Shallow basement and deep underground garage combined construction method
Through the combination of shallow basement and deep underground garage construction methods, the problems of high construction costs and long construction period of deep underground garages are solved, and the effect of increasing the number of parking spaces per unit area and saving costs and construction periods is achieved, reducing environmental disturbances and optimizing management cost.
Patent Information
- Application Number
- CN202411366424.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-29
- Publication Date
- 2024-11-01
AI Technical Summary
The construction of deep underground garages in the existing technology requires special site selection and phased construction, resulting in high costs and long construction periods, and the inability to effectively increase the number of parking spaces per unit area and unable to meet urban parking needs.
The method of combining shallow basement and deep underground garage is adopted. The deep underground garage does not need to be independently selected. It is set inside the existing shallow basement, and shares relevant facilities. It is through foundation pit enclosure, vertical support structure and horizontal support structure. Design, synchronous construction, saving costs and construction period.
It has achieved locally setting up deep garages within the shallow basement area, increasing the number of parking spaces per unit area, reducing costs and construction difficulties, saving construction periods, reducing environmental disturbances, sharing fire protection and ventilation facilities, and optimizing management costs.
Smart Images

Figure CN118880934A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of urban renewal and underground space development, and in particular relates to a method for combining the construction of a shallow basement with a deep underground garage in the development and construction of underground space. Background Art
[0002] With the rapid economic development and the improvement of people's living standards, the demand for urban parking is growing. According to data released by the National Development and Reform Commission, the average ratio of vehicles to parking spaces in my country's cities is about 1:0.7, and the parking space ratio is relatively low. The resulting "difficulty in parking" problem has seriously affected people's lives and travel.
[0003] However, the ground space in the city center is relatively scarce, and parking spaces are usually set up inside the underground space of buildings. In recent years, according to the requirements of relevant planning schemes, the requirements for parking space construction in new urban projects have become increasingly higher. However, due to a series of objective conditions such as the environment, cost and policies, the construction scale of underground parking garages cannot be increased indefinitely. Some projects have begun to study the construction of deep underground garages to increase the number of parking spaces per unit area.
[0004] In current existing technologies and related projects, deep underground garages are usually built separately at specially selected locations. The construction process also requires certain construction site requirements, and the basement of the main building needs to be built in phases, which will extend the total construction period. In addition to its main structure, deep underground garages also need to be equipped with independent fire protection, ventilation, smoke exhaust and maintenance systems, which are relatively expensive. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides a method for combining the construction of a shallow basement with a deep underground garage, which can be achieved in a new underground space project. The deep underground garage does not need to be located separately, but can be set up inside the existing underground garage, and the relevant supporting facilities can be shared.
[0006] A method for combining the construction of a shallow basement and a deep underground garage, the specific method is: Step 1: After the site is leveled, construct the foundation pit retaining structure and vertical support structure of the planned shallow basement; then construct the first horizontal support structure of the foundation pit; the first horizontal support structure of the foundation pit is rigidly connected to the vertical support structure and the foundation pit retaining structure; the planned deep underground garage is located inside the shallow basement; a construction platform is set up on the first horizontal support structure of the foundation pit, and the construction platform is arranged in the corresponding area of the upward projection of the deep underground garage.
[0007] Step 2: Continue to excavate the shallow basement foundation pit downwards, and gradually construct the horizontal supporting structures in the shallow basement until the excavation reaches the bottom of the shallow basement; the deep underground garage is simultaneously constructed below the elevation of the bottom of the shallow basement; the shallow basement foundation slab is poured to the outer wall of the deep underground garage, leaving a construction joint.
[0008] Step 3: Remove the horizontal support structure and construct the main structure of the shallow basement upwards; leave a construction hole for the main structure of the shallow basement within the construction range of the deep underground garage, and continue to construct the deep underground garage downwards; connect the outer wall of the deep underground garage with the foundation slab of the shallow basement.
[0009] Step 4: Construct the deep underground garage to the designed elevation, construct the structural bottom plate, and complete the overall structure of the deep underground garage; remove the first horizontal supporting structure of the foundation pit and the vertical supporting structure of the foundation pit inside the shallow basement, fill the construction hole of the main structure of the shallow basement, and complete the overall construction of the main structure of the shallow basement.
[0010] Based on the above technical features: the shape of the deep underground garage is circular, rectangular or polygonal.
[0011] Based on the above technical features: In step one, the foundation pit retaining body adopts underground continuous wall or bored cast-in-place piles.
[0012] Based on the above technical features: in step one, the vertical supporting structure of the foundation pit is bored cast-in-place piles or bored cast-in-place piles with inserted angle steel lattice columns or steel pipe piles.
[0013] Based on the above technical features: the first horizontal support structure and the horizontal support structure of the foundation pit are concrete supports or steel supports.
