Method for detecting heavy load and overload of time-sharing load of low-voltage user

By extracting time-sharing electrical energy data and user parameters, calculating the secondary average current and load rate, and judging the low-voltage user load status, the problem of the existing technology being unable to monitor the low-voltage user load is solved, and the detailed detection of the low-voltage user load is realized and Accurate analysis provides basic data for distribution network automation and power big data analysis.

CN118884084APending Publication Date: 2024-11-01SHENZHEN POWER SUPPLY BUREAU
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411003877.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-01

AI Technical Summary

Technical Problem

The existing low-voltage table area monitoring system cannot effectively monitor the load conditions of each low-voltage outgoing line and users under the distribution transformer, resulting in the failure to detect heavy load problems of individual users in a timely manner, and there are risks such as meter burning, electrical fires and misalignment, affecting users. Electricity experience.

Method used

A low-voltage user time-sharing load heavy overload detection method is proposed. By extracting time-sharing electrical energy data and user parameters, calculating the secondary average current and load rate, setting threshold values ​​to determine the load state, including non-heavy load, heavy load, overload and overload.

Benefits of technology

Realize detailed detection of low-voltage user loads, provide accurate time-sharing load rate data, fill the gap in low-voltage user load analysis, provide basic data for distribution network automation and power big data analysis, and help desk area line loss analysis .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118884084A_ABST
    Figure CN118884084A_ABST
Patent Text Reader

Abstract

The invention provides a method for detecting time-sharing heavy load and overload of low-voltage users, and the method comprises the steps: extracting time-sharing electric energy data and user parameters of a specified date of a target power user; wherein the electric energy data at least comprises a daily freezing reading; determining the time-sharing power of the user according to the daily freezing reading, determining the secondary average current of the user all day and in different time periods, and determining the average load rate according to the secondary average current; according to the average load rate, the overload condition of the load in the corresponding time period is determined; when the average load rate does not reach the first threshold value, judging that the time period is non-heavy load; when the average load rate reaches a first threshold value, it is judged that the time period is heavy load; when the average load rate reaches a second threshold value, it is judged that the time period is overload; when the average load rate reaches a third threshold value, it is judged that the time period is overload. According to the method, the heavy overload state of the user can be defined by refining to hour precision, the accurate time-sharing load rate can be calculated, and the blank of low-voltage user load analysis is filled.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of load overload detection, and in particular to a method for detecting time-sharing load overload of low-voltage users. Background Art

[0002] At present, the low-voltage area monitoring system of the distribution network is installed on the main outgoing line at the lower end of the distribution transformer. It can only monitor the total load of one transformer, but cannot monitor the load of each low-voltage outgoing line switch under the distribution transformer or even the load of low-voltage users, and cannot effectively support operation guidance and upper-level decision-making. Operation and maintenance personnel can only determine the user load through on-site measurement, and cannot remotely monitor the daily load of low-voltage users, so that the heavy load problems of individual users cannot be discovered in time, and there are risks such as burning meters, electrical fires, and inaccurate metering. In serious cases, it will cause frequent power outages for low-voltage users, affecting the user's electricity experience. Summary of the invention

[0003] The purpose of the present invention is to propose a method for detecting the heavy overload of the time-sharing load of low-voltage users, so as to solve the technical problem of how to detect the load of low-voltage users more accurately.

[0004] On the one hand, a method for detecting a heavy overload of a low-voltage user's time-sharing load is provided, comprising:

[0005] Extracting the time-sharing electric energy data and user parameters of the target electric power user on the specified date; wherein the electric energy data at least includes the daily frozen indication;

[0006] Determine the user's time-sharing power through the daily frozen reading, and determine the user's secondary average current for the whole day and in different time periods, and determine the average load rate through the secondary average current;

[0007] Determine the load or overload status in the corresponding time period according to the average load rate; when the average load rate does not reach the first threshold, determine that the time period is not overloaded; when the average load rate reaches the first threshold, determine that the time period is overloaded; when the average load rate reaches the second threshold, determine that the time period is overloaded; when the average load rate reaches the third threshold, determine that the time period is overloaded; wherein the third threshold is greater than the second threshold, and the second threshold is greater than the first threshold.

