Auxiliary waterproof structure for coal mine burnt rock distribution area

By setting up an upper grouting layer and a lower grouting layer in the coal mine fire rock distribution area, combining anchor cables and support mechanisms, a fire rock anti-seepage layer is formed, which solves the water leakage problem in the fire rock area and improves the mining tunnel surface Waterproof performance and safety.

CN118911729APending Publication Date: 2024-11-08YULIN YANGPAN MINING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411185577.4
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

During the mining process, coal mine fire-changing rock distribution areas are prone to leakage due to cracks. Existing waterproofing measures are difficult to effectively prevent seepage of the inner layer of fire-changing rock, which increases the difficulty of mining and safety hazards.

Method used

An auxiliary waterproof structure for coal mine fire rock distribution area is designed, including setting up an upper grouting layer and a lower grouting layer on the mining tunnel surface, connecting it with the support mechanism through an anchor cable mechanism, and installing water conduits and anchor rods using grouting holes. , forming a burnt rock anti-seepage layer, the water conduit pipe is combined with the filter mesh and annular pipe to achieve the drainage and waterproofing effect of the water source, and improve the waterproof performance through the pressure sensor and sealing layer.

Benefits of technology

It effectively reduces the water content in the burned rock area, improves the waterproof function, ensures the stability and safety of the mining tunnel surface, and realizes the safety and anti-seepage functions of coal mining.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911729A_ABST
    Figure CN118911729A_ABST
Patent Text Reader

Abstract

The invention provides a coal mine burnt rock distribution area auxiliary waterproof structure which comprises a mining roadway face and an anchor cable mechanism located in a burnt rock coal mine area, the burnt rock coal mine area is composed of a to-be-mined coal seam area, a lower-layer burnt rock area and an upper-layer burnt rock area, an upper grouting layer and a lower grouting layer are formed in the upper-layer burnt rock area through grouting, and the upper grouting layer and the lower grouting layer are arranged in the lower-layer burnt rock area. A burnt rock impermeable layer is formed between the upper grouting layer and the lower grouting layer, the anchor cable mechanism is connected with a supporting mechanism in the mining roadway face, and the supporting mechanism is connected with the top face of the mining roadway face in an attached mode. The upper grouting layer is arranged in the upper-layer burnt rock area, the waterproof effect can be achieved, grouting is conducted on the mining roadway face to form the lower grouting layer, waterproof treatment of the aquifer of the burnt rock area can be achieved, the supporting stability of the mining roadway face is achieved through the anchor cable mechanism, and while auxiliary waterproof of the coal mine burnt rock distribution area is achieved, the supporting stability of the aquifer of the burnt rock area is improved. Roadway supporting and anti-seepage functions are ensured, and the subsequent mining safety can be ensured.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an auxiliary waterproof structure in a coal mine burnt rock distribution area and belongs to the technical field of burnt rock coal mining. Background Art

[0002] Coal mine burnt rock is a special rock produced during the spontaneous combustion of coal seams. Its formation is closely related to the high-temperature baking effect of coal seams during spontaneous combustion. Coal mine burnt rock, also known as fire-burned rock, is a rock formed by the metamorphosis of the overlying rock layers during the spontaneous combustion of coal seams due to high-temperature baking or melting. When the coal seams spontaneously combust, the high-temperature heat generated is transferred upward to bake the overlying rock layers. As the degree of baking deepens, the mineral composition, structure and appearance characteristics of the rock layers will change significantly, thus forming burnt rock. The color of burnt rock is generally yellow, orange, red and purple-black, and the color varies with the severity of baking. Its common structural features include pore-like structure, brecciated structure, etc. Slag-like structure can be seen in those with a high degree of baking, with relatively developed holes and generally round or oval pores. In addition, burned rocks also have slightly shiny ablation flow surfaces and show faint wrinkles in some areas. Burned rocks can be divided into different types according to the degree of burning and the location of the burned rock strata. For example, burned rocks close to burning coal seams may suffer the most severe baking, forming molten, slag-like or honeycomb-like rocks; while rock strata far away from burning coal seams may only be slightly baked, and the original rock structure is basically intact. The formation of burned rocks in coal mines is one of the direct consequences of coal seam spontaneous combustion. It not only changes the physical and chemical properties of rocks, but may also have a certain impact on groundwater systems, soil quality and the ecological environment. Therefore, in the process of coal mining and utilization, the monitoring and prevention of coal seam spontaneous combustion should be strengthened to reduce the generation of burned rocks and their impact on the environment.

