance of the concrete structure.
[0061] According to design requirements, various openings are left on the concrete slab, such as equipment openings, pipeline openings, etc.
[0062] All kinds of pipelines and embedded parts are buried in the concrete slab according to the design requirements to provide convenience for subsequent construction.
[0063] The construction area is divided into a plurality of parallel construction blocks, and the casting is carried out in batches at a certain time interval, specifically divided into a first casting bin 10, a second casting bin 20, and a third casting bin 30 formed by cutting the corners of the adjacent construction blocks of the first casting bin 10 and the second casting bin 20.
[0064] By pouring in compartments, the "resistance and release" characteristics of concrete can be fully utilized to release early temperature and shrinkage stresses and reduce the occurrence of cracks.
[0065] Adjacent bins should be poured at least 7 days apart to ensure that the concrete shrinks and hardens sufficiently and to avoid harmful cracks between adjacent bins.
[0066] In an extra-long concrete structure, due to factors such as temperature and shrinkage, large stresses will be generated inside the structure. By setting up the third pouring bin 30, that is, using the cut corners of the adjacent construction blocks of the first pouring bin 10 and the second pouring bin 20 for pouring, these stresses can be effectively dispersed and balanced, and stress concentration can be reduced, thereby improving the overall stability and durability of the structure.
[0067] The third casting bin 30 serves as a bridge connecting the first casting bin 10 and the second casting bin 20. The casting process makes the entire structure more closely connected, thereby enhancing the integrity of the structure. This improvement in integrity helps to resist external loads and deformation and improve the bearing capacity of the structure.
[0068] The establishment of the third pouring bin 30 makes the construction process more reasonable and efficient. In the process of pouring in separate bins, the "resistance and release" characteristics of concrete can be fully utilized to reduce the occurrence of cracks through interval pouring and stress release. At the same time, the pouring time of the third pouring bin 30 can be adjusted according to actual conditions to ensure the construction quality and progress of the entire structure.
[0069] Compared with the traditional construction method, the improved skip bin method simplifies the construction process by setting up a third pouring bin 30 to replace part of the post-casting strips and permanent deformation joints. This not only reduces the construction difficulty and cost, but also improves the construction efficiency and quality.
[0070] By optimizing the pouring sequence and silo design, the overall performance of the concrete structure is enhanced. The connections between silos are more secure, reducing cracks and damage caused by stress concentration, and improving the durability and safety of the ultra-long concrete structure.
[0071] In a specific embodiment, step S40 includes:
[0072] Step S41 : In a first time period, the construction blocks are poured at intervals along the longitudinal direction F1 and the transverse direction F2 to form the first pouring bin 10 .
[0073] Step S42 : in a second time period, pouring the construction blocks at intervals along the longitudinal direction F1 and the transverse direction F2 to form a second pouring bin 20 interlaced with the first pouring bin 10 .
[0074] Specifically, the super-long concrete structure is divided into several construction blocks along the longitudinal direction F1 and the transverse direction F2. In the first time period, the construction blocks spaced along the longitudinal direction F1 and the transverse direction F2 are poured. In this way, a first pouring bin 10, i.e., the first batch of concrete areas where pouring is completed, can be formed.
[0075] In the second time period, the construction blocks spaced along the longitudinal direction F1 and the transverse direction F2 are continuously poured, but the poured areas at this time need to be staggered with the first pouring bin 10. In this way, a second pouring bin 20 staggered with the first pouring bin 10 can be formed.
[0076] In a specific embodiment, step S40 further includes:
[0077] S43: In a third time period, pouring a third pouring bin 30 formed by cutting corners of the first pouring bin 10 and the second pouring bin 20 adjacent to the corners of the construction block.
[0078] Specifically, the third casting bin 30 is not an independently divided construction block, but is composed of the corner cuts of the adjacent construction blocks of the first casting bin 10 and the second casting bin 20. When casting the third casting bin 30, it is necessary to accurately control the casting range to ensure an effective connection with the junction of the first and second casting bins 20.
[0079] Through the pouring of the third pouring bin 30 , cracks caused by stress concentration are further reduced, thereby improving the durability of the structure.
[0080] The addition of the third casting bin 30 enhances the integrity of the structure, making the structure more stable when bearing external loads.
[0081] The pouring arrangement in the third time period is reasonable, which makes full use of the hardening time of the first and second pouring bins 20, optimizes the construction process, and improves the construction efficiency.
[0082] In a specific embodiment, step 41 includes:
[0083] Step 411: before pouring the first pouring bin 10, a second concrete slab side form 11 is set up at the boundary of the construction block;
[0084] Step 412 : A first concrete slab corner cutting mold 12 is set up at the corner cutting of the construction block and connected to the second concrete slab side mold 11 to form a first compartment plate 13 .
[0085] Specifically, before pouring the first pouring bin 10, templates are set on the boundaries of its construction area. These templates are usually made of wood, steel or composite materials, and have sufficient strength and rigidity to withstand the lateral pressure during concrete pouring and ensure that the shape and size of the poured concrete meet the design requirements.
