Method and system for peak shifting regulation and storage of outdoor integrated pump station
By establishing a pump station water supply management system and peak staggered model in an outdoor integrated pump station, and automatically adjusting the water inlet time and water storage volume using the peak water storage algorithm, the problem that traditional pump stations cannot efficiently utilize IoT data is solved, and water use is realized Improved stability and water supply.
Patent Information
- Application Number
- CN202410878535.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-02
- Publication Date
- 2024-11-08
AI Technical Summary
Traditional outdoor integrated pump stations cannot efficiently utilize data collected by IoT devices, resulting in high water supply load during the day and difficult to achieve effective water resource allocation during peak periods of dry seasons, resulting in insufficient water use stability and water supply.
By establishing a water supply management system for pump stations, using the peak water storage algorithm to draw the water storage fluctuation function of secondary pump stations and water supply pump stations, combining the peak-off model, automatically calculate the water inlet time and water storage volume, realize peak-off water supply and ensure water use Stable supply.
The water tanks in a single community and the entire area have been realized to store water staggered water, reduce stagnant water, alleviate the large daytime water supply load and the water supply gap during the peak period of the dry season, and improve water use stability and pump station operation efficiency.
Smart Images

Figure CN118911242A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of water pump equipment, and in particular to a method and system for peak-shifting storage regulation of an outdoor integrated pump station. Background Art
[0002] With the popularization of IoT devices, outdoor integrated pump stations can monitor the water tank level, instantaneous flow, cumulative flow, inlet pressure and other data of the pump station in real time. The overall hardware of the pump station mainly includes secondary systems such as water supply units, electrical control systems, water quality monitoring systems, security systems, remote monitoring systems and overflow alarm systems. This traditional outdoor integrated pump station cannot efficiently utilize the data collected by IoT devices to cope with the working conditions of heavy water supply load during the day, high production pressure of the water production department, and water supply shortage during the peak period of the dry season. This will make it difficult for users who need water resources to obtain water resources in time during the time period when water resources are needed. To this end, it is necessary to propose a method and system for peak-shifting storage of outdoor integrated pump stations in view of the disadvantage that traditional outdoor integrated pump stations cannot efficiently utilize the data collected by IoT devices. Summary of the invention
[0003] Based on this, it is necessary to propose a method and system for peak-shifting storage of outdoor integrated pumping stations to address the drawback that traditional outdoor integrated pumping stations cannot efficiently utilize the data collected by IoT devices.
[0004] The present application provides a method for peak-shifting storage regulation of an outdoor integrated pump station, comprising:
[0005] Establish a pump station water supply management system, incorporate each secondary pump station into the pump station water supply management system, and incorporate the water supply pump station into the pump station water supply management system;
[0006] Select a secondary pumping station;
[0007] receiving water supply data and water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station;
[0008] Returning the water supply data and water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station, until the water supply data and water discharge data of each secondary pumping station in a historical working cycle of the secondary pumping station are received;
[0009] Based on the water supply data and water discharge data of each secondary pumping station in the historical working cycle of the secondary pumping station, a peak water storage algorithm is used to draw a first water storage fluctuation function curve of the secondary pumping station, and the first water storage fluctuation function curve of the secondary pumping station is incorporated into the data management set of the secondary pumping station;
[0010] Returning to the step of selecting a secondary pumping station until all the secondary pumping stations are selected, obtaining the first water storage fluctuation function curve of each secondary pumping station and incorporating each first water storage fluctuation function curve into the data management set of the secondary pumping station corresponding to the first water storage fluctuation function curve;
[0011] Receiving water supply data and water discharge data of multiple water supply pumping stations in historical working cycles of the water supply pumping stations, drawing a second water storage fluctuation function curve of the water supply pumping station by using a peak water storage algorithm based on the water supply data and water discharge data of multiple water supply pumping stations in historical working cycles of the water supply pumping stations, and incorporating the second water storage fluctuation function of the water supply pumping station into a data management set of the water supply pumping station;
[0012] The data management set of each secondary pump station, the data management set of the water supply pump station, and the peak-shifting regulation and storage logic are incorporated into the peak-shifting model as training data to train the peak-shifting model, so as to generate a trained peak-shifting model;
[0013] Obtain the water supply data and water discharge data of multiple secondary pumping stations to be tested during the working cycle to be tested of each secondary pumping station, and obtain the water supply data and water discharge data of multiple water supply pumping stations to be tested during the working cycle to be tested of the water supply pumping station, input the water supply data and water discharge data of multiple secondary pumping stations to be tested during the working cycle to be tested of each secondary pumping station, and the water supply data and water discharge data of multiple water supply pumping stations to be tested during the working cycle to be tested of the water supply pumping station into the trained peak shifting model, run the trained peak shifting model, and obtain the peak shifting regulation strategy output by the trained peak shifting model.
[0014] The present application relates to a system for peak-shifting storage and regulation of an outdoor integrated pump station, comprising:
[0015] A host computer, used to execute the above-mentioned method for peak-shifting storage and regulation of outdoor integrated pumping stations;
[0016] A plurality of water volume sensors are all communicatively connected with the host computer.
[0017] The present application relates to a method and system for staggered peak storage regulation of an outdoor integrated pump station. By establishing a pump station water supply management system, each secondary pump station and water supply pump station is included in the pump station water supply management system, and the pump room water tank level, instantaneous flow, cumulative flow, inlet pressure and other data are monitored in a timely manner. Based on the peak water storage algorithm, the water supply data and water discharge data of multiple working cycles of the secondary pump station and the water supply data and water discharge data of multiple working cycles of the water supply pump station are processed to obtain the first water storage fluctuation function of the secondary pump station and the second water storage fluctuation function of the water supply pump station. The first water storage fluctuation function and the second water storage fluctuation function of the water supply pump station are stored in the water supply pump station data management set. The staggered peak model calls the data 0 in the water supply pump station data management set to predict the water inflow and water inflow time, and controls the water inflow time during the low peak period of water use, thereby realizing staggered water supply and ensuring a stable water supply. It is worth mentioning that the data collection of the secondary pump station can automatically calculate the water inflow time period and water storage capacity according to the water use habits of the community. The water tanks in a single community can be staggered to store water, and the water level in a single water tank can be dynamically replaced to reduce dead water. At the same time, based on the pump station water supply management system, the water storage capacity of the entire area and the water storage time of each water tank can be automatically calculated according to the peak and low-peak time periods of the water supply area of the water plant, combined with the water demand of each community. The pipeline network in the entire area can be staggered to adjust the water storage. Effectively alleviate the production pressure of the water production department due to the heavy water supply load during the day, and reduce the water supply gap during the peak period of the dry season. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A schematic flow chart of a method for peak-shifting storage and regulation of an outdoor integrated pump station provided in one embodiment of the present application.
