Low-clear-height cast-in-place box girder tensioning jack mounting device and construction method thereof
By designing a tension jack installation device for low-net high cast-in-place prestressed box girders in bridge engineering, automatic conveying and upgrading is achieved using conveying ropes and lifting rods, the problems of low construction efficiency and high manual labor intensity are solved, and the problems of low construction efficiency and high labor intensity are significantly Improve construction efficiency.
Patent Information
- Application Number
- CN202411214089.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-31
- Publication Date
- 2024-11-01
AI Technical Summary
In bridge projects, the installation and construction efficiency of the tension jack of low-net high cast-in-place prestressed box girder is low and the labor force is high. This is mainly due to the heavy weight of the tension jack and the uneven bottom plate of the box girder, which leads to inconvenience in transportation and affects the progress of the project .
An installation device including a conveying rope and a lifting rod that can be lifted in a single degree of freedom along the vertical direction is designed. The automatic conveying and lifting of the tension jack is realized through the reserved manhole hole and lifting hole, and the installation process is simplified by the lifting device. , reduce manual operations.
The device can effectively reduce the labor intensity of workers and improve construction efficiency. Through the automatic conveying and lifting mechanism, the tension jack can easily slide to the prestressed reinforcement tensioning point. Only one worker can complete the conveying and installation, which significantly improves the construction efficiency.
Smart Images

Figure CN118880753A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge engineering, and in particular to a tensioning jack installation device for a low-clearance cast-in-place box girder and a construction method thereof. Background Art
[0002] In bridge engineering, cast-in-place prestressed box girders generally use the post-tensioning method to tension the prestressed tendons, that is, when the concrete strength of the component reaches the specified strength, the prestressed tendons are inserted into the reserved channel for tensioning, and the tensioned prestressed tendons are anchored at the end of the component by using anchors. Among them, tensioning jacks are usually used to complete the tensioning of prestressed tendons. At present, the installation and construction method of tensioning jacks is generally as follows: first, the tensioning jacks are hoisted into the box girder from the reserved manhole of the box girder, and then the tensioning jacks are manually dragged to the vicinity of the tooth block (i.e., the component used for anchoring the prestressed tendons) for tensioning the prestressed tendons by flatbed trucks or cables, and then the tensioning jacks are manually lifted and installed on the tooth block to complete the tensioning of the corresponding prestressed tendons; after the tensioning is completed, the tensioning jacks are disassembled and dragged to the next tensioning point. This form has the problems of low installation efficiency and high labor intensity of tensioning jacks for cast-in-place prestressed boxes with low net height (less than 0.8 meters). This is due to the heavy weight of the tensioning jack (usually between 20-80kg) and the uneven surface of the box beam bottom plate. Therefore, when transporting the tensioning jack, one person is usually required to pull it in front and one person is required to push it in the back, which is very inconvenient and extremely inefficient in a low-clearance box beam. In particular, cast prestressed box beams are usually long in length, and multiple prestressing tendon tensioning points are set in the entire length and width directions. The existing jack installation construction method has a serious impact on the project progress.
[0003] Therefore, there is an urgent need to provide a new installation device and construction method suitable for the installation of tensioning jacks for low-net-height cast-in-place prestressed box girders, so as to reduce the labor intensity of workers and improve construction efficiency. Summary of the invention
[0004] In view of this, the present invention is to provide a low-clearance cast-in-place box girder tensioning jack installation device and a construction method thereof, which can effectively improve construction efficiency while reducing the labor intensity of workers.
[0005] To achieve the above-mentioned object, the present invention provides the following technical solutions: a low net height cast-in-place box girder tensioning jack installation device, comprising a conveying rope, two sets of lifting rods that can be lifted and lowered with a single degree of freedom in the vertical direction, and two sets of lifting devices respectively used to drive the corresponding lifting rods to achieve lifting;
[0006] The upper top plate of the box girder is provided with a manhole and two lifting holes, and the two lifting holes are respectively arranged near two adjacent prestressed tendon tensioning points in the length direction of the box girder;
[0007] The two groups of lifting rods are slidably arranged on the two lifting holes respectively, and the two ends of the conveying rope are detachably connected with the bottoms of the two groups of lifting rods respectively.
[0008] Furthermore, the lifting hole is located on the side of the upper gear block corresponding to the installation of the tensioning jack near the prestressed tendon tensioning point.
[0009] Furthermore, the manhole is located in the middle of the two lifting holes along the length direction of the box girder.