[0086] The erection process includes the installation, fixing and adjustment of the formwork to ensure that the position of the formwork is accurate, stable and closely fits the boundaries of the construction block.
[0087] The template is provided at the corners of the adjacent construction blocks of the first casting bin 10 and the second casting bin 20. The first concrete slab corner cutting mold 12 also needs to have sufficient strength and rigidity to withstand the lateral pressure during concrete pouring and ensure that the shape and size of the concrete at the corner cutting part meet the design requirements.
[0088] The first concrete slab corner cutter mold 12 needs to be tightly connected to the erected second concrete slab side mold 11 to form an integral first compartment plate 13. This connection is usually achieved by bolts, clamps or other connectors to ensure the stability and integrity of the template system.
[0089] In a specific embodiment, step 41 further includes:
[0090] Step 413: Water-stopping members are provided at the construction block boundaries between the first casting bin 10 and the second casting bin 20 to take water-stopping measures and limiting members are provided to limit the lateral direction of the boundary concrete.
[0091] In this embodiment, the water stop member is a water stop steel plate or a rubber water stop.
[0092] Prevent moisture from penetrating the concrete joints to ensure the waterproof performance of the structure. It is indispensable to install waterstops in underground structures or areas that require waterproofing.
[0093] The main function of waterstops is to prevent water from penetrating into concrete joints and ensure the waterproof performance of the structure. It is indispensable to install waterstops in underground structures or areas that require waterproofing.
[0094] Waterstop steel plates have high strength and rigidity, can effectively resist groundwater pressure and soil pressure, and are suitable for areas with high waterproofing requirements.
[0095] The rubber waterstop has good elasticity and aging resistance, and can adapt to the slight deformation of the concrete joints to ensure long-term and effective waterproofing effect.
[0096] The main function of the restriction is to limit the lateral flow of the boundary concrete, ensuring that the concrete does not exceed the predetermined boundary range when pouring. At the same time, they can also enhance the structural integrity of the concrete joints to a certain extent. In this implementation, the restriction is a wire mesh or a quick-close mesh. The restriction not only plays a role in limiting the lateral flow of concrete, but also naturally forms the boundary of the compartment.
[0097] Steel wire mesh has high strength and rigidity, and can effectively block the lateral flow of concrete. It comes in various forms and can be selected according to specific construction needs.
[0098] The quick-close mesh is a mesh material that is easy to install and remove. It can quickly form a dividing boundary and be easily removed after pouring. It can also effectively restrict the lateral flow of concrete.
[0099] For concrete slabs on ground floors, there is usually no need to consider waterproofing (unless there are special requirements), so waterstop strips or waterstop steel plates are not required.
[0100] In a specific embodiment, step 42 further includes:
[0101] Step 421: before pouring the second pouring bin 20, the boundary of the first pouring bin 10 is used as the third concrete slab side form 21;
[0102] Step 422 : A second concrete slab corner cutting mold is set up at the corner of the construction block and connected to the boundary of the first casting bin 10 to form a second bin plate 22 .
[0103] Using the boundary of the first casting bin 10 as the side form means that no additional formwork needs to be installed to define this boundary, thereby saving materials and time.
[0104] The corners with non-right angles or special angles formed in the construction area due to the building shape, functional requirements, etc.
[0105] The second compartment plate 22 is a concrete slab to be poured, which is formed by combining the boundary of the first pouring compartment 10 and the second concrete slab cutting corner mold.
[0106] In a specific embodiment, step 43 further includes:
[0107] Step 431: The first concrete slab corner cutout and the second concrete slab corner cutout form four corners to form a rectangle, which is the third pouring area 31 of the third pouring bin 30.
[0108] Specifically, the template provided to form a specific shape (such as a corner of a rectangle) before or during the pouring of the first pouring bin 10. It usually has a geometric profile corresponding to the desired shape and can be firmly fixed in the construction area.
[0109] The corner cutter of the second concrete slab corresponds to the first concrete slab corner cutter 12, which is a template provided for a specific corner of the second casting bin (i.e., the second concrete slab) adjacent to the first casting bin 10. It also has a precise geometric shape and needs to be precisely docked with the first concrete slab corner cutter 12.
[0110] When the first concrete slab corner cutting mold 12 and the second concrete slab corner cutting mold are respectively installed at corresponding positions in the construction area, they jointly form four corners. The four corners jointly define a rectangular third casting area 31, that is, the boundary of the third casting bin 30.
[0111] The rectangular area formed by the above four corners is the specific pouring position of the third pouring bin 30. Its shape, size and position directly determine the concrete shape and quality of the third pouring bin 30.
[0112] In a specific embodiment, step S40 also includes: step S44: pouring in adjacent time periods needs to be greater than 7 days.
[0113] The time period for pouring concrete in two adjacent pouring bins. In the skip bin method of construction, these time periods are consecutive, but not closely connected. Instead, reasonable intervals are determined based on the properties of the concrete, ambient temperature, humidity and other conditions.