[0008] Preferably, the user parameters include at least user number, asset number, metering point number, calibrated current, phase line and comprehensive multiplier.

[0009] Preferably, the time division includes at least the whole day, peak period, peak period, peak period, flat period and trough period.

[0010] Preferably, determining the user's time-sharing power by daily frozen indication specifically includes:

[0011] The total power, peak power, peak power, peak power, flat power and valley power of the user's time-sharing are calculated through daily frozen indications;

[0012] Determine whether the calculation results meet the preset elimination conditions. If so, clean and eliminate the corresponding time-sharing calculation results of the user.

[0013] Preferably, the preset rejection conditions specifically include:

[0014] Any value of total power, peak power, peak power, peak power, flat power and valley power is less than zero;

[0015] The total power is less than any one of the peak power, peak power, peak power, flat power and valley power;

[0016] The absolute value of the difference between the total power and the sum of the peak power, the peak power, the flat power and the valley power is greater than one.

[0017] Preferably, the determination of the secondary average current of the user throughout the day and in different time periods specifically includes:

[0018] When the user's electric meter type is a single-phase meter, the total average current is determined according to the following formula:

[0019] I 总 =W 总 ÷U÷cosθ÷T 总

[0020] Among them, I 总 Represents the total average current, W 总 represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power;

[0021] The average current during the peak period is determined according to the following formula:

[0022] I 尖 =W 尖 ÷U÷cosθ÷T 尖

[0023] Among them, I 尖 Indicates the average current during the peak period, W 尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power;

[0024] The peak-average current is determined using the following formula:

[0025] I 峰 =W 峰 ÷U÷cosθ÷T 峰

[0026] Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power;

[0027] The average current during the peak period is determined according to the following formula:

[0028] I 尖峰 =W 尖峰 ÷U÷cosθ÷T 尖峰

[0029] Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power;

[0030] The average current in the flat period is determined according to the following formula:

[0031] I 平 =W 平 ÷U÷cosθ÷T 平

[0032] Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power;

[0033] The average valley current is determined according to the following formula:

[0034] I 谷 =W 谷 ÷U÷cosθ÷T 谷

[0035] Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

[0036] Preferably, the determination of the secondary average current of the user throughout the day and in different time periods also includes:

[0037] When the user's electric meter type is a three-phase meter, the total average current is determined according to the following formula:

[0038] I 总 =W 总 ÷U÷cosθ÷T 总 ÷3

[0039] Among them, I 总 Represents the total average current, W 总represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power;

[0040] The average current during the peak period is determined according to the following formula:

[0041] I 尖 =W 尖 ÷U÷cosθ÷T 尖 ÷3

[0042] Among them, I 尖 Indicates the average current during the peak period, W 尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power;

[0043] The peak-average current is determined using the following formula:

[0044] I 峰 =W 峰 ÷U÷cosθ÷T 峰 ÷3

[0045] Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power;

[0046] The average current during the peak period is determined according to the following formula:

[0047] I 尖峰 =W 尖峰 ÷U÷cosθ÷T 尖峰 ÷3

[0048] Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power;

[0049] The average current in the flat period is determined according to the following formula:

[0050] I 平 =W 平 ÷U÷cosθ÷T 平 ÷3

[0051] Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power;

[0052] The average valley current is determined according to the following formula:

[0053] I谷 =W 谷 ÷U÷cosθ÷T 谷 ÷3

[0054] Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

[0055] Preferably, determining the average load rate by the secondary average current specifically includes:

[0056] When the user's electric meter type is a single-phase meter or a three-phase direct-flow meter, the user's rated current is extracted from the calibrated current information;

[0057] When the user's electric meter type is a three-phase meter with a current transformer, the rated current of the current transformer is used as the user's rated current.

