Method for reinforcing sewage pipe soil body through retreating type segmented grouting

Through the backward segment grouting method, the sewage pipe soil is reinforced by double slurry of ordinary silicate cement and water glass with a label of no less than 42.5, which solves the sewage pipe safety problems caused by foundation pit excavation and realizes soil Stable reinforcement of the body and safety protection of sewage pipes.

CN118880852AInactive Publication Date: 2024-11-01CHINA CONSTR EIGHT ENG DIV CORP LTD
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411256487.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-09
Publication Date
2024-11-01
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The excavation of foundation pits leads to loosening of the sewage pipe, which can easily lead to sewage leakage and safety problems, and it is difficult to effectively solve the existing technology.

Method used

Reverse segmented grouting method is adopted, grouting holes are arranged below both sides of the sewage pipe, and grouting is carried out using double slurry with an equal ratio of ordinary silicate cement and water glass with a label of no less than 42.5 to reinforce the soil body. , the grouting pressure is controlled to not exceed 0.5MPa, the design elevation is lower than the top of the sewage pipe, and the jumping grouting and vertical segmented grouting are adopted to ensure soil strength and safety.

Benefits of technology

It effectively improves the strength and elastic deformation modulus of the soil, prevents the displacement of the sewage pipe, protects the safety of the sewage pipe, avoids soil disturbances caused by foundation pit excavation, and ensures the stability and safety of the sewage pipe.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118880852A_ABST
    Figure CN118880852A_ABST
Patent Text Reader

Abstract

The invention discloses a method for reinforcing a sewage pipe soil body through retreating type segmented grouting. The method comprises the following steps that 1, construction preparation is conducted; step 2, positioning and paying off; 3, grouting point position drilling is carried out; step 4, mixing double-liquid slurry; 5, double-liquid grouting is conducted till the designed elevation is reached; 6, hole jumping grouting is conducted; and step 7, grouting acceptance and monitoring. The invention relates to the technical field of foundation pit engineering, and can solve the problem that the safety of a sewage pipe is influenced by foundation pit excavation in the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit engineering, and in particular to a method for reinforcing soil of a sewage pipe by backward segmented grouting. Background Art

[0002] During the construction process in urban areas, sewage pipes are often encountered around foundation pits. Due to the excavation of the foundation pit, the soil around the sewage pipe will be disturbed. After the soil is loosened, it cannot provide reliable support for the sewage pipe, which can easily cause the sewage pipe to shift, leading to sewage leakage and affecting the safety of the sewage pipe. Therefore, it is necessary to provide a backward segmented grouting method for reinforcing the soil of the sewage pipe, which can solve the problem of the existing technology that the foundation pit excavation affects the safety of the sewage pipe. Summary of the invention

[0003] The purpose of the present invention is to provide a method for reinforcing the soil of a sewage pipe by backward segmented grouting, which can solve the problem in the prior art that foundation pit excavation affects the safety of the sewage pipe.

[0004] The present invention is achieved in that:

[0005] A method for reinforcing the soil of a sewage pipe by backward segmented grouting comprises the following steps:.

[0006] Step 1: Construction preparation;

[0007] Step 2: Positioning and laying out;

[0008] Step 3: Drill holes at grouting points;

[0009] Step 4: Mix the double liquid slurry;

[0010] Step 5: Double liquid grouting to the designed elevation;

[0011] Step 6: skip hole grouting;

[0012] Step 7: Grouting acceptance and monitoring.

[0013] In the step 1, the construction preparation includes: machinery and equipment, instruments, grouting pipelines, grouting materials, water, electricity inspection and necessary tests.

[0014] In step 2, for the first sewage pipeline adjacent to the foundation pit, grouting holes are arranged on both sides of the sewage pipe, and the soil under the sewage pipe is reinforced by the backward grouting method. The principle of arranging the grouting holes is to make the reinforced soil connected into a whole in plane and depth.

[0015] The cement slurry of the double liquid slurry has an ordinary silicate cement grade of not less than 42.5, and after the slurry solidifies, its volume shrinkage rate is less than 3‰ of the volume, and the slurry does not precipitate water within one hour.