[0019] Figure 2 A schematic diagram of a water storage curve for peak-shifting regulation of an outdoor integrated pumping station provided in one embodiment of the present application.
[0020] Figure 3 A schematic diagram of a water supply curve for peak-shifting regulation of an outdoor integrated pump station provided in one embodiment of the present application.
[0021] Figure 4 A schematic diagram of a water discharge curve for peak-shifting regulation of an outdoor integrated pumping station provided in one embodiment of the present application.
[0022] Figure 5 A schematic diagram of a first water storage fluctuation function for peak-shifting storage regulation of an outdoor integrated pumping station provided in one embodiment of the present application.
[0023] Figure 6 A system structure connection diagram for peak-shifting regulation of an outdoor integrated pump station provided in one embodiment of the present application.
[0024] Reference numerals:
[0025] 100-host computer; 200-water level sensor. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0027] The present application provides a method for peak-shifting storage regulation of an outdoor integrated pump station.
[0028] like Figure 1 As shown, in one embodiment of the present application, a method for peak-shifting storage and regulation of an outdoor integrated pump station includes:
[0029] S100, establish a pump station water supply management system, incorporate each secondary pump station into the pump station water supply management system, and incorporate the water supply pump station into the pump station water supply management system.
[0030] Specifically, the secondary pumping station and water supply pumping station are incorporated into the pumping station water supply management system, and remote monitoring and automatic control are realized through the Internet of Things technology, which is highly automated and intelligent. It can monitor the operating status in real time, conduct data analysis, realize fault diagnosis and early warning, and greatly improve the operating efficiency and reliability of the pumping station.
[0031] S200, select a secondary pumping station.
[0032] S300, receiving water supply data and water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station.
[0033] Specifically, the secondary pump station can be networked with the water supply pump station or operate independently. According to the water use habits of the community, the water inflow time period and water storage volume are automatically calculated. The water tanks of a single community can be staggered to store water, and the water level of a single water tank can be dynamically replaced to reduce dead water.
[0034] In fact, the secondary pumping station is a relatively independent unit, and the overall design of the pumping station is highly integrated, including water supply units, electrical control systems, water quality monitoring systems, security systems, remote monitoring systems, and overflow alarm systems. In other words, the secondary pumping station Internet of Things has a wide coverage and a high degree of intelligence.
[0035] S400, returning to the step of receiving the water supply data and the water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station, until the water supply data and the water discharge data of each secondary pumping station in a historical working cycle of the secondary pumping station are completely received.
[0036] S500, based on the water supply data and water discharge data of each secondary pumping station in the historical working cycle of the secondary pumping station, the peak water storage algorithm is used to draw the first water storage fluctuation function curve of the secondary pumping station, and the first water storage fluctuation function curve of the secondary pumping station is incorporated into the data management set of the secondary pumping station.
[0037] S600, returns to the selection of a secondary pumping station until all the secondary pumping stations are selected, obtains the first water storage fluctuation function curve of each secondary pumping station and incorporates each first water storage fluctuation function curve into the data management set of the secondary pumping station corresponding to the first water storage fluctuation function curve.
[0038] S700, receiving water supply data and water discharge data of multiple water supply pumping stations within historical working cycles of the water supply pumping stations, drawing a second water storage fluctuation function curve of the water supply pumping station using a peak water storage algorithm based on the water supply data and water discharge data of multiple water supply pumping stations within historical working cycles of the water supply pumping stations, and incorporating the second water storage fluctuation function of the water supply pumping station into the data management set of the water supply pumping station.
[0039] S800, the data management set of each secondary pump station, the data management set of the water supply pump station, and the peak-shifting regulation and storage logic are incorporated into the peak-shifting model as training data to train the peak-shifting model to generate a trained peak-shifting model.
[0040] S900, obtain the water supply data and water discharge data of multiple secondary pumping stations to be tested in the working cycle to be tested of each secondary pumping station, and obtain the water supply data and water discharge data of multiple water supply pumping stations to be tested in the working cycle to be tested of the water supply pumping station, input the water supply data and water discharge data of multiple secondary pumping stations to be tested in the working cycle to be tested of each secondary pumping station, and the water supply data and water discharge data of multiple water supply pumping stations to be tested in the working cycle to be tested of the water supply pumping station into the trained peak shifting model, run the trained peak shifting model, and obtain the peak shifting regulation strategy output by the trained peak shifting model.
[0041] The present application relates to a method for peak-shifting storage of an outdoor integrated pump station. By establishing a pump station water supply management system, each secondary pump station and water supply pump station are included in the pump station water supply management system, and the pump room water tank level, instantaneous flow, cumulative flow, inlet pressure and other data are monitored in time. Based on the peak water storage algorithm, the water supply data and water discharge data of multiple working cycles of the secondary pump station and the water supply data and water discharge data of multiple working cycles of the water supply pump station are processed to obtain the first water storage fluctuation function of the secondary pump station and the second water storage fluctuation function of the water supply pump station. The first water storage fluctuation function and the second water storage fluctuation function of the water supply pump station are stored in the water supply pump station data management set. The peak-shifting model calls the data in the water supply pump station data management set to predict the water inflow and water inflow time, and controls the water inflow time during the low peak period of water use, thereby realizing peak-shifting water supply and ensuring a stable water supply. It is worth mentioning that the data collection of the secondary pump station can automatically calculate the water inflow time period and water storage volume according to the water use habits of the community. The water tank of a single community is staggered for water storage, and the water level of a single water tank is dynamically replaced to reduce dead water. At the same time, based on the pump station water supply management system, the water storage capacity of the entire area and the water storage time of each water tank can be automatically calculated according to the peak and off-peak time periods of the water supply area of the water plant, combined with the water demand of each community. The water storage of the entire area can be realized by staggered water diversion in the pipeline network. The production pressure of the water production department due to the heavy water supply load during the day can be effectively alleviated, and the water supply gap during the peak period of the dry season can be reduced.
[0042] In one embodiment of the present application, S100 includes:
[0043] S110, setting a network disconnection traversal check time period. The network disconnection traversal check time period is a time period.
