Auxiliary assembly device for anchoring concrete sleepers
By designing an auxiliary assembly device for concrete sleepers, using the sleeve rod and feed pipe driven by the pneumatic cylinder, multiple sets of mortar injection and automatic conveying of the rail nails is achieved, which solves the problems of low efficiency and cumbersome operation in the existing technology, and improves the Anchor efficiency and quality.
Patent Information
- Application Number
- CN202411364255.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2044-09-29
AI Technical Summary
During the anchoring process of railway concrete sleepers, the existing technology is inefficient and cumbersome. Due to the fixed time limit of sulfur cement mortar, construction personnel are unable to perform anchoring operations of multiple sets of sleeper nails at the same time, resulting in a reduction in assembly efficiency.
An auxiliary assembly device was designed, including a sleeper transmission mechanism, lifting assembly, mortar injection mechanism and lathe feeding assembly. Through the pneumatic cylinder, the sleeve rod and the feeding pipe are driven by the pneumatic cylinder, multiple sets of mortar injection and automatic delivery of lathe to prevent mortar. Spill and bubbles to ensure the mortar is full.
It improves the assembly efficiency of lathe anchoring, avoids mortar overflow and bubbles, ensures anchoring quality, simplifies the operation process, and can handle the anchoring of multiple sets of sleeper lathes at the same time.
Smart Images

Figure CN118876222B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of spike anchoring, in particular to an auxiliary assembly device for anchoring a concrete sleeper. Background Art
[0002] When anchoring spikes on railway concrete sleepers, the anchoring processes generally used are the positive anchoring method and the reverse anchoring method. The positive anchoring method is only suitable for anchoring spikes on a small number of sleepers in production and processing, and the efficiency is low. In the reverse anchoring method, workers need to manually place the spike anchoring bracket in the sleeper rail groove on the anchoring pedestal, and then use a crowbar to flip the sleeper to face the bottom upward, put the spikes in the reserved holes of the sleeper, and pour the boiled sulfur cement mortar into the reserved holes. After the mortar hardens, the sleeper is flipped again to face the top upward.
[0003] In the assembly process, whether the positive anchor method or the reverse anchor method is used, the operation is cumbersome and takes a lot of time. At the same time, each time the sulfur cement mortar is filled, it is necessary to wait for a period of time to complete the solidification of the mortar before continuing the subsequent operation. When the construction workers assemble more sleepers, they fix the spikes by pouring sulfur cement mortar into the reserved holes. During the period of waiting for the cement mortar to solidify, due to the short time, the construction workers can only fill mortar into one reserved hole, and cannot assemble the spikes in the reserved holes of other sleepers, and cannot perform the anchoring operation of multiple groups of sleeper spikes at the same time, which greatly reduces the assembly efficiency of the spikes. Summary of the invention
[0004] In order to solve the problems raised in the above background technology, the present invention provides an auxiliary assembly device for anchoring concrete sleepers, which has the advantage of preventing mortar from overflowing.
[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: an auxiliary assembly device for anchoring a concrete sleeper, comprising a sleeper transmission mechanism, a lifting assembly is arranged on the top of the sleeper transmission mechanism, a plurality of mortar injection mechanisms are arranged on both sides below the lifting assembly, a spike feeding assembly is arranged on the mortar injection mechanism from top to bottom, a smoothing structure is arranged at the bottom of the mortar injection mechanism, a limiting structure is arranged below the lifting assembly, and the limiting structure is fixedly connected to the mortar injection mechanism;
[0006] The mortar injection mechanism comprises a material box, a material injection pipe is arranged inside the material box, the bottom of the material injection pipe extends to the outside of the material box and is provided with a sleeve rod, a stopper is arranged in the inner cavity of the material injection pipe, the stopper is arranged in the inner cavity of the sleeve rod, a ball is elastically arranged on the top of the stopper, and a slide groove is opened on the sleeve rod;
[0007] The spike feeding assembly comprises a feed pipe, the bottom of which passes through the material box and extends into the sleeve rod, mounting frames located in the sleeve rod are arranged on both sides of the feed pipe, a moving frame is movably connected to the bottom of the mounting frame, and a blocking frame is arranged at the bottom of the moving frame;
[0008] The smoothing structure comprises a movable frame, the movable frame is rotatably connected to the bottom of the sleeve rod, and a telescopic rod located in a sliding groove is arranged on the outer side of the movable frame.
[0009] Preferably, the lifting assembly comprises a support frame, a pneumatic cylinder 1 is arranged on the top of the support frame, and a connecting frame is installed on the bottom of the pneumatic cylinder 1.