[0016] The main materials of the double liquid slurry are ordinary Portland cement with a grade of 42.5 and water glass, which are configured in equal proportions, wherein the water-cement ratio is 3:1 and the water: water glass ratio is 4:1.

[0017] In the step 5, when grouting at a single grouting point, it is carried out in vertical sections. When the grouting pressure reaches 0.5PMa, it is immediately increased by 1m each time, and the grouting is continued until the grouting reaches the designed elevation, and then the grouting is stopped.

[0018] The design elevation of the double-liquid grouting is lower than the top elevation of the sewage pipe, so that the grouting area is located below the center elevation of the sewage pipe.

[0019] In step 7, after the grouting reinforcement begins, the grouting reinforcement effect of the soil below the sewage pipe is evaluated: if the daily settlement displacement value of the sewage pipe is no more than 0.04 mm for 7 consecutive days, the grouting reinforcement effect is judged to be good and the grouting can be stopped; otherwise, the grouting reinforcement is continued or the reinforcement scope is expanded.

[0020] In step 7, after the grouting reinforcement construction, daily inspections are carried out on the sewage pipeline and foundation pit surface; the content of the daily inspection of the sewage pipeline includes: cracks, water seepage and collapse of the ground along the sewage pipeline; cracks in ancillary facilities such as inspection wells and whether there is water accumulation in the inspection wells or the depth of water accumulation; the width of existing cracks found in the first inspection is measured and compared with the initial width on site. If the sewage pipeline continues to leak or cracks or water ingress are found in the inspection wells, they should be reported in time and photographed for archiving; during the inspection, fill in the on-site inspection form;

[0021] The contents of daily inspection of the pit surface include: leakage of enclosure; cracks on the foundation pit ground; ground subsidence and uplift; measuring the width of existing cracks found in the first inspection and comparing them with the initial width on site; and promptly reporting any abnormal conditions such as new ground cracks or crack development rates exceeding the warning standards and ground uplift, and taking photos for archiving.

[0022] Compared with the prior art, the present invention has the following beneficial effects:

[0023] 1. The present invention adopts backward segmented grouting, and grouting is performed to reinforce the soil below both sides of the sewage pipe along the pipeline direction by skip-hole grouting. The slurry is injected into the stratum in the form of extrusion, penetration and splitting at a determined pressure through the grouting pipeline, thereby improving the strength and elastic deformation modulus of the soil, effectively weakening the disturbance of the soil and sewage pipe caused by foundation pit excavation, preventing the displacement of the sewage pipe, and achieving the purpose of protecting the safety of the sewage pipe during the foundation pit excavation.

[0024] 2. The present invention adopts double liquid slurry with a water-cement ratio of 3:1 and a water: water glass ratio of 4:1 for grouting, and the grouting pressure does not exceed 0.5MPa. At the same time, the design elevation of the double liquid grouting is controlled not to exceed the top of the sewage pipe. While ensuring the grouting reinforcement effect, the displacement of the sewage pipe due to excessive pressure is avoided, thereby achieving the purpose of protecting the safety of the sewage pipe during the grouting reinforcement process. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a flow chart of the method for reinforcing the soil of a sewage pipe by backward segmented grouting according to the present invention;

[0026] Figure 2 It is a construction elevation view of the backward segmented grouting method for reinforcing the soil of a sewage pipe according to the present invention.

[0027] In the figure, 1 is foundation pit, 2 is sewage pipe, and 3 is grouting area. DETAILED DESCRIPTION

[0028] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0029] Please see attached Figure 1 A method for reinforcing soil of a sewage pipe by backward segmented grouting comprises the following steps:

[0030] Step 1: Construction preparation.

[0031] In the step 1, the construction preparation includes:

[0032] 1. Before determining the grouting reinforcement plan, the distribution range of the reinforced soil layer, water content, soil particle gradation, groundwater and porosity and other physical and mechanical properties of the soil should be found out. At the same time, it is necessary to determine the effective range of grouting, the selection of grouting materials, initial setting time, grouting volume and pressure, grouting hole arrangement and grouting sequence through investigation and research.

