Guiding device and method for secondary follow-up of pile casing

By designing a guide device for the guard casing, the combination of horizontal limit frame and vertical support frame is used to achieve efficient sinking and release of the guard casing secondary follow-up, solving the problem of low sinking and release efficiency in deep water environments. Improve construction safety and progress.

CN118895764APending Publication Date: 2024-11-05CCCC SHEC FOURTH ENG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410996181.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-24
Publication Date
2024-11-05

AI Technical Summary

Technical Problem

In super-large bridge projects constructed in deep water environments, the secondary follow-up process of the casing is inefficient, and due to the shallow cover of the riverbed in the water area or the hard surface soil, it is difficult for the casing to sink in place at one time, resulting in the construction efficiency and safety of the casing being affected. Influence.

Method used

A guide device including a horizontal limit frame and a vertical support frame is designed. The precise guidance and sinking of the guard cartridge is achieved through the horizontal limit frame and guide wheel, which simplifies the installation process and reduces the number of installation and disassembly of the guide device. And fix the guard through welding limit points to ensure construction safety and efficiency.

Benefits of technology

This device has achieved a significant improvement in the construction efficiency of secondary follow-up of the casing, reducing the weight and installation time of the guide device, reducing the risk of overturning, and improving construction safety and progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118895764A_ABST
    Figure CN118895764A_ABST
Patent Text Reader

Abstract

The invention discloses a guiding device for secondary follow-up of a pile casing, and relates to the technical field of long and large bridge construction. The guiding device comprises a horizontal limiting frame, a vertical supporting frame is erected at the center of the horizontal limiting frame and is perpendicular to the horizontal limiting frame, and the horizontal limiting frame comprises a plurality of horizontal limiting frames which are sequentially arranged side by side; the horizontal limiting frame is used for guiding secondary follow-up of the pile casing, and the horizontal limiting frame is provided with a plurality of detachable guiding devices around a pile casing body. The invention further discloses a method of the guiding device, the guiding device and the guiding method for secondary follow-up of the pile casing can meet the actual function requirement of perpendicularity control of secondary follow-up of the pile casing, and the construction efficiency of secondary follow-up of the pile casing is greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of long and large bridge construction, and in particular to a guiding device for secondary follow-up of casing.

[0002] The invention also relates to a guiding method for secondary follow-up of casing. Background Art

[0003] Most bridges use bored pile foundations. If the pier is located in water, steel casing must be sunk to a certain depth in the soil before bored pile construction to ensure the stability of the hole wall during drilling.

[0004] For the deep-water main piers of extra-large bridges, the number of pile foundations is large and the pile diameter is large. The most efficient way to sink steel casings is by using pile-driving ships. However, the riverbed cover layer in many waters is shallow or the surface soil is hard and dense with high bearing capacity. It is difficult to sink the casing into place in one go and it often faces the problem of secondary follow-up.

[0005] For drilling platforms that use casing as stress, the secondary follow-up of casing must be implemented immediately after the first sinking, so that the sunken casing can be connected as a whole as soon as possible to form a stable structure, and also create favorable conditions for quickly entering the next construction process. Therefore, designing an efficient guide device for the second follow-up of casing and improving the construction efficiency of the secondary follow-up of casing is the key to ensuring construction safety and project progress. Summary of the invention

[0006] The purpose of the present invention is: to address the above-mentioned problems, the present invention provides a guiding device for secondary follow-up of casing, and according to the actual functional requirements of the verticality control of the secondary follow-up of casing, a guiding device for the sinking of casing is designed to greatly improve the construction efficiency of the secondary follow-up of casing; at the same time, the present invention also provides a guiding method of the guiding device.

[0007] The first technical solution adopted by the present invention is as follows:

[0008] A guiding device for secondary follow-up of casing comprises a horizontal limit frame, a vertical support frame is erected at the center of the horizontal limit frame, and the vertical support frame is perpendicular to the horizontal limit frame, the horizontal limit frame comprises a plurality of horizontal limit frames arranged side by side in sequence, the horizontal limit frame is used for guiding the secondary follow-up of casing, and a plurality of detachable guiding devices are arranged around the casing barrel body.