[0003] Coal mine burnt rock is a product of the spontaneous combustion of coal seams. Its formation is closely related to the high-temperature baking effect of coal seams during spontaneous combustion. The main characteristics of coal mine burnt rock after formation are high hardness but easy to break. After breaking, the gaps between them are large. The more water accumulates in the cracks of the burnt rock, the larger the aquifer. When coal mines are mined, water leakage is prone to occur on the top of the mining face, especially when the cracks in the burnt rock are connected to the aquifer, which may lead to serious safety hazards on the mining face. The existing waterproof layer is often set on the mining face, but it is difficult to play an effective waterproof role of the inner waterproof layer of the burnt rock, which increases the difficulty of mining in the coal mine burnt rock area. Summary of the invention

[0004] The present invention provides an auxiliary waterproof structure for a coal mine burnt rock distribution area in order to solve the technical problem that cracks easily lead to water leakage on the mining surface when coal mining is carried out in a burnt rock distribution area.

[0005] The present invention solves the above technical problems through the following technical solutions:

[0006] The present invention provides an auxiliary waterproof structure for a coal mine burnt rock distribution area, the auxiliary waterproof structure for a coal mine burnt rock distribution area comprising:

[0007] A mining tunnel face located in a burned rock coal mining area, wherein the burned rock coal mining area is composed of a coal seam area to be mined, a lower burned rock area and an upper burned rock area, wherein the upper burned rock area includes a surface burned rock area, an upper grouting layer, a burned rock anti-seepage layer and a lower grouting layer, wherein an upper grouting layer and a lower grouting layer are formed in the upper burned rock area by grouting, and a burned rock anti-seepage layer is formed between the upper grouting layer and the lower grouting layer;

[0008] An anchor cable mechanism extends from the mining tunnel surface to the lower burned rock area and the upper burned rock area. The anchor cable mechanism is connected to the support mechanism inside the mining tunnel surface, and the support mechanism is fitted and connected to the top surface of the mining tunnel surface. The anchor cable mechanism is used to connect the burned rock coal mining area and the support mechanism, the mining tunnel surface is supported by the support mechanism, and the grouting holes are used to install water pipes and anchor rods, so as to achieve water conduction of the burned rock anti-seepage layer and stable installation of the support mechanism.

[0009] In the present technical solution, a bottom area is provided at the bottom of the mining tunnel face, and the mining tunnel face is arranged correspondingly on one side of the coal seam area to be mined. A dense burnt rock bottom stratum is formed above the coal seam area to be mined, and a lower burned rock area is provided above the burnt rock bottom stratum, and a burnt rock base layer is formed inside the lower burned rock area.

[0010] In the present technical solution, a plurality of evenly distributed grouting holes are opened inside the lower burned rock area and the upper burned rock area, and the plurality of grouting holes located in the lower burned rock area and the upper burned rock area are staggeredly distributed, a surface burned rock area is provided above the upper burned rock area, and the plurality of grouting holes are respectively connected to the bottom rock layer of the burned rock and the interior of the burned rock area.

[0011] In the present technical solution, the upper grouting layer and the lower grouting layer are distributed in parallel, the aquifer in the burned rock distribution area is located inside the burned rock anti-seepage layer between the upper grouting layer and the lower grouting layer, the grouting holes located inside the lower grouting layer extend to the bottom of the burned rock anti-seepage layer, and water pipes and anchor mechanisms are staggered in several grouting holes located inside the lower grouting layer, and each grouting hole located inside the upper grouting layer is injected with a plugging agent after grouting.

[0012] In the present technical scheme, the water pipe is evenly distributed inside the grouting holes in the lower burned rock area, the top of the water pipe is fixedly connected to a filter screen, the diameter of the water pipe above the filter screen is larger than the diameter below it, the water pipe extends to below the burned rock anti-seepage layer, the bottom of the water pipe is fixedly connected to an annular pipe, the annular pipe is located inside a groove opened on the inner wall of the mining tunnel surface, a bottom layer area is formed inside the burned rock coal mine area below the mining tunnel surface, a drainage ditch is excavated inside the bottom layer area, the drainage ditch is set on both sides of the mining tunnel surface, the water source drained by the water pipe is discharged into the drainage ditch through the annular pipe, which is used to reduce the water content of the burned rock anti-seepage layer, which can reduce the waterproof pressure of the lower grouting layer and further improve the waterproof function, and the annular pipe is connected to the drainage ditch, and a blocking layer is provided on the top of the lower burned rock area at the connection between the grouting hole and the lower grouting layer, the blocking layer is correspondingly arranged above the grouting hole, and the water pipe and the blocking layer are penetrated and plugged.

