Ballast track semi-mechanical long steel rail laying construction process
By adopting the semi-mechanical long rail laying process of ballast tracks in the construction of railway tracks, the problems of high cost of mechanized track laying and discontinuous delivery of offline roadbeds are solved, and the effects of high construction flexibility, high efficiency and low cost are achieved, ensuring that The standardization and construction period of track laying are completed.
Patent Information
- Application Number
- CN202411142444.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-20
- Publication Date
- 2024-11-08
AI Technical Summary
In the construction of existing railway tracks, the mechanized track laying method is costly and is not suitable for small-scale projects. Due to the limitations of offline roadbed delivery continuity and tight construction period, the working face cannot be flexibly adjusted to meet the demand for rush work.
Using the process of semi-mechanical long rail paving facilities for balled rails, the construction of standard rails, sleepers and roadbed storage areas, and using mechanical equipment to weld and roadbed paving to form long rails, and in the delivery section and the undelivered section. seamless connection between them.
It improves construction flexibility and efficiency, reduces mechanical costs, avoids the discontinuous impact of offline roadbed delivery, and can complete track laying on time, meeting the requirements of long rail installation specifications.
Smart Images

Figure CN118910950A_ABST
Abstract
Description
Technical Field
[0001] The present application belongs to the field of railway engineering, and specifically relates to a semi-mechanical long rail laying construction process for ballasted track. Background Art
[0002] At present, the construction of railways throughout the country mainly includes the construction of ballastless passenger lines, ballasted tracks, urban subways and freight lines. Although my country and international railway engineering infrastructure have made great progress, ballasted tracks are still the most commonly used line types today. Track laying in track engineering is a key and decisive process in various construction projects, and it is also the last process in railway construction. Due to factors such as tight project schedules, heavy tasks, and high labor costs in rapid railway construction, most of the railways under construction today use mechanized track laying construction methods for track engineering construction, and mechanical track laying is a normalized operation mode; mechanized track laying has high construction efficiency, fast speed, and good results. However, the mechanized track laying construction method has the following problems: First, due to the high cost of track laying machines, the mechanical cost of using track laying machines for track laying operations is high, which is not suitable for small-scale projects or engineering implementation companies. Second, a necessary condition for using track laying machines for mechanized track laying is that the delivery of the line's roadbed must be continuous. If there is a break in the roadbed, the construction of the track laying machine will be hindered, and it will not be possible to skip the power outage for construction. Therefore, the use of track laying machines for track laying is greatly affected by offline construction. If the offline delivery of track laying is slow or discontinuous, it cannot be guaranteed to be completed on time within the specified construction period. Third, when using track laying machines for track laying construction, the number of track laying machines determines the number of working surfaces. If there is a need to rush the work, it is impossible to increase the number of working surfaces.
[0003] In addition to mechanized track laying using track laying machines, another mainstream track laying method is to use rail tracks. This method first assembles 25m rail tracks at the track laying base, then transports them to the track laying site by rail, and finally lays the entire track track. However, this method cannot be implemented in areas such as Europe and the United States where the operating regulations are relatively strict and long rails must be used for track laying operations, and has limitations. Summary of the invention
[0004] In order to at least overcome the problems existing in the related art to a certain extent, the present application provides a semi-mechanical long rail laying construction process for ballasted track.
[0005] According to an embodiment of the present application, the present application provides a semi-mechanical long rail laying construction process for ballasted track, which includes the following steps:
[0006] Determine the priority delivery section of the roadbed and carry out track laying operations on the priority delivery section;
[0007] Build a standard rail storage area, sleeper storage area and ballast storage yard near the construction site, and transport the rails to the standard rail storage area, the sleepers to the sleeper storage area, and the ballast to the ballast storage yard respectively;
[0008] Confirm that the performance and status of construction machinery and equipment are normal;
[0009] Measure and lay out the track, and re-bury the track outward displacement piles according to the track centerline to facilitate track laying;
[0010] Transport rails from standard rail storage areas to the roadbed and place them;
[0011] The rails on the left and right sides of the roadbed are welded separately to form long rails;
[0012] Transport ballast from the ballast storage yard to the construction site and perform ballast paving operations;
[0013] Transport the sleepers to the roadbed adjacent to the track line and spread them on the ballast surface in accordance with the specifications;
[0014] Lift the long rails into the rail grooves of the sleepers to complete the track laying of the priority delivery section;
[0015] The above construction procedures are used to complete the track laying work of the undelivered section, and the undelivered section is connected with the delivered section to form a seamless line.