[0010] Preferably, a second pneumatic cylinder is provided on the top of the material box, and a pressure plate located in the material box is connected to the bottom of the second pneumatic cylinder.
[0011] Preferably, a movable block is arranged on the top of the blocking frame, a telescopic block located on one side of the movable block is installed on the blocking frame, and a fixed block located on the outer side of the blocking frame is arranged on the inner side of the sleeve rod.
[0012] Preferably, the blocking frame is elastically connected to the sleeve rod via a spring 1, and a rubber block is provided at the bottom of the inner side of the moving frame.
[0013] Preferably, the spike loading assembly further comprises a sleeve, the sleeve is movably connected to the sleeve rod, inner cavities on both sides of the sleeve are provided with moving blocks, the moving blocks are elastically connected to the sleeve via spring 2, and inclined blocks and clamping blocks are respectively provided at the upper and lower sides of the inner side of the moving blocks.
[0014] Preferably, a seesaw extending into the injection tube is provided on the outer side of the moving block, and the seesaw is movably connected to the ball.
[0015] Preferably, a sliding block is provided on the top of the movable frame, a mounting block is movably connected to the top of the sliding block, the mounting block is connected to the sleeve rod, a circular ring is provided on the inner side of the mounting block, and the circular ring is sleeved in the sliding block.
[0016] Preferably, the sliding block is elastically connected to the mounting block via a spring three, and the spring three is movably connected to the sliding block.
[0017] Preferably, a baffle is provided in the inner cavity of the movable frame, and a limit plate is movably connected to the top of the movable frame, and the limit plate is elastically connected to the mounting block through a spring four.
[0018] Compared with the prior art, the present invention has the following beneficial effects:
[0019] 1. The present invention provides a sleeve rod and a limit structure. When the limit structure moves downward as a whole, the position of the sleeper on the sleeper transmission mechanism is adjusted. The movable frame under the sleeve rod on the limit structure is inserted into the reserved hole of the sleeper, and the spike is transported to the reserved hole. The reserved hole is filled with sulfur cement mortar through the injection pipe. Multiple groups of mortar injection mechanisms are provided to complete the anchoring of the sleeper spikes, which greatly improves the anchoring efficiency of the spikes.
[0020] 2. The present invention sets a sleeve rod and an injection pipe, drives the sleeve rod as a whole downward through a pneumatic cylinder, blocks the reserved hole on the sleeper through a movable frame, and then fills the reserved hole with sulfur cement mortar through the injection pipe. As the mortar is injected, the mortar squeezes the baffle plate, driving the bottom of the movable frame to be level with the end of the reserved hole. At this time, the baffle plate blocks the block, which is used to seal the injection pipe, thereby preventing excessive sulfur cement mortar from being injected through the movable frame, avoiding overflow and bubbles in the mortar, and ensuring the quality of the spike anchor assembly;
[0021] 3. The present invention provides a movable frame and a telescopic rod. When the cement mortar in the reserved hole is filled, the movable frame is squeezed, and the movable frame drives the telescopic rod to move in the inclined part of the slide slot, drives the movable frame to rotate and move upward, and applies pressure to the spring three and the spring four. Under the elastic force of the spring three, the bottom of the movable frame is driven to smooth the top of the cement mortar in the reserved hole, so that the mortar is kept in a full state without water accumulation in the concave part, thereby ensuring the assembly quality of the road spike. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 It is a schematic diagram of the structure of the present invention;
[0023] Figure 2 It is a structural schematic diagram of the lifting assembly of the present invention;
[0024] Figure 3 It is a schematic cross-sectional structural diagram of the sleeve rod of the present invention;
[0025] Figure 4 An exploded view of the spike anchoring structure of the present invention;
[0026] Figure 5 An exploded view of the leveling structure of the present invention;
[0027] Figure 6 It is a cross-sectional structural schematic diagram of the movable frame of the present invention;
[0028] Figure 7 It is a schematic cross-sectional structural diagram of the sleeve of the present invention;
[0029] Figure 8 A schematic diagram of the structure of the sports frame of the present invention;
[0030] Fig. 9 It is a schematic diagram of the cross-sectional structure of the blocking frame of the present invention;
[0031] Fig.10 It is a structural schematic diagram of the movable frame of the present invention;
[0032] Fig.11 It is a structural schematic diagram of the chute of the present invention.