[0058] Preferably, determining the average load rate by the secondary average current further comprises:

[0059] Determine the total load factor using the following formula:

[0060] K 总 =I 总 ÷In×100%

[0061] Among them, K 总 Indicates the total load factor, I 总 In represents the total average current, and In represents the user's rated current;

[0062] The peak load factor is determined according to the following formula:

[0063] K 尖 =I 尖 ÷In×100%,

[0064] Among them, K 尖 represents the peak load factor, I 尖 represents the average current during the peak period;

[0065] The peak load factor is determined according to the following formula:

[0066] K 峰 =I 峰 ÷In×100%,

[0067] Among them, K 峰 Indicates the peak load factor, I 峰 represents the peak average current;

[0068] The peak load factor is determined according to the following formula:

[0069] K 尖峰=I 尖峰 ÷In×100%,

[0070] Among them, K 尖峰 Indicates the peak load rate, I 尖峰 Indicates the average current during the peak period;

[0071] The average load factor is determined according to the following formula:

[0072] K 平 =I 平 ÷In×100%,

[0073] Among them, K 平 Indicates the average load factor, I 平 Indicates the average current in the flat period;

[0074] The valley load factor is determined according to the following formula:

[0075] K 谷 =I 谷 ÷In×100%

[0076] Among them, K 谷 Indicates the valley load rate, I 谷 Represents the average current during the valley period.

[0077] Preferably, the determining of the load overload situation in the corresponding time period according to the average load rate specifically includes:

[0078] When the average load rate does not reach 80%, the period is determined to be non-heavy load;

[0079] When the average load rate reaches 80%, the period is judged as heavy load;

[0080] When the average load rate reaches 100%, the period is judged as overload;

[0081] When the average load rate reaches 120%, the period is determined to be overloaded.

[0082] In summary, the implementation of the embodiments of the present invention has the following beneficial effects:

[0083] The detection method for the heavy overload of low-voltage user time-sharing load provided by the present invention can define the user's heavy overload state with hourly accuracy, and can calculate the accurate time-sharing load rate, filling the gap in low-voltage user load analysis, providing basic data for the implementation of distribution network automation and power big data analysis, and at the same time providing strong assistance for line loss analysis in the substation area. BRIEF DESCRIPTION OF THE DRAWINGS

[0084] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, without paying creative labor, other drawings obtained based on these drawings still belong to the scope of the present invention.

[0085] Figure 1 The main flow diagram of a method for detecting a heavy overload of a low-voltage user's time-sharing load in an embodiment of the present invention is shown. DETAILED DESCRIPTION

[0086] In order to make the objectives, technical solutions and advantages of the present invention more clear, the present invention will be further described in detail below with reference to the accompanying drawings.

[0087] like Figure 1 FIG. 1 is a schematic diagram of an embodiment of a method for detecting a time-sharing overload of a low-voltage user provided by the present invention. In this embodiment, the method comprises the following steps:

[0088] Step S1, extracting the time-sharing electric energy data and user parameters of the target power user on the specified date; wherein the electric energy data at least includes the daily frozen indication; the user parameters at least include the user number, asset number, metering point number, calibrated current, phase line and comprehensive multiple; the time-sharing at least includes the whole day, peak period, peak period, peak period, flat period and valley period; it can be understood that the user time-sharing daily frozen indication of the specified date (T) and the day after the specified date (T+1) is extracted, including: the total daily indication W T总 , W T+1总 ; Peak period day number W T尖 , W T+1尖 ; Peak daily indication number W T峰 , W T+1峰 ; Average day indication W T平 , W T+1平 ;Valley date number W T谷 , W T+1谷 . Extract the target power user parameters, including user number, asset number, metering point number, calibrated current, phase line, comprehensive multiple, etc. Each user has a unique value corresponding to the above fields. If there are multiple target users, there will be multiple rows of corresponding parameter data. To accommodate all types of users, the calculation period is divided into 6 sections, including: total (full day), peak period, peak period, peak period (peak period plus peak period), flat period, and valley period.

[0089] Step S2, determine the user's time-sharing power through the daily frozen indication, and determine the user's secondary average current for the whole day and in different time periods, and determine the average load rate through the secondary average current; it can be understood that the user's time-sharing power is calculated through the daily frozen indication, and the data is proofread and cleaned to avoid factors such as sudden changes in metering data affecting the data accuracy.

