Fault protection method, device and equipment for phase-shifting transformer and medium
By using the current and voltage detection device on the input side of the phase shift transformer, combined with the inverse time protection function, faults are judged and protected, the problem of high fault protection costs in the prior art is solved, and efficient fault detection and protection is achieved.
Patent Information
- Application Number
- CN202411101056.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-01
AI Technical Summary
In the prior art, the cost of failure protection of phase-shift transformers is too high, and multiple sets of voltage detection devices and current detection devices are required to be installed on the output side.
By using a set of current detection devices and voltage detection devices on the input side, the operation data of the phase-shift transformer is detected by using the inverse time protection function to determine the fault and protect it. The inverse time protection function is created by fitting historical operation data, and mapped differently Failure protection time under running parameters.
The cost investment in fault protection is significantly reduced, and failure protection can be achieved by only one set of detection devices, improving protection efficiency and reducing complexity.
Smart Images

Figure CN118889332A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of frequency converters, and in particular to a fault protection method, device, equipment and medium for a phase-shifting transformer. Background Art
[0002] High-voltage and high-power inverters are important industrial equipment for controlling, speed regulating and soft starting high-power motors. Due to the device's withstand voltage and power limitations, multiple power units are generally connected in series in phases to meet the needs of high-voltage output. Among them, the phase-shifting transformer is an important component for phase-splitting the high-voltage output power of high-voltage and high-power devices. Its characteristics are that the input side is a high-voltage single winding and the output side is a low-voltage multi-winding.
[0003] In the prior art, a voltage detection device and a current detection device are usually added to the output side of the phase-shifting transformer to perform fault protection on the phase-shifting transformer. Since there are a large number of windings on the output side of the phase-shifting transformer, in order to accurately measure the operating data of the phase-shifting transformer, it is necessary to detect the current and voltage data on each winding on the output side of the phase-shifting transformer. In this way, it is necessary to add multiple sets of voltage detection devices and current detection devices to the phase-shifting transformer to perform fault protection on the phase-shifting transformer, which greatly increases the cost investment in fault protection on the phase-shifting transformer. At present, there is no more effective solution to this technical problem.
[0004] It can be seen that how to reduce the cost investment required for fault protection of the phase-shifting transformer is a technical problem that needs to be solved urgently by those skilled in the art. Summary of the invention
[0005] In view of this, the purpose of the present invention is to provide a fault protection method, device, equipment and medium for a phase-shifting transformer, so as to solve the problem of excessively high cost investment in fault protection of a phase-shifting transformer in the prior art. The specific scheme is as follows:
[0006] In order to solve the above technical problems, the present invention provides a fault protection method for a phase-shifting transformer, comprising:
[0007] Using a set of current detection devices and voltage detection devices to detect the operation data of the input side of the phase-shifting transformer to obtain target detection data;
[0008] When it is determined that the phase-shifting transformer is faulty based on the target detection data and the inverse time protection function, the phase-shifting transformer is fault protected; wherein the inverse time protection function is a pre-created mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under operating parameters.
[0009] Preferably, the process of creating the inverse time protection function includes:
[0010] According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted to obtain an inverse time loss protection function;
[0011] According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different reactive current differences is fitted to obtain an inverse time reactive protection function;
[0012] According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection at different heating values is fitted to obtain an inverse time thermal overload protection function;
[0013] The mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different three-phase imbalance degrees is fitted according to the historical operation data of the phase-shifting transformer to obtain an inverse time imbalance protection function.
[0014] Preferably, fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer to obtain the inverse time loss protection function includes:
[0015] Fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer in the standby state, to obtain a first mapping function;
[0016] The mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different power loss amounts is fitted according to the historical operation data of the phase-shifting transformer under normal operation to obtain a second mapping function.
[0017] Preferably, fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance degrees according to the historical operation data of the phase-shifting transformer to obtain the inverse time unbalance protection function includes:
[0018] Determine the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalances according to the historical operation data of the phase-shifting transformer, and obtain a target time set;
[0019] A target constant function is set according to the target time set, and the target constant function is determined as the inverse time imbalance protection function.
[0020] Preferably, when it is determined according to the target detection data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is subjected to fault protection, including:
[0021] According to the target detection data, the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer are determined to obtain target operation data; wherein the reactive current difference of the phase-shifting transformer is the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer;
[0022] When it is determined according to the target operation data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is protected from failure.
[0023] Preferably, determining the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heating value of the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer according to the target detection data includes:
[0024] Determine the difference between the input power and the output power of the phase-shifting transformer according to the target detection data to obtain the power loss of the phase-shifting transformer;
[0025] Determine the actual reactive current of the phase-shifting transformer according to the target detection data, and predict the reactive current corresponding to the phase-shifting transformer under normal operation according to the phase-shifting transformer equivalent model to obtain the theoretical reactive current of the phase-shifting transformer;
[0026] Obtaining the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer to obtain the reactive current difference of the phase-shifting transformer;
[0027] Determine the input current of the phase-shifting transformer according to the target detection data, and integrate the input current of the phase-shifting transformer to obtain the heat generated by the phase-shifting transformer;
[0028] The three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer are determined according to the target detection data, and the three-phase imbalance of the phase-shifting transformer input voltage and the three-phase imbalance of the phase-shifting transformer input current are determined according to the three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer, respectively.
[0029] Preferably, when it is determined according to the target operation data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is subjected to fault protection, including:
[0030] When the inverse time protection function is a mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different power loss amounts, reactive current difference values, heat generation values and three-phase imbalance degrees, the power loss amount of the phase-shifting transformer in the current operation cycle is determined according to the target operation data, or the reactive current difference value of the phase-shifting transformer in the current operation cycle is determined, or the heat generation value of the phase-shifting transformer in the current operation cycle is determined, or the maximum imbalance degree among the three-phase imbalance degrees of input voltage / input current of the phase-shifting transformer in the current operation cycle is determined to obtain the target value;
[0031] If the target value is greater than a preset protection threshold, the time required to trigger the fault protection corresponding to the target value is determined according to the inverse time protection function to obtain a target screening time;
[0032] Determine whether the target screening time is greater than a preset threshold;
[0033] If so, it is determined that the phase-shifting transformer fails, and fault protection is performed on the phase-shifting transformer.
[0034] Preferably, after determining whether the target screening time is greater than a preset threshold, the method further includes:
[0035] When the target screening time is greater than the preset threshold, the target screening time is determined as the count value corresponding to the phase-shifting transformer in the current operation cycle;
[0036] When the target screening time is less than or equal to the preset threshold, the opposite number of the target screening time is determined as the count value corresponding to the phase-shifting transformer in the current operation cycle;
[0037] Adding the count value corresponding to the phase-shifting transformer in the current operation cycle to the historical accumulated value to obtain a target accumulated value; wherein the historical accumulated value is the accumulated value of the count values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle;
[0038] Determining whether the target accumulated value is greater than a preset accumulated value;
[0039] If yes, then executing the step of determining that the phase-shifting transformer is faulty and then performing fault protection on the phase-shifting transformer;
[0040] If not, continue to execute the step of determining the time required to trigger fault protection corresponding to the target value according to the inverse time protection function if the target value is greater than the preset protection threshold, and obtaining the target screening time.
[0041] In order to solve the above technical problems, the present invention further provides a fault protection device for a phase-shifting transformer, comprising:
[0042] A data detection module, used to detect the operation data of the input side of the phase-shifting transformer using a set of current detection devices and voltage detection devices to obtain target detection data;
[0043] A fault protection module is used to perform fault protection on the phase-shifting transformer when it is determined that the phase-shifting transformer has a fault based on the target operating data and the inverse time protection function; wherein the inverse time protection function is a pre-created mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts, reactive current differences, heat generation, and three-phase imbalance.