[0033] 2. The grouting process and effective range should be determined according to the different requirements of the project, and must fully meet the purposes of anti-seepage and leakage prevention, improving soil strength and modulus, filling voids and underpinning.

[0034] 3. The preparatory work before grouting includes inspection and necessary tests of machinery and equipment, instruments, grouting pipelines, grouting materials, water, electricity, etc.

[0035] 5. The grouting sequence must be suitable for the foundation soil conditions, site environment and grouting purpose. Generally, it is carried out in an interval skipping and skipping way to prevent grouting and improve the strength and restraint of the grouting hole. In the special case of underground dynamic water flow, the migration effect under the dynamic water flow should be considered, and grouting should be carried out from the end with high water head.

[0036] 6. The raw materials and mixed slurry (double liquid slurry) used for grouting should meet the following requirements:

[0037] 1) The mixed slurry should be able to solidify within the design time and have a certain strength, and its own impermeability and durability should meet the design requirements. In order to ensure the reinforcement effect, when using cement slurry for grouting, ordinary Portland cement with a grade of not less than 42.5 should be used.

[0038] 2) After solidification, the slurry should not have a large shrinkage rate, generally less than 3‰ of its volume.

[0039] 3) The mixed slurry does not precipitate water within one hour.

[0040] Step 2: Positioning and laying out the lines.

[0041] Please see attached Figure 1 In step 2, for the first sewage pipeline adjacent to the foundation pit 1, grouting holes are arranged on both sides of the sewage pipe 2, and the soil below the sewage pipe 2 is reinforced by the backward grouting method. The arrangement principle of the grouting holes should be such that the reinforced soil is connected into a whole in plane and depth.

[0042] In a certain foundation pit project, there are three existing sewage pipelines outside the foundation pit 1. For the first sewage pipeline (2400mm in diameter) adjacent to the foundation pit 1, a grouting reinforcement point is set at every 2.5m interval along the pipeline direction on both sides of the sewage pipe 2, and the deviation of each grouting hole position shall not exceed 6cm. According to the excavation scope of the foundation pit 1, the reinforcement length of the soil under the sewage pipe 2 is planned to be about 160m, with a total of 130 grouting points, and the grouting point serial numbers are compiled according to the grouting order.

[0043] Through the backward grouting method, the slurry is injected through the grouting pipe at a recognized pressure, so that the slurry is injected into the formation in the form of extrusion, penetration and splitting, thereby improving the strength and elastic deformation modulus of the soil, effectively weakening the disturbance of the soil and sewage pipe caused by the foundation pit excavation, and achieving the purpose of protecting the safety of the sewage pipe.

[0044] According to different soil types, the distance between the sewage pipe and the foundation pit and other actual working conditions, parameters such as grouting pressure, depth, and the spacing of grouting reinforcement points can be adjusted to ensure the grouting reinforcement effect.

[0045] Step 3: Drill holes at grouting points.

[0046] Specifically, according to the grouting point number, the ZLJ-1300 grouting machine is used to drill holes with a drilling depth of 20m. After the drilling rig is placed at the location where the hole needs to be drilled, the drilling rig base is firmly fixed to prevent the drilling rig from moving left and right during drilling and causing the hole to deviate. The verticality deviation of the drilling rig should be less than 1%.

[0047] Step 4: Mix the double liquid slurry.

[0048] Specifically, the design of the double-liquid slurry ratio must take into account the purpose of grouting, geological conditions, pore size of foundation soil, and state of groundwater, and the optimal ratio must be selected within the range that meets the required purpose to ensure the reinforcement effect.

[0049] Preferably, the main materials of the double liquid slurry are ordinary Portland cement with a grade of 42.5 and water glass, which are configured in equal proportions, wherein the water-cement ratio is 3:1 and the water: water glass ratio is 4:1.

[0050] Step 5: Double liquid grouting to the designed elevation.

[0051] After the grouting hole is drilled to the specified depth, double liquid grouting begins. The grouting pressure mainly depends on the double liquid slurry consistency, grouting depth and soil properties. In order to avoid excessive grouting pressure affecting the sewage pipe, the grouting pressure shall not exceed 0.5MPa.