[0090] In one embodiment, determining the user's time-sharing power through daily frozen indications specifically includes calculating the user's total time-sharing power, peak power, peak power, peak power, flat power and valley power through daily frozen indications; judging whether the calculation results meet preset exclusion conditions, and if so, cleaning and eliminating the time-sharing calculation results corresponding to the user.

[0091] Specifically, the preset elimination conditions specifically include: any one of the total power, apex power, peak power, spike power, flat power and valley power is less than zero; the total power is less than any one of the apex power, peak power, spike power, flat power and valley power; the absolute value of the difference between the total power and the sum of the apex power, peak power, flat power and valley power is greater than one.

[0092] Calculate the user's time-sharing power W through the daily frozen indication, including: total power W 总 =W T+1总 -W T总 Peak power W 尖 =W T+1尖 -W T尖 , Peak power W 峰 =W T+1峰 -W T峰 , Peak power W 尖峰 =W 尖 +W 峰 , average power W 平 =W T+1平 -W T平 , valley power W 谷 =W T+1谷 -W T谷 .

[0093] The data is cleaned and eliminated through user time-sharing power calculation, and the user data that meets the following conditions is eliminated:

[0094] (1)W 总 , W 尖 , W 峰 , W 尖峰 , W 平 , W 谷 Any value is less than zero;

[0095] (2)W 总 W尖 , W 峰 , W 尖峰 , W 平 , W 谷 Any value is small;

[0096] (3) |W 总 -(W 尖 +W 峰 +W 平 +W 谷 )|>1.

[0097] In one embodiment, the determination of the secondary average current of the user throughout the day and in different time periods specifically includes:

[0098] When the user's electric meter type is a single-phase meter, the total average current is determined according to the following formula:

[0099] I 总 =W 总 ÷U÷cosθ÷T 总

[0100] Among them, I 总 Represents the total average current, W 总 represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power;

[0101] The average current during the peak period is determined according to the following formula:

[0102] I 尖 =W 尖 ÷U÷cosθ÷T 尖

[0103] Among them, I 尖 Indicates the average current during the peak period, W 尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power;

[0104] The peak-average current is determined using the following formula:

[0105] I 峰 =W 峰 ÷U÷cosθ÷T 峰

[0106] Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power;

[0107] The average current during the peak period is determined according to the following formula:

[0108] I 尖峰=W 尖峰 ÷U÷cosθ÷T 尖峰

[0109] Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power;

[0110] The average current in the flat period is determined according to the following formula:

[0111] I 平 =W 平 ÷U÷cosθ÷T 平

[0112] Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power;

[0113] The average valley current is determined according to the following formula:

[0114] I 谷 =W 谷 ÷U÷cosθ÷T 谷

[0115] Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

[0116] When the user's electric meter type is a three-phase meter, the total average current is determined according to the following formula:

[0117] I 总 =W 总 ÷U÷cosθ÷T 总 ÷3

[0118] Among them, I 总 Represents the total average current, W 总 represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power;

[0119] The average current during the peak period is determined according to the following formula:

[0120] I 尖 =W 尖 ÷U÷cosθ÷T 尖 ÷3

[0121] Among them, I 尖 Indicates the average current during the peak period, W尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power;

[0122] The peak-average current is determined using the following formula:

[0123] I 峰 =W 峰 ÷U÷cosθ÷T 峰 ÷3

[0124] Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power;

[0125] The average current during the peak period is determined according to the following formula:

[0126] I 尖峰 =W 尖峰 ÷U÷cosθ÷T 尖峰 ÷3

[0127] Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power;

[0128] The average current in the flat period is determined according to the following formula:

[0129] I 平 =W 平 ÷U÷cosθ÷T 平 ÷3

[0130] Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power;

[0131] The average valley current is determined according to the following formula:

[0132] I 谷 =W 谷 ÷U÷cosθ÷T 谷 ÷3

[0133] Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

[0134] In this embodiment, the variables are defined and given initial values: voltage U = 0.22, power factor cosθ = 1, time T总 =24, T 尖 =3, T 峰 =4, T 尖峰 =7, T 平 =9, T 谷 = 8. This initial value complies with the current electricity price standard in Shenzhen, and is set as a variable to facilitate subsequent adaptation to changes in electricity price standards.