[0044] Specifically, generally speaking, the network disconnection traversal check time includes the waiting time and the check program execution time. For example, if the waiting time is 5 minutes and the check program execution time is 5 minutes, then the network disconnection traversal check time is 10 minutes.
[0045] S120, determining the end time point of the previous network disconnection traversal check time period.
[0046] Specifically, when the end time of the last network disconnection traversal check is 15:20 on January 1, 2023, the next network disconnection traversal check program will be from 15:20 on January 1, 2023 to 15:30 on January 1, 2023.
[0047] S130, based on the current system time and the network disconnection traversal check time period, determine whether to execute the current network disconnection traversal check program.
[0048] Specifically, if the current system time is 15:24 on January 1, 2023, the current network disconnection traversal check program is in the waiting time and the check program is not executed.
[0049] S140: If the time difference between the current system time and the end time point of the previous network disconnection traversal check time period closest to the current system time is less than the duration of the network disconnection traversal check time period, the network disconnection traversal check program is not executed.
[0050] S150, if the time difference between the current system time and the end time point of the previous network disconnection traversal check time closest to the current system time is equal to or greater than the duration of the network disconnection traversal check time period, execute the subsequent step of selecting a secondary pump station.
[0051] Specifically, based on the example that if the current system time is 15:24 on January 1, 2023, the current network disconnection traversal check program is in the waiting time and the check program is not executed. If the current system time is 15:26 on January 1, 2023, the time interval between 15:26 on January 1, 2023 and the end time point of the last network disconnection traversal check time is 15:20 on January 1, 2023 is 6 minutes, which is greater than the waiting time of 5 minutes, so it is in the check program execution time and the check program is being executed.
[0052] S160, receiving a feedback signal from the secondary pump station.
[0053] S170, based on the feedback signal of the secondary pumping station, determine whether the feedback signal of the secondary pumping station is an idle signal; the idle signal is the feedback value of the circuit break judgment program.
[0054] Specifically, when the host computer receives a code of -1, the host computer can determine that the communication of the secondary pumping station is interrupted, that is, the secondary pumping station is disconnected from the pumping station water supply management system.
[0055] S180, if the feedback signal of the secondary pump station is an idle signal, a disconnection tag is assigned to the secondary pump station, and the information that the circuit of the secondary pump station is disconnected is fed back to the pump station water supply management system.
[0056] S190, if the feedback signal of the secondary pumping station is not an idle signal, then execute the subsequent step of receiving the water supply data and water discharge data within a historical working cycle of the secondary pumping station; the duration of the network disconnection traversal check time period is less than or equal to the minimum secondary pumping station historical working cycle of the secondary pumping station.
[0057] This embodiment relates to a pump station water supply management system. The stand-alone monitoring task can be performed through its own Internet of Things system. That is, the secondary pump station is separated from the pump station water supply management system. The data collection of the secondary pump station can automatically calculate the water inlet time period and water storage volume according to the water use habits of the community. The water tank of a single community can be staggered to store water, and the water level of a single water tank can be dynamically replaced to reduce dead water.
[0058] At the same time, based on the pump station water supply management system, the water storage capacity of the entire area and the water storage time of each water tank can be automatically calculated according to the peak and off-peak time periods of the water supply area of the water plant, combined with the water demand of each community. The water storage of the entire area can be realized by staggered water diversion in the pipeline network. The production pressure of the water production department due to the heavy water supply load during the day can be effectively alleviated, and the water supply gap during the peak period of the dry season can be reduced.
[0059] The execution priority of the disconnection traversal check program of the secondary pump station with the disconnection tag is listed as the first priority. The execution of the disconnection traversal check program of the secondary pump station with the same priority is arranged in order of priority using a random number function. When executing the disconnection traversal check program, the disconnection traversal check program of each secondary pump station is executed in sequence according to the execution priority of the disconnection traversal check program.
[0060] In one embodiment of the present application, S180 includes:
[0061] S181, assigning an off-network label to the secondary pump station.
[0062] S182, listing the off-network traversal check program execution priority of the secondary pump station with the off-network tag as the first priority.
[0063] Specifically, the selection of secondary pumping stations with the same priority level is arranged in order of priority using a random number function. A secondary pumping station may successfully enter the pumping station water supply management system within a period of time. In this case, the secondary pumping station may be disconnected from the network because of a problem with the communication device, which requires manual maintenance.
[0064] Another situation is that the pump station water supply management system has entered the information of the secondary pump station, but the secondary pump station has no communication access to the pump station water supply management system.
[0065] Prioritizing secondary pumping stations with disconnection tags as the first priority can improve the entire pumping station water supply management system.
[0066] S183, when executing the network disconnection traversal checking program, execute the network disconnection traversal checking program according to the priority of the network disconnection traversal checking program.
[0067] S184, returning the feedback signal received from the secondary pumping station until the current network disconnection traversal check program is completed to determine the secondary pumping station with multiple network disconnection tags.
[0068] S185, receiving manually imported water supply data and water discharge data of each secondary pumping station having multiple disconnection tags, so as to integrate the secondary pumping station into the pumping station water supply management system.
[0069] This embodiment involves the information collection of secondary pumping stations. Since the secondary pumping stations in the pumping station water supply management system are connected to the water supply pumping stations through pipelines, the water supply data and water discharge data of each secondary pumping station with multiple disconnection tags can be imported to collect the data of the pumping station water supply management system more completely, which is conducive to the pumping station water supply management using algorithms to predict the water inflow and water inflow time, and control the water inflow time during the low water consumption period.
[0070] like Figures 2 to 5 As shown, in one embodiment of the present application, the peak water storage algorithm in S500 includes:
[0071] S510, receiving a working cycle of a secondary pump station, and determining an inclusion relationship between a system time axis and the working cycle. The unit set of the system time axis is year, month, day and hour.
[0072] Specifically, the system timeline is a natural time period, such as the time when the pump station water supply management system was completed from 16:00 on April 12, 2018 to the current time point of 16:00 on February 12, 2025, so 16:00 on April 12, 2018 to 16:00 on February 12, 2025 is a timeline.
[0073] When the data of the secondary pumping station with a working cycle from 16:00 on April 12, 2020 to 18:00 on April 12, 2020 is received, this working cycle of the secondary pumping station is included in the system timeline.
[0074] S520, integrating the water supply data and the water discharge data in each working cycle of the secondary pump station into a plurality of data points and marking them on the water supply curve, the water discharge curve and the water storage curve respectively.