[0114] Pouring needs to be more than 7 days: This is a specific time interval requirement, which means that after the concrete pouring of one pouring bin is completed, it is necessary to wait at least 7 days before pouring the adjacent pouring bin. This time interval is an empirical value based on scientific principles such as concrete strength growth and stress release. Before pouring, the concrete in each bin has enough time to release internal stress and stabilize the temperature, thus avoiding problems such as large temperature gradient and stress concentration caused by continuous pouring.
[0115] In a specific embodiment, step S40 further includes: step S45: the sides of the construction blocks are equal in length, and the cutting angle is less than 1 / 2 of the side length of the construction blocks.
[0116] When dividing the construction blocks, the side lengths of each block should be equal or similar. This is conducive to the standardization and regularization of the construction process, reducing the construction difficulty and cost increase caused by different block sizes. At the same time, construction blocks with equal side lengths are also more conducive to achieving uniform distribution of concrete stress and improving the overall stability of the structure.
[0117] The requirement for template cutting accuracy is that the cutting angle should be less than 1 / 2 of the side length of the construction block. In the skip bin construction method, the cutting angle refers to the specific angle part cut on the template to achieve the connection between the construction blocks. The cutting angle is required to be less than 1 / 2 of the side length of the construction block and should be designed to be about 2 to 3 meters, mainly to avoid the third casting bin being too large and affecting the subsequent construction of other types of work.
[0118] "Implementing the pretreatment process" includes: implementing the processes of foundation leveling, cushion pouring, waterproofing construction, edge measurement, and line laying. The pretreatment process can be implemented using existing technologies and will not be described one by one in this application.
[0119] The above is only an implementation method of the present application. It should be pointed out that a person skilled in the art can make improvements without departing from the inventive concept of the present application, but these improvements are within the scope of protection of the present application.
Claims
1. An improved skipping method for efficient and high-quality construction of ultra-long concrete structures, characterized in that: Steps include: Set up the construction area; performing a pre-processing process to form a construction area including a plurality of construction blocks arranged side by side and in parallel; Setting up a first concrete slab side formwork at the boundary of the construction area and performing preliminary construction in the casting area; The construction blocks are poured at intervals and divided into three time periods for batch pouring to form three pouring bins; the three pouring bins include: a first pouring bin, a second pouring bin and a third pouring bin formed by the cut corners of the adjacent construction block corners of the first pouring bin and the second pouring bin.
2. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 1 is characterized in that: The step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" includes: In a first time period, pouring the construction blocks spaced longitudinally and transversely to form the first pouring bin; In the second time period, the construction blocks spaced apart in the longitudinal and transverse directions are cast to form a second casting bin interlaced with the first casting bin.
3. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 2 is characterized in that: The step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes: In a third time period, a third casting bin formed by the cut corners of the first casting bin and the second casting bin adjacent to the corners of the construction blocks is cast.
4. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 2 is characterized in that: The step of "casting the construction blocks longitudinally and transversely at intervals in the first time period to form the first casting bin" includes: Before the first casting bin is cast, a second concrete slab side form is erected at the boundary of the construction block; A first concrete slab corner cutting mold is erected on the construction block corner cutting and connected to the second concrete slab side mold to form a first compartment plate.
5. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 2 is characterized in that: The step of "casting the construction blocks longitudinally and transversely at intervals in the first time period to form the first casting bin" also includes: Water-stopping members are provided at the boundaries of the construction areas of the first casting bin and the second casting bin to provide water-stopping measures and limiting members are provided to limit the lateral direction of the boundary concrete.
6. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 2 is characterized in that: The step of "in the second time period, pouring the construction blocks at intervals in the longitudinal and transverse directions to form a second pouring bin staggered with the first pouring bin" includes: Before pouring the second pouring bin, the boundary of the first pouring bin is used as the side form of the third concrete slab; A second concrete slab corner cutting mold is set up at the corner of the construction block and connected to the boundary of the first casting bin to form a second partition slab.
7. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 3 is characterized in that: The step of "casting a third casting bin formed by the cut corners of the first casting bin and the second casting bin adjacent to the corners of the construction block in the third time period" includes: The four corners formed by the cutting corners of the first concrete slab and the cutting corners of the second concrete slab form a rectangle, which is the third casting area of the third casting bin.
8. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 1 is characterized in that: The step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes: The pouring time in adjacent time periods must be greater than 7 days.
9. The improved skipping method for efficient and high-quality construction of ultra-long concrete structures according to claim 1 is characterized in that: The step of "casting the construction block at intervals and casting in batches in three time periods to form three casting bins" also includes: The sides of the construction blocks are equal in length, and the size of the cut corners is less than 1 / 2 of the side length of the construction blocks.
10. The improved skipping method for high-efficiency and high-quality construction of ultra-long concrete structures according to claim 1 is characterized in that: The step "implementing a pre-treatment process" includes: Implement processes such as foundation leveling, cushion layer pouring, waterproofing construction, boundary line measurement, and line laying.