External shuttle cabin device for super-large-diameter slurry shield center cone and center cone entering and exiting method

By designing a shuttle cabin device external to the central cone in the shield tunnel project, the connection and pressure balance between the human cabin and the central cone are achieved, which solves the problem that maintenance personnel cannot safely enter the central cone, improves the safety and efficiency of central cone maintenance, and ensures This ensures the normal progress of shield tunneling.

CN118855486APending Publication Date: 2024-10-29CHINA RAILWAY TUNNEL GROUP CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410806067.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-21
Publication Date
2024-10-29

AI Technical Summary

Technical Problem

In the shield tunnel project, it is difficult to safely inspect the center cone of the shield machine with existing technology, which causes the cutter seat and cutter barrel to retreat, and the flushing pipeline to wear through and leak slurry, affecting the normal tunneling of the shield.

Method used

Design an extra-large-diameter mud-water shield center cone external shuttle cabin device. By setting up a shuttle pipeline between the man cabin and the center cone, the man cabin and the center cone are connected. The communication valve is used to balance the pressure to ensure the safe entry of maintenance personnel. Maintenance work.

Benefits of technology

It improves the safety and maintenance efficiency of the center cone operation, avoids fluctuations in mud level, and ensures the normal operation of the shield cutterhead's normal pressure tool changing operation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118855486A_ABST
    Figure CN118855486A_ABST
Patent Text Reader

Abstract

The invention discloses an external shuttle cabin device for a super-large-diameter slurry shield center cone and a center cone entering and exiting method. The technical problem that in the prior art, maintainers cannot enter the center cone safely is solved. The device mainly comprises a human cabin and a shuttling pipeline, wherein one end of the shuttling pipeline is correspondingly communicated with the human cabin; the other end of the shuttling pipeline is correspondingly communicated with the central cone; a communicating valve for balancing the pressure between the shuttling pipeline and the central cone is arranged on the central cone; the human cabin is correspondingly provided with a pressure gauge and an air pressure adjusting mechanism. The shuttle pipeline is erected between the man cabin and the central cone, so that the man cabin is communicated with the central cone, an operator can enter the central cone from the man cabin under pressure for operation, the operation safety of the central cone is greatly improved, the maintenance operation efficiency of the central cone is improved, and normal operation of normal-pressure cutter changing operation of a shield cutter head is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield tunnel engineering, and in particular to an external shuttle cabin device for a central cone of an ultra-large diameter slurry shield and a method for getting in and out of the central cone. Background Art

[0002] With the rapid development of economy and society, large-diameter shield tunnel projects are becoming more and more common. Large diameter, long distance, high water pressure, deep burial and crossing complex geology are the mainstream development direction of shield construction technology. However, the various safety risks faced in construction are becoming more and more severe, especially in highly sensitive working environment areas. Complex and unfavorable strata such as uneven hardness and broken zones have brought greater challenges to the construction of large-diameter slurry shield.

[0003] During the construction process of shield machines in unevenly hard and soft strata, due to the development of geological structures, there are unfavorable geological conditions such as karst and broken strata. Therefore, it is necessary to frequently enter the warehouse to check and replace the cutters during tunnel excavation. Considering the ground buildings (structures), working environment and the efficiency and safety of the cutter changing operation, the shield machines currently usually use the normal pressure cutter changing method.

[0004] In full-section hard rock strata that are soft on top and hard on the bottom, the overall strength of the slurry shield tunneling face will be uneven due to the large fluctuations in rock surface hardness. The high hardness and strength of the rock strata and the large vibration of the cutterhead may cause the flushing pipeline, cutter barrel, cutter seat bolts and other structures in the center cone of the shield to loosen. With long-term excavation, there is a problem of wear of the flushing pipeline. If the shield tunneling process is not properly inspected or maintained, the cutter seat and cutter barrel will retreat, and the flushing pipeline will be worn through and leak slurry, which will cause the center cone to be filled with slurry and make it impossible to carry out normal pressure cutter changing operations, thus affecting the normal excavation of the shield.

[0005] However, the existing shield machine brings great difficulties and challenges to the maintenance work of the center cone because personnel cannot safely enter the center cone.

[0006] The information disclosed in this background technology section is only used to deepen the understanding of the background technology of the present disclosure, and should not be regarded as acknowledging or suggesting in any form that the information constitutes the prior art known to those skilled in the art. Summary of the invention

[0007] In view of at least one of the above technical problems, the present invention provides an external shuttle cabin device for the central cone of an ultra-large diameter slurry shield and a method for entering and exiting the central cone. By setting up a shuttle pipeline between the man cabin and the central cone, the man cabin and the central cone are connected, so that maintenance personnel can enter the central cone under pressure from the man cabin to perform operations, which solves the problem in the prior art that maintenance personnel cannot safely enter the central cone, greatly improves the safety of the central cone operation, and improves the efficiency of the central cone maintenance operation, thereby ensuring the normal operation of the shield cutter head at normal pressure.