[0044] In order to solve the above technical problem, the present invention further provides an electronic device, comprising:
[0045] Memory for storing computer programs;
[0046] A processor is used to implement the steps of a fault protection method for a phase-shifting transformer as disclosed above when executing the computer program.
[0047] In order to solve the above technical problem, the present invention also provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of a fault protection method for a phase-shifting transformer as disclosed above are implemented.
[0048] Beneficial effect: In the present invention, a mapping relationship between the time required for triggering fault protection of a phase-shifting transformer under different operating parameters is created in advance to obtain an inverse time protection function. When performing fault protection on a phase-shifting transformer, firstly, a set of current detection devices and voltage detection devices are used to detect the operating data on the input side of the phase-shifting transformer to obtain target detection data; then, when it is determined that a fault occurs in the phase-shifting transformer according to the target detection data and the inverse time protection function, the phase-shifting transformer is protected from faults.
[0049] Since the method uses a set of current detection devices and voltage detection devices to detect the operating data of the input side of the phase-shifting transformer, the target detection data is obtained, and the target detection data contains various operating parameters of the phase-shifting transformer under the actual operating state. At this time, combined with the inverse time protection function created in advance, it can be determined whether the phase-shifting transformer is faulty. When it is determined that the phase-shifting transformer is faulty, it can be fault-protected. Obviously, through this method, only one set of current detection devices and voltage detection devices are needed to perform fault protection on the phase-shifting transformer. Compared with the prior art, because there is no need to set multiple sets of current detection devices and voltage detection devices on the phase-shifting transformer to perform fault protection on the phase-shifting transformer, the cost investment in fault protection of the phase-shifting transformer can be significantly reduced through this method.
[0050] Correspondingly, the fault protection device, equipment and medium for a phase-shifting transformer provided by the present invention also have the above-mentioned beneficial effects. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying creative work.
[0052] Figure 1 A flow chart of a fault protection method for a phase-shifting transformer provided by an embodiment of the present invention;
[0053] Figure 2 A schematic diagram of an inverse time loss protection function corresponding to a phase-shifting transformer provided by an embodiment of the present invention in a normal operation state and a standby state;
[0054] Figure 3 A flow chart of another fault protection method for a phase-shifting transformer provided by an embodiment of the present invention;
[0055] Figure 4 A schematic diagram showing the relationship between the maximum reactive current and the active current of a phase-shifting transformer predicted by using an equivalent model of the phase-shifting transformer;
[0056] Figure 5 The schematic diagram of the principle for obtaining the effective value of the input current of the phase-shifting transformer;
[0057] Figure 6 A flow chart of another fault protection method for a phase-shifting transformer provided by an embodiment of the present invention;
[0058] Figure 7A schematic diagram of the principle of a phase-shifting transformer triggering excessive loss fault protection provided by an embodiment of the present invention;
[0059] Figure 8 A schematic diagram of the principle of a phase-shifting transformer triggering excessive reactive current difference fault protection provided by an embodiment of the present invention;
[0060] Fig. 9 A schematic diagram of the principle of triggering thermal overload fault protection of a phase-shifting transformer provided in an embodiment of the present invention;
[0061] Fig.10 A schematic diagram of the principle of a phase-shifting transformer triggering three-phase voltage unbalance fault protection according to an embodiment of the present invention;
[0062] Fig.11 A schematic diagram of the principle of a phase-shifting transformer triggering three-phase current unbalance fault protection according to an embodiment of the present invention;
[0063] Fig.12 A structural diagram of a fault protection device for a phase-shifting transformer provided by an embodiment of the present invention;
[0064] Fig.13 A structural diagram of an electronic device provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0065] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0066] See also Figure 1 , Figure 1 A flow chart of a fault protection method for a phase-shifting transformer provided by an embodiment of the present invention, the method comprising:
[0067] Step S11: using a set of current detection devices and voltage detection devices to detect the operation data of the input side of the phase-shifting transformer to obtain target detection data;
[0068] Step S12: When it is determined that the phase-shifting transformer is faulty according to the target detection data and the inverse time protection function, the phase-shifting transformer is fault-protected; wherein the inverse time protection function is a pre-created mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters.
[0069] In this embodiment, a fault protection method for a phase-shifting transformer is provided. By using this method to perform fault protection on the phase-shifting transformer, the cost investment in performing fault protection on the phase-shifting transformer can be significantly reduced.
[0070] In this method, it is necessary to pre-create a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters to obtain an inverse time protection function. That is, the inverse time protection function stores a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters.
[0071] It should be noted that, in the conventional sense, inverse time protection means that when a fault occurs in the protected device, the greater the fault current, the smaller the delay in triggering the fault protection action. When a fault occurs in the protected device, the corresponding operating parameters can be considered as the fault operating parameters of the protected device, and can be regarded as the same type of operating parameters. Therefore, based on the idea of inverse time protection, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters can be created, and then the inverse time protection function can be obtained.
[0072] When the phase-shifting transformer is protected from faults, a set of current detection devices and voltage detection devices are first used to detect the operating data on the input side of the phase-shifting transformer to obtain target detection data. The current detection device and the voltage detection device are used to detect the three-phase input current and three-phase input voltage on the input side of the phase-shifting transformer, respectively, and thereby obtain the target detection data.
[0073] It can be understood that since the target detection data can characterize the operating parameters corresponding to the phase-shifting transformer under various operating conditions, the actual operating state of the phase-shifting transformer and the various operating parameters corresponding to the actual operating state of the phase-shifting transformer can be determined based on the target detection data, such as: the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer, etc.
[0074] When a phase-shifting transformer fails or operates abnormally, the operating parameters of the phase-shifting transformer will inevitably change significantly compared to its operating parameters under normal operating conditions. The inverse time protection function stores the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters. This is equivalent to storing the operating parameters corresponding to various types of faults in the phase-shifting transformer and the time required to trigger fault protection in the inverse time protection function. Therefore, in actual applications, when the target detection data of the phase-shifting transformer is obtained, it can be determined whether the phase-shifting transformer is faulty in combination with the inverse time protection function.
[0075] When it is determined that the phase-shifting transformer has a fault, corresponding fault protection measures can be taken for the phase-shifting transformer according to the fault level of the phase-shifting transformer, such as overcurrent protection for the phase-shifting transformer, power-off of the phase-shifting transformer, or control of the load of the phase-shifting transformer to stop running, etc.
[0076] In addition, compared with the prior art, which requires multiple sets of current detection devices and voltage detection devices to be set on the output side of the phase-shifting transformer to perform fault protection on the phase-shifting transformer, this method only needs to use one set of current detection devices and voltage detection devices when performing fault protection on the phase-shifting transformer. Under this setting mode, not only can the difficulty of performing fault maintenance on the phase-shifting transformer and the circuit complexity of the phase-shifting transformer fault protection circuit be reduced, but also the cost investment in performing fault protection on the phase-shifting transformer can be greatly reduced.
[0077] Obviously, since this method uses a set of current detection devices and voltage detection devices to detect the operating data on the input side of the phase-shifting transformer to obtain target detection data, and the target detection data contains various operating parameters of the phase-shifting transformer under the actual operating state. At this time, combined with the inverse time protection function created in advance, it can be determined whether the phase-shifting transformer is faulty. When it is determined that the phase-shifting transformer is faulty, it can be fault-protected. Obviously, through this method, only one set of current detection devices and voltage detection devices are needed to perform fault protection on the phase-shifting transformer. Compared with the prior art, because there is no need to set multiple sets of current detection devices and voltage detection devices on the phase-shifting transformer to perform fault protection on the phase-shifting transformer, the cost investment in fault protection of the phase-shifting transformer can be significantly reduced through this method.