[0009] Furthermore, the horizontal limiting frame is a hollow rectangular frame.

[0010] Furthermore, the vertical support frame includes two load-bearing beams arranged in parallel in the horizontal direction. The load-bearing beams are erected above the horizontal limit frame through vertical connecting columns, and the load-bearing beams are parallel to the horizontal limit frame in the vertical direction, and the distance between the two load-bearing beams is smaller than the diameter of the casing.

[0011] Furthermore, a large diagonal brace is connected between the vertical connecting column and the horizontal frame, and the large diagonal brace, the horizontal frame and the vertical connecting column are arranged in a right triangle.

[0012] Furthermore, the horizontal limit frame includes two transverse limit beams, which are arranged between the two side frames of the horizontal limit frame and parallel to the load-bearing beam. The transverse limit beams and the two side frames of the horizontal limit frame form a rectangular horizontal limit frame, and there are three horizontal limit frames arranged side by side, and the load-bearing beam is located directly above the second horizontal limit frame.

[0013] Furthermore, the casing is located at the center of the horizontal limit frame during the secondary follow-up, and each frame of the horizontal limit frame is 200m away from the casing.

[0014] Furthermore, the guide device includes a guide wheel arranged on each frame of the horizontal limit frame, and the guide wheel extends into the horizontal limit frame and is connected to the casing.

[0015] The second technical solution adopted by the present invention is a guiding method for secondary follow-up of casing, which adopts a guiding device for secondary follow-up of casing, and is specifically implemented according to the following steps:

[0016] Step 1, hoist the guide device, insert the three horizontal limit frames into the first casing, the second casing and the third casing respectively, until the load-bearing beam is close to the top of the second casing; then select the welding point to weld the third casing and the horizontal limit frame to complete the limit, and the guide device is initially fixed;

[0017] Step 2: weld the second casing and the horizontal limit frame in the same manner as the selection of the welding point of the third casing, and complete the fixing of the guide device to the second casing and the third casing; then install the guide wheels around the four vertex directions of the circumference of the first casing on the horizontal limit frame; hoist the pile hammer to the first casing, and then sink the first casing to the designed height;

[0018] Step 3, remove the guide wheel on the horizontal limit frame at the first casing; weld the limit between the first casing and the horizontal limit frame, and release the limit between the third casing and the horizontal limit frame; install the guide wheel on the third casing in the same way as the first casing; hoist the pile hammer to the third casing, sink the third casing to the designed height, remove the pile hammer, release the limit of all casings and guide devices, and lift the guide device to the next casing for construction.

[0019] Furthermore, the welding points of the three protective tubes are respectively located at the center of each frame of the horizontal frame.

[0020] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:

[0021] 1. The horizontal limit frame of the guide device for secondary follow-up of casing of the present invention is single-layer and designed as a symmetrical structure, so there is no need to set up additional anti-overturning counterweights, achieving a lightweight design and reducing the weight of the guide device by more than 50%.

[0022] 2. The horizontal limit frame of the guide device of the present invention covers three casings, and the middle casing also takes into account the vertical support function. Two casings can be installed at one time, which greatly reduces the number of installation and removal times of the guide device.

[0023] 3. The guide device of the present invention respectively covers three horizontal limit frames on three casings, and the load-bearing beam of the vertical support frame falls on the top surface of the middle casing. It can be unhooked by simple welding limit. The lifting equipment takes a short time, and no measurement and auxiliary positioning are required during the entire installation process, and the installation efficiency is high.