[0008] According to one aspect of the present disclosure, there is provided an external shuttle cabin device for the central cone of an ultra-large diameter slurry shield, comprising a man cabin and a shuttle pipeline having one end connected to the man cabin; the other end of the shuttle pipeline is connected to the central cone; a connecting valve for balancing the pressure between the shuttle pipeline and the central cone is provided on the central cone; and a pressure gauge and an air pressure regulating mechanism are provided to the man cabin.

[0009] In some embodiments of the present disclosure, the shuttle pipeline is a steel structure, the top of which is correspondingly connected to the top of the shield machine through at least one pulling member, and the bottom of which is provided with a support frame for supporting the shuttle pipeline.

[0010] In some embodiments of the present disclosure, the pulling member is a hand winch, and the support frame is an H-shaped steel.

[0011] In some embodiments of the present disclosure, the shuttle pipeline is connected to the central cone and the human cabin with corresponding bolts, and sealing rings are provided at corresponding connecting end surfaces of the shuttle pipeline, the central cone and the human cabin.

[0012] In some embodiments of the present disclosure, a normally closed central cone door is provided at the corresponding connection between the central cone and the shuttle pipeline, and a normally closed human cabin door is provided at the corresponding connection between the human cabin and the shuttle pipeline.

[0013] In some embodiments of the present disclosure, the connecting valve is a rigid ball valve, one end of which is connected to the interior of the central cone and the other end of which is connected to the interior of the shuttle pipeline.

[0014] According to another aspect of the present disclosure, a center cone entry and exit method is provided, which is implemented based on the above shuttle cabin device, comprising: S1: One end of the shuttle pipeline is sealed and connected to the center cone, and the other end is sealed and connected to the man cabin; S2: The maintenance personnel enters the shuttle pipeline and pressurizes the center cone to a set pressure; S3: After the pressurization of the center cone stops, pressurize the man cabin and the shuttle pipeline to the same pressure as the pressure in the center cone, open the connecting valve between the shuttle pipeline and the center cone, and balance the pressure among the man cabin, shuttle pipeline and center cone; S4: Open the center cone hatch at the connection between the center cone and the shuttle pipeline and enter the center cone to observe the mud level in the center cone. After confirming that the mud level is stable, the maintenance personnel start the maintenance work in the center cone. S5: After the maintenance work in the center cone is completed, the maintenance personnel enter the shuttle pipeline, close the center cone door and then close the connecting valve to release the pressure in the center cone and the cabin, and the maintenance personnel evacuate the cabin.

[0015] In some embodiments of the present disclosure, in step S2, the set pressure causes the mud level in the center cone to drop to the upper part of the center flushing pipe.

[0016] One or more technical solutions provided in the embodiments of the present application have at least any of the following technical effects or advantages: 1. By setting up a shuttle pipeline between the man cabin and the center cone, the man cabin and the center cone are connected, so that maintenance personnel can enter the center cone under pressure from the man cabin to perform center cone maintenance operations, which solves the problem that maintenance personnel cannot enter the center cone in the prior art, greatly improves the safety of center cone operations, and improves the efficiency of center cone maintenance operations, thereby ensuring the normal pressure change of the shield cutter head.

[0017] 2. A connecting valve is installed at the corresponding connection between the center cone and the shuttle pipeline. Before personnel enter the center cone, the pressure inside the center cone can be balanced with the pressure inside the shuttle pipeline, avoiding the problem of fluctuation of mud level in the center cone due to different pressures when the center cone door is opened directly, thus ensuring the safety of operation.

[0018] 3. Several lifting rings are provided on the top of the shuttle pipeline, which are connected to the hand winch on the top of the shield machine. H-shaped steel is provided at the bottom of the shuttle pipeline to support the shuttle pipeline. The shuttle pipeline is small in size, which makes it easy to lift and disassemble the shuttle pipeline. It can be installed and used at any time, and is highly practical. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 This is a schematic structural diagram of an external shuttle cabin device connected to the central cone of an ultra-large diameter slurry shield in one embodiment of the present application.

[0020] Figure 2 Schematic diagram of the structure of the central cone in one embodiment of the present application.

[0021] Figure 3 This is a construction scene diagram of the shuttle pipeline in one embodiment of the present application.