[0033] In the figure: 1. sleeper transmission mechanism; 2. lifting assembly; 201. support frame; 202. pneumatic cylinder 1; 203. connecting frame; 3. mortar injection mechanism; 301. material box; 302. injection pipe; 303. sleeve rod; 304. pneumatic cylinder 2; 305. pressing plate; 306. stopper; 307. ball; 308. slide; 4. spike loading assembly; 401. feeding pipe; 402. mounting frame; 403. telescopic block; 404. moving frame; 405. fixed block ; 406, blocking frame; 407, rubber block; 408, sleeve; 409, moving block; 410, spring two; 411, block; 412, inclined block; 413, seesaw; 414, movable block; 415, spring one; 5, leveling structure; 501, movable frame; 502, telescopic rod; 503, sliding block; 504, mounting block; 505, ring; 506, spring three; 507, spring four; 508, baffle; 509, limit plate; 6, limit structure. DETAILED DESCRIPTION
[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] In order to better understand the auxiliary assembly device for anchoring concrete sleepers provided by the present embodiment, the following first briefly introduces the assembly of existing spike anchoring. Since spikes are widely used, in the existing solutions, the problem of anchoring and installation of spikes is solved by using the positive anchoring method or the reverse anchoring method to assemble the spikes. In the positive anchoring method, sulfur cement mortar is poured from top to bottom, and then the spikes are inserted into the anchoring frame, and the assembly is completed after the mortar is cooled. At the same time, the reverse anchoring method installs a spike fastener at the reserved hole to fix the spike in the reserved hole, and then the sleeper is turned over to inject sulfur cement mortar into the reserved hole from the rear, and the assembly is completed after cooling.
[0036] The existing technology is relatively complicated in the assembly of road spikes, and multiple personnel can only operate on one sleeper, and it is impossible to perform anchoring operations on multiple groups of sleeper spikes at the same time. At the same time, the waiting time for each mortar to solidify causes a certain amount of time to be wasted each time the road spikes are assembled. The accumulated time causes a decrease in the spike assembly rate.
[0037] The embodiment of the present application provides an auxiliary assembly device for anchoring a concrete sleeper, wherein a lifting assembly 2 is used to move a mortar injection mechanism 3 to the top of a reserved hole of the sleeper, and a movable frame 501 is inserted into the reserved hole, and a spike feeding assembly 4 transports the spike to the center of the reserved hole, and multiple groups of mortar injection mechanisms 3 are injected simultaneously, and then when the mortar fills the reserved hole, the movable frame 501 is squeezed by the mortar and rotates inwardly and shrinks, blocking the feed pipe 401 to prevent excessive mortar from being injected, and when the movable frame 501 is rotated out of the reserved hole, the movable frame 501 is horizontally reset to smooth the top of the cement mortar in the reserved hole, and then the mortar is solidified, thereby completing the auxiliary assembly of multiple groups of spikes, and the time consumption is reduced, thereby improving the assembly efficiency of the spike anchoring, and the key contents of the scheme are summarized;
[0038] Embodiment 1, as Figures 1 to 6 As shown, it is the first embodiment of the present invention, which provides an auxiliary assembly device for anchoring a concrete sleeper, the device comprises a sleeper transmission mechanism 1, a lifting assembly 2 is arranged above the sleeper transmission mechanism 1, the lifting assembly 2 comprises a support frame 201, a pneumatic cylinder 202 is arranged on the top of the support frame 201, and a connecting frame 203 is installed at the bottom of the pneumatic cylinder 202;
[0039] The sleeper to be assembled is limitedly transported to the bottom of the mortar injection mechanism 3 through the sleeper transmission mechanism 1, and the pneumatic cylinder 1 202 is started to drive the connecting frame 203 to move downward. The bottom of the mortar injection mechanism 3 installed below the connecting frame 203 is inserted into the reserved holes on both sides of the sleeper, which is used to fill the reserved holes with sulfur cement mortar and fix the spikes in the reserved holes;
[0040] The bottom of the sleepers transported at the top of the sleeper transmission mechanism 1 is provided with a base, and the bottom of the reserved hole of the sleeper is blocked by the base to prevent the sulfur cement mortar filled inside from leaking out and sticking to the sleeper transmission mechanism 1 to affect the subsequent positioning deviation. The base is not drawn in the figure and can also be replaced by other structures;
[0041] The lifting assembly 2 is provided with a mortar injection mechanism 3, which includes a material box 301 installed on the support frame 201, an injection pipe 302 is sleeved inside the material box 301, the bottom of the injection pipe 302 extends to the outside of the material box 301 and is sleeved with a sleeve rod 303, a pneumatic cylinder 304 is provided on the top of the material box 301, and a pressure plate 305 located inside the material box 301 is installed at the bottom of the pneumatic cylinder 304;
