Topology layered optimization method, system and equipment of wind power plant current collection system and medium
By constructing a topological optimization model for search grid space and collecting system of substations, the optimal substation location of onshore wind farms was determined, and the problem of difficulty and high cost of substations with unevenly distributed fan clusters was solved, and cable and network losses were reduced cost effect.
Patent Information
- Application Number
- CN202410916286.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-09
- Publication Date
- 2024-11-01
AI Technical Summary
The topological optimization method of existing wind farm collecting systems is not suitable for onshore wind farms, especially in unevenly distributed fan clusters, where substation site selection is difficult, and the impact of wind power output characteristics on the cost of the current collecting system is not considered.
Use wind farm data information to build a substation search grid space, establish a set of feasible alternative connection solutions for the topology of the collecting system, and build an optimization model to solve the optimal substation location. Combined with the internal and external optimization algorithm, determine the optimal substation location to reduce the cable and Network loss cost.
It effectively solves the problem of substation site selection for unevenly distributed fan clusters, reduces cable and grid losses costs, and improves the economy and investment returns of the wind farm.
Smart Images

Figure CN118886145A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of topology optimization, and relates to a topology layered optimization method, system, equipment and medium for a wind farm power collection system. Background Art
[0002] The large-scale wind power and photovoltaic base in Shagohuang is an important support for the construction of new power systems. With the continuous advancement of the construction of large bases, it will bring significant growth to the development of new energy. At the same time, the subsidies for new energy power generation are tightened, and the grid-connected power is implemented at a parity price, participating in market competition like general thermal power. However, the construction cost of Shagohuang new energy power generation is high, higher than that of thermal power units. Therefore, how to improve the economic efficiency of power generation in large-scale new energy bases needs to be solved urgently.
[0003] For large-scale wind farms, the power collection system is an important component. Its optimization design is not only related to the initial construction cost, but also has a great impact on the operation loss and maintenance costs after commissioning. It is the focus of wind farm planning. At present, there are a large number of literatures on the topological optimization of wind power collection systems. The literature [Fu Yang, Wu Jing, Wei Shurong. Topological structure optimization and planning of power collection systems for large offshore wind farms [J]. Power System Technology, 2013, 37(09): 2553-2558. DOI: 10.13335 / j.1000-3673.pst.2013.09.033.] uses a parthenogenetic algorithm to target the common structures of the power collection system and takes the cable cost as the optimization target to establish an economic optimization model. References [Wei Shurong, Fu Yang, Huang Lingling. Optimization method of topological structure of medium-voltage collector system in large offshore wind farms [J]. Journal of Shanghai Electric Power University, 2015, 31(03): 201-205+213.] The method of optimizing the design of single-parent genetic algorithm was used to optimize the ring structure collector system and build an offshore wind farm electrical system cost optimization model. References [Wang Weiyuan, Qiao Ying, Dou Fei, etc. Topological optimization of offshore wind farm collector system based on improved genetic algorithm [J]. China Electric Power, 2019, 52(01): 63-68.] For the optimization problem of topological structure of large-scale offshore wind power collector system, the single-parent genetic algorithm was improved and a collector system full life cycle cost present value calculation model was established. Reference [Yuan Yukuan, Chen Xiaoyue, Huang Hai, et al. Topology optimization of large-scale offshore wind power collection system based on improved parthenogenetic algorithm [J]. Hydropower Energy Science, 2023, 41(01): 212-216. DOI: 10.20040 / j.cnki.1000-7709.2023.20220392.] An optimization design method for cable layout of offshore wind farm collection system and an optimization design method for offshore substation location were established to determine the optimal layout of the overall design of the wind farm. Reference [Sun Ruijuan, Liang Jun, Wang Kewen, et al. A review of research on offshore wind power collection system [J]. Electric Power Construction, 2021, 42(06): 105-115.] For AC collection and multi-terminal flexible direct current transmission grid connection of offshore wind farms, a multi-objective optimization planning model that takes into account both economy and reliability was established by considering the coupling of topology and flow. Reference [Liang Yutao, Lin Shunjiang, Feng Xiangyong, etc. Multi-objective optimization planning of AC collection and multi-terminal flexible direct current transmission grid-connected system of offshore wind farm [J / OL]. Power System Technology: 1-13 [2023-11-20]. https: / / doi.org / 10.13335 / j.1000-3673.pst.2023.0860.] Considering the optimal configuration of switches and the comprehensive cost of reliability, a full life cycle optimization model of offshore wind collection system was constructed. However, most of the existing studies are based on offshore wind farms, where wind turbines can be evenly distributed and there is no influence of terrain distribution.However, the terrain distribution of onshore wind farms is complex, and the layout of substations and wind turbines is highly uncertain. The existing topology optimization methods and models of the power collection system are not fully applicable. In addition, wind power output is intermittent and random, and the impact of wind farm output characteristics on the cost of the power collection system needs to be considered, which is not covered by existing optimization methods.