[0014] Based on the above technical features: In step one, the construction platform uses a concrete slab or a steel plate.
[0015] Based on the above technical features: the construction of deep underground garages adopts self-sinking caisson technology or press-in caisson technology or vertical shield technology or vertical jacking technology or sequential excavation.
[0016] Based on the above technical features: the vertical supporting structure of the foundation pit also serves as the reaction fulcrum of the deep underground garage construction facilities.
[0017] Another method of combining the shallow basement with the deep underground garage is as follows: Step 1: After the site is leveled, construct the foundation pit retaining body and the vertical supporting structure of the shallow basement; excavate downward to the elevation below the beam and slab structure of the first floor structure of the shallow basement, and construct the beam and slab structure of the first floor structure of the shallow basement; the beam and slab of the first floor structure of the shallow basement are rigidly connected to the vertical supporting structure and the foundation pit retaining body; the proposed deep underground garage is located inside the shallow basement; the beam and slab structure of the first floor structure of the shallow basement leaves a hole in the corresponding area of the upward projection of the proposed deep underground garage.
[0018] Step 2: Construct the main structure of the shallow basement downwards in reverse construction, and simultaneously construct the deep underground garage below the elevation of the shallow basement basement basement; leave a construction hole for the main structure of the shallow basement within the construction range of the deep underground garage, and connect the foundation slab of the shallow basement to the outer wall of the deep underground garage.
[0019] Step 3: Continue to construct the deep underground garage downward to the designed elevation, construct the structural bottom plate, and complete the overall structure of the deep underground garage; fill the construction holes of the main structure of the shallow basement; fill the holes in the beam and slab structure of the first floor of the shallow basement, and complete the overall construction of the main structure of the shallow basement.
[0020] Due to the adoption of the above scheme, the beneficial effects of the present invention are: (1) Deep garages are set up locally within the shallow basement of the building to increase the number of parking spaces per unit area, which can avoid the need to increase the number of shallow basement floors as a whole to meet the planning requirements. This can greatly reduce the cost of underground space development of the building and reduce the difficulty of construction of "deep and large" shallow basement foundation pits. Generally, the shallow basement is 6m to 20m high, and the deep underground garage can reach 50m to 70m high.
[0021] (2) The deep underground garage is combined with the existing main shallow basement garage. The relevant infrastructure indicators such as fire protection and ventilation can be coordinated and shared, which is conducive to saving management costs.
[0022] (3) The deep underground garage and the main shallow basement foundation pit are implemented simultaneously, without the need for phased implementation, which can save the overall construction period. The deep garage construction platform can be combined with the foundation pit support structure to save construction costs.
[0023] (4) During the construction process, although the deep underground garage is relatively deep, it is basically located inside the foundation pit of the main shallow basement, which has relatively little disturbance to the surrounding environment and the construction space is more controllable. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the plan relationship between the deep underground garage and the shallow basement foundation pit support structure in the technology of the present invention.
[0025] Figure 2It is a cross-sectional schematic diagram of the relationship between the shallow basement foundation pit support structure and the deep underground garage construction platform in the technology of the present invention.
[0026] Figure 3 It is a schematic diagram of the synchronous downward construction process of the shallow basement foundation pit and the deep underground garage in the technology of the present invention.
[0027] Figure 4 It is a schematic diagram of the shallow basement foundation pit in the technology of the present invention, the shallow basement main structure is built upward, and the deep underground garage continues to be constructed downward.
[0028] Figure 5 It is a schematic diagram of the final state of the shallow basement main structure and the deep underground garage after construction in the technology of the present invention.
[0029] The numbers in the figure are as follows: foundation pit retaining body 1; first horizontal supporting structure of foundation pit 2; horizontal supporting structure 21; construction platform 3; outer wall 4; vertical supporting structure of foundation pit 5; shallow basement foundation slab 6; shallow basement main structure 7; structural slab 8; deep underground garage 9; construction hole 10. DETAILED DESCRIPTION
[0030] The specific embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings. These embodiments are only used to illustrate the present invention, but not to limit the present invention.
[0031] In the description of the present invention, it should be noted that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0032] The present invention is a method for combining the construction of a shallow basement and a deep underground garage, wherein the deep underground garage is located inside the main shallow basement. Figure 1 The diagram shows the plane relationship between the deep underground garage and the shallow basement foundation pit support structure. The deep underground garage and the shallow basement foundation pit of the main building can be constructed simultaneously. Combined with the attached figure, the specific description is as follows.