[0022] In the above figures, 1 is the central cone, 2 is the man cabin, 3 is the shuttle pipeline, and 4 is the connecting valve. DETAILED DESCRIPTION

[0023] In order to better understand the technical solution of the present application, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0024] In the description of this application, it should be understood that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", "vertical", "horizontal", "clockwise", "counterclockwise", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing this application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as a limitation on this application. The "connection" and "coupling" involved in this application, unless otherwise specified, include direct and indirect connections (couplings).

[0025] Unless otherwise specified, the components, structures, mechanisms, sensors and other devices involved in the following embodiments are conventional commercially available products.

[0026] The embodiment of the present application solves the problem in the prior art that maintenance personnel cannot safely enter the center cone by providing an external shuttle cabin device for the center cone of an ultra-large diameter slurry shield and a method for entering and exiting the center cone, thereby achieving communication between the man cabin and the center cone, so that maintenance personnel can enter the center cone under pressure from the man cabin to perform operations.

[0027] Embodiment 1 This example discloses a super-large diameter slurry shield central cone external shuttle cabin device, see Figure 1 , including a man cabin 2 and a shuttle pipe 3; one end of the shuttle pipe 3 is connected to the man cabin 2, and the other end is connected to the center cone 1. Maintenance personnel can safely enter the center cone under pressure from the man cabin to perform center cone maintenance operations, which greatly improves the safety of center cone operations and improves the efficiency of center cone maintenance operations.

[0028] See also Figure 1 The man cabin 2 includes a main cabin and an auxiliary cabin. The main cabin is connected to the shuttle pipeline 3 accordingly. A man cabin door is provided at the corresponding connection point. The man cabin door is closed when there is no need to enter the center cone for operation to ensure the safety of operation in the man cabin; an air pressure regulating mechanism is provided in the man cabin 2 to adjust the pressure in the man cabin and the shuttle pipeline. Before entering the center cone for operation, the pressure in the man cabin and the shuttle pipeline needs to be adjusted to the same as the pressure in the center cone. After the center cone operation is completed, the pressure in the man cabin is adjusted to the same as the atmospheric pressure; at the same time, ventilation can be achieved in the man cabin as needed, and silencers are provided at the inlet and exhaust ports of the man cabin to reduce the noise of the internal and external environment.

[0029] In addition, man cabin 2 is also equipped with a pressure gauge and a pressure recorder to monitor the pressure in the man cabin at any time to ensure the safety of personnel operations; man cabin 2 is also equipped with a temperature and humidity gauge, lighting mechanism, oxygen breathing equipment, heating equipment, telephone, diving intercom host, manual speaker, fire industrial water sprinkler system and other auxiliary equipment to ensure normal operation of personnel.

[0030] See also Figure 1 , Figure 3 The shuttle pipeline 3 is a steel structure, and its two ends are fixedly connected to the man cabin 2 and the center cone 1 respectively by high-strength bolts. Sealing rings are provided at the corresponding connection end faces to enhance the sealing effect of the corresponding connections, ensuring that the higher pressure in the shuttle device will not leak when the center cone is operating, thereby improving the safety of the center cone operation; an H-shaped steel is provided at the bottom of the shuttle pipeline 3 to fix and support the shuttle pipeline 3, and a number of lifting rings are provided at the top of the shuttle pipeline 3. A number of hand winches corresponding to the positions of the lifting rings are provided at the top of the shield, and the hand winches are connected to the lifting rings accordingly. The H-shaped steel and the hand winch are used together to achieve stable installation of the shuttle pipeline; in addition, the shuttle pipeline is small in size, and the use of hand winches and H-shaped steel makes the shuttle pipeline hanging and assembly simple and convenient, and the shuttle device is flexible to use and highly practical.

[0031] See also Figure 2 A center cone hatch is provided at the corresponding connection between the center cone 1 and the shuttle pipeline 3 for the passage of operating personnel. A sealing ring is provided at the center cone hatch to achieve sealing inside the center cone. A connecting valve 4 is also provided at the corresponding connection between the center cone 1 and the shuttle pipeline 3 to connect the center cone 1 and the shuttle pipeline 3. The connecting valve 4 is a rigid ball valve. Opening the connecting valve before personnel enter the center cone can achieve pressure balance between the center cone, the shuttle pipeline and the human cabin, avoiding the problem of fluctuation of the mud level in the center cone due to different pressures caused by directly opening the center cone hatch, thereby ensuring operation safety.

