Power system modeling method
Collect and set power system data through the DIgSILENT PowerFactory tool for steady-state and transient verification, which solves the problem of inaccurate external power grid simulation in power system modeling, improves the accuracy and reliability of the model, and ensures the stability of the power grid operation. nature and scientific evaluation.
Patent Information
- Application Number
- CN202411006558.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-10-29
AI Technical Summary
Common power system modeling methods cannot ensure the simulation accuracy of the external power grid background environment, affecting the accuracy of the overall modeling.
The DIgSILENT PowerFactory modeling tool is used to collect and set power system data and parameters, including specific parameters of generators, transformers, lines and loads, for steady-state and transient verification to ensure the accuracy and reliability of the model.
It improves the accuracy of the load model and power system unit model, ensures the reliability of external grid simulation and the stability of grid operation, complies with industry standards, and provides a scientific basis for evaluation and planning.
Smart Images

Figure CN118868071A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power systems, and in particular relates to a power system modeling method. Background Art
[0002] The power system is an indispensable infrastructure in modern society. It is responsible for transmitting the electric energy generated by power plants to various substations through high-voltage transmission lines, and then sending it to end users through distribution lines after the voltage is reduced by transformers. The entire system includes five links: power generation, transmission, transformation, distribution and power consumption. In the power generation link, electric energy is mainly composed of thermal power generation, hydropower generation, nuclear power generation, and renewable energy such as wind power and solar energy that have developed rapidly in recent years. Various power generation methods have their own unique advantages and limitations, and together provide stable and reliable electric energy for the power system. The transmission link is to transmit the electric energy generated by the power plant to a distant substation through high-voltage transmission lines. This process requires solving problems such as voltage stability, frequency control and dynamic stability of the power system. The erection and operation of transmission lines are an important part of the power system, which directly affects the safe, stable and economic operation of the power system. The substation link is to reduce the voltage of high-voltage electric energy through transformers for industrial and residential use. The transformer is a key equipment in the substation link. It can not only realize voltage conversion, but also isolate and filter the power system to ensure the quality of electric energy. The power distribution link is to deliver the power output from the substation to the end user through the distribution line. The problem that needs to be solved in this link is to ensure the reliability and quality of power supply, while reducing line losses and improving distribution efficiency. Power system modeling is to use specific tools and methods to simulate and reproduce the various components of the power system in detail. These models are crucial for analyzing, designing and optimizing power systems.
[0003] However, common power system modeling methods cannot ensure the accuracy of simulation of the external power grid background environment, which affects the accuracy of the overall modeling. Summary of the invention
[0004] The purpose of the present invention is to provide a power system modeling method in order to solve the above-mentioned problems.
[0005] The technical solution adopted by the present invention is as follows: a method for modeling a power system, comprising the following steps: S1: First, determine the modeling objectives through analysis and investigation; S2: Collect the data and parameters required in the power system modeling process; S3: Select the appropriate DIgSILENTPowerFactory modeling tool to build the power system model; S4: Create a project first: Create a new project in PowerFactory; S5: Establish the network: Use the single-line diagram editor to draw the single-line diagram of the power grid, including generators, transformers, lines, and load elements; S6: Define component parameters: Assign specific parameters to each component, including the rated power of the generator, the transformation ratio of the transformer, and the resistance and reactance of the line; S7: Set control device: set control logic for protection devices and automatic devices in the power grid; S8: Load modeling: Select a suitable load model according to the load characteristics and set the corresponding parameters; S9: Perform model verification, through steady-state verification: run steady-state analysis, compare simulation results with actual grid operation parameters, including node voltages and line flows; through transient verification: verify the dynamic response of the model by simulating grid transient processes, including short-circuit faults S10: After verification, the entire power system modeling method can be completed.
[0006] In a preferred embodiment, in step S1, the modeling objectives include: Functional objectives: optimize grid operation, improve power supply reliability, and reduce line losses.
[0007] Performance goal: Simulate the performance and fault response of the power grid under different load conditions.
[0008] Economic objectives: cost-benefit analysis, investment payback period forecast.
[0009] In a preferred embodiment, in step S2, the data and parameters include: Power generation information: type, capacity, efficiency, start-up time, and downtime of various generators; Grid information: length, type, capacity, resistance and reactance parameters of transmission lines.