[0078] Based on the above embodiment, this embodiment further illustrates and optimizes the technical solution. As a preferred implementation, the process of creating an inverse time protection function includes:
[0079] According to the historical operation data of the phase-shifting transformer, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted to obtain the inverse time loss protection function;
[0080] According to the historical operation data of the phase-shifting transformer, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different reactive current differences is fitted to obtain the inverse time reactive protection function;
[0081] According to the historical operation data of the phase-shifting transformer, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different heating values is fitted to obtain the inverse time thermal overload protection function.
[0082] The mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance degrees is fitted according to the historical operation data of the phase-shifting transformer, and the inverse time unbalance protection function is obtained.
[0083] Since the inverse time protection function stores the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters, and excessive loss, excessive reactive current, thermal overload and three-phase current and voltage imbalance of the phase-shifting transformer are very common fault types of the phase-shifting transformer in practical applications, the mapping relationship between these parameters and the time required to trigger fault protection can be created in advance from the four dimensions of power loss, reactive current difference, heat generation and three-phase imbalance of the phase-shifting transformer.
[0084] Specifically, because the historical operation data of the phase-shifting transformer contains the operating parameters corresponding to the phase-shifting transformer under various operating conditions and the time required to trigger the fault protection, the time required for the phase-shifting transformer to trigger the fault protection under different operating conditions can be determined based on the historical operation data of the phase-shifting transformer. On this basis, a mapping relationship between the time required for the phase-shifting transformer to trigger the fault protection under different power loss, reactive current difference, heat generation and three-phase imbalance can be created. Among them, the reactive current difference refers to the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer.
[0085] In actual operation, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts can be fitted according to the historical operation data of the phase-shifting transformer to obtain an inverse time loss protection function, and the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different reactive current differences can be fitted according to the historical operation data of the phase-shifting transformer to obtain an inverse time reactive protection function.
[0086] At the same time, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different heating values is fitted according to the historical operation data of the phase-shifting transformer, and the inverse time thermal overload protection function is obtained. The mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance values is fitted according to the historical operation data of the phase-shifting transformer, and the inverse time unbalance protection function is obtained.
[0087] It should be noted that, in this embodiment, the historical operation data of the phase-shifting transformer refers to all the operation data corresponding to the phase-shifting transformer before the current operation time, and these operation data include both the operation data corresponding to the phase-shifting transformer in the normal operation state and the operation data corresponding to the phase-shifting transformer in the fault operation state. Among them, the historical operation data of the phase-shifting transformer include: the historical power loss of the phase-shifting transformer, the historical reactive current difference, the historical heating value, the historical three-phase imbalance of the input voltage, the historical three-phase imbalance of the input current, and the time required to trigger the fault protection under different fault conditions.
[0088] In addition, when using the historical operating data of the phase-shifting transformer to fit the inverse time loss protection function, inverse time reactive power protection function, inverse time thermal overload protection function and inverse time unbalance protection function, the least squares method, interpolation method, polynomial fitting method, etc. can be used to fit these functions.
[0089] Obviously, through the technical solution provided by this embodiment, the accuracy and reliability of the created inverse time protection function can be guaranteed.
[0090] As a preferred implementation, the above step of fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer to obtain the inverse time loss protection function includes:
[0091] Fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer in the standby state, to obtain a first mapping function;
[0092] The mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted according to the historical operation data of the phase-shifting transformer under normal operation to obtain a second mapping function.
[0093] In this embodiment, after studying and analyzing the historical operation data of the phase-shifting transformer, it is found that the power loss corresponding to the phase-shifting transformer in the standby state and the normal operation state and the time required to trigger the fault protection under different power loss amounts are significantly different. Therefore, in this embodiment, in order to ensure the accuracy and reliability of creating the inverse time loss protection function, the inverse time loss protection function corresponding to the phase-shifting transformer in the standby state and the normal operation state is created separately.
[0094] Specifically, first, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted according to the historical operation data of the phase-shifting transformer in the standby state, and the first mapping function is obtained; then, the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted according to the historical operation data of the phase-shifting transformer in the normal operation state, and the second mapping function is obtained. Among them, the first mapping function represents the inverse time loss protection function corresponding to the phase-shifting transformer in the standby state, and the second mapping function represents the inverse time loss protection function corresponding to the phase-shifting transformer in the normal operation state.
[0095] See also Figure 2 , Figure 2 The following is a schematic diagram of the inverse time loss protection function corresponding to the phase-shifting transformer provided by the embodiment of the present invention in the normal operation state and the standby state. Figure 2 In , ① represents the inverse time loss protection function corresponding to the phase-shifting transformer in normal operation, and ② represents the inverse time loss protection function corresponding to the phase-shifting transformer in standby state. Figure 2 In the schematic diagram shown, the horizontal axis represents the loss ratio of the phase-shifting transformer, in percentage / %, and the vertical axis represents time, in seconds / s. Figure 2 In order to better present the changing trend of the inverse time loss protection function corresponding to the phase-shifting transformer in normal operation and standby state, the power loss of the phase-shifting transformer is replaced by the loss ratio of the phase-shifting transformer. Among them, the loss ratio of the phase-shifting transformer refers to the ratio between the power loss of the phase-shifting transformer and the input power of the phase-shifting transformer.
[0096] After obtaining the first mapping function and the second mapping function, it is equivalent to obtaining the inverse time loss protection function corresponding to the phase-shifting transformer in the standby state and the normal operation state, respectively. According to the conduction state, current and voltage parameters, and load parameters of the switch tube in the phase-shifting transformer in the target detection data, it can be judged whether the phase-shifting transformer is in the standby state or in the normal operation state. Therefore, when it is judged that the phase-shifting transformer is in the standby state according to the target detection data, the time required to trigger the fault protection can be found in the first mapping function according to the power loss of the phase-shifting transformer at the current moment, and the phase-shifting transformer can be judged according to the search result. When it is judged that the phase-shifting transformer is in the normal operation state according to the target detection data, the time required to trigger the fault protection can be found in the second mapping function according to the power loss of the phase-shifting transformer at the current moment, and the phase-shifting transformer can be judged according to the search result.
[0097] Obviously, through the technical solution provided by this embodiment, the accuracy of the created inverse time loss protection function can be further guaranteed.
[0098] As a preferred implementation, the above step of fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalances according to the historical operation data of the phase-shifting transformer to obtain the inverse time unbalance protection function includes:
[0099] Determine the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalances according to the historical operation data of the phase-shifting transformer, and obtain a target time set;
[0100] A target constant function is set according to a target time set, and the target constant function is determined as an inverse time unbalance protection function.
[0101] In this embodiment, when creating the inverse time unbalance protection function, firstly, the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance degrees is determined according to the historical operation data of the phase-shifting transformer to obtain a target time set.
[0102] In actual operation, after analyzing the data in the target time set, it is found that most of the data in the target time set are concentrated in a numerical range. Therefore, in order to reduce the difficulty of creating an inverse time imbalance protection function, a target constant function can be set based on the data in the target time set and combined with manual experience, and the target constant function can be determined as an inverse time imbalance protection function.