[0042] When injection is required, the second pneumatic cylinder 304 is started, and the pressure plate 305 is driven downward by the second pneumatic cylinder 304 to squeeze the cement mortar in the material box 301 into the injection pipe 302, and the mortar is introduced into the reserved hole through the injection pipe 302 to complete the injection of the cement mortar;
[0043] The inner wall of the injection tube 302 is provided with a stopper 306, a ball 307 is provided on the top of the stopper 306, a spring sheet located on the injection tube 302 is provided above the ball 307, and the bottom of the spring sheet is connected to the ball 307;
[0044] The elastic force of the spring sheet applies downward pressure to the ball 307, and the ball 307 fits tightly with the stopper 306, blocking the material discharge channel of the injection pipe 302 to stop the material discharge, thereby preventing the sulfur cement mortar from being continuously injected into the reserved hole and causing the cement mortar to overflow through the control of the injection pipe 302 by the ball 307;
[0045] The outer surface of the sleeve rod 303 is sleeved with the limiting structure 6, and the top of the limiting structure 6 is connected to the connecting frame 203;
[0046] When the sleeper is transported to the bottom of the mortar injection mechanism 3, a slight deviation will occur. At this time, the pneumatic cylinder 202 drives the connecting frame 203 to move downward, and the inclined surface of the bottom of the limiting structure 6 squeezes the two sides of the sleeper. The sleeper position is corrected by the inclined surface, and the reserved hole on the sleeper is aligned with the sleeve rod 303. As the connecting frame 203 continues to press downward, the inner side of the limiting structure 6 is clamped into the two sides of the sleeper, and the bottom of the sleeve rod 303 and the top of the sleeper are kept in a horizontal position, so that the position of the sleeper to be processed below is adjusted by the limiting structure 6, ensuring that the sleeve rod 303 is aligned with the reserved hole, so that the mortar injection mechanism 3 is used to complete the simultaneous injection of multiple groups of sleepers, which greatly reduces the assembly efficiency;
[0047] Embodiment 2, as Figures 4 to 9 As shown, on the basis of Example 1, a spike loading assembly 4 is arranged inside the mortar injection mechanism 3, and the spike loading assembly 4 includes a feed pipe 401 arranged on the material box 301, and the upper and lower parts of the feed pipe 401 extend to the outside of the material box 301, and the feed pipe 401 is connected to the material box 301. The bottom of the feed pipe 401 passes through the injection pipe 302 and is sleeved on the outside of the sleeve rod 303, and mounting frames 402 extending to the inner cavity of the sleeve rod 303 are arranged on both sides of the feed pipe 401.
[0048] When the second pneumatic cylinder 304 is started, the sleeve rod 303 is driven to move downward. At this time, the feed pipe 401 sleeved on the outside of the sleeve rod 303 does not move. As the sleeve rod 303 continues to descend as a whole, the movement of the spike feeding assembly 4 is triggered through the mounting frame 402, and the external spikes are transported to the reserved holes through the feed pipe 401, which facilitates the assembly of the spikes.
[0049] Fixed columns are provided on both sides of the inner cavity of the sleeve rod 303, and a moving frame 404 is sleeved on the fixed columns. The moving frame 404 is movably connected to the mounting frame 402. The moving frame 404 is elastically connected to the sleeve rod 303 through a spring, and a rubber block 407 is installed on the inner side of the top of the moving frame 404. A blocking frame 406 located below the moving frame 404 is movably provided inside the sleeve rod 303, and a pulley is provided on the inner side of the blocking frame 406.
[0050] When the sleeve rod 303 moves downward as a whole, the mounting frame 402 squeezes the inclined surface of the moving frame 404, and the moving frame 404 moves along the fixed column and applies pressure to the spring, so that the moving frame 404 is easily reset by the spring.
[0051] When the moving frame 404 moves, it will drive the rubber block 407 and the blocking frame 406 to move outward, thereby removing the obstruction to the inner cavity of the sleeve rod 303, and the spikes in the inner cavity of the sleeve rod 303 will fall down and fall into the reserved hole of the sleeper. At the same time, the sleeve rod 303 is corrected and limited by the limiting structure 6, and the conveying channel of the spikes is located at the center of the sleeve rod 303. The fallen spikes are accurately located at the center of the reserved hole, which prevents the installation of the spikes from being offset after the mortar solidifies, and facilitates the subsequent installation of the sleeper. In addition, the rubber block 407 moves inward to clamp the second spike in the sleeve rod 303, so as to prevent the second spike from falling after the first spike falls, so as to avoid affecting the continuity of the installation of the spikes.