[0010] Furthermore, an upper hoisting part and a lower hoisting part are respectively provided at the upper and lower ends of the lifting rod, the upper hoisting part is connected to the corresponding side lifting device, and the lower hoisting part is connected to the corresponding end of the conveying rope.
[0011] Furthermore, the upper hoisting part is an upper hoisting ring fixedly connected to the upper end of the lifting rod, the lower hoisting part is a lower hoisting ring fixedly connected to the lower end of the lifting rod, and the conveying rope is a steel wire rope, and both ends of the steel wire rope are connected to the corresponding side lower hoisting rings respectively through hooks.
[0012] Furthermore, the lifting device includes a movable support frame and an electric hoist arranged on the top of the movable support frame, and the working end of the electric hoist is detachably connected to the upper lifting part on the corresponding side.
[0013] Furthermore, the sliding outer sleeve of the lifting rod is provided with a guide sleeve, and the guide sleeve is arranged in the lifting hole in a manner that it can be taken out upwards.
[0014] Furthermore, the outer sleeves at both ends of the lifting rod are respectively fixed with limiting sleeves for preventing the lifting rod from sliding out of the guide sleeve.
[0015] Furthermore, it also includes two groups of buffer pads which are arranged on the lower bottom plate of the box beam and are correspondingly located below the two lifting holes.
[0016] A method for installing a tensioning jack for a low-clearance cast-in-place box beam, using the installation device described above for construction, comprises the following steps:
[0017] S1: When pouring the box girder, reserve manholes and lifting holes on the upper top plate;
[0018] S2: Hang the tensioning jack into the box beam through the manhole;
[0019] S3: Hook the tensioning jack onto the conveying rope;
[0020] S4: Adjust the height of the lifting rods at both ends to change the inclination angle of the conveying rope, and push the tensioning jack to slide along the conveying rope to the vicinity of the corresponding prestressed tendon tensioning point;
[0021] S5: Hook the tensioning jack onto the bottom of the lifting rod, and lift the tensioning jack through the lifting device to complete the installation of the tensioning jack on the upper top plate.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] The tensioning jack installation device for cast-in-place box girders with low net height provided by the present invention can help reduce the labor intensity of workers and improve construction efficiency at the same time; specifically, by setting a conveying rope, the tensioning jack can slide on the conveying rope to complete the conveying, and since the lifting rods at both ends can adjust the inclination angle of the conveying rope, the tensioning jack can easily slide to the corresponding position, and only one worker needs to gently push the tensioning jack to complete the conveying; at the same time, for the tensioning jack on the upper top plate, the lifting rod can be directly pulled by the lifting device to complete the lifting of the tensioning jack, thereby completing the whole process, and the installation is more convenient and quick;
[0024] The low net height cast-in-place box girder tensioning jack installation construction method provided by the invention has high installation efficiency and low labor intensity of workers.
[0025] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 It is a schematic cross-sectional diagram of the overall structure of the present invention.
[0027] Figure 2 for Figure 1 A partial enlarged view of the center
[0028] Figure numerals: 1- conveying rope; 2- lifting rod; 201- upper lifting part; 202- lower lifting part; 203- guide sleeve; 204- limit sleeve; 3- lifting device; 301- movable support frame; 302- electric hoist; 4- upper top plate; 401- manhole; 402- lifting hole; 403- tooth block; 5- lower bottom plate; 6- buffer pad; 7- tensioning jack. DETAILED DESCRIPTION
[0029] The following describes the embodiments of the present invention by specific examples, and those skilled in the art can easily understand other advantages and effects of the present invention from the contents disclosed in this specification. The present invention can also be implemented or applied through other different specific embodiments, and the details in this specification can also be modified or changed in various ways based on different viewpoints and applications without departing from the spirit of the present invention. It should be noted that the illustrations provided in the following embodiments are only used to illustrate the basic concept of the present invention, and the following embodiments and the features in the embodiments can be combined with each other without conflict.