[0103] It is not difficult to imagine that after the inverse time unbalance protection function is set as the target constant function, the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance levels becomes a constant value. This not only reduces the difficulty of creating the inverse time unbalance protection function, but also reduces the resource overhead required by the processor when executing the control logic described in this application.
[0104] Obviously, the technical solution provided by this embodiment can significantly reduce the difficulty of creating an inverse time-imbalance protection function.
[0105] Based on the above embodiments, this embodiment further illustrates and optimizes the technical solution. Figure 3 , Figure 3 A flow chart of another method for fault protection of a phase-shifting transformer provided by an embodiment of the present invention. As a preferred implementation, the above step S12: when it is determined that a phase-shifting transformer fails according to target detection data, target operation data and an inverse time protection function, the phase-shifting transformer is protected from faults, including:
[0106] Step S21: determining the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer according to the target detection data, and obtaining target operation data; wherein the reactive current difference of the phase-shifting transformer is the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer;
[0107] Step S22: When it is determined that the phase-shifting transformer fails according to the target operation data and the inverse time protection function, the phase-shifting transformer is protected from failure.
[0108] When a phase-shifting transformer fails, the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance between the input voltage and the input current of the phase-shifting transformer will change significantly compared to the power loss, reactive current difference, heat generated, and the three-phase imbalance between the input voltage and the input current of the phase-shifting transformer under normal operating conditions.
[0109] Therefore, when judging the fault of the phase-shifting transformer, the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer can be determined according to the target detection data to obtain the target operation data; then, the target operation data and the inverse time protection function are used to determine whether the phase-shifting transformer is faulty. This setting method is equivalent to selecting characteristic data that can better characterize the fault of the phase-shifting transformer from the target detection data. In this case, the processor can determine whether the phase-shifting transformer is faulty according to the target operation data and the inverse time protection function in a shorter time.
[0110] Obviously, the technical solution provided by this embodiment can further improve the speed and efficiency of fault diagnosis on the phase-shifting transformer.
[0111] As a preferred implementation, the above step of determining the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer according to the target detection data includes:
[0112] Determine the difference between the input power and the output power of the phase-shifting transformer according to the target detection data, and obtain the power loss of the phase-shifting transformer;
[0113] The actual reactive current of the phase-shifting transformer is determined according to the target detection data, and the reactive current corresponding to the phase-shifting transformer under normal operation is predicted according to the equivalent model of the phase-shifting transformer to obtain the theoretical reactive current of the phase-shifting transformer;
[0114] Obtaining the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer, and obtaining the reactive current difference of the phase-shifting transformer;
[0115] Determine the input current of the phase-shifting transformer according to the target detection data, and integrate the input current of the phase-shifting transformer to obtain the heat generated by the phase-shifting transformer;
[0116] The three-phase input voltage and the three-phase input current of the phase-shifting transformer are determined according to the target detection data, and the three-phase imbalance of the phase-shifting transformer input voltage and the three-phase imbalance of the phase-shifting transformer input current are determined according to the three-phase input voltage and the three-phase input current of the phase-shifting transformer respectively.
[0117] In this embodiment, when calculating the power loss of the phase-shifting transformer, the input power and output power of the phase-shifting transformer are first determined based on the target detection data, and then the power loss of the phase-shifting transformer can be determined by taking the difference between the input power and the output power of the phase-shifting transformer.
[0118] When calculating the reactive current difference of the phase-shifting transformer, the actual reactive current of the phase-shifting transformer is first determined based on the target detection data, and then the reactive current corresponding to the phase-shifting transformer under normal operation is predicted based on the equivalent model of the phase-shifting transformer to obtain the theoretical reactive current of the phase-shifting transformer; thereafter, the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer is obtained to determine the reactive current difference of the phase-shifting transformer.
[0119] Among them, the mathematical expression of the equivalent model of the phase-shifting transformer is:
[0120] ;
[0121] In the formula, represents the equivalent model of the phase-shifting transformer, Indicates the maximum reactive current of a single cycle of the phase-shifting transformer, represents the protection constant of the phase-shifting transformer, Represents the active component of the phase-shifting transformer input current.
[0122] See also Figure 4 , Figure 4 The diagram below shows the relationship between the maximum reactive current and active current of a phase-shifting transformer predicted using the equivalent model of the phase-shifting transformer. Figure 4In the figure, the constant of the phase-shifting transformer is 0.5. The horizontal axis represents the active current of the phase-shifting transformer predicted by the equivalent model of the phase-shifting transformer, and the vertical axis represents the maximum reactive current of the phase-shifting transformer predicted by the equivalent model of the phase-shifting transformer. The units of the active current and the maximum reactive current are both ampere / A.
[0123] Since the heating value of the phase-shifting transformer can be expressed by the integration of the input current of the phase-shifting transformer, when calculating the heating value of the phase-shifting transformer, the input current of the phase-shifting transformer can be determined according to the target detection data, and then the heating value of the phase-shifting transformer can be determined by integrating the input current of the phase-shifting transformer.
[0124] When calculating the three-phase imbalance of the phase-shifting transformer, it is necessary to determine the three-phase imbalance of the three-phase input voltage of the phase-shifting transformer and the three-phase imbalance of the input current of the phase-shifting transformer according to the target detection data.
[0125] When determining the three-phase imbalance of the three-phase input voltage of the phase-shifting transformer based on the target detection data, it is necessary to first use an all-pass filter to perform phase shift processing on the three-phase input voltage of the phase-shifting transformer, and then use the filtered three-phase input voltage and the original three-phase input voltage to calculate the effective value of the three-phase input voltage. Finally, the average effective value of the three-phase input voltage is calculated based on the effective value of the three-phase input voltage, and by comparing the voltage of each phase with the average effective value of the three-phase input voltage, the imbalance of each phase input voltage can be determined.
[0126] Similarly, when determining the three-phase imbalance of the three-phase input current of the phase-shifting transformer based on the target detection data, it is necessary to first use an all-pass filter to perform phase shift processing on the three-phase input current of the phase-shifting transformer, and then use the filtered three-phase input current and the original three-phase input current to calculate the effective value of the three-phase input current. Finally, the average effective value of the three-phase input current is calculated based on the effective value of the three-phase input current, and by comparing the current of each phase with the average effective value of the three-phase input current, the imbalance of each phase input current can be determined.
[0127] See also Figure 5 , Figure 5 The schematic diagram is used to obtain the effective value of the input current of the phase-shifting transformer. Figure 5 In the figure, Ia represents the input current of the phase-shifting transformer in phase A, α and β are the components of Ia in the alpha-beta coordinate system after Clark transformation, and IaRMS represents the effective value of Ia.
[0128] In addition, in practical applications, when calculating the active component and reactive component of the input current of the phase-shifting transformer, the voltage data and current data in the target detection data can be first converted to the alpha-beta coordinate system through the Clark-Park transformation, and then the angle of the input voltage of the phase-shifting transformer on the alpha-beta coordinate axis can be calculated. The active component and reactive component of the input current of the phase-shifting transformer can be calculated through the angle and the component of the input voltage of the phase-shifting transformer on the alpha-beta coordinate axis.
[0129] When calculating the output power of the phase-shifting transformer, the product of the rated voltage and the rated current on the rotor of the phase-shifting transformer can be obtained first, and then the product can be divided by the rated power of the phase-shifting transformer to calculate the output power of the phase-shifting transformer. When calculating the input power of the phase-shifting transformer, the input power of the phase-shifting transformer can be calculated by obtaining the product of the active component of the input current of the phase-shifting transformer, the input voltage and the rated current.
[0130] Obviously, through the technical solution provided in this embodiment, the target detection data can be used to accurately and reliably determine the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heating value of the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer.