[0052] The sleeve rod 303 is movably connected inside with a sleeve 408 located below the blocking frame 406. The diameters of the central inner cavities of the sleeve 408 and the sleeve rod 303 are the same as the diameter of the spike. Moving blocks 409 are provided on both sides of the sleeve 408. The moving block 409 is elastically connected to the sleeve 408 through a spring 410. A clamping block 411 is provided at the bottom of the inner side of the moving block 409, and an inclined block 412 is provided at the top of the inner side of the moving block 409. The inner sides of the clamping block 411 and the inclined block 412 extend into the inner cavity of the sleeve 408.
[0053] A movable block 414 located above the blocking frame 406 is movably installed inside the sleeve rod 303, and the outer side of the movable block 414 is in contact with the moving frame 404. A fixed block 405 located outside the blocking frame 406 is provided on the inner wall of the sleeve rod 303. The blocking frame 406 is elastically connected to the sleeve rod 303 through a spring 415. A telescopic block 403 located outside the movable block 414 is provided inside the blocking frame 406, and the top of the telescopic block 403 extends from the outside of the blocking frame 406.
[0054] When the moving frame 404 is squeezed by the mounting frame 402, the moving frame 404 is driven to move inward, and the bottom of the moving frame 404 squeezes the movable block 414, driving one side of the movable block 414 to rotate, and at the same time, the other side of the movable block 414 squeezes the telescopic block 403 and drives the blocking frame 406 to move. As the blocking frame 406 moves outward, the blocking frame 406 squeezes the inclined block 412 and the telescopic block 403 hits the fixed block 405, and the telescopic block 403 is squeezed into the inner cavity of the blocking frame 406 through the inclined surface on the fixed block 405. The blocking frame 406 is driven to reset through the elastic force of the spring 1 415 to clamp the falling spike, and the pulley installed on the inside will not affect the falling of the spike. When the movable block 414 is reset, the inclined surface on the other side of the movable block 414 squeezes the telescopic block 403, which will press the telescopic block 403 into the blocking frame 406 and move the telescopic block 403 to the other side of the movable block 414.
[0055] When the blocking frame 406 moves outside, it will squeeze the inclined block 412, drive the inclined block 412, the moving block 409 and the clamping block 411 to move out from the inner diameter of the sleeve 408, so that the spike will not be hindered when falling inside the sleeve 408. When the first spike falls, the spike falls into the inner cavity of the sleeve 408 along the sleeve rod 303. The inclined block 412 is pressed by the blocking frame 406, causing the inclined block 412 to expand outward, and the inclined block 412 and the clamping block 411 move out from the inner cavity of the sleeve rod 303.
[0056] Since the lower end of the spike is relatively flat, when the spike falls, it slides out from the inner side of the blocking frame 406, and the spring 1 415 releases the squeezing of the blocking frame 406 on the inclined block 412, and the elastic force of the spring 2 410 drives the moving block 409 to move inward, and the moving block 411 is clamped into the threaded portion of the falling spike, so that the threaded portion is kept outside the reserved hole, thereby facilitating the assembly operation of the anchoring of the spike and preventing the inaccurate height position of the spike from affecting the quality of the sleeper;
[0057] A seesaw 413 is installed on the outer side of the moving block 409, and the other end of the seesaw 413 extends to the inner cavity of the injection tube 302 and is located below the ball 307;
[0058] When the clamping block 411 on the moving block 409 is clamped to the threaded part of the spike, the clamping block 411 is not reset to the original state. At this time, the seesaw 413 will lift up the ball 307, driving the ball 307 to separate from the stopper 306. The sulfur cement mortar prepared in the material box 301 is squeezed out by starting the second pneumatic cylinder 304, and the mortar is injected into the reserved hole. After the mortar is filled and solidified, the sleeve rod 303 is reset as a whole, and the spike is pulled out of the clamping block 411 by the elastic buffer of the first spring 415, so as to facilitate the assembly of the spike.
[0059] Thus, the automatic loading of the spikes can be realized, the operation is simple and convenient, and the efficiency of the device's auxiliary assembly of the spikes is improved. At the same time, the spikes are always kept in the center of the reserved holes to prevent position deviation from affecting the installation of the rails. The threaded part of the spikes is always kept outside the reserved holes, which is convenient for the subsequent connection and use of sleepers.
