Cone crusher lining plate wear monitoring method and cone crusher
By automatically monitoring and compensating for the wear of the cone crusher lining plate, the problem of difficulty in monitoring the wear of the equipment is solved, ensuring the crushing effect and equipment safety, and improving production efficiency.
Patent Information
- Application Number
- CN202410948983.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-16
- Publication Date
- 2024-11-05
AI Technical Summary
During use, due to its closed structure, it is difficult to effectively monitor the wear of the lining plate, resulting in failure to adjust the discharge port in time or replace the lining plate when the wear is severe, which affects the material crushing effect and may cause equipment damage.
Provide a method for monitoring the wear of the liner plate by cone crusher. By automatically calibrating the wear amount of the liner plate, calculating the total amount of the accumulated wear, and intelligently compensate the discharge port size according to the wear amount, issue an early warning notice, reserve and replace the liner plate in advance to prevent Excessive wear.
Accurate monitoring and real-time compensation of liner wear are achieved, the quality of crushed materials is ensured, early warning is taken to prevent equipment accidents, and production efficiency is improved.
Smart Images

Figure CN118892879A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of crushers, and in particular to a method for monitoring the wear of a liner of a cone crusher and a cone crusher. Background Art
[0002] Cone crusher is a material crushing equipment widely used in metallurgy, mining, sand and gravel aggregate industries. Cone crusher has large crushing ratio, high efficiency, low energy consumption, uniform product size, and is suitable for medium and fine crushing of various ores and rocks. The working mechanism of cone crusher consists of fixed cone and moving cone, and lining plates are attached to the cones. The space between the lining plates forms a crushing chamber.
[0003] The working principle of cone crusher is to use the rotation of cone and the change of eccentricity to achieve material crushing. The material enters the crushing chamber of the cone from above, and under the action of the rotation and eccentricity of the moving cone, the material is compressed, bent and sheared, thereby achieving the crushing effect. The crushed material is discharged from the discharge port, and the size of the finished particles can be controlled by adjusting the gap between the moving cone liner and the fixed cone liner.
[0004] However, in the actual use of cone crushers, due to their closed structure, it is often impossible to effectively obtain the wear data of the liner. If the liner is severely worn, the discharge port cannot be adjusted or replaced in time, the material will be discharged from the discharge port without being crushed to the required particle size, affecting the material crushing effect and even causing damage to the crusher, resulting in huge losses. Summary of the invention
[0005] The present application aims to solve at least one of the technical problems existing in the prior art or related art.
[0006] To this end, the present application provides a method for monitoring the wear of the liner of a cone crusher. During automatic calibration, the sum of the wear of the fixed cone liner and the wear of the dynamic cone liner is monitored more accurately, and the actual wear of the liner can be understood in real time. According to the wear of the liner, the discharge port is intelligently compensated, and the size of the discharge port is more accurate, which effectively guarantees the quality of the crushed material. According to the total accumulated wear, minor, severe and scrapped warning notifications are issued, so that the liner can be reserved in advance and replaced in time to prevent excessive wear or waste of the liner, avoid serious accidents of the equipment, and effectively improve production efficiency.
[0007] The present application also provides a cone crusher including the above-mentioned cone crusher liner wear monitoring method.
[0008] A method for monitoring liner wear of a cone crusher provided in accordance with an embodiment of the first aspect of the present application includes: when the cone crusher reaches a preset working cycle, automatically calibrating the liner, the automatic calibration includes: obtaining the amount of liner wear; the liner wear is the sum of the fixed cone liner wear and the dynamic cone liner wear; according to the set value of the initial discharge port size, the liner is fully compensated, and the full compensation includes: adjusting the discharge port size so that the discharge port size reaches the set value of the initial discharge port size; the discharge port size is the distance between the fixed cone liner and the dynamic cone liner; according to the liner wear, calculating the total cumulative wear of the liner; and performing wear analysis on the liner based on the total cumulative wear.
[0009] Optionally, when the cone crusher has been working for a preset cycle, the step of automatically calibrating the liner includes: when the cone crusher has been working for a preset cycle, sending a first motor control instruction, the first motor control instruction is used to control the motor gear to drive the fixed cone gear ring to move, and the fixed cone gear ring drives the fixed cone liner to move toward the dynamic cone liner; when the fixed cone liner contacts the dynamic cone liner, receiving the high-pressure alarm issued by the hydraulic system, and recording the number of turns of the motor gear; calculating the discharge port size according to the number of turns of the motor gear; and calculating the amount of liner wear according to the discharge port size.