[0131] Based on the above embodiment, this embodiment further illustrates and optimizes the above technical solution. Figure 6 , Figure 6 A flow chart of another method for fault protection of a phase-shifting transformer provided by an embodiment of the present invention. As a preferred implementation, the above step S22: when it is determined according to the target operation data and the inverse time protection function that the phase-shifting transformer is faulty, the phase-shifting transformer is fault-protected, including:
[0132] Step S121: When the inverse time protection function is a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts, reactive current difference values, heat generation values, and three-phase imbalance degrees, the power loss amount of the phase-shifting transformer in the current operation cycle is determined according to the target operation data, or the reactive current difference value of the phase-shifting transformer in the current operation cycle is determined, or the heat generation value of the phase-shifting transformer in the current operation cycle is determined, or the maximum imbalance degree among the three-phase imbalance degrees of input voltage / input current of the phase-shifting transformer in the current operation cycle is determined to obtain the target value;
[0133] Step S122: if the target value is greater than the preset protection threshold, the time required to trigger the fault protection corresponding to the target value is determined according to the inverse time protection function to obtain the target screening time;
[0134] Step S123: determine whether the target screening time is greater than a preset threshold; if so, determine that the phase-shifting transformer is faulty, and perform fault protection on the phase-shifting transformer.
[0135] In this embodiment, when judging whether a phase-shifting transformer fails, if the inverse time protection function is a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts, reactive current difference values, heat generation values and three-phase imbalance degrees, the power loss amount of the phase-shifting transformer in the current operating cycle can be determined according to the target operating data, or the reactive current difference value of the phase-shifting transformer in the current operating cycle can be determined according to the target operating data, or the heat generation value of the phase-shifting transformer in the current operating cycle can be determined according to the target operating data, or the maximum imbalance degree among the three-phase imbalance degrees of input voltage / input current of the phase-shifting transformer in the current operating cycle can be determined according to the target operating data to obtain the target value.
[0136] Among them, the target value can represent the power loss of the phase-shifting transformer in the current operating cycle, or represent the reactive current difference of the phase-shifting transformer in the current operating cycle, or represent the heat generation of the phase-shifting transformer in the current operating cycle, or represent the maximum imbalance among the three-phase imbalances of input voltage / input current of the phase-shifting transformer in the current operating cycle.
[0137] It should be noted that, in the present embodiment, in the control system where the phase-shifting transformer is located, the voltage detection device and the current detection device detect the operation data of the input side of the phase-shifting transformer according to the preset operation cycle. Therefore, when the voltage detection device and the current detection device are used to detect the operation data of the input side of the phase-shifting transformer, the operation data of the phase-shifting transformer can be detected under different operation cycles.
[0138] When the target value is determined, the target value is compared with the preset protection threshold; if the target value is less than or equal to the preset protection threshold, the subsequent judgment process will not be triggered. It should be noted that the preset protection threshold is set according to the power loss, reactive current difference, heat generation, three-phase imbalance of input voltage or three-phase imbalance of input current of the phase-shifting transformer under normal operating conditions.
[0139] That is, if the target value is the power loss of the phase-shifting transformer in the current operating cycle, then the preset protection threshold is the power loss threshold set according to the power loss of the phase-shifting transformer in normal operating conditions; if the target value is the reactive current difference of the phase-shifting transformer in the current operating cycle, then the preset protection threshold is the reactive current protection threshold set according to the reactive current difference of the phase-shifting transformer in normal operating conditions; if the target value is the heat generation of the phase-shifting transformer in the current operating cycle, then the preset protection threshold is the thermal overload protection threshold set according to the heat generation of the phase-shifting transformer in normal operating conditions; if the target value is the maximum imbalance among the three-phase imbalances of the input voltage of the phase-shifting transformer in the current operating cycle, then the preset protection threshold is the voltage imbalance protection threshold set according to the three-phase imbalance of the input voltage of the phase-shifting transformer in normal operating conditions; if the target value is the maximum imbalance among the three-phase imbalances of the input current of the phase-shifting transformer in the current operating cycle, then the preset protection threshold is the current imbalance protection threshold set according to the three-phase imbalance of the input current of the phase-shifting transformer in normal operating conditions.
[0140] If the target value is greater than the preset protection threshold, it is necessary to find the time required to trigger the fault protection corresponding to the target value from the inverse time protection function to obtain the target screening time. At this time, the target screening time corresponds to the time required to trigger the fault protection corresponding to the power loss of the phase-shifting transformer in the current operation cycle, or the time required to trigger the fault protection corresponding to the reactive current difference of the phase-shifting transformer in the current operation cycle, or the time required to trigger the fault protection corresponding to the heat generation of the phase-shifting transformer in the current operation cycle, or the time required to trigger the fault protection corresponding to the maximum imbalance among the three-phase imbalance of the input voltage / input current of the phase-shifting transformer in the current operation cycle.
[0141] After the target screening time is obtained, the target screening time is compared with the preset threshold. If the target screening time is greater than the preset threshold, it means that the phase-shifting transformer has a fault, and the phase-shifting transformer needs to be fault-protected. If the target screening time is less than or equal to the preset threshold, it means that the phase-shifting transformer is still in normal operation.
[0142] Obviously, through the technical solution provided in this embodiment, it is possible to determine whether a phase-shifting transformer fails.
[0143] As a preferred implementation, after the above step S123: determining whether the target screening time is greater than a preset threshold, further includes:
[0144] Step S01: when the target screening time is greater than a preset threshold, the target screening time is determined as a count value corresponding to the phase-shifting transformer in the current operation cycle;
[0145] Step S02: when the target screening time is less than or equal to the preset threshold, the opposite number of the target screening time is determined as the count value corresponding to the phase-shifting transformer in the current operation cycle;
[0146] Step S03: adding the count value corresponding to the current operation cycle of the phase-shifting transformer to the historical accumulated value to obtain a target accumulated value; wherein the historical accumulated value is the accumulated value of the count values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle;
[0147] Step S04: determine whether the target accumulated value is greater than the preset accumulated value; if so, execute step S05; if not, execute step S123.
[0148] Step S05: If it is determined that the phase-shifting transformer fails, fault protection is performed on the phase-shifting transformer.
[0149] In practical applications, if the phase-shifting transformer frequently triggers the fault protection logic, it will inevitably affect the stable operation of the phase-shifting transformer. In order to avoid this situation, when it is determined that the target screening time is greater than the preset threshold, the target screening time can also be determined as the count value corresponding to the current operation cycle of the phase-shifting transformer. At the same time, when it is determined that the target screening time is less than or equal to the preset threshold, the opposite number of the target screening time is determined as the count value corresponding to the current operation cycle of the phase-shifting transformer.
[0150] When the count value corresponding to the current operation cycle of the phase-shifting transformer is determined, the count value corresponding to the current operation cycle of the phase-shifting transformer is added to the historical accumulated value to obtain the target accumulated value. The historical accumulated value is the cumulative value of the calculated values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle.
[0151] Here, if any operation cycle before the current operation cycle is named as the target operation cycle, then the power loss of the phase-shifting transformer in the target operation cycle can be determined according to the target operation data, or the reactive current difference of the phase-shifting transformer in the target operation cycle can be screened out from the target operation data, or the heat generation of the phase-shifting transformer in the target operation cycle can be screened out from the target operation data, or the maximum imbalance degree of the three-phase imbalance degree of input voltage / input current of the phase-shifting transformer in the target operation cycle can be screened out from the target operation data, thereby obtaining the target search data.