[0075] Specifically, in the reservoir model, in addition to the parameter of time, the relationship between water supply and time, the relationship between water output and time, and the relationship between water storage in the reservoir and time will affect water allocation.
[0076] Therefore, the relationship between water supply and time has a water supply curve in the two-dimensional graph of system time axis and water volume.
[0077] Therefore, the relationship between water output and time has a water supply curve in the two-dimensional graph of system time axis and water volume.
[0078] Therefore, the relationship between the water storage capacity and time in the reservoir has a water storage curve in the two-dimensional graph of system time axis and water volume.
[0079] S530, taking an average of the water storage capacities of all data points of the water storage curve, dividing the water storage curve using the average of the water storage capacities of the water storage curve, and determining the lowest point and the highest point of the water storage curve.
[0080] Specifically, in the water storage curve, the lowest and highest points of the water storage curve can provide feedback on the water abundance of the water storage tank in the secondary pump station. The water storage tank has a buffering function for regulating and allocating water in the entire outdoor integrated pump station system. That is, when the peak water storage algorithm predicts that the water volume will be insufficient at some point in the future based on the data, the water storage tank can store water in advance. This achieves the function of dynamic adjustment and staggered water storage.
[0081] S540: Draw a plurality of water storage guarantee threshold lines on the water storage curve based on the water storage amount at the lowest point and the water storage amount at the highest point of the water storage curve. Each water storage guarantee threshold line is parallel to the expression line of the water storage amount mean of the water storage curve.
[0082] Specifically, the average water volume in the water tank can basically reflect the dynamic fluctuation range of the water volume in the water tank during the entire time period, which is of reference significance for peak shifting and adjusting water volume.
[0083] In fact, the entire outdoor integrated pumping station has more than one water storage tank. Dynamically adjusting the water volume of each water storage tank in the outdoor integrated pumping station system can help alleviate the working pressure of the outdoor integrated pumping station during peak water discharge periods.
[0084] S550, using a plurality of water storage guarantee threshold lines and an expression line of the water storage amount mean of the water storage curve, the water supply curve and the water discharge curve are respectively segmented to obtain a plurality of water supply guarantee time periods and a plurality of water discharge guarantee time periods.
[0085] Specifically, under normal circumstances, the water volume in the water tank of the secondary pump station fluctuates slightly within a working cycle, that is, the expression line of the mean value will be close to the entire water storage curve.
[0086] When there is a peak water usage period, without the help of a peak water storage algorithm, the secondary pump station will be overloaded to meet the large water demand.
[0087] When these water demands decrease, the secondary pumping station will have a water surplus. At this time, the water storage capacity of the water storage tank will fluctuate around the mean expression line. The time corresponding to this water storage fluctuation is the water supply guarantee period and the water output guarantee period.
[0088] More specifically, when the water storage curve is below the 35% water storage guarantee threshold line, the time period will be marked, such as Figure 2 As shown, the time period from T1 to T2.
[0089] Similarly, when the water storage curve is above the 65% water storage guarantee threshold line, the time period will be marked, such as Figure 2 As shown, the time period from T3 to T4.
[0090] S560, determining a first water storage fluctuation function through a plurality of water supply guarantee time periods, a plurality of water output guarantee time periods and a water storage curve.
[0091] Specifically, the amount of water replenishment should be increased during the period from T1 to T2 or before the period from T1 to T2.
[0092] During the period from T3 to T4 or before the period from T3 to T4, the amount of water replenishment should be reduced or stored water should be pumped out for water storage allocation.
[0093] Specifically, based on the explanation in S450, the first water storage fluctuation function may actually be a piecewise function based on the water supply guarantee time period and the water output guarantee time period.
[0094] In one embodiment of the present application, the peak water storage algorithm in S500 further includes:
[0095] S571, select a water supply guarantee time period.
[0096] S572, determining the average water supply rate during the water supply guarantee time period.
[0097] S573, returning to the process of selecting a water supply guarantee time period until all water supply guarantee time periods are selected and completed.
[0098] Specifically, due to the large capacity of the water tank and the small amount of water used, the water is not replaced for a long time, causing water pollution and other problems that will affect the actual capacity of the water tank of the entire system. According to the usage pattern of the water tank liquid level, the water inlet time and water inlet level are automatically adjusted. The cleaning time is automatically set in the early morning when no one is using water, and the spray drainage system is automatically turned on to enter the cleaning mode to reduce the impact on user water use.
[0099] S581, select a water supply guarantee time period.
[0100] S582, determining the average water outflow rate within the water outflow guarantee time period.
[0101] S583, returning to the process of selecting a water supply guarantee time period until all water supply guarantee time periods are selected.
[0102] Specifically, based on the average water supply rate in the water supply guarantee time period and the average water output rate in the water output guarantee time period, the water supply guarantee time period and the water output guarantee time period, a first water storage fluctuation function can be generated, which can be a piecewise function based on the water supply guarantee time period and the water output guarantee time period.
[0103] In one embodiment of the present application, S540 includes:
[0104] S541, call the water tank capacity of the secondary pump station.
[0105] Specifically, the water storage tank capacity of each secondary pumping station is a reflection of the regulation and storage capacity of each secondary pumping station. In fact, when executing the water supply distribution plan, that is, when the peak-shifting model is executed, the water storage tank capacity of the secondary pumping station plays a guiding role in allocating water in advance. Simply put, the water storage tank capacity of each secondary pumping station takes into account the water consumption and water consumption speed of the entire community when the water storage tank is built.
[0106] S542, based on the water storage at the lowest point of the water storage curve, the water storage at the highest point of the water storage curve and the water tank capacity of the secondary pumping station, determine the ratio of the water storage at the lowest point of the water storage curve to the water tank capacity of the secondary pumping station, and the ratio of the water storage at the highest point of the water storage curve to the water tank capacity of the secondary pumping station.
[0107] Specifically, based on the water storage tank capacity and water storage curve of the secondary pump station, the liquid level change of the water tank can be roughly divided into several liquid level segments, that is, the water storage guarantee threshold line is determined.
[0108] S543, defining a first ratio between the water storage capacity at the lowest point of the water storage curve and the water storage tank capacity of the secondary pump station.
[0109] S544, defining a second ratio between the water storage capacity at the highest point of the water storage curve and the water storage tank capacity of the secondary pump station.
[0110] S545, divide the numerical interval between the first ratio and the second ratio into N sub-intervals; N is a positive integer.
[0111] S546: Draw a straight line parallel to the horizontal axis through the data point where the first ratio is located as a water storage guarantee threshold line corresponding to the first ratio.