[0010] Optionally, the formula for calculating the discharge opening size is:
[0011] L=A*N
[0012] In the formula, L is the size of the discharge opening, A is the change in the discharge opening per rotation of the motor gear, and N is the number of rotations of the motor gear.
[0013] Optionally, the formula for calculating the liner wear is:
[0014] f=L-Ls
[0015] In the formula, f is the wear amount of the liner, L is the discharge opening size, and Ls is the set value of the initial discharge opening size.
[0016] Optionally, the step of fully compensating the liner according to the set value of the initial discharge port size includes: when the fixed cone liner contacts the movable cone liner, receiving a high-pressure alarm from the hydraulic system, and setting the number of turns the current motor gear has made as a reference value; calculating the number of turns the motor gear needs to adjust according to the set value of the initial discharge port size, and using the required number of turns as an adjustment value; sending a second motor control instruction, the second motor control instruction is used to control the motor gear to adjust the discharge port size according to the adjustment value on the basis of the reference value, so that the discharge port size reaches the set value of the initial discharge port size.
[0017] Optionally, the formula for calculating the total accumulated wear is:
[0018]
[0019] In the formula, F n is the total accumulated wear of the nth automatic calibration, f i is the wear of the liner automatically calibrated for the i-th time, C i is the adjustment coefficient of the i-th automatic calibration.
[0020] Optionally, the step of performing wear analysis on the liner based on the total accumulated wear includes: calculating the wear ratio of the liner based on the total accumulated wear; and performing wear analysis on the liner based on the wear ratio.
[0021] Optionally, the step of performing wear analysis on the lining according to the wear ratio includes: when the wear ratio is greater than or equal to a first threshold and the wear ratio is less than a second threshold, sending a slight wear alarm signal; when the wear ratio is greater than or equal to the second threshold and the wear ratio is less than a third threshold, sending a severe wear alarm signal; when the wear ratio is greater than or equal to the third threshold, sending a scrap wear alarm signal.
[0022] Optionally, the formula for calculating the wear ratio is:
[0023] R=F n / F c *T
[0024] In the formula, R is the wear ratio, F n is the total accumulated wear, F c is the set value of the total allowance for liner wear, and T is the usage coefficient adjusted according to the working conditions.
[0025] A cone crusher provided in accordance with an embodiment of the second aspect of the present application includes: a fixed cone liner, a movable cone liner, a fixed cone gear ring, a motor gear and a controller, wherein the distance between the fixed cone liner and the movable cone liner is the size of the discharge port; the motor gear is used to drive the fixed cone gear ring to move, and the fixed cone gear ring drives the fixed cone liner to move toward or away from the movable cone liner through the motor gear; the controller is configured to execute a cone crusher liner wear monitoring method in the first aspect or its various implementation methods.
[0026] One of the above technical solutions has at least the following advantages or beneficial effects:
[0027] A method for monitoring the liner wear of a cone crusher according to an embodiment of the present application includes: when the cone crusher reaches a preset cycle, the liner is automatically calibrated, and the automatic calibration includes: obtaining the amount of liner wear; the liner wear is the sum of the fixed cone liner wear and the dynamic cone liner wear; according to the set value of the initial discharge port size, the liner is fully compensated, and the full compensation includes: adjusting the discharge port size so that the discharge port size reaches the set value of the initial discharge port size; the discharge port size is the distance between the fixed cone liner and the dynamic cone liner; according to the liner wear, the total accumulated wear of the liner is calculated; according to the total accumulated wear, the liner is analyzed for wear. During automatic calibration, the sum of the fixed cone liner wear and the dynamic cone liner wear is monitored more accurately, and the actual liner wear can be understood in real time. According to the liner wear, the discharge port is intelligently compensated, and the discharge port size is more accurate, which effectively guarantees the quality of the crushed material. According to the total accumulated wear, minor, serious and scrap warning notices are issued, so that the lining can be reserved in advance and replaced in time to prevent excessive wear or waste of the lining, avoid serious accidents of the equipment, and effectively improve production efficiency.