[0033] Step 1: If Figure 2As shown, after the site is leveled, the foundation pit retaining body 1 and the foundation pit vertical supporting structure 5 of the planned shallow basement are constructed; the foundation pit retaining body 1 can adopt underground continuous walls, bored cast-in-place piles or other mature foundation pit retaining structures; the foundation pit vertical supporting structure 5 can adopt bored cast-in-place piles, bored cast-in-place piles with inserted angle steel lattice columns or steel pipe piles.
[0034] After the construction of the foundation pit retaining body 1 and the foundation pit vertical supporting structure 5 is completed and reaches the design strength requirements, the first horizontal supporting structure 2 of the foundation pit is constructed. The specific implementation method of this step can be: excavate downward to the elevation of the first horizontal supporting structure 2 of the foundation pit in the shallow basement, dig trenches to construct the first horizontal supporting structure 2 of the foundation pit, and rigidly connect the first horizontal supporting structure 2 of the foundation pit with the foundation pit vertical supporting structure 5 and the foundation pit retaining body 1; the first horizontal supporting structure 2 of the foundation pit can be made of concrete support or steel support.
[0035] A construction platform 3 is set up in the corresponding area of the upward projection of the proposed deep underground garage, and the construction platform 3 is set on the first horizontal support structure 2 of the foundation pit. The specific implementation method of this step can be: Figure 1 As shown, the specific specifications, dimensions and reinforcement of the first horizontal support structure 2 of the foundation pit in the construction platform 3 area are determined according to the construction load force calculation of the construction platform 3; the construction platform 3 can be cast together with the first horizontal support structure 2 of the foundation pit using a concrete slab, or the first horizontal support structure 2 of the foundation pit can be constructed first, and then a steel plate can be laid on the first horizontal support structure 2 of the foundation pit as the construction platform 3; Figure 1 The arrangement of the first horizontal support structure of the foundation pit in the construction platform 3 area shown in the figure is for reference only and can be arranged according to actual conditions.
[0036] Step 2: If Figure 3 As shown, the shallow basement foundation pit continues to be excavated downwards, and the deep underground garage 9 is constructed downwards synchronously. The specific implementation method of this step can be: the foundation pit is excavated downwards, and the remaining horizontal support structures 21 are constructed successively until the shallow basement basement is excavated. The deep underground garage is constructed downwards using self-sinking caisson technology, press-in caisson technology, vertical shield technology or vertical jacking technology.
[0037] The deep underground garage construction technology can also adopt other mature technologies in the existing deep garage construction field.
[0038] Construct the shallow basement foundation slab 6. The specific implementation method of this step can be: after the shallow basement foundation pit is excavated to the base, the shallow basement foundation slab 6 is poured to the four sides of the outer wall of the deep underground garage 9, and a construction joint is left.
[0039] Step 3: If Figure 4As shown, the horizontal support structure 21 is removed, and the main structure 7 of the shallow basement is constructed upwards; the main structure 7 of the shallow basement leaves a construction hole 10 within the construction range of the deep underground garage 9, and the deep underground garage 9 continues to be constructed downwards; the outer wall 4 of the deep underground garage 9 is connected to the shallow basement foundation slab 6, and after the construction of the outer wall 4 reaches the depth and the settlement is relatively stable, the shallow basement foundation slab 6 is rigidly connected to the outer wall 4 by means of steel bar embedding or reserved connectors to form a frame as a whole.
[0040] Step 4: If Figure 5 As shown, the deep underground garage 9 is constructed to the designed elevation, and the structural base plate 8 is constructed to complete the overall structure of the deep underground garage 9; the first horizontal supporting structure 2 of the foundation pit and the vertical supporting structure 5 of the foundation pit inside the shallow basement are demolished, and the construction hole 10 of the main structure 7 of the shallow basement is filled to complete the overall construction of the main structure 7 of the shallow basement.
[0041] As a special case of the above technical solution, when the main shallow basement foundation pit is constructed by reverse construction, the main shallow basement structure beams and slabs replace the temporary horizontal support structure of the foundation pit, and the construction platform of the deep underground garage can be set up in combination with the main shallow basement structure beams and slabs on the first floor. The construction steps are: Step 1: After the site is leveled, construct the foundation pit retaining body 1 and the foundation pit vertical supporting structure 5 of the proposed shallow basement; excavate downward to the elevation below the shallow basement first floor structural beam and slab structure, and construct the shallow basement first floor structural beam and slab structure; the shallow basement first floor structural beam and slab are rigidly connected to the foundation pit vertical supporting structure 5 and the foundation pit retaining body 1; the proposed deep underground garage 9 is located inside the shallow basement; the shallow basement first floor structural beam and slab structure leaves a hole in the corresponding area of the proposed deep underground garage 9 projected upward.
[0042] Step 2: Construct the main structure 7 of the shallow basement downwards in a reverse manner, and simultaneously construct the deep underground garage 9 below the elevation of the shallow basement basement; leave a construction hole for the lower room main structure 7 within the construction range of the deep underground garage 9, and connect the shallow basement foundation slab 6 to the outer wall of the deep underground garage 9.