[0024] 4. The horizontal limit frame of the present invention is installed at a low position and covers three casings at the same time. The theoretical distance between the limit beam and the casing is 200 mm. The risk of overturning of the guide device is extremely small, and the construction safety is high. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a front view of a guide device for secondary follow-up of casing according to the present invention;

[0026] Figure 2 It is a top view of a guide device for secondary follow-up of casing according to the present invention;

[0027] Figure 3 It is a front view of an operating platform in a guide device for secondary follow-up of casing according to the present invention;

[0028] Figure 4 It is a top view of an operating platform in a guide device for secondary follow-up of casing according to the present invention;

[0029] Figure 5 It is a front view of the operating state of the device in step 1 of a guiding method for secondary follow-up of casing according to the present invention;

[0030] Figure 6 It is a top view of the operating state of the device in step 1 of a guiding method for secondary follow-up of casing according to the present invention;

[0031] Figure 7 It is a front view of the operating state of the device in step 2 of a guiding method for secondary follow-up of casing according to the present invention;

[0032] Figure 8 It is a top view of the operating state of the device in step 2 of a guiding method for secondary follow-up of casing according to the present invention;

[0033] Fig. 9It is a front view of the operating state of the device in step 3 of a guiding method for secondary follow-up of casing according to the present invention;

[0034] Fig.10 It is a top view of the operating status of the device in step 3 of the guiding method for secondary follow-up of casing according to the present invention.

[0035] In the figure, 1. casing; 2. pile hammer; 3. load-bearing beam; 4. vertical connecting column; 5. large diagonal brace; 6. longitudinal limit beam; 7. transverse limit beam; 8. small diagonal brace; 9. welding limit point; 10. guide wheel. DETAILED DESCRIPTION

[0036] The present invention will be described in detail below in conjunction with the accompanying drawings.

[0037] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0038] Example

[0039] This embodiment provides a guiding device for secondary follow-up of casing, which includes a single-layer horizontal limit frame, a vertical support frame, a guiding device and an operating platform.

[0040] Single-layer horizontal limit frame: Since the casing 1 has been sunk into the soil to a certain depth during the first sinking, the bottom of the casing 1 is constrained by the soil, and the bottom of the casing 1 will not be displaced significantly during the second follow-up; during the second follow-up, a single-layer horizontal limit frame is set on the top of the casing 1 to meet the guidance requirements. The height of the horizontal limit frame is determined according to the depth of the second follow-up. If the casing 1 needs to be sunk 2m for the second follow-up, the position of the horizontal limit frame must be more than 2m lower than the top of the casing to ensure that the pile hammer 2 does not conflict with the horizontal limit frame when the casing is finally sunk. The horizontal limit frame consists of a longitudinal limit beam 6, a transverse limit beam 7 and a small diagonal brace 8. Figure 2As shown, in this embodiment, two longitudinal limiting beams 6 are provided and are parallel, and multiple transverse limiting beams 7 are provided and vertically connected between the two longitudinal limiting beams 6. The two transverse limiting beams 7 form a group, and form a rectangular horizontal limiting frame with the longitudinal limiting beams 6. When the casing 1 sinks, it passes through the center of the horizontal limiting frame and sinks. The horizontal limiting frame plays a good limiting role. The small diagonal braces 8 are located at the four corners of the rectangular horizontal limiting frame to support the transverse limiting beams 7. The theoretical distance between the limiting beam and the casing 1 is 200mm, that is, the transverse limiting beam 7 is 200mm away from the longitudinal limiting beam 6 and the edge of the casing 1 in the longitudinal direction; to ensure that the horizontal limiting frame can adapt to the deviation of the first sinking of the casing 1 and ensure smooth installation. In this embodiment, three horizontal limiting frames are arranged side by side in sequence, forming a symmetrical structure, that is, the horizontal limiting frame can cover 3 casings, and the limiting beam is welded and fixed to two adjacent casings by small steel. A guide device is installed on the limiting beam around the third casing, and the third casing is sunk.

[0041] In this embodiment, the horizontal limit frame is not limited to a rectangular structure, as long as it is a stable single-layer frame structure. The horizontal limit frame is not limited to a rectangle, and it can ensure that the casing can pass through smoothly and adapt to the deviation generated when the casing is placed for the first time. The number of horizontal limit frames is not limited. In this embodiment, 3 are preferred, and it can also be more than one, to ensure that the horizontal limit frames are distributed in a stacked structure to prevent overturning.