[0112] S547, draw a straight line parallel to the horizontal axis through the data point where the second ratio is located as a water storage guarantee threshold line corresponding to the second ratio.
[0113] S548: Delineate a water storage guarantee threshold line between every two adjacent sub-intervals to form a plurality of water storage guarantee threshold lines between the water storage guarantee threshold line corresponding to the first ratio and the water storage guarantee threshold line corresponding to the second ratio.
[0114] Specifically, this embodiment is briefly described by way of an example:
[0115] For example, for a 100-cubic-meter water tank, the water storage capacity at the lowest point of the water storage curve is 20 cubic meters, and the first ratio is 20%. Similarly, if the water storage capacity at the highest point of the water storage curve is 80 cubic meters, the second ratio is 80%. When N=4, the water storage guarantee threshold line is the 20% water storage guarantee threshold line, the 35% water storage guarantee threshold line, the 50% water storage guarantee threshold line, the 65% water storage guarantee threshold line, and the 80% water storage guarantee threshold line. Generally speaking, when the steady-state water level of the water tank of the secondary pump station, that is, the liquid level of the water tank is stable, the liquid level of the water tank will be close to the 50% water storage guarantee threshold line. The average water volume of the water tank will also be close to the 50% water storage guarantee threshold line. When it is necessary to clean the impurities on the inner wall of the water tank, the water tank will be drained to the 20% water storage guarantee threshold line.
[0116] This embodiment relates to a peak water storage algorithm. The peak water storage algorithm is based on the water storage guarantee threshold line of the water storage tank of each secondary pumping station. When the steady-state water level of the water storage tank of the secondary pumping station is associated with time, since the water use habits of each season and each water user group remain generally unchanged, the peak and valley value changes of the water storage tank of the secondary pumping station can be quantitatively controlled. This greatly alleviates the production pressure of the water production department due to the large water supply load during the day, and reduces the water supply gap during the peak period of the dry season.
[0117] In one embodiment of the present application, the peak shifting model in S800 includes:
[0118] S810, calling the water supply data and water discharge data of the secondary pumping station in K consecutive full years in the data management set of the water supply pumping station, and the water supply data and water discharge data of the water supply pumping station in the same K consecutive full years, to form a sample library of the peak shifting model. K is a positive integer.
[0119] The water supply data and water discharge data of multiple working cycles of the water supply pump station are received, and based on the peak water storage algorithm, multiple second water storage fluctuation functions of the water supply pump station are obtained, specifically:
[0120] S710, receiving a working cycle of a water supply pump station, and determining an inclusion relationship between a system time axis and the working cycle. The unit set of the system time axis is year, month, day and hour.
[0121] S720: Mark the water supply data and water discharge data of a working cycle of the water supply pump station on the system time axis to form a second water storage fluctuation curve set. The second water storage fluctuation curve set includes a water supply curve, a water discharge curve and a water storage curve.
[0122] S730, taking an average of the water storage curve, dividing the water storage curve using the average of the water storage curve, and determining the lowest point and the highest point of the water storage curve.
[0123] S740: Based on the water storage amount at the lowest point and the water storage amount at the highest point of the water storage curve, a water storage guarantee threshold line is divided. The water storage guarantee threshold line is parallel to an expression line of the mean value of the water storage curve.
[0124] S750, using the water storage guarantee threshold line and the expression line of the mean value of the water storage curve, the water supply curve and the water discharge curve are segmented to obtain multiple water supply guarantee time periods and multiple water discharge guarantee time periods.
[0125] S760, determining a second water storage fluctuation function through the water supply guarantee time period, the water output guarantee time period and the water storage curve.
[0126] S820: Select a time period in a system timeline.
[0127] Specifically, the system time axis is taken as the traversal baseline, the system time axis is divided into multiple time periods, and the water supply, water discharge and water storage conditions of the entire outdoor integrated pump station within the time period are traversed.
[0128] S830: Select a time period corresponding to the second water storage fluctuation function of the water supply pump station in the sample library.
[0129] Specifically, during the peak-shifting and storage process, the water supply pump station can serve as the water supply, water discharge and water storage hub for the entire outdoor integrated pump station in each period, which ensures the water supply, water discharge and water storage actions of the water supply pump station have a regulating effect on the entire secondary pump station system network.
[0130] S840, selecting a time period corresponding to a first water storage fluctuation function of a secondary pumping station in the sample library.
[0131] S851, based on the first water storage fluctuation function of the secondary pump station in the corresponding time period, determine whether the water storage capacity of the secondary pump station in the time period fluctuates.
[0132] S852, if the water storage capacity of the secondary pumping station does not fluctuate within the time period, return to the time period corresponding to the first water storage fluctuation function of a secondary pumping station in the selected sample library until all secondary pumping stations are selected.
[0133] Specifically, the water storage capacity of the secondary pumping station did not fluctuate, indicating that the water supply and discharge of the secondary pumping station were in a relatively balanced state during the sample period, and there was no need to supply or drain water in advance.
[0134] S853, if the water storage capacity of the secondary pumping station fluctuates within the time period, the average water supply rate and the average water discharge rate of the secondary pumping station within the time period are called, and the corresponding time period in the first water storage fluctuation function of a secondary pumping station in the selected sample library is returned until all secondary pumping stations are selected.
[0135] Specifically, the water pump station can be the water supply, water discharge and water storage hub of the entire outdoor integrated pump station in each time period. The average total water supply and average total water discharge of all secondary pump stations in the statistical sample time period can determine the water supply, water discharge and water storage capacity of the water supply pump station.
[0136] S861, based on the average water supply rate of all secondary pumping stations and the corresponding time period, determine the average total water supply and average total water output of all secondary pumping stations.
[0137] S862, calling the second water storage fluctuation function of the water supply pump station to determine the total water supply and total water output of the water supply pump station in the corresponding time period.
[0138] S863, using the total water output of the water supply pump station in the corresponding time period and the average total water supply of all secondary pump stations, determine the water loss of the outdoor integrated pump station in the corresponding time period.
[0139] Specifically, the biggest sample error of outdoor integrated pump stations is caused by pipe damage, water leakage, etc. Such inaccurate sample data can be avoided by calculating the water loss in the corresponding time period.
[0140] S864, using the total water output of the water supply pump station in the corresponding time period and the average total water output of all secondary pump stations, determine the dynamic surplus of the outdoor integrated pump station in the corresponding time period.