[0030] See also Figure 1-2 In the present embodiment, a tensioning jack installation device for a low net height cast-in-place box girder is disclosed, comprising a conveying rope 1, two groups of lifting rods 2 that can be lifted and lowered along a single degree of freedom in the vertical direction, and two groups of lifting devices 3 respectively used to drive the corresponding lifting rods 2 to achieve lifting; a manhole 401 and two lifting holes 402 are provided on the upper top plate 4 of the box girder, and the two lifting holes 402 are respectively and correspondingly arranged near two adjacent prestressed tendon tensioning points in the length direction of the box girder; the two groups of lifting rods 2 are respectively and correspondingly arranged in the two lifting holes 402 for sliding, and the two ends of the conveying rope 1 are respectively and correspondingly connected to the bottom of the two groups of lifting rods 2 for detachable connection; it can be understood that the manhole 401 and the lifting hole 402 here can usually be reserved when the box girder is cast, wherein the manhole 401 serves as a passage for workers to enter and exit the box girder; the lifting hole 402 refers to a mounting hole for the lifting rod 2 to pass through, the lifting rod 2 is inserted into the box girder from the lifting hole 402, and the lifting rod 2 is lifted by the lifting device 3 The drive realizes lifting in the up and down directions; in order to ensure the carrying capacity of the lifting rod 2 for the conveying rope 1, the lifting rod 2 is generally made of steel, such as a steel pipe; the setting of the lifting rod 2 can ensure that the conveying rope 1 forms a stable conveying track, and the conveying rope 1 and the lifting rod 2 can be detachably connected through a hook to ensure the convenience of installation of the overall device; when in use, the tensioning jack 7 can be hooked on the conveying rope 1 through the hook to complete the sliding conveying, and cooperate with the lifting rod 2 to change the inclination angle of the conveying rope 1, which can ensure fast and easy transportation; of course, it can be understood that the conveying rope 1 is in a state of being close to being straight (allowing a small bending at the hanging point of the tensioning jack 7) between the two lifting rods 2, ensuring that the conveying rope 1 will not be excessively deformed after the tensioning jack 7 is hung; the above-mentioned "near the prestressed tendon tensioning point" is also near the installation point of the tensioning jack 7, and the tensioning jack 7 is usually installed on the tooth block 403 (i.e., the component used for anchoring the prestressed tendons) on the upper top plate 4;
[0031] The tensioning jack installation device for the low-net-height cast-in-place box girder in the above-mentioned structural design can help reduce the labor intensity of workers and improve construction efficiency. Specifically, by setting the conveying rope 1, the tensioning jack 7 can slide on the conveying rope 1 to complete the conveying. Since the lifting rods 2 at both ends can adjust the inclination angle of the conveying rope, the tensioning jack 2 can be easily slid to the corresponding position, and only one worker needs to gently push the tensioning jack 2 to complete the conveying. At the same time, for the installation of the tensioning jack 7 on the upper top plate 4, the lifting rod 2 can be directly pulled by the lifting device 3 to complete the lifting of the tensioning jack 7, thereby completing the whole process, and the installation is more convenient and quick. At the same time, the structural design of this device is ingenious, and the overall structure of the device is simple. The setting of the lifting rod 2 can not only provide a stable installation point for the conveying rope 1, At the same time, it can also be directly used as a lifting mechanism for the tensioning jack 7 to complete the installation of the tensioning jack 7 on the upper top plate; of course, it is understandable that the tensioning points of the prestressed tendons of the cast-in-place box girder are basically set on the upper top plate 4 and the lower bottom plate 5 of the box girder, wherein the tensioning point positions on the upper top plate 4 and the lower bottom plate 5 are staggered in the length direction of the box girder, then the device can also transport the tensioning jack 7 to the position of the tensioning point on the lower bottom plate 5, when the tensioning jack 7 is transported to the corresponding position of the tensioning point on the lower bottom plate 5, the lifting rods 2 on both sides are controlled to descend at the same time, so as to ensure that the tensioning jack 7 falls to the corresponding installation position for installation; that is, no matter whether the jacks are installed on the upper top plate 4 or the lower bottom plate 5 of the box girder, the transportation of the tensioning jack 7 can be completed by the device, which greatly reduces the labor intensity and greatly improves the construction efficiency.
[0032] In this embodiment, the lifting hole 402 is located on the side of the upper tooth block 403 corresponding to the installation of the tensioning jack 7 near the prestressed tendon tensioning point. Here, the upper tooth block 403 is a component used for anchoring the prestressed tendons. The hole position is reasonably designed, which is conducive to completing the lifting and installation of the tensioning jack 7 on the upper tooth block 403, and is conducive to further improving the installation efficiency of the tensioning jack 7 on the upper top plate 4.
[0033] In this embodiment, the manhole 401 is located in the middle of the two lifting holes 402 along the length direction of the box girder, preferably at the midpoint; by setting the manhole 401 in the middle of the two lifting holes 402 along the length direction of the box girder, it is helpful to avoid the single-sided transportation distance being too long, causing discomfort to the workers, and improve the ventilation effect of the construction inside the box girder.