[0013] In the present technical solution, the anchor cable mechanism includes an anchor rod, and the anchor rod and the water pipe are staggered and distributed inside the grouting hole. The top of the anchor rod is fixedly connected with an end head, and the diameter of the end head is larger than the diameter of the anchor rod. The anchor rod located below the end head is rotatably connected to the support rod, and the end of the support rod is provided with a warped edge of a bending structure, the middle part of the support rod is rotatably connected to one end of the connecting rod, and the surface of the anchor rod is provided with a sliding groove for moving the slider, and the slider is rotatably connected to the other end of the connecting rod.

[0014] In the present technical solution, the bottom of the anchor rod is respectively fixedly connected with a first fixed shaft and a guide rod, the surface of the guide rod is movably sleeved with a sleeve, the end of the sleeve is fixedly connected with a second fixed shaft, and a pressure sensor is fixedly installed on the top of the second fixed shaft. The pressure sensor is connected to the first fixed shaft through a spring, and the spring is respectively sleeved with the anchor rod and the surface of the sleeve.

[0015] In the present technical solution, the support mechanism includes a waterproof wall, which is fitted and connected to the inner wall of the mining tunnel surface. The top of the waterproof wall is an annular structure. The outer wall of the waterproof wall is connected to the annular pipe. A cavity is opened inside the bottom rock layer of the burned rock located on the outer wall of the waterproof wall. The cavity is connected to the grouting hole, and a casing and a casing are provided inside the cavity. The casing is inserted through the inside of the waterproof wall.

[0016] In the present technical solution, the support mechanism also includes a support plate, which is fitted and connected to the inner wall of the waterproof wall, the top of the support plate is penetrated and plugged with a sleeve, the bottom of the sleeve is threaded with a nut, and the nut is fit and connected to the inner wall of the support plate, the outer wall of the support plate is fixedly connected to a block, the inside of the block is movably sleeved with a sleeve, and the block is embedded and connected to the inside of the waterproof wall, the support plate and the waterproof wall are penetrated and plugged with a number of evenly distributed long screws, and each of the long screws extends into the interior of the wall.

[0017] In the present technical solution, there are several waterproof walls which are spliced ​​with each other, and a notch is provided at the joint of the waterproof walls. The waterproof wall is composed of two vertical parts and an annular part, and a splicing seam is formed on the outside of the connection between the vertical part and the annular part. A sealing layer is embedded in the joint of the waterproof wall, and the sealing layer is fixedly connected to both ends of the sealing strip respectively, and the sealing strip is embedded in the inside of the splicing seam.

[0018] On the basis of being in accordance with the common sense in the art, the above-mentioned preferred conditions can be arbitrarily combined to obtain the preferred embodiments of the present invention.

[0019] The positive and progressive effects of the present invention are:

[0020] The above-mentioned auxiliary waterproof structure for the burned rock distribution area of ​​a coal mine, when coal mining is carried out in the burned rock distribution area, drills holes and injects grouting in the burned rock area, uses high-pressure slurry to extrude the burned rock layer, so that the burned rock fills the gaps and plays a waterproof role, and sets an upper grouting layer in the upper burned rock area, which can play a waterproof role and solve the problem of excessive water seepage caused by excessive gaps in the burned rock. Grouting is carried out on the mining tunnel surface to waterproof the aquifer in the burned rock area, and the grouting holes are used to achieve drainage in the aquifer, solving the problem of water leakage caused by excessive water content in the burned rock distribution area. The anchor mechanism is used to achieve the stability of the support at the mining tunnel surface, and the waterproof performance at the mining surface is ensured by tightening the support plate, and the tunnel support performance is ensured, which can ensure the safety of coal mining, and while realizing the auxiliary waterproofing of the burned rock distribution area of ​​the coal mine, the tunnel support and anti-seepage functions are ensured, and the water diversion treatment of the aquifer is realized to ensure the safety of subsequent mining. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the present invention.

[0022] Figure 2 It is a schematic diagram of the plane distribution structure of the coal mining area of ​​the present invention.

[0023] Figure 3 It is a schematic diagram of the internal plane distribution structure of the coal mine area of ​​the present invention.

[0024] Figure 4 It is a schematic diagram of the side structure of the water conduit of the present invention.

[0025] Figure 5 It is a schematic diagram of the side structure of the anchor cable mechanism of the present invention.

[0026] Figure 6 For the present invention Figure 3 Schematic diagram of the local enlarged structure at point A in the middle.