[0135] Calculate the secondary average current I of the user throughout the day and in different time periods, among which the total average current I of the single-phase meter user 总 =W 总 ÷U÷cosθ÷T 总 , peak average current I 尖 =W 尖 ÷U÷cosθ÷T 尖 , peak average current I 峰 =W 峰 ÷U÷cosθ÷T 峰 , the average current during the peak period I 尖峰 =W 尖峰 ÷U÷cosθ÷T 尖峰 , average current in the flat period I 平 =W 平 ÷U÷cosθ÷T 平 , valley average current I 谷 =W 谷 ÷U÷cosθ÷T 谷 .

[0136] Three-phase meter users: total average current I 总 =W 总 ÷U÷cosθ÷T 总 ÷3, peak average current I 尖 =W 尖 ÷U÷cosθ÷T 尖 ÷3, peak average current I 峰 =W 峰 ÷U÷cosθ÷T 峰 ÷3, average current during peak period I 尖峰 =W 尖峰 ÷U÷cosθ÷T 尖峰 ÷3, average current during normal period I 平 =W 平 ÷U÷cosθ÷T 平 ÷3, average current during valley period I 谷 =W 谷 ÷U÷cosθ÷T 谷 ÷3.

[0137] In one embodiment, the determination of the average load rate by the secondary average current specifically includes: when the user's meter type is a single-phase meter or a three-phase direct-flow meter, extracting the user's rated current from the calibrated current information; when the user's meter type is a three-phase meter with a current transformer, using the current transformer rated current as the user's rated current. The rated current value is defined in combination with the user's meter type, with the parameters for ensuring the operational safety of the metering device as a reference, wherein the single-phase meter user and the three-phase direct-flow meter user rated current In are extracted from the calibrated current information; the three-phase meter user rated current In with a current transformer is the current transformer rated current.

[0138] In one embodiment, determining the average load rate by the secondary average current further comprises:

[0139] Determine the total load factor using the following formula:

[0140] K 总 =I 总 ÷In×100%

[0141] Among them, K 总 Indicates the total load factor, I 总 In represents the total average current, and In represents the user's rated current;

[0142] The peak load factor is determined according to the following formula:

[0143] K 尖 =I 尖 ÷In×100%,

[0144] Among them, K 尖 represents the peak load factor, I 尖 represents the average current during the peak period;

[0145] The peak load factor is determined according to the following formula:

[0146] K 峰 =I 峰 ÷In×100%,

[0147] Among them, K 峰 Indicates the peak load factor, I 峰 represents the peak average current;

[0148] The peak load factor is determined according to the following formula:

[0149] K 尖峰 =I 尖峰 ÷In×100%,

[0150] Among them, K 尖峰 Indicates the peak load rate, I 尖峰 Indicates the average current during the peak period;

[0151] The average load factor is determined according to the following formula:

[0152] K 平 =I 平 ÷In×100%,

[0153] Among them, K 平 Indicates the average load factor, I 平 Indicates the average current in the flat period;

[0154] The valley load factor is determined according to the following formula:

[0155] K 谷 =I 谷 ÷In×100%

[0156] Among them, K 谷 Indicates the valley load rate, I 谷 Represents the average current during the valley period.

[0157] Step S3, determine the load overload situation in the corresponding time period according to the average load rate; when the average load rate does not reach the first threshold, determine the time period as non-heavy load; when the average load rate reaches the first threshold, determine the time period as heavy load; when the average load rate reaches the second threshold, determine the time period as overload; when the average load rate reaches the third threshold, determine the time period as overload; wherein the third threshold is greater than the second threshold, and the second threshold is greater than the first threshold. Define the non-heavy overload, heavy load, overload or overload label of each time period with a load rate of less than 80%, 80%, 100% or 120%, and mark each user with a corresponding heavy overload label for each time period according to the corresponding load rate, and take the corresponding label with the largest value in each time-sharing load rate of the user as the user's specified date attribute, so that each user has a unique heavy overload attribute for each specified date, and each user has a corresponding heavy overload label for each of the six time periods.