[0034] In this embodiment, the upper and lower ends of the lifting rod 2 are respectively provided with an upper lifting part 201 and a lower lifting part 202, the upper lifting part 201 is connected to the corresponding side lifting device 3, and the lower lifting part 202 is connected to the corresponding end of the conveying rope 1; by providing the lifting part, the connection convenience of the corresponding end of the lifting rod 2 is facilitated, thereby further improving the construction efficiency.
[0035] In this embodiment, the upper hoisting part 201 is an upper hoisting ring fixedly connected to the upper end of the lifting rod 2, the lower hoisting part 202 is a lower hoisting ring fixedly connected to the lower end of the lifting rod 2, and the conveying rope 1 is a steel wire rope, and the two ends of the steel wire rope are respectively connected to the corresponding side lower hoisting rings through hooks; by adopting the hoisting ring structure, the overall structure has high reliability, hook connection, high installation convenience, and the steel wire rope has good durability and bearing capacity.
[0036] In this embodiment, the lifting device 3 includes a movable support frame 301 and an electric hoist 302 arranged on the top of the movable support frame 301. The working end of the electric hoist 302 is detachably connected to the upper lifting part 201 on the corresponding side; it can be understood that the electric hoist 302 and the upper lifting part are generally connected through a hook; the lifting device 3 has a simple structure, and the movable support frame 301 is conducive to quickly moving to the next position for construction after the construction at this position is completed.
[0037] In this embodiment, the sliding outer sleeve of the lifting rod 2 is provided with a guide sleeve 203, and the guide sleeve 203 is arranged in the lifting hole 401 in a manner that it can be removed upward; by providing the guide sleeve 203, it is beneficial to ensure the movement stability of the lifting rod 2 and reduce the risk of the lifting rod 2 getting stuck, thereby ensuring that the construction continues smoothly; at the same time, the guide sleeve 203 is easy to install.
[0038] In this embodiment, the outer sleeves at both ends of the lifting rod 2 are respectively fixed with limit sleeves 204 for preventing the lifting rod 2 from slipping out of the guide sleeve 203. Specifically, the limit sleeves 204 are welded and fixed on the lifting rod 2. The two limit sleeves 204 can prevent the lifting rod 2 from moving excessively upward or downward, reduce the risk of collision with the tensioning jack 7, and of course improve construction safety.
[0039] In this embodiment, it also includes two groups of buffer pads 6 arranged on the lower base plate 5 of the box beam and correspondingly located below the two lifting holes 402; here, the buffer pads 6 can be foam, wooden boards, etc.; by providing the buffer pads 6, it is possible to avoid collision between the tensioning jack 7 and the lower base plate, and at the same time, the tensioning jack 7 can be slowed down, so that the tensioning jack 7 can be stably placed at the designated position, thereby improving construction safety.
[0040] This embodiment also discloses a method for installing a tensioning jack for a low-clearance cast-in-place box beam, which is constructed using the installation device described above and includes the following steps:
[0041] S1: When casting the box beam, a manhole 401 and a lifting hole 402 are reserved on the upper top plate 4;
[0042] S2: hoisting the tensioning jack 7 into the box girder through the manhole 401, usually by a small crane or hoisting equipment;
[0043] S3: Hook the tensioning jack 7 onto the conveying rope 1. It can be understood that the tensioning jack 7 is generally provided with a hoisting portion, which can be hung on the conveying rope 1 through a hook and a wire rope;
[0044] S4: Adjust the height of the lifting rods 2 at both ends to change the inclination angle of the conveying rope 1, and push the tensioning jack 7 to slide along the conveying rope 1 to the vicinity of the corresponding prestressed tendon tensioning point. It can be understood that the one that is sent to the other side is adjusted lower, and the pushing is usually done by a worker pushing by hand;
[0045] S5: Hook the tensioning jack 7 at the bottom of the lifting rod 2, and lift the tensioning jack 7 through the lifting device 3 to complete the installation of the tensioning jack 7 on the upper top plate 4; it can be understood that at this time, the tensioning jack 7 can be first taken off the conveying rope 1, and then hung on the lifting rod 2. Of course, two sets of hooks can also be set on the tensioning jack 7, and one set can be hung on the lifting rod 2; after lifting to the set position, the tensioning jack 7 is assembled to the tooth block 403 at the corresponding position, and the subsequent tensioning construction of the prestressed tendons is completed;
[0046] The above-mentioned low-clearance cast-in-place box girder tensioning jack installation construction method has high installation efficiency and low labor intensity of workers; of course, it can be understood that the subsequent disassembly construction process is the opposite of the installation process, which will not be repeated here; after completing the construction of this part, it can be moved to the next construction position to repeat the above-mentioned construction until all tensioning points of the box girder are completed.
