Optimized energy-saving method for heat supply unit
By scientifically allocating the power generation load and heating steam volume of the heating unit, the problem of not considering the actual operation of multiple different units in the existing technology is solved, the economic operation and energy-saving effects of the heating unit are achieved, and the standard coal consumption is reduced .
Patent Information
- Application Number
- CN202411039576.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-31
- Publication Date
- 2024-11-08
AI Technical Summary
The existing heating units do not consider the actual operation of multiple different units when optimizing allocation, resulting in the allocation results not being related to the actual situation and there are operating deviations.
By obtaining the total power generation plan command curve and the hot steam flow characteristic curve for heat users, combining the output information of the operating unit, the plant-level AGC control system and heating control system are used to allocate the power generation load and heating steam volume. The first and second strategies are optimized to allocate according to the unit's power generation load and rated load relationship and the heat supply and boundary relationship respectively to ensure that the power generation load and heating steam during operation of each unit are reasonably allocated.
The energy-saving and optimized operation of the heating unit is achieved, and the economicality of the unit's power generation and heating flow is maximized, which reduces standard coal consumption and improves operating efficiency.
Smart Images

Figure CN118912565A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of resource allocation optimization methods for units, and in particular to an optimization energy-saving method for heating units. Background Art
[0002] Thermal power plants are constantly deepening their energy-saving and peak-shaving flexibility transformation to adapt to the deep peak-shaving of units and improve the economic operation level of units, especially in the comprehensive smart energy aspect, implementing heating transformation for old units and considering the implementation of heating projects during the design and construction of new units. At present, most domestic units have the function of taking heating into consideration. In order to meet the needs of heating and power generation, heating units mostly use multiple units to operate in parallel for heating. It is common that they only operate to meet the heating needs, but there is no in-depth research on how to achieve more economical and energy-saving under the heating operation mode of the unit on the basis of heating.
[0003] At present, some adaptive improvements have been made for the economical and energy-saving operation of heating. For example, a method for distributing thermal and electric loads in the whole plant based on the optimal heating economy is described in the literature, including the following steps: 1) obtaining the real-time heating load; 2) determining the real-time power plant electric load according to the electric load time characteristic curve given by the power grid; 3) determining the electric load of each heating unit in the thermal power plant; 4) calculating the unit time standard coal consumption of each heating unit according to the electric load of each heating unit; 5) sorting each heating unit according to the unit time standard coal consumption of each heating unit, and then, on the premise of meeting the real-time heating load, distributing the thermal and electric load of the whole plant according to the sorting results, so that the total unit time standard coal consumption of all heating units is the lowest, and the thermal and electric load of each heating unit is obtained, completing the distribution of thermal and electric loads in the whole plant based on the optimal heating economy. This method and system can maximize the comprehensive economic benefits of heating and power generation in thermal power plants.
[0004] Although existing literature has conducted optimization methods for the distribution of heat and electricity loads, this optimization method does not take into account the actual operating conditions of multiple different units. The results of the optimization distribution do not conform to the actual situation, resulting in certain deviations in the operation of the units. Summary of the invention
[0005] The present invention is intended to provide an optimization energy-saving method for a heating unit, so as to solve the problem that the allocation result does not conform to the actual situation due to failure to take into account a plurality of different units during optimization allocation.
[0006] The optimization energy-saving method for heating units in this scheme includes the following contents:
[0007] The total power generation plan instruction curve and the heat steam flow characteristic curve for heat users issued by the power dispatch of the power grid are obtained, and based on this, the total power generation plan instruction and the heat demand characteristic instruction of heat users are optimized according to the energy-saving strategy of the heating units. Combined with the output information of the operating units, the total power generation load of the heating units and the total heat flow of heat users are distributed to each heating unit through the plant-level AGC control system and the heating control system, so that each heating unit can carry a certain amount of power generation load and heating steam during operation to simultaneously meet the total power generation load demand of the power grid and the total heat demand of heat users.
[0008] Furthermore, the heating unit optimization energy-saving strategy includes a first strategy and a second strategy, and the first strategy and the second strategy are both set according to the relationship between the power generation load and the rated load of each unit, and the relationship between the heating amount and the heating amount boundary of the unit.
[0009] Furthermore, when the heating units operating in parallel have no defects that affect the unit output, the first strategy or the second strategy is randomly selected.