[0052] When grouting at a single grouting point, adopt a backward vertical segmented approach. When the grouting pressure reaches 0.5PMa, increase it immediately by 1m each time, and continue grouting until the design elevation is reached, then stop grouting.

[0053] Please see attached Figure 2 The design elevation of the double-liquid grouting is lower than the top elevation of the sewage pipe 2, and is preferably consistent with the center elevation of the sewage pipe 2, so that the grouting area 3 is located below the center elevation of the sewage pipe 2 to prevent the grouting area 3 from covering the top of the sewage pipe 2 and causing excessive pressure, thereby causing the sewage pipe 2 to move.

[0054] During the grouting construction process, if the grouting interruption time is long or the interval time of double-liquid grouting is long, the pump and pipeline should be flushed in time to prevent the slurry from solidifying and adhering to the pump and pipeline.

[0055] Inspection methods for reinforcement grouting should include: excavation, drilling, penetration, standard penetration, load test, settlement observation, sampling strength inspection, etc. Load test should be carried out for important projects. The contour of the reinforcement body can be inspected by penetration test, and the strength of the reinforcement body should be tested by taking test blocks for infinite compression test, or by penetration test or standard penetration test evaluation.

[0056] During the construction process, detailed construction records, analysis and collation should be carried out, and deformation monitoring of the ground surface and nearby buildings (structures) should be carried out.

[0057] During the grouting process, the flow, pressure and injection volume of adjacent grouting holes should be compared frequently to analyze the problems in grouting and solve them in time. When the grouting pressure suddenly drops or the flow suddenly increases, the grouting should be stopped immediately to check whether there is grouting or leakage. When grouting or leakage occurs, the following measures should be taken:

[0058] 1) Stop grouting and seal;

[0059] 2) Reduce the pressure, thicken the slurry or use intermittent grouting.

[0060] 3) Use water glass and cement slurry for alternate grouting to make the injected slurry set quickly. When using alternate grouting, the grouting alternation amount and frequency should be strictly controlled according to the design.

[0061] After grouting is completed, the orifice valve should be temporarily closed, the pump and pipeline should be flushed in time, and the grouting pipe should be pulled out after the pressure in the hole is released. When the grouting of the entire hole is completed, the hole should be sealed with grouting liquid or cement mortar.

[0062] Step 6: Skip hole grouting.

[0063] The grouting of all grouting points is completed by skip hole grouting. Specifically, after the grouting of one grouting point is completed, the drilling rig is moved to the next grouting point. For the grouting points in the same row, interval grouting, i.e. skip hole grouting, is adopted.

[0064] Step 7: Grouting acceptance and monitoring.

[0065] After the grouting reinforcement construction, acceptance should be carried out, and the completion data should include: collected data, design documents, test reports, original construction records, various results charts and quality inspection and other relevant documents.

[0066] After the grouting reinforcement begins, the grouting reinforcement effect of the soil under the sewage pipe should be evaluated: if the daily settlement displacement value of sewage pipe 2 is no more than 0.04mm for 7 consecutive days, the grouting reinforcement effect is judged to be good and the grouting can be stopped; otherwise, the grouting reinforcement should be continued or the reinforcement scope should be expanded according to the actual situation on site.

[0067] After the grouting reinforcement construction, the construction workers and technicians should conduct daily inspections of the foundation pit. The project manager should lead the inspection team regularly, and all units should coordinate and communicate in a timely manner. The contents of daily inspections are as follows:

[0068] 1) Daily inspection of sewage pipelines. The contents include: cracks, water seepage and collapse of the ground along the sewage pipelines; cracks in ancillary facilities such as inspection wells and whether there is water accumulation in the inspection wells or the depth of water accumulation, etc. Measure the width of existing cracks found in the first inspection and compare it with the initial width on site. If abnormal conditions such as continuous leakage of sewage pipelines or cracks or water inflow in inspection wells are found, they should be reported in time and photographed for archiving. During the inspection, fill in the on-site inspection form.