[0004] The topological structure of the onshore wind farm collection system is as follows: Figure 1a and Figure 1b As shown. The chain structure without backup is also called radial structure. It has a simple topology and low construction cost and is widely used in engineering [Wang Bangyan, Wang Xiuli, Shuai Xuanyue, etc. Centralized topology optimization of offshore wind farm collection system based on tidal current and reliability linearization analysis [J]. Electric Power Automation Equipment, 2023, 43(08): 96-104. DOI: 10.16081 / j.epae.202302010.]. Therefore, the radial structure collection system is generally selected as the basic form of the onshore wind farm scene. The onshore wind farm collection system consists of wind turbine export lines, circuit breakers and substations. The optimization content includes wind turbine topology connection, cable selection and substation site selection.
[0005] Onshore wind farms collect the electricity generated by wind turbines to substations through the power collection system. The location of the substation will affect the overall layout of the power collection system from the outside, and then affect its internal topology and cost. From an engineering perspective, building a substation in the center of the wind farm can reduce the overall investment. However, for onshore wind farms, due to terrain constraints, the wind turbines in the wind turbine cluster are unevenly distributed, so it is difficult to select a substation site. Summary of the invention
[0006] The purpose of the present invention is to overcome the shortcomings of the above-mentioned prior art and provide a method, system, device and medium for topological hierarchical optimization of a wind farm collection system. The method, system, device and medium can solve the substation site selection problem of unevenly distributed wind turbine clusters.
[0007] In order to achieve the above object, the present invention adopts the following technical scheme:
[0008] In one aspect of the present invention, the method for topological layered optimization of a wind farm power collection system according to the present invention comprises:
[0009] Obtain wind farm data information;
[0010] Constructing a substation search grid space according to the wind farm data information;
[0011] According to the wind farm data information, a set of feasible alternative connection schemes for the collection system topology is established in the substation search grid space;
[0012] Constructing a topology optimization model of the power collection system according to a set of feasible alternative connection schemes of the power collection system topology;
[0013] Solve the collection system topology optimization model to obtain the optimal substation location and output it.
[0014] The wind farm power collection system topology hierarchical optimization method of the present invention is further improved in that:
[0015] Furthermore, the wind farm data information includes location information of the substation.
[0016] Furthermore, the process of constructing a substation search grid space according to the wind farm data information is as follows:
[0017] Get the search distance;
[0018] taking the location of the substation as a candidate center;
[0019] A substation search grid space is constructed according to the candidate centers and the search intervals.
[0020] Furthermore, the process of solving the collection system topology optimization model, obtaining the optimal substation location and outputting it is as follows:
[0021] Solving the collector system topology optimization model to obtain the current optimal substation center location;
[0022] Determine whether the center position of the currently selected optimal substation is consistent with the center position of the candidate;
[0023] When the center position of the currently selected optimal substation is inconsistent with the center position of the candidate, the current search interval is expanded and the center position of the currently selected optimal substation is recalculated;
[0024] When the center position of the current preliminary optimal substation is consistent with the position of the candidate center, it is determined whether the current search interval is less than or equal to the preset minimum search interval. When the current search interval is less than or equal to the preset minimum search interval, the center position of the current preliminary optimal substation is used as the optimal substation position and output; when the current search interval is greater than the preset minimum search interval, the current search interval is reduced and the center position of the preliminary optimal substation is recalculated.
[0025] Furthermore, the objective function of the current collection system topology optimization model is:
[0026] minC=C cable +C loss
[0027]
[0028] Among them, A0 is the annual value-present value conversion coefficient, C cable is the cable cost, C lossis the present value of network loss cost, c i,j,t represents the purchase and installation cost per unit length of cable of model t between nodes i and j, c e is the on-grid electricity price of onshore wind power, P N is the rated output of the fan, P sum is the sum of the average output of the fans, p s is the probability of scenario s occurring, d ij is the distance between unit i and unit j, y i,j,t A 0-1 variable indicating whether there is a cable of type t between nodes i and j, I i,1,s is the current transmitted from node i to node 1 through the branch between nodes in scenario s, N w is the set of unit nodes, and S is the set of scenarios.