[0028] The cone crusher provided in the embodiment of the present application is provided with the above-mentioned cone crusher lining wear monitoring method. Since the cone crusher lining wear monitoring method has the above-mentioned technical effects, the cone crusher provided with the cone crusher lining wear monitoring method should also have corresponding technical effects. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] In order to more clearly illustrate the technical solution of the present application, the drawings required for use in the embodiments are briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.
[0030] Figure 1 A schematic flow chart of a cone crusher liner wear monitoring method provided in an embodiment of the present application is shown;
[0031] Figure 2 A schematic diagram of the process of automatic calibration steps provided in an embodiment of the present application is shown;
[0032] Figure 3 A structural schematic diagram of a cone crusher provided in an embodiment of the present application is shown.
[0033] Description of reference numerals:
[0034] 1. Fixed cone lining, 2. Moving cone lining, 3. Fixed cone gear ring, 4. Motor gear. DETAILED DESCRIPTION
[0035] In order to better explain the present application and facilitate understanding, the present application is described in detail below in conjunction with the accompanying drawings through specific implementation methods. Figure 2 The orientation of is used as a reference. The position of the fixed cone liner 1 relative to the movable cone liner 2 is defined as "upper"; the position of the fixed cone liner 1 relative to the fixed cone gear ring 3 is defined as "inner".
[0036] As mentioned above, cone crushers are suitable for crushing rocks and ores of various hardness, such as limestone, granite, coal ore, iron ore, etc., and are widely used in mining, construction, roads, bridges and other industries. Cone crushers have the advantages of compact structure, high production efficiency, large crushing ratio, and easy maintenance. They can perform coarse, medium and fine crushing on rocks and ores of various hardness.
[0037] The working principle of cone crusher is to use the rotation of cone and the change of eccentricity to achieve material crushing. The material enters the crushing chamber of the cone from above, and under the action of the rotation and eccentricity of the moving cone, the material is compressed, bent and sheared, thereby achieving the crushing effect. The crushed material is discharged from the discharge port, and the size of the finished particles can be controlled by adjusting the gap between the moving cone liner and the fixed cone liner.
[0038] When the cone crusher is working, three-dimensional abrasive wear is formed between the fixed cone lining, the moving cone lining and the ore being ground. The squeezed ore exerts huge pressure on the local surface of the lining. At the same time, the high-speed operation of the moving cone produces huge shear stress. The two act at the same time, which can cause chiseling, cutting and impact extrusion pits on the lining. This will cause continuous wear of the cone crusher lining.
[0039] However, in the actual use of cone crushers, due to their closed structure, it is often impossible to effectively obtain the wear data of the liner. If the liner is severely worn, the discharge port cannot be adjusted or replaced in time, the material will be discharged from the discharge port without being crushed to the required particle size, affecting the material crushing effect and even causing damage to the crusher, resulting in huge losses.
[0040] In order to solve at least one of the technical problems existing in the prior art or related technology, the present application provides a cone crusher liner wear monitoring method and a cone crusher, the cone crusher liner wear monitoring method includes: when the cone crusher reaches the preset cycle, the liner is automatically calibrated, and the automatic calibration includes: obtaining the liner wear; the liner wear is the sum of the fixed cone liner wear and the dynamic cone liner wear; according to the setting value of the initial discharge port size, the liner is fully compensated, and the full compensation includes: adjusting the discharge port size so that the discharge port size reaches the setting value of the initial discharge port size; the discharge port size is the distance between the fixed cone liner and the dynamic cone liner; according to the liner wear, the total cumulative wear of the liner is calculated; according to the total cumulative wear, the liner is wear analyzed. During automatic calibration, the sum of the fixed cone liner wear and the dynamic cone liner wear is monitored more accurately, and the actual liner wear can be understood in real time. According to the liner wear, the discharge port is intelligently compensated, and the discharge port size is more accurate, which effectively guarantees the quality of the crushed material. According to the total accumulated wear, minor, serious and scrap warning notices are issued, so that the lining can be reserved in advance and replaced in time to prevent excessive wear or waste of the lining, avoid serious accidents of the equipment, and effectively improve production efficiency.
[0041] The following describes a cone crusher liner wear monitoring method and a cone crusher according to some embodiments provided by the present application with reference to the accompanying drawings.
[0042] See also Figures 1 to 3 The first aspect of the present application provides a method for monitoring the wear of a cone crusher liner, comprising:
[0043] S100: Program initialization.