[0042] Vertical support frame: In the present embodiment, the vertical support frame is designed as a door-shaped hanging structure, including a load-bearing beam 3, a vertical connecting column 4 and a large diagonal brace 5. The vertical connecting column 4 is set to four in the present embodiment, and two groups of two are symmetrically arranged on two longitudinal limiting beams 6, and the vertical connecting column 4 is perpendicular to the longitudinal limiting beam 6. There are two load-bearing beams 3, which are respectively erected on the top of the vertical connecting column 4. The two load-bearing beams 3 are parallel and parallel to the transverse limiting beam 7. The distance between the two load-bearing beams 3 is less than the diameter of the casing. When placing the guide device of the present application, it is ensured that the two load-bearing beams 3 are erected on the top of the casing. A large diagonal brace 5 is also provided at the connection between the load-bearing beam 3 and the vertical connecting column 4. The other end of the large diagonal brace 5 is connected to the longitudinal limiting beam 6 on the same side as the vertical connecting column 4. The large diagonal brace 5 plays a supporting role to ensure the stability of the vertical connecting column 4 after the load-bearing beam 3 is erected. The above-mentioned vertical support frame can be quickly fixed in combination with the horizontal limiting frame to achieve rapid installation. At the same time, the hanging structure can meet the installation height requirements of the horizontal limiting frame.

[0043] Guide equipment; in this embodiment, the theoretical distance between the limit beam and the casing is 200mm. Due to the influence of the first casing sinking deviation and the installation deviation of the guide device, the actual gap between the limit beam and the casing is uncertain. By installing 4 guide wheels, the casing is located at the center of the horizontal limit frame, and the 4 guide wheels are located at the center of each frame of the horizontal limit frame. One end is welded to the frame, i.e., the limit beam, and the other end is pressed against the casing to achieve precise limiting of the casing sinking; the guide wheel 10 is not limited to welding, and can be threaded, plug-in, or other convenient disassembly methods.

[0044] Operating platform; in this embodiment, the operating platform is a construction platform for the entire process of installing and removing the guide device and sinking the casing to ensure construction safety.

[0045] Example 2

[0046] Based on Example 1, this example provides a guiding method for secondary follow-up of casing, which is specifically implemented in the following steps:

[0047] Step 1, such as Figure 5 As shown, the lifting equipment hoists the horizontal limit frame, and the three horizontal limit frames are respectively inserted into the 1# casing, the 2# casing and the 3# casing until the load-bearing beam 3 is close to the top of the 2# casing; then the welding points are selected to weld the 3# casing and the horizontal limit frame to complete the limit, that is, the welding is as shown in FIG. Figure 6 At the two limit points shown, the guide device is initially fixed and the lifting equipment is unhooked and withdrawn;

[0048] Step 2, such as Figure 7 As shown in the figure, according to the selection method of the welding point of the 3# casing, weld the 2# casing and the horizontal limit frame in the same way. Figure 8 The welding limit point 9 shown in the figure is welded to complete the fixing of the guide device and the three casings; then the horizontal limit frame is installed with guide wheels in the four vertex directions around the circumference of the 1# casing; the lifting equipment is used to drive the pile hammer 2 to the 1# casing, and then the 1# casing is sunk to the designed height;

[0049] Step 3, such as Fig. 9 As shown in the figure, remove the guide wheel on the horizontal limit frame at the 1# casing; Fig.10 As shown, a limiter is welded at the limit point between 1# casing and the horizontal limit frame, and the limit point between 3# casing and the horizontal limit frame is released; guide wheels are installed on 3# casing in the same way as 1# casing; pile hammer 2 is hoisted to 3# casing by hoisting equipment, pile hammer 2 is started, 3# casing is sunk to the designed height, pile hammer is moved away, the limit of all casings and guide devices is released, and the guide device is hoisted to the next casing for construction.