[0029] Furthermore, the constraints of the power collection system topology optimization model include voltage constraints, cable operating current constraints and topology constraints.
[0030] In a second aspect of the present invention, the wind farm power collection system topology hierarchical optimization system of the present invention comprises:
[0031] A first acquisition module is used to acquire wind farm data information;
[0032] A first construction module is used to construct a substation search grid space according to the wind farm data information;
[0033] An establishment module is used to establish a feasible alternative connection scheme set of the collection system topology in the substation search grid space according to the wind farm data information;
[0034] A second construction module is used to construct a topology optimization model of the power collection system according to the set of feasible alternative connection schemes of the power collection system topology;
[0035] The first solving module is used to solve the collection system topology optimization model, obtain the optimal substation location and output it.
[0036] The wind farm power collection system topology hierarchical optimization system of the present invention is further improved in that:
[0037] Furthermore, the first building block includes:
[0038] A second acquisition module is used to acquire the search distance;
[0039] A setting module, used for taking the location of the substation as a candidate center;
[0040] The third construction module is used to construct a substation search grid space according to the candidate center and the search interval.
[0041] Furthermore, the first solution module includes:
[0042] The second solving module is used to solve the topology optimization model of the power collection system to obtain the current preliminary optimal substation center position;
[0043] A judgment module, used to judge whether the center position of the currently selected optimal substation is consistent with the center position of the candidate;
[0044] The first processing module is used to expand the current search interval and recalculate the center position of the preliminary optimal substation when the center position of the current preliminary optimal substation is inconsistent with the center position of the candidate;
[0045] The second processing module is used to determine whether the current search interval is less than or equal to the preset minimum search interval when the center position of the current preliminary optimal substation is consistent with the position of the candidate center. When the current search interval is less than or equal to the preset minimum search interval, the center position of the current preliminary optimal substation is used as the optimal substation position and output; when the current search interval is greater than the preset minimum search interval, the current search interval is reduced and the center position of the preliminary optimal substation is recalculated.
[0046] In a third aspect of the present invention, the computer device described in the present invention includes a memory, a processor, and a computer program stored in the memory and executable on the processor, and the processor implements the steps of the wind farm collection system topology layering optimization method when executing the computer program.
[0047] In a fourth aspect of the present invention, the computer-readable storage medium of the present invention stores a computer program, and when the computer program is executed by a processor, the steps of the wind farm collection system topology layering optimization method are implemented.
[0048] The present invention has the following beneficial effects:
[0049] During specific operation, the method, system, equipment and medium for hierarchical optimization of the wind farm collection system topology described in the present invention establish a set of feasible alternative connection schemes for the collection system topology within the substation search grid space, construct a collection system topology optimization model based on the set of feasible alternative connection schemes for the collection system topology, and then solve the collection system topology optimization model, that is, the inner layer collection system topology optimization and the outer layer substation location optimization are used to determine the optimal substation location and output it, so as to solve the substation site selection problem of unevenly distributed wind turbine clusters, provide a theoretical basis for onshore wind farm planning and design, and are of great significance to improving the investment returns of renewable energy power generation. BRIEF DESCRIPTION OF THE DRAWINGS
[0050] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the accompanying drawings:
[0051] Figure 1a It is a structural diagram of the radial current collection system;
[0052] Figure 1b It is the structural diagram of the single-sided ring type current collection system;
[0053] Figure 2 is a flow chart of the method of the present invention;
[0054] Figure 3 This is a schematic diagram of the continuous output curve of a wind farm;
[0055] Figure 4 The distribution map of wind turbines in the wind farm;
[0056] Figure 5 This is the connection diagram of the collector system of Scheme 1;
[0057] Figure 6 Searching for feasible alternative topological connection diagrams for a substation location;
[0058] Figure 7 It is the principle diagram of the iterative process of the PS algorithm;
[0059] Figure 8 This is the optimal layout diagram of the collector system for Scheme 2;
[0060] Fig. 9 This is the topology optimization result diagram of the collector system under the original substation location in Scheme 3;
[0061] Fig.10 It is a system structure diagram of the present invention. DETAILED DESCRIPTION
[0062] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiment of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiment of the present invention. Obviously, the described embodiment is only an embodiment of a part of the present invention, not all embodiments, and is not intended to limit the scope of the present invention. In addition, in the following description, the description of well-known structures and technologies is omitted to avoid unnecessary confusion of the concepts disclosed in the present invention. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work should fall within the scope of protection of the present invention.