[0027] Figure 7 It is a schematic diagram of the three-dimensional structure of the water guide pipe of the present invention.

[0028] Figure 8 It is a schematic diagram of the three-dimensional structure of the anchor rod of the present invention.

[0029] Fig. 9 It is a schematic diagram of the three-dimensional structure of the support plate of the present invention.

[0030] Fig.10 It is a schematic diagram of the three-dimensional structure of the waterproof wall of the present invention.

[0031] Description of Reference Numerals

[0032] 100, burnt rock coal mining area; 101, mining tunnel face; 102, coal seam area to be mined; 103, bottom layer area; 104, burnt rock bottom layer; 105, lower burnt rock area; 106, burnt rock base layer; 107, upper burnt rock area; 108, upper grouting layer; 109, lower grouting layer; 110, surface burnt rock area; 111, burnt rock anti-seepage layer;

[0033] 200, grouting hole; 201, water pipe; 202, filter screen; 203, annular pipe; 204, drainage ditch; 205, plugging layer;

[0034] 300, anchor cable mechanism; 301, anchor rod; 302, end; 303, support rod; 304, warping edge; 305, connecting rod; 306, slide groove; 307, first fixed axis; 308, guide rod; 309, sleeve; 310, second fixed axis; 311, pressure sensor; 312, spring; 313, nut;

[0035] 400, supporting mechanism; 401, waterproof wall; 402, cavity; 403, blocking block; 404, supporting plate; 405, long screw; 406, notch; 407, joint; 408, sealing layer; 409, sealing strip. DETAILED DESCRIPTION

[0036] The present invention is further described below by way of examples, but the present invention is not limited to the scope of the examples.

[0037] like Figure 1-10 As shown, the auxiliary waterproof structure of the coal mine burnt rock distribution area includes:

[0038] A mining tunnel face 101 is located in a burned rock coal mining area 100, wherein the burned rock coal mining area 100 is composed of a coal seam area 102 to be mined, a lower burned rock area 105 and an upper burned rock area 107, wherein the upper burned rock area includes a surface burned rock area 110, an upper grouting layer 108, a burned rock anti-seepage layer 111 and a lower grouting layer 109, wherein an upper grouting layer 108 and a lower grouting layer 109 are formed in the upper burned rock area 107 by grouting, and a burned rock anti-seepage layer 111 is formed between the upper grouting layer 108 and the lower grouting layer 109, and the upper grouting layer 108 and the lower grouting layer 109 are formed by grouting in the burned rock coal mining area 100 to provide waterproof and The upper grouting layer 108 can play the role of waterproofing the upper layer, avoiding the problem of excessive water content caused by rainwater penetration, and the lower grouting layer 109 can further play the role of anti-seepage, and at the same time can realize the water source diversion at the burnt rock anti-seepage layer 111 with a water-containing layer, which is used to reduce the waterproof pressure of the lower grouting layer 109, and the water guide pipe 201 is set in the weak area of ​​the upper grouting layer 108. When the upper grouting layer 108 is grouted through the grouting holes 200 above, the slurry is dispersed and diffused, so that the density of the upper grouting layer 108 in the middle position between the grouting holes 200 is reduced. When water leakage occurs, the water source penetrates into the burnt rock anti-seepage layer 111, and the water flow is discharged through the water guide pipe 201 at this time;

[0039] The anchor cable mechanism 300 extends from the mining tunnel face 101 to the lower burned rock area 105 and the upper burned rock area 107. The anchor cable mechanism 300 is connected to the support mechanism 400 inside the mining tunnel face 101, and the support mechanism 400 is closely connected to the top surface of the mining tunnel face 101. The anchor cable mechanism 300 is used to stabilize the support mechanism 400 in the mining tunnel face 101, and the grouting hole 200 is used to install the anchor cable to ensure the safety of the mining tunnel face 101.

[0040] In the present technical scheme, a bottom area 103 is provided at the bottom of the mining tunnel face 101, and the mining tunnel face 101 is correspondingly arranged on one side of the coal seam area 102 to be mined, and a dense burned rock bottom stratum 104 is formed above the coal seam area 102 to be mined, and a lower burned rock area 105 is provided above the burned rock bottom stratum 104, and a burned rock base layer 106 is formed inside the lower burned rock area 105. The bottom area 103 serves as the base layer of the mining tunnel face 101, and a drainage ditch 204 is excavated in the bottom area 103 for water seepage diversion in the burned rock coal mining area 100. When coal mining is carried out in the coal seam area 102 to be mined, the gaps formed in the burned rock bottom stratum 104, the lower burned rock area 105 and the upper burned rock area 107 above it are connected to the aquifer, which will cause water seepage problems. Grouting and sealing the aquifer can achieve anti-seepage treatment.