[0010] Substation information: transformer type, capacity, number of phases, and connection group.
[0011] Power distribution information: distribution network structure, line parameters, and distribution transformer parameters.
[0012] Load information: load characteristics, maximum load, and load change patterns of different users.
[0013] In a preferred embodiment, in step S4, in the process of creating a new project in PowerFactory: open the software and select "New Project". Enter the project name and description. Select the project storage location. Set the basic parameters of the project, including the reference voltage and reference power.
[0014] In a preferred embodiment, in the step S5, during the process of using the single-line diagram editor: Draw a network diagram: drag the generator, transformer, line, and load icons from the component library to the editing area. Connect components: use the line segment tool to connect the components to form a complete power grid topology. Set nodes: assign a unique node number to each connection point. Add comments: add comments to important components or nodes for easy identification.
[0015] In a preferred embodiment, in step S6, specific parameters are assigned to each component during the process of defining component parameters: Generator: set rated power, rated voltage, starting characteristics, and speed regulator parameters. Transformer: input ratio, short-circuit impedance, connection group, and rated capacity. Line: define resistance, reactance, capacitance, and ground conductivity parameters. Load: set active power, reactive power, and power factor according to the actual measured or estimated load characteristics.
[0016] In a preferred embodiment, in the step S7, the control logic is set for the protection device and the automatic device in the power grid during the process of setting the control device: Protection device: define the action characteristics of overcurrent protection, distance protection, and differential protection. Automatic device: set the control logic of automatic reclosing, automatic switching capacitors, and generator excitation system. Regulator: configure the parameters of the voltage regulator and frequency regulator to simulate the regulation process in the system.
[0017] In a preferred embodiment, in step S8, during the load modeling process, a suitable load model is selected according to the load characteristics, and corresponding parameters are set: Static load model: set a constant power, constant current or constant impedance model. Motor load model: input the starting mode, rated power, and efficiency parameters of the motor. Dynamic load model: set the dynamic change characteristics of the load according to the time series data of the load.
[0018] In a preferred embodiment, in step S5, when simulating the external power grid, the system impedance can be simulated in series with the ideal voltage source based on the equivalent calculation of the PSD-BPA actual power grid model, or the technical route of converting the BPA actual large power grid data into the DIgSILENT / PF model can be used for processing. The accuracy of the power grid background environment simulation during power system modeling is ensured by equivalent or data conversion. The sequence components of the voltage, active power, and reactive power at the grid connection point are obtained by measurement and sent to the field-level controller as input, the control mode of the field control is selected, and the power command is issued to each unit to realize the static control function of the power system grid connection point flow control, and also realize the dynamic control function of the power system AGC / AVC / primary frequency modulation, wherein the primary frequency modulation is modeled according to the latest requirements of Q / CSG 1211017-2018.
[0019] In a preferred embodiment, in step S8, the power system transmission cable, power system step-up transformer, and power system on-site collection line are all constructed according to the parameters and topology of the actual power system, and the internal structure and electrical parameters of the power system, as well as the electrical coupling characteristics between different units, are constructed in detail. e) Construct a complete mechanical transmission and electrical integration power system unit model suitable for primary frequency regulation capability. Compared with the standard 4A power system unit model that comes with the software, this study provides a detailed back-to-back converter electrical part and optimized control function. The fault ride-through performance of the power system unit is in accordance with the requirements of NB / T31053-2014 "Modeling and Verification Method for Low Voltage Ride-through of Power System Units", combined with the field recording and measured data, to verify the accuracy of the unit model.
[0020] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are: 1. In the present invention, the accuracy of the load model is improved: by selecting a suitable load model and setting corresponding parameters, the operating characteristics of the actual load can be simulated more accurately. This helps to predict the voltage level, power demand and system stability of the power grid in the power system operation simulation. The reliability of the external power grid simulation is improved: using PSD-BPA or BPA actual large power grid data for equivalent calculation or data conversion can ensure the simulation accuracy of the external power grid background environment. This is crucial for evaluating the power system grid connection point flow control and realizing the dynamic control functions of automatic power generation control, automatic voltage control and primary frequency regulation. Through the integrated simulation of the power system, the internal structure and electrical parameters of the power system are constructed in detail, including transmission cables, step-up transformers and on-site collection lines, and considering the electrical coupling characteristics between different units, the operating behavior of the power system can be simulated more accurately, especially when multiple power systems influence each other.