[0063] The accompanying drawings show schematic diagrams of structures according to embodiments disclosed in the present invention. These figures are not drawn to scale, and some details are magnified and some details may be omitted for the purpose of clear expression. The shapes of various regions and layers shown in the figures and the relative sizes and positional relationships therebetween are only exemplary, and may deviate in practice due to manufacturing tolerances or technical limitations, and those skilled in the art may additionally design regions / layers with different shapes, sizes, and relative positions according to actual needs.
[0064] Embodiment 1
[0065] refer to Figure 2 The wind farm power collection system topology hierarchical optimization method of the present invention comprises the following steps:
[0066] 1) Obtain wind farm data information;
[0067] The collected wind farm data information includes the continuous output curve of the wind farm, the longitude position information and latitude position information of each wind turbine, the original longitude position information and latitude position information of the substation, the total installed capacity of the wind farm, the voltage of the wind farm collection system, the rated power of a single wind turbine, the wind power grid-connected electricity price, the capital discount rate, the wind farm operation years and cable parameters of different conductor models, and the cable parameters include conductor model, unit price, current carrying capacity and resistance.
[0068] 2) constructing a substation search grid space according to the wind farm data information;
[0069] The original longitude and latitude positions of the substation are used as the initial candidate positions of the substation specified by the PS algorithm, and the minimum search spacing and the initial search spacing are set. The candidate position is used as the candidate center, and the initial 3x3 substation search grid space is generated according to the search spacing. The 3x3 substation search grid space includes 9 search points in total including the candidate point and its surrounding 8 directions.
[0070] 3) establishing a set of feasible alternative connection solutions for the collection system topology in the substation search grid space according to the wind farm data information;
[0071] According to the longitude and latitude location information of each wind turbine and the substation search grid space, a set of feasible alternative connection schemes for the collection system topology in the substation search grid space is generated by setting the location parameters of each unit separately, and is represented by the set E in the directed graph as follows:
[0072] E={(i,j)|(i,j)∈E',r i -r j >βd ij}
[0073] ∪{(j,i)|(i,j)∈E',r j -r i >βd ij}
[0074] Among them, r i is the distance from unit i to the substation, r j is the distance from unit j to the substation, d ij is the distance between unit i and unit j, β is a parameter ranging from 0 to 1, and β represents the utilization rate of the line between unit i and unit j.
[0075] 4) constructing a topology optimization model of the power collection system according to the set of feasible alternative connection schemes of the power collection system topology;
[0076] The specific operations of step 4) are:
[0077] 41) Generate wind power output scenarios;
[0078] The continuous output continuity curve of the wind farm is selected as the data object, and the step function is used to fit the continuous output continuity curve of the wind farm to obtain an N-step output continuity curve, in which the output value and duration of a step correspond to a scenario and its probability respectively. In order to ensure the effectiveness of the safety constraint of the maximum output, the maximum output scenario point (0,1) is added to effectively avoid the problem of maximum output reduction, and finally N+1 output scenarios and their corresponding probabilities are obtained.
[0079] 42) Multi-cable power flow constraints and their linearization;
[0080] Through the power flow calculation of the collection system, the voltage and line current information of each node in the system are obtained to calculate the network loss. Since the power generated by the wind turbine unit is almost all active power, the reactive power generated by the reactance in the collection system is extremely small compared to the active power generated by the wind turbine. Therefore, the power flow calculation is simplified, and only the active power flow is considered and linearized, where the current and voltage are both per unit values, that is:
[0081]
[0082] Among them, I i,j,s is the current transmitted from node i to node j through the branch between nodes in scenario s, I i,s is the injected current of node i in scenario s, I a,i,s is the current transmitted from node a to node i through the branch between nodes in scenario s, N w is the charter unit node set, and N is the union of the unit node set and the substation node set.
[0083] Since the voltage of each node is close to 1, I = P / U is Taylor expanded about U at 1 to:
[0084] I i,s =P i,s (2-U i,s )
[0085] Among them, P i,s is the injected power of node i in scenario s, U i,s is the voltage of node i in scenario s.
[0086] The current equations of all wind turbine nodes are obtained as follows:
[0087]
[0088] Let y i,j A 0-1 variable indicating whether there is a cable between node i and node j, y i,j,t A 0-1 variable indicating whether there is a cable of type t between nodes i and j. A value of 1 indicates that there is a cable of type t between nodes i and j, satisfying the constraint:
[0089]
[0090] The voltage drop on each line is U=IR. The voltage-current relationship considering the topological connection is established using the large M method:
[0091]
[0092] Where M is a sufficiently large number, d i,j is the distance between node i and node j, R t Indicates the resistance per unit length of a cable of model t, where T is a set of cable models.