[0044] Initialization is the process of preparing for the normal operation of the program. It is necessary to ensure that all necessary resources are initialized and configured correctly, including the initial setting of parameters, such as setting the total liner wear margin F. c Set the use coefficient T to 1.5, set the initial discharge opening size Ls to 45mm, set the discharge opening change A per motor gear rotation to 1.2mm / circle, set the automatic calibration adjustment coefficient C to 0.8, etc.
[0045] S200: Periodic detection is performed to regularly execute the automatic calibration task according to a preset period. The preset period can be set according to the working time, for example: the cone crusher performs automatic calibration every 10 working hours; or it can be set according to the working batch, for example: the cone crusher performs automatic calibration every 5 working batches.
[0046] Periodic detection can be implemented using a timer, which sets a time interval and triggers an event or callback function when the interval ends. It can also be implemented using a loop, which counts and triggers an event or callback function when the set number of times is reached.
[0047] S300: When the cone crusher reaches a preset operation cycle, the liner is automatically calibrated, and the automatic calibration includes: obtaining the wear amount of the liner; the wear amount of the liner is the sum of the wear amount of the fixed cone liner and the wear amount of the moving cone liner.
[0048] By using regular automatic calibration, the total amount of wear of the fixed cone liner and the movable cone liner can be intelligently monitored.
[0049] In an illustrative embodiment, Figure 2 As shown, when the preset cycle is reached, automatic calibration is performed, and the steps for obtaining the liner wear amount include:
[0050] S301: When the cone crusher reaches a preset operation cycle, a first motor control instruction is sent, wherein the first motor control instruction is used to control the motor gear to drive the fixed cone gear ring to move, and the fixed cone gear ring drives the fixed cone liner to move toward the direction close to the moving cone liner.
[0051] When the preset cycle is reached, for example, the working time reaches 10 hours, or the working batch reaches 5 batches, the automatic calibration starts. At this time, the cone crusher will stop crushing and enter the automatic calibration state, and the controller sends the first motor control instruction to the motor. After receiving the first motor control instruction, the motor will drive the motor gear to rotate counterclockwise, and the counterclockwise rotation of the motor gear will drive the fixed cone liner to move downward, that is, the fixed cone liner will be close to the moving cone liner.
[0052] S302: When the fixed cone lining plate contacts the movable cone lining plate, a high-pressure alarm is received from the hydraulic system, and the number of revolutions of the motor gear is recorded.
[0053] When the fixed cone liner is in contact with the movable cone liner, if the motor continues to drive the motor gear to rotate counterclockwise, the fixed cone liner will generate pressure on the hydraulic system of the movable cone liner. When the pressure reaches a certain value, the hydraulic system will issue a high-pressure alarm. After the controller receives the high-pressure alarm, it means that the fixed cone liner and the movable cone liner are in contact. At this time, the discharge port size is zero. The controller can record the number of turns of the motor gear. For example, the number of turns of the motor gear during automatic calibration is 39.
[0054] S303: Calculate the size of the discharge port according to the number of revolutions of the motor gear.
[0055] In an illustrative embodiment, the formula for calculating the discharge opening size is:
[0056] L=A*N (1)
[0057] In formula 1, L is the size of the discharge opening, A is the change in the discharge opening per rotation of the motor gear, and N is the number of rotations of the motor gear.
[0058] Formula 1 can be used to calculate the discharge opening size L during automatic calibration. For example, the discharge opening change A is 1.2mm / turn for each rotation of the motor gear. The number of turns of the motor gear during automatic calibration is 39 turns, so the discharge opening size L during automatic calibration is 46.8mm.
[0059] S304: Calculate the wear amount of the liner according to the size of the discharge port.
[0060] In an exemplary embodiment, the formula for calculating the wear amount of the liner is:
[0061] f=L-Ls (2)
[0062] In formula 2, f is the wear amount of the liner, L is the discharge opening size, and Ls is the setting value of the initial discharge opening size.
[0063] Since the fixed cone liner and the movable cone liner will wear, the discharge port size L during automatic calibration will be larger than the set value of the initial discharge port size by Ls, and the difference between the two is the liner wear f. For example: the initial discharge port size Ls is 45mm, and the discharge port size L during automatic calibration is 46.8mm, then the liner wear f is 1.8mm.