[0043] Step 3: Continue to construct the deep underground garage 9 downward to the designed elevation, construct the structural bottom plate 8, and complete the overall structure of the deep underground garage 9; fill the construction hole of the main structure 7 of the shallow basement; fill the hole in the beam and slab structure of the first floor of the shallow basement, and complete the overall construction of the main structure 7 of the shallow basement.
[0044] The above are only preferred embodiments of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.
Claims
1. A method for combining the construction of a shallow basement and a deep underground garage, characterized in that: Step 1: After the site is leveled, a foundation pit retaining structure (1) and a foundation pit vertical support structure (5) of a proposed shallow basement are constructed; then the first horizontal support structure (2) of the foundation pit is constructed; the first horizontal support structure (2) of the foundation pit is rigidly connected to the foundation pit vertical support structure (5) and the foundation pit retaining structure (1); the proposed deep underground garage (9) is located inside the shallow basement; a construction platform (3) is set on the first horizontal support structure (2) of the foundation pit, and the construction platform (3) is arranged in a corresponding area of the upward projection of the deep underground garage (9); Step 2: Continue to excavate the shallow basement foundation pit downwards, and successively construct the various horizontal support structures (21) in the shallow basement until the shallow basement basement is excavated; the deep underground garage (9) is simultaneously constructed below the elevation of the shallow basement basement; the shallow basement foundation slab (6) is poured to the edge of the outer wall (4) of the deep underground garage (9), leaving a construction joint; Step 3: dismantle the horizontal support structure (21) and construct the shallow basement main structure (7) upwards; the shallow basement main structure (7) leaves a construction hole (10) within the construction range of the deep underground garage (9), and the deep underground garage (9) continues to be constructed downwards; connect the outer wall (4) of the deep underground garage (9) to the shallow basement foundation slab (6); Step 4: The deep underground garage (9) is constructed to the designed elevation, and the structural base plate (8) is constructed to complete the overall structure of the deep underground garage (9); the first horizontal support structure (2) of the foundation pit and the vertical support structure (5) of the foundation pit inside the shallow basement are removed, and the construction hole (10) of the main structure (7) of the shallow basement is filled to complete the overall construction of the main structure (7) of the shallow basement.
2. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: The deep underground garage (9) is circular, rectangular or polygonal in shape.
3. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: In the step 1, the foundation pit retaining body (1) is an underground continuous wall or bored cast-in-place piles.
4. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: In the step 1, the foundation pit vertical support structure (5) is bored cast-in-place piles or bored cast-in-place piles with inserted angle steel lattice columns or steel pipe piles.
5. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: The first horizontal support structure (2) of the foundation pit and the horizontal support structure (21) are concrete supports or steel supports.
6. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: In the step 1, the construction platform (3) is made of a concrete plate or a steel plate.
7. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: The deep underground garage (9) is constructed by using a self-sinking caisson technology, a press-in caisson technology, a vertical shield technology, a vertical pipe jacking technology, or a sequential excavation method.
8. The method for combining the construction of a shallow basement and a deep underground garage according to claim 1 is characterized by: The foundation pit vertical support structure (5) also serves as a reaction force fulcrum for the construction facilities of the deep underground garage (9).
9. A method for combining the construction of a shallow basement and a deep underground garage, characterized in that: Step 1: After the site is leveled, the foundation pit retaining structure (1) and the foundation pit vertical support structure (5) of the proposed shallow basement are constructed; excavation is carried out downward to the elevation below the beam and slab structure of the first floor structure of the shallow basement, and the beam and slab structure of the first floor structure of the shallow basement is constructed; the beam and slab of the first floor structure of the shallow basement is rigidly connected to the foundation pit vertical support structure (5) and the foundation pit retaining structure (1); the proposed deep underground garage (9) is located inside the shallow basement; the beam and slab structure of the first floor structure of the shallow basement leaves a hole in the corresponding area of the upward projection of the proposed deep underground garage (9); Step 2: construct the shallow basement main structure (7) downwards in a reverse construction method, and the deep underground garage (9) is simultaneously constructed below the elevation of the shallow basement basement; the shallow basement main structure (7) leaves a construction hole within the construction range of the deep underground garage (9), and the shallow basement foundation floor (6) is connected to the outer wall of the deep underground garage (9); Step 3: The deep underground garage (9) is constructed downwards to the designed elevation, and the structural base plate (8) is constructed to complete the overall structure of the deep underground garage (9); the construction hole of the main structure of the shallow basement (7) is filled; the hole of the beam and slab structure of the first floor of the shallow basement is filled to complete the overall construction of the main structure of the shallow basement (7).