[0093] The voltage-current relationship of the topological connection considered has a continuous variable I i,j,s With 0-1 variable y i,j,t The multiplied term is a quadratic constraint. At this time, the collector system topology optimization model is a mixed integer quadratic constraint programming problem. In order to linearize it, the variable I is introduced. s,i,j,t for:
[0094] I s,i,j,t =I i,j,s y i,j,t
[0095] Among them, I s,i,j,t is the current transmitted from node i to node j through cable t in scenario s. s,i,j,t For variable I i,j,s With variable y i,j,t The product of , adding constraints:
[0096]
[0097] Is,i,j,t ≤My i,j,t (i,j)∈E,t∈T,s∈S
[0098] Then the voltage and current relationship considering the topological connection is modified as follows:
[0099]
[0100] The substation is directly connected to the power grid. The power grid is regarded as an infinite power grid. The substation node can be set as a balance node. Node 1 is set as the substation node and the wind turbine node is set as the power node. The voltage constraint condition is:
[0101] U 1,s =1p.us∈S
[0102] 1p.u.≤U i,s ≤1.05pui∈N w ,s∈S
[0103] The cable operating current constraint conditions are:
[0104]
[0105] Among them, I t Indicates the current carrying capacity of cable model t.
[0106] 43) Construct topological constraints;
[0107] In the optimization of the collector system with radial topology, according to the principle that the outlet branch of the wind turbine is unique and the cables cannot cross each other, the topological constraint is:
[0108]
[0109] y i,j +y a,f ”1(i,j,a,f)∈X
[0110] Among them, y a,f A 0-1 variable indicating whether there is a cable between node a and node f. X is the intersection set, which is calculated by enumeration of mutual straddling experiments. The element (i,j,a,f) indicates that (i,j) intersects (a,f).
[0111] 44) Construct the objective function of the topology optimization model of the power collection system;
[0112] The optimization cost of the collection system takes into account the economic differences, that is, the costs of different topological connections and different cable selections and the network loss costs. The present value is used to calculate the network loss over the entire life cycle, and the annual value-present value conversion coefficient A0 is recorded as:
[0113]
[0114] Among them, r is the discount rate and T0 is the project cycle.
[0115] The objective function of the topology optimization model of the collector system is obtained as follows:
[0116] minC=C cable +C loss
[0117]
[0118] Among them, C cable is the cable cost, C loss is the present value of network loss cost, c i,j,t represents the purchase and installation cost per unit length of cable of model t between nodes i and j, c e is the on-grid electricity price of onshore wind power, P N is the rated output of the fan, P sum is the sum of the average output of the fans, p s is the probability of scenario s occurring.
[0119] Finally, based on the directed graph E of the set of feasible alternative connection schemes of the system topology in the substation search grid space, a collection system topology optimization model is established to optimize the economic efficiency of the collection system. The optimal topology of the system in the substation search grid space and its total cost are calculated, and the substation search point with the lowest economic cost is selected as the preliminary optimal substation center location.
[0120] 5) Solve the collection system topology optimization model to obtain the optimal substation location and output it.
[0121] The process of step 5) is:
[0122] 51) Solving the topology optimization model of the power collection system to obtain the current optimal substation center position;
[0123] 52) Determine whether the center position of the current preliminary optimal substation is consistent with the position of the candidate center. When the center position of the current preliminary optimal substation is inconsistent with the original candidate center, double the search interval, and then go to step 2) to recalculate the center position of the preliminary optimal substation; otherwise, determine whether the current search interval is less than or equal to the minimum search interval. When the current search interval is less than or equal to the minimum search interval, take the center position of the current preliminary optimal substation as the optimal substation position and output it. Otherwise, reduce the current search interval by half, and then go to step 2) to recalculate the center position of the initial optimal substation.
[0124] Embodiment 2
[0125] Taking the annual output continuity curve of a 99MW wind farm as an example, 11 output scenarios and their corresponding probabilities are obtained, such as Figure 3 As shown, the horizontal axis represents the percentage of time in a year, and the vertical axis represents the output per unit value based on the installed capacity.
[0126] Select a typical scenario of the UK BOWF wind farm, wind turbine distribution and substation location information such as Figure 4 As shown, the rated power of a single wind turbine is 6MW, there are 30 wind turbines in total, the total installed capacity of the wind farm is 180MW, the wind turbine output is simulated using the 11 output scenarios constructed above, the wind farm collection system voltage is 35kV, the wind power on-grid electricity price is 0.38 yuan / kWh, the capital discount rate is 0.05, and the wind farm operates for 25 years.