[0064] S400: Full compensation is performed on the liner according to the set value of the initial discharge opening size. The full compensation includes: adjusting the discharge opening size so that the discharge opening size reaches the set value of the initial discharge opening size; the discharge opening size is the distance between the fixed cone liner and the movable cone liner.
[0065] In an illustrative embodiment, the step of fully compensating the liner according to the set value of the initial discharge opening size includes:
[0066] S401: When the fixed cone lining plate contacts the movable cone lining plate, a high pressure alarm is received from the hydraulic system, and the number of revolutions of the motor gear is currently set as a reference value.
[0067] When the controller receives a high-pressure alarm, it indicates that the fixed cone liner and the movable cone liner are in contact. At this time, the discharge port size is zero. The number of turns of the motor gear during automatic calibration is set as the reference value. For example, the number of turns of the motor gear during automatic calibration is 39. The current state is used as the reference value.
[0068] S402: Calculate the number of turns required to adjust the motor gear according to the set value of the initial discharge opening size, and use the number of turns required to adjust as the adjustment value.
[0069] Formula 1 can be used to calculate the number of turns that the motor gear needs to adjust to reach the set value Ls of the initial discharge opening size. For example: the initial discharge opening size Ls is 45mm, and the discharge opening change A per rotation of the motor gear is 1.2mm / turn. Then the number of turns that the motor gear needs to adjust is 37.5 turns, and the adjustment value is 37.5 turns.
[0070] S403: Send a second motor control instruction, where the second motor control instruction is used to control the motor gear to adjust the discharge port size according to the adjustment value based on the reference value, so that the discharge port size reaches the set value of the initial discharge port size.
[0071] The controller sends the second motor control command to control the motor to drive the motor gear to rotate clockwise. The motor gear rotates clockwise to drive the fixed cone liner to move upward, that is, the fixed cone liner will move away from the moving cone liner. For example: based on the reference value, the motor gear is controlled to rotate 37.5 times clockwise to make the discharge port size reach 45mm. In this way, the purpose of full compensation is achieved, so that the discharge port size is always equal to the set value, ensuring the material crushing effect.
[0072] S500: Calculate the total accumulated wear of the lining plate according to the wear amount of the lining plate.
[0073] In an exemplary embodiment, the formula for calculating the total accumulated wear is:
[0074]
[0075] In formula 3, F n is the total accumulated wear of the nth automatic calibration, f i is the wear of the liner automatically calibrated for the i-th time, C i is the adjustment coefficient of the i-th automatic calibration.
[0076] The total accumulated wear can be calculated using Formula 3, where the automatic calibration adjustment coefficient C is adjusted according to the different crushing objects, and needs to be comprehensively considered based on the hardness, particle size, humidity and other characteristics of the material. For example, when the crushing object is coal ore, the automatic calibration adjustment coefficient C can be set to 0.6; when the crushing object is limestone, the automatic calibration adjustment coefficient C can be set to 0.8; when the crushing object is granite, the automatic calibration adjustment coefficient C can be set to 1.2; when the crushing object is iron ore, the automatic calibration adjustment coefficient C can be set to 1.3.
[0077] S600: Perform wear analysis on the liner based on the total accumulated wear amount.
[0078] In an exemplary embodiment, the step of performing wear analysis on the liner according to the total accumulated wear amount includes:
[0079] Based on the total accumulated wear, calculate the wear ratio of the liner.
[0080] In an exemplary embodiment, the formula for calculating the wear ratio is:
[0081] R=F n / F c *T (4)
[0082] In formula 4, R is the wear ratio, F n is the total accumulated wear, F c is the set value of the total allowance for liner wear, and T is the usage coefficient adjusted according to the working conditions.
[0083] The total wear margin of the lining is set according to the material of the lining and is the maximum wear that the lining can withstand. For example, if the set value Fc of the total wear margin of the lining is 200mm, once the accumulated wear is close to 200mm, it will be dangerous to continue using the lining. The closer the wear ratio R is to 100%, the greater the accumulated wear Fc is. n The closer to the set value F of the total allowance for liner wear c The usage coefficient T is adjusted according to the working conditions, that is, according to the working conditions such as the material of the crushed material and the lining plate. For example, when the crushed material is coal ore, the usage coefficient T is set to 0.8; when the crushed material is limestone, the usage coefficient T is set to 1; when the crushed material is granite, the usage coefficient T is set to 1.2; when the crushed material is iron ore, the usage coefficient T is set to 1.4.