[0016] In the above-mentioned semi-mechanical long rail laying construction process for ballasted track, the process of building a standard rail storage area, a sleeper storage area and a ballast storage yard near the construction site is as follows:
[0017] At the starting point of self-laying track, standard rail storage areas and sleeper storage areas are built every 8km to 12km; at the starting point of self-laying track, ballast storage yards are set up in the area adjacent to the track every 18km to 22km.
[0018] In the above-mentioned semi-mechanical long rail laying construction process for ballasted track, the construction machinery and equipment include one or more of rail trailers, sleeper trailers, vehicle-mounted mobile welders, sleeper scattering machines, crawler excavators, tire excavators, ballast spreaders, dump trucks, loaders, graders, fastener wrenches and measuring equipment.
[0019] Furthermore, the process of transporting the rails from the standard rail storage area to the roadbed and placing them is as follows:
[0020] Using a crane to load standard rails onto rail trailers in the standard rail storage area;
[0021] The rail trailer transports the rails to the roadbed surface of the construction area through the construction access road;
[0022] The crawler excavator uses a rail hoist to unload the rails from the rail trailer and places the unloaded rails in sequence along the extension direction of the roadbed, where the left and right rails in the roadbed width direction are spaced at a preset distance.
[0023] Furthermore, the process of welding the rails on the left and right sides of the roadbed to form the long rails is as follows:
[0024] The vehicle-mounted mobile welding machine enters between the scattered rails through the construction access road.
[0025] The vehicle-mounted mobile welding machine sequentially welds the rails on the left and right sides of the roadbed to form long rails; wherein the welding length of the rails is the length of the dispersed unit rail section.
[0026] Furthermore, the process of transporting the ballast from the ballast storage yard to the construction site and performing the ballast paving operation is as follows:
[0027] At the ballast storage yard, loaders load ballast onto dump trucks;
[0028] The dump truck reverses through the construction access road and the reserved passageway toward the ballast paver;
[0029] The ballast paver starts ballast paving operations from the construction starting point;
[0030] The grader levels the paved ballast;
[0031] After the dump truck completes unloading, it drives out through the reserved passage, and the next dump truck enters the operation in a cycle.
[0032] Furthermore, the process of transporting the sleepers to the roadbed adjacent to the track line and spreading them on the ballast surface according to the specification requirements is as follows:
[0033] The sleeper trailer loads sleepers in the sleeper storage area and enters the roadbed near the track line in the laying section through the construction access road;
[0034] The crawler excavator uses a sleeper lift to remove the sleepers from the sleeper trailer;
[0035] The sleeper spreading machine enters the laid ballast and evenly spreads the sleepers on the ballast surface according to the sleeper spacing required by the specifications and with reference to the track outward displacement piles.
[0036] Furthermore, the process of hoisting the long rail into the rail bearing groove of the sleeper to complete the track laying of the priority delivery section is as follows:
[0037] The tire excavator is equipped with a single spreader on the roadbed near the track line;
[0038] The tire excavator uses a hoist to lift the long welded rails;
[0039] Two tire excavators alternately lift the long rails from back to front into the rail grooves of the sleepers, working from one end to the other.
[0040] Install the fastening line fasteners on the sleepers and install the rails at the reserved passage openings. Now the installation of the long rails is completed.
[0041] In the above-mentioned semi-mechanical long rail laying construction process for ballasted track, when laying tracks on the priority delivery section, the undelivered section of the roadbed is first crossed, and the operation is carried out after the undelivered section of the roadbed is delivered.
[0042] According to the above-mentioned specific implementation methods of the present application, it can be known that at least the following beneficial effects are achieved: the semi-mechanical long rail laying construction process for ballasted track provided by the present application lays the track sequentially along the extension direction of the track; when encountering an undelivered section, it is crossed first, and the undelivered section is laid sequentially after the laying of the delivered section is completed, and the undelivered section and the delivered section are connected through to form a seamless line; the present application has good construction flexibility, high operating efficiency, and low machinery cost, and is not affected by the full track laying or discontinuous delivery of the offline roadbed, and can meet the requirements of the long rail installation and laying specifications.
[0043] It should be understood that the above general description and the following specific embodiments are only exemplary and illustrative and do not limit the scope of the present application. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] The attached drawings below are part of the specification of the present application, which illustrate embodiments of the present application. The attached drawings together with the description of the specification are used to explain the principles of the present application.
[0045] Figure 1 A flow chart of a semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0046] Figure 2 A schematic diagram of unloading rails from a rail trailer in the semi-mechanical long rail laying process for ballasted track provided in an embodiment of the present application.