[0152] Afterwards, the time corresponding to the triggering of the fault protection corresponding to the target search data can be determined according to the inverse time protection function, and the target search time can be obtained. If the target search time is greater than the preset threshold, the target search time can be determined as the count value corresponding to the phase-shifting transformer in the target operation cycle. If the target search time is less than or equal to the preset threshold, the opposite of the target search time can be determined as the count value corresponding to the phase-shifting transformer in the target operation cycle. According to this method, the cumulative value of the count values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle can be determined, and then the historical cumulative value can be obtained.
[0153] After obtaining the target cumulative value, the target cumulative value is compared with the preset cumulative value. If the target cumulative value is greater than the preset cumulative value, it means that the phase-shifting transformer has a fault. At this time, the phase-shifting transformer needs to be fault-protected; if the target cumulative value is less than or equal to the preset cumulative value, it means that although the phase-shifting transformer is in an abnormal operating state, the conditions for triggering fault protection have not been met. At this time, you only need to continue to execute step S123.
[0154] Obviously, through the technical solution provided in this embodiment, the frequency of triggering the fault protection logic of the phase-shifting transformer can be reduced, thereby further improving the stability of the phase-shifting transformer during operation.
[0155] In order to enable those skilled in the art to more clearly understand the implementation principle of the present application, the technical contents disclosed in the above embodiments are combined here and the above technical contents are described in detail through a scenario embodiment.
[0156] See also Figure 7 , Figure 7The schematic diagram of the principle of the excessive loss fault protection of a phase-shifting transformer triggered by an embodiment of the present invention is provided. When judging the fault, firstly, a set of current detection devices and voltage detection devices are used to detect the operation data of the input side of the phase-shifting transformer, and the output power and input power of the phase-shifting transformer in the current operation cycle are determined according to the detection data of the input side of the phase-shifting transformer; then, the power loss of the phase-shifting transformer in the current operation cycle is determined according to the output power and input power of the phase-shifting transformer in the current operation cycle. When the power loss of the phase-shifting transformer in the current operation cycle is determined, the power loss of the phase-shifting transformer in the current operation cycle is compared with a pre-set power loss threshold. If the power loss of the phase-shifting transformer in the current operation cycle is greater than the power loss threshold, the time required to trigger the fault protection corresponding to the power loss of the phase-shifting transformer in the current operation cycle is found from the inverse time loss protection function to obtain T1; then, T1 is compared with the pre-set threshold T01. When T1>T01, T1 is determined to be the count value corresponding to the current operation cycle of the phase-shifting transformer. At this time, the count value corresponding to the current operation cycle of the phase-shifting transformer is added to the historical accumulated value to obtain Y1; finally, Y1 is compared with the pre-set threshold Y01. When Y1>Y01, it means that the power loss of the phase-shifting transformer is too large, and the phase-shifting transformer needs to be fault protected.
[0157] See also Figure 8 , Figure 8 The present invention provides a schematic diagram of the principle of a phase-shifting transformer triggering a reactive current difference excessive fault protection. Figure 8 middle, Indicates the maximum reactive current of a single cycle of the phase-shifting transformer, represents the protection constant of the phase-shifting transformer, represents the active component of the input current of the phase-shifting transformer, Indicates the actual reactive current of the phase-shifting transformer.
[0158] In this fault judgment, firstly, a set of current detection devices and voltage detection devices are used to detect the operation data of the input side of the phase-shifting transformer, and the actual reactive current of the phase-shifting transformer in the current operation cycle is determined based on the detection data of the input side of the phase-shifting transformer, and the theoretical reactive current of the phase-shifting transformer in the current operation cycle is predicted based on the equivalent model of the phase-shifting transformer. After that, the difference between the theoretical reactive current and the actual reactive current of the phase-shifting transformer in the current operation cycle is calculated to obtain P0, and P0 is compared with the preset reactive current protection threshold. If P0 is greater than the reactive current protection threshold, the time required to trigger the fault protection corresponding to P0 is found from the inverse time reactive protection function to obtain T2; then, T2 is compared with the preset threshold T02. When T2>T02, T2 is determined to be the count value corresponding to the current operation cycle of the phase-shifting transformer. At this time, the count value corresponding to the current operation cycle of the phase-shifting transformer is added to the historical accumulated value to obtain Y2; finally, Y2 is compared with the preset threshold Y02. When Y2>Y02, it means that the reactive current difference of the phase-shifting transformer is too large, and the phase-shifting transformer needs to be protected from faults.
[0159] See also Fig. 9 , Fig. 9 A schematic diagram of the principle of a phase-shifting transformer triggering thermal overload fault protection provided by an embodiment of the present invention. In this method, firstly, a set of current detection devices and voltage detection devices are used to detect the operating data of the input side of the phase-shifting transformer, and the input current Iract of the phase-shifting transformer in the current operating cycle is determined according to the detection data of the input side of the phase-shifting transformer; secondly, the input current Iract of the phase-shifting transformer in the current operating cycle is integrated to obtain D0, and it is determined whether D0 is greater than a preset thermal overload protection threshold. If D0 is greater than a preset thermal overload protection threshold, the time required to trigger the fault protection corresponding to D0 is found from the inverse time thermal overload protection function to obtain T3; then, T3 is compared with the preset threshold T03. When T3>T03, T3 is determined to be the count value corresponding to the current operating cycle of the phase-shifting transformer. At this time, the count value corresponding to the current operating cycle of the phase-shifting transformer is added to the historical accumulated value to obtain Y3; finally, Y3 is compared with the preset threshold Y03. When Y3>Y03, it means that the heat emitted by the phase-shifting transformer is too high, and the phase-shifting transformer needs to be protected from faults.
[0160] See also Fig.10 and Fig.11 , Fig.10 A schematic diagram of the principle of a phase-shifting transformer triggering three-phase voltage unbalance fault protection according to an embodiment of the present invention is provided. Fig.11The following is a schematic diagram of the principle of a phase-shifting transformer triggering a three-phase current imbalance fault protection according to an embodiment of the present invention. Since the principle of a phase-shifting transformer triggering a three-phase voltage imbalance fault is similar to the principle of a phase-shifting transformer triggering a three-phase current imbalance fault, Fig.10 The phase-shifting transformer triggering three-phase voltage unbalance fault protection is taken as an example for specific description.
[0161] exist Fig.10 In the method, firstly, a group of current detection devices and voltage detection devices are used to detect the operation data of the input side of the phase-shifting transformer, and the three-phase input voltages Ua, Ub and Uc of the phase-shifting transformer in the current operation cycle are determined according to the detection data of the input side of the phase-shifting transformer, and the effective values UaRMS, UbRMS and UcRMS of the three-phase input voltage are calculated and filtered; then, the three-phase imbalance of the three-phase input voltage is calculated, and the maximum imbalance in the three-phase input voltage is determined to obtain X1; when the maximum imbalance in the three-phase input voltage is determined to obtain X1, X1 is compared with a preset voltage imbalance protection threshold. If X1 is greater than the voltage unbalance protection threshold, the time required to trigger the fault protection corresponding to X1 is found from the inverse time unbalance protection function to obtain T4; then, T4 is compared with the preset threshold T04; when T4>T04, T4 is determined to be the count value corresponding to the current operation cycle of the phase-shifting transformer, and the count value corresponding to the current operation cycle of the phase-shifting transformer is added to the historical accumulated value to obtain Y4; finally, Y4 is compared with the preset threshold Y04. When Y4>Y04, it means that the three-phase input voltage of the phase-shifting transformer is unbalanced, and the phase-shifting transformer needs to be protected from faults.