[0141] Specifically, based on the total water output of the water supply pump station in the corresponding time period and the average total water output of all secondary pump stations, it can be determined whether the outdoor integrated pump station is short of water in the corresponding time period, that is, the dynamic surplus of the outdoor integrated pump station in the corresponding time period.
[0142] S865, returning to the process of selecting a time period in the system timeline until K consecutive complete years in the system timeline are selected.
[0143] In one embodiment of the present application, the peak shifting model in S800 further includes:
[0144] S871, based on the water loss amount of the outdoor integrated pumping station in each corresponding time period and the water loss threshold, determine whether the water loss amount of the outdoor integrated pumping station in each corresponding time period is greater than the water loss threshold.
[0145] S872: If the amount of water lost by the outdoor integrated pump station in each corresponding time period is greater than the water loss threshold, the samples in the time period are removed.
[0146] Specifically, this situation occurs when the pipes of the outdoor integrated pump station are damaged or leaking, which causes inaccurate data for this group of samples and requires the samples of this time period to be eliminated.
[0147] S873: If the amount of water lost by the outdoor integrated pump station in each corresponding time period is less than or equal to the water loss threshold, determine whether the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero.
[0148] S874: If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero, the total water supply of the water supply pump station in the corresponding time period is adjusted.
[0149] S875: If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is equal to zero, the water supply and water output of the outdoor integrated pump station in the corresponding time period are maintained.
[0150] Specifically, the dynamic surplus of the outdoor integrated pumping station in the corresponding time period is equal to zero, indicating that the outdoor integrated pumping station is in normal working condition during the sample time.
[0151] There are two situations in this working state:
[0152] On the one hand, it may be that users' water demand is not high and the pumping station is performing normal water supply and intake work.
[0153] On the other hand, it may be that the user's water demand has surged, and the pump station system has stored water in advance to ensure the demand for the surge in water use. At the same time, the pump station is performing normal water supply and intake work.
[0154] S876: If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is less than zero, the total water supply of the water supply pump station in the corresponding time period is adjusted.
[0155] In one embodiment of the present application, the peak shifting model in S800 further includes:
[0156] S881, calling the water storage guarantee threshold line in the corresponding time period.
[0157] S882, Select a secondary pumping station.
[0158] S883: If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero, determine whether the water storage capacity of the secondary pump station in the corresponding time period exceeds the water storage guarantee threshold line.
[0159] S884, if the water storage capacity of the time period corresponding to the secondary pumping station is greater than the water storage capacity corresponding to the water storage guarantee threshold line, the secondary pumping station is included in the list of water supply to be reduced, and the process of selecting a secondary pumping station is returned until all secondary pumping stations are selected.
[0160] Specifically, in the process of implementing staggered water supply and inlet allocation, the water supply pump station will reduce or increase the water intake of the secondary pump station, and will also store water in advance based on the target water shortage of the overall secondary pump station.
[0161] S885, if the water storage capacity of the time period corresponding to the secondary pumping station is less than or equal to the water storage capacity corresponding to the water storage guarantee threshold line, return to the selection of a secondary pumping station until all secondary pumping stations are selected.
[0162] Specifically, if the water storage capacity of the secondary pump station in the corresponding time period does not exceed the water storage guarantee threshold line, it can be determined that the user's water demand is not high and the pump station is performing normal water supply and intake work.
[0163] S886, if the water storage capacity of the time period corresponding to the secondary pumping station is lower than the water storage guarantee threshold line, the secondary pumping station is included in the list of water supply to be increased, and the process of selecting a secondary pumping station is returned until all the secondary pumping stations are selected.
[0164] S887, count the number of secondary pumping stations in the list of water supply to be reduced and the list of water supply to be increased, and reduce the water supply of the water supply pumping station according to the water supply reduction formula.
[0165] Specifically, in general, the scale of the secondary pumping stations is roughly the same. In this case, the water supply formula is used:
[0166] Water supply formula = the number of items in the list of water supply to be increased - the number of items in the list of water supply to be reduced.
[0167] In fact, in S446, N=4, and the water storage capacity of the secondary pumping station in the corresponding time period is between 35% and 65% of the water storage guarantee threshold line. It can be considered that the water storage capacity of the secondary pumping station in the corresponding time period does not exceed the water storage guarantee threshold line.
[0168] If the water storage capacity of the secondary pumping station in the time period corresponding to the secondary pumping station is between 20% and 35% of the water storage guarantee threshold line, it can be considered that the water storage capacity of the secondary pumping station in the time period corresponding to the secondary pumping station is lower than the water storage guarantee threshold line.
[0169] If the water storage capacity of the time period corresponding to the secondary pumping station is between 65% and 80% of the water storage guarantee threshold line, it can be considered that the water storage capacity of the time period corresponding to the secondary pumping station exceeds the water storage guarantee threshold line.
[0170] This embodiment involves a peak-shifting model. The data collection of the secondary pump station can automatically calculate the water inlet time period and water storage capacity according to the water use habits of the community. The water tanks of a single community can be staggered for water storage, and the water level of a single water tank can be dynamically replaced to reduce dead water. At the same time, based on the pump station water supply management system, the water storage capacity of the entire area and the water storage time of each water tank can be automatically calculated according to the peak and low-peak water use time periods of the water supply area of the water plant, combined with the water demand of each community. The pipeline network in the entire area can be staggered for water storage. Effectively alleviate the production pressure of the water production department due to the heavy water supply load during the day, and reduce the water supply gap during the peak period of the dry season.
[0171] like Figure 6 As shown, in one embodiment of the present application, a system for peak-shifting storage and regulation of an outdoor integrated pump station includes a host computer 100 and a water volume sensor 200.
[0172] The host computer 100 is used to execute the method for peak-shifting storage and regulation of outdoor integrated pumping stations.
[0173] The plurality of water volume sensors 200 are all communicatively connected to the host computer 100 .
[0174] Specifically, the host computer 100 controls the pump bodies of each pump station.