[0047] Figure 3 A schematic diagram of welding long rails by a vehicle-mounted mobile welding machine in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0048] Figure 4 A schematic diagram of the ballast paving operation in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0049] Figure 5 A schematic diagram of transporting sleepers by a sleeper trailer and laying sleepers in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0050] Figure 6 This is a schematic diagram of the sleeper layout in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0051] Figure 7 A cross-sectional schematic diagram of the installation of long rails in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0052] Figure 8 A top view of the installation of long rails in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application.
[0053] Fig. 9 A schematic diagram of the construction sequence of the delivered section and the undelivered section in the semi-mechanical long rail laying construction process for ballasted track provided in an embodiment of the present application. DETAILED DESCRIPTION
[0054] In order to make the purpose, technical solutions and advantages of the embodiments of the present application more clearly understood, the spirit of the contents disclosed in the present application will be clearly explained with the accompanying drawings and detailed descriptions below. After understanding the embodiments of the contents of the present application, any technician in the relevant technical field can change and modify them according to the techniques taught by the contents of the present application without departing from the spirit and scope of the contents of the present application.
[0055] The exemplary embodiments and descriptions of the present application are used to explain the present application, but are not intended to limit the present application. In addition, elements / components with the same or similar reference numerals used in the drawings and embodiments are used to represent the same or similar parts.
[0056] The terms “first”, “second”, etc. used in this document do not particularly refer to an order or sequence, nor are they used to limit this application. They are only used to distinguish elements or operations described with the same technical terms.
[0057] The words “include,” “including,” “have,” “contain,” etc. used in this document are open-ended terms, meaning including but not limited to.
[0058] As used herein, "and / or" includes any or all combinations of the items described.
[0059] As used herein, “plurality” includes “two” and “more than two”; as used herein, “plurality of groups” includes “two groups” and “more than two groups”.
[0060] Certain terms used to describe the present application are discussed below or elsewhere in this specification to provide additional guidance to those skilled in the art regarding the description of the present application.
[0061] like Figure 1As shown, the semi-mechanical long rail laying construction process for ballasted track provided by the present application includes the following steps:
[0062] S1, determine the priority delivery section of the roadbed and carry out track laying operations on the priority delivery section.
[0063] Confirm the construction status of the delivered and undelivered sections of the roadbed with the offline units that ensure the roadbed, so as to formulate a construction plan, scientifically and reasonably plan the specific construction plan, achieve the continuity and feasibility of the construction, and then allocate reasonable construction resources.
[0064] S2. Build a standard rail storage area, sleeper storage area and ballast storage yard near the construction site, and transport the rails to the standard rail storage area, the sleepers to the sleeper storage area, and the ballast to the ballast storage yard. The process is as follows:
[0065] S21. From the starting point of track laying, set up standard rail storage areas and sleeper storage areas every 8km to 12km to store rails and sleepers in advance and reduce transportation distance during construction.
[0066] Among them, the equipment for transporting standard rails mainly includes cranes and rail trailers; the equipment for transporting sleepers mainly includes cranes and sleeper trailers.
[0067] S22. Ballast storage yards shall be set up near the track area at intervals of 18km to 22km from the starting point of track laying.
[0068] Among them, the main equipment for transporting ballast are dump trucks and loaders.
[0069] S23. Use construction access roads, rail trailers, sleeper trailers and loaders to transport rails, sleepers, ballast and other materials to the vicinity of the construction site.
[0070] Among them, the construction access road is the working access road of the offline unit of the roadbed and the access road from the working access road to the road surface. The construction access road is mainly used to meet the entry and exit of rail trailers and sleeper trailers, and ensure that rails and sleepers are transported from the storage area to the construction site.
[0071] S3. Confirm that the performance and condition of mechanical equipment such as rail trailers, sleeper trailers, vehicle-mounted mobile welding machines, sleeper scattering machines, crawler excavators, tire excavators, ballast spreaders, dump trucks, loaders, graders, fastener wrenches, and measuring equipment used in construction are normal.
[0072] The above-mentioned construction machinery and equipment should be debugged in advance to achieve optimal performance.
[0073] In addition, ensure that the equipment operators obtain the corresponding professional qualification certificates, undergo safety training, coordinate equipment operation with worker operation, etc. Configure a mechanical repair team to maintain the above-mentioned mechanical equipment used in construction.
[0074] S4. Measure and lay out the tracks, and re-bury the track outboard piles according to the track centerline to facilitate track laying.
[0075] Specifically, GPS is used to measure the position of track outward displacement piles for controlling the direction of the track during laying.
[0076] S5. The rails are transported from the standard rail storage area to the roadbed and placed. The process is as follows:
[0077] S51. Use a crane to load the standard rails onto a rail trailer in the standard rail storage area.