[0010] Furthermore, the first strategy and the second strategy determine the relationship between power generation load at 70% rated load and / or 40% rated load, and the first strategy and the second strategy determine the relationship between heating supply at 5%, and / or 20%, and / or 95%.
[0011] Furthermore, the load distribution size of the unit is determined based on whether there are major equipment defects in the heating unit that affect the unit's output, and the heating unit's optimized energy-saving strategy is determined.
[0012] Furthermore, after the heating unit optimization energy-saving strategy is matched to different units and applied, the power generation load of all units is summed to obtain the total power generation load, and the heat supply of all units is summed to obtain the total heat flow of heat users.
[0013] The beneficial effects of this program are:
[0014] By reasonably and scientifically allocating and controlling the power generation load and heating steam flow data of the parallel heating units, the energy-saving and optimized operation mode of the heating units can be achieved, and the unit's power supply standard coal consumption is more economical than the normal average distribution of the unit's power generation load and heating flow rate, and the heating affects the optimal level of power supply standard coal consumption. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 The optimized energy-saving diagram of a heating unit in the embodiment of the optimized energy-saving method for a heating unit of the present invention;
[0016] Figure 2 A graph showing changes in power supply standard coal consumption calculated for different power generation loads and heating steam volumes of a 300MW-class subcritical reheat cold section heating unit in an embodiment of the method for optimizing energy conservation for a heating unit of the present invention;
[0017] Figure 3 This is a graph showing the trend of standard coal consumption for power supply under different heating steam amounts in an embodiment of the method for optimizing energy saving for a heating unit of the present invention. DETAILED DESCRIPTION
[0018] The following is further explained in detail through specific implementation methods.
[0019] Example
[0020] Optimized energy saving methods for heating units, such as Figure 1 As shown, including the following:
[0021] The total power generation plan instruction curve and the heat steam flow characteristic curve for heat users issued by the power dispatch of the power grid are obtained. The total power generation plan instruction curve and the heat steam flow characteristic curve for heat users are issued every day according to the dispatch of the power grid. Based on this, the total power generation plan instruction and the heat demand characteristic instruction of heat users are optimized according to the energy-saving strategy of the heating units. Combined with the output information of the operating units, the total power generation load of the heating units and the total heat flow of heat users are distributed to each heating unit through the plant-level AGC control system and the heating control system, so that each heating unit can carry a certain amount of power generation load and heating steam during operation to simultaneously meet the total power generation load demand of the power grid and the total heat demand of heat users.
[0022] The optimization energy-saving strategy for heating units includes the first strategy and the second strategy. The first strategy and the second strategy are set according to the relationship between the power generation load and the rated load of each unit, and the relationship between the heating supply and the heating supply boundary of the unit. When the heating units running in parallel have no defects that affect the output of the units, the first strategy or the second strategy is randomly selected.
[0023] The first strategy and the second strategy judge the relationship between the power generation load of each unit at 70% rated load and / or 40% rated load, and the first strategy and the second strategy judge the relationship between the heat supply of each unit at 5%, and / or 20%, and / or 95%. For example, taking two units as an example, represented as unit A and unit B respectively, the first strategy or the second strategy is determined according to the total heat flow and the total power generation load. When it is the first strategy, it is judged whether the load of unit A is greater than 70% of the rated load, and at the same time, it is judged whether the heat supply of unit A is less than 20% and greater than 5%, and whether the load of unit B is less than 70% and greater than 40% of the rated load, and at the same time, it is judged whether the heat supply of unit B is greater than 20% and less than 95%, and the load of unit A and the load of unit B that meet the corresponding conditions are output as the total load, and the heat supply of unit A and the heat supply of unit B that meet the corresponding conditions are output as the total heat supply. The judgment method of the second strategy is the same.
[0024] The above-mentioned load distribution and heating steam allocation judgment principles are based on the fact that the long-term average load rate of domestic heating thermal power units is basically 70%-75% of the rated load. Taking this node as the benchmark, the changes in the unit's standard coal consumption for power supply under different heating steam volume operating modes under this load rate are calculated, and the changes in the standard coal consumption for power supply under different load operating modes under the same heating steam volume are comprehensively compared, and it is concluded that this method is the best economic operation mode to achieve optimized energy-saving effects.