[0050] In this embodiment, the welding limiting points 9 are all selected at the center of each frame of the horizontal limiting frame.

[0051] The principles and implementation methods of the present invention are described in this article using specific embodiments. The description of the above embodiments is only used to help understand the method and core ideas of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made to the present invention without departing from the principles of the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.

[0052] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, or are the directions or positional relationships in which the inventive product is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.

[0053] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

Claims

1. A guide device for secondary follow-up of casing, characterized in that: It includes a horizontal limit frame, a vertical support frame is set up at the center of the horizontal limit frame, and the vertical support frame is perpendicular to the horizontal limit frame. The horizontal limit frame includes multiple horizontal limit frames arranged side by side in sequence. The horizontal limit frame is used for guiding the secondary follow-up of the casing. The horizontal limit frame is provided with multiple detachable guide devices around the casing barrel.

2. A guide device for secondary follow-up of casing according to claim 1, characterized in that: The horizontal limiting frame is a hollow rectangular frame.

3. A guide device for secondary follow-up of casing according to claim 1, characterized in that: The vertical support frame includes two load-bearing beams arranged in parallel in the horizontal direction. The load-bearing beams are erected above the horizontal limit frame through vertical connecting columns. The load-bearing beams are parallel to the horizontal limit frame in the vertical direction, and the distance between the two load-bearing beams is smaller than the diameter of the casing.

4. A guide device for secondary follow-up of casing according to claim 3, characterized in that: A large diagonal brace is also connected between the vertical connecting column and the horizontal frame, and the large diagonal brace, the horizontal frame and the vertical connecting column are arranged in a right triangle.

5. A guide device for secondary follow-up of casing according to claim 3, characterized in that: The horizontal limit frame includes two transverse limit beams, which are arranged between the two side frames of the horizontal limit frame and are parallel to the load-bearing beams. The transverse limit beams and the two side frames of the horizontal limit frame form a rectangular horizontal limit frame, and there are three horizontal limit frames arranged side by side, and the load-bearing beam is located directly above the second horizontal limit frame.

6. A guide device for secondary follow-up of casing according to claim 5, characterized in that: The casing is located at the center of the horizontal limit frame during the secondary follow-up, and each frame of the horizontal limit frame is 200m away from the casing.

7. A guide device for secondary follow-up of casing according to claim 1 or 5, characterized in that: The guide device comprises a guide wheel arranged on each frame of the horizontal limit frame, the guide wheel extends into the horizontal limit frame and is connected with the casing.

8. A guiding method for secondary follow-up of casing, using a guiding device for secondary follow-up of casing as claimed in any one of claims 1 to 7, characterized in that: Please follow the steps below to implement: Step 1, hoist the horizontal limit frame, insert the three horizontal limit frames into the first casing, the second casing and the third casing respectively, until the load-bearing beam is close to the top of the second casing; then select the welding point to weld the third casing and the horizontal limit frame to complete the limit, and the guide device is initially fixed; Step 2, welding the second casing and the horizontal limit frame in the same manner as the selection of the welding point of the third casing, completing the fixing of the guide device to the second casing and the third casing; then installing guide wheels around the four vertex directions of the circumference of the first casing on the horizontal limit frame; hanging the pile hammer to the first casing, and then sinking the first casing to the designed height; Step 3, remove the guide wheel on the horizontal limit frame at the first casing; weld the limit between the first casing and the horizontal limit frame, and release the limit between the third casing and the horizontal limit frame; install the guide wheel on the third casing in the same way as the first casing; hoist the pile hammer to the third casing, sink the third casing to the designed height, remove the pile hammer, release the limit of all casings and guide devices, and lift the guide device to the next casing for construction.

9. A guiding method for secondary follow-up of casing according to claim 8, characterized in that: The welding points of the three protective tubes are respectively arranged at the center of each frame of the horizontal frame.