[0127] Table 1 gives the cable parameters of different conductor types in the wind farm collection system. Among them, the 3×630 cable has the largest current carrying capacity and can connect 8 wind turbines. There are a total of 30 wind turbines in the wind farm. Considering the maximum number of cable connections, it needs to be divided into 3.75 partitions, which is rounded up to 4 partitions.
[0128] Table 1
[0129]
[0130]
[0131] A hierarchical optimization model of the BOWF wind farm collection system is established, and the topology calculated by the present invention is compared with the actual topology of the project.
[0132] First, the original wind farm collection system connection scheme is recorded as Scheme 1, and its substation location and wind turbine connection topology are as follows: Figure 5 As shown, Figure 5 The wire models used in the cable lines between wind machines are represented by the corresponding serial numbers 1-9 in the table.
[0133] Then, the substation location is optimized by specifying the original wind farm substation location as the search starting point, setting the initial search gap to 1 km and the minimum search gap to 0.1 km, and obtaining the substation location search trajectory, as shown in Figure 7 As shown in the figure, each substation location obtained by searching has a corresponding feasible alternative topological connection solution, such as Figure 6 shown.
[0134] Under the outer PS search algorithm, based on the directed graph E of the feasible alternative connection scheme set of the system topology in the substation search grid space, the inner optimization algorithm is called to evaluate the points in the search space, and the search space is continuously updated, so that the location of the substation gradually tends to the central area of the wind farm, and finally converges to the coordinates (3.5, 2.25), which is the best location. Finally, this point is selected as the new substation location, and the inner topology optimization of the collection system is re-performed. The results are as follows: Figure 8 As shown, it is recorded as Scheme 2.
[0135] In order to illustrate the role of optimizing the location of the outer substation, the topology optimization results of the collection system under the original substation location of the wind farm are given, as shown in Fig. 9 As shown, it is recorded as Scheme 3. Table 2 lists the calculation results of the present value of economic costs of the above three schemes.
[0136] Table 2
[0137]
[0138]
[0139] By comparing the results of Scheme 1 and Scheme 3, it can be seen that, under the premise of a given substation location, after optimizing the collection system topology through the inner optimization algorithm, the cable cost and network loss cost are significantly reduced, and the total cost is saved by 6.8439 million yuan, a reduction of 12.2%, with significant results.
[0140] By comparing the results of Scheme 2 and Scheme 3, it can be seen that by adding a hierarchical optimization algorithm for searching the outer substation, optimizing the substation location and then optimizing the collection system topology, the cost of collection cables and network losses can be further reduced. The total cost is reduced by 11.1715 million on the basis of Scheme 2, a decrease of 22.7%, further verifying the scientificity and effectiveness of the present invention.
[0141] Embodiment 3
[0142] refer to Fig.10 The wind farm power collection system topology hierarchical optimization system of the present invention comprises:
[0143] A first acquisition module is used to acquire wind farm data information;
[0144] A first construction module is used to construct a substation search grid space according to the wind farm data information;
[0145] An establishment module is used to establish a feasible alternative connection scheme set of the collection system topology in the substation search grid space according to the wind farm data information;
[0146] A second construction module is used to construct a topology optimization model of the power collection system according to the set of feasible alternative connection schemes of the power collection system topology;
[0147] The first solving module is used to solve the collection system topology optimization model, obtain the optimal substation location and output it.
[0148] As an implementation manner of the present invention, the wind farm data information includes location information of the substation.
[0149] As an embodiment of the present invention, the first building block includes:
[0150] A second acquisition module is used to acquire the search distance;
[0151] A setting module, used for taking the location of the substation as a candidate center;
[0152] The third construction module is used to construct a substation search grid space according to the candidate center and the search interval.
[0153] As an implementation manner of the present invention, the first solution module includes:
[0154] The second solving module is used to solve the topology optimization model of the power collection system to obtain the current preliminary optimal substation center position;
[0155] A judgment module, used to judge whether the center position of the currently selected optimal substation is consistent with the center position of the candidate;
[0156] The first processing module is used to expand the current search interval and recalculate the center position of the preliminary optimal substation when the center position of the current preliminary optimal substation is inconsistent with the center position of the candidate;
[0157] The second processing module is used to determine whether the current search interval is less than or equal to the preset minimum search interval when the center position of the current preliminary optimal substation is consistent with the position of the candidate center. When the current search interval is less than or equal to the preset minimum search interval, the center position of the current preliminary optimal substation is used as the optimal substation position and output; when the current search interval is greater than the preset minimum search interval, the current search interval is reduced and the center position of the preliminary optimal substation is recalculated.