[0041] In the technical solution, a plurality of evenly distributed grouting holes 200 are opened inside the lower burned rock area 105 and the upper burned rock area 107, and the plurality of grouting holes 200 located in the lower burned rock area 105 and the upper burned rock area 107 are staggeredly distributed, and a surface burned rock area 110 is arranged above the upper burned rock area 107, and the plurality of grouting holes 200 are respectively connected with the bottom rock layer 104 of the burned rock and the inside of the burned rock area, and the upper burned rock area 107 in the burned rock coal mine area 100 is grouted by setting a plurality of grouting holes 200. Grouting treatment is performed, and staggered drilling and grouting are performed in sequence from above the burned rock coal mining area 100 and the top of the mining tunnel face 101, so that the upper burned rock area 107 forms an upper grouting layer 108 and a lower grouting layer 109 to play a dual waterproofing function. The hardness of the surface burned rock area 110, the upper burned rock area 107, the lower burned rock area 105 and the burned rock bottom rock layer 104 increases from top to bottom. The hardness increases due to the spontaneous combustion and baking of the coal seam, but it is easy to break, so that the internal stress formed is very likely to cause cracks. At this time, grouting is used to perform waterproofing treatment on the burned rock coal mining area 100.

[0042] In the present technical solution, the upper grouting layer 108 and the lower grouting layer 109 are arranged in parallel, the aquifer in the burnt rock distribution area is located inside the burnt rock impermeable layer 111 between the upper grouting layer 108 and the lower grouting layer 109, the grouting holes 200 located inside the lower grouting layer 109 extend to the bottom of the burnt rock impermeable layer 111, and the water pipes 201 and the anchor cable mechanisms 300 are staggered in the plurality of grouting holes 200 located inside the lower grouting layer 109, and each grouting hole 200 located inside the upper grouting layer 108 is filled with water after grouting. A plugging agent is injected, and an upper grouting layer 108 and a lower grouting layer 109 are formed after grouting through the grouting holes 200. At this time, a burnt rock anti-seepage layer 111 is formed between the upper grouting layer 108 and the lower grouting layer 109, and the aquifer of the burnt rock coal mining area 100 is located between the burnt rock anti-seepage layers 111. The upper grouting layer 108 can prevent rainwater from penetrating into the surface burnt rock area 110, and the lower grouting layer 109 is used to prevent water from penetrating into the aquifer, and the anchor mechanism 300 and the water pipe 201 are installed in the grouting holes 200 of the lower grouting layer 109.

[0043] In the present technical solution, the water pipe 201 is evenly distributed inside the grouting hole 200 of the lower burnt rock area 105, the top of the water pipe 201 is fixedly connected to a filter screen 202, the diameter of the water pipe 201 above the filter screen 202 is larger than the diameter below it, the water pipe 201 extends to below the burnt rock impermeable layer 111, the bottom of the water pipe 201 is fixedly connected to an annular pipe 203, and the annular pipe 203 is located in a groove opened on the inner wall of the mining roadway face 101. A bottom area 103 is formed inside the burned rock coal mining area 100 located below the mining roadway face 101, a drainage ditch 204 is excavated inside the bottom area 103, and the annular pipe 203 is connected to the drainage ditch 204, and a plugging layer 205 is provided on the top of the lower burned rock area 105 where the grouting hole 200 is connected to the lower grouting layer 109, and the plugging layer 205 is correspondingly arranged above the grouting hole 200, and the water pipe 201 is inserted through the plugging layer 205, and the water pipe 201 It is used to connect the aquifer inside the burnt rock impermeable layer 111, realize the discharge of the aquifer to play an anti-seepage role. After the grouting hole 200 is opened from the mining roadway surface 101, grouting is injected from the grouting hole 200 to form a lower grouting layer 109. After the formation is completed, continue to drill upward along the grouting hole 200 to make it pass through the lower grouting layer 109 and extend the grouting hole 200 to the bottom of the burnt rock impermeable layer 111. After the water guide pipe 201 is installed from the grouting hole 200, the position of the grouting hole 200 is waterproofed. The water-conducting layer 201 is treated to form a blocking layer 205. At this time, the filter screen 202 above the water pipe 201 is located inside the burnt rock anti-seepage layer 111. When the aquifer of the burnt rock anti-seepage layer 111 leaks, the leaked water enters the water pipe 201 from the filter screen 202, thereby realizing the water conduction treatment of the burnt rock anti-seepage layer 111, alleviating the waterproof pressure of the lower grouting layer 109, and realizing the fixed-point discharge of the aquifer in the burnt rock coal mining area 100, thereby avoiding water leakage in the mining tunnel face 101 due to leakage.