[0025] The principle of determining the minimum power generation load of 40% is based on the boundary value determined by the minimum stable combustion load of the unit and the heating demand. The lower limit of the heating boundary of 5% is based on the consideration of the heating steam pipes of the high power generation load heating unit for standby and appropriate heating. The upper limit of the heating steam volume of the low power generation load unit is 95% based on improving the heat-to-electricity ratio of the unit to maximize economic efficiency.
[0026] Determine the load distribution of the unit and the optimal energy-saving strategy for the heating unit based on whether there are major equipment defects that affect the unit's output.
[0027] After the optimized energy-saving strategy of the heating unit is matched to different units and applied, the total power generation load is obtained by summing up the power generation load of all units, and the total heat flow of heat users is obtained by summing up the heat supply of all units.
[0028] According to the different power generation loads and heating steam volume of 300MW subcritical reheat cold section heating units, the changes in standard coal consumption for power supply are calculated as follows: Figure 2 As shown in the figure, the power generation load rate is 75% (225MW), and the trend of standard coal consumption for power supply under different heating steam quantities is as follows Figure 3 shown.
[0029] Compared with conventional heating operation units, this embodiment does not consider the optimized distribution of power generation load and heating steam volume, does not achieve the best economic operation mode, and only meets the power generation load and conventional heating operation mode. The optimized energy-saving method of this embodiment has been verified in practice in the heating units of thermal power companies. The economic effects obtained are different according to different capacities and different heating amounts. According to the performance calculation of the 300MW subcritical unit of this unit, the standard coal consumption of the unit power supply under the optimized energy-saving operation mode can be reduced by 0.5g / kWh compared with the non-optimized operation mode. Two 300MW units, with an annual power generation of 3.2 billion kWh, can save 160 tons of standard coal, which not only saves fuel costs but also reduces carbon emissions, and plays a great role in the company's realization of energy conservation and emission reduction.
[0030] The method of this embodiment is applicable to thermal power plants with plant-level AGC control functions and two or more heating units that provide heating. Optimized energy-saving operation can be achieved without any additional investment, and the principle is also applicable to optimized energy saving when three or more units are providing heating at the same time. At this time, the third and above units can be directly judged under each strategy.
[0031] The above is only an embodiment of the present invention, and the common knowledge such as the known specific structure and characteristics in the scheme is not described in detail here. It should be pointed out that for those skilled in the art, several deformations and improvements can be made without departing from the structure of the present invention, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. An optimization energy-saving method for a heating unit, characterized in that: Includes the following: The total power generation plan instruction curve and the heat steam flow characteristic curve for heat users issued by the power dispatch of the power grid are obtained, and based on this, the total power generation plan instruction and the heat demand characteristic instruction of heat users are optimized according to the energy-saving strategy of the heating units. Combined with the output information of the operating units, the total power generation load of the heating units and the total heat flow of heat users are distributed to each heating unit through the plant-level AGC control system and the heating control system, so that each heating unit can carry a certain amount of power generation load and heating steam during operation to simultaneously meet the total power generation load demand of the power grid and the total heat demand of heat users.
2. The method for optimizing energy saving for a heating unit according to claim 1, characterized in that: The heating unit optimization energy-saving strategy includes a first strategy and a second strategy, and the first strategy and the second strategy are both set according to the relationship between the power generation load and the rated load of each unit, and the relationship between the heating supply and the heating supply boundary of the unit.
3. The method for optimizing energy saving for a heating unit according to claim 2, characterized in that: When the heating units operating in parallel have no defects that affect the unit output, the first strategy or the second strategy is randomly selected.
4. The optimization energy saving method for a heating unit according to claim 3 is characterized in that: The first strategy and the second strategy determine the relationship between power generation load at 70% rated load and / or 40% rated load, and the first strategy and the second strategy determine the relationship between heating supply at 5%, and / or 20%, and / or 95%.
5. The optimization energy-saving method for a heating unit according to claim 3, characterized in that: Determine the load distribution of the unit and the optimal energy-saving strategy for the heating unit based on whether there are major equipment defects that affect the unit's output.
6. The optimization energy saving method for a heating unit according to claim 3 is characterized in that: After the heating unit optimization energy-saving strategy is matched to different units and applied, the total power generation load is obtained by summing the power generation loads of all units, and the total heat flow of heat users is obtained by summing the heat supply of all units.