[0175] The present application relates to a system for staggered peak storage and regulation of outdoor integrated pump stations. The host computer 100 incorporates each secondary pump station and water supply pump station into the pump station water supply management system by establishing a pump station water supply management system. The water volume sensor 200 timely monitors the pump room water tank level, instantaneous flow, cumulative flow, inlet pressure and other data. Based on the peak water storage algorithm, the water supply data and water discharge data of multiple working cycles of the secondary pump station and the water supply data and water discharge data of multiple working cycles of the water supply pump station are processed to obtain the first water storage fluctuation function of the secondary pump station and the second water storage fluctuation function of the water supply pump station. The staggered peak storage of water tanks in a single community and the dynamic replacement of the water level of a single water tank are realized to reduce dead water. At the same time, based on the pump station water supply management system, the water storage capacity of the entire area and the water storage time of each water tank can be automatically calculated according to the peak and low peak time periods of the water supply area of the water plant, combined with the water demand of each community. The pipeline network of the entire area is realized to stagger water storage and regulation. It can effectively alleviate the production pressure of water production departments due to the heavy water supply load during the day and reduce the water supply gap during the peak period of the drought season.
[0176] The technical features of the above-described embodiments may be arbitrarily combined, and the execution order of the method steps is not limited. To make the description concise, not all possible combinations of the technical features in the above-described embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.
[0177] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the attached claims.
Claims
1. A method for peak-shifting storage and regulation of outdoor integrated pumping stations, characterized in that: include: Establish a pump station water supply management system, incorporate each secondary pump station into the pump station water supply management system, and incorporate the water supply pump station into the pump station water supply management system; Select a secondary pumping station; receiving water supply data and water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station; Returning the water supply data and water discharge data of a secondary pumping station in a historical working cycle of the secondary pumping station, until the water supply data and water discharge data of each secondary pumping station in a historical working cycle of the secondary pumping station are received; Based on the water supply data and water discharge data of each secondary pumping station in the historical working cycle of the secondary pumping station, a peak water storage algorithm is used to draw a first water storage fluctuation function curve of the secondary pumping station, and the first water storage fluctuation function curve of the secondary pumping station is incorporated into the data management set of the secondary pumping station; Returning to the step of selecting a secondary pumping station until all the secondary pumping stations are selected, obtaining the first water storage fluctuation function curve of each secondary pumping station and incorporating each first water storage fluctuation function curve into the data management set of the secondary pumping station corresponding to the first water storage fluctuation function curve; Receiving water supply data and water discharge data of multiple water supply pumping stations in historical working cycles of the water supply pumping stations, drawing a second water storage fluctuation function curve of the water supply pumping station by using a peak water storage algorithm based on the water supply data and water discharge data of multiple water supply pumping stations in historical working cycles of the water supply pumping stations, and incorporating the second water storage fluctuation function of the water supply pumping station into a data management set of the water supply pumping station; The data management set of each secondary pump station, the data management set of the water supply pump station, and the peak-shifting regulation and storage logic are incorporated into the peak-shifting model as training data to train the peak-shifting model, so as to generate a trained peak-shifting model; Obtain the water supply data and water discharge data of multiple secondary pumping stations to be tested during the working cycle to be tested of each secondary pumping station, and obtain the water supply data and water discharge data of multiple water supply pumping stations to be tested during the working cycle to be tested of the water supply pumping station, input the water supply data and water discharge data of multiple secondary pumping stations to be tested during the working cycle to be tested of each secondary pumping station, and the water supply data and water discharge data of multiple water supply pumping stations to be tested during the working cycle to be tested of the water supply pumping station into the trained peak shifting model, run the trained peak shifting model, and obtain the peak shifting regulation strategy output by the trained peak shifting model.
2. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 1, characterized in that: The said establishment of a pump station water supply management system, incorporating each secondary pump station into the pump station water supply management system, and incorporating the water supply pump station into the pump station water supply management system, includes: Set a time period for disconnection traversal inspection; Determine the end time point of the last network disconnection traversal check time period; Based on the current system time and the network disconnection traversal check time period, determine whether to execute the current network disconnection traversal check program; If the time difference between the current system time and the end time point of the previous network disconnection traversal check time period closest to the current system time is less than the duration of the network disconnection traversal check time period, the network disconnection traversal check program is not executed; If the time difference between the current system time and the end time point of the previous network disconnection traversal check time closest to the current system time is equal to or greater than the duration of the network disconnection traversal check time period, the subsequent step of selecting a secondary pump station is executed.
3. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 2, characterized in that: After selecting a secondary pump station and before receiving water supply data and water discharge data of a secondary pump station in a historical working cycle of the secondary pump station, the method further includes executing a network disconnection traversal check program; The execution of the disconnection traversal check procedure includes: receiving a feedback signal from the secondary pumping station; Based on the feedback signal of the secondary pump station, determining whether the feedback signal of the secondary pump station is an idle signal; the idle signal is a feedback value of a circuit breaking determination program; If the feedback signal of the secondary pump station is an idle signal, a disconnection tag is assigned to the secondary pump station, and the information that the circuit of the secondary pump station is disconnected is fed back to the pump station water supply management system; If the feedback signal of the secondary pumping station is not an idle signal, the subsequent step of receiving the water supply data and water output data within a historical working cycle of the secondary pumping station is executed; the duration of the offline traversal check time period is less than or equal to the minimum historical working cycle of the secondary pumping station.
4. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 3 is characterized in that: The execution priority of the network disconnection traversal check program of the secondary pumping station with the network disconnection label is listed as the first priority; the execution order of the network disconnection traversal check program of the secondary pumping station with the same priority is arranged in a random number function; when the network disconnection traversal check program is executed, the network disconnection traversal check program of each secondary pumping station is executed in turn according to the execution priority of the network disconnection traversal check program.
5. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 4, characterized in that: The method comprises: drawing a first water storage fluctuation function curve of the secondary pumping station based on the water supply data and water discharge data of each secondary pumping station in the historical working cycle of the secondary pumping station by using a peak water storage algorithm, and incorporating the first water storage fluctuation function curve of the secondary pumping station into the data management set of the secondary pumping station, including: The water supply data and water discharge data in each working cycle of the secondary pump station are integrated into multiple data points and marked on the water supply curve, water discharge curve and water storage curve respectively; The water storage capacity of all data points of the water storage curve is averaged, the water storage curve is divided using the water storage capacity average of the water storage curve, and the lowest point and the highest point of the water storage curve are determined; Based on the water storage capacity at the lowest point and the water storage capacity at the highest point of the water storage curve, a plurality of water storage guarantee threshold lines are drawn on the water storage curve; each water storage guarantee threshold line is parallel to the expression line of the water storage mean value of the water storage curve; Using multiple water storage guarantee threshold lines and the expression line of the water storage amount mean of the water storage curve, the water supply curve and the water discharge curve are respectively segmented to obtain multiple water supply guarantee time periods and multiple water discharge guarantee time periods; The first water storage fluctuation function is determined by using a plurality of water supply guarantee time periods, a plurality of water output guarantee time periods and a water storage curve.
6. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 5, characterized in that: The method comprises: drawing a first water storage fluctuation function curve of the secondary pumping station based on the water supply data and water discharge data of each secondary pumping station in the historical working cycle of the secondary pumping station by using a peak water storage algorithm, and incorporating the first water storage fluctuation function curve of the secondary pumping station into the data management set of the secondary pumping station, and further comprising: Select a water supply guarantee period; Determine the average water supply rate during the water supply guarantee period; Return to the step of selecting a water supply guarantee time period until all water supply guarantee time periods are selected and completed; Select a water supply guarantee time period; Determine the average water output rate within the water output guarantee time period; Return to selecting a water supply guarantee time period until all water supply guarantee time periods are selected and completed.
7. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 6, characterized in that: Based on the water storage capacity at the lowest point and the water storage capacity at the highest point of the water storage curve, a plurality of water storage guarantee threshold lines are drawn on the water storage curve, including: Call the water storage tank capacity of the secondary pumping station; Based on the water storage at the lowest point of the water storage curve, the water storage at the highest point of the water storage curve and the water storage tank capacity of the secondary pumping station, determine the ratio of the water storage at the lowest point of the water storage curve to the water storage tank capacity of the secondary pumping station and the ratio of the water storage at the highest point of the water storage curve to the water storage tank capacity of the secondary pumping station; The ratio of the water storage volume at the lowest point of the water storage curve to the water storage tank volume of the secondary pumping station is defined as a first ratio; The ratio of the water storage volume at the highest point of the water storage curve to the water storage tank volume of the secondary pumping station is defined as a second ratio; Divide the numerical interval between the first ratio and the second ratio into N sub-intervals; N is a positive integer; Draw a straight line parallel to the horizontal axis through the data point where the first ratio is located as the water storage guarantee threshold line corresponding to the first ratio; A straight line parallel to the horizontal axis is drawn through the data point where the second ratio is located as a water storage guarantee threshold line corresponding to the second ratio; A water storage guarantee threshold line is defined between every two adjacent sub-intervals to form a plurality of water storage guarantee threshold lines between the water storage guarantee threshold line corresponding to the first ratio and the water storage guarantee threshold line corresponding to the second ratio.
8. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 7, characterized in that: The data management set of each secondary pump station, the data management set of the water supply pump station, and the peak-shifting regulation and storage logic are incorporated into the peak-shifting model as training data to train the peak-shifting model to generate a trained peak-shifting model, including: The water supply data and water discharge data of the secondary pumping station in K consecutive complete years in the data management set of the water supply pumping station, as well as the water supply data and water discharge data of the water supply pumping station in the same K consecutive complete years, are called to form a sample library of the peak shifting model; K is a positive integer; Select a time period in the system timeline; Select a time period corresponding to the second water storage fluctuation function of a water supply pump station in the sample library; Select a time period corresponding to the first water storage fluctuation function of a secondary pumping station in the sample library; Based on the first water storage fluctuation function of the secondary pump station in the corresponding time period, determining whether the water storage capacity of the secondary pump station in the time period fluctuates; If the water storage capacity of the secondary pumping station does not fluctuate within the time period, then return to the time period corresponding to the first water storage fluctuation function of a secondary pumping station in the selected sample library until all secondary pumping stations are selected; If the water storage capacity of the secondary pumping station fluctuates within the time period, the average water supply rate and the average water discharge rate of the secondary pumping station within the time period are called, and the corresponding time period in the first water storage fluctuation function of a secondary pumping station in the selected sample library is returned until all the secondary pumping stations are selected; Based on the average water supply rate of all secondary pumping stations and the corresponding time period, determine the average total water supply and average total water output of all secondary pumping stations; The second water storage fluctuation function of the water supply pump station is called to determine the total water supply and total water output of the water supply pump station in the corresponding time period; The water loss of the outdoor integrated pump station in the corresponding time period is determined by using the total water output of the water supply pump station in the corresponding time period and the average total water supply of all secondary pump stations; The dynamic surplus of the outdoor integrated pumping station in the corresponding time period is determined by using the total water output of the water supply pumping station in the corresponding time period and the average total water output of all secondary pumping stations; Return to selecting a time period in the system timeline until K consecutive complete years in the system timeline are selected.
9. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 8, characterized in that: The peak shifting model also includes: Based on the water loss amount and water loss threshold of the outdoor integrated pump station in each corresponding time period, it is determined whether the water loss amount of the outdoor integrated pump station in each corresponding time period is greater than the water loss threshold; If the water loss of the outdoor integrated pump station in each corresponding time period is greater than the water loss threshold, the samples in this time period will be removed; If the water loss of the outdoor integrated pump station in each corresponding time period is less than or equal to the water loss threshold, then determine whether the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero; If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero, the total water supply of the water supply pump station in the corresponding time period is adjusted; If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is equal to zero, the water supply and water output of the outdoor integrated pump station in the corresponding time period are maintained; If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is less than zero, the total water supply of the water supply pump station in the corresponding time period is adjusted.
10. The method for peak-shifting storage regulation of outdoor integrated pumping stations according to claim 9, characterized in that: The adjusting the total amount of water supplied by the water supply pump station in the corresponding time period includes: Call the water storage guarantee threshold line in the corresponding time period; Select a secondary pumping station; If the dynamic surplus of the outdoor integrated pump station in the corresponding time period is greater than zero, it is determined whether the water storage capacity of the secondary pump station in the corresponding time period exceeds the water storage guarantee threshold line; If the water storage capacity of the time period corresponding to the secondary pump station is greater than the water storage capacity corresponding to the water storage guarantee threshold line, the secondary pump station is included in the list of water supply to be reduced, and the process of selecting a secondary pump station is returned until all secondary pump stations are selected; If the water storage capacity of the time period corresponding to the secondary pumping station is less than or equal to the water storage capacity corresponding to the water storage guarantee threshold line, return to the step of selecting a secondary pumping station until all secondary pumping stations are selected; If the water storage capacity of the time period corresponding to the secondary pumping station is lower than the water storage guarantee threshold line, the secondary pumping station is included in the list of water supply to be increased, and the process of selecting a secondary pumping station is returned to the step of selecting a secondary pumping station until all the secondary pumping stations are selected; Count the number of secondary pumping stations in the list of water supply to be reduced and the list of water supply to be increased, and reduce the water supply of the water supply pumping stations according to the water supply reduction formula.