[0158] In one embodiment, the load and overload conditions in the corresponding time period determined according to the average load rate specifically include: when the average load rate does not reach 80%, the time period is determined to be non-heavy loaded; when the average load rate reaches 80%, the time period is determined to be heavy loaded; when the average load rate reaches 100%, the time period is determined to be overloaded; when the average load rate reaches 120%, the time period is determined to be overloaded.

[0159] In one embodiment, the calculation results of the specified date and all field data are stored in the server. If multiple date data are required, the date parameters are adjusted and steps S1 to S3 are repeated. The operation and maintenance personnel can query the user overload information of each user-specified date or specified time period from the server, and specify the metering device operation and maintenance plan for different time periods based on the user's time-divided overload label and user overload attribute.

[0160] In summary, the implementation of the embodiments of the present invention has the following beneficial effects:

[0161] The detection method for the heavy overload of low-voltage user time-sharing load provided by the present invention can define the user's heavy overload state with hourly accuracy, and can calculate the accurate time-sharing load rate, filling the gap in low-voltage user load analysis, providing basic data for the implementation of distribution network automation and power big data analysis, and at the same time providing strong assistance for line loss analysis in the substation area.

[0162] The above disclosure is only the preferred embodiment of the present invention, which certainly cannot be used to limit the scope of the present invention. Therefore, equivalent changes made according to the claims of the present invention are still within the scope of the present invention.

Claims

1. A method for detecting heavy overload of low-voltage user time-sharing load, characterized in that: include: Extracting time-sharing electric energy data and user parameters of a target electric power user on a specified date; wherein the electric energy data at least includes a daily frozen indication; Determine the user's time-sharing power through the daily frozen reading, and determine the user's secondary average current for the whole day and in different time periods, and determine the average load rate through the secondary average current; Determine the load or overload status in the corresponding time period according to the average load rate; when the average load rate does not reach the first threshold, determine that the time period is not overloaded; when the average load rate reaches the first threshold, determine that the time period is overloaded; when the average load rate reaches the second threshold, determine that the time period is overloaded; when the average load rate reaches the third threshold, determine that the time period is overloaded; wherein the third threshold is greater than the second threshold, and the second threshold is greater than the first threshold.

2. The detection method according to claim 1, characterized in that The user parameters include at least user number, asset number, metering point number, calibrated current, phase line and comprehensive multiplier.

3. The detection method according to claim 2, characterized in that The time-sharing includes at least the whole day, peak period, peak period, peak period, flat period and trough period.

4. The detection method according to claim 3, characterized in that Determining the user's time-sharing power by daily frozen indication specifically includes: The total power, peak power, peak power, peak power, flat power and valley power of the user's time-sharing are calculated through daily frozen indications; Determine whether the calculation results meet the preset elimination conditions. If so, clean and eliminate the corresponding time-sharing calculation results of the user.

5. The detection method according to claim 4, characterized in that: The preset rejection conditions specifically include: Any value of total power, peak power, peak power, peak power, flat power and valley power is less than zero; The total power is less than any one of the peak power, peak power, peak power, flat power and valley power; The absolute value of the difference between the total power and the sum of the peak power, the flat power, and the trough power is greater than one.