[0047] Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the purpose and scope of the technical solutions of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A tensioning jack installation device for a low net height cast-in-place box girder, characterized in that: It comprises a conveying rope (1), two groups of lifting rods (2) capable of being lifted and lowered in a single degree of freedom in a vertical direction, and two groups of lifting devices (3) respectively used for driving the corresponding lifting rods (2) to achieve lifting and lowering; The upper top plate (4) of the box beam is provided with a manhole (401) and two lifting holes (402), and the two lifting holes (402) are respectively and correspondingly arranged near two adjacent prestressed tendon tensioning points in the length direction of the box beam; The two sets of lifting rods (2) are slidably arranged in the two hanging holes (402) respectively, and the two ends of the conveying rope (1) are detachably connected to the bottom of the two sets of lifting rods (2) respectively.
2. The low net height cast-in-place box girder tensioning jack installation device according to claim 1 is characterized in that: The hoisting hole (402) is located on the side of the upper gear block (403) near the prestressed tendon tensioning point corresponding to the installation of the tensioning jack (7).
3. The tensioning jack installation device for low net height cast-in-place box beam according to claim 2 is characterized in that: The manhole (401) is located in the middle of the two lifting holes (402) along the length direction of the box beam.
4. The low net height cast-in-place box girder tensioning jack installation device according to claim 1 is characterized in that: An upper hoisting part (201) and a lower hoisting part (202) are respectively provided at the upper and lower ends of the lifting rod (2); the upper hoisting part (201) is connected to a corresponding side lifting device (3); and the lower hoisting part (202) is connected to a corresponding end of the conveying rope (1).
5. The low net height cast-in-place box girder tensioning jack installation device according to claim 4 is characterized in that: The upper hoisting portion (201) is an upper hoisting ring fixedly connected to the upper end of the lifting rod (2), the lower hoisting portion (202) is a lower hoisting ring fixedly connected to the lower end of the lifting rod (2), and the conveying rope (1) is a steel wire rope, and the two ends of the steel wire rope are respectively connected to the corresponding side lower hoisting rings through hooks.
6. The low net height cast-in-place box girder tensioning jack installation device according to claim 4 is characterized in that: The lifting device (3) comprises a movable support frame (301) and an electric hoist (302) arranged on the top of the movable support frame (301), and the working end of the electric hoist (302) is detachably connected to the upper lifting part (201) on the corresponding side.
7. The tensioning jack installation device for low net height cast-in-place box beam according to claim 1 is characterized in that: The sliding outer sleeve of the lifting rod (2) is provided with a guide sleeve (203), and the guide sleeve (203) is arranged in the lifting hole (401) in a manner that it can be taken out upwards.
8. The tensioning jack installation device for low net height cast-in-place box beam according to claim 7 is characterized in that: The lifting rod (2) is fixed with outer sleeves at both ends thereof, respectively, and is provided with limiting sleeves (204) for preventing the lifting rod (2) from sliding out of the guide sleeve (203).
9. The low net height cast-in-place box girder tensioning jack installation device according to claim 1, characterized in that: It also includes two groups of buffer pads (6) which are arranged on the lower bottom plate (5) of the box beam and are correspondingly located below the two lifting holes (402).
10. A method for installing a tensioning jack for a low net height cast-in-place box beam, using the installation device according to any one of claims 1 to 9, wherein: The steps include: S1: When casting the box girder, a manhole (401) and a lifting hole (402) are reserved on the upper top plate (4); S2: Hang the tensioning jack (7) into the box beam through the manhole (401); S3: Hook the tensioning jack (7) onto the conveying rope (1); S4: adjusting the height of the lifting rods (2) at both ends to change the inclination angle of the conveying rope (1), and pushing the tensioning jack (7) to slide along the conveying rope (1) to the vicinity of the corresponding prestressed tendon tensioning point; S5: Hook the tensioning jack (7) on the bottom of the lifting rod (2), and lift the tensioning jack (7) through the lifting device (3) to complete the installation of the tensioning jack (7) on the upper top plate (4).