[0069] 2) Daily inspection of the foundation pit surface. The content includes: enclosure leakage; foundation pit surface cracks; ground subsidence, uplift, etc. Measure the width of existing cracks found in the first inspection and compare it with the initial width on site. If new ground cracks or crack development rates exceed the warning standard, ground uplift and other abnormal conditions are found, report them in time and take photos for archiving.

[0070] The above are only preferred embodiments of the present invention and are not intended to limit the scope of protection of the invention. Therefore, any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. A method for reinforcing the soil of a sewage pipe by backward segmented grouting, characterized in that: The following steps are involved: 。 Step 1: Construction preparation; Step 2: Positioning and laying out; Step 3: Drill holes at grouting points; Step 4: Mix the double liquid slurry; Step 5: Double liquid grouting to the designed elevation; Step 6: skip hole grouting; Step 7: Grouting acceptance and monitoring.

2. The method for reinforcing the soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: In the step 1, the construction preparation includes: machinery and equipment, instruments, grouting pipelines, grouting materials, water, electricity inspection and necessary tests.

3. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: In step 2, grouting holes are arranged on both sides of the sewage pipe (2) for the first sewage pipe adjacent to the foundation pit (1), and the soil below the sewage pipe (2) is reinforced by a backward grouting method. The principle of arranging the grouting holes is to make the reinforced soil connected into a whole in plane and depth.

4. The method for reinforcing the soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: The cement slurry of the double liquid slurry has an ordinary silicate cement grade of not less than 42.5, and after the slurry solidifies, its volume shrinkage rate is less than 3‰ of the volume, and the slurry does not precipitate water within one hour.

5. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 or 4, characterized in that: The main materials of the double liquid slurry are ordinary Portland cement with a grade of 42.5 and water glass, which are configured in equal proportions, wherein the water-cement ratio is 3:1 and the water: water glass ratio is 4:

1.

6. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: In the step 5, when grouting at a single grouting point, it is carried out in vertical sections. When the grouting pressure reaches 0.5PMa, it is immediately increased by 1m each time, and the grouting is continued until the grouting reaches the designed elevation, and then the grouting is stopped.

7. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: The design elevation of the double-liquid grouting is lower than the top elevation of the sewage pipe (2), so that the grouting area (3) is located below the center elevation of the sewage pipe (2).

8. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: In step 7, after the grouting reinforcement is implemented, the grouting reinforcement effect of the soil below the sewage pipe is evaluated: if the daily settlement displacement value of the sewage pipe (2) is no more than 0.04 mm for 7 consecutive days, it is determined that the grouting reinforcement effect is good and the grouting can be stopped; otherwise, the grouting reinforcement is continued or the reinforcement range is expanded.

9. The method for reinforcing soil of a sewage pipe by backward segmented grouting according to claim 1 is characterized in that: In step 7, after the grouting reinforcement construction, daily inspections are carried out on the sewage pipeline and foundation pit surface; the content of the daily inspection of the sewage pipeline includes: cracks, water seepage and collapse of the ground along the sewage pipeline; cracks in ancillary facilities such as inspection wells and whether there is water accumulation in the inspection wells or the depth of water accumulation; the width of existing cracks found in the first inspection is measured and compared with the initial width on site. If the sewage pipeline continues to leak or cracks or water ingress are found in the inspection wells, they should be reported in time and photographed for archiving; during the inspection, fill in the on-site inspection form; The contents of daily inspection of the pit surface include: leakage of enclosure; cracks on the foundation pit ground; ground subsidence and uplift; measuring the width of existing cracks found in the first inspection and comparing them with the initial width on site; and promptly reporting any abnormal conditions such as new ground cracks or crack development rates exceeding the warning standards and ground uplift, and taking photos for archiving.

Citation Information

Patent Citations

  • Subsection retrusive slip-casting method for porthole slurry-stop mixed double-pipe within tube

    CN101251019A

  • Sublevel retreating type two-fluid composite grouting construction method for deep foundation pit of sandy gravel stratum

    CN103266614A

  • Karst cave and soil cave grouting treatment construction method and application thereof

    CN108999181A

  • Reinforcement and settlement prevention method for pipeline close to foundation pit

    CN116537159A

  • Retreating type segmented grouting construction method

    CN117662181A