[0021] 2. In the present invention, the accuracy of the power system unit model is improved: a complete mechanical transmission and electrical integrated power system unit model is constructed, and the control function is optimized, which can improve the simulation accuracy of the model on the dynamic behavior of the power system unit. This is crucial for evaluating the fault ride-through performance of the power system unit and the stability of the power grid. Model development that meets industry standards: Model development is carried out in accordance with industry standards such as Q / CSG 1211017-2018 and NB / T31053-2014 to ensure that the model is not only accurate, but also complies with industry specifications, thereby enhancing the credibility and applicability of the model. Model verification and calibration: The accuracy of the model is verified in combination with field recording and measured data to ensure the effectiveness and reliability of the model, providing a solid scientific basis for the operation and planning of the power system. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the process principle of the present invention. DETAILED DESCRIPTION
[0023] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0024] Reference Figure 1 , Example: A power system modeling method comprises the following steps: S1: First, determine the modeling objectives through analysis and investigation; S2: Collect data and parameters; S3: Select the appropriate DIgSILENTPowerFactory modeling tool to build the power system model; S4: Create a project first: Create a new project in PowerFactory; S5: Establish the network: Use the single-line diagram editor to draw the single-line diagram of the power grid, including generators, transformers, lines, loads and other components; S6: Define component parameters: assign specific parameters to each component, such as the rated power of the generator, the transformation ratio of the transformer, the resistance and reactance of the line; S7: Set control device: set control logic for protection devices, automatic devices, etc. in the power grid; S8: Load modeling: Select a suitable load model according to the load characteristics and set the corresponding parameters; S9: Perform model verification, through steady-state verification: run steady-state analysis, compare simulation results with actual grid operation parameters, including node voltages and line flows; through transient verification: verify the dynamic response of the model by simulating grid transient processes, including short-circuit faults S10: After verification, the entire power system modeling method can be completed.
[0025] In step S1, the modeling objectives include: Functional objectives: optimize grid operation, improve power supply reliability, and reduce line losses.
[0026] Performance goal: Simulate the performance and fault response of the power grid under different load conditions.
[0027] Economic objectives: cost-benefit analysis, investment payback period forecast.
[0028] In step S2, the data and parameters include: Power generation information: type, capacity, efficiency, start-up time, and downtime of various generators; Grid information: length, type, capacity, resistance and reactance parameters of transmission lines.
[0029] Substation information: transformer type, capacity, number of phases, and connection group.
[0030] Power distribution information: distribution network structure, line parameters, and distribution transformer parameters.
[0031] Load information: load characteristics, maximum load, and load change patterns of different users.
[0032] In step S4, in the process of creating a new project in PowerFactory: Open the software and select "NewProject". Enter the project name and description. Select the project storage location. Set the basic parameters of the project, such as reference voltage and reference power.
[0033] In step S5, in the process of using the single-line diagram editor: Draw a network diagram: drag the generator, transformer, line, load and other icons from the component library to the editing area. Connect components: use the line segment tool to connect the components to form a complete power grid topology. Set nodes: assign a unique node number to each connection point. Add comments: add comments to important components or nodes for easy identification.
[0034] In step S6, specific parameters are assigned to each component during the process of defining component parameters: Generator: set rated power, rated voltage, starting characteristics, speed regulator parameters, etc. Transformer: input ratio, short-circuit impedance, connection group, rated capacity, etc. Line: define parameters such as resistance, reactance, capacitance and ground conductance. Load: set active power, reactive power and power factor according to the actual measured or estimated load characteristics.
[0035] In step S7, the control logic is set for the protection devices, automatic devices, etc. in the power grid during the process of setting the control device: Protection device: define the action characteristics of overcurrent protection, distance protection, differential protection, etc. Automatic device: set the control logic of automatic reclosing, automatic switching capacitors, generator excitation system, etc. Regulator: configure the parameters of the voltage regulator, frequency regulator, etc. to simulate the regulation process in the system.