[0060] Embodiment 3, as Figure 5 , Fig.10 and Fig.11 As shown, on the basis of Example 1, a smoothing structure 5 is provided at the bottom of the mortar injection mechanism 3, and the smoothing structure 5 includes a movable frame 501 arranged in the inner cavity of the end of the sleeve rod 303, the bottom of the movable frame 501 extends to the outside of the sleeve rod 303, and a slide groove 308 located outside the movable frame 501 is opened inside the sleeve rod 303, and the slide groove 308 is triangular, and the depths of the three sides of the slide groove 308 are gradually increased in sequence, and a telescopic rod 502 located in the slide groove 308 is provided on the outside of the movable frame 501, and a scraper is provided at the bottom of the movable frame 501;
[0061] When the sleeve rod 303 moves downward, the movable frame 501 will move into the reserved hole of the sleeper, thereby blocking the reserved hole, and fill the reserved hole with sulfur cement mortar through the injection pipe 302. When the reserved hole is gradually filled with mortar, the movable frame 501 will be squeezed. As the filling is continuously continued, the extrusion drives the telescopic rod 502 on the movable frame 501 to move in the inclined part of the slide slot 308, driving the movable frame 501 to rotate and rise. When the reserved hole is filled, the telescopic rod 502 moves to the top of the inclined part, and the movable frame 501 is kept flush with the bottom of the sleeve rod 303 to block the opening of the reserved hole to prevent the mortar from overflowing, and the cement mortar in the reserved hole can be effectively blocked by the resistance of the movable frame 501 and the spring four 507, and the air cavity inside the cement mortar is squeezed out to ensure the quality of the anchoring assembly of the spike.
[0062] A sliding block 503 is arranged on the top of the movable frame 501, a mounting block 504 is arranged on the inner wall of the sleeve rod 303 and is located outside the sliding block 503, a circular ring 505 is arranged inside the mounting block 504, the sliding block 503 is sleeved on the circular ring 505, the mounting block 504 is elastically connected to the sliding block 503 through a spring 3 506, and the spring 3 506 is movably connected to the sliding block 503,
[0063] When the movable frame 501 is squeezed and rotated upward, it will drive the sliding block 503 to move on the ring 505, thereby pulling the spring three 506. When the telescopic rod 502 moves to the top of the inclined part of the slide groove 308, the elastic force of the spring three 506 recovers and drives the telescopic rod 502 to move to the horizontal part of the slide groove 308, driving the movable frame 501 to rotate horizontally as a whole. The scraper at the bottom is used to smooth the mortar at the port of the reserved hole to prevent the mortar in the reserved hole from being uneven, and to avoid the phenomenon of concave water accumulation in the cement mortar after solidification, thereby ensuring the quality of the anchor assembly of the sleeper;
[0064] A limit plate 509 located above the movable frame 501 is movably sleeved inside the sleeve rod 303, and the bottom of the limit plate 509 is movably connected to the movable frame 501. The limit plate 509 is elastically connected to the mounting block 504 through a spring 507, and a baffle 508 is installed inside the movable frame 501;
[0065] When the movable frame 501 rotates and moves upward, it drives the baffle plate 508 to move upward, and the end of the baffle plate 508 is stuck into the inside of the stopper 306, thereby blocking the injection pipe 302, stopping the injection, and preventing the sulfur cement mortar from being over-injected and overflowing;
[0066] After the telescopic rod 502 on the movable frame 501 moves in the horizontal part on the slide groove 308, the sleeve rod 303 is reset after the mortar solidifies, and the spike is pulled out from the block 411. As the movable frame 501 is separated from the reserved hole, the movable frame 501 is acted upon by the elastic force of the spring 4 507, driving the movable frame 501 and the limit plate 509 to move downward, and the telescopic rod 502 moves along the vertical part of the slide groove 308, driving the movable frame 501 to reset to the original state, which is convenient for subsequent anchoring processing;
[0067] Therefore, the movable frame 501 ensures the flatness of the rear end of the mortar after solidification, prevents the occurrence of concave water accumulation, and thus affects the anchoring quality and the use of the sleeper.