[0044] In the present technical solution, the anchor cable mechanism 300 includes an anchor rod 301, and the anchor rod 301 and the water pipe 201 are staggered and distributed inside the grouting hole 200. The top of the anchor rod 301 is fixedly connected with an end head 302, and the diameter of the end head 302 is larger than the diameter of the anchor rod 301. The anchor rod 301 located below the end head 302 is rotatably connected to the support rod 303, and the end of the support rod 303 is provided with a warped edge 304 of a bending structure, and the middle part of the support rod 303 is rotatably connected to one end of the connecting rod 305. The surface of the anchor rod 301 is provided with a sliding groove 306 for moving the slider, and the slider is rotatably connected to the other end of the connecting rod 305. After the anchor rod 301 is installed, the installation of the support mechanism 400 is realized, and the lower grouting layer 109 is grouted. After forming, continue drilling along the grouting hole 200 to extend the grouting hole 200 to the inside of the lower grouting layer 109, insert the anchor rod 301 into the grouting hole 200, and move the end 302 into the lower grouting layer 109. During the insertion of the anchor rod 301, the warped edge 304 at the end of the support rod 303 contacts the inner wall of the grouting hole 200. When reaching the specified position, when the anchor rod 301 is pulled outward, the warped edge 304 is inserted into the lower grouting layer 109, and the support rod 303 is stretched outward, so that when the slider moves inside the slide groove 306, it drives the connecting rod 305 to rotate, so that the support rod 303 is inserted into the lower grouting layer 109 to fix the anchor rod 301, and then the anchor rod 301 and the grouting hole 200 are sealed to form a sealing layer 205, so as to achieve stable installation of the anchor rod 301.

[0045] In the present technical solution, the bottom of the anchor rod 301 is respectively fixedly connected with a first fixed shaft 307 and a guide rod 308, the surface of the guide rod 308 is movably sleeved with a sleeve 309, the end of the sleeve 309 is fixedly connected with a second fixed shaft 310, and a pressure sensor 311 is fixedly installed on the top of the second fixed shaft 310, the pressure sensor 311 is connected to the first fixed shaft 307 through a spring 312, and the spring 312 is respectively sleeved with the surface of the anchor rod 301 and the sleeve 309, so that the support machine After the support mechanism 400 is installed, the nut 313 is tightened to install the sleeve 309. At this time, the spring 312 plays a tightening function for the support mechanism 400, and the force generated by the spring 312 is detected by the pressure sensor 311, which is convenient for determining the force applied by the anchor rod 301 to the support mechanism 400 during construction, and is used to solve the problem of the tension of the anchor rod 301 affected by the stress change at the installation position. The spring 312 is used to alleviate the force on the support mechanism 400 to ensure that the support mechanism 400 can be stably installed.

[0046] In the present technical solution, the support mechanism 400 includes a waterproof wall 401, the waterproof wall 401 is closely connected to the inner wall of the mining tunnel face 101, the top of the waterproof wall 401 is an annular structure, the outer wall of the waterproof wall 401 is connected to the annular pipe 203, and a cavity 402 is opened inside the rock layer 104 at the bottom of the burnt rock located on the outer wall of the waterproof wall 401. The cavity 402 is connected to the grouting hole 200, and the cavity 402 is provided with a casing 309 and a casing 309. The casing 309 is inserted through the waterproof wall 401, and excavation is performed in the coal seam area 102 to be mined to form a mining tunnel face 1 01, the waterproof wall 401 is installed on the inner wall of the mining tunnel face 101, and the support plate 404 is installed on the inner wall of the waterproof wall 401. At this time, the casing 309 passes through the waterproof wall 401 and the support plate 404 in turn, and the block 403 is installed at the cavity 402. The block 403 is squeezed and pressed inside the cavity 402. At this time, the casing 309 is wrapped and fixed, and the installation is achieved by tightening the nut 313. The block 403 is used to prevent the casing 309 from rotating. When the tension of the anchor rod 301 changes, the force is adjusted by rotating the nut 313 to ensure the stability of the support plate 404 and the waterproof wall 401.