[0078] S52. Rail trailers transport rails to the roadbed surface in the construction area via construction access roads.
[0079] S53, such as Figure 2 As shown, the crawler excavator uses a rail hanger to unload the rails from the rail trailer, and places the unloaded rails in sequence along the extension direction of the roadbed, wherein the left and right rails in the width direction of the roadbed are spaced at a preset distance.
[0080] For the undelivered section of the roadbed, cross it first and then work on it after it is delivered. A passageway is reserved at every preset distance to facilitate dump trucks to transport ballast in and out of the construction area.
[0081] S6. The rails on the left and right sides of the roadbed are welded respectively to form long rails. The process is as follows:
[0082] S61, the vehicle-mounted mobile welding machine enters between the scattered rails through the construction access road.
[0083] S62, such as Figure 3 As shown, the vehicle-mounted mobile welding machine sequentially welds the rails on the left and right sides of the roadbed to form a long rail. The welding length of the rail is the length of the loose unit rail section.
[0084] S7: transporting ballast from the ballast storage yard to the construction site and performing ballast paving operations, the process is as follows:
[0085] S71. At the ballast storage yard, the loader loads the ballast onto the dump truck.
[0086] S72. The dump truck reverses through the construction access road and the reserved passageway toward the ballast paver.
[0087] S73. The ballast paver starts ballast paving operations from the construction starting point.
[0088] S74, such as Figure 4 As shown, the motor grader levels the paved ballast.
[0089] S75. After the dump truck has finished unloading the ballast, it drives out from the reserved passage, and the next dump truck enters the operation in a cycle.
[0090] S8. Transport the sleepers to the roadbed adjacent to the track and spread them on the ballast surface in accordance with the specifications. The process is as follows:
[0091] S81, such as Figure 5 As shown, the sleeper trailer is loaded with sleepers in the sleeper storage area and enters the roadbed adjacent to the track line in the laying section through the construction access road.
[0092] S82. The crawler excavator uses a sleeper hoist to unload the sleepers from the sleeper trailer.
[0093] S83, such as Figure 6 As shown, the sleeper spreading machine enters the laid ballast and evenly spreads the sleepers on the ballast surface according to the sleeper spacing required by the specification and with reference to the track outward displacement piles.
[0094] S9. Hoist the long rails into the rail bearing grooves of the sleepers to complete the track laying of the priority delivery section. The process is as follows:
[0095] S91. A tire excavator is equipped with a single spreader on the roadbed near the track line.
[0096] S92, such as Figure 7 As shown, the tire excavator uses a lifting device to lift the long welded rails.
[0097] S93, such as Figure 8 As shown, two tire excavators alternately lift the lifted long rails into the rail bearing grooves of the sleepers from back to front, working from one end to the other.
[0098] S94. Install the line fasteners on the sleepers and install the rails at the reserved passage openings. Now the long rails are installed.
[0099] S10. Using the construction procedures of steps S2 to S9, complete the track laying operation of the undelivered section, and connect the undelivered section with the delivered section to form a seamless line.
[0100] Compared with traditional construction technology, the semi-mechanical long rail laying construction technology for ballasted track provided by this application is flexible, convenient, efficient, saves construction time, reduces costs, is not affected by offline critical structures, and can complete the established goals on schedule. Laying tracks in the delivery section can effectively reduce the pressure of subsequent track laying; constructing the delivery section first and then the undelivered section is flexible in construction and provides a working surface for subsequent processes; it can effectively reduce the pressure of construction period of offline units.
[0101] like Fig. 9As shown, the semi-mechanical long rail laying construction process for ballasted track provided by this application breaks the limitations of existing track laying construction methods, and tracks are laid sequentially along the extension direction of the track; when encountering an undelivered section, it is crossed first, and the undelivered section is laid sequentially after the delivery section is laid, and the undelivered section and the delivered section are connected to form a seamless line. This application has high operating efficiency and low mechanical cost, is not affected by the full track laying or discontinuous delivery of the offline roadbed, and meets the requirements of the long rail installation and laying specifications; it is a construction method suitable for projects with tight schedules and delayed delivery of offline units, which affects the overall track laying progress and improves the overall progress of the project.
[0102] The above description is only an illustrative specific implementation manner of the present application. Without departing from the concept and principle of the present application, any equivalent changes and modifications made by any technician in the field should fall within the scope of protection of the present application.