[0158] As an embodiment of the present invention, the objective function of the current collection system topology optimization model is:
[0159] minC=C cable +C loss
[0160]
[0161] Among them, A0 is the annual value-present value conversion coefficient, C cable is the cable cost, C loss is the present value of network loss cost, c i,j,t represents the purchase and installation cost per unit length of cable of model t between nodes i and j, c e is the on-grid electricity price of onshore wind power, P N is the rated output of the fan, P sum is the sum of the average output of the fans, p s is the probability of scenario s occurring, d ij is the distance between unit i and unit j, y i,j,t A 0-1 variable indicating whether there is a cable of type t between nodes i and j, I i,1,s is the current transmitted from node i to node 1 through the branch between nodes in scenario s, N w is the set of unit nodes, and S is the set of scenarios.
[0162] As an implementation mode of the present invention, the constraint conditions of the power collection system topology optimization model include voltage constraint conditions, cable operating current constraint conditions and topology constraint parts.
[0163] The division of modules in the embodiments of the present invention is schematic and is only a logical function division. There may be other division methods in actual implementation. In addition, each functional module in each embodiment of the present invention may be integrated into one processor, or may exist physically separately, or two or more modules may be integrated into one module. The above-mentioned integrated modules may be implemented in the form of hardware or in the form of software functional modules.
[0164] Embodiment 4
[0165] A computer device includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the computer program, the steps of the wind farm power collection system topology hierarchical optimization method are implemented, for example, including: obtaining wind farm data information; constructing a substation search grid space according to the wind farm data information; establishing a collection system topology feasible alternative connection scheme set in the substation search grid space according to the wind farm data information; constructing a collection system topology optimization model according to the collection system topology feasible alternative connection scheme set; solving the collection system topology optimization model, obtaining an optimal substation location and outputting it. Wherein, the memory may include a memory, such as a high-speed random access memory, and may also include a non-volatile memory, such as at least one disk memory, etc.; the processor, the network interface, and the memory are interconnected through an internal bus, and the internal bus may be an industrial standard architecture bus, a peripheral component interconnection standard bus, an extended industrial standard architecture bus, etc., and the bus may be divided into an address bus, a data bus, a control bus, etc. The memory is used to store programs. Specifically, the program may include program code, and the program code includes computer operation instructions. The memory may include memory and nonvolatile memory and provides instructions and data to the processor.
[0166] Embodiment 5
[0167] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the wind farm collection system topology hierarchical optimization method are implemented, for example, including: obtaining wind farm data information; constructing a substation search grid space according to the wind farm data information; establishing a collection system topology feasible alternative connection scheme set in the substation search grid space according to the wind farm data information; constructing a collection system topology optimization model according to the collection system topology feasible alternative connection scheme set; solving the collection system topology optimization model, obtaining the optimal substation location and outputting it. Specifically, the computer-readable storage medium includes, but is not limited to, for example, volatile memory and / or non-volatile memory. The volatile memory may include random access memory (RAM) and / or cache memory (cache), etc. The non-volatile memory may include read-only memory (ROM), hard disk, flash memory, optical disk, magnetic disk, etc.
[0168] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.
[0169] The present invention is described with reference to the flowchart and / or block diagram of the method, device (system), and computer program product according to the embodiment of the present invention. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the process and / or box in the flowchart and / or block diagram can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor or other programmable data processing device to produce a machine, so that the instructions executed by the processor of the computer or other programmable data processing device produce a device for implementing the functions specified in one or more processes in the flowchart and / or one or more boxes in the block diagram.
[0170] These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing device to work in a specific manner, so that the instructions stored in the computer-readable memory produce a manufactured product including an instruction device that implements the functions specified in one or more processes in the flowchart and / or one or more boxes in the block diagram.
[0171] These computer program instructions may also be loaded onto a computer or other programmable data processing device so that a series of operational steps are executed on the computer or other programmable device to produce a computer-implemented process, whereby the instructions executed on the computer or other programmable device provide steps for implementing the functions specified in one or more processes in the flowchart and / or one or more boxes in the block diagram.
[0172] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.