[0036] In step S8, during the load modeling process, a suitable load model is selected according to the load characteristics, and corresponding parameters are set: Static load model: set a constant power, constant current or constant impedance model. Motor load model: input the motor starting method, rated power, efficiency and other parameters. Dynamic load model: set the dynamic change characteristics of the load according to the time series data of the load.
[0037] In step S5, when simulating the external power grid, the system impedance can be simulated in series with the ideal voltage source based on the equivalent calculation of the actual power grid model of PSD-BPA, or the technical route of converting the actual large power grid data of BPA into the DIgSILENT / PF model can be used for processing. The accuracy of the power grid background environment simulation during power system modeling is ensured by equivalent or data conversion. The sequence components of the voltage, active power, and reactive power at the grid connection point are obtained by measurement and sent to the field-level controller as input, the control mode of the field control is selected, and the power command is issued to each unit to realize the static control function of the power system grid connection point flow control, and also realize the dynamic control function of the power system AGC / AVC / primary frequency modulation, where the primary frequency modulation is modeled according to the latest requirements of Q / CSG 1211017-2018.
[0038] In step S8, the power transmission cable, power system step-up transformer, and power system on-site collection line must be constructed according to the parameters and topology of the actual power system, and the internal structure and electrical parameters of the power system, as well as the electrical coupling characteristics between different units, must be constructed in detail. A complete mechanical transmission and electrical integration power system unit model suitable for primary frequency regulation is constructed. Compared with the standard 4A power system unit model that comes with the software, this study provides a detailed back-to-back converter electrical part and optimized control function. The fault ride-through performance of the power system unit is in accordance with the requirements of NB / T31053-2014 "Modeling and Verification Methods for Low Voltage Ride-through of Power System Units", combined with on-site recording and measured data, to verify the accuracy of the unit model.
[0039] In the present invention, the accuracy of the load model is improved: by selecting a suitable load model and setting corresponding parameters, the operating characteristics of the actual load can be simulated more accurately. This helps to predict the voltage level, power demand and system stability of the power grid in the power system operation simulation. The reliability of the external power grid simulation is improved: using PSD-BPA or BPA actual large power grid data for equivalent calculation or data conversion can ensure the simulation accuracy of the external power grid background environment. This is crucial for evaluating the power system grid connection point flow control and realizing the dynamic control functions of automatic generation control (AGC), automatic voltage control (AVC) and primary frequency regulation. Through the integrated simulation of the power system, the internal structure and electrical parameters of the power system are constructed in detail, including transmission cables, step-up transformers and on-site collection lines, and the electrical coupling characteristics between different units are considered, which can more accurately simulate the operating behavior of the power system, especially when multiple power systems influence each other.
[0040] In the present invention, the accuracy of the power system unit model is improved: a complete mechanical transmission and electrical integrated power system unit model is constructed, and the control function is optimized, which can improve the simulation accuracy of the model on the dynamic behavior of the power system unit. This is crucial for evaluating the fault ride-through performance of the power system unit and the stability of the power grid. Model development that meets industry standards: Model development is carried out in accordance with industry standards such as Q / CSG 1211017-2018 and NB / T31053-2014 to ensure that the model is not only accurate, but also complies with industry specifications, thereby enhancing the credibility and applicability of the model. Model verification and calibration: The accuracy of the model is verified in combination with field recording and measured data to ensure the effectiveness and reliability of the model, providing a solid scientific basis for the operation and planning of the power system.
[0041] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0042] The above description enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. A power system modeling method, characterized in that: The steps include: S1: First, determine the modeling objectives through analysis and investigation; S2: Collect the data and parameters required in the power system modeling process; S3: Select the appropriate DIgSILENTPowerFactory modeling tool to build the power system model; S4: Create a project first: Create a new project in PowerFactory; S5: Establish the network: Use the single-line diagram editor to draw the single-line diagram of the power grid, including generators, transformers, lines, and load elements; S6: Define component parameters: Assign specific parameters to each component, including the rated power of the generator, the transformation ratio of the transformer, and the resistance and reactance of the line; S7: Set control device: set control logic for protection devices and automatic devices in the power grid; S8: Load modeling: Select a suitable load model according to the load characteristics and set the corresponding parameters; S9: Perform model verification, through steady-state verification: run steady-state analysis, compare simulation results with actual grid operation parameters, including node voltages and line flows; through transient verification: verify the dynamic response of the model by simulating grid transient processes, including short-circuit faults S10: After verification, the entire power system modeling method can be completed.