Claims
1. A semi-mechanical long rail laying process for ballasted track, characterized in that: The following steps are involved: Determine the priority delivery section of the roadbed and carry out track laying operations on the priority delivery section; Build a standard rail storage area, sleeper storage area and ballast storage yard near the construction site, and transport the rails to the standard rail storage area, the sleepers to the sleeper storage area, and the ballast to the ballast storage yard respectively; Confirm that the performance and status of construction machinery and equipment are normal; Measure and lay out the track, and re-bury the track outward displacement piles according to the track centerline to facilitate track laying; Transport rails from standard rail storage areas to the roadbed and place them; The rails on the left and right sides of the roadbed are welded separately to form long rails; Transport ballast from the ballast storage yard to the construction site and perform ballast paving operations; Transport the sleepers to the roadbed adjacent to the track line and spread them on the ballast surface in accordance with the specifications; Lift the long rails into the rail grooves of the sleepers to complete the track laying of the priority delivery section; The above construction procedures are used to complete the track laying work of the undelivered section, and the undelivered section is connected with the delivered section to form a seamless line.
2. The semi-mechanical long rail laying construction process for ballasted track according to claim 1 is characterized in that: The process of building a standard rail storage area, a sleeper storage area and a ballast storage area near the construction site is as follows: At the starting point of self-laying track, standard rail storage areas and sleeper storage areas are built every 8km to 12km; at the starting point of self-laying track, ballast storage yards are set up in the area adjacent to the track every 18km to 22km.
3. The semi-mechanical long rail laying construction process for ballasted track according to claim 1 is characterized in that: The construction machinery and equipment include one or more of rail trailers, sleeper trailers, vehicle-mounted mobile welders, sleeper scattering machines, crawler excavators, tire excavators, ballast spreaders, dump trucks, loaders, graders, fastener wrenches and measuring equipment.
4. The semi-mechanical long rail laying construction process for ballasted track according to claim 3 is characterized in that: The process of transporting the rails from the standard rail storage area to the roadbed and placing them is as follows: Using a crane to load standard rails onto rail trailers in the standard rail storage area; The rail trailer transports the rails to the roadbed surface of the construction area through the construction access road; The crawler excavator uses a rail hoist to unload the rails from the rail trailer and places the unloaded rails in sequence along the extension direction of the roadbed, where the left and right rails in the roadbed width direction are spaced at a preset distance.
5. The semi-mechanical long rail laying construction process for ballasted track according to claim 3 is characterized in that: The process of welding the rails on the left and right sides of the roadbed to form long rails is as follows: The vehicle-mounted mobile welding machine enters between the scattered rails through the construction access road. The vehicle-mounted mobile welding machine sequentially welds the rails on the left and right sides of the roadbed to form long rails; wherein the welding length of the rails is the length of the dispersed unit rail section.
6. The semi-mechanical long rail laying construction process for ballasted track according to claim 3 is characterized in that: The process of transporting the ballast from the ballast storage yard to the construction site and performing the ballast paving operation is as follows: At the ballast storage yard, loaders load ballast onto dump trucks; The dump truck reverses through the construction access road and the reserved passageway toward the ballast paver; The ballast paver starts ballast paving operations from the construction starting point; The grader levels the paved ballast; After the dump truck completes unloading, it drives out through the reserved passage, and the next dump truck enters the operation in a cycle.
7. The semi-mechanical long rail laying construction process for ballasted track according to claim 3 is characterized in that: The process of transporting the sleepers to the roadbed adjacent to the track line and spreading them on the ballast surface according to the specification requirements is as follows: The sleeper trailer loads sleepers in the sleeper storage area and enters the roadbed near the track line in the laying section through the construction access road; The crawler excavator uses a sleeper lift to remove the sleepers from the sleeper trailer; The sleeper spreading machine enters the laid ballast and evenly spreads the sleepers on the ballast surface according to the sleeper spacing required by the specifications and with reference to the track outward displacement piles.
8. The semi-mechanical long rail laying construction process for ballasted track according to claim 3 is characterized in that: The process of hoisting the long rail into the rail bearing groove of the sleeper to complete the track laying of the priority delivery section is as follows: The tire excavator is equipped with a single spreader on the roadbed near the track line; The tire excavator uses a hoist to lift the long welded rails; Two tire excavators alternately lift the long rails from back to front into the rail grooves of the sleepers, working from one end to the other. Install the fastening line fasteners on the sleepers and install the rails at the reserved passage openings. Now the installation of the long rails is completed.
9. The semi-mechanical long rail laying construction process for ballasted track according to claim 1, characterized in that: When laying tracks on the priority delivery section, first cross the undelivered section of the roadbed, and then proceed with the work after the undelivered section of the roadbed is delivered.