Claims
1. A topological hierarchical optimization method for a wind farm power collection system, characterized in that: include: Obtain wind farm data information; Constructing a substation search grid space according to the wind farm data information; According to the wind farm data information, a set of feasible alternative connection schemes for the collection system topology is established in the substation search grid space; Constructing a topology optimization model of the power collection system according to a set of feasible alternative connection schemes of the power collection system topology; Solve the collection system topology optimization model to obtain the optimal substation location and output it.
2. The wind farm power collection system topology hierarchical optimization method according to claim 1, characterized in that: The wind farm data information includes location information of the substation.
3. The method for topological hierarchical optimization of a wind farm power collection system according to claim 2, characterized in that: The process of constructing a substation search grid space according to the wind farm data information is as follows: Get the search distance; taking the location of the substation as a candidate center; A substation search grid space is constructed according to the candidate centers and the search intervals.
4. The method for topological hierarchical optimization of a wind farm power collection system according to claim 3, characterized in that: The process of solving the collector system topology optimization model, obtaining the optimal substation location and outputting it is as follows: Solving the collector system topology optimization model to obtain the current optimal substation center location; Determine whether the center position of the currently selected optimal substation is consistent with the center position of the candidate; When the center position of the currently selected optimal substation is inconsistent with the center position of the candidate, the current search interval is expanded and the center position of the currently selected optimal substation is recalculated; When the center position of the current preliminary optimal substation is consistent with the position of the candidate center, it is determined whether the current search interval is less than or equal to the preset minimum search interval. When the current search interval is less than or equal to the preset minimum search interval, the center position of the current preliminary optimal substation is used as the optimal substation position and output; when the current search interval is greater than the preset minimum search interval, the current search interval is reduced and the center position of the preliminary optimal substation is recalculated.
5. The method for topological hierarchical optimization of a wind farm power collection system according to claim 1, characterized in that: The objective function of the current collection system topology optimization model is: minC=C cable +C loss Among them, A0 is the annual value-present value conversion coefficient, C cable is the cable cost, C loss is the present value of network loss cost, c i,j,t represents the purchase and installation cost per unit length of cable of model t between nodes i and j, c e is the on-grid electricity price of onshore wind power, P N is the rated output of the fan, P sum is the sum of the average output of the fans, p s is the probability of scenario s occurring, d ij is the distance between unit i and unit j, y i,j,t A 0-1 variable indicating whether there is a cable of type t between nodes i and j, I i,1,s is the current transmitted from node i to node 1 through the branch between nodes in scenario s, N w is the set of unit nodes, and S is the set of scenarios.
6. The method for topological hierarchical optimization of a wind farm power collection system according to claim 1, characterized in that: The constraints of the power collection system topology optimization model include voltage constraints, cable operating current constraints and topology constraints.
7. A wind farm power collection system topology hierarchical optimization system, characterized in that: include: A first acquisition module is used to acquire wind farm data information; A first construction module is used to construct a substation search grid space according to the wind farm data information; An establishment module is used to establish a feasible alternative connection scheme set of the collection system topology in the substation search grid space according to the wind farm data information; A second construction module is used to construct a topology optimization model of the power collection system according to the set of feasible alternative connection schemes of the power collection system topology; The first solving module is used to solve the collection system topology optimization model, obtain the optimal substation location and output it.
8. The wind farm power collection system topology hierarchical optimization system according to claim 7, characterized in that: The first building block comprises: A second acquisition module is used to acquire the search distance; A setting module, used for taking the location of the substation as a candidate center; The third construction module is used to construct a substation search grid space according to the candidate center and the search interval.
9. The wind farm power collection system topology hierarchical optimization system according to claim 8, characterized in that: The first solution module comprises: The second solving module is used to solve the topology optimization model of the power collection system to obtain the current preliminary optimal substation center position; A judgment module, used to judge whether the center position of the currently selected optimal substation is consistent with the center position of the candidate; The first processing module is used to expand the current search interval and recalculate the center position of the preliminary optimal substation when the center position of the current preliminary optimal substation is inconsistent with the center position of the candidate; The second processing module is used to determine whether the current search interval is less than or equal to the preset minimum search interval when the center position of the current preliminary optimal substation is consistent with the position of the candidate center. When the current search interval is less than or equal to the preset minimum search interval, the center position of the current preliminary optimal substation is used as the optimal substation position and output; when the current search interval is greater than the preset minimum search interval, the current search interval is reduced and the center position of the preliminary optimal substation is recalculated.
10. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the method for topological hierarchical optimization of a wind farm collection system as claimed in any one of claims 1 to 6 are implemented.
11. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of the method for topological layered optimization of a wind farm collection system as claimed in any one of claims 1 to 6 are implemented.