[0032] Embodiment 2 This example discloses a method for entering and exiting the center cone, see Figures 1 to 3 , implemented based on the shuttle cabin device in the first embodiment, including: S1: One end of the shuttle pipeline is fixedly and sealedly connected to the center cone, and the other end is fixedly and sealedly connected to the man cabin, and the shuttle pipeline is fixed and supported by a hand winch and H-shaped steel.

[0033] S2: Open the cabin door, and the maintenance personnel enter the shuttle pipeline and pressurize the center cone to observe the pressure inside the center cone. When the mud level in the center cone drops to the upper part of the center flushing pipe, the personnel can enter the center cone under pressure to operate. Therefore, stop pressurizing the center cone when the mud level in the center cone drops to the upper part of the center flushing pipe.

[0034] S3: After the pressurization of the center cone stops, the pressure in the man cabin and the shuttle pipeline is pressurized to be consistent with the pressure in the center cone through the air pressure regulating mechanism in the man cabin; the connecting valve between the shuttle pipeline and the center cone is opened to balance the pressure among the man cabin, the shuttle pipeline and the center cone.

[0035] S4: After the air pressure is balanced, open the center cone hatch and enter the center cone to observe the mud level in the center cone. After confirming that the mud level does not rise, that is, the air pressure in the center cone is stable and the center cone is in a safe state, the maintenance personnel begin maintenance work in the center cone.

[0036] S5: After the maintenance work in the center cone is completed, the maintenance personnel enter the shuttle pipeline and close the center cone cabin door, close the connecting valve, and then release the pressure in the center cone and the cabin, and the maintenance personnel evacuate the cabin.

[0037] Through the external shuttle cabin device of the center cone, maintenance personnel can safely enter and exit the center cone, which greatly reduces the construction risk of the center cone and improves the efficiency of center cone leakage treatment, thereby restoring the center cone normal pressure cutter change and ensuring normal excavation of the shield.

[0038] Although some preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications that fall within the scope of the present application.

[0039] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the inventive concept. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A super-large diameter slurry shield central cone external shuttle cabin device, characterized in that: It includes a human cabin and a shuttle pipeline with one end connected to the human cabin; the other end of the shuttle pipeline is connected to the center cone; the center cone is provided with a connecting valve for balancing the pressure between the shuttle pipeline and the center cone; the human cabin is provided with a pressure gauge and an air pressure regulating mechanism.

2. The shuttle cabin device according to claim 1, characterized in that: The shuttle pipeline is a steel structure, the top of which is correspondingly connected to the top of the shield machine through at least one pulling member, and the bottom of which is provided with a support frame for supporting the shuttle pipeline.

3. The shuttle cabin device according to claim 2, characterized in that: The pulling member is a hand chain hoist, and the support frame is an H-shaped steel.

4. The shuttle cabin device according to claim 1, characterized in that: The shuttle pipeline is connected to the central cone and the man cabin with corresponding bolts respectively, and sealing rings are respectively provided at the corresponding connecting end surfaces of the shuttle pipeline, the central cone and the man cabin.

5. The shuttle cabin device according to claim 4, characterized in that: A normally closed central cone door is provided at the corresponding connection between the central cone and the shuttle pipeline, and a normally closed human cabin door is provided at the corresponding connection between the human cabin and the shuttle pipeline.

6. The shuttle cabin device according to claim 1, characterized in that: The connecting valve is a rigid ball valve, one end of which is connected to the interior of the central cone and the other end of which is connected to the interior of the shuttle pipeline.

7. A method for entering and exiting a center cone, characterized in that: The shuttle cabin device according to claim 1 is implemented, comprising: S1: One end of the shuttle pipeline is sealed and connected to the center cone, and the other end is sealed and connected to the man cabin; S2: The maintenance personnel enters the shuttle pipeline and pressurizes the center cone to a set pressure; S3: After the pressurization of the center cone stops, pressurize the man cabin and the shuttle pipeline to the same pressure as the pressure in the center cone, open the connecting valve between the shuttle pipeline and the center cone, and balance the pressure among the man cabin, shuttle pipeline and center cone; S4: Open the center cone hatch at the connection between the center cone and the shuttle pipeline and enter the center cone to observe the mud level in the center cone. After confirming that the mud level is stable, the maintenance personnel start the maintenance work in the center cone. S5: After the maintenance work in the center cone is completed, the maintenance personnel enter the shuttle pipeline, close the center cone door and then close the connecting valve to release the pressure in the center cone and the cabin, and the maintenance personnel evacuate the cabin.

8. The center cone entry and exit method according to claim 7, characterized in that: In step S2, the set pressure causes the mud level in the center cone to drop to the upper part of the center flushing pipe.