[0162] In practical applications, the faults on the output side of the phase-shifting transformer in a high-voltage inverter can be divided into: ground short-circuit fault and phase-to-phase short-circuit fault. The following specifically describes the process of triggering fault protection of the phase-shifting transformer based on these two faults.
[0163] When a short circuit occurs to the ground in the winding on the output side of the phase-shifting transformer, the voltage of the faulty winding fluctuates, but the voltage fluctuation cannot form an effective basis for judging the short circuit to the ground. When a single-phase short circuit or a two-phase short circuit occurs to the ground in the phase-shifting transformer, the bus voltage of the faulty winding will not change significantly, but the three-phase input current of the phase-shifting transformer will increase significantly, and the imbalance will increase. At this time, the phase-shifting transformer will trigger the input current three-phase imbalance fault protection, thermal overload fault protection, and excessive loss fault protection. When a three-phase short circuit occurs to the ground in the phase-shifting transformer, the bus voltage and input power factor of the faulty winding in the phase-shifting transformer will drop significantly, and the input current will increase significantly. At this time, the phase-shifting transformer will trigger the thermal overload fault protection and excessive loss fault protection.
[0164] When a two-phase short circuit fault occurs in a phase-shifting transformer, the bus voltage of the faulty winding will not show a significant voltage drop. However, the fault will cause the phase imbalance to increase and the power loss to increase. At this time, the phase-shifting transformer will trigger the input current three-phase imbalance fault protection, thermal overload fault protection, excessive power loss protection, and reactive current difference protection. When a three-phase short circuit fault occurs in a phase-shifting transformer, the bus voltage and input power factor of the faulty winding will drop significantly, and the input current will increase significantly. At this time, the phase-shifting transformer will trigger the excessive power loss protection and reactive current difference protection.
[0165] Obviously, through this method, only one set of current detection device and voltage detection device is needed to perform fault protection on the phase-shifting transformer, thereby significantly reducing the cost investment in performing fault protection on the phase-shifting transformer.
[0166] See also Fig.12 , Fig.12 A structural diagram of a fault protection device for a phase-shifting transformer provided in an embodiment of the present invention, the device comprising:
[0167] The data detection module 21 is used to detect the operation data of the input side of the phase-shifting transformer using a group of current detection devices and voltage detection devices to obtain target detection data;
[0168] The fault protection module 22 is used to perform fault protection on the phase-shifting transformer when it is determined that a fault occurs in the phase-shifting transformer based on target detection data and an inverse time protection function; wherein the inverse time protection function is a pre-created mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different operating parameters.
[0169] Preferably, the fault protection module 22 includes:
[0170] The first function establishment unit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer, so as to obtain an inverse time loss protection function;
[0171] The second function establishment unit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different reactive current differences according to the historical operation data of the phase-shifting transformer, so as to obtain an inverse time reactive protection function;
[0172] The third function establishment unit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different heating values according to the historical operation data of the phase-shifting transformer, so as to obtain an inverse time thermal overload protection function;
[0173] The fourth function establishment unit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance degrees according to the historical operation data of the phase-shifting transformer, so as to obtain an inverse time unbalance protection function.
[0174] Preferably, the first function establishing unit includes:
[0175] The first subunit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer in the standby state, so as to obtain a first mapping function;
[0176] The second subunit is used to fit the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer under normal operation state, so as to obtain a second mapping function.
[0177] Preferably, the fourth function establishing unit includes:
[0178] A set acquisition subunit is used to determine the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalances according to the historical operation data of the phase-shifting transformer, and obtain a target time set;
[0179] The function determination subunit is used to set a target constant function according to a target time set, and determine the target constant function as an inverse time unbalance protection function.
[0180] Preferably, the fault protection module 22 includes:
[0181] A data determination submodule is used to determine the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer according to the target detection data, so as to obtain target operation data; wherein the reactive current difference of the phase-shifting transformer is the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer;
[0182] The fault determination submodule is used to perform fault protection on the phase-shifting transformer when it is determined that the phase-shifting transformer has a fault according to the target operation data and the inverse time protection function.
[0183] Preferably, the data determination submodule includes:
[0184] A loss determination unit, used to determine the difference between the input power and the output power of the phase-shifting transformer according to the target detection data, and obtain the power loss of the phase-shifting transformer;
[0185] The power obtaining unit is used to determine the actual reactive current of the phase-shifting transformer according to the target detection data, and predict the reactive current corresponding to the phase-shifting transformer under normal operation according to the equivalent model of the phase-shifting transformer, so as to obtain the theoretical reactive current of the phase-shifting transformer;
[0186] A difference calculation unit is used to obtain the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer, so as to obtain the reactive current difference of the phase-shifting transformer;
[0187] A heat calculation unit, used to determine the input current of the phase-shifting transformer according to the target detection data, and integrate the input current of the phase-shifting transformer to obtain the heat generated by the phase-shifting transformer;
[0188] The imbalance calculation unit is used to determine the three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer according to the target detection data, and to determine the three-phase imbalance of the phase-shifting transformer input voltage and the three-phase imbalance of the phase-shifting transformer input current according to the three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer respectively.
[0189] Preferably, the fault protection module 22 includes:
[0190] A data calculation unit is used to determine the power loss of the phase-shifting transformer in the current operation cycle according to the target operation data, or determine the reactive current difference of the phase-shifting transformer in the current operation cycle, or determine the heating value of the phase-shifting transformer in the current operation cycle, or determine the maximum imbalance among the three-phase imbalances of input voltage / input current of the phase-shifting transformer in the current operation cycle, to obtain a target value when the inverse time protection function is a mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different power loss amounts, reactive current difference values, heating values and three-phase imbalance degrees;
[0191] A time screening unit, for determining the time required to trigger the fault protection corresponding to the target value according to the inverse time protection function if the target value is greater than a preset protection threshold, and obtaining a target screening time;
[0192] A time judgment unit, used to judge whether the target screening time is greater than a preset threshold;
[0193] The fault determination unit is used to determine that a fault occurs in the phase-shifting transformer when the determination result of the time determination unit is yes, and then perform fault protection on the phase-shifting transformer.
[0194] Preferably, it also includes:
[0195] A first count value determination subunit, configured to determine the target screening time as a count value corresponding to the phase-shifting transformer in the current operation cycle when the target screening time is greater than a preset threshold;
[0196] The second count value determination subunit is used to determine the opposite number of the target screening time as the count value corresponding to the phase-shifting transformer in the current operation cycle when the target screening time is less than or equal to the preset threshold;
[0197] The count value accumulation subunit is used to add the count value corresponding to the phase-shifting transformer in the current operation cycle to the historical accumulated value to obtain a target accumulated value; wherein the historical accumulated value is the accumulated value of the count values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle;
[0198] The cumulative value judgment subunit is used to judge whether the target cumulative value is greater than the preset cumulative value;
[0199] A first determination subunit, configured to enter a fault determination unit when the determination result of the accumulated value determination subunit is yes;
[0200] The second determination subunit is used to enter the time screening unit when the determination result of the accumulated value determination subunit is no.
[0201] A fault protection device for a phase-shifting transformer provided in an embodiment of the present invention has the beneficial effects of the fault protection method for a phase-shifting transformer disclosed above.
[0202] See also Fig.13 , Fig.13 A structural diagram of an electronic device provided by an embodiment of the present invention, the electronic device comprising:
[0203] A memory 31, used for storing computer programs;
[0204] The processor 32 is used to implement the steps of the fault protection method for a phase-shifting transformer disclosed above when executing a computer program.