[0084] According to the wear ratio, the wear analysis of the liner is carried out.
[0085] In an exemplary embodiment, the step of performing wear analysis on the liner according to the wear ratio includes:
[0086] When the wear ratio is greater than or equal to the first threshold and less than the second threshold, a slight wear alarm signal is sent. For example, if the first threshold is 40% and the second threshold is 60%, when the wear ratio is 50%, a slight wear alarm signal is sent to remind the operator to pay attention to the wear of the liner.
[0087] When the wear ratio is greater than or equal to the second threshold and less than the third threshold, a severe wear alarm signal is sent. For example, if the second threshold is 60% and the third threshold is 80%, when the wear ratio is 70%, a severe wear alarm signal is sent, which serves to remind the operator to prepare reserve liner.
[0088] When the wear ratio is greater than or equal to the third threshold, a scrap wear alarm signal is sent. For example, when the third threshold is 80%, when the wear ratio is 90%, a severe wear alarm signal is sent, which serves to remind the operator to replace the liner.
[0089] It is understandable that when the crushing object changes, the alarm signal will change. For example, when the crushing object is coal ore, the wear ratio is 50%, and a slight wear alarm signal is sent. When the crushing object is switched to iron ore, the wear ratio will change to 75% due to the change in the use factor T, and a severe wear alarm signal will be sent. This is because the hardness of coal ore is smaller than that of iron ore. If the current liner continues to be worn, the wear will also increase. Therefore, it is necessary to remind the reserve liner.
[0090] A cone crusher provided in a second embodiment of the present application is as follows: Figure 3 As shown, it includes: a fixed cone liner 1, a dynamic cone liner 2, a fixed cone gear ring 3, a motor gear 4 and a controller, wherein the distance between the fixed cone liner 1 and the dynamic cone liner 2 is the discharge port size L; the motor gear 4 is used to drive the fixed cone gear ring 3 to move, and the fixed cone gear ring 3 drives the fixed cone liner 1 to move toward or away from the dynamic cone liner 2 through the motor gear 4; the controller is configured to execute a cone crusher liner wear monitoring method provided in the first aspect embodiment above.
[0091] The controller is connected to each mechanism by cables or wireless means, and is used to receive signals fed back by each sensor and control the operation of the motors, brakes, valves and other equipment of each mechanism. The controller can be a mobile phone, tablet computer, desktop computer, server, industrial computer, single-chip microcomputer, PLC (Programmable Logic Controller), DSP (digital signal processor), FPGA (Field Programmable Gate Array), ASIC (Application-specific integrated circuit) and other devices with storage and computing functions, and the embodiments of the present application do not limit this.
[0092] Since the cone crusher provided in this embodiment has the cone crusher liner wear monitoring method provided in any of the above embodiments, the cone crusher has all the beneficial effects of the cone crusher liner wear monitoring method provided in any of the above embodiments, which will not be repeated here.
[0093] In the description of the present application, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the feature. In the description of the present application, "plurality" means two or more, unless otherwise clearly and specifically defined.
[0094] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0095] In the present application, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or that the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.
[0096] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "exemplary embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0097] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present application.
Claims
1. A method for monitoring the wear of a cone crusher liner, characterized in that: include: When the cone crusher reaches a preset cycle, the liner is automatically calibrated, and the automatic calibration includes: obtaining the wear amount of the liner; the wear amount of the liner is the sum of the wear amount of the fixed cone liner and the wear amount of the moving cone liner; According to the setting value of the initial discharge opening size, the liner is fully compensated, and the full compensation includes: adjusting the discharge opening size so that the discharge opening size reaches the setting value of the initial discharge opening size; the discharge opening size is the distance between the fixed cone liner and the moving cone liner; Calculating the total accumulated wear of the lining plate according to the wear amount of the lining plate; A wear analysis is performed on the liner according to the total accumulated wear amount.