[0047] In the present technical solution, the support mechanism 400 further comprises a support plate 404, the support plate 404 is fitted and connected to the inner wall of the waterproof wall 401, the top of the support plate 404 is penetrated and plugged with the sleeve 309, the bottom of the sleeve 309 is threadedly connected with a nut 313, and the nut 313 is fitted and connected to the inner wall of the support plate 404, the outer wall of the support plate 404 is fixedly connected with a block 403, the inner part of the block 403 is movably sleeved with the sleeve 309, and the block 403 is connected to the waterproof wall 401. 1 is internally engaged and connected, the support plate 404 and the waterproof wall 401 are penetrated and plugged with a number of evenly distributed long screws 405, each of which extends to the inside of the wall, and the cavity 402 can be blocked by the block 403 to play a waterproof role, and the top of the waterproof wall 401 is supported by the support plate 404, which can improve the stability of the waterproof wall 401 after installation, and the support plate 404 is installed by the long screw 405 to improve the support strength of the mining tunnel face 101.

[0048] In the present technical solution, the number of the waterproof walls 401 is several and they are spliced ​​together, and a notch 406 is provided at the splicing of the waterproof walls 401. The waterproof wall 401 is composed of two vertical parts and an annular part. A splicing seam 407 is formed on the outside of the connection between the vertical part and the annular part. The splicing of the waterproof wall 401 is embedded with a sealing layer 408, and the sealing layer 408 is fixedly connected to the two ends of the sealing strip 409 respectively, and the sealing strip 409 is embedded with the inside of the splicing seam 407. When installing the next waterproof wall 401, the annular portion of the waterproof wall 401 is installed on the top of the mining tunnel surface 101, and the annular portion is supported by the vertical portion of the waterproof wall 401. The joint seam 407 formed at the joint is interlocked with the sealing strip 409 to improve the sealing performance of the joint. When installing the next waterproof wall 401, the sealing layer 408 is installed between adjacent waterproof walls 401. After the support plate 404 is installed in the same way, it is fixed by the long screw 405 to improve the stability after installation.

[0049] The present invention is not limited to the above-mentioned embodiments. Any changes in shape or structure are within the protection scope of the present invention. The protection scope of the present invention is defined by the attached claims. Those skilled in the art can make various changes or modifications to these embodiments without departing from the principle and essence of the present invention, but these changes and modifications are within the protection scope of the present invention.

Claims

1. Auxiliary waterproof structure in coal mine burnt rock distribution area, characterized in that: The auxiliary waterproof structure of the coal mine burnt rock distribution area includes: A mining tunnel face (101) located in a burnt rock coal mining area (100), wherein the burnt rock coal mining area (100) is composed of a coal seam area (102) to be mined, a lower burnt rock area (105) and an upper burnt rock area (107), wherein the upper burnt rock area (107) includes a surface burnt rock area (110), an upper grouting layer (108), a burnt rock anti-seepage layer (111) and a lower grouting layer (109), wherein an upper grouting layer (108) and a lower grouting layer (109) are formed in the upper burnt rock area (107) by grouting, and a burnt rock anti-seepage layer (111) is formed between the upper grouting layer (108) and the lower grouting layer (109); An anchor cable mechanism (300), the anchor cable mechanism (300) extending from the mining tunnel face (101) to the interior of the lower burned rock area (105) and the upper burned rock area (107), the anchor cable mechanism (300) being connected to a support mechanism (400) inside the mining tunnel face (101), and the support mechanism (400) being closely connected to the top surface of the mining tunnel face (101).

2. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: A bottom layer area (103) is provided at the bottom of the mining tunnel face (101), and the mining tunnel face (101) is arranged correspondingly on one side of the coal seam area (102) to be mined, and a dense burnt rock bottom stratum (104) is formed above the coal seam area (102) to be mined, and a lower burnt rock area (105) is provided above the burnt rock bottom stratum (104), and a burnt rock base layer (106) is formed inside the lower burnt rock area (105).

3. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: A plurality of evenly distributed grouting holes (200) are provided inside the lower burned rock area (105) and the upper burned rock area (107), and the plurality of grouting holes (200) located in the lower burned rock area (105) and the upper burned rock area (107) are staggeredly distributed, a surface burned rock area (110) is provided above the upper burned rock area (107), and the plurality of grouting holes (200) are respectively connected to the bottom rock layer (104) of the burned rock and the inside of the burned rock area.

4. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: The upper grouting layer (108) and the lower grouting layer (109) are distributed in parallel, the water-bearing layer in the burned rock distribution area is located inside the burned rock anti-seepage layer (111) between the upper grouting layer (108) and the lower grouting layer (109), the grouting holes (200) located inside the lower grouting layer (109) extend to the bottom of the burned rock anti-seepage layer (111), and water pipes (201) and anchor mechanisms (300) are staggeredly arranged in a plurality of grouting holes (200) located inside the lower grouting layer (109), and each grouting hole (200) located inside the upper grouting layer (108) is injected with a plugging agent after grouting.

5. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: The water pipe (201) is evenly distributed inside the grouting hole (200) of the lower burnt rock area (105); the top of the water pipe (201) is fixedly connected to a filter screen (202); the diameter of the water pipe (201) above the filter screen (202) is larger than the diameter below the filter screen; the water pipe (201) extends below the burnt rock impermeable layer (111); the bottom of the water pipe (201) is fixedly connected to an annular pipe (203); the annular pipe (203) is located inside a groove opened on the inner wall of the mining tunnel surface (101), and is positioned A bottom layer area (103) is formed inside a burnt rock coal mining area (100) below a mining tunnel surface (101), a drainage ditch (204) is excavated inside the bottom layer area (103), and the annular pipe (203) is connected to the drainage ditch (204), and a blocking layer (205) is provided on the top of the lower burnt rock area (105) at the connection between the grouting hole (200) and the lower grouting layer (109), and the blocking layer (205) is correspondingly arranged above the grouting hole (200), and the water guide pipe (201) and the blocking layer (205) are inserted through.

6. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: The anchor cable mechanism (300) comprises an anchor rod (301), wherein the anchor rod (301) and the water conduit (201) are staggeredly distributed inside the grouting hole (200), an end head (302) is fixedly connected to the top of the anchor rod (301), the diameter of the end head (302) is larger than the diameter of the anchor rod (301), the anchor rod (301) located below the end head (302) is rotatably connected to a support rod (303), a warped edge (304) of a bending structure is provided at the end of the support rod (303), the middle part of the support rod (303) is rotatably connected to one end of a connecting rod (305), a sliding groove (306) for moving a slider is provided on the surface of the anchor rod (301), and the slider is rotatably connected to the other end of the connecting rod (305).

7. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 6, characterized in that: The bottom of the anchor rod (301) is fixedly connected to a first fixed shaft (307) and a guide rod (308), respectively; the surface of the guide rod (308) is movably sleeved with a sleeve (309); the end of the sleeve (309) is fixedly connected to a second fixed shaft (310); a pressure sensor (311) is fixedly installed on the top of the second fixed shaft (310); the pressure sensor (311) is connected to the first fixed shaft (307) via a spring (312), and the spring (312) is sleeved with the surfaces of the anchor rod (301) and the sleeve (309), respectively.

8. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 1, characterized in that: The support mechanism (400) includes a waterproof wall (401), which is closely connected to the inner wall of the mining tunnel surface (101), the top of the waterproof wall (401) is an annular structure, the outer wall of the waterproof wall (401) is connected to the annular pipe (203), and a cavity (402) is opened inside the rock layer (104) at the bottom of the burned rock located on the outer wall of the waterproof wall (401), the cavity (402) is connected to the grouting hole (200), and a casing (309) and a casing (309) are provided inside the cavity (402), and the casing (309) is inserted through the inside of the waterproof wall (401).

9. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 8, characterized in that: The support mechanism (400) further comprises a support plate (404), wherein the support plate (404) is fitted and connected to the inner wall of the waterproof wall (401), the top of the support plate (404) is inserted through a sleeve (309), the bottom of the sleeve (309) is threadedly connected with a nut (313), and the nut (313) is fitted and connected to the inner wall of the support plate (404), the outer wall of the support plate (404) is fixedly connected with a block (403), the inside of the block (403) is movably sleeved with a sleeve (309), and the block (403) is embedded and connected to the inside of the waterproof wall (401), the support plate (404) and the waterproof wall (401) are both inserted through a plurality of evenly distributed long screws (405), and each of the long screws (405) extends into the interior of the wall.

10. The auxiliary waterproof structure for coal mine burnt rock distribution area according to claim 8, characterized in that: The waterproof walls (401) are in multiple numbers and are spliced ​​with each other. A notch (406) is provided at the splicing point of the waterproof walls (401). The waterproof wall (401) is composed of two vertical parts and an annular part. A splicing seam (407) is formed on the outside of the connection between the vertical part and the annular part. A sealing layer (408) is embedded and connected at the splicing point of the waterproof wall (401). The sealing layer (408) is fixedly connected to both ends of a sealing strip (409) respectively, and the sealing strip (409) is embedded and connected inside the splicing seam (407).