6. The detection method according to claim 5, characterized in that Determining the secondary average current of the user throughout the day and in different time periods specifically includes: When the user's electric meter type is a single-phase meter, the total average current is determined according to the following formula: AND 总 =In 总 ÷U÷cosθ÷T 总 Among them, I 总 Represents the total average current, W 总 represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power; The average current during the peak period is determined according to the following formula: AND 尖 =In 尖 ÷U÷cosθ÷T 尖 Among them, I 尖 Indicates the average current during the peak period, W 尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power; The peak-average current is determined using the following formula: AND 峰 =In 峰 ÷U÷cosθ÷T 峰 Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power; The average current during the peak period is determined according to the following formula: AND 尖峰 =In 尖峰 ÷U÷cosθ÷T 尖峰 Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power; The average current in the flat period is determined according to the following formula: AND 平 =In 平 ÷U÷cosθ÷T 平 Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power; The average valley current is determined according to the following formula: AND 谷 =In 谷 ÷U÷cosθ÷T 谷 Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

7. The detection method according to claim 6, characterized in that The determination of the secondary average current of the user throughout the day and in different time periods also includes: When the user's electric meter type is a three-phase meter, the total average current is determined according to the following formula: AND 总 =In 总 ÷U÷cosθ÷T 总 ÷3 Among them, I 总 Represents the total average current, W 总 represents total power, U represents voltage, cosθ represents power factor, T 总 Indicates the time corresponding to the total power; The average current during the peak period is determined according to the following formula: AND 尖 =In 尖 ÷U÷cosθ÷T 尖 ÷3 Among them, I 尖 Indicates the average current during the peak period, W 尖 represents the peak power, T 尖 Indicates the time corresponding to the peak power; The peak-average current is determined using the following formula: AND 峰 =In 峰 ÷U÷cosθ÷T 峰 ÷3 Among them, I 峰 Indicates the peak average current, W 峰 represents the peak power, T 峰 Indicates the time corresponding to the peak power; The average current during the peak period is determined according to the following formula: AND 尖峰 =In 尖峰 ÷U÷cosθ÷T 尖峰 ÷3 Among them, I 尖峰 Indicates the average current during the peak period, W 尖峰 represents the peak power, T 尖峰 Indicates the time corresponding to the peak power; The average current in the flat period is determined according to the following formula: AND 平 =In 平 ÷U÷cosθ÷T 平 ÷3 Among them, I 平 Indicates the average current in the flat period, W 平 represents the average power, T 平 Indicates the time corresponding to the average power; The average valley current is determined according to the following formula: AND 谷 =In 谷 ÷U÷cosθ÷T 谷 ÷3 Among them, I 谷 Represents the average current during valley period, W 谷 represents the valley power, T 谷 Indicates the time corresponding to the valley power.

8. The detection method according to claim 7, characterized in that Determining the average load rate by the secondary average current specifically includes: When the user's electric meter type is a single-phase meter or a three-phase direct-flow meter, the user's rated current is extracted from the calibrated current information; When the user's electric meter type is a three-phase meter with a current transformer, the rated current of the current transformer is used as the user's rated current.

9. The detection method according to claim 8, characterized in that: Determining the average load rate by the secondary average current also includes: Determine the total load factor using the following formula: K 总 =I 总 ÷In×100% Among them, K 总 Indicates the total load factor, I 总 In represents the total average current, and In represents the user's rated current; The peak load factor is determined according to the following formula: K 尖 =I 尖 ÷In×100%, Among them, K 尖 represents the peak load factor, I 尖 represents the average current during the peak period; The peak load factor is determined according to the following formula: K 峰 =I 峰 ÷In×100%, Among them, K 峰 Indicates the peak load factor, I 峰 represents the peak average current; The peak load factor is determined according to the following formula: K 尖峰 =I 尖峰 ÷In×100%, Among them, K 尖峰 Indicates the peak load rate, I 尖峰 Indicates the average current during the peak period; The average load factor is determined according to the following formula: K 平 =I 平 ÷In×100%, Among them, K 平 Indicates the average load factor, I 平 Indicates the average current in the flat period; The valley load factor is determined according to the following formula: K 谷 =I 谷 ÷In×100% Among them, K 谷 Indicates the valley load rate, I 谷 Represents the average current during the valley period.

10. The detection method according to claim 1, characterized in that: Determining the load overload situation in the corresponding time period according to the average load rate specifically includes: When the average load rate does not reach 80%, the period is determined to be non-heavy load; When the average load rate reaches 80%, the period is judged as heavy load; When the average load rate reaches 100%, the period is judged as overload; When the average load rate reaches 120%, the period is determined to be overloaded.