[0068] The working principle and use process of the present invention:
[0069] When the spikes are assembled in the reserved holes of the sleepers, the sleeper transmission mechanism 1 is used to move the multiple groups of positioned sleepers to the bottom of the mortar injection mechanism 3, and the pneumatic cylinder 202 is started to drive the connecting frame 203 and the sleeve rod 303 to move downward. The limiting structure 6 on the sleeve rod 303 contacts the sleepers first, and the sleepers are corrected through the inclined surfaces at the bottom of both sides of the limiting structure 6 to avoid position deviation caused by shaking of the sleeper transmission mechanism 1 during transportation. After that, the sleeve rod 303 continues to move downward, and the movable frame 501 is inserted into the reserved holes of the sleepers, and the bottom of the sleeve rod 303 is in contact with the The end of the reserved hole is kept in a horizontal position, and at the same time, the bottom of the mounting frame 402 squeezes the moving frame 404, and the moving frame 404 drives the blocking frame 406 to release the blocking of the inner cavity of the sleeve rod 303 through the movable block 414, and the spike in the inner cavity of the sleeve rod 303 falls into the sleeve 408, and the rubber block 407 clamps the second spike, resulting in only one spike falling. When the blocking frame 406 moves outward, it squeezes the inclined block 412, and the moving block 409 and the clamping block 411 are driven to contract through the inclined block 412, so that the spike will not be blocked when it falls, and then the spike is removed from the blocking block. When the inner side of the frame 406 moves over, the telescopic block 403 on the blocking frame 406 is squeezed by the fixed block 405, and the movable block 414 passes over the telescopic block 403, releasing the blocking of the blocking frame 406, and then the elastic force of the spring 1 415 drives the blocking frame 406 to reset, and squeezes the spike through the pulley without affecting the falling, and the inclined block 412 is also released from pressing, and the elastic force of the spring 2 410 drives the moving block 409 and the clamping block 411 to reset, and the inner side of the clamping block 411 is inserted into the screw thread groove of the spike, and the screw thread part of the spike is clamped to the outside of the reserved hole of the sleeper, and the clamping block When 411 is squeezed by the spike and cannot be completely reset, the clamping block 411 will drive the moving block 409 and the seesaw 413 to move, and the seesaw 413 squeezes the ball 307, opens the opening of the injection pipe 302, starts the pneumatic cylinder 304, and drives the pressing plate 305 to inject the prepared sulfur cement mortar into the reserved hole, so as to control the feeding of the spike through the moving frame 404, and ensure that the spike always keeps the center position of the reserved hole, so as to avoid the skewness of the spike during assembly, which affects the subsequent installation and use, and improves the assembly efficiency of the concrete sleeper anchoring position;
[0070] Afterwards, the reserved hole is continuously filled through the injection pipe 302. When the cement mortar in the reserved hole contacts the movable frame 501, the mortar drives the movable frame 501 to move upward, and the telescopic rod 502 rotates and moves upward along the inclined part of the slide groove 308. When the telescopic rod 502 moves to the terminal end of the inclined part, the movable frame 501 drives the baffle 508 to snap into the inner cavity of the block 306, controls the feeding of the injection pipe 302, stops the filling of mortar, and fills the reserved hole of the sleeper.
[0071] Then, since the telescopic rod 502 moves to the top of the inclined part at this time, due to the elastic force of spring three 506, it drives the sliding block 503, the movable frame 501, the sleeve 408 and the injection tube 302 to return to horizontal movement, and the telescopic rod 502 is moved from the outermost side of the horizontal part of the slide groove 308, and the scraper at the bottom of the movable frame 501 smoothes the mortar in the reserved hole as it rotates, thereby ensuring the flatness of the rear end of the mortar solidification, so as to avoid affecting the quality of the sleeper and prevent the occurrence of concave water accumulation.
[0072] Finally, after the sulfur cement mortar solidifies, the spike in the reserved hole is fixed inside it, and the pneumatic cylinder 1 202 is started at the same time, driving the connecting frame 203 and the sleeve rod 303 to move upward as a whole, and the threaded part of the spike squeezes the block 411. Through the buffering of the spring 2 410, the block 411 is pulled out from the outside of the spike to release the fixation of the spike, and due to the elastic force of the spring 4 507, the movable frame 501 is squeezed to move downward, and the telescopic rod 502 moves in the vertical part of the slide groove 308, and the telescopic rod 502 is moved to the inclined part, and the baffle 508 is also moved out from the inside of the block 306, and the ball 307 is reset by the spring sheet, and the injection pipe 302 is closed to feed the material, and then the block 411 is reset, so that the mortar injection mechanism 3 and the spike feeding assembly 4 are completely reset, which is convenient for continuous simultaneous anchoring of multiple groups of sleepers and improves the assembly efficiency of the spike.