2. A cone crusher liner wear monitoring method according to claim 1, characterized in that: When the cone crusher reaches a preset cycle, the step of automatically calibrating the liner includes: When the cone crusher reaches a preset cycle, a first motor control instruction is sent, wherein the first motor control instruction is used to control the motor gear to drive the fixed cone gear ring to move, and the fixed cone gear ring drives the fixed cone liner to move in a direction close to the moving cone liner; When the fixed cone lining plate contacts the movable cone lining plate, a high pressure alarm issued by the hydraulic system is received, and the number of revolutions of the motor gear is recorded; Calculate the size of the discharge port according to the number of revolutions of the motor gear; The wear amount of the liner is calculated according to the size of the discharge opening.
3. A cone crusher liner wear monitoring method as claimed in claim 2, characterized in that: The formula for calculating the discharge opening size is: L=A*N (1) In formula (1), L is the size of the discharge opening, A is the change in the discharge opening per rotation of the motor gear, and N is the number of rotations of the motor gear.
4. A cone crusher liner wear monitoring method as claimed in claim 2, characterized in that: The formula for calculating the wear amount of the liner is: f=L-Ls (2) In formula (2), f is the wear amount of the liner, L is the size of the discharge port, and Ls is the set value of the initial discharge port size.
5. A cone crusher liner wear monitoring method as claimed in claim 2, characterized in that: The step of fully compensating the liner according to the set value of the initial discharge opening size includes: When the fixed cone lining plate contacts the movable cone lining plate, a high pressure alarm issued by the hydraulic system is received, and the number of revolutions of the current motor gear is set as a reference value; According to the set value of the initial discharge opening size, the number of turns required for adjusting the motor gear is calculated, and the number of turns required for adjustment is used as the adjustment value; Send a second motor control instruction, wherein the second motor control instruction is used to control the motor gear to adjust the discharge port size according to the adjustment value on the basis of the reference value, so that the discharge port size reaches the set value of the initial discharge port size.
6. A cone crusher liner wear monitoring method according to claim 1, characterized in that: The formula for calculating the total accumulated wear is: In formula (3), F n is the total accumulated wear amount of the nth automatic calibration, f i is the wear amount of the liner automatically calibrated for the i-th time, C i is the adjustment coefficient of the i-th automatic calibration.
7. A cone crusher liner wear monitoring method according to claim 1, characterized in that: The step of performing wear analysis on the liner according to the total accumulated wear amount comprises: Calculating the wear ratio of the liner according to the total accumulated wear amount; A wear analysis is performed on the liner according to the wear ratio.
8. A cone crusher liner wear monitoring method according to claim 7, characterized in that: The step of performing wear analysis on the liner according to the wear ratio comprises: When the wear ratio is greater than or equal to a first threshold value, and the wear ratio is less than a second threshold value, sending a slight wear alarm signal; When the wear ratio is greater than or equal to the second threshold and the wear ratio is less than a third threshold, sending a severe wear alarm signal; When the wear ratio is greater than or equal to the third threshold, a scrap wear alarm signal is sent.
9. A cone crusher liner wear monitoring method according to claim 7, characterized in that: The formula for calculating the wear ratio is: R=F n / F c *T (4) In formula (4), R is the wear ratio, F n is the total accumulated wear, F c is the set value of the total allowance for liner wear, and T is the usage coefficient adjusted according to the working conditions.
10. A cone crusher, characterized in that: include: A fixed cone liner (1), a movable cone liner (2), a fixed cone gear ring (3), a motor gear (4) and a controller, wherein the distance between the fixed cone liner (1) and the movable cone liner (2) is the size of the discharge port; The motor gear (4) is used to drive the fixed cone gear ring (3) to move, and the fixed cone gear ring (3) drives the fixed cone liner (1) to move in a direction close to or away from the movable cone liner (2) through the motor gear (4); The controller is configured to execute a cone crusher liner wear monitoring method according to any one of claims 1-9.
Citation Information
Patent Citations
Control method used for discharge opening of cone crusher with multiple hydraulic cylinders
CN106216078A
Automatic calibration system and automatic calibration method for cone crusher discharge hole
CN107899649A
Automatic control system and method of hydraulic multi-cylinder cone crusher
CN110665627A
Automatic detection and compensation device and method for abrasion loss of lining plate of cone crusher
CN113617509A
Cited By
Monitoring method and system for multi-stage crushing station
CN120861255A
A monitoring method and system for a multi-stage crushing plant
CN120861255B
Modularized wear frame plate of crushing equipment and replacement method of modularized wear frame plate
CN122098794A
A modular wear shelf plate for a comminution apparatus and method of replacing the same
CN122098794B