[0205] An electronic device provided by an embodiment of the present invention has the beneficial effects of the fault protection method for a phase-shifting transformer disclosed above.
[0206] Accordingly, an embodiment of the present invention provides a computer-readable storage medium, on which a computer program is stored. When the computer program is executed by a processor, the steps of a fault protection method for a phase-shifting transformer disclosed above are implemented.
[0207] A computer-readable storage medium provided by an embodiment of the present invention has the beneficial effects of the fault protection method for a phase-shifting transformer disclosed above.
[0208] In this specification, each embodiment is described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the embodiments can be referred to each other. For the device disclosed in the embodiment, since it corresponds to the method disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the method part.
[0209] Finally, it should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0210] The above is a detailed introduction to the fault protection method, device, equipment and medium of a phase-shifting transformer provided by the present invention. Specific examples are used in this article to illustrate the principles and implementation methods of the present invention. The description of the above embodiments is only used to help understand the method of the present invention and its core idea; at the same time, for general technical personnel in this field, according to the idea of the present invention, there will be changes in the specific implementation method and application scope. In summary, the content of this specification should not be understood as a limitation on the present invention.
Claims
1. A fault protection method for a phase-shifting transformer, It is characterized in that include: Using a set of current detection devices and voltage detection devices to detect the operation data of the input side of the phase-shifting transformer to obtain target detection data; When it is determined that the phase-shifting transformer is faulty based on the target detection data and the inverse time protection function, the phase-shifting transformer is fault protected; wherein the inverse time protection function is a pre-created mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different operating parameters.
2. A fault protection method for a phase-shifting transformer according to claim 1, It is characterized in that The creation process of the inverse time protection function includes: According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts is fitted to obtain an inverse time loss protection function; According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different reactive current differences is fitted to obtain an inverse time reactive protection function; According to the historical operation data of the phase-shifting transformer, a mapping relationship between the time required for the phase-shifting transformer to trigger fault protection at different heating values is fitted to obtain an inverse time thermal overload protection function; The mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different three-phase imbalance degrees is fitted according to the historical operation data of the phase-shifting transformer to obtain an inverse time imbalance protection function.
3. A fault protection method for a phase-shifting transformer according to claim 2, It is characterized in that The step of fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer to obtain an inverse time loss protection function includes: Fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts according to the historical operation data of the phase-shifting transformer in the standby state, to obtain a first mapping function; The mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different power loss amounts is fitted according to the historical operation data of the phase-shifting transformer under normal operation to obtain a second mapping function.
4. A fault protection method for a phase-shifting transformer according to claim 2, It is characterized in that The step of fitting the mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalance degrees according to the historical operation data of the phase-shifting transformer to obtain an inverse time unbalance protection function includes: Determine the time required for the phase-shifting transformer to trigger fault protection under different three-phase imbalances according to the historical operation data of the phase-shifting transformer, and obtain a target time set; A target constant function is set according to the target time set, and the target constant function is determined as the inverse time imbalance protection function.
5. A fault protection method for a phase-shifting transformer according to claim 1, It is characterized in that When it is determined according to the target detection data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is subjected to fault protection, including: According to the target detection data, the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and input current of the phase-shifting transformer are determined to obtain target operation data; wherein the reactive current difference of the phase-shifting transformer is the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer; When it is determined according to the target operation data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is protected from failure.
6. A fault protection method for a phase-shifting transformer according to claim 5, It is characterized in that The step of determining the power loss of the phase-shifting transformer, the reactive current difference of the phase-shifting transformer, the heat generated by the phase-shifting transformer, and the three-phase imbalance of the input voltage and the input current of the phase-shifting transformer according to the target detection data includes: Determine the difference between the input power and the output power of the phase-shifting transformer according to the target detection data to obtain the power loss of the phase-shifting transformer; Determine the actual reactive current of the phase-shifting transformer according to the target detection data, and predict the reactive current corresponding to the phase-shifting transformer under normal operation according to the phase-shifting transformer equivalent model to obtain the theoretical reactive current of the phase-shifting transformer; Obtaining the difference between the theoretical reactive current of the phase-shifting transformer and the actual reactive current of the phase-shifting transformer to obtain the reactive current difference of the phase-shifting transformer; Determine the input current of the phase-shifting transformer according to the target detection data, and integrate the input current of the phase-shifting transformer to obtain the heat generated by the phase-shifting transformer; The three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer are determined according to the target detection data, and the three-phase imbalance of the phase-shifting transformer input voltage and the three-phase imbalance of the phase-shifting transformer input current are determined according to the three-phase input voltage of the phase-shifting transformer and the three-phase input current of the phase-shifting transformer, respectively.
7. A fault protection method for a phase-shifting transformer according to claim 5, It is characterized in that When it is determined according to the target operation data and the inverse time protection function that the phase-shifting transformer fails, the phase-shifting transformer is subjected to fault protection, including: When the inverse time protection function is a mapping relationship between the time required for triggering fault protection of the phase-shifting transformer under different power loss amounts, reactive current difference values, heat generation values and three-phase imbalance degrees, the power loss amount of the phase-shifting transformer in the current operation cycle is determined according to the target operation data, or the reactive current difference value of the phase-shifting transformer in the current operation cycle is determined, or the heat generation value of the phase-shifting transformer in the current operation cycle is determined, or the maximum imbalance degree among the three-phase imbalance degrees of input voltage / input current of the phase-shifting transformer in the current operation cycle is determined to obtain the target value; If the target value is greater than a preset protection threshold, the time required to trigger the fault protection corresponding to the target value is determined according to the inverse time protection function to obtain a target screening time; Determine whether the target screening time is greater than a preset threshold; If so, it is determined that the phase-shifting transformer fails, and fault protection is performed on the phase-shifting transformer.
8. A fault protection method for a phase-shifting transformer according to claim 7, It is characterized in that After determining whether the target screening time is greater than a preset threshold, the method further includes: When the target screening time is greater than the preset threshold, the target screening time is determined as the count value corresponding to the phase-shifting transformer in the current operation cycle; When the target screening time is less than or equal to the preset threshold, the opposite number of the target screening time is determined as the count value corresponding to the phase-shifting transformer in the current operation cycle; Adding the count value corresponding to the phase-shifting transformer in the current operation cycle to the historical accumulated value to obtain a target accumulated value; wherein the historical accumulated value is the accumulated value of the count values corresponding to all operation cycles of the phase-shifting transformer before the current operation cycle; Determining whether the target accumulated value is greater than a preset accumulated value; If yes, then executing the step of determining that the phase-shifting transformer is faulty and then performing fault protection on the phase-shifting transformer; If not, continue to execute the step of determining the time required to trigger fault protection corresponding to the target value according to the inverse time protection function if the target value is greater than the preset protection threshold, and obtaining the target screening time.
9. A fault protection device for a phase-shifting transformer, It is characterized in that include: A data detection module, used to detect the operation data of the input side of the phase-shifting transformer using a set of current detection devices and voltage detection devices to obtain target detection data; A fault protection module is used to perform fault protection on the phase-shifting transformer when it is determined that the phase-shifting transformer is faulty based on the target detection data and the inverse time protection function; wherein the inverse time protection function is a pre-created mapping relationship between the time required for the phase-shifting transformer to trigger fault protection under different power loss amounts, reactive current differences, heat generation, and three-phase imbalance.
10. An electronic device, It is characterized in that include: Memory for storing computer programs; A processor, configured to implement the steps of a fault protection method for a phase-shifting transformer as claimed in any one of claims 1 to 8 when executing the computer program.