[0073] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0074] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An auxiliary assembly device for anchoring a concrete sleeper, comprising a sleeper transmission mechanism (1), characterized in that: A lifting assembly (2) is arranged on the top of the sleeper transmission mechanism (1), a plurality of mortar injection mechanisms (3) are arranged on both sides below the lifting assembly (2), a spike loading assembly (4) is arranged on the mortar injection mechanism (3) from top to bottom, a leveling structure (5) is arranged at the bottom of the mortar injection mechanism (3), a limiting structure (6) is arranged below the lifting assembly (2), and the limiting structure (6) is fixedly connected to the mortar injection mechanism (3); The mortar injection mechanism (3) comprises a material box (301), a material injection pipe (302) is arranged inside the material box (301), the bottom of the material injection pipe (302) extends to the outside of the material box (301) and is provided with a sleeve rod (303), a stopper (306) is arranged in the inner cavity of the material injection pipe (302), the stopper (306) is arranged in the inner cavity of the sleeve rod (303), a round ball (307) is elastically arranged on the top of the stopper (306), and a slide groove (308) is provided on the sleeve rod (303); The spike loading assembly (4) comprises a feed pipe (401), the bottom of which passes through the material box (301) and extends into the sleeve rod (303), mounting frames (402) located in the sleeve rod (303) are arranged on both sides of the feed pipe (401), the bottom of the mounting frame (402) is movably connected to a moving frame (404), and a blocking frame (406) is arranged at the bottom of the moving frame (404); The smoothing structure (5) comprises a movable frame (501), the movable frame (501) being rotatably connected to the bottom of the sleeve rod (303), and a telescopic rod (502) located in a slide groove (308) is arranged outside the movable frame (501).
2. The auxiliary assembly device for anchoring concrete sleepers according to claim 1, characterized in that: The lifting assembly (2) comprises a support frame (201), a pneumatic cylinder 1 (202) is arranged on the top of the support frame (201), and a connecting frame (203) is installed on the bottom of the pneumatic cylinder 1 (202).
3. The auxiliary assembly device for anchoring concrete sleepers according to claim 2, characterized in that: A second pneumatic cylinder (304) is disposed on the top of the material box (301), and a pressure plate (305) located inside the material box (301) is connected to the bottom of the second pneumatic cylinder (304).
4. The auxiliary assembly device for anchoring concrete sleepers according to claim 3, characterized in that: A movable block (414) is arranged on the top of the blocking frame (406), a telescopic block (403) located on one side of the movable block (414) is installed on the blocking frame (406), and a fixed block (405) located on the outside of the blocking frame (406) is arranged on the inner side of the sleeve rod (303).
5. The auxiliary assembly device for anchoring concrete sleepers according to claim 4, characterized in that: The blocking frame (406) is elastically connected to the sleeve rod (303) via a spring 1 (415), and a rubber block (407) is provided at the bottom of the inner side of the moving frame (404).
6. The auxiliary assembly device for anchoring concrete sleepers according to claim 5, characterized in that: The spike loading assembly (4) further comprises a sleeve (408), the sleeve (408) being movably connected to the sleeve rod (303), the inner cavities on both sides of the sleeve (408) being provided with moving blocks (409), the moving blocks (409) being elastically connected to the sleeve (408) via a second spring (410), and the upper and lower sides of the inner side of the moving block (409) being provided with an inclined block (412) and a clamping block (411), respectively.
7. The auxiliary assembly device for anchoring concrete sleepers according to claim 6, characterized in that: A seesaw (413) extending into the injection tube (302) is arranged outside the moving block (409), and the seesaw (413) is movably connected to the ball (307).
8. The auxiliary assembly device for anchoring concrete sleepers according to claim 6, characterized in that: A sliding block (503) is arranged on the top of the movable frame (501), and a mounting block (504) is movably connected to the top of the sliding block (503). The mounting block (504) is connected to the sleeve rod (303), and a circular ring (505) is arranged on the inner side of the mounting block (504), and the circular ring (505) is sleeved in the sliding block (503).
9. The auxiliary assembly device for anchoring concrete sleepers according to claim 8, characterized in that: The sliding block (503) is elastically connected to the mounting block (504) via a spring three (506), and the spring three (506) is movably connected to the sliding block (503).
10. The auxiliary assembly device for anchoring concrete sleepers according to claim 9, characterized in that: The inner cavity of the movable frame (501) is provided with a baffle (508), and the top of the movable frame (501) is movably connected to a limit plate (509), and the limit plate (509) is elastically connected to the mounting block (504) via a spring four (507).