2. A power system modeling method according to claim 1, characterized in that: In step S1, the modeling objectives include: Functional objectives: optimize grid operation, improve power supply reliability, and reduce line losses; Performance objectives: Simulate the performance of the power grid under different load conditions and fault response; Economic objectives: cost-benefit analysis, investment payback period forecast.
3. A power system modeling method as claimed in claim 1, characterized in that: In step S2, the data and parameters include: Power generation information: type, capacity, efficiency, start-up time, and downtime of various generators; Grid information: length, type, capacity, resistance, and reactance parameters of transmission lines; Substation information: transformer type, capacity, number of phases, and connection group; Power distribution information: distribution network structure, line parameters, distribution transformer parameters; Load information: load characteristics, maximum load, and load change patterns of different users.
4. A power system modeling method as claimed in claim 1, characterized in that: In step S4, in the process of creating a new project in PowerFactory: open the software and select "New Project"; enter the project name and description; select the project storage location; set the basic parameters of the project, including reference voltage and reference power.
5. A power system modeling method as claimed in claim 1, characterized in that: In the step S5, during the use of the single-line diagram editor: draw a network diagram: drag generator, transformer, line, and load icons from the component library to the editing area; connect components: use the line segment tool to connect each component to form a complete power grid topology; set nodes: assign a unique node number to each connection point; add comments: add comments to important components or nodes.
6. A power system modeling method according to claim 1, characterized in that: In the step S6, specific parameters are assigned to each component during the process of defining component parameters: generator: set rated power, rated voltage, starting characteristics, and speed regulator parameters; transformer: input ratio, short-circuit impedance, connection group, and rated capacity; Line: define resistance, reactance, capacitance and conductance to ground parameters; Load: Set active power, reactive power, and power factor based on actual measured or estimated load characteristics.
7. A power system modeling method according to claim 1, characterized in that: In the step S7, during the process of setting the control device, the control logic is set for the protection device and the automatic device in the power grid: the protection device: defines the action characteristics of overcurrent protection, distance protection, and differential protection; the automatic device: sets the control logic of automatic reclosing, automatic switching capacitors, and generator excitation system; Regulator: Configure the voltage regulator and frequency regulator parameters to simulate the regulation process in the system.
8. A power system modeling method according to claim 1, characterized in that: In step S8, during the load modeling process, a suitable load model is selected according to the load characteristics, and corresponding parameters are set: static load model: setting a constant power, constant current or constant impedance model; motor load model: inputting the starting mode, rated power, and efficiency parameters of the motor; dynamic load model: setting the dynamic change characteristics of the load according to the time series data of the load.
9. A power system modeling method as claimed in claim 1, characterized in that: In the step S5, when simulating the external power grid, the system impedance can be obtained by simulating in series with the ideal voltage source based on the equivalent calculation of the PSD-BPA actual power grid model, or the technical route of converting the BPA actual large power grid data into the DIgSILENT / PF model can be used for processing; by means of equivalent or data conversion, the accuracy of the power grid background environment simulation during power system modeling is ensured. The sequence components of the voltage, active power, and reactive power at the grid connection point are obtained by measurement and sent to the field-level controller as input, the control mode of the field control is selected, and the power command is issued to each unit to realize the static control function of the power system grid connection point flow control, and also realize the dynamic control function of the power system AGC / AVC / primary frequency modulation, wherein the primary frequency modulation model is developed in accordance with the latest requirements of Q / CSG 1211017-2018.
10. A power system modeling method according to claim 1, characterized in that: In the step S8, the power system transmission cables, power system step-up transformers, and power system on-site collection lines are all constructed according to the parameters and topology of the actual power system, and the internal structure and electrical parameters of the power system, as well as the electrical coupling characteristics between different units are constructed in detail; e) a complete mechanical transmission and electrical integration power system unit model suitable for primary frequency regulation capability is constructed; compared with the standard 4A power system unit model that comes with the software, this study provides a detailed back-to-back converter electrical part and optimized control function.